REKAPITULASI AKHIR
PPN 10 % #N/A
Catatan :
Pekerjaan persiapan merupakan satu paket pekerjaan yang terdiri dari 1 unit bangunan Workshop 6 Bays, 1 unit
bangunan Washing Bay, 1 unit bangunan Power House dan Compressor Room, 1 unit bangunan WOSA
PROYEK PEMBANGUNAN WORKSHOP FACILITY
PAKET PEMBANGUNAN PEMINDAHAN WORKSHOP BARU
PT PAMAPERSADA NUSANTARA – BAYA - KALIMANTAN TIMUR
1,806,100,000
1,806,100,000
(2,000,000) 33,000,000
7,142,200
48,600,000
88,000,000
5,000,000
7,500,000
1,500,000
-
52,500,000
36,405,000
30,000,000
-
25,283,795 25,000,000
-
(35,000,000) 245,000,000
5,000,000
211,000,000
(110,000,000) 594,980,000
-
21,000,000
5,000,000
-
-
48,000,000
42,000,000
42,000,000
42,000,000
207,000,000 33,000,000
264,000,000 -
(57,000,000) 90,000,000
21,000,000
144,540,000 7,500,000
132,540,000 5,040,000
(12,000,000) 9,000,000
-
(100,000,000) 50,000,000
1,806,167,200
(316,000,000)
1.04 1.04
PROYEK : PEMBANGUNAN OFFICE, WORKSHOP & WAREHOUSE FACILITY 11
PAKET PEKERJAAN : WORKSHOP 6 BAYS OHC 15 TON Sumber : PAMA-KPCS #N/A
LOKASI : PAMA BAYA-KALIMANTAN TIMUR BELUM DIISI / RAGU
REKAPITULASI AKHIR
VOL UNIT PRICE TOTAL PRICE VOL VOL Koef Sirtu Koef Pasir Urug Readymix Sitemix
Lantai kerja Readymix Koef Split Koef Pasir Beton Koef Semen Koef Besi Koef M.6 Koef M.7 Koef M.8 Koef M.10 Koef Bekisting MECAMICAL ELECTRICAL
NO JENIS PEKERJAAN SPESIFIKASI UNIT HARGA SATUAN
PAMA KONT MATRIAL UPAH MATERIAL UPAH PAMA GGL m3 m3 m3 m3 m3 m3 m3 kg Kg lbr lbr lbr m2 (Rp) (Rp)
PEKERJAAN WORKSHOP
1. PEKERJAAN TANAH 200,387,979.30 78,768,706.85
1 Galian tanah untuk pondasi dan tie beam & ramp m³ 112.41 112.41 - 77,880 - 8,754,490.80 112.41 75,000 8,754,490.80
2 Urugan tanah kembali m³ 54.28 54.28 - 77,880 - 4,227,162.85 54.28 4,227,162.85
3 Perapihan & Pemadatan tanah m² 1,940.00 2,040.00 - 15,576 - 31,775,040.00 1,940.00 15,000 31,775,040.00
4 Lantai kerja , t = 5 cm dibawah pondasi /poer / tie beam m³ 6.25 6.25 1,104,541 337,480 6,903,382.50 2,109,250.00 6.25 9,012,632.50
5 Sirtu dibawah slab lantai Ramp & Main Bays. t = 30 cm Lokal m³ 486.00 486.00 347,692 57,112 168,978,312.00 27,756,432.00 486.00 450.00 196,734,744.00 1.20 583.20
6 Sirtu dibawah slab lantai office& oil storage. t = 10 cm Lokal m³ 32.00 42.00 347,692 57,112 14,603,064.00 2,398,704.00 32.00 45.00 17,001,768.00 1.20 50.40
7 Plastik cor m² 1,940.00 2,040.00 4,855 857 9,903,220.80 1,747,627.20 1,940.00 2,020.00 5,500 11,650,848.00
- - -
2. PEKERJAAN STRUKTUR DASAR #N/A #N/A -
1 Mini pile 25x25, include jasa pemancangan & penyambungan L = 12 m K-500 ( Prestress) m' 720.00 720.00 373,824 67,496 269,153,280.00 48,597,120.00 720.00 720.00 425,000 317,750,400.00
2 Bobok kepala mini pile Readymix K250 ttk 60.00 60.00 67,496 - 4,049,760.00 60.00 60.00 65,000 4,049,760.00
3 Poer P 1 ( 600 x 600 x 600 cm ) Readymix K250 m³ 3.46 3.46 4,521,249 1,201,851 15,625,436.54 4,153,597.06 3.46 3.46 19,779,033.60 3.46 207.51 717.16 6.67 23.04
4 Poer P 2 ( 800 x 1300 x 600 cm ) Readymix K250 m³ 8.74 8.74 4,521,249 1,201,851 39,497,631.26 10,499,370.34 8.74 8.74 49,997,001.60 8.74 207.51 1,812.82 6.67 58.24
5 Poer P 3 ( 1300 x 1300 x 700 cm ) Readymix K250 m³ 4.73 4.73 4,521,249 1,201,851 21,394,550.27 5,687,158.93 4.73 4.73 27,081,709.20 4.73 207.51 981.94 6.67 31.55
6 Kolom pendestal K1 = 40 x 30 cm Readymix K250 m³ 2.88 3.96 3,486,902 926,898 13,808,131.92 3,670,516.08 2.88 3.96 17,478,648.00 3.96 114.34 452.80 7.78 30.80
7 Kolom pendestal K2 = 51 x 51 cm Readymix K250 m³ 5.46 3.12 3,627,206 964,194 11,321,235.37 3,009,442.31 5.46 3.12 14,330,677.68 3.12 152.57 476.20 4.90 15.30
8 Kolom pendestal K3 = 110 x 51 cm Readymix K250 m³ 3.37 3.37 4,336,389 1,152,711 14,596,285.37 3,880,025.23 3.37 3.37 18,476,310.60 3.37 205.97 693.30 5.74 19.32
9 Tie beam TB1 30x50 cm Readymix K250 m³ 22.50 22.50 3,039,367 807,933 68,385,757.50 18,178,492.50 22.50 22.50 86,564,250.00 22.50 108.47 2,440.63 4.17 93.75
10 Tie beam TB2 25x35 cm Readymix K250 m³ 7.00 14.18 3,687,483 980,217 52,302,337.00 13,903,152.87 7.00 14.18 66,205,489.88 14.18 129.18 1,832.32 8.00 113.47
11 Slab Lantai dasar t = 30 cm ( big tyre & ramp) Tul. D13-150 double Readymix K250 m³ 486.00 487.17 2,629,752 699,048 1,281,136,281.84 340,555,214.16 486.00 487.17 1,621,691,496.00 487.17 97.20 47,352.92 6.67 - 66.00 107,177.40 52,213,613.96 36 1623.9
12 Slab Lantai dasar t = 10 cm ( office dan locker & restroom ) M.7 Single Readymix K175 m3 21.00 30.00 2,268,406 602,994 68,052,180.00 18,089,820.00 21.00 30.00 86,142,000.00 30.00 14.29 10.00 300.00 5.60 0.04 1.13 5.6 900
13 Slab lantai 2 t : 12 cm + wiremesh m8 single + floordeck Readymix K250 m³ 34.20 34.20 #N/A #N/A #N/A #N/A 34.20 34.20 #N/A 34.20 8.33 28.00 27.20 0.04 1.28 9.6
14 Kolom praktis 10 x 10 cm Sitemix K175 m³ 0.88 3.54 4,636,431 1,232,469 16,430,352.36 4,367,562.02 0.88 3.54 20,797,914.38 3.54 0.990 3.51 0.75 2.66 326.00 1,155.26 176.17 624.29 26.67 94.50
15 Ring Balk praktis 10 x 15 cm Sitemix K175 m³ 1.68 3.98 4,636,431 1,232,469 18,461,804.60 4,907,568.31 1.68 3.98 23,369,372.91 3.98 0.99 3.94 0.75 2.99 326.00 1,298.10 176.17 701.48 26.67 106.18
16 Oilpit ( saluran Oli )+ grill uk. 20 x 30 cm t = 20 cm, ø 12 - 150 double Readymix K250 m¹ 112.00 112.00 49,220 13,084 5,512,657.92 1,465,390.08 112.00 60,000 6,978,048.00 13.44 130.78 1,757.68
17 Dowel dia 16 dibungkus pipa pvc 1,5” bh 600.00 600.00 20,508 5,452 12,305,040.00 3,270,960.00 600.00 25,000 15,576,000.00 1.30 780.00
18 Bouhlar Pelindung Kolom Pipa black steel Dia 8 in ( dicor ) bh 8.00 8.00 2,973,718 790,482 23,789,744.00 6,323,856.00 8.00 8.00 3,625,000 30,113,600.00
19 Oil Storage 10x10m ( Incl.Bundwall t : 1m tebal plat 12cm ) + atap baja ringan unit 1.00 1.00 32,141,645 8,519,336 32,141,645.01 8,519,336.02 RANGKA 215
1.00UPAH 35; TUTUP 100 UPAH 2538,782,339 40,660,981.03 24.80 93.60 2,321.28
20 Cerucuk dolken dia 10 l : 2m tiap 1m2 PC dari Pama bh 1,705.00 1,705.00 46,520 11,630 79,317,145.60 19,829,286.40 1,705.00 1,705.00 56,000 99,146,432.00
-
3. PEKERJAAN STRUKTUR BAJA 2,466,476,162.21 711,828,313.55 -
WORKSHOP DAN OFFICE -
1 Kolom K 1 - H 400.400.13.21 Gunung Garuda/KS kg 36,326.40 33,987.20 16,500 5,000 560,788,800.00 169,936,000.00 36,326.40 33,987.20 730,724,800.00
2 Kolom K2 - WF 350.175.7.11 Gunung Garuda/KS kg 2,976.00 5,694.87 16,000 5,000 91,117,977.60 28,474,368.00 2,976.00 5,694.87 119,592,345.60
3 Kolom K3 - WF 350.175.7.11 Gunung Garuda/KS kg 1,776.00 2,381.79 16,000 5,000 38,108,672.00 11,908,960.00 1,776.00 2,381.79 50,017,632.00
4 Kolom K4 - WF 250.125.6.9 Gunung Garuda/KS kg 3,372.80 3,083.28 16,000 5,000 49,332,544.00 15,416,420.00 3,372.80 3,083.28 64,748,964.00
5 Rafter R1 - WF 300.150.7.9 Gunung Garuda/KS kg 7,758.38 8,276.58 16,000 5,000 132,425,344.00 41,382,920.00 7,758.38 8,276.58 173,808,264.00
6 Rafter R2 ( office ) - WF 250.125.6.9 Gunung Garuda/KS kg 2,299.92 2,194.66 16,000 5,000 35,114,598.40 10,973,312.00 2,299.92 2,194.66 46,087,910.40
7 Balok BL1 - WF 300.150.7.9 Gunung Garuda/KS kg 3,303.00 2,312.10 16,000 5,000 36,993,600.00 11,560,500.00 3,303.00 2,312.10 48,554,100.00
8 Balok BL2 - WF 250.125.6.9 Gunung Garuda/KS kg 1,776.00 6,615.60 16,000 5,000 105,849,600.00 33,078,000.00 1,776.00 6,615.60 138,927,600.00
9 Balok BL3 + plat t 10mm - WF 700.300.13.24+plat t 10mm Gunung Garuda/KS kg 22,242.12 22,496.00 16,500 5,000 371,184,000.00 112,480,000.00 22,242.12 22,496.00 483,664,000.00
10 Balok BL4 - WF 600.200.11.17 Gunung Garuda/KS kg 1,526.40 1,547.60 16,000 5,000 24,761,600.00 7,738,000.00 1,526.40 1,547.60 32,499,600.00
11 Balok G1 ( Office ) - WF 350.175.7.11 Gunung Garuda/KS kg 7,688.00 4,027.52 16,000 5,000 64,440,320.00 20,137,600.00 7,688.00 4,027.52 18,374.49 84,577,920.00
