EKONOMI TEKNIK " POS JAGA "

DAFTAR HARGA UPAH PEKERJA DAN HARGA BAHAN


TAHUN 2008

A DAFTAR HARGA UPAH PEKERJA

NO URAIAN JENIS PEKERJA SATUAN NILAI UPAH (Rp)

1 MANDOR ORG/HARI 42000.00


2 KEPALA TUKANG ORG/HARI 45000.00
3 TUKANG LISTRIK ORG/HARI 40000.00
4 TUKANG KAYU ORG/HARI 40000.00
5 TUKANG BATU ORG/HARI 40000.00
6 TUKANG BESI ORG/HARI 40000.00
7 TUKANG CAT ORG/HARI 40000.00
8 TUKANG LEDENG ORG/HARI 40000.00
9 PEKERJA ORG/HARI 30000.00

B DAFTAR HARGA BAHAN MATERIAL

NO URAIAN JENIS PEKERJA SATUAN NILAI UPAH (Rp)

1 TANAH URUG M3 45650.00


2 PASIR URUG M3 75000.00
3 BATA MERAH BH 300.00
4 PASIR PASANG M3 100000.00
5 SEMEN KG 1200.00
6 BATU GUNUNG M3 120000.00
7 KERIKIL M3 201308.00
8 PAKU 2''- 5'' KG 12650.00
9 KAYU 5/7MIRANTI M3 896400.00
10 KAYU PAPAN 3/20 M3 700000.00
11 PAPAN BEKISTING M3 1000000.00
12 PAKU CAMPUR KG 15000.00
13 MINYAK BEKISTING LTR 17000.00
14 BESI BETON KG 14000.00
15 KAWAT BESI KG 15000.00
16 PASIR BETON M3 141333.00
17 SUPLIT M3 183503.00
18 BALOK KAYU M3 1000000.00
19 DOLKEN DIA 8 CM/4 BTG 6000.00
20 TEGEL 30 x 30 cm BUAH 2600.00
21 NAT KG 6325.00
22 TEGEL 20 x 20 cm BUAH 1600.00
23 TEGEL 10 x 10 cm BUAH 1000.00
24 SEMEN ABU-ABU KG 1200.00
25 KAYU MIRANTI M3 896400.00
26 TRIPLEKS 5MM LBR 42000.00
27 PAKU TRIPLEKS KG 20000.00
28 KAYU PROFIL SILAE LBR 15000.00
29 KAYU KALAPI M3 1800000.00

AFAN MPONIALA E1 B1 06 051


EKONOMI TEKNIK " POS JAGA "

30 PAPAN KAYU JATI M3 1500000.00

31 KUNCI TANAM ACHOR BH 92690.00


32 ENGSEL PINTU TYPE H BH 15000.00
33 GRENDEL PINTU BH 4000.00
34 BEGEL,BAUT,ANGKER, BESI KG 20000.00
35 KAYU SILAE M3 1800000.00
36 ATAP SENG BJLS 20 LBR 6785.00
37 PAKU SENG KG 20000.00
38 SENG PLAT BJLS 20 M3 40000.00
39 KLOSED JONGKOK BH 85000.00
40 KRAN AIR BH 20000.00
41 SEAL TAPE BH 2500.00
42 FLOOR DRAIN BH 34000.00
43 TEMPAT SABUN BH 5000.00
44 PIPA PVC Ø 1/2'' M 14000.00
45 LEM PIPA BH 5000.00
46 AMPLAS LBR 3000.00
47 PIPA PVC Ø 4'' M 144000.00
48 GALIAN TANAH M3 14250.00
49 PASANGAN IJUK M2 7500.00
50 URUGAN KERIKIL 3,5 M3 115000.00
51 PENYAMBUNGAN AIR DARI PDAM LS 3000000.00
52 LAMPU PIJAR 25 WATT TITIK 4000.00
53 LAMPU TL 60 WATT TITIK 80000.00
54 STOP KONTAK BH 14000.00
55 SAKLAR GANDA BH 13000.00
56 SAKLAR TUNGGAL BH 10000.00
57 KOTAK MCB BH 75000.00
58 KABEL NYM M 80000.00
59 FITING PLAFOND BH 12000.00
60 PENYAMBUNGAN DAYA LS 3000000.00
61 PLAMIR KG 5000.00
62 CAT DASAR KG 29000.00
63 CAT TEMBOK 2 X KG 12000.00
64 CAT PLAFOND KG 5000.00
65 KUAS KG 12000.00
66 LIST PLAFOND KG 11000.00
67 PAPAN KAYU SILAE KG 1500000.00
68 VERNIS KAYU LTR 35000.00
69 DEMPUL KG 12000.00
70 LEM FOX BH 10000.00
71 KACA BENING 5 MM M2 125000.00
72 LIST KACA 1 X 1 CM M 2500.00

AFAN MPONIALA E1 B1 06 051


EKONOMI TEKNIK " POS JAGA "

DAFTAR ANALIASA HARGA SATUAN PEKERJAAN

1.1M2- PEKERJAAN PEMBERSIHAN SITE/ LOKASI

NO URAIAN PEKERJAAN SATUAN HARGA SATUAN KUANTITAS JUMLAH HARGA


A. TENAGA KERJA
1TUKANG BATU ORG/HARI 40000.00 0.01 400.00
2PEKERJA ORG/HARI 30000.00 0.02 600.00
3MANDOR ORG/HARI 42000.00 0.02 840.00
JUMLAH 1,840.00
B BAHAN
1 PERALATAN LS 200.00 1.00 200.00
JUMLAH 200.00
HARGA ( A + B ) 2,040.00

2.1M1- PENGUKURAN DAN PEMASANGAN BOUW PLANK

NO URAIAN PEKERJAAN SATUAN HARGA SATUAN KUANTITAS JUMLAH HARGA


A. TENAGA KERJA
1TUKANG KAYU ORG/HARI 40000.00 0.1 4,000.00
2PEKERJA ORG/HARI 30000.00 0.1 3,000.00
3MANDOR ORG/HARI 42000.00 0.005 210.00
JUMLAH 7,210.00
B BAHAN
1 PAKU 2''- 5'' KG 12650.00 0.02 253
2 KAYU 5/7 M3
896400.00 0.012 10756.8
3 KAYU PAPAN 3/20 M3
700000.00 0.007 4900
JUMLAH 15,909.80
HARGA(A+B) 23,119.80

3.1M3- PEK. GALIAN TANAH PONDASI SEDALAM 1 M

NO URAIAN PEKERJAAN SATUAN HARGA SATUAN KUANTITAS JUMLAH HARGA


A. TENAGA KERJA
1 PEKERJA ORG/HARI 30000.00 0.4 12,000.00
2 MANDOR ORG/HARI 42000.00 0.04 1,680.00
JUMLAH
B BAHAN
HARGA(A+B) 13,680.00

4.1M3- PEK. URUGAN KEMBALI

NO URAIAN PEKERJAAN SATUAN HARGA SATUAN KUANTITAS JUMLAH HARGA


A. TENAGA KERJA
1 PEKERJA ORG/HARI 30000.00 0.192 5,760.00
2 MANDOR ORG/HARI 42000.00 0.0192 806.40
JUMLAH
B BAHAN
HARGA(A+B) 6,566.40

5.1M3- PEKERJAAN URUGAN TANAH UNTUK PENINGGIAN LANTAI SETEBAL 30 CM

NO URAIAN PEKERJAAN SATUAN HARGA SATUAN KUANTITAS JUMLAH HARGA


A. TENAGA KERJA
1 PEKERJA ORG/HARI 30000.00 0.3 9,000.00
2 MANDOR ORG/HARI 42000.00 0.01 420.00
JUMLAH 9,420.00
B BAHAN

3 AFAN MPONIALA E1 B1 06 051


EKONOMI TEKNIK " POS JAGA "

