Anda di halaman 1dari 73

DAFTAR HARGA SATUAN BAHAN & UPAH TENAGA KERJA

KEGIATAN #REF!
LOKASI #REF!
TAHUN #REF!

Harga
No. Jenis Bahan Satuan Satuan
1 2 3 4

A. Bahan Pasir dan Tanah


1. Pasir Pasang m3 197,000.00
2. Pasir Cor / Beton m3 197,000.00
3. Pasir Urug m3 115,000.00
4. Tanah Urug m3 100,000.00
B. Bahan Batu
1. Batu Kali Pecah 2/3 ( mesin ) m3 249,000.00
2. Batu Bata merah ( kelas I ) bh 650.00
3. Batu Belah 15/20 m3 194,000.00
C. Bahan Semen
1. Semen Warna kg 12,000.00
2. Semen PC SNI 40 kg zak 48,000.00
D. Bahan kapur
1. Kapur Padam Kg 11,500.00
E. Bahan Lantai
1. Lantai keramik polos 40x40 cm m2 42,500.00
2. Lantai keramik motif 20x20 cm m2 48,000.00
3. Dinding keramik motif 20x25 cm m2 50,000.00
F. Bahan Kayu
1. Kayu Kamfer balok 6/15 m3 8,000,000.00
2. Kayu kamfer papan 3/30/300 m3 8,500,000.00
3. Kayu kruing balok 8/12,6/12 m3 5,600,000.00
4. Kayu meranti / berneo balok 8/12, 6/15 m3 4,600,000.00
5. Kayu meranti papan begesting m3 4,850,000.00
6. Kayu kruing usuk 5/7 m3 5,300,000.00
8. Triplek 120,240,6 mm lbr 77,000.00
9. List kayu profil 5cm-1cm m' 12,000.00
10. Bambu bongkotan btg 15,000.00
G. Bahan Besi
1. Besi beton Polos kg 8,500.00
1. Besi strip kg 15,000.00
2. Kawat bendrat kg 12,500.00
3. Paku 2" - 5" kg 12,500.00
4. Talang plat BJLS 28 lbr' 22,000.00
Harga
No. Jenis Bahan Satuan Satuan
1 2 3 4

H. Bahan Penutup
1. Genteng beton bh 3,500.00
2. Bubungan genteng beton bh 6,000.00
3 Asbes Eternit lbr 15,000.00
I. Bahan Cat
1. Plamur tembok kg 29,000.00
2. Plamur kayu " PEDANG " kg 25,000.00
3. Cat kayu / besi EMCO/setara kg 58,500.00
4. Cat tembok "DECOLITH" kg 18,800.00
5. Cat meni "PEDANG" kg 26,000.00
6. Dempul kayu kg 25,000.00
7. Minyak cat / thiner B ltr 22,000.00
8. Lem kayu ltr 12,000.00
9. Residu / Ter ltr 25,000.00
10. Minyak Begisting ltr 6,550.00
11. Ampelas / kertas gosok lbr 3,500.00
12. Kuas cat bh 15,000.00
J. Bahan Kaca
1. Kaca bening 5 mm m2 88,000.00
K. Bahan Accecoris Kusen
1. Kunci tanam bh 61,000.00
2. Engsel pintu bh 22,500.00
3. Engsel jendela bh 16,000.00
4. Grendel pintu / jendela bh 9,000.00
L. Bahan lampu dan instalasi listrik
1. Pasang Instalasi Listrik + Ongkos Pasang ttk 125,000.00
2. Pasang lampu downlight 6" lengkap (lampu+accesoris) bh 200,000.00
3. Lampu SL 15 w PHILIPS + Ongkos Pasang + Accecoris bh 25,000.00
4. Stop Kontak "BROCO" + Ongkos Pasang bh 14,000.00
5. Saklar tunggal "BROCO" + Ongkos Pasang bh 12,500.00
6. Saklar ganda " BROCO " + Ongkos Pasang bh 15,000.00
7. Sekering ganda "LN" bh 17,500.00
8. Panel MCB unit 150,000.00
M. Harga upah tenaga kerja
1. Mandor Org/hr -
2. Kepala Tukang Org/hr -
3. Tukang Batu Org/hr 85,000.00
4. Tukang Kayu Org/hr 85,000.00
5. Tukang Cat Org/hr 85,000.00
6. Tukang Besi Org/hr 85,000.00
7. Pekerja Org/hr 70,000.00
REKAPITULASI PEKERJAAN
ENGINERING ESTIMATE

#REF! #REF!
#REF! #REF!
#REF! #REF!

NO URAIAN PEKERJAAN TOTAL HARGA

I PEKERJAAN PERSIAPAN 500,000.00


II PEKERJAAN TANAH 6,564,563.13
III PEKERJAAN PONDASI 21,499,017.93
IV PEKERJAAN BETON STRUKTUR 20,134,931.00
V PEKERJAAN PASANGAN & PLESTERAN 35,218,880.42
VI PEKERJAAN KUSEN 9,663,236.00
VII PEKERJAAN ATAP 18,109,066.40
VIII PEKERJAAN PLAFOND 10,663,935.00
IX PEKERJAAN LANTAI DAN DINDING 8,245,828.84
X PEKERJAAN PENGECATAN 10,723,214.28
XI PEKERJAAN LISTRIK 3,046,000.00
XII PEKERJAAN SANITASI 3,191,407.50

JUMLAH BIAYA FISIK 147,560,080.50

TOTAL 147,560,080.50

DIBULATKAN 147,560,000.00

Terbilang : Seratus Lima Juta Dua Ratus Tujuh Puluh Tiga Ribu Rupiah

Jombang, Januari 2017


RIZKI BAROKAH DESAIN
RIZKI BAROKAH DESAIN

FERDY ARI CAHYO


Drafner
RENCANA ANGGARAN BIAYA (RAB)
ENGINERING ESTIMATE
HARGA
NO URAIAN PEKERJAAN VOL. SAT SATUAN JUMLAH HARGA
( Rp. ) ( Rp. )
1 2 3 4 5 6

I PEKERJAAN PERSIAPAN
1 Pembongkaran dan pembersihan lokasi 1.00 ls 500,000.00 500,000.00
Sub jumlah 500,000.00

II PEKERJAAN TANAH
1 Galian tanah 94.44 m3 52,500.00 4,957,837.50
2 Urugan tanah kembali 31.48 m3 17,500.00 550,870.83
3 Urugan pasir 4.10 m3 257,400.00 1,055,854.80
Sub jumlah 6,564,563.13

III PEKERJAAN PONDASI


1 Pasangan pondasi rolag bata 10.14 m2 204,289.80 2,071,498.57
2 Pasangan anstampeng 7.41 m3 379,650.00 2,812,447.20
3 Pondasi batu kali 1Pc : 6Ps 25.47 m3 652,467.00 16,615,072.16
Sub jumlah 21,499,017.93

IV PEKERJAAN BETON STRUKTUR


1 Lantai kerja di bawah pondasi 2.25 m3 622,790.00 1,401,277.50
3 Sloof beton 15/25 1.39 m3 3,451,180.00 4,793,689.02
4 Kolom beton 20/20 - m3 2,384,102.90 -
4 Kolom beton 15/15 1.25 m3 3,461,890.00 4,338,613.64
5 Balok beton 15/15 1.60 m3 3,461,890.00 5,525,176.44
8 Konsol 15/30 0.63 m3 3,476,191.48 2,190,000.63
9 Balok beton 15/20 0.57 m3 3,309,076.79 1,886,173.77
9 Plat deck 7 cm - m3 3,029,482.25 -
Sub jumlah 20,134,931.00

V PEKERJAAN PASANGAN & PLESTERAN


1 Pasangan 1/2 bata 1Pc : 3Ps 26.10 m2 99,030.40 2,584,693.44
2 Plesteran 1Pc : 3Ps tebal 15mm 52.20 m2 39,378.60 2,055,562.92
3 Pasangan 1/2 bata 1Pc : 6Ps 176.59 m2 99,409.40 17,554,208.90
4 Plesteran 1Pc : 6Ps tebal 15mm 353.17 m2 36,878.60 13,024,415.16
5 Pasang rooster - bh 25,000.00 -
6. Pasangan batu tempel m2 175,000.00 -
7. Benangan/Tali air - m' 12,387.00 -
Sub jumlah 35,218,880.42

VI PEKERJAAN KUSEN
1 Pasang kusen pintu dan jendela - m3 7,495,000.00 -
2 Pintu PVC 1.00 ls 275,000.00 275,000.00
3 Pasang daun pintu panil 10.08 m2 671,000.00 6,763,680.00
4 Pasang Daun Jendela 2.08 m2 467,600.00 972,608.00
5 Pasang kaca jendela, tebal 5 mm 2.08 m2 110,600.00 230,048.00
3 Pasang jalusi 2/12 - m2 728,775.00 -
6 Pasang kunci tanam biasa 6.00 bh 104,200.00 625,200.00
7 Pasang engsel pintu 9.00 set 36,300.00 326,700.00
HARGA
NO URAIAN PEKERJAAN VOL. SAT SATUAN JUMLAH HARGA
( Rp. ) ( Rp. )
1 2 3 4 5 6
8 Pasang engsel jendela 4.00 set 25,200.00 100,800.00
9 Pasang grendel 10.00 bh 27,400.00 274,000.00
2. Pasang kusen pintu dan jendela m' 64,875.00 -
3. Pasang alluminium strip pintu utama m2 452,175.00 -
4. Pasang kaca pintu, tebal 5 mm m2 110,600.00 -
5. Pasang sanblast kaca pintu m2 45,000.00 -
10 Pasang kait angin 4.00 bh 23,800.00 95,200.00
8. Pasang jendela alluminium strip lebar 8 cm m2 452,175.00 -
13. Pasang bouvenlist alluminium strip lebar 8 cm m2 452,175.00 -
14. Pasang kaca bouvenlist, tebal 5 mm m2 110,600.00 -
15. Pasang kusen dan pintu KM unit 450,000.00 -
16. Pasang rangka dinding pemisah metal stat m2 118,250.00 -
17. Pasang gypsumboard untuk dinding m2 47,906.00 -
18. Pasang kusen jendela partisi m' 64,875.00 -
8 Pasang kaca jendela, tebal 5 mm - m2 110,600.00 -
Sub jumlah 9,663,236.00

VII PEKERJAAN ATAP


1 Pasang kuda-kuda kayu 8/12 - m3 7,755,000.00 -
2 Pasang kuda-kuda kayu lama - m3 1,595,000.00 -
1 Pasang gording kayu 6/12 - m3 7,062,500.00 -
4 Pasang gording kayu lama - m3 1,042,500.00 -
2 Pasang rangka usuk dan reng galvalume 45.00 m2 250,000.00 11,250,000.00
6 Pasang rangka usuk lama dan reng k. kruing - m3 23,100.80 -
3 Pasang atap genteng 71.68 m2 79,375.00 5,689,600.00
8 Pasang atap genteng lama m2 16,875.00 -
4 Pasang genteng bubung kodok 8.00 m2 82,120.80 656,966.40
5 Pasang woodplank 30 cm 20.50 m' 25,000.00 512,500.00
6. Pasang talang Seng m' 90,287.50 -
7. Pasang PVC ø 2,5" untuk air hujan m' 37,980.00 -
8. Pasang listplank kayu 2/20 m' 91,050.00 -
Sub jumlah 18,109,066.40
HARGA
NO URAIAN PEKERJAAN VOL. SAT SATUAN JUMLAH HARGA
( Rp. ) ( Rp. )
1 2 3 4 5 6

VIII PEKERJAAN PLAFOND


1 Pasang langit langit Rangka Aluminium 51.00 m2 144,700.00 7,379,700.00
2 Pasang rangka plafond (1m x 1m) kayu lama - m2 33,000.00 -
2 Pasang plafond kalsibort 9 mm 51.00 m2 49,290.00 2,513,790.00
3 Pasang list plafond 43.90 m' 17,550.00 770,445.00
Sub jumlah 10,663,935.00

IX PEKERJAAN LANTAI DAN DINDING


1. Pasang lantai granit 60/60 m2 233,485.00 -
1 Pasang lantai keramik 40/40 39.47 m2 160,115.00 6,320,139.34
2 Pasang lantai keramik 20/20 11.30 m2 170,415.00 1,925,689.50
4. Pasang dinding keramik 20/25 m2 192,236.00 -
Sub jumlah 8,245,828.84

X PEKERJAAN PENGECATAN
1 Pengecatan dinding baru 405.37 m2 20,961.00 8,496,960.57
2 Pengecatan dinding lama - m2 11,170.00 -
2 Pengecatan plat 4.46 m2 20,961.00 93,460.91
3 Pengecatan plafond 51.00 m2 20,961.00 1,069,011.00
4 Pengecatan kayu baru 26.52 m2 40,120.00 1,063,781.80
6 Pengecatan kayu lama - m2 34,915.00 -
6 Pengecatan genteng lama - m2 23,080.00 -
Sub jumlah 10,723,214.28

XI PEKERJAAN LISTRIK
1 Pasang instalasi listrik 11.00 ls 250,000.00 2,750,000.00
2 Pasang lampu TL - bh 200,000.00 -
2 Pasang lampu SL 7.00 bh 25,000.00 175,000.00
3 Pasang stop kontak 4.00 bh 14,000.00 56,000.00
4 Pasang saklar tunggal 4.00 bh 12,500.00 50,000.00
5 Pasang saklar ganda 1.00 bh 15,000.00 15,000.00
Sub jumlah 3,046,000.00

XII PEKERJAAN SANITASI


1. Pasang wastafel bh 792,250.00 -
2. Pasang kloset duduk unit 1,914,500.00 -
1 Pasang kloset jongkok 1.00 unit 451,700.00 451,700.00
2 Pasang pipa PVC tipe AW ø 3/4" 8.00 m' 18,276.25 146,210.00
3 Pasang pipa PVC tipe AW ø 3" 12.00 m' 74,070.00 888,840.00
6. Pasang pipa PVC tipe AW ø 4" m' 100,255.50 -
7. Pasang Buis beton ø 30 cm m' 108,062.00 -
4 Bak air fiberglass 1.00 bh 400,000.00 400,000.00
5 Pasang kran air 2.00 bh 38,036.25 76,072.50
6 Pasang avour 1.00 bh 28,585.00 28,585.00
11. Pasang floordrain bh 32,200.00 -
7 Pas. Septictank + Resapan 1.00 unit 1,200,000.00 1,200,000.00
Sub jumlah 3,191,407.50
grand total 147,560,080.50
BACK UP VOLUME

### #REF!
### #REF!
### #REF!

NO URAIAN PEKERJAAN PERHITUNGAN VOL. SAT

1 2 3 4 5

I PEKERJAAN PERSIAPAN
1 Pembongkaran dan pembersihan lokasi = 1.00 1.00 ls

II PEKERJAAN TANAH
1 Galian tanah pondasi = 1.75 X 0.80 X 53.63 = 75.08 94.44 m3
= 2.75 X 0.80 X 0.80 X 11.00 = 19.36
= 94.44

