Nomor : 10 / 03 / HAR / SIPIL / 17

Tanggal : 17 MARET 2017


Halaman : 02 HALAMAN
Group : PEK. FASILITAS SIPIL
( Gedung Kantor & Workshop,
Emplasement & Jalan,
MCK & Drainase )
RENCANA ANGGARAN BIAYA MATERIAL / JASA
( ESTIMASI HARGA / OWNER ESTIMATE )

DEPARTEMEN PEMELIHARAAN
NO MACAM / LOKASI / RENCANA KEBUTUHAN MATERIAL / PART / JASA ESTIMASI HARGA NO. SPR / KETERANGAN
URAIAN PEKERJAAN BAGIAN No Nama (Material / Part / Jasa) dan Spesifikasi Jml Sat Per Satuan Total OKR / MEMO (SKOPE OF WORK)
01 02 03 04 05 06 07 08 09 10 11 12
PENUTUP ATAP UNTUK TEMPORARY STORAGE I MATERIAL & JASA
ZWEIWEG 1 PERSIAPAN (PREPARE), 1.00 LS 2,500,000.00 1,500,000.00 (RUSH ORDER) U/. PERBAIKAN SESUAI
(Mobilisasi, Equipment, Tools, Cleaning Area) DENGAN PERMINTAAN

LOKASI : 2 STRUKTUR BAWAH 3,282,950.00


SELATAN GD. L (rangka kolom IWF 100.50.5 mm, sepatu kolom 200x200x200 mm
include painting setara amco, warna hitam)
# kolom IWF 100.50.5mm berat 9,3kg/m.
VOLUME : # Panjang kolom depan : 4m ; Qty : 2 bh
PANJANG = 7 M # panjang kolom belakang : 4,5 m ; Qty : 2 bh
LEBAR = 6 M # vol. total : (4x2)+(4,5 x 2) x 9,3 = 158,1 kg 158.10 kg 19,500.00 3,082,950.00
TINGGI = 4 M # sepatu kolom 200x200x200 mm : Qty : 4 bh 4.00 bh 50,000.00 200,000.00

3 PEKERJAAN ATAP 16,262,500.00


(rangka atap CNP 100.50.20.2,3mm double, gording CNP 100.50.20.2,3mm,
atap zincalume 0,3 mm, painting setara AMCO warna hitam)
3.1 rangka atap CNP 100.50.20.2,3mm double, berat 4,06 kg/m 211.12 kg 19,000.00 4,011,280.00
PEKERJAAN : # panjang : 14 + 12 = 26 x 2 = 52 m
1. PERSIAPAN # vol : 52 x 4,06 = 211,2 kg
2. STRUKTUR BAWAH 3.2 rangka atap CNP 100.50.20.2,3mm, berat 4,06 kg/m 170.52 kg 19,000.00 3,239,880.00
3. PEKERJAAN ATAP # panjang : 6 m : Qty = 7 bh
4. FINISH 3.3 atap zincalume 0,3 mm 42.00 m2 165,000.00 6,930,000.00
# volume atap : 7 x 6 = 42 m2
3.4 listplang zincalume 0,3 mm, lebar 250 mm, panjang 7 m : QTY : 2 bh
# rangka hollow 40x40x2mm, panjang besi total : 32 m 77.12 kg 19,500.00 1,503,840.00
# volume : 0,25 x 7 x 2 = 3,5 m2 3.50 m2 165,000.00 577,500.00

Catatan :
1. PEKERJAAN OLEH PIHAK LUAR (SUBKONT) JUMLAH RP. 21,045,450.00
( Incl. material, equipment, tools)
2. PEKERJAAN SEGERA STAFF MANAGER SENIOR MANAGER
3. REFERENSI HARGA SATUAN POKOK KOTA MADIUN TAHUN 2017 FASILITAS DEPT HAR
Tanggal 17/03/2017 17/03/2017 17/03/2017
Nama PUPUT INDRA PRAJITNO