1 TANAH URUG M3 45650.00 1.20 54,780.00


HARGA(A+B) 64,200.00

6.1M3- PEK. URUGAN PASIR

NO URAIAN PEKERJAAN SATUAN HARGA SATUAN KUANTITAS JUMLAH HARGA


A. TENAGA KERJA
1 PEKERJA ORG/HARI 30000.00 0.3 9,000.00
2 MANDOR ORG/HARI 42000.00 0.01 420.00
JUMLAH 9,420.00
B BAHAN
1 PASIR URUG M3 75000.00 1.20 90,000.00
HARGA(A+B) 99,420.00

7.1M3- URUGAN TANAH UNTUK PENINGGIAN LANTAI SETINGGI 30CM

NO URAIAN PEKERJAAN SATUAN HARGA SATUAN KUANTITAS JUMLAH HARGA


A. TENAGA KERJA
1 PEKERJA ORG/HARI 30000.00 0.3 9,000.00
2 MANDOR ORG/HARI 42000.00 0.01 420.00
JUMLAH 9,420.00
B BAHAN
1 TANAH URUG M3 45650.00 1.20 54,780.00
HARGA(A+B) 64,200.00

8.1M3- PEK. SALURAN AIR KELILING BANGUNAN ,DIPLESTER+DILICIN

NO URAIAN PEKERJAAN SATUAN HARGA SATUAN KUANTITAS JUMLAH HARGA


A. TENAGA KERJA
1PEKERJA ORG/HARI 30000.00 0.598 17,940.00
2MANDOR ORG/HARI 42000.00 0.022 924.00
3TUKANG BATU ORG/HARI 40000.00 0.0279 1,116.00
4KEPALA TUKANG ORG/HARI 45000.00 0.027 1,215.00
JUMLAH 21,195.00
B BAHAN
1 BATA MERAH BH 300.00 0.132 39.6
2 PASIR PASANG M3
100000.00 0.0864 8640
3 SEMEN KG 1200.00 0.571 685.2
JUMLAH 9364.8
HARGA(A+B) 30,559.80

9.1M3- PEK. PASANGAN PONDASI BATU GUNUNG 1PC : 5PSR

NO URAIAN PEKERJAAN SATUAN HARGA SATUAN KUANTITAS JUMLAH HARGA


A. TENAGA KERJA
1 PEKERJA ORG/HARI 30000.00 1.5 45,000.00
2 MANDOR ORG/HARI 42000.00 0.075 3,150.00
3 TUKANG BATU ORG/HARI 40000.00 0.6 24,000.00
4 KEPALA TUKANG ORG/HARI 45000.00 0.06 2,700.00
JUMLAH 74,850.00
B BAHAN
1 BATU GUNUNG M3 120000.00 1.1 132000
2 PASIR PASANG M3
100000.00 0.544 54400
3 SEMEN KG 1200.00 136 163200
JUMLAH 349600
HARGA(A+B) 424,450.00

4 AFAN MPONIALA E1 B1 06 051


EKONOMI TEKNIK " POS JAGA "

10.1M3- PEK. RABAT BETON 1PC : 2PSR : 3KRL

NO URAIAN PEKERJAAN SATUAN HARGA SATUAN KUANTITAS JUMLAH HARGA


A. TENAGA KERJA
1 PEKERJA ORG/HARI 30000.00 1.65 49,500.00
2 MANDOR ORG/HARI 42000.00 0.08 3,360.00
3 TUKANG BATU ORG/HARI 40000.00 0.25 10,000.00
4 KEPALA TUKANG ORG/HARI 45000.00 0.25 11,250.00
JUMLAH 74,110.00
B BAHAN
1 KERIKIL M3 201308.00 0.87 175137.96
2 PASIR PASANG M3
100000.00 0.52 52000
3 SEMEN KG 1200.00 218 261600
JUMLAH 488737.96
HARGA(A+B) 562,847.96

11.1M3- PEKERJAAN PONDASI BATU KOSONG

NO URAIAN PEKERJAAN SATUAN HARGA SATUAN KUANTITAS JUMLAH HARGA


A. TENAGA KERJA
1PEKERJA ORG/HARI 30000.00 0.78 23400
2MANDOR ORG/HARI 42000.00 0.039 1638
3TUKANG BATU ORG/HARI 40000.00 0.39 15600
4KEPALA TUKANG ORG/HARI 45000.00 0.039 1755
JUMLAH 42,393.00
B BAHAN
1 BATU GUNUNG M3 120000.00 1.2 144000
JUMLAH
HARGA(A+B) 186,393.00

12.1M3- PEKERJAAN SLOFF (200KG BESI+ BEKISTING ) 1 PC: 3 PSR

NO URAIAN PEKERJAAN SATUAN HARGA SATUAN KUANTITAS JUMLAH HARGA


A. TENAGA KERJA
1 PEKERJA ORG/HARI 30000.00 4.85 145500
2 MANDOR ORG/HARI 42000.00 0.17 7140
3 TUKANG BATU ORG/HARI 40000.00 0.35 14000
4 KEPALA TUKANG ORG/HARI 45000.00 0.331 14895
5 TUKANG KAYU ORG/HARI 40000.00 1.56 62400
6 TUKANG BESI ORG/HARI 40000.00 1.4 56000
JUMLAH 299935
B BAHAN
1 PAPAN BEKISTING M3 1000000.00 0.27 270,000.00
2 PAKU CAMPUR KG 15000.00 2 30,000.00
3 MINYAK BEKISTING LTR 17000.00 2.0 34,000.00
4 BESI BETON KG 14000.00 200 2,800,000.00
5 KAWAT BESI KG 15000.00 3 45,000.00
6 SEMEN KG 1200.00 323 387,600.00
7 PASIR BETON M3 141333.00 0.52 73,493.16
8 SUPLIT M3
183503.00 0.78 143,132.34
JUMLAH 3,783,225.50
HARGA(A+B) 4,083,160.50

5 AFAN MPONIALA E1 B1 06 051


EKONOMI TEKNIK " POS JAGA "

13.1M3- PEK. KOLOM BETON (200 KG BESI+BEKISTING) 1 PC:2 PSR: 3 KRL

NO URAIAN PEKERJAAN SATUAN HARGA SATUAN KUANTITAS JUMLAH HARGA


A. TENAGA KERJA
1 PEKERJA ORG/HARI 30000.00 7.3 219000
2 MANDOR ORG/HARI 42000.00 0.25 10500
3 TUKANG BATU ORG/HARI 40000.00 0.35 14000
4 KEPALA TUKANG ORG/HARI 45000.00 0.57 25650
5 TUKANG KAYU ORG/HARI 40000.00 3.30 132000
6 TUKANG BESI ORG/HARI 40000.00 2.1 84000
JUMLAH 485150
B BAHAN
1 PAPAN BEKISTING M3 1000000.00 0.27 270,000.00
2 PAKU CAMPUR KG 15000.00 2 30,000.00
3 MINYAK BEKISTING LTR 17000.00 2.0 34,000.00
4 BESI BETON KG 14000.00 200 2,800,000.00
5 KAWAT BESI KG 15000.00 3 45,000.00
6 SEMEN KG 1200.00 323 387,600.00
7 PASIR BETON M3 141333.00 0.52 73,493.16
8 SUPLIT M3
183503.00 0.78 143,132.34
9 BALOK KAYU M3
1000000.00 0.15 150,000.00
10 DOLKEN DIA 8 CM/4 BTG 6000.00 20 120,000.00
JUMLAH 4,053,225.50
HARGA(A+B) 4,538,375.50

14.1 M3-PEKERJAAN RING BALOK BETON BERTULANG 1PC:2PSR:3KRL

NO URAIAN PEKERJAAN SATUAN HARGA SATUAN KUANTITAS JUMLAH HARGA


A. TENAGA KERJA
1 PEKERJA ORG/HARI 30000.00 0.033 990
2 MANDOR ORG/HARI 42000.00 0.033 1386
3 TUKANG BATU ORG/HARI 40000.00 0.033 1320
4 KEPALA TUKANG ORG/HARI 45000.00 0.01 450
5 TUKANG KAYU ORG/HARI 40000.00 0.10 4000
6 TUKANG BESI ORG/HARI 40000.00 0.005 200
JUMLAH 8346
B BAHAN
1 BALOK KAYU M3 1000000.00 0.02 20,000.00
2 DOLKEN DIA 8 CM/4 BTG 6000.00 3.6 21,600.00
3 KAWAT BESI KG 15000.00 0.05 750.00
4 SEMEN KG 1200.00 5.5 6,600.00
5 PASIR BETON M3 141333.00 0.09 12,719.97
6 SUPLIT M3
183503.00 0.015 2,752.55
7 BALOK KAYU M 3
1000000.00 0.03 30,000.00
8 BESI BETON KG 14000.00 3.6 94,422.52
JUMLAH 188,845.03
HARAG ( A + B ) 197,191.03

