Anda di halaman 1dari 9

MENGHITUNG VOLUME

1. PEKERJAAN PERSIAPAN GALIAN DAN URUGAN


A. Pembersihan Site Atau Lokasi Tanah Pembangunan

V=P×l
=8M×6M
= 48 M2
B. Pengukuran Dan Pemasangan Bouwplank

V = ( P × l )2
= ( 6 M + 4 M )2
= 20 M2
C. Galian Tanah Pondasi

V=(a+b)×h
×P
2

= ( 0,7 M + 1M ) × 0,85 M × 26M


2

= 18,785 M3
D. Urugan Pasir Dan Tanah

1). Urugan Pasir Di Bawah Pondasi


V=T×L×P
= 0,1M × 0,70M × 26M1
= 1,82 M3

2). Urugan Pasir Di Bawah Lantai


V=T×L
= 0,10M× 22M2
= 2,2 M3

3. Urugan Tanah Kembali Kesisi Pondasi


V = VGalian Tanah – ( VPAS. Batu Kali + Vurugan Pasir Dibawah Pondasi )
= 18,785M3 – ( 7,02M3 + 1,82M3 )
= 9,945 M3

4. Urugan Tanah Untuk Peninggian Lantai


Peninggian Lantai Adalah 20 Cm Dari Permukaan Tanah
V = ( h × L ) – st
= ( 0,3 M × 22 M2 ) – ( 18,785M3 – 9,945M3 )
= - 2,24 M3 Sisa Tanah

E. Pekerjaan Saluran Air


V = P × L ( ATAS × BAWAH ) × T
= 29 ( 2 × 0,4 ) × 0,4
= 9,28 M3

2. PEKERJAAN PAS. PONDASI


A. Pondasi Batu Kali / Gunung
V=(a+b)×h
×P
2

= ( 0,3 + 0,6 ) 0,6


× 26
2

= 7,02 M3
B. Pek. Rabat beton 1 pc: 2 psr : 3 krl
V=P×L×T
= 29 M × 1M × 0,2 M
= 5,8 M3
C. Pek. Batu kosong
V=P×L×T
= 26M × 0,8M × 0,15M
= 3,12 M3

3. PEK. BETON BERTULANG

A). Sloof Beton Ukuran 15/20 ( 1 Pc : 2 Psr : 3 Krl )


V=b×h×p
= 0,15M × 0,2M × 26M
= 0, 78 M3
B). Kolom Beton Bangunan 15/15 ( 1 Pc : 2 Psr : 3 Krl )
V = b × h × p × ∑KOLOM
= 0,15M × 0,15M × 3,8M × 10 bh
= 0,855 M3
C). Beton Ringbalk 15/15 ( 1 Pc : 2 Psr : 3 Krl )
V=b×h×p
= 0,15M × 0,15M × 26M
= 0,585 M3
D). Spesi Lantai Tebal 5 Cm
V=h×L
= 0,05M × 22 M3
= 1,1 M3

4. PEK. PAS. DINDING

A). Pas. Dinding Bata Merah Trasram 1pc: 3psr


Volume Diatas Sloof 15/30 Cm
V = h × p × L PINTU
= 0,3M × 26M – ( 3 bh × (0,8M + 0,7M ) × 1M × 0,3M
= 5,55 M2
B). Menghitung Volume Trasram Pada Km / Wc 1:3
Setinggi 1 M
V = h × p – Pasangan Pintu ( p × T )
= 1M × 6M – 2,5M × 0,3M
= 5,25 M2
C). Pas. Dinding Bata Merah 1 Pc : 5 Psr
V = ( h × p ) - ∑Lp - ∑Lv
= ( 3,8M × 26M ) – 4,75M2 – 1 M
= 93,05 M2

