Nomor : 04 / 10 / HAR / SIPIL / 17

Tanggal : 11 DESEMBER 2017


Halaman : 03 HALAMAN
Group : PEK. FASILITAS SIPIL
( Gedung Kantor & Workshop,
Emplasement & Jalan,
MCK & Drainase )
RENCANA ANGGARAN BIAYA MATERIAL / JASA
( ESTIMASI HARGA / OWNER ESTIMATE )

DEPARTEMEN PEMELIHARAAN DAN FASILITAS


NO MACAM / LOKASI / RENCANA KEBUTUHAN MATERIAL / PART / JASA ESTIMASI HARGA NO. SPR / KETERANGAN
URAIAN PEKERJAAN BAGIAN No Nama (Material / Part / Jasa) dan Spesifikasi Jml Sat Per Satuan Total OKR / MEMO (SKOPE OF WORK)
01 02 03 04 05 06 07 08 09 10 11 12
RENOVASI KAMAR WISMA SALAK I MATERIAL & JASA
1 PERSIAPAN (PREPARE), 1.00 LS 2,000,000.00 2,000,000.00 (RUSH ORDER) U/. PERBAIKAN SESUAI
(Mobilisasi, Equipment, Tools, Cleaning Area) DENGAN PERMINTAAN

LOKASI : 2 PEKERJAAN TALANG 39,050,000.00


WISMA SALAK, JL. SALAK, MADIUN (Penggantian talang datar/ jurai)
# Panjang Talang : 6 m ; Qty : 4 bh
# Pembongkaran Talang 24.00 m 25,000.00 600,000.00
# Pemasangan Talang Baru, bjls 0,3 24.00 m 135,000.00 3,240,000.00
# Talang plat beton konsul, include pembesian (di atas jendela) 5.40 m3 3,350,000.00 18,090,000.00
# Bekisting talang 54.00 m2 280,000.00 15,120,000.00
# Bongkar bekisting 4.00 ls 500,000.00 2,000,000.00

VOLUME : 3 PEKERJAAN PLAFON 29,167,750.00


4 KAMAR (Pembongkaran dan pemasangan plafon baru)
# Pembongkaran plafon 120.00 m2 30,000.00 3,600,000.00
# Plafon Kalsiboard tebal 4,5mm, rangka metal puring (area Toilet & teras) 56.00 m2 116,000.00 6,496,000.00
# Plafon Gypsum area kamar, tebal 9 mm 64.00 m2 126,000.00 8,064,000.00
# List Gypsum, 12 cm (terpasang) 71.00 m 16,750.00 1,189,250.00
# Droop Cyling (terpasang) 71.00 m2 93,500.00 6,638,500.00
# Pengecatan plafon 120.00 m2 26,500.00 3,180,000.00

4 PEKERJAAN PINTU & JENDELA 37,748,000.00


(Penggantian Pintu Depan dan Pintu kamar mandi)
# Pembongkaran pintu & jendela eksisting (4 kamar) 1.00 Ls 3,000,000.00 3,000,000.00
# Pintu depan, frame aluminium, daun pintu upvc ex S-plus, uk 0,9 x 2 m 4.00 Unit 2,900,000.00 11,600,000.00
# Pintu Kamar Mandi, PVC uk 0,85 x 2 m 4.00 Unit 700,000.00 2,800,000.00
# Jendela Depan, kusen aluminium, kaca bening 5 mm, uk 3,28 x 2 m 4.00 Unit 5,087,000.00 20,348,000.00
PEKERJAAN : (4 daun jendela @ 0,76m)
1 PERSIAPAN
2 PEKERJAAN TALANG 5 INTERIOR KAMAR 185,140,000.00
3 PEKERJAAN PLAFON (Pekerjaan interior untuk 4 kamar, pengadaan dan pemasangan)
4 PEKERJAAN PINTU # Backdrop Kamar 4.00 Unit 18,625,000.00 74,500,000.00
5 INTERIOR KAMAR # Meja Laci kecil 8.00 Unit 950,000.00 7,600,000.00
6 PEKERJAAN LANTAI # Nakas 4.00 Unit 1,260,000.00 5,040,000.00
7 PEKERJAAN ELECTRICAL # Almari 4.00 Unit 8,125,000.00 32,500,000.00
8 PEKERJAAN AREA KAMAR MANDI # Lukisan ukuran sedang 4.00 Unit 425,000.00 1,700,000.00