6 AFAN MPONIALA E1 B1 06 051


EKONOMI TEKNIK " POS JAGA "

15.1 M2- PEK.PASANGAN BATA MERAH TRANSRAM 1/2 BATA 1PC: 3PSR

NO URAIAN PEKERJAAN SATUAN HARGA SATUAN KUANTITAS JUMLAH HARGA


A. TENAGA KERJA
1 PEKERJA ORG/HARI 30000.00 0.32 9600
2 MANDOR ORG/HARI 42000.00 0.015 630
3 TUKANG BATU ORG/HARI 40000.00 0.1 4000
4 KEPALA TUKANG ORG/HARI 45000.00 0.01 450
JUMLAH 14680
B. BAHAN
1 BATU BATA BIJI 300.00 85.00 25,500.00
2 PASIR PASANG M 3
100000.00 0.04 4,000.00
3 SEMEN KG 1200.00 14.37 17,244.00
JUMLAH 46,744.00
HARGA(A+B) 61,424.00

16.1 M2- PEK.PASANGAN BATA MERAH BIASA 1/2 BATA 1PC: 5PSR

NO URAIAN PEKERJAAN SATUAN HARGA SATUAN KUANTITAS JUMLAH HARGA


A. TENAGA KERJA
1PEKERJA ORG/HARI 30000.00 0.32 9600
2MANDOR ORG/HARI 42000.00 0.015 630
3TUKANG BATU ORG/HARI 40000.00 0.1 4000
4KEPALA TUKANG ORG/HARI 45000.00 0.01 450
JUMLAH 14680
B BAHAN
1 BATU BATA BIJI 300.00 85.00 25,500.00
2 PASIR PASANG M 3
100000.00 0.04 4,000.00
3 SEMEN KG 1200.00 14.37 17,244.00
JUMLAH 46,744.00
HARGA(A+B) 61,424.00

17.1 M2- PEK.PLESTERAN 1PC: 3PSR, TEBAL 15 MM

NO URAIAN PEKERJAAN SATUAN HARGA SATUAN KUANTITAS JUMLAH HARGA


A. TENAGA KERJA
1 PEKERJA ORG/HARI 30000.00 0.2 6000
2 MANDOR ORG/HARI 42000.00 0.01 420
3 TUKANG BATU ORG/HARI 40000.00 0.15 6000
4 KEPALA TUKANG ORG/HARI 45000.00 0.015 675
JUMLAH 13095
B BAHAN
1 PASIR PASANG M3 100000.00 0.019 1,900.00
2 SEMEN KG 1200.00 6.48 7,776.00
JUMLAH 9,676.00
HARGA(A+B) 22,771.00

18.1 M2- PEK.PLESTERAN 1PC: 5PSR, TEBAL 15 MM

7 AFAN MPONIALA E1 B1 06 051


EKONOMI TEKNIK " POS JAGA "
NO URAIAN PEKERJAAN SATUAN HARGA SATUAN KUANTITAS JUMLAH HARGA
A. TENAGA KERJA
1 PEKERJA ORG/HARI 30000.00 0.2 6000
2 MANDOR ORG/HARI 42000.00 0.01 420
3 TUKANG BATU ORG/HARI 40000.00 0.15 6000
4 KEPALA TUKANG ORG/HARI 45000.00 0.015 675
JUMLAH 13095
B BAHAN
1 PASIR PASANG M3 100000.00 0.02 2,000.00
2 SEMEN KG 1200.00 4.32 5,184.00
JUMLAH 7,184.00
HARGA(A+B) 20,279.00

19.1 M2- PEK.LANTAI TEGEL KERAMIK 30 x 30 cm

NO URAIAN PEKERJAAN SATUAN HARGA SATUAN KUANTITAS JUMLAH HARGA


A. TENAGA KERJA
1PEKERJA ORG/HARI 30000.00 0.26 7800
2MANDOR ORG/HARI 42000.00 0.03 1260
3TUKANG BATU ORG/HARI 40000.00 0.35 14000
4KEPALA TUKANG ORG/HARI 45000.00 0.035 1575
JUMLAH 24635
B BAHAN
1 TEGEL 30 x 30 cm BUAH 2600.00 11.87 30,862.00
2 SEMEN KG 1200.00 11.38 13,656.00
3 PASIR M3 100000.00 0.042 4,200.00
4 NAT KG 6325.00 1.5 9,487.50
JUMLAH 58,205.50
HARGA(A+B) 82,840.50

20.1 M2- PEK.LANTAI TEGEL KERAMIK 20 x 20 cm

NO URAIAN PEKERJAAN SATUAN HARGA SATUAN KUANTITAS JUMLAH HARGA


A. TENAGA KERJA
1PEKERJA ORG/HARI 30000.00 0.620 18600
2MANDOR ORG/HARI 42000.00 0.030 1260
3TUKANG BATU ORG/HARI 40000.00 0.35 14000
4KEPALA TUKANG ORG/HARI 45000.00 0.035 1575
JUMLAH 35435
B BAHAN
1 TEGEL 20 x 20 cm BUAH 1600.00 25.0 40,000.00
2 SEMEN KG 1200.00 11.38 13,656.00
3 PASIR M3 100000.00 0.042 4,200.00
4 NAT KG 6325.00 1.5 9,487.50
JUMLAH 67,343.50
HARGA(A+B) 102,778.50

21.1 M2- PEK.LANTAI TEGEL KERAMIK 10 x 10 cm

NO URAIAN PEKERJAAN SATUAN HARGA SATUAN KUANTITAS JUMLAH HARGA


A. TENAGA KERJA
1PEKERJA ORG/HARI 30000.00 0.620 18600
2MANDOR ORG/HARI 42000.00 0.030 1260
3TUKANG BATU ORG/HARI 40000.00 0.35 14000
4KEPALA TUKANG ORG/HARI 45000.00 0.035 1575
JUMLAH 35435
B BAHAN
1 TEGEL 10 x 10 cm BUAH 1000.00 50.0 50,000.00
2 SEMEN KG 1200.00 11.38 13,656.00
3 PASIR M3 100000.00 0.042 4,200.00

8 AFAN MPONIALA E1 B1 06 051


EKONOMI TEKNIK " POS JAGA "
4 NAT KG 6325.00 1.5 9,487.50
JUMLAH 77,343.50
HARGA(A+B) 112,778.50

22.1 M2- PEK.DINDING KERAMIK 20 x 20 cm, 1PC : 3PSR

NO URAIAN PEKERJAAN SATUAN HARGA SATUAN KUANTITAS JUMLAH HARGA


A. TENAGA KERJA
1PEKERJA ORG/HARI 30000.00 0.60 18000
2MANDOR ORG/HARI 42000.00 0.030 1260
3TUKANG BATU ORG/HARI 40000.00 0.10 4000
4KEPALA TUKANG ORG/HARI 45000.00 0.045 2025
JUMLAH 25285
B BAHAN
1 TEGEL 20 x 20 cm BUAH 1600.00 25.0 40,000.00
2 SEMEN ABU-ABU KG 1200.00 9.3 11,160.00
3 PASIR M3 100000.00 0.018 1,800.00
4 NAT KG 6325.00 1.5 9,487.50
JUMLAH 62,447.50
HARGA(A+B) 87,732.50

