Nomor : 06 / 10 / HAR / SIPIL / 17

Tanggal : 30 OKT 2017


Halaman : 02 HALAMAN
Group : PEK. FASILITAS SIPIL
( Gedung Kantor & Workshop,
Emplasement & Jalan,
MCK & Drainase )
RENCANA ANGGARAN BIAYA MATERIAL / JASA
( ESTIMASI HARGA / OWNER ESTIMATE )

DEPARTEMEN PEMELIHARAAN
NO MACAM / LOKASI / RENCANA KEBUTUHAN MATERIAL / PART / JASA ESTIMASI HARGA NO. SPR / KETERANGAN
URAIAN PEKERJAAN BAGIAN No Nama (Material / Part / Jasa) dan Spesifikasi Jml Sat Per Satuan Total OKR / MEMO (SKOPE OF WORK)
01 02 03 04 05 06 07 08 09 10 11 12
PEMBUATAN TEMPAT PARKIR MOBIL DAMKAR I MATERIAL & JASA
1 PERSIAPAN (PREPARE), 1.00 LS 1,000,000.00 750,000.00 (RUSH ORDER) U/. PERBAIKAN SESUAI
(Mobilisasi, Equipment, Tools, Cleaning Area) DENGAN PERMINTAAN

2 PEMBONGKARAN SMOKING AREA 1,074,000.00


LOKASI : (Pembongkaran atap dan struktur baja)
SELATAN WS PPL # Bongkar penutup atap, Luas atap : 4 m x 5 m = 20 m2 20.00 m2 3,500.00 70,000.00
# Bongkar Struktur atap, Luas atap : 4 m x 5 m = 20 m2 20.00 m2 13,000.00 260,000.00
# Bongkar Kolom H 100.50.5 mm 148.80 kg 5,000.00 744,000.00

3 STRUKTUR BAWAH 8,655,970.00


(rangka kolom IWF 100.50.5 mm, sepatu kolom 200x200x200 mm
include painting setara amco, warna hitam)
# kolom IWF 100.50.5mm berat 9,3kg/m.
VOLUME : # Panjang kolom depan : 4m ; Qty : 2 bh
PANJANG = 7 M # Panjang kolom tengah : 3,7m ; Qty : 2 bh
LEBAR = 4 M # panjang kolom belakang : 3,4 m ; Qty : 2 bh
TINGGI = 4 M # vol. total : (4x2)+(3,7x2)+(3,4 x 2) x 9,3 = 206,46 kg 206.46 kg 19,500.00 4,025,970.00
# sepatu kolom 200x200x200 mm : Qty : 6 bh 6.00 bh 100,000.00 600,000.00
# Struktur Lantai, Rabat beton k-125 P: 4 m, L: 5 m, t : 0,1m 2.00 m3 950,000.00 1,900,000.00
# Penambahan keramik lantai : P : 4m , L : 5 m 20.00 m2 106,500.00 2,130,000.00

4 PEKERJAAN ATAP 20,999,874.28


(rangka atap CNP 100.50.20.2,3mm double, gording CNP 100.50.20.2,3mm,
atap zincalume 0,3 mm, painting setara AMCO, finishing warna hitam)
3.1 rangka atap CNP 100.50.20.2,3mm double, berat 8,12 kg/m 148.43 kg 18,800.00 2,790,551.68
PEKERJAAN : # panjang : 9,14 m. Qty 2 bh
1. PERSIAPAN # vol : 9,14 x 8,12 = 148,43 kg
2. PEMBONGKARAN SMOKING AREA 3.2 Gording CNP 100.50.20.2,3mm, berat 4,06 kg/m 194.88 kg 18,800.00 3,663,744.00
3. STRUKTUR BAWAH # panjang : 4 m : Qty = 12 bh
4. PEKERJAAN ATAP 3.2 Beam CNP 100.50.20.2,3mm, berat 4,06 kg/m 126.67 kg 18,800.00 2,381,433.60
5. PEKERJAAN PIPA AIR # panjang : 7 m : Qty = 2 bh
# panjang 4 m ; Qty : 3 bh
# beam kanopy : 1 m + 1 m + 1,6 m + 1,6 m = 5,2 m
3.3 atap zincalume 0,3 mm 42.70 m2 145,000.00 6,191,500.00
# volume atap utama : 36 m2
# volume atap kanopy : 6,7 m2

Page 1 of 4 486761622.xls
Nomor : 06 / 10 / HAR / SIPIL / 17
Tanggal : 30 OKT 2017
Halaman : 02 HALAMAN
Group : PEK. FASILITAS SIPIL
( Gedung Kantor & Workshop,
Emplasement & Jalan,
MCK & Drainase )
RENCANA ANGGARAN BIAYA MATERIAL / JASA
( ESTIMASI HARGA / OWNER ESTIMATE )

DEPARTEMEN PEMELIHARAAN
NO MACAM / LOKASI / RENCANA KEBUTUHAN MATERIAL / PART / JASA ESTIMASI HARGA NO. SPR / KETERANGAN
URAIAN PEKERJAAN BAGIAN No Nama (Material / Part / Jasa) dan Spesifikasi Jml Sat Per Satuan Total OKR / MEMO (SKOPE OF WORK)
01 02 03 04 05 06 07 08 09 10 11 12
3.4 listplang zincalume 0,3 mm, lebar 250 mm,
# rangka hollow 40x40x2mm, panjang besi total : 71 m 171.11 kg 19,500.00 3,336,645.00
# volume : 0,25 x (9,1+9,1+4+4+4+1,7+1,7) = 8,4 m2 8.40 m2 165,000.00 1,386,000.00
3.5 Talang Air
# Talang PVC, panjang 4,5 m Qty 2 bh 9.00 m 50,000.00 450,000.00
# Pipa PVC 4" kelas D panjang 4 m terpasang; Qty : 2 bh 8.00 m 100,000.00 800,000.00

