V=P×l
=8M×6M
= 48 M2
B. Pengukuran Dan Pemasangan Bouwplank
V = ( P × l )2
= ( 6 M + 4 M )2
= 20 M2
C. Galian Tanah Pondasi
V=(a+b)×h
×P
2
= 18,785 M3
D. Urugan Pasir Dan Tanah
= 7,02 M3
B. Pek. Rabat beton 1 pc: 2 psr : 3 krl
V=P×L×T
= 29 M × 1M × 0,2 M
= 5,8 M3
C. Pek. Batu kosong
V=P×L×T
= 26M × 0,8M × 0,15M
= 3,12 M3
8. PEK. PLAFOND
A). Rangka Plafond
V = ∑Ruang Dipasang Plafond + ∑Bagian Konsol Dipasang Plafond
= ( 3 × 6M) + ( 1 × 29M)
= 47 M2
B). Plafond Tripleks
V = ∑CD + ∑CL
= ( 3 × 6M ) + ( 1 × 29M )
= 47 M2
C). List Plafond Kayu 5 Cm Di Profil
V = ∑PLP
= 73 M1
E). List Kayu 1 × 4 CM
V = ∑PLP
= 48 M
9. PEK. KUSEN, PINTU & VENTILASI
A). Kusen Kayu Pintu ( P1 )
V1 = b × h × P1 ( Pintu Utama )
= 0,05M × 0,15M × 2,0M2
= 0,015 M3
B). Kusen Kayu Pintu ( P2 )
V2 = b × h × p
= 0,05M × 0,15M × 6,4M2
= 0,048M3
C). Kusen Kayu Pintu (P- 3)
V = 0,05M × 0,15M2
= 0,055 M3
D). Ventilasi ( V1 & V2 )
V3 = b × h × p ( V – 2 ) + ( V – 1 )
= 0,05M × 0,15M × 2 M2 + 2 M2
= 0,03 M3
Total Keseluruhan Vtotal = V1 + V2 + V3 + V4 = 0,148 M3
E). Pek. Daun pintu
1. Pek. Daun Pintu Panel Di Ruang Jaga ( P1 )
V1 = I × h × ∑P1
= 1 M × 1,39 M × 1 bh
= 1,39 M2
2. Pek. Daun Pintu Panel ( P2 )
V2 = I × h × ∑P2
= 0,7M × 2M × 1 bh
= 1,4 M2
3. Pek. Pintu Panel ( P3 )
V3 = I × h × ∑P3
= 0,8M × 2 M × 1 bh
= 1,6 M2
TOTAL VP = V1 + V2 + V3
= 1,39 + 1,4 + 1,6
= 4,39 M2
4. Pek. Pemasangan Kaca Ventilasi
V = I × h × ∑V
= 0,5 M × 0,5 M × 4 bh
= 1 M2
D). Bubungan
V=h×b×p
= 0,03M × 0,3 M × 8 M
= 0,072 M3
E). Jurai Luar & Dalam
V = b × h × ∑JR
= 0,08M × 0,12M × 37M
= 0,35523 M3
F). SEKUR
V=h×b×p
= 0,06M × 0,12M × 26 M
= 1,872 M3
= ( 1 M + 0,5M ) × 1,5 M × 1M
2
= 1,125 M3