12 Balok G2 ( Office ) - WF 300.150.6,5.9 Gunung Garuda/KS kg 1,776.00 4,197.01 16,000 5,000 67,152,192.00 20,985,060.00 1,776.00 4,197.01 88,137,252.00
13 Balok penghubung antar kolom tengah - WF 200.100.6.9 Gunung Garuda/KS kg 1,023.84 - 16,000 5,000 - - 1,023.84 -
14 Balok penghubung antar kolom tengah atas - H 400.400.13.21 Gunung Garuda/KS kg 688.00 - 16,500 5,000 - - 688.00 -
15 Braching Runway Beam L 60.60.6 Gunung Garuda/KS kg 1,350.00 - 16,000 5,000 - - 1,350.00 -
16 Braching antar kolom L 60.60.6 Gunung Garuda/KS kg 3,888.00 364.22 16,000 5,000 5,827,584.00 1,821,120.00 3,888.00 364.22 7,648,704.00
17 Kolom K5 ( K.Gantung ) - WF 250.125.6.9 Gunung Garuda/KS kg 1,924.00 - 16,000 5,000 - - 1,924.00 -
18 Balok BL5 ( B diagonal ) - WF 250.125.6.9 Gunung Garuda/KS kg 345.55 476.86 16,000 5,000 7,629,696.00 2,384,280.00 345.55 476.86 10,013,976.00
19 Stiffener t=6 THK Gunung Garuda/KS kg 765.00 1,010.77 16,000 5,000 16,172,299.44 5,053,843.58 765.00 1,010.77 21,226,143.02
20 Plat t=10 mm Gunung Garuda/KS kg 876.00 3,064.18 16,000 5,000 49,026,808.86 15,320,877.77 876.00 3,064.18 64,347,686.63
21 Plat t=12 mm Gunung Garuda/KS kg 976.00 4,605.48 16,000 5,000 73,687,734.30 23,027,416.97 976.00 4,605.48 96,715,151.27
22 Base plat t : 20 mm Gunung Garuda/KS kg 1,123.00 2,146.83 16,000 5,000 34,349,301.01 10,734,156.57 1,123.00 2,146.83 45,083,457.58
23 Angkur bout ø 25 mm l : 100 cm Gunung Garuda/KS bh 96.00 96.00 175,000 75,000 16,800,000.00 7,200,000.00 96.00 96.00 24,000,000.00
24 Angkur bout ø 16 mm L : 80 cm Gunung Garuda/KS bh 132.00 - 95,000 50,000 - - 132.00 -
25 HTB ø 16 mm HTB bh 866.00 1,056.00 5,737 500 6,058,440.96 528,000.00 866.00 1,056.00 6,500.00 6,586,440.96
26 Baut hitam ø 13 mm HTB bh 1,125.00 1,116.00 6,600 400 7,365,600.00 446,400.00 1,125.00 1,116.00 3,500.00 7,812,000.00
27 Tangga safety Gunung Garuda/KS unit 1.00 1.00 7,125,000 3,000,000 7,125,000.00 3,000,000.00 1.00 10,125,000.00
28 Tangga utama unit 1.00 1.00 30,000,000 5,000,000 30,000,000.00 5,000,000.00 1.00 35,000,000.00
29 Gording CNP 150.65.20.2,3 - CNP 150.65.20.3,2 Gunung Garuda/KS kg 3,822.00 9,200.40 16,000 5,000 147,206,400.00 46,002,000.00 3,822.00 9,200.40 193,208,400.00
30 Rangka Cladding CNP 150.50.20.2,3 - CNP 125.65.20.2,3 Gunung Garuda/KS kg 2,940.00 3,593.57 16,000 5,000 57,497,088.00 17,967,840.00 2,940.00 3,593.57 75,464,928.00
31 Trekstang 12 mm Gunung Garuda/KS bh 44.00 3,084.00 32,500 750 100,230,000.00 2,313,000.00 44.00 3,084.00 102,543,000.00
32 Ikatan angin dia 16 Termasuk Turnbulk Gunung Garuda/KS bh 28.00 88.00 425,000 5,000 37,400,000.00 440,000.00 28.00 88.00 37,840,000.00
33 Pengecatan Baja Kansai Paint, white kg 112,542.41 133,104.98 2,200 650 292,830,961.64 86,518,238.67 112,542.41 133,104.98 379,349,200.30
-
4. PEKERJAAN PASANGAN ATAP & CLADDING 461,734,541.62 87,278,805.02 -
1 Atap Galvalume type G680, t = 0,5 mm (Incl.alumunium sunstop area office) Fumira, sunstop/Indofoil m² 1,261.20 1,298.23 163,548 33,748 212,322,920.04 43,812,666.04 1,261.20 1,298.23 190,000 256,135,586.08
2 Cladding Galvume t: 0,4mm Colour Fumira kg 717.00 896.62 150,568 25,960 135,002,280.16 23,276,255.20 717.00 896.62 170,000 158,278,535.36
3 Lisplank GRC 6/25cm ( area office ) GRC Board kg 54.00 54.00 57,372 10,124 3,098,066.40 546,717.60 54.00 65,000 3,644,784.00
4 Pasangan nok atap BJLS m¹ 30.00 30.65 75,024 13,240 2,299,497.86 405,793.74 30.00 30.65 85,000 2,705,291.60
5 Safety Roof ( Sling Ø 16 mm dan tiang Pipa 2" ) m¹ 202.40 202.40 154,462 27,258 31,263,108.80 5,517,019.20 202.40 175,000 36,780,128.00
6 Flashing BJLS m' 202.40 202.40 75,024 13,240 15,184,938.56 2,679,695.04 202.40 202.40 85,000 17,864,633.60
7 Talang Datar Mtr 60.00 61.30 286,858 50,622 17,584,395.40 3,103,128.60 60.00 61.30 325,000 20,687,524.00
8 Down pipe dia 6 inc Mtr 208.00 208.00 216,247 38,161 44,979,334.40 7,937,529.60 208.00 245,000 52,916,864.00 52,916,864.00
-
PEKERJAAN OFFICE -
-
1. PEKERJAAN DINDING + PLESTERAN DAN PLAFOND 341,917,992.32 60,338,469.23 -
1 Pasangan dinding batako keliling office & WC Batako m² 908.63 714.18 127,983 22,585 91,402,756.10 16,129,898.14 908.63 714.18 2,15) 145,000 107,532,654.24
2 Plesteran & acian dinding m² 1,817.26 1,428.36 83,851 14,797 119,769,128.69 21,135,728.59 1,817.26 95,000 140,904,857.28
3 Pengecatan Exterior mowilex m² 1,558.65 714.18 29,127 5,140 20,802,006.56 3,670,942.33 1,558.65 33,000 24,472,948.90
4 Pengecatan Interior vinilex m² 1,558.65 1,184.48 20,301 3,582 24,045,796.83 4,243,375.91 1,558.65 23,000 28,289,172.74
5 Plafond gypsum 9 mm rangka hollo knauf m² 562.90 543.50 101,504 17,912 55,167,206.60 9,735,389.40 562.90 543.50 115,000 64,902,596.00
6 Plafond grc 4 mm rangka hollo jayaboard m² 89.10 42.50 110,330 19,470 4,689,025.00 827,475.00 89.10 42.50 125,000 5,516,500.00
7 Lis plafond gypsum cornis m¹ 712.30 712.30 19,859 3,505 14,145,850.62 2,496,326.58 712.30 22,500 16,642,177.20
8 Pengecatan plafond vinilex m² 652.00 586.00 20,301 3,582 11,896,221.92 2,099,333.28 652.00 23,000 13,995,555.20
-
2. PEKERJAAN PASANGAN PINTU / JENDELA 168,089,239.66 44,681,949.78 -
1 Pintu type P 1 Alumunium, As. Solid unit 3.00 2.00 4,055,334 1,078,000 8,110,668.35 2,156,000.45 3.00 2.00 10,266,668.80
2 Pintu type P2 Alumunium, As. Solid unit 18.00 20.00 2,355,393 626,117 47,107,864.32 12,522,343.68 18.00 20.00 59,630,208.00
3 Pintu type P3 (PVC) Alumunium, As. Solid unit 9.00 9.00 1,549,554 411,907 13,945,986.29 3,707,160.91 9.00 9.00 17,653,147.20
4 Pintu type P4 Alumunium, As. Solid unit 2.00 2.00 2,355,393 626,117 4,710,786.43 1,252,234.37 2.00 2.00 5,963,020.80
5 Pintu type P4 Alumunium, As. Solid unit - - -
6 Jendela type J 1 Alumunium, As. Solid unit 26.00 26.00 2,407,692 640,019 62,599,979.83 16,640,500.97 26.00 79,240,480.80
7 Jendela type J 2 Alumunium, As. Solid unit 20.00 20.00 1,020,339 271,229 20,406,785.78 5,424,588.62 20.00 25,831,374.40
8 Jendela type J 3 Alumunium, As. Solid unit 4.00 4.00 1,309,588 348,118 5,238,350.20 1,392,472.84 4.00 6,630,823.04
9 Bouwvenlight BV1 Alumunium, As. Solid unit 17.00 17.00 351,107 93,332 5,968,818.46 1,586,647.94 17.00 7,555,466.40
- - -
3. PEKERJAAN LANTAI DAN TANGGA 101,852,056.01 25,199,754.20 -
1 Pasang lantai keramik 40 x 40 cm ex : Asia Tile asia tile m² 533.50 533.50 103,896 26,597 55,428,278.27 14,189,232.75 533.50 543.50 -O144 126,650 69,617,511.02
2 Pasang lantai keramik 30 x 30 cm ex : Asia Tile asia tile m² 42.50 42.50 103,896 26,597 4,415,561.06 1,130,351.25 42.50 42.50 126,650 5,545,912.31
3 Pasang dinding keramik 30 x 25 cm, t = 2 m asia tile m² 181.40 176.80 103,896 26,597 18,368,734.02 4,702,261.20 181.40 176.80 3+10) 126,650 23,070,995.22
4 Plint lantai keramik 40 x10 cm ex : Asia Tile asia tile m¹ 712.30 712.30 18,868 4,830 13,439,482.65 3,440,409.00 712.30 23,000 16,879,891.65
5 Waterprofing, coating ex. Sika → Toilet Mezzanine sika m² 17.50 17.50 90,000 35,000 1,575,000.00 612,500.00 17.50 17.50 2,187,500.00
6 Railling pipa baja medium dicat, lantai 2 pipa blacksteel m¹ 15.00 15.00 575,000 75,000 8,625,000.00 1,125,000.00 15.00 9,750,000.00
-
4. PEKERJAAN ALAT SANITAIR 43,216,000.00 9,941,000.00 -
1 Kloset jongkok American Standard American standart bh 5.00 5.00 357,080 94,920 1,785,400.00 474,600.00 5.00 5.00 452,000 2,260,000.00
2 Kloset duduk American Standard American standart bh 2.00 4.00 2,372,500 250,000 9,490,000.00 1,000,000.00 ### 2.00 4.00 2,622,500 10,490,000.00
3 Floor drain American Standard American standart bh 17.00 19.00 406,850 108,150 7,730,150.00 2,054,850.00 17.00 19.00 515,000 9,785,000.00