2 Urugan tanah kembali = 1/3 X 94.44 = 31.48 31.48 m3

3 Urugan pasir Bawah pondasi = 0.05 X 0.80 X #REF! = 4.10 m3


lantai = 0.05 X 0.80 X 46.30 = 1.85
= 0.05 X 45.00 = 2.25
= 4.10

III PEKERJAAN PONDASI


1 Pasangan pondasi rolag bata 1Pc : 4Ps (teras) = 16.90 X 0.60 10.14 10.14 m2
= 10.14

1 Pasangan anstampeng = 0.20 X 0.80 X #REF! = 7.41 m3


= 0.20 X 0.80 X 46.30 = 7.41
= 7.41

2 Pondasi batu kali 1Pc:6Ps = 0.30 + 0.80 X 1.00 X 46.30 = 25.47 25.47 m3
2.00
= 0.23 + 0.60 X 0.90 X 46.30 =
2.00
= 25.47

IV PEKERJAAN BETON STRUKTUR


1 Lantai kerja = 0.10 X 0.50 X 0.50 X - = - 2.25 m3
lantai = 0.05 X 45.00 = 2.25
= 2.25

2 Pondasi beton 50/50/20 = 0.50 X 0.50 X 0.20 X - = - - m3

3 Sloof beton 15/20 = 0.15 X 0.20 X 46.30 = 1.39 1.39 m3

5 Kolom beton 15/15 = 0.15 X 0.15 X 3.95 X 12.00 = 1.07 1.25 m3


teras = 0.15 X 0.15 X 3.55 X 1.00 =
gewel = 0.15 X 0.15 X 4.15 X 2.00 = 0.19
= 1.25

8 Balok beton 15/15 Ring balk = 0.15 X 0.20 X 46.30 = 1.39 1.60 m3
Ring gewel = 0.15 X 0.15 X 4.00 X 1.00 = 0.09
Ring gewel = 0.15 X 0.15 X 5.20 X 1.00 = 0.12
= 1.60

10 Lisplank beton t:7cm = X 0.07 X 4.46 = 0.31 0.31 m3

V PEKERJAAN PASANGAN & PLESTERAN


1 Pasangan 1/2 bata 1Pc : 3Ps = 0.40 X 92.60 = 37.04 26.10 m2
= 37.04

2 Plesteran 1Pc : 3Ps tebal 15mm = 2.00 X 26.10 = 52.20 52.20 m2

3 Pasangan 1/2 bata 1Pc : 6Ps = 3.05 X 92.60 = 282.43 176.59 m2


gewel = 0.50 X 4.00 X 1.15 X 1.00 = 2.30
gewel = 0.50 X 5.50 X 1.70 X 2.00 = 4.68
= 0.30 X 19.50 X 1.00 = 5.85
dikurangi pintu jendela = 10.88 + 1.44 + 5.46 = 17.78
= 277.48

4 Plesteran 1Pc : 6Ps tebal 15mm = 2.00 X 176.59 = 353.17 353.17 m2


= 353.17
NO URAIAN PEKERJAAN PERHITUNGAN VOL. SAT

1 2 3 4 5
VI PEKERJAAN KUSEN
1 Pasang kusen pintu dan jendela
P1 = 4.92 X 4.00 X 0.06 X 0.15 = 0.18 m3
J1 = 6.36 X 3.00 X 0.06 X 0.15 = 0.17
BV 1 = 1.84 X 1.00 X 0.06 X 0.15 = 0.02
= 0.35

2 Pintu PVC = 1.00 = 1.00 1.00 ls

3 Pasang daun pintu panil = 0.80 X 2.10 X 6.00 = 10.08 10.08 m2

4 Pasang Daun Jendela = 0.40 X 1.30 X 4.00 = 2.08 2.08 m2

5 Pasang kaca tebal 5 mm 2.08 m2


P1 = 0.15 X 1.20 X 1.00 = 0.18
J1 = 0.40 X 1.30 X 2.00 X 3.00 = 3.12
BV 1 = 0.30 X 0.40 X 2.00 X 1.00 = 0.24
= 3.54

6 Pasang kunci tanam biasa = 6.00 6.00 bh

7 Pasang engsel pintu = 3.00 X 6.00 = 18.00 bh 9.00 set


2.00
9.00 set

8 Pasang engsel jendela = 2.00 X 4.00 = 8.00 bh 4.00 set


2.00
4.00 set

9 Pasang kait angin = 2.00 X 4.00 = 8.00 bh 4.00 set


2.00
4.00 set

10 Pasang grendel = 6.00 + 4.00 = 10.00 10.00 bh

VII PEKERJAAN ATAP


3 Pasang gording kayu kruing 6/12 = 6.00 X 5.00 X 0.08 X 0.12 = 0.29 m3

5 Pasang rangka usuk dan reng galvalum = 17.76 + 11.52 + 13.44 = 42.72 m2

6 Pasang atap genteng kodok = 71.68 71.68 m2

7 Pasang genteng bubung kodok = 8.00 = 8.00 8.00 m'

8 Pasang woodplank 30 cm = 8.00 X 2.00 + 4.50 = 20.50 20.50 m'

VIII PEKERJAAN PLAFON


1 Pasang rangka plafond Galvalume = 4.00 X 3.00 + 5.50 X 3.00 = 45.00 51.00 m2
tritisan samping = 0.50 X 12.00 = 6.00
= 51.00

2 Pasang plafond Kalsibord 9 mm = 51.00 + - = 51.00 51.00 m2

3 Pasang list plafond = 22.10 + 10.40 + 11.40 = 43.90 43.90 m'

IX PEKERJAAN LANTAI DAN DINDING


1 Pasang lantai keramik 40/40 = 6.70 + 8.12 + 24.65 = 39.47 39.47 m2

2 Pasang lantai keramik 20/20 = 1.50 X 1.50 = 2.25 11.30 m2


NO URAIAN PEKERJAAN PERHITUNGAN VOL. SAT

1 2 3 4 5
IX PEKERJAAN PENGECATAN
1 Pengecatan dinding baru
dinding = 353.17 + 52.20 = 405.37 405.37 m2
= 405.37

3 Pengecatan plat = 0.31 : 0.07 = 4.46 4.46 m2


4.46

4 Pengecatan plafond = 51.00 51.00 m2

5 Pengecatan kayu kusen = 0.27 X - / 0.06 / 0.15 = - 26.52 m2


daun pintu = 10.08 X 2.00 = 20.16
daun jendela = 2.08 X 2.00 = 4.16
lis plafond = 43.90 X 0.05 = 2.20
woodplank = 20.50 X 0.30 =
= 26.52

X PEKERJAAN LISTRIK
1 Pasang instalasi listrik = 11.00 11.00 ls

2 Pasang lampu SL = 7.00 7.00 bh

3 Pasang stop kontak = 4.00 4.00 bh

4 Pasang saklar ganda = 1.00 1.00 bh

5 Pasang saklar Tunggal = 4.00 4.00 bh

X PEKERJAAN SANITASI
1 Pasang kloset jongkok = 1.00 1.00 ls
2 Pasang pipa PVC tipe AW ø 3/4" = 8.00 8.00 m'
3 Pasang pipa PVC tipe AW ø 3" = 12.00 12.00 m'
4 Bak air fiberglass = 1.00 1.00 bh
5 Pasang kran air = 2.00 2.00 bh
6 Pasang avour = 1.00 1.00 bh
7 Pas. Septictank + Resapan = 1.00 1.00 bh
PEKERJAAN TANAH

۞ 1 m3 Galian Untuk Tanah Biasa sedalam 1 m


Upah An. SNI 6.1
0.750 Oh Pekerja @ Rp. 70,000.00 = Rp. 52,500.00
0.025 Oh Mandor @ Rp. - = Rp. -
= Rp. 52,500.00

۞ 1 m3 Urugan Pasir Pasang


Bahan An. SNI 6.11
1.200 m3 Pasir Pasang @ Rp. 197,000.00 = Rp. 236,400.00
= Rp. 236,400.00

Upah An. SNI 6.11


0.300 Oh Pekerja @ Rp. 70,000.00 = Rp. 21,000.00
0.010 Oh Mandor @ Rp. - = Rp. -
= Rp. 21,000.00

Total Upah dan Bahan = Rp. 257,400.00

۞ 1 m3 Mengurug kembali tanah galian


Upah ( SNI 2835:2008 ) 6.9
0.250 oh Pekerja @ Rp. 70,000.00 = Rp. 17,500.00
0.008 oh Mandor @ Rp. - = Rp. -
Total Harga = Rp. 17,500.00
PEKERJAAN PONDASI

۞ 1 m3 Pasang pondasi batu kosong


Bahan An. SNI 6.1
1.200 m3 Batu belah ( 15/20 ) @ Rp. 194,000.00 = Rp 232,800.00
0.300 m3 Pasir pasang @ Rp. 197,000.00 = Rp 59,100.00
= Rp 291,900.00

Upah An. SNI 6.1


0.780 Oh Pekerja @ Rp. 70,000.00 = Rp 54,600.00
0.390 Oh Tukang batu @ Rp. 85,000.00 = Rp 33,150.00
0.039 Oh Kepala tukang @ Rp. - = Rp -
0.039 Oh Mandor @ Rp. - = Rp -
= Rp 87,750.00
Total harga = Rp 379,650.00

۞ 1 m3 Pasang pondasi batu belah 1 Pc : 6 Ps


Bahan An. SNI 6.4 `
1.200 m3 Batu belah ( 15/20 ) @ Rp. 194,000.00 = Rp 232,800.00
117.000 Kg Semen porland @ Rp. 1,200.00 = Rp 140,400.00
0.561 m3 Pasir pasang @ Rp. 197,000.00 = Rp 110,517.00
= Rp 483,717.00

Upah An. SNI 6.4


1.500 Oh Pekerja @ Rp. 70,000.00 = Rp 105,000.00
0.750 Oh Tukang batu @ Rp. 85,000.00 = Rp 63,750.00
0.075 Oh Kepala tukang @ Rp. - = Rp -
0.075 Oh Mandor @ Rp. - = Rp -
= Rp 168,750.00
Total harga = Rp 652,467.00
PEKERJAAN PASANGAN

۞ 1 m2 Pasangan bata merah tebal 1 bata, 1 Pc : 4 Ps


Bahan An. SNI 6.3
140.000 Bh Bata merah 5 x 11 x 22 cm @ Rp. 650.00 = Rp 91,000.00
26.550 Kg Semen portland @ Rp. 1,200.00 = Rp 31,860.00
0.093 m3 Pasir pasang @ Rp. 197,000.00 = Rp 18,321.00
= Rp 141,181.00
Upah An. SNI 6.3
0.600 Oh Pekerja @ Rp. 70,000.00 = Rp 42,000.00
0.200 Oh Tukang batu @ Rp. 85,000.00 = Rp 17,000.00
0.020 Oh Kepala tukang @ Rp. - = Rp -
0.030 Oh Mandor @ Rp. - = Rp -
= Rp 59,000.00
Total harga = Rp 200,181.00

۞ 1 m2 Pasangan bata merah tebal 1/2 bata, 1 Pc : 3 Ps


Bahan An. SNI 6.8
70.000 Bh Bata merah 5 x 11 x 22 cm @ Rp. 650.00 = Rp 45,500.00
14.370 Kg Semen portland @ Rp. 1,200.00 = Rp 17,244.00
0.040 m3 Pasir pasang @ Rp. 197,000.00 = Rp 7,880.00
= Rp 70,624.00
Upah An. SNI 6.9
0.300 Oh Pekerja @ Rp. 70,000.00 = Rp 21,000.00
0.100 Oh Tukang batu @ Rp. 85,000.00 = Rp 8,500.00
0.010 Oh Kepala tukang @ Rp. - = Rp -
0.015 Oh Mandor @ Rp. - = Rp -
= Rp 29,500.00
Total harga = Rp 100,124.00
Total harga/m3 = Rp 834,366.67

۞ 1 m2 Pasangan bata merah tebal 1/2 bata, 1 Pc : 6 Ps


Bahan An. SNI 6.11
70.000 Bh Bata merah 5 x 11 x 22 cm @ Rp. 650.00 = Rp 45,500.00
8.320 Kg Semen portland @ Rp. 1,200.00 = Rp 9,984.00
0.049 m3 Pasir pasang @ Rp. 197,000.00 = Rp 9,653.00
= Rp 65,137.00
Upah An. SNI 6.11
0.300 Oh Pekerja @ Rp. 70,000.00 = Rp 21,000.00
0.100 Oh Tukang batu @ Rp. 85,000.00 = Rp 8,500.00
0.010 Oh Kepala tukang @ Rp. - = Rp -
0.015 Oh Mandor @ Rp. - = Rp -
= Rp 29,500.00

Total harga = Rp 94,637.00


۞ 1 m2 Plesteran, 1 Pc : 3 Ps, tebal 15 mm
Bahan An. SNI ( Revisi ) 6.3.1
6.480 Kg Semen portland @ Rp. 1,200.00 = Rp 7,776.00
0.019 m3 Pasir pasang @ Rp. 197,000.00 = Rp 3,743.00
= Rp 11,519.00
Upah An. SNI 6.4
0.300 Oh Pekerja @ Rp. 70,000.00 = Rp 21,000.00
0.150 Oh Tukang batu @ Rp. 85,000.00 = Rp 12,750.00
0.015 Oh Kepala tukang @ Rp. - = Rp -
0.015 Oh Mandor @ Rp. - = Rp -
= Rp 33,750.00
Total harga = Rp 45,269.00

۞ 1 m2 Plesteran, 1 Pc : 6 Ps, tebal 15 mm


Bahan An. SNI ( Revisi ) 6.6.1
3.680 Kg Semen portland @ Rp. 1,200.00 = Rp 4,416.00
0.023 m3 Pasir pasang @ Rp. 197,000.00 = Rp 4,531.00
= Rp 8,947.00
Upah An. SNI ( Revisi ) 6.6.2
0.200 Oh Pekerja @ Rp. 70,000.00 = Rp 14,000.00
0.150 Oh Tukang batu @ Rp. 85,000.00 = Rp 12,750.00
0.015 Oh Kepala tukang @ Rp. - = Rp -
0.010 Oh Mandor @ Rp. - = Rp -
= Rp 26,750.00
Total harga = Rp 35,697.00
PEKERJAAN LANGIT - LANGIT

1. 1 m2 Pasang langit-langit rangka alluminium


Bahan Membuat (An. SNI 6.9)
3.600 m' Profil alluminium T @ Rp. 18,000.00 = Rp
0.150 Kg Kawat diameter 4 mm @ Rp. 5,500.00 = Rp
1.050 Bh Ramset/dinabolt @ Rp. 1,500.00 = Rp
= Rp
Upah Membuat (An. SNI 6.9)
0.500 Oh Pekerja @ Rp. 70,000.00 = Rp
0.500 Oh Tukang kayu @ Rp. 85,000.00 = Rp
0.050 Oh Kepala tukang @ Rp. - = Rp
0.025 Oh Mandor @ Rp. - = Rp
= Rp

Total harga = Rp

2. 1 m2 Pasang langit-langit gypsum board, tebal 9 mm


Bahan An. SNI 6.7
0.364 Lbr Gypsum board ( 120x240x9 mm ) @ Rp. 90,000.00 = Rp
0.110 Kg Paku sekrup @ Rp. 48,000.00 = Rp
= Rp
Upah An. SNI 6.7
0.100 Oh Pekerja @ Rp. 70,000.00 = Rp
0.050 Oh Tukang kayu @ Rp. 85,000.00 = Rp
0.005 Oh Kepala tukang @ Rp. - = Rp
0.005 Oh Mandor @ Rp. - = Rp
= Rp

