PEKERJAAN :
1 PERSIAPAN
2 PENGECATAN JIG LRT
Catatan :
1. PEKERJAAN OLEH PIHAK LUAR (SUBKONT) JUMLAH RP. 39,900,000.00
( Incl. material, equipment, tools)
2. PEKERJAAN SEGERA STAFF MANAGER SENIOR MANAGER
3. REFERENSI HARGA SATUAN POKOK KOTA MADIUN TAHUN 2017 HAR HAR. GEDUNG DEPT HAR
Tanggal 29 DESEMBER 2017 29 DESEMBER 2017 29 DESEMBER 2017
Nama PUPUT INDRA DARMAJI PRAJITNO
Tanda Tangan
Page 1 of 2 483185287.xls
UTARA GD. INTERNASIONAL