5. PLESTERAN DAN ACI

A). Plesteran Dan Aci 1 Pc : 3 Psr


( Trasram ) Luar Dan Dalam
∑VBATA = ( V1 × 2 ) + ( V2 × 2 )
= ( 5,55M2 × 2 ) + ( 5,25M2 × 2 )
= 21,6 M2
B). Plesteran Dan Aci 1 Pc : 5 Psr
( Dinding Biasa ) Luar Dan Dalam
V = ( V1 × 2 )
= 93,05 M2 × 2
= 186,1 M2
6. PEK. LANTAI KERAMIK
A). Lantai Kramik Ruang Jaga
Ukuran 30 Cm × 30 Cm
V=P×L
= 4,7M × 3M
= 14 M2
B). Lantai Keramik Dinding Km / Wc
Ukuran 20 Cm × 20 Cm
V=P×L
=2M ×2M
= 4 M2
C). Lantai kramik R. Istirahat
V=p×L
= 2M × 2M
= 4 M2
D). Kramik Pada Dudukan Closed
V = h × LS
= 0,4 M × 0,8 M
= 0,32 M2
7. PEK. DINDING KERAMIK
A). Dinding Keramik
Ukuran 20 Cm × 20 Cm Km / Wc Campuran 1 : 3
V = h × p – Lebar Pintu Km / Wc
= 1,5 M × 8M – 0,7 M
= 8,8 M2
B). Plint Kramik 15/30 Cm Campuran 1 Pc : 3 Psr
V = ∑pk – LEBAR PINTU
= 18 M – 2,5M
= 15,5 M
C). DINDING KRAMIK PADA BAK AIR
V =( P × 2 ) × ( L× 2 ) × T
=( 1,2M × 2 ) × ( 0,15M × 2 ) × 10M
= 0,72 M3

8. PEK. PLAFOND
A). Rangka Plafond
V = ∑Ruang Dipasang Plafond + ∑Bagian Konsol Dipasang Plafond
= ( 3 × 6M) + ( 1 × 29M)
= 47 M2
B). Plafond Tripleks
V = ∑CD + ∑CL
= ( 3 × 6M ) + ( 1 × 29M )
= 47 M2
C). List Plafond Kayu 5 Cm Di Profil
V = ∑PLP
= 73 M1
E). List Kayu 1 × 4 CM
V = ∑PLP
= 48 M
9. PEK. KUSEN, PINTU & VENTILASI
A). Kusen Kayu Pintu ( P1 )
V1 = b × h × P1 ( Pintu Utama )
= 0,05M × 0,15M × 2,0M2
= 0,015 M3
B). Kusen Kayu Pintu ( P2 )
V2 = b × h × p
= 0,05M × 0,15M × 6,4M2
= 0,048M3
C). Kusen Kayu Pintu (P- 3)
V = 0,05M × 0,15M2
= 0,055 M3
D). Ventilasi ( V1 & V2 )
V3 = b × h × p ( V – 2 ) + ( V – 1 )
= 0,05M × 0,15M × 2 M2 + 2 M2
= 0,03 M3
Total Keseluruhan Vtotal = V1 + V2 + V3 + V4 = 0,148 M3
E). Pek. Daun pintu
1. Pek. Daun Pintu Panel Di Ruang Jaga ( P1 )
V1 = I × h × ∑P1
= 1 M × 1,39 M × 1 bh
= 1,39 M2
2. Pek. Daun Pintu Panel ( P2 )
V2 = I × h × ∑P2
= 0,7M × 2M × 1 bh
= 1,4 M2
3. Pek. Pintu Panel ( P3 )
V3 = I × h × ∑P3
= 0,8M × 2 M × 1 bh
= 1,6 M2
TOTAL VP = V1 + V2 + V3
= 1,39 + 1,4 + 1,6
= 4,39 M2
4. Pek. Pemasangan Kaca Ventilasi
V = I × h × ∑V
= 0,5 M × 0,5 M × 4 bh
= 1 M2

10. PEK. PERLENGKAPAN PINTU & JENDELA


A). Kunci Panel Tanam ACHOR 693 LD 2 Kali Putar
V = ( ∑dp × 1 ) SET
= ( 3 × 1 ) SET
= 3 SET
B). Engsel Pintu Tipe H
Volume Engsel Pintu ( 3 Bh Perpintu )
V = ( ∑dp × 3 ) bh
= ( 3 × 3 ) bh
= 9 bh
C). Grendel Pintu
V = ( ∑dp × 1 ) bh
= ( 3 × 1 ) bh
= 3 bh
11. PEK. ATAP

