Anda di halaman 1dari 16

RINCIAN RENCANA ANGGARAN BIAYA (RAB)

PEMBANGUNAN GEDUNG PRIMARY


PROYEK :
SCHOOL

KLIEN : PT. ROEMA ARSI DEVELOPINDO

JL. CIPINANG BALI,KALIMALANG


LOKASI :
JAKARTA TIMUR
DOC. NO. : REV

PEMBANGUNAN GEDUNG PRIMARY SCHOOL 0

22 – Agust -19

DAFTAR ISI

1. REKAPITULASI ANGGARAN BIAYA…………………………………………………………………………………………….

2. RINCIAN RENCANA ANGGARAN BIAYA……………………………………………………………………………………..

3. ANALISA PEKERJAAN………………………………………………………………………………………………………………
1. REKAPITULASI ANGGARAN BIAYA
SKD-01

NO URAIAN PEKERJAAN HARGA TOTAL


RP
I PEKERJAAN PERSIAPAN 214,816,022.48
I PEKERJAAN STRUKTUR
A. PEKERJAAN GALIAN,URUGAN & LANTAI KERJA 64,307,030.57
B. PEKERJAAN PONDASI 936,887,437.03
C. PEKERJAAN LANTAI DASAR 1,218,664,029.72
D. PEKERJAAN LANTAI 1 2,624,759,671.45
E. PEKERJAAN LANTAI 2 1,635,668,740.36
F. PEKERJAAN LANTAI 3 1,635,668,740.36
G. PEKERJAAN LANTAI DAK ATAP 860,353,628.92
H. PEKERJAAN LANTAI DAK TANGGA 41,517,141.31
I. PEKERJAAN TANGGA 239,287,947.48
J. PEKERJAAN RANGKA ATAP 250,783,100.65

TOTAL 9,722,713,490.34
PPN 10%
GRAND TOTAL 9,722,713,490.34
PEMBULATAN 9,722,713,000.00

TERBILANG : SEMBILAN MILYAR TUJUH RATUS DUA PULUH DUA JUTA TUJUH RATUS
TIGA BELAS RIBU RUPIAH
2. RINCIAN RENCANA ANGGARAN BIAYA
RINCIAN RENCANA ANGGARAN BIAYA (RAB)
KEGIATAN : PEMBANGUNAN GEDUNG PRIMARY SCHOOL
TAHUN : 2019
LOKASI : Jl.Cipinang Bali, Kalimalang Jakarta Timur

NO VOLUME SAT HARGA SATUAN JUMLAH HARGA HARGA TOTAL


URAIAN PEKERJAAN
RP RP RP
I. PEKERJAAN PERSIAPAN
a. Papan Nama Proyek 1.00 Ls Rp 1,095,050 Rp 1,095,050 Rp 1,095,050

b. Biaya Keamanan Proyek Rp 100,000,000


– Seragam Keamanan 8.00 Stel Rp 500,000 Rp 4,000,000
– Petugas Keamanan @ 4 Orang 6.00 Bln Rp 16,000,000 Rp 96,000,000

c. Mobilisasi dan Demobilisasi 1.00 Ls Rp 50,000,000 Rp 50,000,000 Rp 50,000,000

d. Biaya Penyediaan Perlengkapan K3 Rp 54,450,000


– Tabung Pemadam @6kg 4.00 Bh Rp 1,750,000 Rp 7,000,000
– Kotak P3K 4.00 Bh Rp 600,000 Rp 2,400,000
– Keselamatan Kerja (Helm, Safety Belt, dll) 50.00 org Rp 225,000 Rp 11,250,000
– Jaring pengaman & hardness 1.00 Ls Rp 33,800,000 33,800,000

e. Pekerjaan Pemasangan Bouwplank 179.17 m1 51,744.00 Rp 9,270,972 Rp 9,270,972

II. PEKERJAAN STRUKTUR

A. PEKERJAAN GALIAN

a. GALIAN TANAH Rp 35,124,606


- Galian pondasi type P1 8.10 m3 Rp 110,427 Rp 894,460
- Galian pondasi type P3 47.39 m3 Rp 110,427 Rp 5,232,648
- Galian pondasi type P4 39.38 m3 Rp 110,427 Rp 4,348,068
- Galian TB 1 21.17 m3 Rp 110,427 Rp 2,337,521
- Galian TB 2 19.60 m3 Rp 110,427 Rp 2,164,371
- Galian TB 3 25.92 m3 Rp 110,427 Rp 2,862,271
- Galian TB 4 147.16 m3 Rp 110,427 Rp 16,250,344
- Galian BC1 2.92 m3 Rp 110,427 Rp 322,005
- Galian BC3 6.46 m3 Rp 110,427 Rp 712,917

b. PEK. URUGAN Rp 10,883,239


a Pek. Urugan Pasir t= 10 cm
- type PC1 0.90 m3 Rp 293,634 Rp 264,271
- type PC3 5.27 m3 Rp 293,634 Rp 1,546,001
- type PC4 4.38 m3 Rp 293,634 Rp 1,284,649
- TB1 ( 300 X 600) 3.44 m3 Rp 293,634 Rp 1,010,395
- TB2 ( 350 X 700 ) 2.80 m3 Rp 293,634 Rp 822,175
- TB3 ( 400 X800 ) 3.45 m3 Rp 293,634 Rp 1,013,155
- TB4 (500 X 900 ) 16.35 m3 Rp 293,634 Rp 4,799,888
- BC1 ( 300 X 600 ) 0.49 m3 Rp 293,634 Rp 142,706
- BC3 ( 400 X 800) 0.45 m3 Rp 293,634 Rp 132,546