Total harga = Rp

3. 1 m' Pasang list langit-langit gypsum profil


Bahan An. SNI 6.8
1.050 m' List gypsum profil @ Rp. 7,500.00 = Rp
0.150 Kg Tepung gypsum @ Rp. 2,500.00 = Rp
= Rp
Upah An. SNI 6.8
0.060 Oh Pekerja @ Rp. 70,000.00 = Rp
0.060 Oh Tukang kayu @ Rp. 85,000.00 = Rp
0.006 Oh Kepala tukang @ Rp. - = Rp
0.003 Oh Mandor @ Rp. - = Rp
= Rp

Total harga = Rp
64,800.00
825.00
1,575.00
67,200.00

35,000.00
42,500.00
-
-
77,500.00

144,700.00

32,760.00
5,280.00
38,040.00

7,000.00
4,250.00
-
-
11,250.00

49,290.00

7,875.00
375.00
8,250.00

4,200.00
5,100.00
-
-
9,300.00

17,550.00
PEKERJAAN KUSEN

۞ 1 m3 Pasang kusen pintu & jendela kayu kelas II


Bahan An. SNI 6.2
1.200 m3 Kayu kamper, balok @ Rp. 8,000,000.00 = Rp 9,600,000.00
1.250 Kg Paku 10 cm @ Rp. 12,500.00 = Rp 15,625.00
1.000 Kg Lem kayu @ Rp. 12,000.00 = Rp 12,000.00
= Rp 9,627,625.00
Upah An. SNI 6.2
6.000 Oh Pekerja @ Rp. 70,000.00 = Rp 420,000.00
18.000 Oh Tukang kayu @ Rp. 85,000.00 = Rp 1,530,000.00
1.800 Oh Kepala tukang @ Rp. - = Rp -
0.300 Oh Mandor @ Rp. - = Rp -
= Rp 1,950,000.00
Total harga = Rp 11,577,625.00

۞ 1 m2 Pasang pintu panil kayu kamper


Bahan An. SNI 6.6
0.040 m3 Kayu kamper, papan @ Rp. 8,500,000.00 = Rp 340,000.00
0.500 Kg Lem kayu @ Rp. 12,000.00 = Rp 6,000.00
= Rp 346,000.00
Upah An. SNI 6.6
1.000 Oh Pekerja @ Rp. 70,000.00 = Rp 70,000.00
3.000 Oh Tukang kayu @ Rp. 85,000.00 = Rp 255,000.00
0.300 Oh Kepala tukang @ Rp. - = Rp -
0.050 Oh Mandor @ Rp. - = Rp -
= Rp 325,000.00
Total harga = Rp 671,000.00

۞ 1 m2 Pasang pintu & jendela kaca kayu kelas II


Bahan An. SNI 6.6
0.024 m3 Kayu kamper, papan @ Rp. 8,500,000.00 = Rp 204,000.00
0.300 Kg Lem kayu @ Rp. 12,000.00 = Rp 3,600.00
= Rp 207,600.00
Upah An. SNI 6.6
0.800 Oh Pekerja @ Rp. 70,000.00 = Rp 56,000.00
2.400 Oh Tukang kayu @ Rp. 85,000.00 = Rp 204,000.00
0.240 Oh Kepala tukang @ Rp. - = Rp -
0.040 Oh Mandor @ Rp. - = Rp -
= Rp 260,000.00
Total harga = Rp 467,600.00

۞ 1 m2 pasang kaca, tebal 5 mm


Bahan An. SNI 6.17.1
1.100 m2 Kaca tebal 5 mm @ Rp. 88,000.00 = Rp 96,800.00
= Rp 96,800.00
Upah An. SNI 6.17.2
0.015 Oh Pekerja @ Rp. 70,000.00 = Rp 1,050.00
0.150 Oh Tukang kayu @ Rp. 85,000.00 = Rp 12,750.00
0.015 Oh Kepala tukang @ Rp. - = Rp -
0.00075 Oh Mandor @ Rp. - = Rp -
= Rp 13,800.00
Total harga = Rp 110,600.00
۞ 1 buah pasang kunci tanam biasa
Bahan An. SNI 6.2.1
1.000 Bh Kunci tanam biasa @ Rp. 61,000.00 = Rp 61,000.00
= Rp 61,000.00
Upah An. SNI 6.2.2
0.010 Oh Pekerja @ Rp. 70,000.00 = Rp 700.00
0.500 Oh Tukang kayu @ Rp. 85,000.00 = Rp 42,500.00
0.010 Oh Kepala tukang @ Rp. - = Rp -
0.005 Oh Mandor @ Rp. - = Rp -
= Rp 43,200.00
Total harga = Rp 104,200.00

۞ 1 buah pasang engsel pintu


Bahan An. SNI 6.5.1
1.000 Bh Engsel pintu @ Rp. 22,500.00 = Rp 22,500.00
= Rp 22,500.00
Upah An. SNI 6.5.2
0.015 Oh Pekerja @ Rp. 70,000.00 = Rp 1,050.00
0.150 Oh Tukang kayu @ Rp. 85,000.00 = Rp 12,750.00
0.015 Oh Kepala tukang @ Rp. - = Rp -
0.00075 Oh Mandor @ Rp. - = Rp -
= Rp 13,800.00
Total harga = Rp 36,300.00

۞ 1 buah pasang engsel jendela kupu-kupu


Bahan An. SNI 6.6.1
1.000 Bh Engsel jendela @ Rp. 16,000.00 = Rp 16,000.00
= Rp 16,000.00
Upah An. SNI 6.6.2
0.010 Oh Pekerja @ Rp. 70,000.00 = Rp 700.00
0.100 Oh Tukang kayu @ Rp. 85,000.00 = Rp 8,500.00
0.010 Oh Kepala tukang @ Rp. - = Rp -
0.0005 Oh Mandor @ Rp. - = Rp -
= Rp 9,200.00
Total harga = Rp 25,200.00

۞ 1 buah pasang kait angin


Bahan An. SNI 6.9.1
1.000 Bh Kait angin @ Rp. 10,000.00 = Rp 10,000.00
= Rp 10,000.00
Upah An. SNI 6.9.2
0.015 Oh Pekerja @ Rp. 70,000.00 = Rp 1,050.00
0.150 Oh Tukang kayu @ Rp. 85,000.00 = Rp 12,750.00
0.015 Oh Kepala tukang @ Rp. - = Rp -
0.00075 Oh Mandor @ Rp. - = Rp -
= Rp 13,800.00
Total harga = Rp 23,800.00
۞ 1 buah pasang kunci selot
Bahan An. SNI 6.11.1
1.000 Bh Kunci selot @ Rp. 9,000.00 = Rp 9,000.00
= Rp 9,000.00
Upah An. SNI 6.11.2
0.020 Oh Pekerja @ Rp. 70,000.00 = Rp 1,400.00
0.200 Oh Tukang kayu @ Rp. 85,000.00 = Rp 17,000.00
0.020 Oh Kepala tukang @ Rp. - = Rp -
0.001 Oh Mandor @ Rp. - = Rp -
= Rp 18,400.00
Total harga = Rp 27,400.00
PEKERJAAN LANGIT - LANGIT

۞ 1 m2 Pasang rangka langit-langit ( 1.00 x 1.00 ) m, kayu borneo


Bahan An. SNI ( Revisi ) 6.40.1
0.012 m3 Kayu borneo, balok @ Rp. 4,600,000.00 = Rp 55,200.00
0.100 Kg Paku biasa 2" - 5" @ Rp. 12,500.00 = Rp 1,250.00
= Rp 56,450.00
Upah An. SNI ( Revisi ) 6.40.2
0.150 Oh Pekerja @ Rp. 70,000.00 = Rp 10,500.00
0.250 Oh Tukang kayu @ Rp. 85,000.00 = Rp 21,250.00
0.025 Oh Kepala tukang @ Rp. - = Rp -
0.075 Oh Mandor @ Rp. - = Rp -
= Rp 31,750.00
Total harga = Rp 88,200.00

۞ 1 m2 Pasang langit-langit asbes ( 1.00 x 1.00 ) m, tebal 4, 5, 6 mm


Bahan An. SNI 6.1
1.100 Lbr Asbes langit-langit @ Rp. 15,000.00 = Rp 16,500.00
0.010 Kg Paku @ Rp. 12,500.00 = Rp 125.00
= Rp 16,625.00
Upah An. SNI 6.1
0.030 Oh Pekerja @ Rp. 70,000.00 = Rp 2,100.00
0.070 Oh Tukang kayu @ Rp. 85,000.00 = Rp 5,950.00
0.007 Oh Kepala tukang @ Rp. - = Rp -
0.004 Oh Mandor @ Rp. - = Rp -
= Rp 8,050.00
Total harga = Rp 24,675.00

۞ 1 m' Pasang list langit-langit kayu profil


Bahan An. SNI 6.10
1.050 m' List kayu profil @ Rp. 12,000.00 = Rp 12,600.00
0.010 Kg Paku @ Rp. 12,500.00 = Rp 125.00
= Rp 12,725.00
Upah An. SNI 6.10
0.050 Oh Pekerja @ Rp. 70,000.00 = Rp 3,500.00
0.050 Oh Tukang kayu @ Rp. 85,000.00 = Rp 4,250.00
0.005 Oh Kepala tukang @ Rp. - = Rp -
0.003 Oh Mandor @ Rp. - = Rp -
= Rp 7,750.00
Total harga = Rp 20,475.00
PEKERJAAN BETON

1. 1 m3 Membuat Lantai kerja Beton mutu F'c = 7.4 Mpa ( K 100 ), Slump ( 3-6 ) Cm, w/c = 0.87
Bahan An. SNI 6.4
4.600 Zak Semen portland @ Rp. 48,000.00 = Rp 220,800.00
0.638 m3 Pasir beton @ Rp. 197,000.00 = Rp 125,657.86
0.761 m3 Kerikil ( Maksimum 30 mm ) @ Rp. 249,000.00 = Rp 189,424.44
200.000 lt Air @ Rp. - = Rp -
= Rp 535,882.30
Upah An. SNI 6.4
1.200 Oh Pekerja @ Rp. 70,000.00 = Rp 84,000.00
0.200 Oh Tukang batu @ Rp. 85,000.00 = Rp 17,000.00
0.020 Oh Kepala tukang @ Rp. - = Rp -
0.060 Oh Mandor @ Rp. - = Rp -
= Rp 101,000.00
Total harga = Rp 636,882.30

2. 1 m3 Membuat Beton mutu F'c = 19.3 MPa ( K 225 ), Slump ( 12 ± 2 ) Cm, w/c = 0.58
Bahan An. SNI 6.7
371.000 Kg Semen portland @ Rp. 1,200.00 = Rp 445,200.00
0.499 m3 Pasir beton @ Rp. 197,000.00 = Rp 98,218.57
0.776 m3 Kerikil ( Maksimum 30 mm ) @ Rp. 249,000.00 = Rp 193,113.33
215 Liter Air @ Rp. - = Rp -
= Rp 736,531.90
Upah An. SNI 6.7
1.650 Oh Pekerja @ Rp. 70,000.00 = Rp 115,500.00
0.275 Oh Tukang batu @ Rp. 85,000.00 = Rp 23,375.00
0.028 Oh Kepala tukang @ Rp. - = Rp -
0.083 Oh Mandor @ Rp. - = Rp -
= Rp 138,875.00
Total harga = Rp 875,406.90

1 kg Memasang besi profil


Bahan ( SNI 7393:2008 ) 6.1
1.150 kg Besi profil @ Rp. 15,000.00 = Rp. 17,250.00
Biaya Pengelasan + Perakitan 2% = Rp. 345.00
Total bahan = Rp. 17,595.00

Upah ( SNI 7393:2008 ) 6.1


0.060 oh Pekerja @ Rp. 70,000.00 = Rp. 4,200.00
0.060 oh Tukang las konstruksi @ Rp. 85,000.00 = Rp. 5,100.00
0.006 oh Kepala tukang @ Rp. - = Rp. -
0.003 oh Mandor @ Rp. - = Rp. -
Total upah = Rp. 9,300.00
Total bahan dan upah = Rp. 26,895.00

1 Kg Pembesian dengan besi polos atau ulir


Bahan An. SNI 6.17
1.050 Kg Besi beton ( polos/ulir ) @ Rp. 8,500.00 = Rp 8,925.00
0.015 Kg Kawat beton @ Rp. 12,500.00 = Rp 187.50
= Rp 9,112.50
Upah An. SNI 6.17
0.007 Oh Pekerja @ Rp. 70,000.00 = Rp 490.00
0.007 Oh Tukang besi @ Rp. 85,000.00 = Rp 595.00
0.0007 Oh Kepala tukang @ Rp. - = Rp -
0.0004 Oh Mandor @ Rp. - = Rp -
= Rp 1,085.00
Total harga = Rp 10,197.50
4. 1 m2 Pasang bekisting untuk pondasi
Bahan An. SNI 6.20
0.040 m3 Kayu terentang @ Rp. 4,850,000.00 = Rp 194,000.00
0.300 Kg Paku biasa 2" - 5" @ Rp. 12,500.00 = Rp 3,750.00
0.100 Ltr Minyak bekisting @ Rp. 6,550.00 = Rp 655.00
= Rp 198,405.00
Upah An. SNI 6.20
0.520 Oh Pekerja @ Rp. 70,000.00 = Rp 36,400.00
0.260 Oh Tukang kayu @ Rp. 85,000.00 = Rp 22,100.00
0.026 Oh Kepala tukang @ Rp. - = Rp -
0.026 Oh Mandor @ Rp. - = Rp -
= Rp 58,500.00
Total harga = Rp 256,905.00

5. 1 m2 Pasang bekisting untuk sloof


Bahan An. SNI 6.21
0.045 m3 Kayu terentang @ Rp. 4,850,000.00 = Rp 218,250.00
0.300 Kg Paku biasa 2" - 5" @ Rp. 12,500.00 = Rp 3,750.00
0.100 Ltr Minyak bekisting @ Rp. 6,550.00 = Rp 655.00
= Rp 222,655.00
Upah An. SNI 6.21
0.520 Oh Pekerja @ Rp. 70,000.00 = Rp 36,400.00
0.260 Oh Tukang kayu @ Rp. 85,000.00 = Rp 22,100.00
0.026 Oh Kepala tukang @ Rp. - = Rp -
0.026 Oh Mandor @ Rp. - = Rp -
= Rp 58,500.00
Total harga = Rp 281,155.00