23.1M2 PEK. RANGKA PLAFOND, BALOK 5/7 KAYU MIRANTI

NO URAIAN PEKERJAAN SATUAN HARGA SATUAN KUANTITAS JUMLAH HARGA


A. TENAGA KERJA
1 PEKERJA ORG/HARI 30000.00 0.15 4500
2 MANDOR ORG/HARI 42000.00 0.075 3150
3 TUKANG KAYU ORG/HARI 40000.00 0.250 10000
4 KEPALA TUKANG ORG/HARI 45000.00 0.025 1125
JUMLAH 18775
B BAHAN
1 KAYU MIRANTI 5/7 M3 896400.00 0.012 10,756.80
2 PAKU BIASA 2'-5' KG 12650.00 0.10 1,265.00
JUMLAH 12,021.80
HARGA(A+B) 30,796.80

24.1M2- PEK. PLAFOND TRIPLEKS(60X100) 5 MM

NO URAIAN PEKERJAAN SATUAN HARGA SATUAN KUANTITAS JUMLAH HARGA


A. TENAGA KERJA
1PEKERJA ORG/HARI 30000.00 0.07 2100
2MANDOR ORG/HARI 42000.00 0.0035 147
3TUKANG KAYU ORG/HARI 40000.00 0.100 4000
4KEPALA TUKANG ORG/HARI 45000.00 0.0100 450
JUMLAH 6697
B BAHAN
1 TRIPLEKS 5MM LBR 42000.00 0.012 504.00
2 PAKU TRIPLEKS KG 20000.00 0.10 2,000.00
JUMLAH 2,504.00
HARGA(A+B) 9,201.00

9 AFAN MPONIALA E1 B1 06 051


EKONOMI TEKNIK " POS JAGA "
25.1M1- PEK. PASA. LIST PLAFOND 5 CM & 1 X 4 C M KAYU SILAE

NO URAIAN PEKERJAAN SATUAN HARGA SATUAN KUANTITAS JUMLAH HARGA


A. TENAGA KERJA
1PEKERJA ORG/HARI 30000.00 0.05 1500
2MANDOR ORG/HARI 42000.00 0.0025 105
3TUKANG KAYU ORG/HARI 40000.00 0.050 2000
4KEPALA TUKANG ORG/HARI 45000.00 0.0050 225
JUMLAH 3830
B BAHAN
1 KAYU PROFIL SILAE LBR 15000.00 1.100 16,500.00
2 PAKU TRIPLEKS KG 20000.00 0.01 200.00
JUMLAH 16,700.00
HARGA(A+B) 20,530.00

26.1M- PEK. KUSEN PINTU DAN VENTILASI ( KAYU KALAPI )

NO URAIAN PEKERJAAN SATUAN HARGA SATUAN KUANTITAS JUMLAH HARGA


A. TENAGA KERJA
1 PEKERJA ORG/HARI 30000.00 6.0 180000
2 MANDOR ORG/HARI 42000.00 0.30 12600
3 TUKANG KAYU ORG/HARI 40000.00 18.0 720000
4 KEPALA TUKANG ORG/HARI 45000.00 2.00 90000
JUMLAH 1002600
B BAHAN
1 KAYU KALAPI M3 1800000.00 1.200 2,160,000.00
HARGA(A+B) 3,162,600.00

27.1M2- PEK. PASANG PINTU PANEL JATI

NO URAIAN PEKERJAAN SATUAN HARGA SATUAN KUANTITAS JUMLAH HARGA


A. TENAGA KERJA
1 PEKERJA ORG/HARI 30000.00 0.8 24000
2 MANDOR ORG/HARI 42000.00 0.04 1680
3 TUKANG KAYU ORG/HARI 40000.00 2.0 80000
4 KEPALA TUKANG ORG/HARI 45000.00 0.20 9000
JUMLAH 114680
B BAHAN
1 PAPAN KAYU JATI M3 1500000.00 0.035 52,500.00
HARGA(A+B) 167,180.00

28.1BH- PEK. PASANG KUNCI TANAM ACHOR 693, LD 2 X PUTAR

NO URAIAN PEKERJAAN SATUAN HARGA SATUAN KUANTITAS JUMLAH HARGA


A. TENAGA KERJA
1PEKERJA ORG/HARI 30000.00 0.06 1800
2MANDOR ORG/HARI 42000.00 0.003 126
3TUKANG KAYU ORG/HARI 40000.00 0.60 24000
4KEPALA TUKANG ORG/HARI 45000.00 0.1 2700
JUMLAH 28626
B BAHAN
1 KUNCI TANAM ACHOR BH 92690.00 1.0 92,690.00
HARGA(A+B) 121,316.00

29.1BH- PASANG ENGSEL PINTU TYPE H

NO URAIAN PEKERJAAN SATUAN HARGA SATUAN KUANTITAS JUMLAH HARGA


A. TENAGA KERJA
1 PEKERJA ORG/HARI 30000.00 0.02 450
2 MANDOR ORG/HARI 42000.00 0.0008 33.6
3 TUKANG KAYU ORG/HARI 40000.00 0.150 6000

10 AFAN MPONIALA E1 B1 06 051


EKONOMI TEKNIK " POS JAGA "
4 KEPALA TUKANG ORG/HARI 45000.00 0.015 675
JUMLAH 7158.6
B BAHAN
1 ENGSEL PINTU TYPE H BH 15000.00 1.0 15,000.00
HARGA(A+B) 22,158.60

30.1BH- PASANG GRENDEL PINTU

NO URAIAN PEKERJAAN SATUAN HARGA SATUAN KUANTITAS JUMLAH HARGA


A. TENAGA KERJA
1PEKERJA ORG/HARI 30000.00 0.02 450
2MANDOR ORG/HARI 42000.00 0.0010 42
3TUKANG KAYU ORG/HARI 40000.00 0.200 8000
4KEPALA TUKANG ORG/HARI 45000.00 0.020 900
JUMLAH 9392
B BAHAN
1 GRENDEL PINTU BH 4000.00 1.0 4,000.00
HARGA(A+B) 13,392.00

31.1M3 -PEK. KONSTRUKSI KUDA-KUDA KAYU KALAPI

NO URAIAN PEKERJAAN SATUAN HARGA SATUAN KUANTITAS JUMLAH HARGA


A. TENAGA KERJA
1 PEKERJA ORG/HARI 30000.00 4.00 120000
2 MANDOR ORG/HARI 42000.00 0.2000 8400
3 TUKANG KAYU ORG/HARI 40000.00 12.000 480000
4 KEPALA TUKANG ORG/HARI 45000.00 1.200 54000
JUMLAH 662400
B BAHAN
1 KAYU KALAPI M3 1800000.00 1.1 1,980,000.00
2 BEGEL,BAUT,ANGKER, BESI KG 20000.00 15 300,000.00
3 PAKU 2'-5' KG 12650.00 0.8 10120
JUMLAH 2,290,120.00
HARGA(A+B) 2,952,520.00

32.1M3- PASANG GORDING ,NOK, JURAI ( DALAM DAN LUAR )

NO URAIAN PEKERJAAN SATUAN HARGA SATUAN KUANTITAS JUMLAH HARGA


A. TENAGA KERJA
1 PEKERJA ORG/HARI 30000.00 0.08 2520
2 MANDOR ORG/HARI 42000.00 0.0040 168
3 TUKANG KAYU ORG/HARI 40000.00 0.125 5000
4 KEPALA TUKANG ORG/HARI 45000.00 0.013 585
JUMLAH 8273
B BAHAN
1 KAYU KALAPI M3 1800000.00 1.1 1,980,000.00
2 PAKU 2'-5' KG 12650.00 0.8 10120
JUMLAH 1,990,120.00
HARGA(A+B) 1,998,393.00

33.1M1- PASANG LIST PLANK ( 2 X 2/ 30 ) CM, KAYU SILAE

NO URAIAN PEKERJAAN SATUAN HARGA SATUAN KUANTITAS JUMLAH HARGA


A. TENAGA KERJA
1 PEKERJA ORG/HARI 30000.00 0.15 4500
2 MANDOR ORG/HARI 42000.00 0.0750 3150
3 TUKANG KAYU ORG/HARI 40000.00 0.250 10000
4 KEPALA TUKANG ORG/HARI 45000.00 0.025 1125
JUMLAH 18775
B BAHAN
1 KAYU SILAE M3 1800000.00 0.0145 26,100.00
2 PAKU CAMPUR KG 15000.00 0.06 900