c. PEK. LANTAI KERJA Rp 18,299,186


a Pek. Lantai kerja t= 5 cm
- type PC1 0.45 m3 Rp 975,557 Rp 439,001
- type PC3 2.63 m3 Rp 975,557 Rp 2,568,183
- type PC4 2.19 m3 Rp 975,557 Rp 2,134,031
- TB1 ( 300 X 600) 1.72 m3 Rp 975,557 Rp 1,678,446
- TB2 ( 350 X 700 ) 1.40 m3 Rp 975,557 Rp 1,365,780
- TB3 ( 400 X800 ) 1.73 m3 Rp 975,557 Rp 1,683,031
- TB4 (500 X 900 ) 8.17 m3 Rp 975,557 Rp 7,973,471
- BC1 ( 300 X 600 ) 0.24 m3 Rp 975,557 Rp 237,060
- BC3 ( 400 X 800) 0.23 m3 Rp 975,557 Rp 220,183

B. PEKERJAAN PONDASI

a. TIANG BOR
- Tiang Bor Ø 500 x L=12M 64.00 ttk Rp 8,288,322 Rp 530,452,638 Rp 530,452,638
b. PONDASI
Pondasi telapak Type P1 0.60 Rp 27,919,233
- Bekisting batako 13.50 m2 149,187.50 Rp 2,014,031
- Besi Beton ( tul : D13 & D16) 1,417.50 kg 13,970.00 Rp 19,802,475
- Beton Ready Mix K300 8.10 m3 753,423.00 Rp 6,102,726

Pondasi Pile Cap Type PC 3 0.60 Rp 205,199,576


- Pecah kepala tiang BOR 36.00 ttk 142,995.60 Rp 5,147,842
- Bekisting batako 35.93 m2 94,336.00 Rp 3,389,873
- Besi Beton ( tul : D13 & D16) 8,292.47 kg 14,960.00 Rp 124,055,344
- Beton Ready Mix K300 47.39 m3 1,532,250.50 Rp 72,606,517

Pondasi Pile Cap Type PC 4 Rp 173,315,990


- Pecah kepala tiang BOR 28.00 ttk 142,995.60 Rp 4,003,877
- Bekisting batako 62.50 m2 94,336.00 Rp 5,896,000
- Besi Beton ( tul : D13 & D16) 6,890.63 kg 14,960.00 Rp 103,083,750
- Beton Ready Mix K300 39.38 m3 1,532,250.50 Rp 60,332,363
C. PEKERJAAN LANTAI DASAR

a. TB1 =300/600 Rp 101,165,199


- Bekisting batako 141.12 m2 94,336.00 Rp 13,312,696
- Besi Beton 3,704.40 kg 14,960.00 Rp 55,417,824
- Beton Ready Mix K300 21.17 m3 1,532,250.50 Rp 32,434,679

b. TB 2 = 350/700 Rp 91,910,542
- Bekisting batako 112.00 m2 94,336.00 Rp 10,565,632
- Besi Beton 3,430.00 kg 14,960.00 Rp 51,312,800
- Beton Ready Mix K300 19.60 m3 1,532,250.50 Rp 30,032,110

c. TB 3= 400/800 Rp 119,800,439
- Bekisting batako 129.60 m2 94,336.00 Rp 12,225,946
- Besi Beton 4,536.00 kg 14,960.00 Rp 67,858,560
- Beton Ready Mix K300 25.92 m3 1,532,250.50 Rp 39,715,933

d. TB4= 500/900 Rp 666,276,279


- Bekisting batako 588.64 m2 94,336.00 Rp 55,529,566
- Besi Beton 25,752.83 kg 14,960.00 Rp 385,262,262
- Beton Ready Mix K300 147.16 m3 1,532,250.50 Rp 225,484,451

e. BC1= 300/600 Rp 13,936,022


- Bekisting batako 19.44 m2 94,336.00 Rp 1,833,892
- Besi Beton 510.30 kg 14,960.00 Rp 7,634,088
- Beton Ready Mix K300 2.92 m3 1,532,250.50 Rp 4,468,042

f. BC3= 400/800 Rp 29,839,183


- Bekisting 32.28 m2 94,336.00 Rp 3,045,166
- Besi Beton 1,129.80 kg 14,960.00 Rp 16,901,808
- Beton Ready Mix K300 6.46 m3 1,532,250.50 Rp 9,892,209

g. KOLOM 600 x 600 Rp 195,736,366


Kolom Beton K1(600x600) = 23 bh
- Bekisting 251.16 m2 325,091.80 Rp 81,650,056
- Besi Beton 3,767.40 kg 14,960.00 Rp 56,360,304
- Beton Ready Mix K300 37.67 m3 1,532,250.50 Rp 57,726,005