6. 1 m2 Pasang bekisting untuk kolom


Bahan An. SNI 6.22
0.040 m3 Kayu terentang @ Rp. 4,850,000.00 = Rp 194,000.00
0.400 Kg Paku biasa 2" - 5" @ Rp. 12,500.00 = Rp 5,000.00
0.200 Ltr Minyak bekisting @ Rp. 6,550.00 = Rp 1,310.00
0.015 m3 Balok kayu borneo @ Rp. 4,600,000.00 = Rp 69,000.00
0.350 Lbr Tripleks tebal 8 mm @ Rp. 77,000.00 = Rp 26,950.00
2.000 Btg Bambu @ Rp. 15,000.00 = Rp 30,000.00
= Rp 326,260.00
Upah An. SNI 6.22
0.660 Oh Pekerja @ Rp. 70,000.00 = Rp 46,200.00
0.330 Oh Tukang kayu @ Rp. 85,000.00 = Rp 28,050.00
0.033 Oh Kepala tukang @ Rp. - = Rp -
0.033 Oh Mandor @ Rp. - = Rp -
= Rp 74,250.00
Total harga = Rp 400,510.00
7. 1 m2 Pasang bekisting untuk balok
Bahan An. SNI 6.23
0.040 m3 Kayu terentang @ Rp. 4,850,000.00 = Rp 194,000.00
0.400 Kg Paku biasa 2" - 5" @ Rp. 12,500.00 = Rp 5,000.00
0.200 Ltr Minyak bekisting @ Rp. 6,550.00 = Rp 1,310.00
0.018 m3 Balok kayu borneo @ Rp. 4,600,000.00 = Rp 82,800.00
0.350 Lbr Tripleks tebal 8 mm @ Rp. 77,000.00 = Rp 26,950.00
2.000 Btg Bambu @ Rp. 15,000.00 = Rp 30,000.00
= Rp 340,060.00
Upah An. SNI 6.23
0.660 Oh Pekerja @ Rp. 70,000.00 = Rp 46,200.00
0.330 Oh Tukang kayu @ Rp. 85,000.00 = Rp 28,050.00
0.033 Oh Kepala tukang @ Rp. - = Rp -
0.033 Oh Mandor @ Rp. - = Rp -
= Rp 74,250.00
Total harga = Rp 414,310.00

8. 1 m2 Pasang bekisting untuk lantai


Bahan An. SNI 6.24
0.040 m3 Kayu terentang @ Rp. 4,850,000.00 = Rp 194,000.00
0.400 Kg Paku biasa 2" - 5" @ Rp. 12,500.00 = Rp 5,000.00
0.200 Ltr Minyak bekisting @ Rp. 6,550.00 = Rp 1,310.00
0.015 m3 Balok kayu borneo @ Rp. 4,600,000.00 = Rp 69,000.00
0.350 Lbr Tripleks tebal 8 mm @ Rp. 77,000.00 = Rp 26,950.00
6.000 Btg Bambu @ Rp. 15,000.00 = Rp 90,000.00
= Rp 386,260.00
Upah An. SNI 6.24
0.660 Oh Pekerja @ Rp. 70,000.00 = Rp 46,200.00
0.330 Oh Tukang kayu @ Rp. 85,000.00 = Rp 28,050.00
0.033 Oh Kepala tukang @ Rp. - = Rp -
0.033 Oh Mandor @ Rp. - = Rp -
= Rp 74,250.00
Total harga = Rp 460,510.00

9. 1 m3 Membuat beton pondasi 60/60/20 K-225


An. SNI 6.7 + An. SNI 6.17 + An. SNI 6.20
103.333 Kg Besi beton @ Rp. 10,197.50 = Rp 1,053,741.67
1.000 m3 Spesi beton K-225 @ Rp. 875,406.90 = Rp 875,406.90
4.000 m2 Cetakan bekisting @ Rp. 256,905.00 = Rp 1,027,620.00
Total harga = Rp 2,956,768.57

10. 1 m3 Membuat beton sloof 15/20 K-225


An. SNI 6.7 + An. SNI 6.17 + An. SNI 6.21
181.796 Kg Besi beton @ Rp. 10,197.50 = Rp 1,853,865.12
1.000 m3 Spesi beton K-225 @ Rp. 875,406.90 = Rp 875,406.90
6.667 m2 Cetakan bekisting @ Rp. 281,155.00 = Rp 1,874,366.67
Total harga = Rp 4,603,638.69

11. 1 m3 Membuat beton sloof 20/30 K-225


An. SNI 6.7 + An. SNI 6.17 + An. SNI 6.21
212.994 Kg Besi beton @ Rp. 10,197.50 = Rp 2,172,011.37
1.000 m3 Spesi beton K-225 @ Rp. 875,406.90 = Rp 875,406.90
5.000 m2 Cetakan bekisting @ Rp. 281,155.00 = Rp 1,405,775.00
Total harga = Rp 4,453,193.27

12. 1 m3 Membuat beton kolom 15/15 K-225


An. SNI 6.7 + An. SNI 6.17 + An. SNI 6.22
175.661 Kg Besi beton @ Rp. 10,197.50 = Rp 1,791,298.07
1.000 m3 Spesi beton K-225 @ Rp. 875,406.90 = Rp 875,406.90
6.667 m2 Cetakan bekisting @ Rp. 400,510.00 = Rp 2,670,066.67
Total harga = Rp 5,336,771.64

13. 1 m3 Membuat beton kolom 15/20 K-225


An. SNI 6.7 + An. SNI 6.17 + An. SNI 6.22
120.556 Kg Besi beton @ Rp. 10,197.50 = Rp 1,229,371.75
1.000 m3 Spesi beton K-225 @ Rp. 875,406.90 = Rp 875,406.90
6.667 m2 Cetakan bekisting @ Rp. 400,510.00 = Rp 2,670,066.67
Total harga = Rp 4,774,845.32

14. 1 m3 Membuat beton kolom 30/30 K-225


An. SNI 6.7 + An. SNI 6.17 + An. SNI 6.22
156.843 Kg Besi beton @ Rp. 10,197.50 = Rp 1,599,411.36
1.000 m3 Spesi beton K-225 @ Rp. 875,406.90 = Rp 875,406.90
6.667 m2 Cetakan bekisting @ Rp. 400,510.00 = Rp 2,670,066.67
Total harga = Rp 5,144,884.93

15. 1 m3 Membuat beton kolom 40/50 K-225


An. SNI 6.7 + An. SNI 6.17 + An. SNI 6.22
170.108 Kg Besi beton @ Rp. 10,197.50 = Rp 1,734,676.33
1.000 m3 Spesi beton K-225 @ Rp. 875,406.90 = Rp 875,406.90
4.500 m2 Cetakan bekisting @ Rp. 400,510.00 = Rp 1,802,295.00
Total harga = Rp 4,412,378.23

16. 1 m3 Membuat beton kolom 50/50 K-225


An. SNI 6.7 + An. SNI 6.17 + An. SNI 6.22
170.108 Kg Besi beton @ Rp. 10,197.50 = Rp 1,734,676.33
1.000 m3 Spesi beton K-225 @ Rp. 875,406.90 = Rp 875,406.90
4.800 m2 Cetakan bekisting @ Rp. 400,510.00 = Rp 1,922,448.00
Total harga = Rp 4,532,531.23

17. 1 m3 Membuat beton kolom 50/70 K-225


An. SNI 6.7 + An. SNI 6.17 + An. SNI 6.22
170.108 Kg Besi beton @ Rp. 10,197.50 = Rp 1,734,676.33
1.000 m3 Spesi beton K-225 @ Rp. 875,406.90 = Rp 875,406.90
4.857 m2 Cetakan bekisting @ Rp. 400,510.00 = Rp 1,945,334.29
Total harga = Rp 4,555,417.52

18. 1 m3 Membuat beton balok 15/15 K-225


An. SNI 6.7 + An. SNI 6.17 + An. SNI 6.23
143.018 Kg Besi beton @ Rp. 10,197.50 = Rp 1,458,421.40
1.000 m3 Spesi beton K-225 @ Rp. 875,406.90 = Rp 875,406.90
6.667 m2 Cetakan bekisting @ Rp. 414,310.00 = Rp 2,762,066.67
Total harga = Rp 5,095,894.97
19. 1 m3 Membuat beton balok 15/20 K-225
An. SNI 6.7 + An. SNI 6.17 + An. SNI 6.23
154.977 Kg Besi beton @ Rp. 10,197.50 = Rp 1,580,378.81
1.000 m3 Spesi beton K-225 @ Rp. 875,406.90 = Rp 875,406.90
6.667 m2 Cetakan bekisting @ Rp. 414,310.00 = Rp 2,762,066.67
Total harga = Rp 5,217,852.38

20. 1 m3 Membuat beton balok 15/35 K-225


An. SNI 6.7 + An. SNI 6.17 + An. SNI 6.23
168.033 Kg Besi beton @ Rp. 10,197.50 = Rp 1,713,514.81
1.000 m3 Spesi beton K-225 @ Rp. 875,406.90 = Rp 875,406.90
6.190 m2 Cetakan bekisting @ Rp. 414,310.00 = Rp 2,564,776.19
Total harga = Rp 5,153,697.90

21. 1 m3 Membuat beton balok 30/50 K-225


An. SNI 6.7 + An. SNI 6.17 + An. SNI 6.23
223.004 Kg Besi beton @ Rp. 10,197.50 = Rp 2,274,079.89
1.000 m3 Spesi beton K-225 @ Rp. 875,406.90 = Rp 875,406.90
5.000 m2 Cetakan bekisting @ Rp. 414,310.00 = Rp 2,071,550.00
Total harga = Rp 5,221,036.80

22. 1 m3 Membuat beton plat, t=12 cm K-225


An. SNI 6.7 + An. SNI 6.17 + An. SNI 6.23
119.411 Kg Besi beton @ Rp. 10,197.50 = Rp 1,217,691.05
1.000 m3 Spesi beton K-225 @ Rp. 875,406.90 = Rp 875,406.90
8.333 m2 Cetakan bekisting @ Rp. 460,510.00 = Rp 3,837,583.33
Total harga = Rp 5,930,681.29

23. 1 m3 Membuat beton plat, t=8 cm K-225


An. SNI 6.7 + An. SNI 6.17 + An. SNI 6.23
117.100 Kg Besi beton @ Rp. 10,197.50 = Rp 1,194,127.25
1.000 m3 Spesi beton K-225 @ Rp. 875,406.90 = Rp 875,406.90
7.500 m2 Cetakan bekisting @ Rp. 460,510.00 = Rp 3,453,825.00
Total harga = Rp 5,523,359.15
HITUNGAN VOLUME
KEGIATAN : REHAB. SEDANG/BERAT GEDUNG DPPKAD KABUPATEN JOMBANG
LOKASI : KECAMATAN JOMBANG, KABUPATEN JOMBANG
TAHUN : 2013

1 PLAT PONDASI 60X60X20


Persegi 0.600 X 0.600 X 0.200 = 0.072 m3
Besi :
Tulangan bawah ø 10 mm - 20 cm 1.200 X 4.000 bh 0.620 = 2.976 kg
Tulangan Atas ø 10 mm - 20 cm 1.800 X 4.000 bh 0.620 = 4.464 kg
Jumlah = 7.440 kg
Volume pondasi = 0.072 m3
Jumlah besi tiap 1 m3 beton = 103.333 kg

2 PONDASI POOR 40X40X40 type A


Persegi 0.400 X 0.400 X 0.400 = 0.064 m3
Besi :
Tulangan beugel ø 8 mm 1.350 X 3.000 bh 0.393 = 1.592 kg
Tulangan bawah ø 16 mm 0.450 X 2.000 bh 1.574 = 1.417 kg
Tulangan keliling ø 16 mm 1.350 X 3.000 bh 1.574 = 6.376 kg
Jumlah = 9.385 kg
Volume pondasi = 0.064 m3
Jumlah besi tiap 1 m3 beton = 146.640 kg

3 KOLOM 20/30
Beton 0.200 X 0.300 X 3.880 = 0.233 m3

Tulangan ø 16 mm ( polos ) 5.030 X 4.000 X 1.578 = 31.740 kg


Tulangan ø 12 mm ( polos ) 5.030 X 2.000 X 0.887 = 8.927 kg
Tulangan ø 8 mm ( polos ) 0.990 X 26.867 bh 0.393 = 10.453 kg
Jumlah besi 51.120 kg
Volume beton 0.233 kg
Jumlah besi tiap 1 m3 beton 219.587 m3

1 KOLOM 30/30
Beton 0.300 X 0.300 X 7.900 = 0.711 m3

Tulangan ø 16 mm ( polos ) 9.130 X 6.000 X 1.578 = 86.417 kg


Tulangan ø 8 mm ( polos ) 1.190 X 53.667 bh 0.393 = 25.098 kg
Jumlah besi 111.516 kg
Volume beton 0.711 kg
Jumlah besi tiap 1 m3 beton 156.843 m3

4 KOLOM 20/20
Beton 0.200 X 0.200 X 3.580 = 0.143 m3

Tulangan ø 12 mm ( polos ) 4.430 X 4.000 X 0.887 = 15.724 kg


Tulangan ø 8 mm ( polos ) 0.790 X 24.333 bh 0.394 = 7.581 kg
Jumlah besi 23.305 kg
Volume beton 0.143 m3
Jumlah besi tiap 1 m3 beton 162.748 kg

2 KOLOM 15/15
Beton 0.150 X 0.150 X 3.500 = 0.079 m3

Tulangan ø 10 mm ( polos ) 4.320 X 4.000 X 0.616 = 10.648 kg


Tulangan ø 6 mm ( polos ) 0.590 X 24.333 bh 0.222 = 3.185 kg
Jumlah besi 13.833 kg
Volume beton 0.079 m3
Jumlah besi tiap 1 m3 beton 175.661 kg
6 Beton Sloof 15/20 K.175
Beton 0.150 X 0.200 X 3.800 = 0.114 m3

Tulangan atas ø 12 mm 4.150 X 2.000 X 0.887 = 7.362 kg


Tulangan bawah ø 12 mm 4.150 X 2.000 X 0.887 = 7.362 kg
Tulangan ø 8 mm 0.640 X 23.857 bh 0.393 = 6.001 kg
Jumlah 20.725 kg
Volume beton 0.114 m3
Jumlah besi tiap 1 m3 beton 181.796 kg

7 Beton Sloof 20/30 K.175


Sloof 20/30 0.200 X 0.300 X 3.800 = 0.228 m3

Tulangan atas ø 12 mm 4.150 X 3.000 X 1.578 = 19.640 kg


Tulangan bawah ø 16 mm 4.150 X 3.000 X 1.578 = 19.640 kg
Tulangan ø 8 mm 0.990 X 23.857 bh 0.393 = 9.282 kg
Jumlah 48.563 kg
Volume beton / besi 0.228 m3
Jumlah besi tiap 1 m3 beton 212.994 kg

8 Beton Sloof 15/30 K.175


Sloof 15/30 0.150 X 0.300 X 3.800 = 0.171 m3

Tulangan ø 16 mm 4.150 X 4.000 X 1.578 = 26.187 kg


Tulangan ø 12 mm 4.150 X 2.000 X 0.887 = 7.365 kg
Tulangan ø 8 mm 0.890 X 23.857 bh 0.393 = 8.345 kg
Jumlah 41.897 kg
Volume beton 0.171 m3
Jumlah besi tiap 1 m3 beton 245.010 kg

9 Beton Sloof 20/40 K.175


Sloof 20/40 0.200 X 0.400 X 3.800 = 0.304 m3

Tulangan ø 16 mm 4.150 X 4.000 X 1.578 = 26.187 kg


Tulangan ø 16 mm 4.150 X 2.000 X 1.578 = 13.094 kg
Tulangan ø 8 mm 1.040 X 22.857 bh 0.393 = 9.342 kg
Jumlah 48.623 kg
Volume beton 0.304 m3
Jumlah besi tiap 1 m3 beton 159.943 kg

3 KOLOM 15/20 CM
Volume beton kolom 0.150 X 0.200 X 3.500 = 0.105 m3

Tulangan ø 10 mm ( polos ) 3.880 X 4.000 X 0.620 = 9.622 kg


Tulangan ø 6 mm ( polos ) 0.690 X 20.000 bh 0.220 = 3.036 kg
Jumlah besi 12.658 kg
Volume beton 0.105 m3
Jumlah besi tiap 1 m3 beton 120.556 kg

