ESTIMASI RENCANA ANGGARAN BIAYA

LOKASI : PUJASERA CIPANAS

HARGA SATUAN TOTAL HARGA TOTAL HARGA


VOLUME
NO. JENIS PEKERJAAN SATUAN MATERIAL UPAH MATERIAL UPAH (Rp)
a b c d=axb e=axc f=d+e

I PEKERJAAN TANAH
1 Pek. Galian Tanah Untuk Pondasi Batu Kali + Galian Tanah Untuk Pondasi Setempat 0,6X0,6X1,2 M m3 12.42 - 40,000 - 496,800 496,800
2 Pek. Urugan Tanah Kembali Untuk Pondasi m3 4.14 - 15,500 - 64,170 64,170
3 Pek. Urugan Tanah Untuk Kenaikan Elevasi Dari Elevasi Existing +20 cm + Pemadatan m3 17.18 90,000 23,000 1,546,200 395,140 1,941,340
sub-total 1,546,200 395,140 1,941,340
III PEKERJAAN PONDASI DAN BETON
1 Pek. Pondasi Batu Kali 1pc : 6ps + Stek Besi ke Sloof Tiap 1 Meter m3 6.89 447,500 102,500 3,081,038 705,713 3,786,750
2 Pek. Pondasi Setempat/Telapak Dimensi 0,6x0,6x0,25 Meter (Tulangan Besi Ø 12 mm – 150 mm) m3 0.54 1,725,000 352,500 931,500 190,350 1,121,850
3 Pek. Pondasi Rolaq Bata 1pc : 4ps Untuk Trap Teras m1 15.00 40,875 13,375 613,125 200,625 813,750
4 Pek. Kolom Pedestal 25/25 Untuk Dudukan Tiang Besi m3 0.38 3,000,000 500,000 1,125,000 187,500 1,312,500
5 Pek. Sloof Beton 15/20 cm (Tulangan Besi 4 Ø 10 mm, Ring Ø8 mm-150 mm) m3 0.81 3,000,000 500,000 2,430,000 405,000 2,835,000
6 Pek. Ringbalk 12/15 cm + Ampig (Tulangan Besi 4 Ø 10 mm, Ring Ø8 mm-150 mm) m3 0.49 3,000,000 500,000 1,458,000 243,000 1,701,000
9 Pek. Kolom Praktis 12/12 cm (Tulangan Besi 4 Ø 10 mm, Ring Ø8 mm-150 mm) m3 0.20 3,000,000 500,000 604,800 100,800 705,600
11 Pek. Angkur + Bout Ø 16 mm Panjang 60 Cm bh 6.00 31,500 5,513 189,000 33,078 222,078
12 Pek. Base Plat Tebal 10 mm (Ukuran 20x20 cm) kg 18.84 18,000 4,000 339,120 75,360 414,480
12 Pek. Kolom besi hollow 100.100 tebal 3.20 mm + cat Zingcromate kg 207.48 18,000 4,000 3,734,640 829,920 4,564,560
13 Pek. Balok besi hollow 100.100 tebal 3.20 mm + cat Zingcromate kg 474.24 18,000 4,000 8,536,320 1,896,960 10,433,280
14 Pek. lantai plur Beton 4 cm m3 3.44 650,000 150,000 2,233,400 515,400 2,748,800
sub-total 25,275,943 5,383,706 30,659,648
IV PEKERJAAN PASANGAN
1 Pek. Pasangan Dinding Setengah Bata 1Pc : 5Ps m2 81.00 94,500 23,700 7,654,500 1,919,700 9,574,200
2 Pek. Plester + Acian 1pc : 5ps m2 162.00 35,000 20,000 5,670,000 3,240,000 8,910,000
3 Pek. Partisi Gypsum 9 mm ex. Aplus, 2 muka + Rangka Metal Strut untuk sekat kedai m2 19.50 130,000 23,000 2,535,000 448,500 2,983,500
4 Pek. GRC Lisplank Atap m2 43.20 75,500 18,750 3,261,600 810,000 4,071,600
sub-total 19,121,100 6,418,200 25,539,300
V PEKERJAAN PLAFOND & PARTISI
1 Pek. Plafond Gypsum 9 mm ex. Aplus + Rangka Hollow Galvanis m2 85.90 70,000 20,000 6,013,000 1,718,000 7,731,000
2 Pek. Man Hole Gypsum 60x60 cm ls 1.00 125,000 20,000 125,000 20,000 145,000