5 PEKERJAAN PIPA AIR 4,778,000.00


(Material Pipa Galvanis medium A 2" )
# Panjang : 30 m
# Pengadaan & Installasi pipa, include sealtape 5.00 Lonjor 800,000.00 4,000,000.00
# Socket 2" 6.00 titik 30,000.00 180,000.00
# Elbow 2" 6.00 titik 35,000.00 210,000.00
# Tee 2" 6.00 titik 38,000.00 228,000.00
# Water Moor 2.00 titik 80,000.00 160,000.00
Catatan :
1. PEKERJAAN OLEH PIHAK LUAR (SUBKONT) JUMLAH RP. 36,257,844.28
( Incl. material, equipment, tools)
2. PEKERJAAN SEGERA STAFF MANAGER SENIOR MANAGER
3. REFERENSI HARGA SATUAN POKOK KOTA MADIUN TAHUN 2017 FASILITAS DEPT HAR
Tanggal 17/03/2017 17/03/2017 17/03/2017
Nama PUPUT INDRA SUMONO PRAJITNO

Tanda Tangan

Page 2 of 4 486761622.xls
PERHITUNGAN PENAMBAHAN JALUR REL HUTAN LINDUNG (18 M x 12)
PANJANG JALUR / TRACK : 18M x 12 = 216 M
PANJANG REL : 216 x 2 = 432 M

No Skope Pekerjaan Panjang Lebar Tebal/Tinggi Luas Volume Berat Jenis Jumlah Total Qty Satuan Harga/Sat Total Harga
(Nama Object) (m) (m) (m) (m2) (m3) (kg/m3) (Qty) (Rp) (Rp)

1 PREPARE (PERSIAPAN) 1.00 LS 1,500,000.00 1,500,000.00


(Mobilisasi, Equipment, Tools)

2 RABAT BETON,
(Perabatan Beton tanpa tulangan, K-300, Ready mix)
- WorkShop Har & Fas : 17.50 20.00 0.050 17.500 1.00 17.50 M3 1,350,000.00 23,625,000.00
(Panjang 17,5m, Lebar 20m, Tebal 5cm, Qty : 1 Bh)
- WorkShop Forklift :
(Panjang 20m, Lebar 10m, Tebal 8,5cm, Qty : 1 Bh) 20.00 10.00 0.085 17.000 1.00 17.00 M3 1,350,000.00 22,950,000.00
- Tempat Parkir Forklift :
(Panjang 11,3m, Lebar 4,6m, Tebal 10cm, Qty : 1 Bh) 11.30 4.60 0.100 5.198 1.00 5.20 M3 1,350,000.00 7,017,300.00

3 PENGECATAN LANTAI WORKSHOP,


(Pengecatan Lantai WorkShop, Jenis Cat :Epoxy Coating)
- Lantai WorkShop Har & Fas : 22.50 20.00 450.00 1.00 450.00 M2 75,000.00 33,750,000.00
(Panjang 22,5m, Lebar 20m, Epoxy Coating, Qty : 1 Bh)
- Lantai WorkShop Forklift :
(Panjang 20m, Lebar 10m, Epoxy Coating, Qty : 1 Bh) 20.00 10.00 200.00 1.00 200.00 M2 75,000.00 15,000,000.00

103,842,300.00

Catatan :
1. Refference Harga Berdasarkan :
Daftar Rekapitulasi Harga Satuan Pokok Kegiatan Tahun 2015 (Zona 1)
Kabupaten Madiun & Kodya Madiun

MADIUN, 10 NOVEMBER 2015

STAFF FAS-HAR

JOKO HARIYANTO
INKA
PT. INDUSTRI KERETA API (PERSERO)
Jl. Yos Sudarso No. 71 Madiun. Telp. 0351 452271-74 Fax. 0351 452274
Website : www.inka.co.id
E-mail : sekretaris@inka.co.id

PERBAIKAN KEMBALI SELOKAN


LOKASI SEBELAH UTARA WORKSHOP T (MO)

1. LATAR BELAKANG

Kondisi sekarang selokan mengalami kerusakan :


- Dinding samping sebelah utara roboh menimpa sisi sebelah selatan
- Aliran air yang keluar INKA menjadi tidak lancar
- Menimbulkan erosi tanah di sebelah dalam dinding

2. LANGKAH PERBAIKAN

Selokan direncanakan di perbaiki untuk di kembalikan ke fungsi


semula dengan langkah perbaikan sebagai berikut :
- Pembongkaran dinding bekas selokan yang roboh
- Di lakukan penambahan betonan bertulang
(Sloof Ring dan Kolom) untuk menambah kekuatan
structure dinding samping
- Dinding di kembalikan tetap dengan pasangan batu gibal
- Penambahan penguat dinding samping dengan rel bekas
untuk tambahan penyangga dinding agar tidak roboh
(seperti yang sudah di lakukan dengan structure selokan
yang lain)
- Foto kerusakan dan RAB terlampir

Demikian rencana perbaikan kembali selokan dan atas perhatianya


terima kasih.

Pekerjaan Sipil

Joko Hariyanto