Anda di halaman 1dari 1

Nomor : 03 / 11 / HAR / SIPIL / 17

Tanggal : 08 NOV 2017


Halaman : 01 HALAMAN
Group : PEK. FASILITAS SIPIL
( Gedung Kantor & Workshop,
Emplasement & Jalan,
MCK & Drainase )
RENCANA ANGGARAN BIAYA MATERIAL / JASA
( ESTIMASI HARGA / OWNER ESTIMATE )
DEPARTEMEN PEMELIHARAAN
NO MACAM / LOKASI / RENCANA KEBUTUHAN MATERIAL / PART / JASA ESTIMASI HARGA NO. SPR / KETERANGAN
URAIAN PEKERJAAN BAGIAN No Nama (Material / Part / Jasa) dan Spesifikasi Jml Sat Per Satuan Total OKR / MEMO (SKOPE OF WORK)
01 02 03 04 05 06 07 08 09 10 11 12
01 RENOVASI RUANG RAPAT PPC I MATERIAL & JASA
1 PERSIAPAN (PREPARE), 1,500,000.00 (RUSH ORDER) U/. PERBAIKAN SESUAI
(Mobilisasi, Equipment, Tools, Cleaning Area) 1 ls Rp 1,500,000 Rp 1,500,000

LOKASI : 2 PEMBONGKARAN EKSISTING 3,000,000.00


KANTOR PPC # Pekerjaan pembongkaran plafon teras 1 ls Rp 3,000,000 Rp 3,000,000

3 PERBAIKAN DINDING PARTISI 38,211,000.00


# dinding GRC tebal 8 mm, rangka hollow 2 x 4 162.6 m2 Rp 235,000 Rp 38,211,000

PEKERJAAN : 4 PEKERJAAN PLAFON 20,126,500.00


1 PERSIAPAN # plafon gypsum tebal 9 mm, rangka 4 x 4 / 2 x 4 95 m2 Rp 120,000 Rp 11,400,000
2 PEMBONGKARAN EKSISTING # drop cyling 56 m Rp 65,000 Rp 3,640,000
3 PERBAIKAN DINDING PARTISI # pengecatan plafon 95 m2 Rp 25,000 Rp 2,375,000
4 PEKERJAAN PLAFON # List plafon gypsum, lebar 10 cm 58 m Rp 16,750 Rp 971,500
5 BACKDROP RUANG RAPAT # List kayu area lantai, Lebar 10 cm 58 m Rp 30,000 Rp 1,740,000
6 WALLPAPER DINDING
7 PEKERJAAN ELECTRICAL 5 BACKDROP RUANG RAPAT 8,500,000.00
8 FINISH # Ukuran 1,5 x 2,4 m 1 ls Rp 8,500,000 Rp 8,500,000

6 WALLPAPER DINDING 15,447,000.00


# standart type 162.6 m2 Rp 95,000 Rp 15,447,000

7 PEKERJAAN ELECTRICAL 9,780,000.00


# Instalasi lampu baru, incl kabel NYM 3x1,5 12 unit Rp 450,000 Rp 5,400,000
# instalasi stop kontak, incl kabel NYM 3x1,5 8 unit Rp 365,000 Rp 2,920,000
# instalasi saklar, incl kabel NYM 3x1,5 4 unit Rp 365,000 Rp 1,460,000
Catatan :
1. PEKERJAAN OLEH PIHAK LUAR (SUBKONT) JUMLAH RP. 96,564,500.00
( Incl. material, equipment, tools)
2. PEKERJAAN SEGERA STAFF MANAGER SENIOR MANAGER
3. REFERENSI HARGA SATUAN POKOK KOTA MADIUN TAHUN 2017 HAR HAR - GEDUNG DEPT HAR
Tanggal 08 NOV 2017 08 NOV 2017 08 NOV 2017
Nama PUPUT INDRA DARMAJI PRAJITNO

Tanda Tangan

Page 1 of 1 472537710.xls

Anda mungkin juga menyukai