4 Jet washer American Standard American standart bh 2.00 4.00 213,000 75,000 852,000.00 300,000.00 75 2.00 4.00 288,000 1,152,000.00
5 Kran air Amreican Standard American standart bh 11.00 11.00 201,450 53,550 2,215,950.00 589,050.00 11.00 11.00 255,000 2,805,000.00
6 urinoir American standart bh 5.00 5.00 2,524,050 670,950 12,620,250.00 3,354,750.00 5.00 5.00 3,195,000 15,975,000.00
7 Wastafel American Standard American standart bh 3.00 3.00 1,125,750 299,250 3,377,250.00 897,750.00 3.00 3.00 1,425,000 4,275,000.00
8 Tempat sabun American Standard American standart bh 9.00 11.00 175,000 50,000 1,925,000.00 550,000.00 50 9.00 11.00 225,000 2,475,000.00
9 Kaca Cermin 160 x 180 cm lokal bh 2.00 2.00 685,000 35,000 1,370,000.00 70,000.00 2.00 2.00 1,440,000.00
10 Kicthen sink satu lobang + kran angsa ex. American Standard IN 38 W/M Chrome Royal bh 1.00 1.00 485,000 65,000 485,000.00 65,000.00 1.00 1.00 550,000.00
11 Meja beton lapis keramik Keramik m¹ 1.50 2.60 525,000 225,000 1,365,000.00 585,000.00 1.50 2.60 1,950,000.00 0.18
-
PEKERJAAN SARANA LUAR -
1. PEKERJAAN SARANA LUAR #N/A #N/A -
1 Saluran Beton,t = 15cm uk. 30 x 60 cm, Readymix K250 m¹ 142.00 172.00 1,211,070 321,930 208,304,040.00 55,371,960.00 142.00 172.00 1,533,000 263,676,000.00 38.34
2 Bak kontrol uk. 40 x 40 cm bh 6.00 8.00 435,073 115,652 3,480,582.00 925,218.00 6.00 8.00 550,725 4,405,800.00 0.13
3 Rabat beton t = 10 cm, wiremesh m6 single m² 40.00 98.00 #N/A #N/A #N/A #N/A 40.00 98.00 #N/A 9.80 10.00 10.00
4 Biotech BT 16 Biotech unit 1.00 1.00 23,543,643 6,258,437 23,543,643.20 6,258,436.80 1.00 1.00 28,700,000 29,802,080.00 0.23
5 Pembuatan Oil Trap uk ( 600 x 200 x 200 )cm UNIT 1.00 1.00 53,285,500 14,164,500 53,285,500.00 14,164,500.00 1.00 1.00 67,450,000 67,450,000.00 10.37 73.73 764.43
6 Grill saluran UNP 100 m' 84.00 150.00 1,797,250 477,750 269,587,500.00 71,662,500.00 84.00 150.00 2,275,000 341,250,000.00
7 Groudwater tank Readymix K250 unit 1.00 1.00 87,492,500 23,257,500 87,492,500.00 23,257,500.00 1.00 1.00 110,750,000.00 14.94 86.30 1,289.67
8 Floorhardener 5kg/m2 sika m2 1,620.00 1,620.00 30,000 15,000 48,600,000.00 24,300,000.00 1,620.00 1,500.00 35,000.00 72,900,000.00
-
PEKERJAAN MEP -
PEKERJAAN MEKANIKAL / ELEKTRIKAL WORKSHOP 1,453,572,343.36 272,975,044.00 -
A ELECTRICAL WORKS -
A.1 ELECTRICAL MAINWORKSHOP -
1 Pekerjaan Panel Lokal, Standard PAMA -
LP – WS & Ofc unit 1.00 1.00 22,921,600 2,000,000 22,921,600.00 2,000,000.00 1.00 24,000,000.00 24,921,600.00 24,921,600.00
PP – Stop Kontak unit 1.00 1.00 17,710,400 1,500,000 17,710,400.00 1,500,000.00 1.00 18,500,000.00 19,210,400.00 19,210,400.00
Panel - PP UPS-1 unit 1.00 1.00 17,710,400 1,500,000 17,710,400.00 1,500,000.00 1.00 18,500,000.00 19,210,400.00 19,210,400.00
Panel SDP Main workshop unit 1.00 1.00 42,151,200 2,500,000 42,151,200.00 2,500,000.00 1.00 43,000,000.00 44,651,200.00 44,651,200.00
2 Kabel - -
Kabel Sub ari LVDP ke SDP WS : - -
Kabel Sub Feeder dari SDP WS ke : NYY 4c – 185 mm Kabel Metal, Kabelindo, Sup mtr 298.00 298.00 1,110,564 250,000 330,947,952.80 74,500,000.00 298.00 1,310,250.00 405,447,952.80 405,447,952.80
Panel SK NYY 4c – 95 mm Kabel Metal, Kabelindo, Sup mtr 8.00 8.00 702,824 55,000 5,622,594.56 440,000.00 8.00 729,800.00 6,062,594.56 6,062,594.56
Panel LP WS & Ofc NYY 4c - –35 mm Kabel Metal, Kabelindo, Sup mtr 8.00 8.00 218,370 35,000 1,746,956.80 280,000.00 8.00 244,000.00 2,026,956.80 2,026,956.80
Panel PP UPS NYY 4c – 6 mm Kabel Metal, Kabelindo, Sup mtr 8.00 8.00 71,312 25,000 570,492.80 200,000.00 8.00 92,750.00 770,492.80 770,492.80
Sparing kabel ls 1.00 1.00 32,112 25,000 32,112.00 25,000.00 1.00 55,000.00 57,112.00 57,112.00
3 Kabel leeder 300 x 100 c/w fitting, Tree Star/ traytek mtr -.0 181,841 48,338 - - -.0 221,667 - -
Kabel leeder 200 x 100 c/w fitting, mtr 120.00 120.00 144,926 38,525 17,391,123.20 4,622,956.80 120.00 176,667 22,014,080.00 22,014,080.00
Elbow 90 derajat Tree Star/ traytek bh 4.00 4.00 61,525 16,355 246,100.80 65,419.20 4.00 75,000 311,520.00 311,520.00
T 200 x 200 Tree Star/ traytek bh 4.00 4.00 113,445 16,355 453,780.80 65,419.20 4.00 125,000.00 519,200.00 519,200.00
4 support and accessories ls 1.00 1.00 2,871,176 763,224 2,871,176.00 763,224.00 1.00 3,500,000 3,634,400.00 3,634,400.00
5 FLOOD LED 180 W TYPE : NNP 34935 SM Panasonic bh 8.00 8.00 8,626,968 350,000 69,015,744.00 2,800,000.00 16.00 8.00 8,645,000.00 71,815,744.00 71,815,744.00
6 Lampu HPIBU LED 210 W TYPE : NNP 35736 SM Panasonic bh 48.00 48.00 7,536,648 350,000 361,759,104.00 16,800,000.00 54.00 48.00 7,595,000.00 378,559,104.00 378,559,104.00
7 Stop kontak 50 A/ 3 phase TYPE 56C550RP+56P550 Clipsal bh 3.00 3.00 1,709,206 259,600 5,127,619.20 778,800.00 3.00 3.00 1,896,000 5,906,419.20 5,906,419.20
8 Stop kontak 32 A/ 3 phase TYPE 56C432+56P432 Clipsal bh 3.00 3.00 1,260,618 259,600 3,781,852.80 778,800.00 3.00 3.00 1,464,000 4,560,652.80 4,560,652.80
9 Stop kontak 15 A/ 1 phase TYPE 56C316+56P316 Clipsal bh 3.00 3.00 783,992 259,600 2,351,976.00 778,800.00 3.00 3.00 1,005,000 3,130,776.00 3,130,776.00
-
-
10 Instalation Kabel Metal, Kabelindo, Supreme -
Installation lampu HPIT LED 180 W NYM 3 x 2,5mm + Conduit Kabel Metal, Kabelindo, Sup ttk 8.00 8.00 306,328 155,760 2,450,624.00 1,246,080.00 16.00 445,000 3,696,704.00 3,696,704.00
Installation lampu HPIBU Lampu LED 210 W NYM 3 x 2,5mm + Conduit Kabel Metal, Kabelindo, Sup ttk 48.00 48.00 306,328 155,760 14,703,744.00 7,476,480.00 54.00 22,180,224.00 22,180,224.00
Installation Stop kontak 16 A/1 p NYM 3 x 2,5mm + Conduit Kabel Metal, Kabelindo, Sup ttk 3.00 3.00 3,092,355 155,760 9,277,065.60 467,280.00 3.00 3,128,000 9,744,345.60 9,744,345.60
Installation Stop kontak 50 A/3 p NYY 4 x 16mm + G Kabel Metal, Kabelindo, Sup ttk 3.00 3.00 7,815,907 259,600 23,447,721.00 778,800.00 3.00 7,776,875 24,226,521.00 24,226,521.00
Installation Stop kontak 32 A/3 p NYY 4 x 6mm + G Kabel Metal, Kabelindo, Sup ttk 3.00 3.00 3,582,610 259,600 10,747,829.40 778,800.00 3.00 3,700,125 11,526,629.40 11,526,629.40
-
A.2 ELECTRICAL WORKS OFFICE -
1 Lighting, Outlet and Instlation -
2 Lampu 2 x 36 Watt Surface Mounted with V-Shave (TKO) Philips,Panasonic,Lucolite bh 52.00 52.00 498,432 129,800 25,918,464.00 6,749,600.00 52.00 62.00 605,000.00 32,668,064.00 32,668,064.00
Lampu 1 x 36 Watt Surface Mounted with V-Shave (TKO) Philips,Panasonic,Lucolite bh 26.00 26.00 381,093 129,800 9,908,412.80 3,374,800.00 26.00 7.00 492,000.00 13,283,212.80 13,283,212.80
3 Down Light 1x18 Watt dia 5 " Philips,Panasonic,Lucolite bh -.0 0.00 154,202 129,800 - - -.0 273,500.00 - -
Down Light 1x 9 Watt dia 3 " Philips,Panasonic,Lucolite bh -.0 0.00 140,184 129,800 - - -.0 260,000.00 - -
4 Stop Kontak 1 Ph/ 16 A 1 Gang MK / CLIPSAL bh 30.00 30.00 31,152 36,344 934,560.00 1,090,320.00 30.00 65,000 2,024,880.00 2,024,880.00
5 Stop Kontak 1 Ph/ 16 A 4 Gang ( UPS ) MK / CLIPSAL bh 30.00 30.00 93,456 36,344 2,803,680.00 1,090,320.00 30.00 125,000 3,894,000.00 3,894,000.00
6 Single Switch Clipsal Standard bh 45.00 45.00 25,960 36,344 1,168,200.00 1,635,480.00 45.00 18.00 60,000 2,803,680.00 2,803,680.00
7 Double Switch Clipsal Standard bh 25.00 25.00 31,152 36,344 778,800.00 908,600.00 25.00 12.00 65,000 1,687,400.00 1,687,400.00
8 NYM 3 x 2,5 mm2 + conduit to Installation FL 2 x 36 Watt & 1 x 36 Watt Supreme ttk 52.00 100.00 153,640 80,000 15,364,000.00 8,000,000.00 52.00 225,000 23,364,000.00 23,364,000.00
9 NYM 3 x 2,5 mm2 + conduit to Installation Down Light 18 Watt + 9 Watt Supreme ttk 26.00 0.00 153,640 80,000 - - 26.00 - -
10 NYM 3 x 2,5 mm2 + conduit to Installation Receptacle 1 Ph/16 A 1 Gang' Supreme ttk 30.00 30.00 153,640 80,000 4,609,200.00 2,400,000.00 30.00 7,009,200.00 7,009,200.00