11 AFAN MPONIALA E1 B1 06 051


EKONOMI TEKNIK " POS JAGA "
JUMLAH 27,000.00
HARGA(A+B) 45,775.00

34.1M3 - PASANG ATAP SENG GELOMBAMG BJLS 20 7 KAKI

NO URAIAN PEKERJAAN SATUAN HARGA SATUAN KUANTITAS JUMLAH HARGA


A. TENAGA KERJA
1PEKERJA ORG/HARI 30000.00 0.12 3600
2MANDOR ORG/HARI 42000.00 0.0060 252
3TUKANG KAYU ORG/HARI 40000.00 0.060 2400
4KEPALA TUKANG ORG/HARI 45000.00 0.006 270
JUMLAH 6522
B BAHAN
1 ATAP SENG BJLS 20 LBR 6785.00 5.120 34,739.20
2 PAKU SENG KG 20000.00 0.02 400
JUMLAH 35,139.20
HARGA(A+B) 41,661.20

35.1M -PEK. PENUTUP ATAP SENG

NO URAIAN PEKERJAAN SATUAN HARGA SATUAN KUANTITAS JUMLAH HARGA


A. TENAGA KERJA
1 PEKERJA ORG/HARI 30000.00 0.10 3000
2 MANDOR ORG/HARI 42000.00 0.0050 210
3 TUKANG KAYU ORG/HARI 40000.00 0.100 4000
4 KEPALA TUKANG ORG/HARI 45000.00 0.010 450
JUMLAH 7660
B BAHAN
1 SENG PLAT BJLS M3 40000.00 0.3000 12,000.00
2 PAKU SENG KG 20000.00 0.04 800
JUMLAH 12,800.00
HARGA(A+B) 20,460.00

36.1M- PEKERJAAN BAK AIR 100 X 120

NO URAIAN PEKERJAAN SATUAN HARGA SATUAN KUANTITAS JUMLAH HARGA


A. TENAGA KERJA
1PEKERJA ORG/HARI 30000.00 2.10 63000
2MANDOR ORG/HARI 42000.00 0.110 4620
3TUKANG BATU ORG/HARI 40000.00 0.750 30000
4KEPALA TUKANG ORG/HARI 45000.00 0.070 3150
JUMLAH 100770
B BAHAN
1 BATA MERAH BH 400.00 1.00 400.00
2 SEMEN KG 1200.00 6 7,200.00
3 PASIR PASANG M3 100000.00 0.01 1000
JUMLAH 8,600.00
HARAG(A+B) 109,370.00

37.1BH- MEMASANG 1 BH KLOSED JONGKOK PORSELIN

NO URAIAN PEKERJAAN SATUAN HARGA SATUAN KUANTITAS JUMLAH HARGA


A. TENAGA KERJA
1PEKERJA ORG/HARI 30000.00 1.00 30000
2MANDOR ORG/HARI 42000.00 0.160 6720
3TUKANG BATU ORG/HARI 40000.00 1.500 60000
4KEPALA TUKANG ORG/HARI 45000.00 1.500 67500
JUMLAH 164220
B BAHAN
1 KLOSED JONGKOK BH 85000.00 1.00 85,000.00

12 AFAN MPONIALA E1 B1 06 051


EKONOMI TEKNIK " POS JAGA "
2 SEMEN KG 1200.00 6 7,200.00
3 PASIR PASANG M3
100000.00 0.01 1000.00
JUMLAH 93,200.00
HARAG(A+B) 257,420.00

38.1BH- MEMASANG 2 BH KRAN AIR

NO URAIAN PEKERJAAN SATUAN HARGA SATUAN KUANTITAS JUMLAH HARGA


A. TENAGA KERJA
1PEKERJA ORG/HARI 30000.00 0.01 300
2MANDOR ORG/HARI 42000.00 0.005 210
3TUKANG BATU ORG/HARI 40000.00 0.100 4000
4KEPALA TUKANG ORG/HARI 45000.00 0.010 450
JUMLAH 4960
B BAHAN
1 KRAN AIR BH 20000.00 1.00 20,000.00
2 SEAL TAPE BH 2500.00 0.025 62.50
JUMLAH 20,062.50
HARAG(A+B) 25,022.50

39.1BH- PEK. FLOOR DRAIN

NO URAIAN PEKERJAAN SATUAN HARGA SATUAN KUANTITAS JUMLAH HARGA


A. TENAGA KERJA
1PEKERJA ORG/HARI 30000.00 0.01 300
2MANDOR ORG/HARI 42000.00 0.005 210
3TUKANG BATU ORG/HARI 40000.00 0.100 4000
4KEPALA TUKANG ORG/HARI 45000.00 0.010 450
JUMLAH 4960
B BAHAN
1 FLOOR DRAIN BH 34000.00 1.00 34,000.00
JUMLAH 34,000.00
HARAG(A+B) 38,960.00

40.1BH- PEMASANGAN TEMPAT SABUN

NO URAIAN PEKERJAAN SATUAN HARGA SATUAN KUANTITAS JUMLAH HARGA


A. TENAGA KERJA
1PEKERJA ORG/HARI 30000.00 0.01 300
2MANDOR ORG/HARI 42000.00 0.005 210
3TUKANG BATU ORG/HARI 40000.00 0.100 4000
4KEPALA TUKANG ORG/HARI 45000.00 0.010 450
JUMLAH 4960
B BAHAN
1 TEMPAT SABUN BH 5000.00 1.00 5,000.00
JUMLAH 5,000.00
HARAG(A+B) 9,960.00

41. 1M1- PEK. INSTALASI AIR BERSIH DARI PDAM

NO URAIAN PEKERJAAN SATUAN HARGA SATUAN KUANTITAS JUMLAH HARGA


A. TENAGA KERJA
1PEKERJA ORG/HARI 30000.00 0.01 300
2MANDOR ORG/HARI 42000.00 0.005 210
3TUKANG LEDENG ORG/HARI 40000.00 0.100 4000
4KEPALA TUKANG ORG/HARI 45000.00 0.010 450
JUMLAH 4960
B BAHAN
1 PIPA PVC Ø 1/2'' M 14000.00 1.00 14,000.00
2 LEM PIPA BH 5000.00 0.01 14,000.00
3 AMPLAS LBR 3000.00 1 18,960.00

13 AFAN MPONIALA E1 B1 06 051


EKONOMI TEKNIK " POS JAGA "
JUMLAH 46,960.00
HARGA( A+ B ) 51,920.00

42. 1M- PEK. INSTALASI AIR KOTOR

NO URAIAN PEKERJAAN SATUAN HARGA SATUAN KUANTITAS JUMLAH HARGA


A. TENAGA KERJA
1PEKERJA ORG/HARI 30000.00 0.01 300
2MANDOR ORG/HARI 42000.00 0.005 210
3TUKANG LEDENG ORG/HARI 40000.00 0.100 4000
4KEPALA TUKANG ORG/HARI 45000.00 0.010 450
JUMLAH 4960
B BAHAN
1 PIPA PVC Ø 4'' M 144000.00 1.00 144,000.00
2 LEM PIPA BH 5000.00 0.01 144,000.00
3 AMPLAS LBR 3000.00 1 148,960.00
JUMLAH 436,960.00
HARGA( A+ B ) 441,920.00

43. 1M3- PEKERJAAN SEPTIC TANK DAN RESAPAN

NO URAIAN PEKERJAAN SATUAN HARGA SATUAN KUANTITAS JUMLAH HARGA


A. TENAGA KERJA
1 PEKERJA ORG/HARI 30000.00 0.04 1200
2 MANDOR ORG/HARI 42000.00 0.005 210
3 TUKANG BATU ORG/HARI 40000.00 0.073 2920
4 KEPALA TUKANG ORG/HARI 45000.00 0.073 3285
JUMLAH 7615
B BAHAN
1 GALIAN TANAH M3 14250.00 4.500 64,125.00
2 PIPA PVC Ø 4'' M 144000.00 1.00 144,000.00
3 LEM PIPA BH 5000.00 0.01 144,000.00
4 PASIR PASANG M3 100000.00 0.21 151,615.00
5 PAS. 1BATA&PLESTER M3 400.00 15 439,615.00
6 GALIAN TANAH M3 14250.00 4.5 64125
7 PASANGAN IJUK M2 7500.00 5.4 40500
8 URUGAN KERIKIL 3,5 M3 115000.00 1.05 120750
9 PIPA PVC Ø 4'' M 144000.00 1 144,000.00
10 URUGAN KEMBALI M3 6900.00 1.13 7,797.00
JUMLAH 1,320,527.00
HARGA ( A + B ) 1,328,142.00