sub-total 6,138,000 1,738,000 7,876,000
VI PEKERJAAN LANTAI & DINDING KERAMIK
1 Pek. Lantai plur Beton 4 cm + pengacian m3 3.44 650,000 150,000 2,233,400 515,400 2,748,800
sub-total 2,233,400 515,400 2,748,800
VII PEKERJAAN SANITARY
1 Pek. Kichen sink meja beton + sink Cuci piring unit 5.00 450,000 300,000 2,250,000 1,500,000 3,750,000
2 Pek. Instalasi Air Bersih Pipa PVC 1/2'' Wavin D m1 25.00 15,000 3,000 375,000 75,000 450,000
3 Pek. Instalasi Pipa Pembuangan Air kotor Kichen sink, Pipa PVC 3" Wavin D m1 24.00 15,000 3,000 360,000 72,000 432,000
sub-total 2,985,000 1,647,000 4,632,000
VIII PEKERJAAN ATAP
Pek. Rangka Kuda-kuda Atap Baja Ringan, Zincalume T=0,70 mm + Rangka cremona untuk lisplank +
1 rangka talang m2 144.00 135,000 18,000 19,440,000 2,592,000 22,032,000
2 Pek. Atap Zincalum Tebal 0,30 mm Natural, Model Profil Spandeck + Kanopi m2 144.00 75,000 18,000 10,800,000 2,592,000 13,392,000
3 Pek. Nok Zincalum TCT = 0,35 mm AZ 150 m1 15.00 45,000 10,000 675,000 150,000 825,000
4 Pek. Talang Galvalume BJLS 90 Cm + Sambungan Dipatri m1 36.00 75,000 25,000 2,700,000 900,000 3,600,000
5 Pek. Plesingan Galvalume Topi Lebar 45 cm Untuk Ampig m1 52.00 45,000 10,000 2,340,000 520,000 2,860,000
6 Pek. Talang Vertikal Air Hujan 3” ex. Wavin D (Total, Dilapisi Ram Kawat) m1 21.00 55,000 5,000 1,155,000 105,000 1,260,000
sub-total 37,110,000 6,859,000 43,969,000
X PEKERJAAN FINISHING
1 Pek. Cat dinding luar + grc lisplank ex. Avitex Exterior Super White (Type SW Exterior Tutup Warna Hijau m2 122.60 12,000 5,000 1,471,200 613,000 2,084,200
2 Pek. Cat Plafond ex. Avitex Super White (Kode SW Tutup Warna Biru) m2 85.90 10,000 5,000 859,000 429,500 1,288,500
3 Pek. Cat Dinding dan Partisi ex. Avitex Super White (Kode SW Tutup Warna Biru) m2 141.00 10,000 5,000 1,410,000 705,000 2,115,000
sub-total 3,740,200 1,747,500 5,487,700

Total (Rp) 120,912,448


Pembulatan ( Rp ) 120,912,000
Grand Total 120,912,000
REKAP

REKAPITULASI RENCANA ANGGARAN BIAYA

LOKASI : PUJASERA CIPANAS

REKAPITULASI
Total Harga Total Harga
NO. JENIS PEKERJAAN Material Upah (Rp)
a b c=a+b
I PEKERJAAN TANAH 1,546,200 395,140 1,941,340.00
III PEKERJAAN PONDASI DAN BETON 25,275,943 5,383,706 30,659,648.00
IV PEKERJAAN PASANGAN 19,121,100 6,418,200 25,539,300.00
V PEKERJAAN PLAFOND & PARTISI 6,138,000 1,738,000 7,876,000.00
VI PEKERJAAN LANTAI & DINDING KERAMIK 2,233,400 515,400 2,748,800.00
VII PEKERJAAN SANITARY 2,985,000 1,647,000 4,632,000

VIII PEKERJAAN ATAP 37,110,000 6,859,000 43,969,000.00


X PEKERJAAN FINISHING 3,740,200 1,747,500 5,487,700.00
Total (Rp) 98,149,843 24,703,946 122,853,788.00
Pembulatan ( Rp ) 122,854,000

Grand Total 122,854,000