4 BALOK LATEI 15/35


Volume beton 0.150 X 0.300 X 3.800 = 0.171 m3
Tulangan ø 12 mm ( polos ) 4.150 X 6.000 X 0.887 = 22.086 kg
Tulangan ø 8 mm ( polos ) 0.740 X 22.857 X 0.393 = 6.647 kg
Jumlah besi 28.734 kg
Volume beton 0.171 m3
Jumlah besi tiap 1 m3 beton 168.033 kg

12 BALOK REPEL MEMANJANG 15/40


Volume beton 0.150 X 0.400 X 3.800 = 0.228 m3

Tulangan ø 16 mm ( polos ) 4.150 X 4.000 X 1.578 = 26.195 kg


Tulangan ø 8 mm ( polos ) 1.090 X 23.857 X 0.393 = 10.220 kg
Jumlah besi 36.414 kg
Volume beton 0.228 m3
Jumlah besi tiap 1 m3 beton 159.713 kg
5 BALOK RING 15/15
Volume beton 0.150 X 0.150 X 3.800 = 0.086 m3

Tulangan ø 10 mm ( polos ) 4.150 X 4.000 X 0.620 = 10.292 kg


Tulangan ø 6 mm ( polos ) 0.440 X 20.000 X 0.220 = 1.936 kg
Jumlah besi 12.228 kg
Volume beton 0.086 m3
Jumlah besi tiap 1 m3 beton 143.018 kg

14 BALOK RING 15/20


Volume beton 0.150 X 0.200 X 3.800 = 0.114 m3

Tulangan ø 10 mm ( polos ) 4.150 X 4.000 X 0.620 = 10.292 kg


Tulangan ø 6 mm ( polos ) 0.690 X 22.857 X 0.220 = 3.470 kg
Jumlah besi 13.762 kg
Volume beton 0.114 m3
Jumlah besi tiap 1 m3 beton 120.717 kg

UNTUK PEMBESIAN BALOK RING 15/15 DAN 15/20 = 131.867 kg

14 BALOK MEMANJANG 20/40


Volume beton 0.200 X 0.400 X 5.700 = 0.456 m3

Tulangan ø 16 mm ( polos ) 6.450 X 6.000 X 1.578 = 61.069 kg


Tulangan ø 8 mm ( polos ) 1.090 X 35.286 X 0.393 = 15.115 kg
Jumlah besi 76.184 kg
Volume beton 0.456 m3
Jumlah besi tiap 1 m3 beton 167.070 kg

15 KONSOL 20/30 ( UNTUK LISPLANK )


Volume beton kolom pendek 0.200 X 0.225 X 1.000 = 0.045 m3

Tulangan ø 12 mm ( polos ) 1.890 X 3.000 X 0.887 = 5.029 kg


Tulangan ø 12 mm ( polos ) 1.410 X 2.000 X 0.887 = 2.501 kg
Tulangan ø 8 mm ( polos ) 0.830 X 8.667 X 0.393 = 2.827 kg
Jumlah besi 10.358 kg
Volume beton 0.045 m3
Jumlah besi tiap 1 m3 beton 230.169 kg

16 KONSOL 20/30 ( UNTUK REPEL )


Volume beton kolom pendek 0.200 X 0.225 X 1.500 = 0.068 m3

Tulangan ø 16 mm ( polos ) 2.550 X 3.000 X 0.887 = 6.786 kg


Tulangan ø 16 mm ( polos ) 1.910 X 2.000 X 0.887 = 3.388 kg
Tulangan ø 8 mm ( polos ) 0.830 X 9.571 X 0.393 = 3.122 kg
Jumlah besi 13.296 m3
Volume beton 0.068 kg
Jumlah besi tiap 1 m3 beton 196.978 m3

17 PLAT REPEL TEBAL 10 CM


Volume beton kolom pendek 0.100 X 1.500 X 3.800 = 0.570 m3

Tulangan ø 10 mm ( polos ) 1.810 X 26.667 X 0.620 = 29.925 kg


Tulangan ø 8 mm ( polos ) 4.000 X 8.500 X 0.393 = 13.362 kg
Jumlah besi 43.287 kg
Volume beton 0.570 m3
Jumlah besi tiap 1 m3 beton 75.943 kg

6 LISPLANK 8/40
Volume beton 0.080 X 0.400 X 4.000 = 0.128 m3

Tulangan ø 10 mm ( polos ) 4.100 X 4.000 X 0.620 = 10.168 kg


Tulangan ø 8 mm ( polos ) 0.460 X 26.667 X 0.393 = 4.821 kg
Jumlah besi 14.989 kg
Volume beton 0.128 m3
Jumlah besi tiap 1 m3 beton 117.100 kg

19 BETON B0X CLUVET SALURAN DEPAN


Volume beton = 48.928 m3

Tulangan ø 12 mm ( polos ) 359.550 X 12.000 X 0.887 = 3,827.050 kg


Tulangan ø 16 mm ( polos ) 290.560 X 12.000 X 1.578 = 5,500.426 kg
Jumlah besi 9,327.477 kg
Volume beton 48.928 m3
Jumlah besi tiap 1 m3 beton 190.637 kg

20 BETON DEUKER PADA SALURAN DEPAN


Volume beton 0.150 X 1.100 X 84.500 = 13.943 m3

Tul. ø 12 mm 54.080 X 12.000 X 0.887 = 575.628 kg


Tul. ø 10 mm 181.090 X 12.000 X 0.620 = 1,347.310 kg
Jumlah besi 1,922.937 kg
Volume beton 13.943 m3
Jumlah besi tiap 1 m3 beton 137.919 kg

2 KOLOM 15/20 CM , DIATAS SLOOF, TINGGI KOLOM = 5 M', JUMLAH TULANGAN Ø 12 = 4 BH


Volume beton 0.150 X 0.200 X 5.000 = 0.150 m3

Tulangan ø 12 mm ( polos ) 5.400 X 4.000 X 0.887 = 19.159 kg


Tulangan ø 6 mm ( polos ) 0.850 X 33.333 bh 0.220 = 6.233 kg
Jumlah besi 25.393 kg
Volume beton 0.150 m3
Jumlah besi tiap 1 m3 beton 169.284 kg

3 Beton Sloof 20/20 K.175 ( Keliling Bangunan )


Beton 0.200 X 0.200 X 108.000 = 4.320 m3

Tulangan atas ø 12 mm 113.000 X 2.000 X 0.887 = 200.462 kg


Tulangan bawah ø 12 mm 113.000 X 2.000 X 0.887 = 200.462 kg
Tulangan ø 6 mm 0.850 X 720.000 bh 0.220 = 134.640 kg
Jumlah 535.564 kg
Volume beton 4.320 m3
Jumlah besi tiap 1 m3 beton 123.973 kg

4 Beton Sloof 15/30 K.175 ( Melintang Tengah Bentang 10M' )


Sloof 15/30 0.150 X 0.300 X 14.000 = 0.630 m3
0
Tulangan atas ø 12 mm 14.600 X 3.000 X 0.887 = 38.851 kg
Tulangan bawah ø 12 mm 14.600 X 3.000 X 0.887 = 38.851 kg
Tulangan ø 8 mm 1.350 X 93.333 bh 0.393 = 49.518 kg
Jumlah 127.219 kg
Volume beton / besi 0.630 m3
Jumlah besi tiap 1 m3 beton 201.935 kg

5 KOLOM 30/30 CM , TINGGI KOLOM =4+3,25=7,25 M', JUMLAH TULANGAN Ø 16 = 6 BH


Volume beton 0.300 X 0.300 X 7.250 = 0.653 m3

Tulangan ø 16 mm ( polos ) 7.650 X 8.000 X 1.578 = 96.545 kg


Tulangan ø 8 mm ( polos ) 1.350 X 48.333 bh 0.393 = 25.643 kg
Jumlah besi 122.188 kg
Volume beton 0.653 m3
Jumlah besi tiap 1 m3 beton 187.262 kg

Kolom beton gewel 0.300 X 0.300 X 2.000 = 0.180 m3


6 BALOK RING 15/25 ( KELILING )
Volume beton 0.150 X 0.250 X 108.000 = 4.050 m3

Tulangan ø 12 mm ( polos ) 113.000 X 4.000 X 0.887 = 400.924 kg


Tulangan ø 8 mm ( polos ) 0.950 X 720.000 X 0.393 = 268.812 kg
Jumlah besi 669.736 kg
Volume beton 4.050 m3
Jumlah besi tiap 1 m3 beton 165.367 kg

7 BALOK RING 15/20 ( GEVEL )


Volume beton 0.150 X 0.200 X 32.000 = 0.960 m3

Tulangan ø 12 mm ( polos ) 33.500 X 4.000 X 0.887 = 118.858 kg


Tulangan ø 6 mm ( polos ) 0.850 X 160.000 X 0.220 = 29.920 kg
Jumlah besi 148.778 kg
Volume beton 0.960 m3
Jumlah besi tiap 1 m3 beton 154.977 kg

8 LISPLANK SUNCREAN 10/40 ( TEPI MEMANJANG )


Volume beton 0.100 X 0.400 X 80.000 = 3.200 m3

Tulangan ø 16 mm ( polos ) 85.000 X 1.000 X 1.578 = 134.091 kg


Tulangan ø 12 mm ( polos ) 85.000 X 4.000 X 0.887 = 301.580 kg
Tulangan ø 8 mm ( polos ) 0.550 X 533.333 X 0.393 = 115.280 kg
Jumlah besi 550.951 kg
Volume beton 3.200 m3
Jumlah besi tiap 1 m3 beton 172.172 kg

9 LISPLANK 8/30 ( TEPI ATAS MEMANJANG )


Volume beton 0.080 X 0.300 X 84.000 = 2.016 m3

Tulangan ø 10 mm ( polos ) 89.000 X 4.000 X 0.620 = 220.720 kg


Tulangan ø 8 mm ( polos ) 0.550 X 560.000 X 0.393 = 121.044 kg
Jumlah besi 341.764 kg
Volume beton 2.016 m3
Jumlah besi tiap 1 m3 beton 169.526 kg

10 KONSOL 20/30
Volume beton 0.200 X 0.300 X 1.000 = 0.060 m3

Tulangan ø 16 mm ( polos ) 1.700 X 2.000 X 1.578 = 5.364 kg


Tulangan ø 12 mm ( polos ) 1.500 X 2.000 X 0.887 = 2.661 kg
Tulangan ø 8 mm ( polos ) 1.150 X 6.667 X 0.393 = 3.013 kg
Jumlah besi 11.038 kg
Volume beton 0.060 m3
Jumlah besi tiap 1 m3 beton 183.960 kg

G BANGUNAN TYPE F, LOS TERTUTUP, UKURAN 8M X 65M, LUAS = 552 M2


1 PONDASI TYPE. A ( 1,2 X 1,2 = 54 BH )
Beton :
Persegi 0.200 X 1.200 X 1.200 = 0.288 m3
Besi :
Tulangan atas ø 12 mm 1.800 X 7.000 bh 0.887 X 2.00 bh = 22.352 kg
Tulangan bawah ø 16 mm 1.350 X 7.000 bh 1.578 X 2.00 bh = 29.824 kg
Jumlah = 52.177 kg
Volume pondasi = 0.288 m3
Jumlah besi tiap 1 m3 beton = 181.169 kg

2 Beton Sloof 20/20 K.175 ( Keliling Bangunan )


Beton 0.200 X 0.200 X 154.000 = 6.160 m3

Tulangan atas ø 12 mm 163.000 X 3.000 X 0.887 = 433.743 kg


Tulangan bawah ø 12 mm 163.000 X 3.000 X 0.887 = 433.743 kg
Tulangan ø 6 mm 0.850 X 1,026.667 bh 0.220 = 191.987 kg
Jumlah 1,059.473 kg
Volume beton 6.160 m3
Jumlah besi tiap 1 m3 beton 171.992 kg
3 Beton Sloof 15/30 K.175 ( Melintang Tengah Bentang 8 M' )
Sloof 15/30 0.150 X 0.300 X 8.000 = 0.360 m3

Tulangan ø 16 mm 8.600 X 4.000 X 1.578 = 54.283 kg


Tulangan ø 12 mm 8.600 X 2.000 X 0.887 = 15.256 kg
Tulangan ø 8 mm 0.850 X 53.333 bh 0.393 = 17.816 kg
Jumlah 87.356 kg
Volume beton / besi 0.360 m3
Jumlah besi tiap 1 m3 beton 242.654 kg

4 Beton Sloof 15/30 K.175 ( Memanjang Tengah Panjang = 40M' )


Sloof 15/30 0.150 X 0.300 X 69.000 = 3.105 m3

Tulangan ø 16 mm 74.000 X 4.000 X 1.578 = 467.088 kg


Tulangan ø 12 mm 74.000 X 2.000 X 0.887 = 131.276 kg
Tulangan ø 8 mm 1.350 X 460.000 bh 0.393 = 244.053 kg
Jumlah 842.417 kg
Volume beton 3.105 m3
Jumlah besi tiap 1 m3 beton 271.310 kg

5 KOLOM 20/30 CM, DIBAWAH SLOF, TINGGI KOLOM =3,25 M', JUMLAH TULANGAN Ø 16 = 8 BH
Volume beton kolom pendek 0.200 X 0.300 X 3.250 = 0.195 m3

Tulangan ø 16 mm ( polos ) 3.850 X 6.000 X 1.578 = 36.452 kg


Tulangan ø 8 mm ( polos ) 1.400 X 21.667 bh 0.393 = 11.921 kg
Jumlah besi 48.373 kg
Volume beton 0.195 m3
Jumlah besi tiap 1 m3 beton 248.066 kg

6 KOLOM 20/30 CM , DIATAS SLOOF, TINGGI KOLOM =4 M', JUMLAH TULANGAN Ø 16 = 6 BH


Kolom Pada Keliling Bangunan
Volume beton kolom 0.200 X 0.300 X 4.000 = 0.240 m3

Tulangan ø 16 mm ( polos ) 4.000 X 4.000 X 1.578 = 25.248 kg


Tulangan ø 12 mm ( polos ) 4.000 X 2.000 X 0.887 = 7.096 kg
Tulangan ø 8 mm ( polos ) 1.200 X 26.667 bh 0.393 = 12.576 kg
Jumlah besi 44.920 kg
Volume beton 0.240 m3
Jumlah besi tiap 1 m3 beton 187.167 kg

Kolom beton gewel 0.200 X 0.300 X 2.250 = 0.135 m3

7 KOLOM 15/20 CM , DIATAS SLOOF, TINGGI KOLOM =4 M', JUMLAH TULANGAN Ø 12 = 4 BH


Kolom Pada Tengah Bentang
Volume beton kolom pendek 0.150 X 0.200 X 4.000 = 0.120 m3

Tulangan ø 10 mm ( polos ) 4.000 X 4.500 X 0.620 = 11.160 kg


Tulangan ø 6 mm ( polos ) 0.850 X 26.667 bh 0.220 = 4.987 kg
Jumlah besi 16.147 kg
Volume beton 0.120 kg
Jumlah besi tiap 1 m3 beton 134.556 kg

8 BALOK LATEI 15/25 ( KELILING DAN TENGAH )


Volume beton 0.150 X 0.250 X 186.000 = 6.975 m3

Tulangan ø 12 mm ( polos ) 197.000 X 4.000 X 0.887 = 698.956 kg


Tulangan ø 8 mm ( polos ) 0.950 X 1,240.000 X 0.393 = 462.954 kg
Jumlah besi 1,161.910 kg
Volume beton 6.975 kg
Jumlah besi tiap 1 m3 beton 166.582 kg