44. 1 UNIT - PENYAMBUNGAN AIR BERSIH DARI PDAM

NO URAIAN PEKERJAAN SATUAN HARGA SATUAN KUANTITAS JUMLAH HARGA


A. TENAGA KERJA
1 PEKERJA ORG/HARI 30000.00 0.01 300
2 MANDOR ORG/HARI 42000.00 0.005 210
3 TUKANG LEDENG ORG/HARI 40000.00 0.100 4000
4 KEPALA TUKANG ORG/HARI 45000.00 0.010 450
JUMLAH 4960
B BAHAN
PDAM LS 3000000.00 0.010 30,000.00
JUMLAH 30,000.00
HARGA ( A+ B ) 34,960.00

45. 1 PEKERJAAN LISTRIK

14 AFAN MPONIALA E1 B1 06 051


EKONOMI TEKNIK " POS JAGA "

NO URAIAN PEKERJAAN SATUAN HARGA SATUAN KUANTITAS JUMLAH HARGA JUMLAH HARGA
A. TENAGA KERJA
1 PEKERJA ORG/HARI 30000.00 0.01 300
2 MANDOR ORG/HARI 42000.00 0.005 210
3 TUKANG LISTRIK ORG/HARI 40000.00 0.100 4000
4 KEPALA TUKANG ORG/HARI 45000.00 0.010 450
JUMLAH 4960
B BAHAN
1 LAMPU PIJAR 25 WATT TITIK 4000.00 0.030 120.00 5,080.00
2 LAMPU TL 60 WATT TITIK 80000.00 0.010 800.00 5,760.00
3 STOP KONTAK BH 14000.00 0.010 140.00 5,100.00
4 SAKLAR GANDA BH 13000.00 0.010 130.00 5,090.00
5 SAKLAR TUNGGAL BH 10000.00 0.020 200.00 5,160.00
6 KOTAK MCB BH 75000.00 0.010 750.00 5,710.00
7 KABEL NYM M 80000.00 2.200 176,000.00 180,960.00
8 FITING PLAFOND BH 12000.00 0.030 360.00 5,320.00
9 PENYA. DAYA PLN UNIT 3000000.00 1.000 3,000,000.00 3,004,960.00
JUMLAH
HARGA ( A+ B ) 3,223,140.00

46. 1M2- PENGECETAN DINDING ( 1 X PLAMIR, 1 X CAT DASAR, 2 X CAT PENUTUP

NO URAIAN PEKERJAAN SATUAN HARGA SATUAN KUANTITAS JUMLAH HARGA


A. TENAGA KERJA
1PEKERJA ORG/HARI 30000.00 0.02 600
2MANDOR ORG/HARI 42000.00 0.0025 105
3TUKANG CAT ORG/HARI 40000.00 0.063 2520
4KEPALA TUKANG ORG/HARI 45000.00 0.006 283.5
JUMLAH 3508.5
B BAHAN
1 PLAMIR KG 5000.00 0.100 500.00
2 CAT DASAR KG 29000.00 0.100 2,900.00
3 CAT TEMBOK 2 X KG 12000.00 0.260 3,120.00
JUMLAH 6,520.00
HARGA ( A+ B ) 10,028.50

47. 1M2- PENGECETAN PLAFOND TRIPLEKS 60 X 100 CM

NO URAIAN PEKERJAAN SATUAN HARGA SATUAN KUANTITAS JUMLAH HARGA


A. TENAGA KERJA
1PEKERJA ORG/HARI 30000.00 0.02 600
2MANDOR ORG/HARI 42000.00 0.0025 105
3TUKANG CAT ORG/HARI 40000.00 0.063 2520
4KEPALA TUKANG ORG/HARI 45000.00 0.006 283.5
JUMLAH 3508.5
B BAHAN
1 CAT PLAFOND KG 5000.00 0.100 500.00
2 KUAS KG 12000.00 0.260 3,120.00
JUMLAH 3,620.00
HARGA ( A+ B ) 7,128.50

48. 1M2- PENGECETAN LIST PLAFOND (PROFI 5 CM & 1 X 4 CM )

NO URAIAN PEKERJAAN SATUAN HARGA SATUAN KUANTITAS JUMLAH HARGA


A. TENAGA KERJA
1 PEKERJA ORG/HARI 30000.00 0.02 600
2 MANDOR ORG/HARI 42000.00 0.0025 105

15 AFAN MPONIALA E1 B1 06 051


EKONOMI TEKNIK " POS JAGA "
3 TUKANG CAT ORG/HARI 40000.00 0.063 2520
4 KEPALA TUKANG ORG/HARI 45000.00 0.006 283.5
JUMLAH 3508.5
B BAHAN
1 LIST PLAFOND KG 11000.00 0.100 1,100.00
2 CAT KG 12000.00 0.260 3,120.00
JUMLAH 4,220.00
HARGA ( A+ B ) 7,728.50

49. 1M2 - PENGECETAN LIST PLANK 2X2/30

NO URAIAN PEKERJAAN SATUAN HARGA SATUAN KUANTITAS JUMLAH HARGA


A. TENAGA KERJA
1PEKERJA ORG/HARI 30000.00 0.02 600
2MANDOR ORG/HARI 42000.00 0.0025 105
3TUKANG CAT ORG/HARI 40000.00 0.063 2520
4KEPALA TUKANG ORG/HARI 45000.00 0.006 283.5
JUMLAH 3508.5
B BAHAN
1 PAPAN KAYU SILAE KG 1500000.00 0.100 150,000.00
2 CAT KG 29000.00 0.260 7,540.00
JUMLAH 157,540.00
HARGA ( A+ B ) 161,048.50

50. 1M2- PENGECETAN KUSEN PINTU DAN VENTILASI ( P-1, P-2, P-3 ) + ( V-1, V-2)

NO URAIAN PEKERJAAN SATUAN HARGA SATUAN KUANTITAS JUMLAH HARGA


A. TENAGA KERJA
1 PEKERJA ORG/HARI 30000.00 0.16 4800
2 MANDOR ORG/HARI 42000.00 0.0025 105
3 TUKANG CAT ORG/HARI 40000.00 0.160 6400
4 KEPALA TUKANG ORG/HARI 45000.00 0.016 720
JUMLAH 12025
B BAHAN
1 VERNIS KAYU LTR 35000.00 0.150 5,250.00
2 DEMPUL KG 12000.00 0.050 600.00
3 AMPELAS LBR 3000.00 0.100 5,850.00
4 KUAS BH 15000.00 0.010 17,875.00
JUMLAH 29,575.00
HARGA (A + B) 41,600.00

51. 1M- PEKERJAAN PLINT KRAMIK 15/30 CM

NO URAIAN PEKERJAAN SATUAN HARGA SATUAN KUANTITAS JUMLAH HARGA


A. TENAGA KERJA
1PEKERJA ORG/HARI 30000.00 0.02 600
2MANDOR ORG/HARI 42000.00 0.0025 105
3TUKANG BATU ORG/HARI 40000.00 0.063 2520
4KEPALA TUKANG ORG/HARI 45000.00 0.006 283.5
JUMLAH 3508.5
B BAHAN
1 TEGEL PLINT 15/30 KG 2124.40 0.100 212.44
2 SEMEN ABU-ABU KG 1200.00 9.300 11,160.00
3 PASIR PASANG M3 100,000.00 0.018 1,800.00
4 NAT KG 6325 1.5 9,487.50
JUMLAH 22,659.94
HARGA ( A+ B ) 26,168.44

16 AFAN MPONIALA E1 B1 06 051


EKONOMI TEKNIK " POS JAGA "