D. PEKERJAAN LANTAI 1

a. B1 =300/600 Rp 126,827,578
- Bekisting 152.25 m2 334,991.80 Rp 51,002,502
- Besi Beton 3,197.25 kg 14,960.00 Rp 47,830,860
- Beton Ready Mix K300 18.27 m3 1,532,250.50 Rp 27,994,217

b. TB 2 = 350/700 Rp 128,243,762
- Bekisting 140.00 m2 334,991.80 Rp 46,898,852
- Besi Beton 3,430.00 kg 14,960.00 Rp 51,312,800
- Beton Ready Mix K300 19.60 m3 1,532,250.50 Rp 30,032,110

c. TB 3= 400/800 Rp 161,843,165
- Bekisting 162.00 m2 334,991.80 Rp 54,268,672
- Besi Beton 4,536.00 kg 14,960.00 Rp 67,858,560
- Beton Ready Mix K300 25.92 m3 1,532,250.50 Rp 39,715,933

d. TB4= 500/900 Rp 818,046,527


- Bekisting 713.21 m2 334,991.80 Rp 238,918,497
- Besi Beton 24,419.59 kg 14,960.00 Rp 365,317,029
- Beton Ready Mix K300 139.54 m3 1,532,250.50 Rp 213,811,001

e. BC1= 300/600 Rp 20,242,431


- Bekisting 24.30 m2 334,991.80 Rp 8,140,301
- Besi Beton 510.30 kg 14,960.00 Rp 7,634,088
- Beton Ready Mix K300 2.92 m3 1,532,250.50 Rp 4,468,042

f. BC3= 400/800 Rp 36,354,770


- Bekisting 36.39 m2 334,991.80 Rp 12,190,352
- Besi Beton 1,018.92 kg 14,960.00 Rp 15,243,043
- Beton Ready Mix K300 5.82 m3 1,532,250.50 Rp 8,921,375

g. BT= 300/400 Rp 6,065,647


- Bekisting 7.70 m2 334,991.80 Rp 2,579,437
- Besi Beton 147.00 kg 14,960.00 Rp 2,199,120
- Beton Ready Mix K300 0.84 m3 1,532,250.50 Rp 1,287,090

h. KOLOM 600 X 600 Rp 195,343,864


Kolom Beton K1(600x600) = 23 bh
- Bekisting 193.20 m2 325,091.80 Rp 62,807,736
- Besi Beton 5,071.50 kg 14,960.00 Rp 75,869,640
- Beton Ready Mix K300 28.98 m3 1,955,365.36 Rp 56,666,488
i. KOLOM 300 X 300 Rp 8,018,143
Kolom Beton K2(300x300) =3 bh
- Bekisting 12.60 m2 325,091.80 Rp 4,096,157
- Besi Beton 165.38 kg 14,960.00 Rp 2,474,010
- Beton Ready Mix K300 0.95 m3 1,532,250.50 Rp 1,447,977

j. PEKERJAAN PELAT LANTAI (tebal=12 cm) Rp 1,123,773,784


Lantai Beton t = 120 mm
– Begisting Lantai 1,221.60 m2 421,891.80 Rp 515,381,757
– Besi Beton 25,653.54 kg 14,960.00 Rp 383,776,914
– Beton Ready Mix K300 146.59 m3 1,532,250.50 Rp 224,615,114

E. PEKERJAAN LANTAI 2

a. B1 =300/600 Rp 124,347,256
- Bekisting 149.27 m2 334,991.80 Rp 50,005,063
- Besi Beton 3,134.72 kg 14,960.00 Rp 46,895,449
- Beton Ready Mix K300 17.91 m3 1,532,250.50 Rp 27,446,744

b. B 2 = 350/700 Rp 107,356,059
- Bekisting 117.20 m2 334,991.80 Rp 39,260,201
- Besi Beton 2,871.34 kg 14,960.00 Rp 42,955,228
- Beton Ready Mix K300 16.41 m3 1,532,250.50 Rp 25,140,630

c. B 3= 400/800 Rp 77,524,874
- Bekisting 77.60 m2 334,991.80 Rp 25,995,364
- Besi Beton 2,172.80 kg 14,960.00 Rp 32,505,088
- Beton Ready Mix K300 12.42 m3 1,532,250.50 Rp 19,024,422

d. B4= 500/900 Rp 509,811,639


- Bekisting 444.48 m2 334,991.80 Rp 148,895,480
- Besi Beton 15,218.44 kg 14,960.00 Rp 227,667,825
- Beton Ready Mix K300 86.96 m3 1,532,250.50 Rp 133,248,334

e. BC1= 300/600 Rp 20,242,431


- Bekisting 24.30 m2 334,991.80 Rp 8,140,301
- Besi Beton 510.30 kg 14,960.00 Rp 7,634,088
- Beton Ready Mix K300 2.92 m3 1,532,250.50 Rp 4,468,042

f. BC3= 400/800 Rp 4,375,760


- Bekisting 4.38 m2 334,991.80 Rp 1,467,264
- Besi Beton 122.64 kg 14,960.00 Rp 1,834,694
- Beton Ready Mix K300 0.70 m3 1,532,250.50 Rp 1,073,801

g. BT= 300/400 Rp 10,606,218


- Bekisting 13.46 m2 334,991.80 Rp 4,510,330
- Besi Beton 257.04 kg 14,960.00 Rp 3,845,318
- Beton Ready Mix K300 1.47 m3 1,532,250.50 Rp 2,250,570

h. KOLOM 600 X 600 Rp 151,241,648


Kolom Beton K1(600x600) = 19 bh
- Bekisting 159.60 m2 325,091.80 Rp 51,884,651
- Besi Beton 4,189.50 kg 14,960.00 Rp 62,674,920
- Beton Ready Mix K300 23.94 m3 1,532,250.50 Rp 36,682,077