Tanda Tangan

Page 1 of 3 463616936.xls
PERHITUNGAN PENAMBAHAN JALUR REL HUTAN LINDUNG (18 M x 12)
PANJANG JALUR / TRACK : 18M x 12 = 216 M
PANJANG REL : 216 x 2 = 432 M

No Skope Pekerjaan Panjang Lebar Tebal/Tinggi Luas Volume Berat Jenis Jumlah Total Qty Satuan Harga/Sat Total Harga
(Nama Object) (m) (m) (m) (m2) (m3) (kg/m3) (Qty) (Rp) (Rp)

1 PREPARE (PERSIAPAN) 1.00 LS 1,500,000.00 1,500,000.00


(Mobilisasi, Equipment, Tools)

2 RABAT BETON,
(Perabatan Beton tanpa tulangan, K-300, Ready mix)
- WorkShop Har & Fas : 17.50 20.00 0.050 17.500 1.00 17.50 M3 1,350,000.00 23,625,000.00
(Panjang 17,5m, Lebar 20m, Tebal 5cm, Qty : 1 Bh)
- WorkShop Forklift :
(Panjang 20m, Lebar 10m, Tebal 8,5cm, Qty : 1 Bh) 20.00 10.00 0.085 17.000 1.00 17.00 M3 1,350,000.00 22,950,000.00
- Tempat Parkir Forklift :
(Panjang 11,3m, Lebar 4,6m, Tebal 10cm, Qty : 1 Bh) 11.30 4.60 0.100 5.198 1.00 5.20 M3 1,350,000.00 7,017,300.00

3 PENGECATAN LANTAI WORKSHOP,


(Pengecatan Lantai WorkShop, Jenis Cat :Epoxy Coating)
- Lantai WorkShop Har & Fas : 22.50 20.00 450.00 1.00 450.00 M2 75,000.00 33,750,000.00
(Panjang 22,5m, Lebar 20m, Epoxy Coating, Qty : 1 Bh)
- Lantai WorkShop Forklift :
(Panjang 20m, Lebar 10m, Epoxy Coating, Qty : 1 Bh) 20.00 10.00 200.00 1.00 200.00 M2 75,000.00 15,000,000.00

103,842,300.00

Catatan :
1. Refference Harga Berdasarkan :
Daftar Rekapitulasi Harga Satuan Pokok Kegiatan Tahun 2015 (Zona 1)
Kabupaten Madiun & Kodya Madiun

MADIUN, 10 NOVEMBER 2015

STAFF FAS-HAR

JOKO HARIYANTO
INKA
PT. INDUSTRI KERETA API (PERSERO)
Jl. Yos Sudarso No. 71 Madiun. Telp. 0351 452271-74 Fax. 0351 452274
Website : www.inka.co.id
E-mail : sekretaris@inka.co.id

PERBAIKAN KEMBALI SELOKAN


LOKASI SEBELAH UTARA WORKSHOP T (MO)

1. LATAR BELAKANG

Kondisi sekarang selokan mengalami kerusakan :


- Dinding samping sebelah utara roboh menimpa sisi sebelah selatan
- Aliran air yang keluar INKA menjadi tidak lancar
- Menimbulkan erosi tanah di sebelah dalam dinding

2. LANGKAH PERBAIKAN

Selokan direncanakan di perbaiki untuk di kembalikan ke fungsi


semula dengan langkah perbaikan sebagai berikut :
- Pembongkaran dinding bekas selokan yang roboh
- Di lakukan penambahan betonan bertulang
(Sloof Ring dan Kolom) untuk menambah kekuatan
structure dinding samping
- Dinding di kembalikan tetap dengan pasangan batu gibal
- Penambahan penguat dinding samping dengan rel bekas
untuk tambahan penyangga dinding agar tidak roboh
(seperti yang sudah di lakukan dengan structure selokan
yang lain)
- Foto kerusakan dan RAB terlampir

Demikian rencana perbaikan kembali selokan dan atas perhatianya


terima kasih.

Pekerjaan Sipil

Joko Hariyanto