9 BALOK RING 15/15 ( TENGAH )


Volume beton 0.150 X 0.150 X 205.000 = 4.613 m3

Tulangan ø 10 mm ( polos ) 217.000 X 4.000 X 0.620 = 538.160 kg


Tulangan ø 6 mm ( polos ) 0.750 X 1,025.000 X 0.220 = 169.125 kg
Jumlah besi 707.285 kg
Volume beton 4.613 kg
Jumlah besi tiap 1 m3 beton 153.341 kg

10 BALOK RING 15/20 ( KELILING TEPI MEMANJANG DAN GEVEL )


Volume beton 0.150 X 0.200 X 158.000 = 4.740 m3

Tulangan ø 10 mm ( polos ) 168.000 X 4.000 X 0.620 = 416.640 kg


Tulangan ø 6 mm ( polos ) 0.850 X 790.000 X 0.220 = 147.730 kg
Jumlah besi 564.370 kg
Volume beton 4.740 m3
Jumlah besi tiap 1 m3 beton 119.065 kg

11 LISPLANK 8/30 ( TEPI ATAS MEMANJANG )


Volume beton 0.080 X 0.300 X 142.000 = 3.408 m3

Tulangan ø 10 mm ( polos ) 145.000 X 4.000 X 0.620 = 359.600 kg


Tulangan ø 8 mm ( polos ) 0.550 X 946.667 X 0.393 = 204.622 kg
Jumlah besi 564.222 kg
Volume beton 3.408 m3
Jumlah besi tiap 1 m3 beton 165.558 kg

12 KONSOL 20/30 ( 24 BH )
Volume beton kolom pendek 0.200 X 0.300 X 1.000 = 0.060 m3

Tulangan ø 16 mm ( polos ) 1.700 X 2.000 X 1.578 = 5.365 kg


Tulangan ø 12 mm ( polos ) 1.500 X 2.000 X 0.887 = 2.661 kg
Tulangan ø 8 mm ( polos ) 1.150 X 6.667 X 0.393 = 3.013 kg
Jumlah besi 11.039 kg
Volume beton 0.060 m3
Jumlah besi tiap 1 m3 beton 183.987 kg

H 0

1 PONDASI TYPE. E LAJUR BELAKANG ( 1,2 X 1,2 = 18 BH )


Beton :
Persegi 0.200 X 1.200 X 1.200 = 0.288 m3
Besi :
Tulangan atas ø 10 mm 1.800 X 7.000 bh 0.620 X 2.00 bh = 15.624 kg
Tulangan bawah ø 16 mm 1.450 X 7.000 bh 1.578 X 2.00 bh = 32.033 kg
Jumlah = 47.657 kg
Volume pondasi = 0.288 m3
Jumlah besi tiap 1 m3 beton = 165.477 kg

2 KOLOM 20/30 CM, DIBAWAH SLOF, TINGGI KOLOM =3,25 M', JUMLAH TULANGAN Ø 16 = 8 BH
Volume beton kolom pendek 0.200 X 0.300 X 3.250 = 0.195 m3

Tulangan ø 16 mm ( polos ) 3.850 X 6.000 X 1.578 = 36.452 kg


Tulangan ø 8 mm ( polos ) 1.400 X 21.667 bh 0.393 = 11.921 kg
Jumlah besi 48.373 kg
Volume beton 0.195 m3
Jumlah besi tiap 1 m3 beton 248.066 kg

3 KOLOM 20/30 CM , DIATAS SLOOF, TINGGI KOLOM =4 M', JUMLAH TULANGAN Ø 16 = 6 BH


Volume beton kolom 0.200 X 0.300 X 4.000 = 0.240 m3

Tulangan ø 16 mm ( polos ) 4.000 X 4.000 X 1.578 = 25.248 kg


Tulangan ø 12 mm ( polos ) 4.000 X 2.000 X 0.887 = 7.096 kg
Tulangan ø 8 mm ( polos ) 1.200 X 26.667 bh 0.393 = 12.576 kg
Jumlah besi 44.920 kg
Volume beton 0.240 m3
Jumlah besi tiap 1 m3 beton 187.167 kg

4 PONDASI TYPE. F ( 1,4 X 1,4 = 36 BH )


Beton :
Persegi 0.250 X 1.400 X 1.400 = 0.490 m3
Besi :
Tulangan atas ø 12 mm 2.000 X 7.000 bh 0.887 X 2.00 bh = 24.836 kg
Tulangan bawah ø 16 mm 1.600 X 15.000 bh 1.578 X 2.00 bh = 75.744 kg
Jumlah = 100.580
Volume pondasi = 0.490 m3
Jumlah besi tiap 1 m3 beton = 205.265 kg

5 KOLOM 30/30 CM , TINGGI =3,5M + 4 M', JUMLAH TULANGAN Ø 16 = 8 BH


Volume beton kolom 0.300 X 0.300 X 7.500 = 0.675 m3

Tulangan ø 16 mm ( polos ) 8.000 X 8.000 X 1.578 = 100.992 kg


Tulangan ø 8 mm ( polos ) 1.350 X 50.000 bh 0.393 = 26.528 kg
Jumlah besi 127.520 kg
Volume beton 0.675 m3
Jumlah besi tiap 1 m3 beton 188.918 kg

6 PONDASI TYPE. A LAJUR DEPAN ( 1,5 X 1,5 = 18 BH )


Beton :
Persegi 0.250 X 1.500 X 1.500 = 0.563 m3
Besi :
Tulangan atas ø 12 mm 2.100 X 7.500 bh 0.887 X 2.00 bh = 27.941 kg
Tulangan bawah ø 16 mm 1.700 X 16.000 bh 1.578 X 2.00 bh = 85.843 kg
Jumlah = 113.784
Volume pondasi = 0.563 m3
Jumlah besi tiap 1 m3 beton = 202.282 kg

7 KOLOM 30/40 CM , TINGGI =3,5M + 4 M', JUMLAH TULANGAN Ø 16 = 8 BH


Volume beton kolom 0.300 X 0.400 X 7.500 = 0.900 m3

Tulangan ø 16 mm ( polos ) 8.000 X 8.000 X 1.578 = 100.992 kg


Tulangan ø 10 mm ( polos ) 1.350 X 50.000 bh 0.620 = 41.850 kg
Jumlah besi 142.842 kg
Volume beton 0.900 m3
Jumlah besi tiap 1 m3 beton 158.713 kg

8 PONDASI TYPE. A SELASAR PINTU TENGAH ( 1,8 X 1,8 = 8 BH )


Beton :
Persegi 0.250 X 1.800 X 1.800 = 0.810 m3
Besi :
Tulangan atas ø 12 mm 2.400 X 9.000 bh 0.887 X 2.00 bh = 38.318 kg
Tulangan bawah ø 16 mm 1.900 X 19.000 bh 1.578 X 2.00 bh = 113.932 kg
Jumlah = 152.250
Volume pondasi = 0.810 m3
Jumlah besi tiap 1 m3 beton = 187.963 kg

8 KOLOM 40/50 CM , TINGGI =3,5M + 4 M', JUMLAH TULANGAN Ø 16 = 8 BH


Volume beton kolom 0.400 X 0.500 X 7.500 = 1.500 m3

Tulangan ø 19 mm ( polos ) 8.000 X 12.000 X 2.222 = 213.312 kg


Tulangan ø 10 mm ( polos ) 1.350 X 50.000 bh 0.620 = 41.850 kg
Jumlah besi 255.162 kg
Volume beton 1.500 m3
Jumlah besi tiap 1 m3 beton 170.108 kg

10 PEKERJAAN BETON LANTAI II


BETON BALOK MEMANJANG 20/40
Volume balok memanjang 0.200 X 0.400 X 64.000 = 5.120 m3

Tulangan ø 16 mm ( polos ) 69.000 X 8.000 X 1.578 = 871.056 kg


Tulangan ø 8 mm ( polos ) 1.350 X 427.667 bh 0.393 = 226.899 kg
Jumlah besi 1,097.955 kg
Volume beton 5.120 m3
Jumlah besi tiap 1 m3 beton 214.444 kg

11 BETON BALOK MEMANJANG DEPAN PADA PLAT DAK LANTAI II, 15/20
Volume balok memanjang 0.150 X 0.200 X 64.000 = 1.920 m3

12 BETON LISPLANK MEMANJANG 8/40


Volume balok memanjang 0.080 X 0.400 X 64.000 = 2.048 m3
Plesteran 0.700 X 64.000 = 44.800 m2
Benangan 2.000 X 64.000 = 128.000 m'

13 BETON BALOK MELINTANG PADA PLAT LANTAI II, 20/40


Volume balok melintang 0.200 X 0.400 X 8.000 = 0.640 m3

Tulangan ø 16 mm ( polos ) 8.800 X 8.000 X 1.578 = 111.091 kg


Tulangan ø 8 mm ( polos ) 1.350 X 54.333 bh 0.393 = 28.827 kg
Jumlah besi 139.918 kg
Volume beton 0.640 m3
Jumlah besi tiap 1 m3 beton 218.621 kg
9 BETON PLAT LANTAI II PADA RUKO
Plat lantai II 0.120 X 3.800 X 7.700 = 3.511 m3

Tulangan ø 10 mm ( polos ) 4.000 X 56.000 X 0.620 X 2.00 = 277.760 kg


Tulangan ø 10 mm ( polos ) 8.300 X 27.500 bh 0.620 X 2.00 = 141.515 kg
Jumlah besi 419.275 kg
Volume beton 3.511 m3
Jumlah besi tiap 1 m3 beton 119.411 kg

15 BETON PLAT LANTAI SELASAR DEPAN PADA MUSHOLLA


Plat lantai II pd selasar 0.120 X 8.800 X 13.000 = 13.728 m3

16 BETON BALOK ANAK PADA SELASAR


Volume balok melintang 0.200 X 0.300 X 13.000 = 0.780 m3

Tulangan ø 16 mm ( polos ) 14.000 X 6.000 X 1.578 = 132.552 kg


Tulangan ø 8 mm ( polos ) 1.150 X 87.667 bh 0.393 = 39.621 kg
Jumlah besi 172.173 kg
Volume beton 0.780 m3
Jumlah besi tiap 1 m3 beton 220.735 kg

17 BETON BALOK PORTAL PADA SELASAR


Balok portal 40/80 0.300 X 0.600 X 8.000 = 1.440 m3

Tulangan ø 19 mm ( polos ) 9.500 X 10.000 X 1.950 = 185.250 kg


Tulangan ø 10 mm ( polos ) 2.550 X 54.333 bh 0.620 = 85.901 kg
Jumlah besi 271.151 kg
Volume beton 1.440 m3
Jumlah besi tiap 1 m3 beton 188.299 kg

Balok melintang 20/40 0.200 X 0.400 X 12.000 = 0.960 m3

Tulangan ø 16 mm ( polos ) 13.500 X 8.000 X 1.578 = 170.424 kg


Tulangan ø 8 mm ( polos ) 1.350 X 81.000 bh 0.393 = 42.975 kg
Jumlah besi 213.399 kg
Volume beton 0.960 m3
Jumlah besi tiap 1 m3 beton 222.290 kg

18 BETON BALOK LATEI DEPAN 15/25


Volume balok latei 15/30 0.150 X 0.300 X 64.000 = 2.880 m3

Tulangan ø 12 mm ( polos ) 74.000 X 4.000 X 0.887 = 262.552 kg


Tulangan ø 8 mm ( polos ) 0.950 X 321.000 bh 0.393 = 119.845 kg
Jumlah besi 382.397 kg
Volume beton 2.880 m3
Jumlah besi tiap 1 m3 beton 132.777 kg

19 Beton Sloof 20/40 K.175 ( Memanjang Belakang )


Sloof 20/40 0.200 X 0.400 X 64.000 = 5.120 m3

Tulangan atas ø 16 mm 69.000 X 3.000 X 1.578 = 326.646 kg


Tulangan bawah ø 16 mm 69.000 X 3.000 X 1.578 = 326.646 kg
Tulangan ø 8 mm 1.350 X 426.667 bh 0.393 = 226.368 kg
Jumlah 879.660 kg
Volume beton 5.120 m3
Jumlah besi tiap 1 m3 beton 171.809 kg

20 Beton Sloof 20/40 K.175 ( Melintang )


Sloof 20/40 0.200 X 0.400 X 8.000 = 0.640 m3

Tulangan atas ø 16 mm 9.500 X 3.000 X 1.578 = 44.973 kg


Tulangan bawah ø 16 mm 9.500 X 3.000 X 1.578 = 44.973 kg
Tulangan ø 8 mm 1.350 X 53.333 bh 0.393 = 28.296 kg
Jumlah 118.242 kg
Volume beton 0.640 m3
Jumlah besi tiap 1 m3 beton 184.753 kg
21 Beton Sloof 15/30 K.175 ( Memanjang Tengah dan Depan )
Sloof 15/30 0.150 X 0.300 X 64.000 = 2.880 m3

Tulangan atas ø 12 mm 69.000 X 3.000 X 0.887 = 183.609 kg


Tulangan bawah ø 12 mm 69.000 X 3.000 X 0.887 = 183.609 kg
Tulangan ø 8 mm 1.050 X 365.714 bh 0.393 = 150.912 kg
Jumlah 518.130 kg
Volume beton 2.880 m3
Jumlah besi tiap 1 m3 beton 179.906 kg

22 Beton Sloof 20/40 K.175 ( Portal Selasar )


Sloof 20/40 0.200 X 0.400 X 8.000 = 0.640 m3

Tulangan atas ø 16 mm 9.500 X 3.000 X 1.578 = 44.973 kg


Tulangan bawah ø 16 mm 9.500 X 3.000 X 1.578 = 44.973 kg
Tulangan ø 8 mm 1.350 X 53.333 bh 0.393 = 28.296 kg
Jumlah 118.242 kg
Volume beton 0.640 m3
Jumlah besi tiap 1 m3 beton 184.753 kg

23 Beton Sloof 20/40 K.175 ( Melintang Selasar )


Sloof 20/40 0.200 X 0.400 X 13.000 = 1.040 m3

Tulangan atas ø 16 mm 13.600 X 3.000 X 1.578 = 64.382 kg


Tulangan bawah ø 16 mm 13.600 X 3.000 X 1.578 = 64.382 kg
Tulangan ø 8 mm 1.350 X 86.667 bh 0.393 = 45.981 kg
Jumlah 174.746 kg
Volume beton 1.040 m3
Jumlah besi tiap 1 m3 beton 168.025 kg

23 BETON PONDASI UNTUK LAMPU TAMAN


Pondasi 45/45/70 0.450 X 0.450 X 0.700 = 0.142 m3

Tulangan bawah ø 12 mm 0.750 X 4.000 X 0.887 = 2.661 kg


Tulangan ø 8 mm 1.500 X 5.000 bh 0.393 = 2.948 kg
Jumlah 5.609 kg
Volume beton 0.142 m3
Jumlah besi tiap 1 m3 beton 39.566 kg

23 BETON PONDASI UNTUK LAMPU PJU


Strouse Ø 20 0.785 X 0.040 X 2.550 = 0.080 m3
Pondasi 30/30/45 0.300 X 0.300 X 0.450 = 0.041 m3
= 0.121 m3