i. KOLOM 300 X 300 Rp 8,018,143


Kolom Beton K2(300x300) =3 bh
- Bekisting 12.60 m2 325,091.80 Rp 4,096,157
- Besi Beton 165.38 kg 14,960.00 Rp 2,474,010
- Beton Ready Mix K300 0.95 m3 1,532,250.50 Rp 1,447,977

j. PEKERJAAN PELAT LANTAI (tebal=12 cm) Rp 622,144,712


Lantai Beton t = 120 mm
– Begisting Lantai 581.64 m2 421,891.80 Rp 245,390,201
– Besi Beton 15,886.28 kg 14,960.00 Rp 237,658,741
– Beton Ready Mix K300 90.78 m3 1,532,250.50 Rp 139,095,770

F. PEKERJAAN LANTAI 3

a B1 =300/600 Rp 124,347,256
- Bekisting 149.27 m2 334,991.80 Rp 50,005,063
- Besi Beton 3,134.72 kg 14,960.00 Rp 46,895,449
- Beton Ready Mix K300 17.91 m3 1,532,250.50 Rp 27,446,744

b. B 2 = 350/700 Rp 107,356,059
- Bekisting 117.20 m2 334,991.80 Rp 39,260,201
- Besi Beton 2,871.34 kg 14,960.00 Rp 42,955,228
- Beton Ready Mix K300 16.41 m3 1,532,250.50 Rp 25,140,630

c. B 3= 400/800 Rp 77,524,874
- Bekisting 77.60 m2 334,991.80 Rp 25,995,364
- Besi Beton 2,172.80 kg 14,960.00 Rp 32,505,088
- Beton Ready Mix K300 12.42 m3 1,532,250.50 Rp 19,024,422

d. B4= 500/900 Rp 509,811,639


- Bekisting 444.48 m2 334,991.80 Rp 148,895,480
- Besi Beton 15,218.44 kg 14,960.00 Rp 227,667,825
- Beton Ready Mix K300 86.96 m3 1,532,250.50 Rp 133,248,334

e. BC1= 300/600 Rp 20,242,431


- Bekisting 24.30 m2 334,991.80 Rp 8,140,301
- Besi Beton 510.30 kg 14,960.00 Rp 7,634,088
- Beton Ready Mix K300 2.92 m3 1,532,250.50 Rp 4,468,042

f. BC3= 400/800 Rp 4,375,760


- Bekisting 4.38 m2 334,991.80 Rp 1,467,264
- Besi Beton 122.64 kg 14,960.00 Rp 1,834,694
- Beton Ready Mix K300 0.70 m3 1,532,250.50 Rp 1,073,801

g. BT= 300/400 Rp 10,606,218


- Bekisting 13.46 m2 334,991.80 Rp 4,510,330
- Besi Beton 257.04 kg 14,960.00 Rp 3,845,318
- Beton Ready Mix K300 1.47 m3 1,532,250.50 Rp 2,250,570

h. KOLOM 600 X 600 Rp 151,241,648


Kolom Beton K1(600x600) = 19 bh
- Bekisting 159.60 m2 325,091.80 Rp 51,884,651
- Besi Beton 4,189.50 kg 14,960.00 Rp 62,674,920
- Beton Ready Mix K300 23.94 m3 1,532,250.50 Rp 36,682,077

i. KOLOM 300 X 300 Rp 8,018,143


Kolom Beton K2(300x300) =3 bh
- Bekisting 12.60 m2 325,091.80 Rp 4,096,157
- Besi Beton 165.38 kg 14,960.00 Rp 2,474,010
- Beton Ready Mix K300 0.95 m3 1,532,250.50 Rp 1,447,977

j. PEKERJAAN PELAT LANTAI (tebal=12 cm) Rp 622,144,712


Lantai Beton Atap ( S1 )t = 120 mm
– Begisting Lantai 581.64 m2 421,891.80 Rp 245,390,201
– Besi Beton 15,886.28 kg 14,960.00 Rp 237,658,741
– Beton Ready Mix K300 90.78 m3 1,532,250.50 Rp 139,095,770

G. PEKERJAAN LANTAI DAK ATAP

a. RB1 =300/600 Rp 248,731,997


- Bekisting 298.59 m2 334,991.80 Rp 100,025,202
- Besi Beton 6,270.39 kg 14,960.00 Rp 93,805,034
- Beton Ready Mix K300 35.83 m3 1,532,250.50 Rp 54,901,761

b. RB 2 = 350/700 Rp 179,541,267
- Bekisting 196.00 m2 334,991.80 Rp 65,658,393
- Besi Beton 4,802.00 kg 14,960.00 Rp 71,837,920
- Beton Ready Mix K300 27.44 m3 1,532,250.50 Rp 42,044,954

c. RB3 =400/800 Rp 165,129,844


- Bekisting 154.80 m2 334,991.80 Rp 51,856,731
- Besi Beton 4,334.40 kg 14,960.00 Rp 64,842,624
- Beton Ready Mix K300 24.77 m3 1,955,365.36 Rp 48,430,489

d. RB4= 500/900 Rp 144,536,123


- Bekisting 117.53 m2 334,991.80 Rp 39,371,586
- Besi Beton 4,024.13 kg 14,960.00 Rp 60,200,910
- Beton Ready Mix K300 23.00 m3 1,955,365.36 Rp 44,963,626