52. 1M2 PEK.PASANG KACA BENING 5 MM PADA VENTILASI

NO URAIAN PEKERJAAN SATUAN HARGA SATUAN KUANTITAS JUMLAH HARGA


A. TENAGA KERJA
1PEKERJA ORG/HARI 30000.00 0.80 24000
2MANDOR ORG/HARI 42000.00 0.040 1680
3TUKANG KAYU ORG/HARI 40000.00 2.000 80000
4KEPALA TUKANG ORG/HARI 45000.00 0.200 9000
JUMLAH 114680
B BAHAN
1 KACA BENING 5 MM M2 120000.00 0.030 3,600.00
2 LIST KACA 1 X 1 CM M 2500.00 0.010 25.00
JUMLAH 3,625.00
HARAG ( A + B ) 118,305.00

17 AFAN MPONIALA E1 B1 06 051


DAFTAR HARGA SATUAN JADI

NO URAIAN PEKERJAAN HARGA

1 1M2- PEKERJAAN PEMBERSIHAN SITE/ LOKASI 2,040.00


2 1M1- PENGUKURAN DAN PEMASANGAN BOUW PLANK 23,119.80
3 1M3- PEK. GALIAN TANAH PONDASI SEDALAM 1 M 13,680.00
4 1M3- PEK. URUGAN KEMBALI KE SISI PONDASI 6,566.40
5 1M3- PEKERJAAN URUGAN TANAH 64,200.00
6 1M3- PEK. URUGAN PASIR 99,420.00
7 1M3- PEK. URUGAN TANAH UNTUK PENINGGIAN LANTAI SETINGGI 30CM 64,200.00
8 1M3- PEK. SALURAN AIR KELILING BANGUNAN ,DIPLESTER+DILICIN 30,559.80
9 1M3- PEK. PASANGAN PONDASI BATU KALI 1PC : 5PSR 424,450.00
10 1M3- PEK. RABAT BETON 1PC : 2PSR : 3KRL 562,847.96
11 1M3- PEKERJAAN PONDASI BATU KOSONG 186,393.00
12 1M3- PEKERJAAN SLOOF (200KG BESI+ BEKISTING ) 1:3 4,083,160.50
13 1M3- PEK. KOLOM BETON (200 KG BESI+BEKISTING) 1 PC:2 PSR: 3 KRL 4,538,375.50
14 1 M3-PEKERJAAN RING BALOK BETON BERTULANG 1PC:2PSR:3KRL 197,191.03
15 1 M2- PEK.PASANGAN BATA MERAH TRANSRAM 1/2 BATA 1PC: 3PSR 61,424.00
16 1 M2- PEK.PASANGAN BATA MERAH BIASA 1/2 BATA 1PC: 5PSR 61,424.00
17 1 M2- PEK.PLESTERAN 1PC: 3PSR, TEBAL 15 MM 22,771.00
18 1 M2- PEK.PLESTERAN 1PC: 5PSR, TEBAL 15 MM 20,279.00
19 1 M2- PEK.LANTAI TEGEL KERAMIK 30 x 30 cm 82,840.50
20 1 M2- PEK.LANTAI TEGEL KERAMIK 20 x 20 cm 102,778.50
21 1 M2- PEK.LANTAI TEGEL KERAMIK 10 x 10 cm 112,778.50
22 1 M2- PEK.DINDING KERAMIK 20 x 20 cm, 1PC : 3PSR 87,732.50
23 1M2 -PEK. RANGKA PLAFOND, BALOK 5/7 KAYU MIRANTI 30,796.80
24 1M2- PEK. PLAFOND TRIPLEKS(60X100) 5 MM 9,201.00
25 1M1- PEK. PASA. LIST PLAFOND 5CM&1X4CM KAYU SILAE 20,530.00
26 1M PEK. KUSEN PINTU DAN VENTILASI (KAYU KALAPI) 3,162,600.00
27 1M2- PEK. PASANG PINTU PANEL JATI 167,180.00
28 1BH- PEK. PASANG KUNCI TANAM ACHOR 693LD 2XPUTAR 121,316.00
29 1BH- PASANG ENGSEL PINTU TYPE H 22,158.60
30 1BH-PASANG GRENDEL PINTU 13,392.00
31 1M3 -PEK. KONSTRUKSI KUDA-KUDA KAYU KALAPI 2,952,520.00
32 1M3- PASANG GORDING ,NOK, JURAI(DALAM DAN LUAR) 1,998,393.00
33 1M1- PASANG LIST PLANK (2X2/30)CM, KAYU SILAE 45,775.00
34 1M3 - PASANG ATAP SENG GELOMBAMG BJLS 20 41,661.20
35 1M PEK.PENUTUP ATAP SENG 20,460.00
36 1M- PEK. BAK AIR 100X 120 109,370.00
37 1BH- MEMASANG 1 BH KLOSED JONGKOK 257,420.00
38 1BH- MEMASANG 2 BH KRAN AIR 25,002.50
39 1BH- PEK. FLOOR DRAIN 38,960.00
40 1BH- PEMASANGAN TEMPAT SABUN 9,960.00
41 1M1- PEK. INSTALASI AIR BERSIH DARI PDAM 51,920.00
42 1M- PEK. INSTALASI AIR KOTOR 441,920.00
43 1M3- PEKERJAAN SEPTIC TANK DAN RESAPAN 1,328,142.00
44 1 UNIT - PENYAMBUNGAN AIR BERSIH DARI PDAM 34,960.00
45 1 PEKERJAAN LISTRIK 3,223,140.00
46 1.M2-PENGECETAN DINDING 10,028.50
47 1M2- PENGECETAN PLAFOND TRIPLEKS 7,128.50
48 1M2- PENGECETAN LIST PLAFOND (PROFIL 5 CM & 1 X 4 CM ) 7,728.50
49 1M2 - PENGECETAN LIST PLANK 2X2/30 161,048.50
50 1M2- PENGECETAN KUSEN PINTU DAN VENTILASI ( P-1, P-2, P-3 + V-1, V-2) 41,600.00
51 1M2- PEKERJAAN TEGEL PLINT 15/30 26,168.44
52 1M2 PEK.PASANG KACA BENING 5 MM PADA VENTILASI 118,305.00
EKONOMI TEKNIK " POS JAGA "

RENCANA ANGGARAN BIAYA ( RAB )


POS JAGA DI KENDARI

NO URAIAN DAN JENIS PEKERJAAN VOLUME SATUAN HARGA JUMLAH


SATUAN HARGA
A. PEKERJAAN PERSIAPAN GALIAN DAN URUGAN
1 PEMBERSIHAN SITE / LOKASI TANAH 48 M2 2,040.00 97,920.00
2 PENGUKURAN DAN PEMASANGAN BOUWPLANK 20 M2 23,119.80 462,396.00
TOTAL 560,316.00

B PEKERJAAN GALIAN TANAH & URUGAN


1 PEK. URUGAN PASIR DIBAWAH PONDASI 1.82 M3 99,420.00 180,944.40
2 PEK. URUGAN PASIR DIBAWAH LANTAI 2.2 M3 99,420.00 218,724.00
3 PEK. URUGAN TANAH KEMBALI KE SISI PONDASI 10 M3 6,566.40 65,302.85
4 PEK. URUGAN TANAH UNTUK PENINGGIAN LANTAI & SISA -2.24 M3 64,200.00 (143,808.00)
5 PEK. GALIAN TANAH PONDASI 19 M3 13,680.00 256,978.80
TOTAL 578,142.05

C PEKERJAAN PASANGAN BATU


1 PEK. PONDASI BATU KALI 7.02 M3 424,450.00 2,979,639.00
2 PEK. RABAT BETON 5.8 M3 562,847.96 3,264,518.17
3 PEK. BATU KOSONG 3.12 M3 186,393.00 581,546.16
4 PEK. SALURAN AIR 9.28 M3 30,559.80 283,594.94
TOTAL 7,109,298.27