11 NYM 3 x 2,5 mm2 + Conduit to General Receptacle 1 Ph/16 A 2 Gang ( UPS ) Supreme ttk 30.00 30.00 153,640 80,000 4,609,200.00 2,400,000.00 30.00 7,009,200.00 7,009,200.00
12 Support of Material Lot 1.00 1.00 3,934,900 997,500 3,934,900.00 997,500.00 1.00 4,500,000 4,750,000.00 4,932,400.00 4,932,400.00
13 Grounding Bangunan Keliling ( dari kolom di conenect ke tulangan lantai) BC 50mm Lot 6.00 6.00 3,727,800 945,000 22,366,800.00 5,670,000.00 6.00 4,500,000.00 28,036,800.00 28,036,800.00
14 Telephone ( Outlet + Instalation "ITC 2pair" ) ttk 30.00 30.00 355,500 94,500 10,665,000.00 2,835,000.00 30.00 450,000 13,500,000.00 13,500,000.00
15 Data ( Outlet + Instalation "Cat 6" ) ttk 24.00 24.00 256,750 68,250 6,162,000.00 1,638,000.00 24.00 325,000 7,800,000.00 7,800,000.00
-
B Lighting System -
1 Finial / air terminal ( Electrostatis )R= 120MTR Erico/Prevecton unit 1.00 1.00 32,767,200 1,500,000 32,767,200.00 1,500,000.00 1.00 33,000,000.00 34,267,200.00 34,267,200.00
2 Down Conductur Double Sheilded 2x35mm m' 30.00 30.00 207,100 52,500 6,213,000.00 1,575,000.00 30.00 250,000.00 7,788,000.00 7,788,000.00
3 Grounding ( min 2 titik & tahanan max 2 ohm ) Cover Rood 5/8 " bh 2.00 2.00 2,899,400 735,000 5,798,800.00 1,470,000.00 2.00 3,500,000.00 7,268,800.00 7,268,800.00
4 Bak kontrol bh 1.00 1.00 372,780 94,500 372,780.00 94,500.00 1.00 450,000.00 467,280.00 467,280.00
5 Tiang pipa dia. 2" panjang 3m Galvanis bh 1.00 1.00 165,680 42,000 165,680.00 42,000.00 1.00 200,000.00 207,680.00 207,680.00
- - -
C MECHANICAL WORKS -
1 Packed Booster Pump (Double) ls 1.00 1.00 46,420,000 5,500,000 46,420,000.00 5,500,000.00 1.00 50,000,000.00 51,920,000.00 51,920,000.00
Merk Grounfos / Ebara -
Type -
Kap. -
Total Head 40 m -
Power -
Presure Tank ( include ) -
Model membran -
Cap. 200 lt/m -
Automatic Panel Water Pump -
Cable Power Pump NYY 4x6 mm2 ( 50 m' ) -
Include fitting, support and accessories -
-
2 Air Conditioning -
AC Split Wall type 2 PK – 18000 BTU / H Panasonic Unit 10.00 5.00 6,920,720 400,000 34,603,600.00 2,000,000.00 10.00 5.00 7,050,000 36,603,600.00 36,603,600.00
AC Split Wall type 1.5 PK – 13500 BTU / H Panasonic Unit 6.00 7.00 5,015,256 400,000 35,106,792.00 2,800,000.00 6.00 7.00 5,215,000 37,906,792.00 37,906,792.00
AC Split Wall type 1 PK – 9000 BTU / H Panasonic Unit 2.00 5.00 3,603,032 400,000 18,015,160.00 2,000,000.00 2.00 5.00 3,855,000 20,015,160.00 20,015,160.00
AC Split Wall type 0,75 PK - 7000 BTU / H Panasonic Unit 2.00 6.00 3,494,000 400,000 20,964,000.00 2,400,000.00 2.00 6.00 3,750,000 23,364,000.00 23,364,000.00
Exhaust fan Panasonic - - - -
Kapasitas 318 CFM Wall Type UNIT 16.00 16.00 434,500 115,500 6,952,000.00 1,848,000.00 16.00 550,000 8,800,000.00 8,800,000.00
Kapasitas 265 CFM Ceiling Type UNIT 2.00 2.00 414,750 110,250 829,500.00 220,500.00 2.00 525,000 1,050,000.00 1,050,000.00
Installation AC + Cable Power + Cable Control Panasonic Lot 950,000 175,000 1,125,000 - -
Installation Exhaust + Cable Power + Cable Control Panasonic Lot - - -
Support of Material Lot 1.00 1.00 2,071,000 525,000 2,071,000.00 525,000.00 1.00 2,500,000.00 2,596,000.00 2,596,000.00
-
3 Oil piping instalation -
Pipe dia 50mm line 1 Blacksteel schedul 40 mtr 90.00 90.00 128,786 75,000 11,590,740.00 6,750,000.00 90.00 196,250.00 18,340,740.00 18,340,740.00
Pipe dia 50mm line 2 Blacksteel schedul 40 mtr 90.00 90.00 128,786 75,000 11,590,740.00 6,750,000.00 90.00 18,340,740.00 18,340,740.00
Pipe dia 50mm line 3 Blacksteel schedul 40 mtr 90.00 90.00 128,786 75,000 11,590,740.00 6,750,000.00 90.00 18,340,740.00 18,340,740.00
Pipe dia 50mm line 4 Blacksteel schedul 40 mtr 90.00 90.00 128,786 75,000 11,590,740.00 6,750,000.00 90.00 18,340,740.00 18,340,740.00
Pipe dia 50mm line 5 Blacksteel schedul 40 mtr 90.00 90.00 128,786 75,000 11,590,740.00 6,750,000.00 90.00 18,340,740.00 18,340,740.00
Pipe dia 50mm line 6 Blacksteel schedul 40 mtr 90.00 90.00 128,786 75,000 11,590,740.00 6,750,000.00 90.00 18,340,740.00 18,340,740.00
Pipe dia 50mm line 7 Blacksteel schedul 40 mtr 90.00 90.00 128,786 75,000 11,590,740.00 6,750,000.00 90.00 18,340,740.00 18,340,740.00
- - -
Pipa dia 20mm line 1 Blacksteel schedul 40 mtr 30.00 30.00 66,763 35,000 2,002,896.00 1,050,000.00 30.00 98,000.00 3,052,896.00 3,052,896.00
Pipa dia 20mm line 2 Blacksteel schedul 40 mtr 30.00 30.00 66,763 35,000 2,002,896.00 1,050,000.00 30.00 3,052,896.00 3,052,896.00
Pipa dia 20mm line 3 Blacksteel schedul 40 mtr 30.00 30.00 66,763 35,000 2,002,896.00 1,050,000.00 30.00 3,052,896.00 3,052,896.00
Pipa dia 20mm line 4 Blacksteel schedul 40 mtr 30.00 30.00 66,763 35,000 2,002,896.00 1,050,000.00 30.00 3,052,896.00 3,052,896.00
Pipa dia 20mm line 5 Blacksteel schedul 40 mtr 30.00 30.00 66,763 35,000 2,002,896.00 1,050,000.00 30.00 3,052,896.00 3,052,896.00
Pipa dia 20mm line 6 Blacksteel schedul 40 mtr 30.00 30.00 66,763 35,000 2,002,896.00 1,050,000.00 30.00 3,052,896.00 3,052,896.00
Pipa dia 20mm line 7 Blacksteel schedul 40 mtr 30.00 30.00 66,763 35,000 2,002,896.00 1,050,000.00 30.00 3,052,896.00 3,052,896.00
Ball Valve dia 20" Kitz bh 42.00 42.00 389,660 103,580 16,365,703.20 4,350,376.80 42.00 475,000 20,716,080.00 20,716,080.00
Fitting, support and accessories ls 1.00 1.00 10,254,200 2,625,000 10,254,200.00 2,625,000.00 1.00 12,500,000.00 12,879,200.00 12,879,200.00
- - -
4 Clean Water Piping Instalation - - -
GIP med dia. 50 mm Spindo mtr 108.00 108.00 112,431 75,000 12,142,569.60 8,100,000.00 108.00 180,500 20,242,569.60 20,242,569.60
GIP med dia. 20 mm Spindo mtr 30.00 30.00 39,505 35,000 1,185,156.00 1,050,000.00 30.00 71,750 2,235,156.00 2,235,156.00
Ball Valve dia. 50 mm Kitz nos 2.00 2.00 512,710 136,290 1,025,420.00 272,580.00 2.00 625,000 1,298,000.00 1,298,000.00
Ball Valve dia. 20 mm Kitz nos 6.00 6.00 389,660 103,580 2,337,957.60 621,482.40 6.00 2,959,440.00 2,959,440.00
Fitting, support and accessories lot 1.00 1.00 1,230,504 315,000 1,230,504.00 315,000.00 1.00 1,500,000.00 1,545,504.00 1,545,504.00
- - -
5 Air Compresed Instalation - - -
GIP med dia. 50 mm Spindo m 108.00 108.00 112,431 75,000 12,142,569.60 8,100,000.00 108.00 20,242,569.60 20,242,569.60
GIP med dia. 20 mm Spindo m 30.00 30.00 39,505 35,000 1,185,156.00 1,050,000.00 30.00 2,235,156.00 2,235,156.00
Ball Valve dia. 50 mm Kitz m 2.00 2.00 512,710 103,580 1,025,420.00 207,160.80 2.00 1,232,580.80 1,232,580.80
Ball Valve dia. 20 mm Kitz m 6.00 6.00 389,660 103,580 2,337,957.60 621,482.40 6.00 2,959,440.00 2,959,440.00
Fitting, support and accessories lot 1.00 1.00 1,230,504 315,000 1,230,504.00 315,000.00 1.00 1,545,504.00 1,545,504.00
- - -
6 Clean water piping instalation - - -
Pipa PVC dia. 50 mm Wavin AW m 108.00 108.00 21,920 30,000 2,367,360.00 3,240,000.00 108.00 50,000.00 5,607,360.00 5,607,360.00
Pipa PVC dia. 20 mm Wavin AW m 30.00 30.00 15,114 15,000 453,408.00 450,000.00 30.00 29,000.00 903,408.00 903,408.00
Ball Valve dia. 50 mm Kitz m 2.00 2.00 512,710 35,000 1,025,420.00 70,000.00 2.00 1,095,420.00 1,095,420.00
Ball Valve dia. 20 mm Kitz m 6.00 6.00 389,660 103,580 2,337,957.60 621,482.40 6.00 2,959,440.00 2,959,440.00
Fitting, support and accessories lot 1.00 1.00 1,230,504 315,000 1,230,504.00 315,000.00 1.00 1,500,000.00 1,545,504.00 1,545,504.00
- - -
6 Plumbing Toilet Installation, incl pipa Ventilasi - - -
Pipe PVC AW type dia 100mm Wavin AW Mtr 36.00 36.00 94,722 60,000 3,409,977.60 2,160,000.00 36.00 149000 5,569,977.60 5,569,977.60
Pipe PVC AW type dia 50mm Wavin AW Mtr 18.00 18.00 21,920 30,000 394,560.00 540,000.00 18.00 934,560.00 934,560.00