e. RB5= 300/500 Rp 21,668,177


- Bekisting 27.27 m2 334,991.80 Rp 9,135,226
- Besi Beton 477.23 kg 14,960.00 Rp 7,139,286
- Beton Ready Mix K300 2.73 m3 1,977,874.79 Rp 5,393,665

f. KOLOM 300 X 300 Rp 13,745,389


Kolom Beton K2(300x300) =6 bh
- Bekisting 21.60 m2 325,091.80 Rp 7,021,983
- Besi Beton 283.50 kg 14,960.00 Rp 4,241,160
- Beton Ready Mix K300 1.62 m3 1,532,250.50 Rp 2,482,246

g. PEKERJAAN PELAT LANTAI (tebal=12 cm) Rp 87,000,833


Lantai Beton Atap ( S1 )t = 120 mm
– Begisting Lantai 7.48 m2 421,891.80 Rp 3,153,799
– Besi Beton 3,535.50 kg 14,960.00 Rp 52,891,153
– Beton Ready Mix K300 20.20 m3 1,532,250.50 Rp 30,955,881
H. PEKERJAAN LANTAI DAK TANGGA

a. RB5 =300/500 Rp 26,958,526


- Bekisting 33.12 m2 334,991.80 Rp 11,096,268
- Besi Beton 668.85 kg 14,960.00 Rp 10,005,996
- Beton Ready Mix K300 3.82 m3 1,532,250.50 Rp 5,856,261

b. PEKERJAAN PELAT LANTAI (tebal=12 cm) Rp 14,558,616


Lantai Beton Atap ( S1 )t = 120 mm
– Begisting Lantai 3.18 m2 421,891.80 Rp 1,343,388
– Besi Beton 557.24 kg 14,960.00 Rp 8,336,236
– Beton Ready Mix K300 3.18 m3 1,532,250.50 Rp 4,878,992

I. PEKERJAAN TANGGA

a. Type A (2 unit tangga) Rp 95,731,365


Balok baja
- WF 350 X 175 2666.50 kg 27,840 Rp 74,235,249
- Plat dan Baut 266.65 kg 27,840 Rp 7,423,525
plat bordes
- floordeck t.7mm 10.88 m2 95,000 Rp 1,033,600
- Beton Ready Mix K300 1.33 m3 1,532,251 Rp 2,031,764
- Besi Beton 232.05 kg 14,960 Rp 3,471,468
trap
- Besi Beton 79.85 kg 14,960 Rp 1,194,593
- Beton Ready Mix K300 0.46 m3 1,532,251 Rp 699,166
- cheq'd plate 9 lbr 651,000 Rp 5,642,000
b. Type B ( 3 unit tangga) Rp 143,556,583
Balok baja
- WF 350 X 175 3999.74 kg 27,840 Rp 111,352,873
- Plat dan Baut 399.97 kg 27,840 Rp 11,135,287
plat bordes Rp -
- floordeck t.7mm 16.32 m2 95,000 Rp 1,550,400
- Beton Ready Mix K300 1.99 m3 1,532,251 Rp 3,047,646
- Besi Beton 348.08 kg 14,960 Rp 5,207,202
trap Rp -
- Besi Beton 118.07 kg 14,960 Rp 1,766,365
- Beton Ready Mix K300 0.67 m3 1,532,251 Rp 1,033,809
- cheq'd plate 13.00 lbr 651,000 Rp 8,463,000
J. PEKERJAAN RANGKA ATAP Rp 250,783,101
a Konstruksi rangka atap baja ringan
- Atap Type 1 517.85 m2 Rp 300,000 Rp 155,355,516
- Atap Type 2 318.09 m2 Rp 300,000 Rp 95,427,584
3. ANALISA PEKERJAAN
ANALISA HARGA SATUAN PEKERJAAN

A.2.2.1.4. Pengukuran dan pemasangan 1 m' Bouwplank 51,744.00


Harga Satuan Jumlah
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
1 2 3 4 5 6 7
A Tenaga Kerja
Pekerja L.001 OH 0.1000 90,000.00 9,000.00
Tukang kayu L.009 OH 0.1000 110,000.00 11,000.00
Kepala Tukang L.016 OH 0.0100 125,000.00 1,250.00
Mandor L.017 OH 0.0050 150,000.00 750.00
Jumlah Harga Tenaga Kerja 22,000.00
B Bahan
Kayu 5/7 kelas III M.03007 m3 0.0120 1,300,000.00 15,600.00
Paku Biasa 2"-3" M.08007 kg 0.0200 17,000.00 340.00
Kayu 3/20 kelas III M.03006 m3 0.0070 1,300,000.00 9,100.00
Jumlah Harga Bahan 25,040.00
C Peralatan
Jumlah Harga Peralatan -
D Jumlah (A+B+C) 47,040.00
E Overhead + Profit (Contoh 10%) 10% xD 4,704.00
F Harga Satuan Pekerjaan (D+E) 51,744.00

