Anda di halaman 1dari 2

Nomor : 12 / 12 / HAR / SIPIL / 17

Tanggal : 29 DESEMBER 2017


Halaman : 01 HALAMAN
Group : PEK. FASILITAS SIPIL
( Gedung Kantor & Workshop,
Emplasement & Jalan,
MCK & Drainase )
RENCANA ANGGARAN BIAYA MATERIAL / JASA
( ESTIMASI HARGA / OWNER ESTIMATE )

DEPARTEMEN PEMELIHARAAN DAN FASILITAS


NO MACAM / LOKASI / RENCANA KEBUTUHAN MATERIAL / PART / JASA ESTIMASI HARGA NO. SPR / KETERANGAN
URAIAN PEKERJAAN BAGIAN No Nama (Material / Part / Jasa) dan Spesifikasi Jml Sat Per Satuan Total OKR / MEMO (SKOPE OF WORK)
01 02 03 04 05 06 07 08 09 10 11 12
PENGECATAN JIG LRT I MATERIAL & JASA
1 PERSIAPAN (PREPARE), 1.00 LS 1,500,000.00 1,500,000.00 (RUSH ORDER) U/. PERBAIKAN SESUAI
(Mobilisasi, Equipment, Tools, Cleaning Area) DENGAN PERMINTAAN

LOKASI : 2 PENGECATAN JIG LRT 38,400,000.00


GEDUNG BARU SISI UTARA # Cat Prime Top 2 in 1, warna kuning 960 m2 40,000.00 38,400,000.00
# Volume : 40 kg kaleng cat, setara 240 m2

VOLUME : 1 pile 20 kg;


120 M 160 kg 960

PEKERJAAN :
1 PERSIAPAN
2 PENGECATAN JIG LRT

Catatan :
1. PEKERJAAN OLEH PIHAK LUAR (SUBKONT) JUMLAH RP. 39,900,000.00
( Incl. material, equipment, tools)
2. PEKERJAAN SEGERA STAFF MANAGER SENIOR MANAGER
3. REFERENSI HARGA SATUAN POKOK KOTA MADIUN TAHUN 2017 HAR HAR. GEDUNG DEPT HAR
Tanggal 29 DESEMBER 2017 29 DESEMBER 2017 29 DESEMBER 2017
Nama PUPUT INDRA DARMAJI PRAJITNO

Tanda Tangan

Page 1 of 2 483185287.xls