Page 1 of 3 486761487.xls
Nomor : 04 / 10 / HAR / SIPIL / 17
Tanggal : 11 DESEMBER 2017
Halaman : 03 HALAMAN
Group : PEK. FASILITAS SIPIL
( Gedung Kantor & Workshop,
Emplasement & Jalan,
MCK & Drainase )
RENCANA ANGGARAN BIAYA MATERIAL / JASA
( ESTIMASI HARGA / OWNER ESTIMATE )

DEPARTEMEN PEMELIHARAAN DAN FASILITAS


NO MACAM / LOKASI / RENCANA KEBUTUHAN MATERIAL / PART / JASA ESTIMASI HARGA NO. SPR / KETERANGAN
URAIAN PEKERJAAN BAGIAN No Nama (Material / Part / Jasa) dan Spesifikasi Jml Sat Per Satuan Total OKR / MEMO (SKOPE OF WORK)
01 02 03 04 05 06 07 08 09 10 11 12
9 PEKERJAAN ATAP # Lukisan ukuran Besar 4.00 Unit 625,000.00 2,500,000.00
10 PEKERJAAN DINDING # Backdrop TV dan Meja Rias 4.00 Unit 12,950,000.00 51,800,000.00
# Wallpaper 20.00 Roll 475,000.00 9,500,000.00

6 PEKERJAAN LANTAI 36,478,400.00


(Pengadaan dan pemasangan)
# Pasang kramik ex roman uk 60 x 60 cm 80.00 m2 418,500.00 33,480,000.00
# List/ plin dinding lebar 10 cm, kramik ex roman 6.40 m2 418,500.00 2,678,400.00
# Tali air atas plin 64.00 m 5,000.00 320,000.00

7 PEKERJAAN ELECTRICAL 51,038,000.00


(Pengadaan dan pemasangan)
# Stop Kontak & Saklar incl kabel nym 2 x 1,5 mm 28.00 titik 401,500.00 11,242,000.00
# Pembongkaran & instalasi AC 4.00 Unit 390,500.00 1,562,000.00
# LED Backdrop incl kabel nym 2 x 1,5 mm 12.00 Unit 522,500.00 6,270,000.00
# Lampu atas Backdrop incl kabel nym 2 x 1,5 mm 12.00 titik 522,500.00 6,270,000.00
# Lampu area dropcyling incl kabel nym 2 x 1,5 mm 8.00 ea 401,500.00 3,212,000.00
# Bohlam lampu ex Philips 100s Philips 310 64.00 ea 110,000.00 7,040,000.00
# Lampu Philips 18 watt 28.00 titik 150,000.00 4,200,000.00
# Stop Kontak & Saklar bukan interior incl kabel nym 2 x 1,5 mm 28.00 titik 401,500.00 11,242,000.00

8 PEKERJAAN AREA KAMAR MANDI 94,442,400.00


(Pengadaan dan pemasangan)
# Bongkar Bathup 4.00 LS 165,000.00 660,000.00
# Bongkar keramik 4.00 LS 605,000.00 2,420,000.00
# Shower karan (panas dingin) ex Modena 4.00 Unit 935,000.00 3,740,000.00
# Heater electric ex Modena 4.00 Unit 2,500,000.00 10,000,000.00
# wastafel karan 4.00 Unit 330,000.00 1,320,000.00
# Kran closet 4.00 Unit 165,000.00 660,000.00
# Keramik dinding ex roman type uk 25 x 35 cm 76.80 m2 203,500.00 15,628,800.00
# Keramik lantai ex roman type uk 40 x 40 16.00 m2 191,400.00 3,062,400.00
# Kloset duduk ex American Standart 4.00 Unit 2,750,000.00 11,000,000.00
# Shower Jet 4.00 Unit 99,000.00 396,000.00
# Tempat tisu 4.00 Unit 412,500.00 1,650,000.00
# Wastafel kotak ex American Standart 4.00 Unit 1,925,000.00 7,700,000.00
# Gantungan handuk stainless type 4.00 Unit 132,000.00 528,000.00
# Kaca tampered area shower tbl 10 mm 28.80 m2 825,000.00 23,760,000.00