A.4.1.1.45. Tiang bor beton Ø 500 690,693.54


Harga Satuan Jumlah
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
1 2 3 4 5 6 7
A Tenaga Kerja
Pekerja L.001 OH 0.2367 60,000.00 14,202.00
Tukang Batu L.003 OH 0.1183 75,000.00 8,872.50
Mandor L.017 OH 0.0394 85,000.00 3,349.00
Jumlah Harga Tenaga Kerja 26,423.50
B Bahan
Beton Ready Mix K300 m3 0.1963 988,893.00 194,070.25
Baja tulangan polos U-24 atau ulir U-32 M.160 kg 29.4375 10,350.00 304,678.13
Jumlah Harga Bahan 498,748.38
C Peralatan
Bore Pile Machine E.6 jam 0.1917 551,567.00 105,717.90
Concrete pump E.15 jam 0.0296 331,512.00 9,803.76
alat bantu M.15018 hari 1.0000 50,000.00 50,000.00
Jumlah Harga Peralatan 165,521.66
D Jumlah (A+B+C) 690,693.54
E Overhead + Profit (Contoh 10%) 0% xD -
F Harga Satuan Pekerjaan (D+E) 690,693.54

A.2.3.1.2. Penggalian 1 m3 tanah 110,427.11


Harga Satuan Jumlah
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
1 2 3 4 5 6 7
A Tenaga Kerja
Pekerja L.001 OH 0.9000 90,000.00 81,000.00
Mandor L.017 OH 0.0450 150,000.00 6,750.00
Jumlah Harga Tenaga Kerja 87,750.00
B Bahan
Jumlah Harga Bahan -
C Peralatan
sewa excavator type 225 kap 0.5-1.0m3 M.15007 hari 0.0591 148,571.43 8,780.57
sewa bulldozer M.15008 hari 0.0226 148,571.43 3,357.71
Alat Bantu - Ls 1.0000 500.00 500.00
Jumlah Harga Peralatan 12,638.29
D Jumlah (A+B+C) 100,388.29
E Overhead + Profit (Contoh 10%) 10% xD 10,038.83
F Harga Satuan Pekerjaan (D+E) 110,427.11

A.2.3.1.11. Pengurugan 1 m3 dengan pasir urug 293,634.00


Harga Satuan Jumlah
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
1 2 3 4 5 6 7
A Tenaga Kerja
Pekerja L.001 OH 0.3000 90,000.00 27,000.00
Mandor L.017 OH 0.0100 150,000.00 1,500.00
Jumlah Harga Tenaga Kerja 28,500.00
B Bahan
Pasir urug M.01038 m3 1.2000 198,700.00 238,440.00
Jumlah Harga Bahan 238,440.00
C Peralatan
Jumlah Harga Peralatan -
D Jumlah (A+B+C) 266,940.00
E Overhead + Profit (Contoh 10%) 10% xD 26,694.00
F Harga Satuan Pekerjaan (D+E) 293,634.00
A.4.1.1.4. Membuat 1 m3 beton untuk lantai kerja (bedding) 975,557.00
Harga Satuan Jumlah
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
1 2 3 4 5 6 7
A Tenaga Kerja
Pekerja L.001 OH 1.2000 90,000.00 108,000.00
Tukang Batu L.003 OH 0.2000 110,000.00 22,000.00
Kepala Tukang L.016 OH 0.0200 125,000.00 2,500.00
Mandor L.017 OH 0.0600 150,000.00 9,000.00
Jumlah Harga Tenaga Kerja 141,500.00
B Bahan
Semen Portland M.01044 kg 230.0000 1,375.00 316,250.00
Pasir beton M.01036 M3 0.6200 276,000.00 171,120.00
Batu pecah mesin 2/3 M.01031 M3 0.8000 260,000.00 208,000.00
Air M.17001 liter 200.0000 250.00 50,000.00
Jumlah Harga Bahan 745,370.00
C Peralatan
Jumlah Harga Peralatan -
D Jumlah (A+B+C) 886,870.00
E Overhead + Profit (Contoh 10%) 10% xD 88,687.00
F Harga Satuan Pekerjaan (D+E) 975,557.00

A.3.2.1.23. Pemotongan 1 buah tiang pancang/turap beton 142,996


Harga Satuan Jumlah
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
1 2 3 4 5 6 7
A Tenaga Kerja
Pekerja L.001 OH 1.3334 90,000.00 120,006
Mandor L.017 OH 0.0666 150,000.00 9,990
Jumlah Harga Tenaga Kerja 129,996
B Bahan
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan -
D Jumlah (A+B+C) 129,996
E Overhead + Profit (Contoh 10%) 10% xD 13,000
F Harga Satuan Pekerjaan (D+E) 142,996

A.3.2.1.20. Pemancangan 1 m1 pondasi tiang pancang spun pile Ø400 dengan mesin hidrolik 566,600
Harga Satuan Jumlah
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
1 2 3 4 5 6 7
A Tenaga Kerja
Pekerja L.001 OH 0.0520 90,000.00 4,680
Tukang L.002 OH 0.0104 110,000.00 1,144
Operator alat berat L.018 OH 0.0104 150,000.00 1,560
Pembantu Operator L.019 OH 0.0104 100,000.00 1,040
Mandor L.017 OH 0.0052 150,000.00 780
Jumlah Harga Tenaga Kerja 9,204
B Bahan
Tiang pancang spun pile Ø400 M.01057 m1 1.0300 390,000.00 401,700
Jumlah Harga Bahan 401,700
C Peralatan
Sewa crane M.15006 hari 0.0104 2,806,400.00 29,186.56
Sewa mesin hidrolik M.15020 hari 0.0500 1,500,000.00 75,000
Jumlah Harga Peralatan 104,187
D Jumlah (A+B+C) 515,091
E Overhead + Profit (Contoh 10%) 10% xD 51,509
F Harga Satuan Pekerjaan (D+E) 566,600

