22 – Agust -19
DAFTAR ISI
3. ANALISA PEKERJAAN………………………………………………………………………………………………………………
1. REKAPITULASI ANGGARAN BIAYA
SKD-01
TOTAL 9,722,713,490.34
PPN 10%
GRAND TOTAL 9,722,713,490.34
PEMBULATAN 9,722,713,000.00
TERBILANG : SEMBILAN MILYAR TUJUH RATUS DUA PULUH DUA JUTA TUJUH RATUS
TIGA BELAS RIBU RUPIAH
2. RINCIAN RENCANA ANGGARAN BIAYA
RINCIAN RENCANA ANGGARAN BIAYA (RAB)
KEGIATAN : PEMBANGUNAN GEDUNG PRIMARY SCHOOL
TAHUN : 2019
LOKASI : Jl.Cipinang Bali, Kalimalang Jakarta Timur
A. PEKERJAAN GALIAN
B. PEKERJAAN PONDASI
a. TIANG BOR
- Tiang Bor Ø 500 x L=12M 64.00 ttk Rp 8,288,322 Rp 530,452,638 Rp 530,452,638
b. PONDASI
Pondasi telapak Type P1 0.60 Rp 27,919,233
- Bekisting batako 13.50 m2 149,187.50 Rp 2,014,031
- Besi Beton ( tul : D13 & D16) 1,417.50 kg 13,970.00 Rp 19,802,475
- Beton Ready Mix K300 8.10 m3 753,423.00 Rp 6,102,726
b. TB 2 = 350/700 Rp 91,910,542
- Bekisting batako 112.00 m2 94,336.00 Rp 10,565,632
- Besi Beton 3,430.00 kg 14,960.00 Rp 51,312,800
- Beton Ready Mix K300 19.60 m3 1,532,250.50 Rp 30,032,110
c. TB 3= 400/800 Rp 119,800,439
- Bekisting batako 129.60 m2 94,336.00 Rp 12,225,946
- Besi Beton 4,536.00 kg 14,960.00 Rp 67,858,560
- Beton Ready Mix K300 25.92 m3 1,532,250.50 Rp 39,715,933
D. PEKERJAAN LANTAI 1
a. B1 =300/600 Rp 126,827,578
- Bekisting 152.25 m2 334,991.80 Rp 51,002,502
- Besi Beton 3,197.25 kg 14,960.00 Rp 47,830,860
- Beton Ready Mix K300 18.27 m3 1,532,250.50 Rp 27,994,217
b. TB 2 = 350/700 Rp 128,243,762
- Bekisting 140.00 m2 334,991.80 Rp 46,898,852
- Besi Beton 3,430.00 kg 14,960.00 Rp 51,312,800
- Beton Ready Mix K300 19.60 m3 1,532,250.50 Rp 30,032,110
c. TB 3= 400/800 Rp 161,843,165
- Bekisting 162.00 m2 334,991.80 Rp 54,268,672
- Besi Beton 4,536.00 kg 14,960.00 Rp 67,858,560
- Beton Ready Mix K300 25.92 m3 1,532,250.50 Rp 39,715,933
E. PEKERJAAN LANTAI 2
a. B1 =300/600 Rp 124,347,256
- Bekisting 149.27 m2 334,991.80 Rp 50,005,063
- Besi Beton 3,134.72 kg 14,960.00 Rp 46,895,449
- Beton Ready Mix K300 17.91 m3 1,532,250.50 Rp 27,446,744
b. B 2 = 350/700 Rp 107,356,059
- Bekisting 117.20 m2 334,991.80 Rp 39,260,201
- Besi Beton 2,871.34 kg 14,960.00 Rp 42,955,228
- Beton Ready Mix K300 16.41 m3 1,532,250.50 Rp 25,140,630
c. B 3= 400/800 Rp 77,524,874
- Bekisting 77.60 m2 334,991.80 Rp 25,995,364
- Besi Beton 2,172.80 kg 14,960.00 Rp 32,505,088
- Beton Ready Mix K300 12.42 m3 1,532,250.50 Rp 19,024,422
F. PEKERJAAN LANTAI 3
a B1 =300/600 Rp 124,347,256
- Bekisting 149.27 m2 334,991.80 Rp 50,005,063
- Besi Beton 3,134.72 kg 14,960.00 Rp 46,895,449
- Beton Ready Mix K300 17.91 m3 1,532,250.50 Rp 27,446,744
b. B 2 = 350/700 Rp 107,356,059
- Bekisting 117.20 m2 334,991.80 Rp 39,260,201
- Besi Beton 2,871.34 kg 14,960.00 Rp 42,955,228
- Beton Ready Mix K300 16.41 m3 1,532,250.50 Rp 25,140,630
c. B 3= 400/800 Rp 77,524,874
- Bekisting 77.60 m2 334,991.80 Rp 25,995,364
- Besi Beton 2,172.80 kg 14,960.00 Rp 32,505,088
- Beton Ready Mix K300 12.42 m3 1,532,250.50 Rp 19,024,422