A). Kuda – Kuda Atap


VK1 = h × b × p ( Kaki Kuda – Kuda & Sekur )
= 0,12M × 0,08M × 20 M
= 0,768 M3
B). VK2 = h × b × p ( Balok Kuda – Kuda )
= 0,14M × 0,08M × 40 M
= 0,448 M3

C). VK3 = h × b × p ( Gording & Nok )


= 0,06M × 0,12M × 84M
= 0,6048 M3

D). Bubungan
V=h×b×p
= 0,03M × 0,3 M × 8 M
= 0,072 M3
E). Jurai Luar & Dalam
V = b × h × ∑JR
= 0,08M × 0,12M × 37M
= 0,35523 M3
F). SEKUR
V=h×b×p
= 0,06M × 0,12M × 26 M
= 1,872 M3

12. PEK. SANITAIR


A). Bak Air
V = 1 bh

B). Closed Jongkok


V = 1 bh

C). Kran Air Dalam


V = 1 bh

D). Kran Air Luar


V = 1 bh

E). Floor Drain


V = 1 bh

F). Tempat Sabun


V = 1 bh

13. PEK. INSTALASI AIR


A). Instalasi Air Bersih & Kotor
1). Instalasi Air Bersih
* Volume Pipa Ø 0,5 Inchi = 9,5 M
* Volume Asesoris Lain ( Lem Pipa & Amplas ) = 1 Ls
* Penyambung Pipa Ø 0,15 Inchi = 6 Bh

2). Instalsi Air Kotor


* Volume Pipa Ø 4 Inchi = 9 M
* Asesoris Lain ( Lem Pipa & Amplas ) = 1 Ls
* Penyambung Pipa Ø 4 Inchi = 4 Bh
* Volume Pipa Udara Ø 2 Inchi = 1,5 M
B). Septic Tank
V=p×l×t
= 1,6M × 1M × 2,4M
= 3,92 M3
C). Pembuatan Peresapan
V=(a+b)×h
×P
2

= ( 1 M + 0,5M ) × 1,5 M × 1M
2
= 1,125 M3

D). Penyambungan Air Bersih Dari PDAM


V = 1 Unit

14. PEK. INSTALASI LISTRIK


A). Instalasi Titik Lampu Pijar 25 Watt
V = 3 Titik
B). Instalasi Lampu TL 60 Watt
v = 1 Titik
C). Instalasi Daya Stop Kontak
V = 2 bh
D). Instalasi Daya Saklar Tunggal & Ganda
V = 2 bh Saklar Tunggal
V= 1 bh Saklar Ganda
E). Kotak Mcb
V = 1 bh
F). Kabel Nym
V = 22 M
G). Fiting Lampu
V = 4 bh
H). Penyambungan Daya Listrik Pada PLN
V = 1 LS

15. PEK. PENGECETAN ( FINISHING )


A). Pengecetan Dinding 1 : 3 & 1 : 5
V = 21,6 M2 + 186,1 M2
= 207,7 M2
B). Pengecetan Plafond
V = ∑CD + ∑CL2
= 47 M2
C). Pengecetan List Plafond 5 Cm Di Profil
V = ∑PP
= 73 M3
D). Pengecetan List Plafond Kayu Ukuran 1 × 4 Cm
V = 48 M2

E). Pengecetan List Plant 2 × 30/2


V=P×L
= 28 × 0,4M
= 11,2 M2

E). Pengecetan Kusen Pintu & Ventilasi


1. Pengecetan Kusen Pintu ( P1 )
V=L×K
= 0.2M2 × 6M
= 1.2 M2
2. Pengecetan Kusen ( P2 )
V=L×K
= 0,64M2 × 19,2 M
= 13,184 M2
3. Pengecetan Kusen ( P3)
V=L×K
= 0,66 M2 × 21,4 M
= 14,124 M2
3. Ventilasi ( V1 & V2 )
V=L×K
= 0,4 M2 × 2,4 M
= 0,96 M2
Total Seluruh Finishing Kusen Adalah
V = 29,468 M2