A.4.1.1.10. Membuat 1 m3 beton mutu f'c = 26,4 MPa (K300), slump (12+2) cm, w/c = 0,52 1,532,251
Harga Satuan Jumlah
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
1 2 3 4 5 6 7
A Tenaga Kerja
Pekerja L.001 OH 1.6500 90,000.00 148,500
Tukang Batu L.003 OH 0.2750 110,000.00 30,250
Kepala Tukang L.016 OH 0.0280 125,000.00 3,500
Mandor L.017 OH 0.0830 150,000.00 12,450
Jumlah Harga Tenaga Kerja 194,700
B Bahan
Semen Portland M.01044 kg 413.0000 1,375.00 567,875
Pasir beton M.01036 kg 0.6800 276,000.00 187,680
Batu pecah mesin 2/3 M.01031 kg 1 260,000.00 265,200
Air M.17001 liter 215.0000 250.00 53,750
Jumlah Harga Bahan 1,074,505
C Peralatan
sewa mesin beton molen+Tenaga+bahan bakar M.17015 HARI 0.2250 550,000.00 123,750
D Jumlah (A+B+C) 1,392,955
E Overhead + Profit (Contoh 10%) 10% xD 139,296
F Harga Satuan Pekerjaan (D+E) 1,532,251
A.4.4.1.28. Pemasangan 1 m2 dinding batako (10x20x40) cm campuran 1SP : 4PP 94,336.00
Harga Satuan Jumlah
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
1 2 3 4 5 6 7
A Tenaga Kerja
Pekerja L.001 OH 0.3000 90,000.00 27,000.00
Tukang Batu L.003 OH 0.1000 110,000.00 11,000.00
Kepala Tukang L.016 OH 0.0100 125,000.00 1,250.00
Mandor L.017 OH 0.0150 150,000.00 2,250.00
Jumlah Harga Tenaga Kerja 41,500.00
B Bahan
Batako M.01004 bh 11.0000 1,750.00 19,250.00
Semen Portland M.01044 kg 11.5000 1,240.00 14,260.00
Pasir pasang M.01037 m3 0.0430 250,000.00 10,750.00
Jumlah Harga Bahan 44,260.00
C Peralatan
Jumlah Harga Peralatan -
D Jumlah (A+B+C) 85,760.00
E Overhead + Profit (Contoh 10%) 10% xD 8,576.00
F Harga Satuan Pekerjaan (D+E) 94,336.00

A.4.1.1.20. Pemasangan 1 m2 bekisting untuk pondasi 154,262


Harga Satuan Jumlah
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
1 2 3 4 5 6 7
A Tenaga Kerja
Pekerja L.001 OH 0.5200 90,000.00 46,800
Tukang kayu L.009 OH 0.2600 110,000.00 28,600
Kepala Tukang L.016 OH 0.0260 125,000.00 3,250
Mandor L.017 OH 0.0260 150,000.00 3,900
Jumlah Harga Tenaga Kerja 82,550
B Bahan
Kayu balok kelas III M.03010 m3 0.0400 1,309,700.00 52,388
Paku 5-12 cm M.08003 kg 0.3000 17,000.00 5,100
Minyak bekisting M.16002 liter 0.1000 2,000.00 200
Jumlah Harga Bahan 57,688
C Peralatan
Jumlah Harga Peralatan -
D Jumlah (A+B+C) 140,238
E Overhead + Profit (Contoh 10%) 10% xD 14,024
F Harga Satuan Pekerjaan (D+E) 154,262

A.4.1.1.22. Pemasangan 1 m2 bekisting untuk kolom 325,092


Harga Satuan Jumlah
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
1 2 3 4 5 6 7
A Tenaga Kerja
Pekerja L.001 OH 0.6600 90,000.00 59,400
Tukang kayu L.009 OH 0.3300 110,000.00 36,300
Kepala Tukang L.016 OH 0.0330 125,000.00 4,125
Mandor L.017 OH 0.0330 150,000.00 4,950
Jumlah Harga Tenaga Kerja 104,775
B Bahan
Kayu balok kelas III M.03010 m3 0.0400 1,309,700.00 52,388
Paku 5-12 cm M.08003 kg 0.4000 17,000.00 6,800
Minyak bekisting M.16002 liter 0.2000 2,000.00 400
Kayu balok kelas II M.03009 m3 0.0150 3,000,000.00 45,000
Plywood 9mm M.03024 lembar 0.3500 120,500.00 42,175
Dolken Kayu 8-10/400 cm M.03003 Batang 2.0000 22,000.00 44,000
Jumlah Harga Bahan 190,763
C Peralatan
Jumlah Harga Peralatan -
D Jumlah (A+B+C) 295,538
E Overhead + Profit (Contoh 10%) 10% xD 29,554
F Harga Satuan Pekerjaan (D+E) 325,092