Tulangan bawah ø 12 mm 3.050 X 4.000 X 0.887 = 10.821 kg


Tulangan ø 8 mm 0.728 X 20.000 bh 0.393 = 5.722 kg
Jumlah 16.543 kg
Volume beton 0.121 m3
Jumlah besi tiap 1 m3 beton 137.211 kg

Volume cetakan beton 4.479 m2

24 BETON LANTAI II PADA RUKO


Kolom 15/25 0.150 X 0.250 X 4.000 = 0.150 m3

Balok latei depan 15/20 0.150 X 0.250 X 64.000 = 2.400 m3

Balok ring depan 15/20 0.150 X 0.200 X 64.000 = 1.920 m3

Balok ring miring 15/20 0.150 X 0.200 X 9.700 = 0.291 m3

Balok ring belakang 15/20 0.150 X 0.200 X 64.000 = 1.920 m3

Plat depan diatas kusen 0.070 X 2.400 X 0.750 = 0.126 m3

* Beton ring 15/20 pd tp&slsar 0.150 X 0.200 X #REF! = #REF! m3

25 TANGGA RUKO
PONDASI TANGGA ( 1.2 X 1,2 = 1 BH )
Beton :
Pondasi 0.200 X 1.200 X 1.200 = 0.288 m3
Dinding dan plat dak 0.120 X 1.000 X 10.500 = 1.260 m3

Besi :
Tulangan atas ø 10 mm 1.800 X 7.000 bh 0.620 X 2.00 bh = 15.624 kg
Tulangan bawah ø 16 mm 1.350 X 7.000 bh 1.578 X 2.00 bh = 29.824 kg
Jumlah = 45.448
Volume pondasi = 0.288 m3
Jumlah besi tiap 1 m3 beton = 157.806 kg

26 TANGGA KANTOR DAN MUSHOLLA


PONDASI TANGGA ( 1.4 X 1,4 = 2 BH )
Beton :
Pondasi 0.200 X 1.400 X 1.400 = 0.392 m3
Dinding dan plat dak 0.120 X 1.200 X 11.200 = 1.613 m3

Besi :
Tulangan atas ø 10 mm 2.000 X 8.000 bh 0.620 X 2.00 bh = 19.840 kg
Tulangan bawah ø 16 mm 1.350 X 8.000 bh 1.578 X 2.00 bh = 34.085 kg
Jumlah = 53.925 kg
Volume pondasi = 0.392 m3
Jumlah besi tiap 1 m3 beton = 137.563 kg

JEMBATAN BETON

1 PONDASI POOR 60X200X800 type B


Persegi per m' 0.600 X 2.000 X 8.000 X 2.00 = 19.200 m3
Besi :
Tulangan 25 mm 35.880 X 12.000 X 3.980 = 1,713.629 kg
Tulangan 16 mm 31.900 X 12.000 X 1.560 = 597.168 kg
Jumlah = 2,310.797 kg
Volume pondasi = 19.200 m3
Jumlah besi tiap 1 m3 beton = 120.354 kg

2 Beton 40/80 K.300


Balok 40/80 0.400 X 0.800 X 8.500 X 6.000 = 16.320 m3

Tulangan atas D 22 mm 38.117 X 12.000 X 3.040 = 1,390.496 kg


Tulangan tengah D 16 mm 8.600 X 12.000 X 1.560 = 160.992 kg
Tulangan Ø 12 mm 132.820 X 12.000 X 0.887 = 1,413.736 kg
Jumlah 2,965.224 kg
Volume beton 16.320 m3
Jumlah besi tiap 1 m3 beton 181.693 kg

10 Beton diafragma 30/40 K.300


Balok 30/40 0.300 X 0.400 X 1.000 X 15.000 = 1.800 m3

Tulangan atas D 16 mm 14.250 X 12.000 X 1.560 = 266.760 kg


Tulangan Ø 12 mm 12.650 X 12.000 X 0.887 = 134.647 kg
Jumlah 401.407 kg
Volume beton 1.800 m3
Jumlah besi tiap 1 m3 beton 223.004 kg

4 Beton 40/75 K.300


Balok 40/75 0.400 X 0.750 X 8.000 X 2.000 = 4.800 m3

Tulangan D 16 mm 31.900 X 12.000 X 1.560 = 597.168 kg


Jumlah 597.168 kg
Volume beton 4.800 m3
Jumlah besi tiap 1 m3 beton 124.410 kg

5 Beton konsol trotoar 30/50 K.300


Balok 30/50 0.300 X 0.500 X 1.000 X 6.00 = 0.900 m3
Tulangan D 16 mm 5.200 X 12.000 X 1.560 = 97.344 kg
Tulangan Ø 8 mm 4.750 X 12.000 X 0.393 = 22.401 kg
Jumlah 119.745 X
Volume beton 0.900 m3
Jumlah besi tiap 1 m3 beton 133.050 kg

6 Pelat Beton K.225


Pelat t = 20 0.200 X 8.500 X 9.000 = 15.300 m3

Tulangan atas D 19 mm 106.575 X 12.000 X 2.25 = 2,877.525 kg


Tulangan atas D 12 mm 88.958 X 12.000 X 0.887 = 946.873 kg
Jumlah 3,824.398 kg
Volume beton 15.300 m3
Jumlah besi tiap 1 m3 beton 249.961 kg

7 Pelat Beton injak K.300


Pelat t = 15 0.150 X 1.500 X 7.400 = 1.665 m3

Tulangan atas D 10 mm 53.267 X 12.000 X 0.560 = 357.952 kg


Jumlah 357.952 kg
Volume beton 1.665 m3
Jumlah besi tiap 1 m3 beton 214.986 kg

8 Pelat Beton trotoar K.300


Pelat t = 15 0.150 X 1.000 X 8.500 X 2.000 = 2.550 m3

Tulangan atas D 10 mm 16.328 X 12.000 X 0.560 = 109.721 kg


Jumlah 109.721 kg
Volume beton 2.550 m3
Jumlah besi tiap 1 m3 beton 43.028 kg

9 Sandaran
Beton 0.150 X 0.200 X 0.580 X 10.00 = 0.174 m3

Tulangan D 12 mm 2.850 X 12.000 X 0.887 = 30.335 kg


Tulangan ø 8 mm ( polos ) 2.433 X 12.000 X 0.393 = 11.476 kg
Jumlah besi 41.811 kg
Volume beton 0.174 m3
Jumlah besi tiap 1 m3 beton 240.293 kg

10 Skampal 20 cm
Beton 0.250 X 3.140 X 0.040 X 0.60 X 12 = 0.226 m3

Tulangan ø 12 mm ( polos ) 3.720 X 12.000 X 0.887 = 39.596 kg


Tulangan ø 8 mm ( polos ) 3.640 X 12.000 X 0.393 = 17.166 kg
Jumlah besi 56.762 kg
Volume beton 0.226 m3
Jumlah besi tiap 1 m3 beton 251.070 kg

11 Beton sloof 20/30 K.175


Balok 20/30 0.200 X 0.300 X 2.850 X 2.00 = 0.342 m3

Tulangan atas D 12 mm 1.947 X 12.000 X 0.887 = 20.720 kg


Tulangan Ø 8 mm 3.000 X 12.000 X 0.393 = 14.148 kg
Jumlah 34.868 kg
Volume beton 0.342 m3
Jumlah besi tiap 1 m3 beton 101.954 kg

TANDON AIR

1 PONDASI POOR 25X600X600


Persegi 0.250 X 6.000 X 6.000 = 9.000 m3
Besi :
Tulangan ø 16 mm 87.408 X 12.000 x 1.578 = 1,655.164 kg
Jumlah = 1,655.164 kg
Volume pondasi = 9.000 m3
Jumlah besi tiap 1 m3 beton = 183.907 kg

2 KOLOM 40/40
Beton 0.400 X 0.400 13.250 X 4.00 = 8.480 m3

Tulangan ø 16 mm ( polos ) 57.800 X 12.000 X 1.578 = 1,094.501 kg


Tulangan ø 8 mm ( polos ) 45.500 X 12.000 X 0.393 = 214.578 kg
Jumlah besi 1,309.079 kg
Volume beton 8.480 m3
Jumlah besi tiap 1 m3 beton 154.373 kg

3 Balok 30/40
Beton 0.300 X 0.400 X 2.600 X 4.00 = 1.248 m3

Tulangan ø 19 mm ( polos ) 10.593 X 12.000 X 2.230 = 283.478 kg


Tulangan ø 8 mm ( polos ) 9.240 X 12.000 X 0.393 = 43.576 kg
Jumlah besi 327.053 kg
Volume beton 1.248 m3
Jumlah besi tiap 1 m3 beton 262.062 kg

4 Balok 40/80
Beton 0.400 X 0.800 X 2.600 X 4.00 = 3.328 m3

Tulangan ø 22 mm ( polos ) 16.000 X 12.000 X 2.983 = 572.736 kg


Tulangan ø 12 mm ( polos ) 18.573 X 12.000 X 0.887 = 197.695 kg
Jumlah besi 770.431 kg
Volume beton 3.328 m3
Jumlah besi tiap 1 m3 beton 231.500 kg

5 Pelat Dinding Beton K.225


Pelat t = 20 0.200 X 2.600 X 2.230 X 4.00 = 4.638 m3

Tulangan Ø 12 mm 50.479 X 12.000 X 0.887 = 537.295 kg


Tulangan Ø 10 mm 27.945 X 12.000 X 0.620 = 207.911 kg
Jumlah 745.206 kg
Volume beton 4.638 m3
Jumlah besi tiap 1 m3 beton 160.660 kg

6 Pelat Lantai tandon atas K.225


Pelat t = 20 0.200 X 2.850 X 2.850 = 1.625 m3

Tulangan atas Ø 10 mm 25.593 X 12.000 X 0.620 = 190.414 kg


Jumlah 190.414 kg
Volume beton 1.625 m3
Jumlah besi tiap 1 m3 beton 117.214 kg

7 Beton canopy K.175


Pelat t = 10 CM 0.100 X 0.500 X 5.100 X 4.00 = 1.020 m3

Tulangan memanjang Ø 8 mm 3.350 X 12.000 X 0.393 = 15.799 kg


Tulangan melintang Ø 10 mm 4.267 X 12.000 X 0.620 = 31.744 kg
Jumlah 47.543 kg
Volume beton 1.020 m3
Jumlah besi tiap 1 m3 beton 46.610 kg

8 Beton tempat genzet K.175


Pelat t = 12 CM 0.200 X 1.000 X 2.000 = 0.400 m3

Tulangan memanjang Ø 10 mm 4.581 X 12.000 X 0.620 = 34.079 kg


Jumlah 34.079 kg
Volume beton 0.400 m3
Jumlah besi tiap 1 m3 beton 85.198 kg

9 Balok silang 20/30


Beton 0.200 X 0.300 X 3.820 X 4.000 = 0.917 m3

Tulangan ø 19 mm atas ( polos ) 6.533 X 12.000 X 2.230 = 174.832 kg


Tulangan ø 8 mm ( polos ) 6.440 X 12.000 X 0.393 = 30.371 kg
Jumlah besi 205.203 kg
Volume beton 0.917 m3
Jumlah besi tiap 1 m3 beton 223.825 kg
PEKERJAAN BETON

۞ 1 m3 Membuat Lantai kerja Beton mutu F'c = 7.4 Mpa ( K 100 ), Slump ( 3-6 ) Cm, w/c = 0.87
Bahan An. SNI 6.4
4.600 Zak Semen portland @ Rp. 48,000.00 = Rp 220,800.00
0.638 m3 Pasir beton @ Rp. 197,000.00 = Rp 125,657.86
0.761 m3 Kerikil ( Maksimum 30 mm ) @ Rp. 249,000.00 = Rp 189,424.44
200.000 lt Air @ Rp. - = Rp -
= Rp 535,882.30
Upah An. SNI 6.4
1.200 Oh Pekerja @ Rp. 70,000.00 = Rp 84,000.00
0.200 Oh Tukang batu @ Rp. 85,000.00 = Rp 17,000.00
0.020 Oh Kepala tukang @ Rp. - = Rp -
0.060 Oh Mandor @ Rp. - = Rp -
= Rp 101,000.00
Total harga = Rp 636,882.30

۞ 1 m3 Membuat Beton mutu F'c = 19.3 MPa ( K 225 ), Slump ( 12 ± 2 ) Cm, w/c = 0.58
Bahan An. SNI 6.7
371.000 Kg Semen portland @ Rp. 1,200.00 = Rp 445,200.00
0.499 m3 Pasir beton @ Rp. 197,000.00 = Rp 98,218.57
0.776 m3 Kerikil ( Maksimum 30 mm ) @ Rp. 249,000.00 = Rp 193,113.33
215 Liter Air @ Rp. - = Rp -
= Rp 736,531.90
Upah An. SNI 6.7
1.650 Oh Pekerja @ Rp. 70,000.00 = Rp 115,500.00
0.275 Oh Tukang batu @ Rp. 85,000.00 = Rp 23,375.00
0.028 Oh Kepala tukang @ Rp. - = Rp -
0.083 Oh Mandor @ Rp. - = Rp -
= Rp 138,875.00
Total harga = Rp 875,406.90

۞ 1 Kg Pembesian dengan besi polos atau ulir


Bahan An. SNI 6.17
1.050 Kg Besi beton ( polos/ulir ) @ Rp. 8,500.00 = Rp 8,925.00
0.015 Kg Kawat beton @ Rp. 12,500.00 = Rp 187.50
= Rp 9,112.50
Upah An. SNI 6.17
0.007 Oh Pekerja @ Rp. 70,000.00 = Rp 490.00
0.007 Oh Tukang besi @ Rp. 85,000.00 = Rp 595.00
0.0007 Oh Kepala tukang @ Rp. - = Rp -
0.0004 Oh Mandor @ Rp. - = Rp -
= Rp 1,085.00
Total harga = Rp 10,197.50
۞ 1 m2 Pasang bekisting untuk pondasi
Bahan An. SNI 6.20
0.040 m3 Kayu terentang @ Rp. 4,850,000.00 = Rp 194,000.00
0.300 Kg Paku biasa 2" - 5" @ Rp. 12,500.00 = Rp 3,750.00
0.100 Ltr Minyak bekisting @ Rp. 6,550.00 = Rp 655.00
= Rp 198,405.00
Upah An. SNI 6.20
0.520 Oh Pekerja @ Rp. 70,000.00 = Rp 36,400.00
0.260 Oh Tukang kayu @ Rp. 85,000.00 = Rp 22,100.00
0.026 Oh Kepala tukang @ Rp. - = Rp -
0.026 Oh Mandor @ Rp. - = Rp -
= Rp 58,500.00
Total harga = Rp 256,905.00

۞ 1 m2 Pasang bekisting untuk sloof


Bahan An. SNI 6.21
0.045 m3 Kayu terentang @ Rp. 4,850,000.00 = Rp 218,250.00
0.300 Kg Paku biasa 2" - 5" @ Rp. 12,500.00 = Rp 3,750.00
0.100 Ltr Minyak bekisting @ Rp. 6,550.00 = Rp 655.00
= Rp 222,655.00
Upah An. SNI 6.21
0.520 Oh Pekerja @ Rp. 70,000.00 = Rp 36,400.00
0.260 Oh Tukang kayu @ Rp. 85,000.00 = Rp 22,100.00
0.026 Oh Kepala tukang @ Rp. - = Rp -
0.026 Oh Mandor @ Rp. - = Rp -
= Rp 58,500.00
Total harga = Rp 281,155.00
Bahan pakai 4x = Rp 114,163.75