D PEKERJAAN BETON BERTULANG


1 PEK. SLOOF BETON UKURAN 15/20, 1PC : 2PSR : 3KRL 0.78 M3 4,083,160.50 3,184,865.19
2 PEK. KOLOM BETON UKURAN 15/15, 1PC : 2PSR : 3KRL 0.855 M3 4,538,375.50 3,880,311.05
3 PEK. RING BALK UKURAN 15/15, 1PC : 2PSR : 3KRL 0.585 M3 197,191.03 115,356.75
TOTAL 7,180,533.00

E PEKERJAAN PASANGAN DINDING


1 PASANGAN DINDING TRASRAM 1PC :3PSR 5.55 M2 61,424.00 340,903.20
2 PASANGAN DINDING BATA MERAH, 1PC: 5PSR 93.05 M2 61,424.00 5,715,503.20
TOTAL 6,056,406.40

F PEKERJAAN PLESTERAN DAN ACI


1 PEK. PLESTERAN DAN ACI, 1PC : 3PSR 21.6 M2 22,771.00 491,853.60
2 PEK. PLESTERAN DAN ACI, 1PC : 5PSR 186.1 M2 20,279.00 3,773,921.90
TOTAL 4,265,775.50

G PEKERJAAN LANTAI KERAMIK


1 PEK. LANTAI KRAMIK RUANG JAGA, 30 x 30 14 M2 82,840.50 1,159,767.00
2 PEK. LANTAI KRAMIK KM/WC, 20 x 20 4 M2 102,778.50 411,114.00
3 PEK. LANTAI KRAMIK RUANG ISTIRAHAT, 10 x 10 4 M2 112,778.50 451,114.00
TOTAL 2,021,995.00

H PEKERJAAN DINDING KRAMIK


1 PEK. DINDING KRAMIK KM/WC, 20 x 20 CM, TINGGI 1,5 M 8.8 M2 87,732.50 772,046.00
2 PEK. PLINT KRAMIK, 15 x 30 CM 15.5 M 26,168.44 405,610.82
3 PEK. DINDING KRAMIK PADA BAK AIR,20 x 20 CM 0.72 M3 87,732.50 63,167.40
TOTAL 1,240,824.22

AFAN MPONIALA E1 B1 06 051


EKONOMI TEKNIK " POS JAGA "

I PEKERJAAN PLAFOND
1 PEK.RANGKA PLAFOND 5/7 47 M2 30,796.80 1,447,449.60
2 PEK. PEMASANGAN TRIPLEKS 47 M2 9,201.00 432,447.00
3 PEK. LIST PLAFOND KAYU 5 CM DI PROFIL 73 M 20,530.00 1,498,690.00
4 PEK. LIST KAYU 1 x 4 CM 48 M 20,530.00 985,440.00
TOTAL 4,364,026.60

J PEKERJAAN KUSEN, PINTU & VENTILASI


1 PEK. KUSEN PINTU( P1, P2, P3)&VENTILASI( V1, V2 ) 0.148 M3 3,162,600.00 468,064.80
2 PEK. DAUN PINTU ( P1,P2,P3 ) 4.39 M2 167,180.00 733,920.20
3 PAS. KACA BENING 5 MM 1 M2 118,305.00 118,305.00
TOTAL 1,320,290.00

K PEKERJAAN PERLENGKAPAN PINTU DAN VENTILASI


1 PAS. KUNCI PANEL TANAM ACHOR 693 LD,2x PUTAR 3 BH 121,316.00 363,948.00
2 PAS. ENGSEL PINTU TYPE H 9 BH 22,158.60 199,427.40
3 PAS. GRENDEL PINTU 3 BH 13,392.00 40,176.00
TOTAL 603,551.40

L PEKERJAAN KUDA - KUDA & KAP


1 PEK. KUDA - KUDA & SEKUR 0.763 M3 2,952,520.00 2,252,772.76
2 PEK. PASANG ATAP SENG BJLS 7 KAKI 52.92 M3 41,661.20 2,204,710.70
3 PEK.PENUTUP ATAP PLAT SENG 0.6048 M3 20,460.00 12,374.21
4 PEK. LIST PLANK 2 X 2/30 0.072 M3 45,775.00 3,295.80
5 PEK. GORDING ,NOK, JURAI( LUAR & DALAM ) 0.35523 M3 1,998,393.00 709,889.15
TOTAL 5,183,042.62

M PEKERJAAN SANITAIR
1 PEK. BAK AIR 1 BH 109,370.00 109,370.00
2 PEK. KLOSED JONGKOK 1 BH 257,420.00 257,420.00
3 PEK. KRAN AIR LUAR & DALAM 1 BH 25,002.50 25,002.50
4 PEK. FLOOR DRAIN 1 BH 38,960.00 38,960.00
5 PAS. TAMPAT SABUN PORSELIN 1 BH 9,960.00 9,960.00
TOTAL 440,712.50

N PEKERJAAN INSTALSI AIR BERSIH & KOTOR


1 PEK. INSTALASI AIR BERSIH 0.15 LS 51,920.00 7,788.00
2 PEK. INSTALASI AIR KOTOR 1.5 LS 441,920.00 662,880.00
3 PEK. SEPTIC TANK & PERESAPAN / REMBESAN 5 M3 1,328,142.00 6,700,476.39
5 PEK. SAMBUNGAN AIR DARI PDAM 1 UNIT 34,960.00 34,960.00
TOTAL 7,406,104.39

O PEKERJAAN INSTALASI LISTRIK 3,223,140.00 3,223,140.00


TOTAL

P PEKERJAAN PENGECETAN / FINISHING


1 PEK. PENGECETAN DINDING 207.7 M2 10,028.50 2,082,919.45
2 PEK. PENGECETAN PLAFOND 47 M2 7,128.50 335,039.50
3 PEK. PENGECETAN LIST PLAFOND 5 CM DI PROFIL 73 M2 7,728.50 935,148.50
4 PEK. PENGECETAN LIST PLAFOND KAYU 1 x 4 CM 48 M2
5 PEK. PENGECETAN LIST PLANK 2 x 2/30 11.2 M2 161,048.50 1,803,743.20
6 PEK. PENGECETAN KUSEN PINTU & VENTILASI 29.5 M2 41,600.00 1,227,200.00
TOTAL 3,030,943.20

AFAN MPONIALA E1 B1 06 051


EKONOMI TEKNIK ' POS JAGA '

REKAPITULASI RENCANA ANGGARAN BIAYA


POS JAGA DI KOTA KENDARI TIPE 21

NO URAIAN DAN JENIS PEKERJAAN JUMLAH HARGA

1 PEKERJAAN PERSIAPAN GALIAN DAN URUGAN Rp 560,316.00


2 PEKERJAAN GALIAN TANAH & URUGAN Rp 578,142.05
3 PEKERJAAN PASANGAN BATU KALI Rp 7,109,298.27
4 PEKERJAAN BETON BERTULANG Rp 7,180,533.00
5 PEKERJAAN PASANGAN DINDING Rp 6,056,406.40
6 PEKERJAAN PLESTERAN DAN ACI Rp 4,265,775.50
7 PEKERJAAN LANTAI KERAMIK Rp 2,021,995.00
8 PEKERJAAN DINDING KRAMIK Rp 1,240,824.22
9 PEKERJAAN PLAFOND Rp 4,364,026.60
10 PEKERJAAN KUSEN, PINTU & VENTILASI Rp 1,320,290.00
11 PEKERJAAN PERLENGKAPAN PINTU DAN VENTILASI Rp 603,551.40
12 PEKERJAAN KUDA - KUDA & KAP Rp 5,183,042.62
13 PEKERJAAN SANITAIR Rp 440,712.50
14 PEKERJAAN INSTALSI AIR BERSIH & KOTOR Rp 7,406,104.39
15 PEKERJAAN INSTALASI LISTRIK Rp 3,223,140.00
16 PEKERJAAN PENGECETAN / FINISHING Rp 3,030,943.20

JUMLAH KESELURUHAN ( REAL COST ) Rp 54,585,101.15


DIBULATKAN Rp 54,585,000.00

TERBILANG @ LIMA PULUH EMPAT JUTA LIMA RATUS DELAPAN PULUH LIMA RIBU RUPIAH

AFAN MPONIALA E1 B1 06 051