b. RB 2 = 350/700 Rp 179,541,267
- Bekisting 196.00 m2 334,991.80 Rp 65,658,393
- Besi Beton 4,802.00 kg 14,960.00 Rp 71,837,920
- Beton Ready Mix K300 27.44 m3 1,532,250.50 Rp 42,044,954
I. PEKERJAAN TANGGA
A.3.2.1.20. Pemancangan 1 m1 pondasi tiang pancang spun pile Ø400 dengan mesin hidrolik 566,600
Harga Satuan Jumlah
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
1 2 3 4 5 6 7
A Tenaga Kerja
Pekerja L.001 OH 0.0520 90,000.00 4,680
Tukang L.002 OH 0.0104 110,000.00 1,144
Operator alat berat L.018 OH 0.0104 150,000.00 1,560
Pembantu Operator L.019 OH 0.0104 100,000.00 1,040
Mandor L.017 OH 0.0052 150,000.00 780
Jumlah Harga Tenaga Kerja 9,204
B Bahan
Tiang pancang spun pile Ø400 M.01057 m1 1.0300 390,000.00 401,700
Jumlah Harga Bahan 401,700
C Peralatan
Sewa crane M.15006 hari 0.0104 2,806,400.00 29,186.56
Sewa mesin hidrolik M.15020 hari 0.0500 1,500,000.00 75,000
Jumlah Harga Peralatan 104,187
D Jumlah (A+B+C) 515,091
E Overhead + Profit (Contoh 10%) 10% xD 51,509
F Harga Satuan Pekerjaan (D+E) 566,600
A.4.1.1.10. Membuat 1 m3 beton mutu f'c = 26,4 MPa (K300), slump (12+2) cm, w/c = 0,52 1,532,251
Harga Satuan Jumlah
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
1 2 3 4 5 6 7
A Tenaga Kerja
Pekerja L.001 OH 1.6500 90,000.00 148,500
Tukang Batu L.003 OH 0.2750 110,000.00 30,250
Kepala Tukang L.016 OH 0.0280 125,000.00 3,500
Mandor L.017 OH 0.0830 150,000.00 12,450
Jumlah Harga Tenaga Kerja 194,700
B Bahan
Semen Portland M.01044 kg 413.0000 1,375.00 567,875
Pasir beton M.01036 kg 0.6800 276,000.00 187,680
Batu pecah mesin 2/3 M.01031 kg 1 260,000.00 265,200
Air M.17001 liter 215.0000 250.00 53,750
Jumlah Harga Bahan 1,074,505
C Peralatan
sewa mesin beton molen+Tenaga+bahan bakar M.17015 HARI 0.2250 550,000.00 123,750
D Jumlah (A+B+C) 1,392,955
E Overhead + Profit (Contoh 10%) 10% xD 139,296
F Harga Satuan Pekerjaan (D+E) 1,532,251
A.4.4.1.28. Pemasangan 1 m2 dinding batako (10x20x40) cm campuran 1SP : 4PP 94,336.00
Harga Satuan Jumlah
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
1 2 3 4 5 6 7
A Tenaga Kerja
Pekerja L.001 OH 0.3000 90,000.00 27,000.00
Tukang Batu L.003 OH 0.1000 110,000.00 11,000.00
Kepala Tukang L.016 OH 0.0100 125,000.00 1,250.00
Mandor L.017 OH 0.0150 150,000.00 2,250.00
Jumlah Harga Tenaga Kerja 41,500.00
B Bahan
Batako M.01004 bh 11.0000 1,750.00 19,250.00
Semen Portland M.01044 kg 11.5000 1,240.00 14,260.00
Pasir pasang M.01037 m3 0.0430 250,000.00 10,750.00
Jumlah Harga Bahan 44,260.00
C Peralatan
Jumlah Harga Peralatan -
D Jumlah (A+B+C) 85,760.00
E Overhead + Profit (Contoh 10%) 10% xD 8,576.00
F Harga Satuan Pekerjaan (D+E) 94,336.00
C Peralatan
Jumlah Harga Peralatan -
D Jumlah (A+B+C) 282,341
E Overhead + Profit (Contoh 10%) 10% xD 28,234
F Harga Satuan Pekerjaan (D+E) 310,575
b Upah
fabrikasi (disesuakan borongan dilapangan/mandor LS 1.0000 3,900.00 3,900
erection (disesuakan borongan dilapangan/mandor LS 1.0000 1,900.00 1,900
Dibuat oleh:
PT.BHINEKA TEKNIK UNGGUL PERSADA
Ir.M.Shokeh,MT