Pipe PVC AW type dia 40mm Wavin AW Mtr 42.00 42.00 19,036 22,500 799,512.00 945,000.00 42.00 40,000.00 1,744,512.00 1,744,512.00
Pipe PVC AW dia 25 mm Wavin AW Mtr -.0 0.00 15,633 15,000 - - -.0 29,500.00 - -
Pipe PVC AW dia 20 mm Wavin AW Mtr 12.00 12.00 13,556 15,000 162,672.00 180,000.00 12.00 27,500.00 342,672.00 342,672.00
Pipe PVC AW dia 15 mm Wavin AW Mtr -.0 0.00 10,960 15,000 - - -.0 25,000.00 - -
Fitting of Material Rucika Lot 1.00 1.00 1,230,504 315,000 1,230,504.00 315,000.00 1.00 1,545,504.00 1,545,504.00
-
PEKERJAAN TAMBAHAN 336,582,970.58 1,169,987,671.06 -
1 Pekerjaan Persiapan ls 1.00 1,083,660,000 - 1,083,660,000.00 1,083,660,000.00
2 Pasangan dinding double gypsum m² 470.30 105,184 35,000 49,468,035.20 16,460,500.00 470.30 2,15) 135,000 65,928,535.20
3 Lampu 1 x 18 Watt Surface Mounted with V-Shave (TKO) Philips,Panasonic,Lucolite bh 22.00 381,320 60,000 8,389,040.00 1,320,000.00 22.00 425,000.00 9,709,040.00 9,709,040.00
-
3. PEKERJAAN STRUKTUR BAJA -
WORKSHOP DAN OFFICE -
1 HB 300.300.10.15 (K5) Gunung Garuda/KS kg 1,925.50 16,500 5,000 31,770,684.00 9,627,480.00 1,925.50 41,398,164.00
2 WF 200.100.5,5.8 (R3) Gunung Garuda/KS kg 205.33 16,000 5,000 3,285,333.33 1,026,666.67 205.33 4,312,000.00
3 WF 200.100.5,5.8 (BL3) Gunung Garuda/KS kg 699.73 16,000 5,000 11,195,733.33 3,498,666.67 699.73 14,694,400.00
4 WF 200.100.5,5.8 (G5) Gunung Garuda/KS kg 1,417.60 16,000 5,000 22,681,600.00 7,088,000.00 1,417.60 29,769,600.00
5 L 50.50.5 (Bracing Antar Kolom) Gunung Garuda/KS kg 358.34 16,000 5,000 5,733,504.00 1,791,720.00 358.34 7,525,224.00
6 L 50.50.5 (Bracing Runway) Gunung Garuda/KS kg 686.80 16,000 5,000 10,988,732.16 3,433,978.80 686.80 14,422,710.96
7 L 40.40.4 Gunung Garuda/KS kg 148.98 16,000 5,000 2,383,603.20 744,876.00 148.98 3,128,479.20
8 RB Ø 16 mm (Ikatan Angin) Gunung Garuda/KS kg 1,140.30 16,000 5,000 18,244,864.00 5,701,520.00 1,140.30 23,946,384.00
9 RB Ø 12 mm (Trekstang) Gunung Garuda/KS kg 1,264.03 16,000 5,000 20,224,426.67 6,320,133.33 1,264.03 26,544,560.00
10 Bollard Ø 8 mm t=8,2 mm Gunung Garuda/KS kg 1,009.92 16,000 5,000 16,158,720.00 5,049,600.00 1,009.92 21,208,320.00
11 Plat 16 mm Gunung Garuda/KS kg 260.74 16,000 5,000 4,171,887.88 1,303,714.96 260.74 5,475,602.84
12 Plat 8 mm Gunung Garuda/KS kg 2,271.36 16,000 5,000 36,341,806.81 11,356,814.63 2,271.36 47,698,621.44
13 Angkur Ø 19 mm bh 132.00 135,000 65,000 17,820,000.00 8,580,000.00 132 26,400,000.00
14 HTB Ø 22 mm bh 448.00 26,250 750 11,760,000.00 336,000.00 448 12,096,000.00
15 HTB Ø 19 mm bh 3,454.00 16,900 600 58,372,600.00 2,072,400.00 3,454 60,445,000.00
16 UNC Ø 12 mm bh 2,052.00 3,700 300 7,592,400.00 615,600.00 2,052 8,208,000.00
-
-
633.60 - 717.32 17.86 - 7.45 5.64 2,453.36 64,998.92 10.00 300.00 28.00 - 684.95 367,606,833.60 1,421,566,457.76
VOL UNIT PRICE TOTAL PRICE VOL Volume Koef Sirtu Koef Pasir Urug Readymix Sitemix
Lantai kerja Readymix
Koef Split Koef Pasir Beton Koef Semen Koef Besi Koef M.6 Koef M.8 Koef M.10 Koef Bekisting MECAMICAL ELECTRICAL
NO JENIS PEKERJAAN SPESIFIKASI UNIT KONT
PAMA MATERIAL UPAH MATERIAL UPAH PAMA GGL m3 m3 m3 m3 m3 m3 m3 kg Kg lbr lbr lbr m2 (Rp) (Rp)
I WASHING BAYS
A. PEKERJAAN TANAH 59,677,702 95,089,646 -
1 Galian tanah m³ 221.20 37.13 - 77,880 - 2,891,295 221.20 37.13 2,891,295.00 - 2,891,295.00 2,891,295.00
2 Buangan tanah m³ 962.00 962.00 - 77,880 - 74,920,560 962.00 74,920,560.00 - 74,920,560.00 74,920,560.00
3 Urugan tanah kembali m³ 3.60 3.60 - 77,880 - 280,368 3.60 280,368.00 - 280,368.00 280,368.00
4 Pemadatan tanah m² 435.20 214.75 - 15,576 - 3,344,946 435.20 3,344,946.00 - 3,344,946.00 3,344,946.00
5 Sirtu dibawah slab lantai Washing dan Ramp t = 20 cm m³ 87.04 39.93 347,692 57,112 13,882,646 2,280,368 87.04 39.93 16,163,014.11 13,882,646.18 2,280,367.94 16,163,014.11 1.20 47.91
6 Plastik cor m² 435.20 214.75 4,855 857 1,042,508 183,972 435.20 214.75 1,226,480.20 1,042,508.17 183,972.03 1,226,480.20
7 Pekerjaan Cerucuk dolken-->>asumsi L-2m @1m m 962.00 962.00 46,520 11,630 44,752,548 11,188,137 962.00 962.00 55,940,684.80 44,752,547.84 11,188,136.96 55,940,684.80
- - - -
B PEKERJAAN STRUKTUR DASAR 189,222,280 51,658,992 - - - -
1 Slab Lantai dasar t = 30 cm Tulangan D13-150 Double Layer Ready mix K-250 m³ 88.56 44.55 2,629,752 699,048 117,155,452 31,142,588 88.56 44.55 148,298,040.00 117,155,451.60 31,142,588.40 148,298,040.00 44.55 102.21 4,553.25 25.50
2 Ramp (In) dan (Out) t = 30 cm Tulangan D12-150 double layer m³ 42.00 13.50 2,629,752 699,048 35,501,652 9,437,148 42.00 13.50 44,938,800.00 35,501,652.00 9,437,148.00 44,938,800.00 13.50 102.21 1,379.77 22.80
3 Bund wall atas saluran Tinggi 75 cm, Lebar 15 cm m¹ 3.60 25.00 295,847 78,643 7,396,178 1,966,073 3.60 25.00 9,362,250.00 7,396,177.50 1,966,072.50 9,362,250.00 25.00 102.21 2,555.13
4 Rabat beton T = 10 cm tanpa tulangan L = 240 cm m3 - 4.13 1,129,779 300,321 4,660,338 1,238,824 - 4.13 5,899,162.50 4,660,338.38 1,238,824.13 5,899,162.50 4.13
5 Saluran beton L. 80 cm ke arah bak plumbing m¹ - 0.00 - - - - - - -
6 Saluran Plumbing L. 80 cm bawah Ramp (In) dan (Out) m¹ - 0.00 - - - - - - -
7 Bak kontrol uk. 200x200x100 cm bh 5.00 1.00 18,703,661 4,971,859 18,703,661 4,971,859 5.00 1.00 22,800,000 23,675,520.00 18,703,660.80 4,971,859.20 23,675,520.00 0.90
8 Floor hardener slab washing 5kg/m2 m2 435.20 193.50 30,000 15,000 5,805,000 2,902,500 435.20 193.50 8,707,500.00 5,805,000.00 2,902,500.00 8,707,500.00
- - - -
D. PEKERJAAN SARANA LUAR - - - -
1 Galian tanah ALAT PC dari PAMA m³ 186.35 399.00 - 77,880 - 31,074,120 186.35 399.00 31,074,120.00 - 31,074,120.00 31,074,120.00
2 Buangan tanah m³ 179.00 179.00 - 77,880 - 13,940,520 179.00 13,940,520.00 - 13,940,520.00 13,940,520.00
2 Urugan tanah kembali m³ 7.85 7.85 - 77,880 - 611,670 7.85 611,669.52 - 611,669.52 611,669.52
3 Pemadatan tanah m² 129.20 142.50 - 15,576 - 2,219,580 129.20 104 2,219,580.00 - 2,219,580.00 2,219,580.00
4 Plastik cor m² 129.20 142.50 4,855 857 691,769 122,077 129.20 142.50 813,846.00 691,769.10 122,076.90 813,846.00
5 Sirtu dibawah lantai dasar t = 30 cm m³ 38.76 49.67 347,692 57,112 17,268,123 2,836,467 38.76 49.67 20,104,590.66 17,268,123.18 2,836,467.48 20,104,590.66 1.20 59.60
6 Waterstop m¹ 54.10 46.50 184,576 49,064 8,582,765 2,281,495 54.10 46.50 225,000 10,864,260.00 8,582,765.40 2,281,494.60 10,864,260.00
7 Waterproofing coating (dinding saja) m² 97.00 68.00 90,000 35,000 6,120,000 2,380,000 97.00 68.00 8,500,000.00 6,120,000.00 2,380,000.00 8,500,000.00
8 Tangga Maintenance h-1,8m unit 2.00 2.00 1,107,454 294,386 2,214,907 588,773 2.00 2.00 1,350,000 2,803,680.00 2,214,907.20 588,772.80 2,803,680.00
9 Slab Lantai dasar t = 20 cm D10-200 double m³ 25.84 33.00 2,257,504 600,096 74,497,632 19,803,168 25.84 33.00 94,300,800.00 74,497,632.00 19,803,168.00 94,300,800.00 33.00 91.50 3,019.66 9.64
10 Dinding beton t = 20 cm D13-200 dan Ø12-200 m³ 15.40 15.64 3,642,848 968,352 56,974,143 15,145,025 15.40 15.64 72,119,168.00 56,974,142.72 15,145,025.28 72,119,168.00 15.64 104.97 1,641.71 248.00
11 Pipa out let dia. 4" PVC m' 11.75 11.75 94,722 60,000 1,112,979 705,000 11.75 1,817,978.80 1,112,978.80 705,000.00 1,817,978.80 1,817,978.80
12 Railing baja h-1m finish cat m 8.00 54.00 697,286 185,354 37,653,422 10,009,138 8.00 54.00 850,000 47,662,560.00 37,653,422.40 10,009,137.60 47,662,560.00
- - - - - -
F. PEKERJAAN INSTALASI AIR BERSIH 19,686,013 5,232,991 - - - -
1 Pipa mainline dia 4" Galvanis m 36.00 36.00 426,917 113,484 15,368,995 4,085,429 36.00 520,417 19,454,424.00 15,368,994.96 4,085,429.04 19,454,424.00 19,454,424.00