Page 2 of 3 486761487.xls
Nomor : 04 / 10 / HAR / SIPIL / 17
Tanggal : 11 DESEMBER 2017
Halaman : 03 HALAMAN
Group : PEK. FASILITAS SIPIL
( Gedung Kantor & Workshop,
Emplasement & Jalan,
MCK & Drainase )
RENCANA ANGGARAN BIAYA MATERIAL / JASA
( ESTIMASI HARGA / OWNER ESTIMATE )

DEPARTEMEN PEMELIHARAAN DAN FASILITAS


NO MACAM / LOKASI / RENCANA KEBUTUHAN MATERIAL / PART / JASA ESTIMASI HARGA NO. SPR / KETERANGAN
URAIAN PEKERJAAN BAGIAN No Nama (Material / Part / Jasa) dan Spesifikasi Jml Sat Per Satuan Total OKR / MEMO (SKOPE OF WORK)
01 02 03 04 05 06 07 08 09 10 11 12
# Pintu & accesoris, handel stainless 4.00 Unit 423,500.00 1,694,000.00
# Pintu & accesoris, handel tampered 4.00 Unit 385,000.00 1,540,000.00
# Avour Kamar mandi 4.00 Unit 165,000.00 660,000.00
# Avour closed 4.00 Unit 165,000.00 660,000.00
# Boven Kamar mandi 4.00 Unit 600,000.00 2,400,000.00
# pengecatan dinding kamar mandi, weathersield ex catilac 96.00 m2 51,700.00 4,963,200.00

9 PEKERJAAN ATAP 60,698,400.00


(Pengadaan dan pemasangan)
# Bongkar atap eksisting incl mobilisasi 112.00 m2 15,000.00 1,680,000.00
# Kuda kuda baja ringan tebal 0,75 ex Kencana 112.00 m2 159,500.00 17,864,000.00
# Pasang genteng beton motif datar polos cat hitam ex Munier 192.00 m2 155,450.00 29,846,400.00
# Pasang bubungan genteng ex kalang piliang 16.00 m 148,500.00 2,376,000.00
# Lisplang GRC 32.00 m 104,500.00 3,344,000.00
# Pas. Bata pengunci genteng area gevel incl plester + aci & waterproof 40.00 m 139,700.00 5,588,000.00

10 PEKERJAAN DINDING 118,014,800.00


# Bongkar jendela dalam kamar mandi 19.36 m2 15,000.00 290,400.00
# Pasang Bata incl plester & aci (sudut kamar) 19.36 m2 185,000.00 3,581,600.00
# Pasang Bata incl plester & aci (peninggian kamar) 240.00 m2 185,000.00 44,400,000.00
# Kolom & balok praktis dinding (incl bekisting & besi Ø10mm) 12.00 m3 1,800,000.00 21,600,000.00
# Pengecatan eksterior weathersield ex Catilac 900.00 m2 51,700.00 46,530,000.00
# Pekerjaan benangan 96.00 m 16,800.00 1,612,800.00
Catatan :
1. PEKERJAAN OLEH PIHAK LUAR (SUBKONT) JUMLAH RP. 653,777,750.00
( Incl. material, equipment, tools)
2. PEKERJAAN SEGERA STAFF MANAGER SENIOR MANAGER
3. REFERENSI HARGA SATUAN POKOK KOTA MADIUN TAHUN 2017 FAS-HAR FASILITAS DEPT HAR & FAS
Tanggal 11 DESEMBER 2017 11 DESEMBER 2017 11 DESEMBER 2017
Nama PUPUT INDRA SUMONO PRAJITNO

Tanda Tangan

Page 3 of 3 486761487.xls