A.4.1.1.23. Pemasangan 1 m2 bekisting untuk balok 334,992


Harga Satuan Jumlah
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
1 2 3 4 5 6 7
A Tenaga Kerja
Pekerja L.001 OH 0.6600 90,000.00 59,400
Tukang kayu L.009 OH 0.3300 110,000.00 36,300
Kepala Tukang L.016 OH 0.0330 125,000.00 4,125
Mandor L.017 OH 0.0330 150,000.00 4,950
Jumlah Harga Tenaga Kerja 104,775
B Bahan
Kayu balok kelas III M.03010 m3 0.0400 1,309,700.00 52,388
Paku 5-12 cm M.08003 kg 0.4000 17,000.00 6,800
Minyak bekisting M.16002 liter 0.2000 2,000.00 400
Kayu balok kelas II M.03009 m3 0.0180 3,000,000.00 54,000
Plywood 9mm M.03024 lembar 0.3500 120,500.00 42,175
Dolken Kayu 8-10/400 cm M.03003 Batang 2.0000 22,000.00 44,000
Jumlah Harga Bahan 199,763
C Peralatan
Jumlah Harga Peralatan -
D Jumlah (A+B+C) 304,538
E Overhead + Profit (Contoh 10%) 10% xD 30,454
F Harga Satuan Pekerjaan (D+E) 334,992
A.4.1.1.24. Pemasangan 1 m2 bekisting untuk lantai 421,892
Harga Satuan Jumlah
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
1 2 3 4 5 6 7
A Tenaga Kerja
Pekerja L.001 OH 0.6600 90,000.00 59,400
Tukang kayu L.009 OH 0.3300 110,000.00 36,300
Kepala Tukang L.016 OH 0.0330 125,000.00 4,125
Mandor L.017 OH 0.0330 150,000.00 4,950
Jumlah Harga Tenaga Kerja 104,775
B Bahan
Kayu balok kelas III M.03010 m3 0.0400 1,309,700.00 52,388
Paku 5-12 cm M.08003 kg 0.4000 17,000.00 6,800
Minyak bekisting M.16002 liter 0.2000 2,000.00 400
Kayu balok kelas II M.03009 m3 0.0150 3,000,000.00 45,000
Plywood 9mm M.03024 lembar 0.3500 120,500.00 42,175
Dolken Kayu 8-10/400 cm M.03003 Batang 6.0000 22,000.00 132,000
Jumlah Harga Bahan 278,763
C Peralatan
Jumlah Harga Peralatan -
D Jumlah (A+B+C) 383,538
E Overhead + Profit (Contoh 10%) 10% xD 38,354
F Harga Satuan Pekerjaan (D+E) 421,892

A.4.1.1.26. Pemasangan 1 m2 bekisting untuk tangga 310,575


Harga Satuan Jumlah
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
1 2 3 4 5 6 7
A Tenaga Kerja
Pekerja L.001 OH 0.6600 90,000.00 59,400
Tukang kayu L.009 OH 0.3300 110,000.00 36,300
Kepala Tukang L.016 OH 0.0330 125,000.00 4,125
Mandor L.017 OH 0.0330 150,000.00 4,950
Jumlah Harga Tenaga Kerja 104,775
B Bahan
Kayu balok kelas III M.03010 m3 0.0300 1,309,700.00 39,291
Paku 5-12 cm M.08003 kg 0.4000 17,000.00 6,800
Minyak bekisting M.16002 liter 0.1500 2,000.00 300
Kayu balok kelas II M.03009 m3 0.0150 3,000,000.00 45,000
Plywood 9mm M.03024 lembar 0.3500 120,500.00 42,175
Dolken Kayu 8-10/400 cm M.03003 Batang 2.0000 22,000.00 44,000
Jumlah Harga Bahan 177,566

C Peralatan
Jumlah Harga Peralatan -
D Jumlah (A+B+C) 282,341
E Overhead + Profit (Contoh 10%) 10% xD 28,234
F Harga Satuan Pekerjaan (D+E) 310,575

1 Pekerjaan kontruksi baja per-kg 27,840


a Baja profil ( WF) + cat 1.1000 13,000.00 14,300

b Upah
fabrikasi (disesuakan borongan dilapangan/mandor LS 1.0000 3,900.00 3,900
erection (disesuakan borongan dilapangan/mandor LS 1.0000 1,900.00 1,900

c Alat/Mesin/Sarana kawat/mata grenda dll LS 1.0000 3,100.00 3,100


Jumlah 23,200
Fee 10% 2,320
OHC 10% 2,320
Jumlah Semua 27,840
A.4.1.1.17. Pembesian 10 kg dengan besi polos atau besi ulir 14,960
Harga Satuan Jumlah
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
1 2 3 4 5 6 7
A Tenaga Kerja
Pekerja L.001 OH 0.0700 90,000.00 6,300
Tukang Besi L.004 OH 0.0700 110,000.00 7,700
Kepala Tukang L.016 OH 0.0070 125,000.00 875
Mandor L.017 OH 0.0040 150,000.00 600
Jumlah Harga Tenaga Kerja 15,475
B Bahan
Besi beton M.06004 kg 10.5000 11,250.00 118,125
Kawat beton M.06016 kg 0.1500 16,000.00 2,400
Jumlah Harga Bahan 120,525
C Peralatan
Jumlah Harga Peralatan -
D Jumlah (A+B+C) 136,000
E Overhead + Profit (Contoh 10%) 10% xD 13,600
F Harga Satuan Pekerjaan (D+E) 149,600
G Harga Satuan Pekerjaan ( E x 0,1 )) 1 kg 14,960

Jakarta, 22 Agustus 2019

Dibuat oleh:
PT.BHINEKA TEKNIK UNGGUL PERSADA

Ir.M.Shokeh,MT
Direktur