2 Pipa watercanon Ø 2" Galvanis m 6.00 6.00 377,696 100,400 2,266,178 602,402 6.00 460,417 2,868,580.00 2,266,178.20 602,401.80 2,868,580.00 2,868,580.00
3 Fiting ls 1.00 1.00 2,050,840 545,160 2,050,840 545,160 1.00 2,500,000 2,596,000.00 2,050,840.00 545,160.00 2,596,000.00 2,596,000.00
- - - -
G. PEKERJAAN TAMBAH 35,550,000 235,212,500 - - - -
509,251,736
5 Washing Bays
BAYA
PAKET PEKERJAAN WORKSHOP FACILITY 1.0384
PAKET PEKERJAAN POWER HOUSE & COMPRESSOR ROOM
PT PAMAPERSADA NUSANTARA-BAYA-KALIMANTAN TIMUR
Total #N/A
VOL UNIT PRICE TOTAL PRICE TOTAL PRICE Koef Sirtu Koef Pasir Urug Readymix Sitemix
Lantai kerja Readymix
Koef Batu kali Koef Split Koef Pasir Beton Koef Semen Koef Besi Koef M.5 Koef Bekisting MECAMICAL ELECTRICAL
NO JENIS PEKERJAAN SPESIFIKASI SATUAN
PAMA KONT MATRIAL UPAH MATRIAL (RP) UPAH (RP) m3 m3 m3 m3 m3 m3 m3 m3 kg Kg lbr m2 (Rp) (Rp)
- - 33.07 9.00 5.40 36.72 14.25 10.80 6,292.90 4,329.34 11.00 198.13
Total #N/A
PEKERJAAN BAJA -
1 WF 200.100.5,5.8 kg 676.27 10,820,266.67 3,381,333.33 676.267 14,201,600.00
2 Plat 10 mm kg 12.57 201,093.60 62,841.75 12.5684 263,935.35
3 Plat 6 mm kg 7.54 120,656.16 37,705.05 7.54101 158,361.21
9 Trainning PPD
PROYEK : PEMBANGUNAN WORKSHOP FACILITY 1.038
PAKET PEKERJAAN : WASTE OIL STORAGE (WOSA)
LOKASI : JEMBAYAN, KALIMANTAN TIMUR
REKAPITULASI AKHIR
I. BANGUNAN WOSA
1. PEKERJAAN TANAH ls 1.00 1.00 42,176,384.00 42,176,384.00
2. PEKERJAAN STRUKTUR ls 1.00 1.00 #N/A #N/A
3. PEKERJAAN STRUKTUR ATAP + PENUTUP ATAP ls 1.00 1.00 100,914,092.48 100,914,092.48
4. PEKERJAAN DINDING DAN PLAFOND ls 1.00 1.00 110,746,294.56 110,746,294.56
5. PEKERJAAN PASANGAN PINTU / JENDELA ls 1.00 1.00 8,099,520.00 8,099,520.00
-
II. PEKERJAAN SARANA LUAR ls 1.00 1.00 135,978,885.60 135,978,885.60
-
III. PEKERJAAN MEKANIKAL DAN ELEKTRIKAL ls 1.00 1.00 54,216,291.80 54,216,291.80
IV PEKERJAAN TAMBAH ls 1.00 1.00 404,541,738.21 404,541,738.21
Sub Total #N/A -
Total #N/A -
REKAPITULASI AKHIR
VOL VOL UNIT PRICE TOTAL PRICE VOL UNIT PRICE Koef Sirtu Koef Pasir Urug Readymix Sitemix
Lantai kerja Readymix
Koef Batu kali Koef Split Koef Pasir Beton Koef Semen Koef Besi Koef M.5 Koef M.6 Koef Bekisting MECAMICAL ELECTRICAL
NO JENIS PEKERJAAN SPESIFIKASI UNIT
PAMA KONT (RP) (RP) GGL (RP) m3 m3 m3 m3 m3 m3 m3 m3 kg Kg Lbr Lbr m2 (Rp) (Rp)
I. BANGUNAN WOSA
#N/A #N/A - 41.76 62.03 6.80 14.00 - 20.59 15.60 5,717.32 4,467.50 216.00 18.00 57.52
114.34643
10 WOSA
Main Ws Washing PH & Comp Training Wosa
Material Sat Harga Satuan
Volume Jumlah Volume Jumlah Volume Jumlah Volume Jumlah Volume Jumlah
Sirtu m3 220,000 633.60 139,392,000 107.51 23,652,552 - - - - - -
-
Pasir Urug m3 220,000 - - - - - - - - 41.76 9,187,200
-
Readymix k 250 m3 1,425,000 717.32 1,022,176,654 136.72 194,818,875 33.07 47,121,045 - 62.03 88,390,969
-
Batu Kali m3 528,571 - - 36.72 19,409,143 - - -
-
Split m3 528,571 7.45 3,938,065 - - 14.25 7,534,268 - 20.59 10,885,180
-
Pasir Beton m3 220,000 5.64 1,241,732 - - 10.80 2,375,670 - 15.60 3,432,264
-
Semen (@50kg) Zak 55,000 50.00 2,750,000 - - 126.00 6,930,000 - 115.00 6,325,000
-
Besi beton Kg 10,350 ### 672,738,846 ### 136,097,581 4,329.34 44,808,624 - 4,467.50 46,238,604
-
M.5 lbr 285,000 - - 11.00 3,135,000 - 216.00 61,560,000 24.14 11750 283,645
- -
M.6 lbr 410,000 10.00 4,100,000 - - - 18.00 7,380,000 34.76 408,430
- -
M.7 lbr 560,000 300.00 168,000,000 - - - - 47.31 555,893
1 Besi Beton
1 Besi beton merk SII 1.03 kg 0.00
2 Container dr jkt 1.00 kg 0.00
3 Alat bantu & kawat beton 1.00 ls 0.00
4 upah tukang 1.00 ls 0.00
10 Mobilisasi pekerja
1 tukang batu 60.00 tkg 0.00
2 mandor 4.00 pp 0.00
3 supervisor 4.00 pp 0.00
mobil grandmaz 6.00 bln 0.00
hotel 9.00 x 0.00
Mobilisasi mesin pancang 1.00 ls 0.00
4 driver 6.00 bl 0.00
10 safety & k3
1 sepaty 60.00 pc 0.00
2 kaos kerja 120.00 pc 0.00
3 body hardness 10.00 pc 0.00
4 rompi & helm 60.00 pc 0.00
10 management proyek
1 supervisor 6.00 m2 0.00
2 mandor 6.00 m2 0.00
3 engineer 5.00 bl 0.00
4 driver 6.00 m2 0.00
13 Pasangan keramik
1 Keramik Mulia 1.05 m2 0.00
2 Container dr jkt 1.00 ls 0.00
3 Adukan mortar 1.00 m2 0.00
4 mesin pot keramik, grouting 1.00 ls 0.00
5 Upah tukang 1.00 ls 0.00
17 Pintu PI
1 Kusen Bangkirai 6.00 m'
2 Daun pintu 2.00 Daun
3 Kaca clear t=5mm 0.54 m2
4 Engsel pintu 3.00 pasang
5 Handle pintu panjang 2.00 pasang
6 Door closer 1.00 set
7 Grendel tanam 1.00 set
8 Pengecatan 6.72 m2
9 Upah pasang 1.00 ls
10 ongkos kirim 1.00 ls
18 Pintu P2
1 Kusen meranti 5.10 m'
2 Daun pintu 1.00 daun
3 Kaca clear t=5mm 0.60 m2
4 Engsel pintu 1.00 pasang
5 Handle pintu 1.00 pasang
6 Pengecatan 4.09 m2
7 Upah pasang 1.00 ls
8 Ongkos kirim 1.00 ls
19 Pintu P3
1 Kusen Alumunium 5.30 m'
2 Daun pintu bangkirai 1.00 daun
3 Engsel pintu 1.00 pasang
4 Handle pintu 1.00 pasang
5 Pengecatan 4.30 m2
6 Upah pasang 1.00 ls
7 Ongkos kirim 1.00 ls
20 Jendela J1
1 Kusen alumunium 12.20 m'
2 daun jendela 2.00 bh
3 Kaca clear t=5mm 3.15 m2
4 Engsel jendela 2.00 pasang
5 Grendel tanam 2.00 set
6 Upah pasang 1.00 ls
7 Ongkos kirim 1.00 ls
21 Jendela J2
1 Kusen alumunium 4.80 m'
2 daun jendela 1.00 bh
3 Kaca clear t=5mm 1.40 m2
4 Engsel jendela 1.00 pasang
5 Grendel tanam 1.00 set
6 Upah pasang 1.00 ls
7 Ongkos kirim 1.00 ls
21 Jendela J1 DAPUR
1 Kusen alumunium 7.20 m'
2 daun jendela 1.00 bh
3 Kaca clear t=5mm 1.62 m2
4 Engsel jendela 2.00 pasang
5 Grendel tanam 2.00 set
6 Upah pasang 1.00 ls
7 Ongkos kirim 1.00 ls
25 Meja beton
1 pekerjaan meja beton M8 1 lapis 0.17 m3
2 Bekisting 1.00 ls
3 Pasang keramik 1.72 m2
4 Plaster aci bawah 1.72 m2
5 Upah tukang 1.00 ls
26 Urinal
1 washbrook top spood 1.00 bh
2 Upah pasang 1.00 ls
27 saluran drainage
28 Tangga darurat
1 UNP 150 x 75 x 6.5 x 6m 560.00 kg
2 Plat Bordes 4.00 lbr
3 Siku 50 x 50 48.00 btg
4 Post railing 40 x 40 2.00 btg
5 20 x 40 8.00 btg
6 Hand railing Ø 2.5'' 2.00 btg
7 Upah tukang 1.00 ls
8 epoxy primer 1.00 ls
9 Cat hitam 1.00 ls
29 Biotek
1 BT 8 1.00 BH
2 Ongkos kirim 1.00 bh
3 Gali 4.80 m3
4 Upah tukang 1.00 ls
30 PANEL LT 1
1 PANEL LT 1 1.00 unit
2 Ongkos kirim 1.00 bh
3 Ongkos pasang 1.00 bh
30 PANEL LT 2
1 PANEL LT 2 1.00 unit
2 Ongkos kirim 1.00 bh
3 Ongkos pasang 1.00 bh
31 PINTU PVC
1 Panel PVC 6.00 lbr
Rel atas bawah 1.00 set
Handle 2.00 set
2 Ongkos kirim 1.00 bh
3 Ongkos pasang 1.00 bh
3 pph
sloof
as 1 33.5 0.2 0.35 2.345
as2 28 0.2 0.35 1.96
as 2' 24 0.2 0.35 1.68
as 3 10.5 0.2 0.35 0.735
as 3' 24 0.2 0.35 1.68
as 4 9 0.2 0.35 0.63
as 5 10.5 0.2 0.35 0.735
as 6 9 0.2 0.35 0.63
as 7 10.5 0.2 0.35 0.735
0
I 10.5 0.2 0.35 0.735
H 9 0.2 0.35 0.63
G 9 0.2 0.35 0.63
F 10.5 0.2 0.35 0.735
E 9 0.2 0.35 0.63
D 9 0.2 0.35 0.63
C 24.5 0.2 0.35 1.715
B 4.5 0.2 0.35 0.315
B' 16 0.2 0.35 1.12
B" 18.5 0.2 0.35 1.295
A 24.5 0.2 0.35 1.715
21.28
16,252,675.40
. : PAMA BAYA
Lokasi : KALTIM
WORKSHOP 2
--------- - - - - - - -
Jumlah : Rp. 1,442,021 1,104,541.20
Dibulatkan : Rp. 1,442,000
2 UNTUK : LANTAI 30 CM
tulangan D13-150
2 UNTUK : LANTAI 30 CM
tulangan M.10 Double
I. PEKERJAAN BETON D6
K 175 D13
Bahan: 1 m3 Ready mix K250 @ Rp. 1,520,321 Rp. 1,520,321 Ø 12
0 m3 Pasir beton @ Rp. 285,560 Rp. 0
0 kg Semen @ Rp. 1,194 Rp. 0
0 ltr air @ Rp. 57 Rp. 0
-------- --------------------- Rp. 1,520,321
II PEKERJAAN BESI
2 UNTUK : RABAT B0
tulangan
I. PEKERJAAN BETON D6
D13
Bahan: 0.99 m3 Split @ Rp. 545,160 Rp. 539,708 Ø 12
0.75 m3 Pasir beton @ Rp. 285,560 Rp. 214,170
326 kg Semen @ Rp. 1,194 Rp. 389,296
650 ltr air @ Rp. 57 Rp. 37,123
-------- --------------------- Rp. 1,180,297
II PEKERJAAN BESI
II PEKERJAAN BESI
II PEKERJAAN BESI
II PEKERJAAN BESI
2 UNTUK : LANTAI 20 CM
tulangan Ø 10 - 120 Double
2 UNTUK : DINDING 20 CM
tulangan D13-200 dan Ø12-200 Double
II PEKERJAAN BESI
II PEKERJAAN BESI
WS FABRIKASI
2 UNTUK : PEDESTAL
tulangan
II PEKERJAAN BESI
2 UNTUK : RABAT
tulangan
I. PEKERJAAN BETON D6
D13
Bahan: 0.99 m3 Split @ Rp. 545,160 Rp. 539,708 Ø 12
0.75 m3 Pasir beton @ Rp. 285,560 Rp. 214,170
240 kg Semen @ Rp. 1,194 Rp. 286,598
650 ltr air @ Rp. 57 Rp. 37,123
-------- --------------------- Rp. 1,077,600
II PEKERJAAN BESI
2 UNTUK : lantai 15 cm
tulangan
I. PEKERJAAN BETON Ø8
Ø8
Bahan: 0.99 m3 Split @ Rp. 545,160 Rp. 539,708 Ø 12
0.75 m3 Pasir beton @ Rp. 285,560 Rp. 214,170
350 kg Semen @ Rp. 1,194 Rp. 417,956
650 ltr air @ Rp. 57 Rp. 37,123
-------- --------------------- Rp. 1,208,957
2 UNTUK : dinding 15 cm
tulangan
I. PEKERJAAN BETON Ø8
Ø8
Bahan: 0.99 m3 Split @ Rp. 545,160 Rp. 539,708 Ø 12
0.75 m3 Pasir beton @ Rp. 285,560 Rp. 214,170
350 kg Semen @ Rp. 2,600 Rp. 910,000
650 ltr air @ Rp. 57 Rp. 37,123
-------- --------------------- Rp. 1,701,001
WASHING BAYS
2 UNTUK : LANTAI, T= 30 CM
tulangan
2 UNTUK : SLAB 25 CM
tulangan
WOSA
I. PEKERJAAN BETON Ø 12
Ø8
Bahan: 0.99 m3 Split @ Rp. 545,160 Rp. 539,708 Ø 12
0.75 m3 Pasir beton @ Rp. 285,560 Rp. 214,170
390 kg Semen @ Rp. 1,194 Rp. 465,722
650 ltr air @ Rp. 57 Rp. 37,123
-------- --------------------- Rp. 1,256,724
II PEKERJAAN BESI
TYRESHOP
POWER HOUSE
I. PEKERJAAN BETON Ø 10
Ø 10
Bahan: 0.99 m3 Split @ Rp. 545,160 Rp. 539,708 Ø
0.75 m3 Pasir beton @ Rp. 71,500 Rp. 53,625
390 kg Semen @ Rp. #N/A Rp. #N/A
650 ltr air @ Rp. #N/A Rp. #N/A
I. PEKERJAAN BETON Ø 16
Ø 13
Bahan: 0.99 m3 Split @ Rp. 545,160 Rp. 539,708 Ø 10
0.75 m3 Pasir beton @ Rp. 285,560 Rp. 214,170
390 kg Semen @ Rp. #N/A Rp. #N/A
650 ltr air @ Rp. 3,380 Rp. 2,197,000
#N/A -------- --------------------- Rp. #N/A
#N/A
Upah : 1 m3 Upah cor site mix @ Rp. 285,560 Rp. 285,560
#N/A -------- --------------------- Rp. 285,560
Equipment & Tools
1.000 lsTools @ Rp. #N/A #N/A
-------- --------------------- Rp. #N/A
5 UNTUK : KP1
tulangan
I. PEKERJAAN BETON Ø 16
Ø 13
Bahan: 0.99 m3 Split @ Rp. 545,160 Rp. 539,708 Ø 10
0.75 m3 Pasir beton @ Rp. 285,560 Rp. 214,170
390 kg Semen @ Rp. 2,600 Rp. 1,014,000
650 ltr air @ Rp. 3,380 Rp. 2,197,000
#N/A -------- --------------------- Rp. 3,964,878
#N/A
Upah : 1 m3 Upah cor site mix @ Rp. 285,560 Rp. 285,560
#N/A -------- --------------------- Rp. 285,560
Equipment & Tools
1.000 lsTools @ Rp. #N/A #N/A
-------- --------------------- Rp. #N/A
WORKSHOP 3
5 UNTUK : TB 1 35X40
tulangan
I. PEKERJAAN BETON Ø 16
Ø 13
Bahan: 0.99 m3 Split @ Rp. 545,160 Rp. 539,708 Ø 10
0.75 m3 Pasir beton @ Rp. 285,560 Rp. 214,170
390 kg Semen @ Rp. #N/A Rp. #N/A
650 ltr air @ Rp. #N/A Rp. #N/A
#N/A -------- --------------------- Rp. #N/A
#N/A
Upah : 1 m3 Upah cor site mix @ Rp. 285,560 Rp. 285,560
#N/A -------- --------------------- Rp. 285,560
Equipment & Tools
1.000 lsTools @ Rp. #N/A #N/A
-------- --------------------- Rp. #N/A
I. PEKERJAAN BETON Ø 16
Ø 13
Bahan: 0.99 m3 Split @ Rp. 545,160 Rp. 539,708 Ø 10
0.75 m3 Pasir beton @ Rp. 285,560 Rp. 214,170
390 kg Semen @ Rp. #N/A Rp. #N/A
650 ltr air @ Rp. #N/A Rp. #N/A
#N/A -------- --------------------- Rp. #N/A
#N/A
Upah : 1 m3 Upah cor site mix @ Rp. 285,560 Rp. 285,560
#N/A -------- --------------------- Rp. 285,560
Equipment & Tools
1.000 lsTools @ Rp. #N/A #N/A
-------- --------------------- Rp. #N/A
I. PEKERJAAN BETON Ø 16
Ø 13
Bahan: 0.99 m3 Split @ Rp. 545,160 Rp. 539,708 Ø 10
0.75 m3 Pasir beton @ Rp. 285,560 Rp. 214,170
390 kg Semen @ Rp. #N/A Rp. #N/A
650 ltr air @ Rp. #N/A Rp. #N/A
#N/A -------- --------------------- Rp. #N/A
#N/A
Upah : 1 m3 Upah cor site mix @ Rp. 285,560 Rp. 285,560
#N/A -------- --------------------- Rp. 285,560
Equipment & Tools
1.000 lsTools @ Rp. #N/A #N/A
-------- --------------------- Rp. #N/A
514285.7142857 1.61
214285.7142857
54,667
9500
750000
1750
410000
57,112.00
57,112.00
besi
1,2*1,2*,3 0 m3
,3+1,2+,3 2 18 12.50 33.75
,1+1,2+,1 1 18 12.50 26.25
1,4*4 6 1 -
60.00
- waste 1.80
61.80
143.06 kg/m3
337,480.00
9,500.00 9,500.00
15,000.00 225.00
9,725.00
135,000.00 47,250.00
15,000.00 1,500.00
- -
48,750.00
55,035.20
3,167.12
1,148,229
0.20
besi
0,35*3*4,5 4.725 m3
0,35+3+0,35+3 6.7 31 10.70 185.20 30
0,35+4,5+0,35+4, 9.7 21 10.70 181.63 20
3+4,5+3+4,5 15 4 10.70 53.50 - -
420.33 - -
- waste 14.71 - -
435.04 -
92.07 kg/m3
- -
- -
-
- -
- -
- -
-
55,035.20
3,167.12
besi
0,8*0,8*0,3 0.192 m3
0.8 0.8 12 10.70 8.56 30
0,3+0,8+0,3 1.4 12 12.50 17.50 20
0 0 4 10.70 - - -
26.06 - -
- waste 0.91 - -
26.97 -
140.48 kg/m3
- -
- -
-
- -
654,192.00 65,419.20
- -
65,419.20
55,035.20
3,167.12
860,589
0.19
besi
0,25*0,35*2,2 0.1925 m3 41.616
0,2+2,2 2.4 6 19.00 22.80
0,35*2+0,25*2 1.2 9 4.74 4.27
0 - 18 - -
27.07
- waste 0.95
28.01
145.52 kg/m3
besi
0,51*1,1*1 0.561 m3 41.616
,1+,25+0,7+1 2.05 20.00 26.71 91.25
,1+,25+0,7+1 2.05 2.00 7.40 2.53
0,51+1,1+0,51+1, 3.22 9.00 7.40 17.87
111.64
- waste 3.91
115.55
205.97 kg/m3
besi
0,25*0,35 0.09 m3
1.03 1.03 4 18.94 6.50
1.03 1.03 - 7.40 -
0,2*2+0,35*2 1.60 7 4.73 4.42
10.92
- waste 0.38
11.30
129.18 kg/m3
besi
0,15*0,2 0.03 m3
1.03 1.03 4 10.70 3.67
0 - 4 7.40 -
0 0.70 5 4.74 1.38 5
5.06
- waste 0.18
5.23
174.44 kg/m3
besi
0.3 0.30 m3
1.05 1 14 12.50 14.81
1.05 1 14 12.50 14.81
0 - 1 10.70 -
29.62
- waste 1.04
30.66
102.18 kg/m3
besi
0.3 0 m3
1.05 1 14 12.50 14.81
1.05 1 14 12.50 14.81
0 - 1 10.70 -
29.62
- waste 1.04
30.66
102.18 kg/m3
###
besi
,35*1,8*1 0 m3
,35+1,8+,35 1 10 2.66 2.22
1.03 1 - 2.66
0 - - 10.70
2.22
- waste 0.07
2.28
22.83 kg/m3
###
besi
,35*1,8*1 0 m3
,35+1,8+,35 1 10 2.66 2.22
1.03 1 - 2.66
0 - - 10.70
2.22
- waste 0.07
2.28
22.83 kg/m3
besi
0.2 0.20 m3
1.035 1.04 10 12.50 10.78
1.035 1.04 10 10.70 9.23
0 - 1 10.70 -
20.01
- waste 1.02
21.03
105.17 kg/m3
besi
,35*,225*1,8 0 m3
,1+,25+1,8 2 8 19.00 27.23
,1+1,2+,1 1 8 - -
,35*2+,23*2 1 16 7.40 11.45
38.68
- waste 1.35
40.03
101.09 kg/m3
besi
,35*1,8*1 0 m3
1.03 1 13 4.74 5.42
1.03 1 13 4.74 5.42
0 - 1 -
10.85
- waste 0.54
11.39
75.95 kg/m3
besi
0.25 0 m3
1.03 1 13 12.50 14.31
1.05 1 13 12.50 14.31
0 - 1 -
28.61
- waste 0.86
29.47
117.88 kg/m3
besi
,25*,45*1,25 0 m3
,05+,3+1,25+,05 2 10 12.50 17.19
,25*2+,45*2 1 7 4.74 3.71
5 1 - -
20.89
- waste 0.63
21.52
153.03 kg/m3
besi
0.3 0 m3
1.03 1 27 12.50 29.05
1 16 - -
5 1 - -
29.05
- waste 0.87
29.93
99.75 kg/m3
besi
0.4 0 m3
1.05 1 13 10.70 12.55
1.05 1 13 10.70 12.55
5 1 - -
25.09
- waste 2.51
27.60
69.00 kg/m3
besi
0.1 0 m3
1.03 1 13 7.40 8.51
1.03 1 16 - -
5 1 - -
8.51
- waste 0.26
8.77
besi
0.15 0 m3
1.03 1 11 12.50 12.25
,275*2+,35*2 1 16 - -
5 1 - -
12.25
- waste 0.37
12.62
84.14 kg/m3
besi
0.2 0 m3
1.03 1 11 12.50 12.25
besi
0.1 0 m3
1.03 1 10 7.40 6.35
,275*2+,35*2 1 16 - -
5 1 - -
6.35
- waste 0.32
6.67
66.69 kg/m3
besi
,55*,55*1,5 0 m3
,05+,3+1,5+,05 2 14 19.00 42.12
1.03 1 - 19.00 -
,55*4 2 11 7.40 14.92
57.04
- waste 2.85
59.89
131.99 kg/m3
besi
,35*,4 0 m3
1.03 1 8 19.00 13.05
1.03 1 - 19.00 -
,3*2+,5*2 1 7 7.40 1.6
14.65
- waste 0.73
15.38
109.85 kg/m3
besi
,3*,4*1,5 0 m3
,05+,3+1,5+,05 2 8 19.00 24.07
1.03 1 - 19.00 -
,3*2+,4*2 1 11 7.40 9.50
33.56
- waste 1.68
35.24
195.79 kg/m3
5,133,334
2,981,510
2,914,793
3,047,711
Page 90
Ring balk m' 1.7 67,500 114,750
friction stay,handle cs set 0 207,680 -
1,291,569
1,657,706
444,439
OFFICE FABRIKASI
5,265,216
3,789,648
Page 91
Ring balk m' 1 67,500 67,500
tali air m1 10.28 12,980 133,434
3,003,472
2,832,240
1,457,530
3,233,324
1,876,912
535,611
Page 92
J1 Kusen ALUMINIUM 4" m3 6.8 114,224 776,723
kaca polos 5mm m2 1.6 129,800 207,680
jendela kaca bh 1 650,000 650,000
friction stay,handle cs set 1 310,000 310,000
tali air m1 6.8 12,980 88,264
2,032,667
7,305,400
1,672,602
1,714,269
587,475
1,983,375
Page 93
tali air m1 5.2 12,980 67,496
1,961,461
Page 94
1.0384
harga sat.
110,000
1,320,000
283,500
450,000
350,000
600,000
125,000
12,500
110,000
1,320,000
283,500
450,000
350,000
125,000
12,500
110,000
1,320,000
283,500
450,000
350,000
125,000
12,500
110,000
125,000
650,000
12,500
200,000
110,000
130,000
650,000
12,500
Page 95
200,000
110,000
130,000
650,000
12,500
200,000
-
130,000
650,000
12,500
harga sat.
110,000
1,320,000
283,500
350,000
350,000
600,000
125,000
12,500
110,000
1,320,000
283,500
350,000
350,000
125,000
12,500
110,000
1,320,000
283,500
350,000
350,000
600,000
Page 96
12,500
110,000
1,320,000
283,500
350,000
350,000
125,000
12,500
110,000
125,000
650,000
12,500
200,000
110,000
130,000
650,000
12,500
200,000
110,000
130,000
650,000
12,500
200,000
110,000
130,000
650,000
12,500
200,000
Page 97
110,000
125,000
650,000
310,000
12,500
110,000
125,000
650,000
310,000
12,500
110,000
125,000
650,000
310,000
12,500
110,000
125,000
650,000
310,000
12,500
110,000
125,000
650,000
310,000
12,500
110,000
1,500,000
650,000
310,000
12,500
110,000
950,000
350,000
-
-
Page 98
12,500
Page 99
PEKERJAAN PERSIAPAN
Jumlah 336 m2
Dibulatkan
B TRANSFORT KE PROYEK
a. Pekerja
- dari kampung ke Jakarta 130,000
- Uang Makan 50,000
-Tiket pesawat dari Jakarta ke Balikpapan 600,000
-Travel dari Balikpapan ke Proyrek 450,000
Jumlah 1,230,000
Ongkos PP 2,460,000
b. Staff
- Bus Damri ke AirPort 35,000
-Tiket pesawat dari Jakarta ke Balikpapan 600,000
-Travel dari Balikpapan ke Proyrek 450,000
- Uang Makan 50,000
1,135,000
Ongkos PP 2,270,000
Jumlah
Jumlah
5 SITE MANAGEMENT
A Gaji Staff
- Site Managet 1 org 8,000,000
- Supervisor 3 org 6,000,000
-Safety 1 org 5,000,000
- Admin Gudang 1 org 4,700,000
Jumlah 23,700,000
Jumlah
HIRA / JSA
Mobil LV + sopir 1.5 bln 22,000,000
Solar 1.5 bln 7,650,000
SM 1.5 bln 8,000,000
Saffety Officer 1.5 bln 5,000,000
Kontrakan 1.5 bln 4,000,000
Jumlah
11,205,000
2,168,100
2,250,000
-
-
-
-
15,623,100
15,623,100
17,400,000
109,200,000
126,600,000
126,600,000
6,545,000
27,450,000
1,400,000
6,545,000
6,545,000
3,750,000
1,647,000
549,000
102,850,000
1,200,000
158,481,000
450,180,000
-
40,000,000
490,180,000
142,200,000
11,350,000
2,460,000
13,810,000
27,620,000
169,820,000
21,000,000
115,500,000
53,550,000
159,000,000
46,800,000
28,000,000
25,000,000
32,100,000
480,950,000
650,770,000
16,500,000
5,737,500
6,000,000
3,750,000
3,000,000
34,987,500
PEKERJAAN PERSIAPAN
PENGUKURAN
1 DAN BOUWPLANK
a. WORKSHOP 6 BAYS 15TON 2040 m2 3,000 = 6,120,000
c. Wasing Bays 214.75 m2 3,000 = 644,250
POWER HOUSE & COMPRESSOR ROO 126 3,000 378,000
R.TRAINING PPD 150 = -
PHouase 162 - = -
Wosa 216 - = -
d. m2 3,000 = -
Jumlah 72 m2 48,600,000
Dibulatkan 48,600,000
PENGAMANAN
3 K3 & APD
A JUMLAH PEKERJA
Sipil 25 25
a. WORKSHOP 6 BAYS 15TON 34 org
b. Wasing Bays 25 org
c. POWER HOUSE & COMPRESSOR ROO 10 org
R.TRAINING PPD org
Wosa 15 org
Masjid 0 org
Gudang Oksigen 0 org
Pegecoran yard 0 org
Pos security 0 org
R Mekaink 0 org
d. org
e. Aluminium dan Kaca 2 org
f. Plafond 2 org
g. Mekanikal & Elektrikal 6 org
h. Baja 0 org 9
i. Atap 6 org
B TRANSFORT KE PROYEK
a. Pekerja
- dari kampung ke Jakarta 150,000
- Uang Makan 50,000
-Tiket pesawat dari Jakarta ke Balikpapan 730,000
-Travel dari Balikpapan ke Proyrek 125,000
Jumlah 1,055,000
Ongkos PP 2,110,000
940,000
Ongkos PP 1,880,000
Jumlah 36,405,000
MOBILISASI4DAN DEMOBILISASI
a. Tenaga kerja 100 org 2,110,000 211,000,000
b. Libur lebaran 0 org 2,110,000 -
SITE MANAGEMENT
5
A Gaji Staff
- Site Manager 1 org 8,000,000 8,000,000
- Supervisor 1 org 6,000,000 6,000,000
-Safety 1 org 5,000,000 5,000,000
- Admin Gudang 1 org 4,700,000 4,700,000
4 Jumlah - 23,700,000
9,630,000
Cuti Staff setiap 3 bln 2 PP 2,110,000 4,220,000
Jumlah 195,980,000
HIRA / JSA
Mobil LV 1.0 bln 17,500,000 17,500,000
Solar 1.0 bln 4,500,000 4,500,000
SM 0.0 bln 8,000,000 -
Saffety Officer 1.0 bln 5,000,000 5,000,000
Kontrakan 1.0 bln 4,000,000 4,000,000
sopir 1.0 bln 4,000,000 4,000,000
138,833
1 PEKERJAAN PERSIAPAN #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
#N/A
2 WORKSHOP 6 BAYS 15TON
PEKERJAAN STRUKTUR WORKSHOP #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
#N/A
PEKERJAAN ARSITEKTUR WORKSHOP #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
#N/A
PEKERJAAN SARANA LUAR #N/A #N/A #N/A #N/A #N/A #N/A
#N/A
PEKERJAAN MEP #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
#N/A
#N/A
3 WASHING BAYS #N/A
1 PEKERJAAN TANAH #N/A #N/A #N/A #N/A #N/A
2 PEKERJAAN STRUKTUR DASAR #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
4 PEKERJAAN BAK LUMPUR TERBUKA #N/A #N/A #N/A #N/A #N/A #N/A
#N/A
5 PEKERJAAN INSTALASI AIR BERSIH #N/A #N/A #N/A
#N/A
4 POWER HOUSE & COMPRESSOR ROOM
I. BANGUNAN POWER HOUSE #N/A
1. PEKERJAAN TANAH #N/A #N/A #N/A #N/A
#N/A
II. BANGUNAN COMPRESSOR #N/A
1. PEKERJAAN TANAH #N/A #N/A
#N/A
III. PEKERJAAN SARANA LUAR #N/A #N/A #N/A
#N/A
5 R.TRAINING PPD #N/A
1 PEKERJAAN STRUKTUR #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
2 PEKERJAAN ARSITEKTUR #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
4 PEKERJAAN MEKANIKAL & ELEKTRIKAL #N/A #N/A #N/A #N/A #N/A #N/A
M Soewondo
Kepala Divisi Sipil
#N/A #N/A
- #N/A
- -
#N/A #N/A
- #N/A
#N/A #N/A
- #N/A
#N/A #N/A
- #N/A
#N/A #N/A
- #N/A
- #N/A
- #N/A
#N/A #N/A
#N/A #N/A
- #N/A
#N/A #N/A
- #N/A
#N/A #N/A
- #N/A
- -
- #N/A
#N/A #N/A
#N/A #N/A
#N/A #N/A
#N/A #N/A
#N/A #N/A
- #N/A
- #N/A
#N/A #N/A
#N/A #N/A
#N/A #N/A
#N/A #N/A
#N/A #N/A
- #N/A
#N/A #N/A
#N/A #N/A
#N/A #N/A
- #N/A
- #N/A
#N/A #N/A
#N/A #N/A
#N/A #N/A
#N/A #N/A
- -
- -
- -
DAFTAR HARGA
PROYEK PEMBANGUNAN WORKSHOP FACILITY
PAKET PEMBANGUNAN WORKSHOP 6 BAYS 15TON, WASHING BAY,
POWER HOUSE & COMPRESSOR ROOM, R.TRAINING PPD
PT PAMAPERSADA NUSANTARA
BAYA - KALIMANTAN TIMUR
Ir. M. Soewondo
Kepala Divisi