۞ 1 m2 Pasang bekisting untuk kolom


Bahan An. SNI 6.22
0.040 m3 Kayu terentang @ Rp. 4,850,000.00 = Rp 194,000.00
0.400 Kg Paku biasa 2" - 5" @ Rp. 12,500.00 = Rp 5,000.00
0.200 Ltr Minyak bekisting @ Rp. 6,550.00 = Rp 1,310.00
0.015 m3 Balok kayu borneo @ Rp. 4,600,000.00 = Rp 69,000.00
0.350 Lbr Tripleks tebal 8 mm @ Rp. 77,000.00 = Rp 26,950.00
2.000 Btg Bambu @ Rp. 15,000.00 = Rp 30,000.00
= Rp 326,260.00
Upah An. SNI 6.22
0.660 Oh Pekerja @ Rp. 70,000.00 = Rp 46,200.00
0.330 Oh Tukang kayu @ Rp. 85,000.00 = Rp 28,050.00
0.033 Oh Kepala tukang @ Rp. - = Rp -
0.033 Oh Mandor @ Rp. - = Rp -
= Rp 74,250.00
Total harga = Rp 400,510.00
Bahan pakai 4x = Rp 155,815.00

۞ 1 m2 Pasang bekisting untuk balok


Bahan An. SNI 6.23
0.040 m3 Kayu terentang @ Rp. 4,850,000.00 = Rp 194,000.00
0.400 Kg Paku biasa 2" - 5" @ Rp. 12,500.00 = Rp 5,000.00
0.200 Ltr Minyak bekisting @ Rp. 6,550.00 = Rp 1,310.00
0.018 m3 Balok kayu borneo @ Rp. 4,600,000.00 = Rp 82,800.00
0.350 Lbr Tripleks tebal 8 mm @ Rp. 77,000.00 = Rp 26,950.00
2.000 Btg Bambu @ Rp. 15,000.00 = Rp 30,000.00
= Rp 340,060.00
Upah An. SNI 6.23
0.660 Oh Pekerja @ Rp. 70,000.00 = Rp 46,200.00
0.330 Oh Tukang kayu @ Rp. 85,000.00 = Rp 28,050.00
0.033 Oh Kepala tukang @ Rp. - = Rp -
0.033 Oh Mandor @ Rp. - = Rp -
= Rp 74,250.00
Total harga = Rp 414,310.00
Bahan pakai 4x = Rp 159,265.00

۞ 1 m2 Pasang bekisting untuk lantai


Bahan An. SNI 6.24
0.040 m3 Kayu terentang @ Rp. 4,850,000.00 = Rp 194,000.00
0.400 Kg Paku biasa 2" - 5" @ Rp. 12,500.00 = Rp 5,000.00
0.200 Ltr Minyak bekisting @ Rp. 6,550.00 = Rp 1,310.00
0.015 m3 Balok kayu borneo @ Rp. 4,600,000.00 = Rp 69,000.00
0.350 Lbr Tripleks tebal 8 mm @ Rp. 77,000.00 = Rp 26,950.00
6.000 Btg Bambu @ Rp. 15,000.00 = Rp 90,000.00
= Rp 386,260.00
Upah An. SNI 6.24
0.660 Oh Pekerja @ Rp. 70,000.00 = Rp 46,200.00
0.330 Oh Tukang kayu @ Rp. 85,000.00 = Rp 28,050.00
0.033 Oh Kepala tukang @ Rp. - = Rp -
0.033 Oh Mandor @ Rp. - = Rp -
= Rp 74,250.00
Total harga = Rp 460,510.00
Bahan pakai 4x = Rp 170,815.00

۞ 1 m3 Membuat beton pondasi 50/50/20 K-225


An. SNI 6.7 + An. SNI 6.17 + An. SNI 6.20
298.287 Kg Besi beton @ Rp. 10,197.50 = Rp 3,041,785.35
1.000 m3 Spesi beton K-225 @ Rp. 875,406.90 = Rp 875,406.90
16.000 m2 Cetakan bekisting @ Rp. 256,905.00 = Rp 4,110,480.00
Total harga = Rp 8,027,672.26

۞ 1 m3 Membuat beton sloof 15/20 K-225


An. SNI 6.7 + An. SNI 6.17 + An. SNI 6.21
166.592 Kg Besi beton @ Rp. 10,197.50 = Rp 1,698,821.92
1.000 m3 Spesi beton K-225 @ Rp. 875,406.90 = Rp 875,406.90
6.667 m2 Cetakan bekisting @ Rp. 114,163.75 = Rp 761,091.67
Total harga = Rp 3,335,320.49

۞ 1 m3 Membuat beton kolom 15/15 K-225


An. SNI 6.7 + An. SNI 6.17 + An. SNI 6.22
210.089 Kg Besi beton @ Rp. 10,197.50 = Rp 2,142,381.44
1.000 m3 Spesi beton K-225 @ Rp. 875,406.90 = Rp 875,406.90
6.667 m2 Cetakan bekisting @ Rp. 155,815.00 = Rp 1,038,766.67
Total harga = Rp 4,056,555.02

۞ 1 m3 Membuat beton balok 15/15 K-225


An. SNI 6.7 + An. SNI 6.17 + An. SNI 6.23
210.432 Kg Besi beton @ Rp. 10,197.50 = Rp 2,145,880.32
1.000 m3 Spesi beton K-225 @ Rp. 875,406.90 = Rp 875,406.90
6.667 m2 Cetakan bekisting @ Rp. 159,265.00 = Rp 1,061,766.67
Total harga = Rp 4,083,053.89

۞ 1 m3 Membuat lisplank beton t=7 cm K-225


An. SNI 6.7 + An. SNI 6.17 + An. SNI 6.23
161.200 Kg Besi beton @ Rp. 10,197.50 = Rp 1,643,837.00
1.000 m3 Spesi beton K-225 @ Rp. 875,406.90 = Rp 875,406.90
10.000 m2 Cetakan bekisting @ Rp. 170,815.00 = Rp 1,708,150.00
Total harga = Rp 4,227,393.90
HITUNGAN VOLUME
KEGIATAN #REF!
LOKASI #REF!
TAHUN #REF!

□ PLAT PONDASI 50X50X20


Persegi 0.500 X 0.500 X 0.200 = 0.050 m3
Besi :
Tulangan horizontal ø 12 mm - 10 cm 1.400 X 6.000 bh 0.888 = 7.457 kg
Tulangan horizontal ø 12 mm - 10 cm 1.400 X 6.000 bh 0.888 = 7.457 kg
Jumlah = 14.914 kg
Volume pondasi = 0.050 m3
Jumlah besi tiap 1 m3 beton = 298.287 kg

□ KOLOM 30/30
Beton 0.300 X 0.300 X 1.000 = 0.090 m3
Besi :
Tulangan ø 12 mm ( polos ) 1.000 X 8.000 bh 0.888 = 7.102 kg
Begel ø 8 mm ( polos ) 1.050 X 6.667 x 0.395 = 2.762 kg
Jumlah besi 9.864 kg
Volume beton 0.090 m3
Jumlah besi tiap 1 m3 beton 109.600 kg

□ BALOK 20/40
Beton 0.200 X 0.400 X 1.000 = 0.080 m3
Besi :
Tulangan ø 12 mm 1.000 X 10.000 bh 0.888 = 8.878 kg
Begel ø 8 mm ( polos ) 1.050 X 6.667 x 0.395 = 2.762 kg
Jumlah besi 11.640 kg
Volume beton 0.080 m3
Jumlah besi tiap 1 m3 beton 145.494 kg

□ BALOK 20/30
Beton 0.200 X 0.300 X 1.000 = 0.060 m3
Besi :
Tulangan ø 12 mm ( polos ) 1.000 X 8.000 bh 0.888 = 7.102 kg
Begel ø 8 mm ( polos ) 0.850 X 6.667 x 0.395 = 2.236 kg
Jumlah besi 9.338 kg
Volume beton 0.060 m3
Jumlah besi tiap 1 m3 beton 155.632 kg

□ SLOOF 15/20
Beton 0.150 X 0.200 X 1.000 = 0.030 m3
Besi :
Tulangan ø 12 mm ( polos ) 1.000 X 4.000 bh 0.888 = 3.551 kg
Begel ø 8 mm ( polos ) 0.550 X 6.667 x 0.395 = 1.447 kg
Jumlah besi 4.998 kg
Volume beton 0.030 m3
Jumlah besi tiap 1 m3 beton 166.592 kg

3 KOLOM 15/15
Beton 0.150 X 0.150 X 1.000 = 0.023 m3
Besi :
Tulangan ø 12 mm ( polos ) 1.000 X 4.000 X 0.887 = 3.548 kg
Begel ø 8 mm ( polos ) 0.450 X 6.667 bh 0.393 = 1.179 kg
Jumlah besi 4.727 kg
Volume beton 0.023 m3
Jumlah besi tiap 1 m3 beton 210.089 kg

4 KOLOM praktis 12/12


Beton 0.120 X 0.120 X 1.000 = 0.014 m3
Besi :
Tulangan ø 8 mm ( polos ) 1.000 X 4.000 X 0.393 = 1.572 kg
Tulangan ø 6 mm ( polos ) 0.410 X 4.000 bh 0.220 = 0.361 kg
Jumlah besi 1.933 kg
Volume beton 0.014 m3
Jumlah besi tiap 1 m3 beton 134.222 kg

5 Beton Sloof 15/20


Beton 0.150 X 0.200 X 1.000 = 0.030 m3
Besi :
Tulangan ø 12 mm ( polos ) 1.000 X 4.000 bh 0.887 = 3.548 kg
Tulangan ø 10 mm ( polos ) 1.000 X 2.000 bh 0.620 = - kg
Begel ø 8 mm ( polos ) 0.550 X 5.000 x 0.393 = 1.081 kg
Jumlah 4.629 kg
Volume beton 0.030 m3
Jumlah besi tiap 1 m3 beton 154.292 kg

□ BALOK 15/15
Volume beton 0.150 X 0.150 X 1.000 = 0.023 m3

Tulangan ø 10 mm ( polos ) 1.000 X 4.000 bh 0.888 = 3.551 kg


Begel ø 8 mm ( polos ) 0.450 X 6.667 x 0.395 = 1.184 kg
Jumlah besi 4.735 kg
Volume beton 0.023 m3
210.432 kg

□ KONSOL 15/30
Volume beton 0.150 X 0.300 X 1.000 = 0.045 m3

Tulangan ø 10 mm ( polos ) 1.000 X 7.000 bh 0.888 = 6.214 kg


Begel ø 8 mm ( polos ) 0.650 X 6.667 x 0.395 = 1.710 kg
Jumlah besi 7.924 kg
Volume beton 0.045 m3
176.091 kg

Jumlah besi tiap 1 m3 beton


14 BALOK RING 15/20
Volume beton 0.150 X 0.200 X 1.000 = 0.030 m3

Tulangan ø 12 mm ( polos ) 1.000 X 4.000 bh 0.888 = 3.551 kg


Begel ø 8 mm ( polos ) 0.550 X 5.714 x 0.395 = 1.240 kg
Jumlah besi 4.791 kg
Volume beton 0.030 m3
Jumlah besi tiap 1 m3 beton 159.703 kg

□ BETON PLAT 12 CM
Plat lantai II 0.120 X 21.000 X 9.550 = 24.066 m3

Tulangan ø 10 mm ( polos ) 21.000 X 64.000 bh 0.617 X 2.00 = 1,657.152 kg


Tulangan ø 10 mm ( polos ) 9.550 X 140.000 bh 0.617 X 2.00 = 824.261 kg
Jumlah besi 2,481.413 kg
Volume beton 24.066 m3
Jumlah besi tiap 1 m3 beton 103.109 kg

□ BETON PLAT 5 CM
Plat lantai II 0.050 X 0.500 X 19.000 = 0.475 m3

Tulangan ø 10 mm ( polos ) 19.000 X 4.000 X 0.620 X 1.00 = 47.120 kg


Tulangan ø 10 mm ( polos ) 0.500 X 95.000 X 0.620 X 1.00 = 29.450 kg
Jumlah besi 76.570 kg
Volume beton 0.475 m3
Jumlah besi tiap 1 m3 beton 161.200 kg
PEKERJAAN LANTAI

۞ 1 m2 Pasang lantai keramik 40 x 40 cm


Bahan An. SNI 6.35
6.250 Bh Ubin keramik 40x40 cm @ Rp. 6,800.00 = Rp 42,500.00
10.000 Kg Semen portland @ Rp. 1,200.00 = Rp 12,000.00
0.045 m3 Pasir pasang @ Rp. 197,000.00 = Rp 8,865.00
1.500 Kg Semen warna @ Rp. 12,000.00 = Rp 18,000.00
= Rp 81,365.00
Upah An. SNI 6.35
0.700 Oh Pekerja @ Rp. 70,000.00 = Rp 49,000.00
0.350 Oh Tukang batu @ Rp. 85,000.00 = Rp 29,750.00
0.035 Oh Kepala tukang @ Rp. - = Rp -
0.035 Oh Mandor @ Rp. - = Rp -
= Rp 78,750.00
Total harga = Rp 160,115.00

۞ 1 m2 Pasang lantai keramik 20 x 20 cm


Bahan An. SNI 6.36
26.500 Bh Ubin keramik 20x20 cm @ Rp. 1,920.00 = Rp 50,880.00
10.400 Kg Semen portland @ Rp. 1,200.00 = Rp 12,480.00
0.045 m3 Pasir pasang @ Rp. 197,000.00 = Rp 8,865.00
1.620 Kg Semen warna @ Rp. 12,000.00 = Rp 19,440.00
= Rp 91,665.00
Upah An. SNI 6.36
0.700 Oh Pekerja @ Rp. 70,000.00 = Rp 49,000.00
0.350 Oh Tukang batu @ Rp. 85,000.00 = Rp 29,750.00
0.035 Oh Kepala tukang @ Rp. - = Rp -
0.035 Oh Mandor @ Rp. - = Rp -
= Rp 78,750.00
Total harga = Rp 170,415.00
PEKERJAAN LANTAI

۞ 1 m2 Pasang lantai keramik 30 x 30 cm


Bahan An. SNI 6.35
11.870 Bh Ubin keramik 30x30 cm @ Rp. 3,825.00 = Rp 45,402.75
10.000 Kg Semen portland @ Rp. 1,200.00 = Rp 12,000.00
0.045 m3 Pasir pasang @ Rp. 197,000.00 = Rp 8,865.00
1.500 Kg Semen warna @ Rp. 1,200.00 = Rp 1,800.00
= Rp 68,067.75
Upah An. SNI 6.35
0.671 Oh Pekerja @ Rp. 70,000.00 = Rp 46,995.45
0.350 Oh Tukang batu @ Rp. 85,000.00 = Rp 29,750.00
0.035 Oh Kepala tukang @ Rp. - = Rp -
0.035 Oh Mandor @ Rp. - = Rp -
= Rp 76,745.45
Total harga = Rp 144,813.20
PEKERJAAN PENGECATAN

۞ 1 m2 Pengecatan bidang kayu baru ( 1x plamir , 1x cat dasar, 2x cat penutup )


Bahan An. SNI 6.8.1
0.200 Kg Cat meni @ Rp. 26,000.00 = Rp 5,200.00
0.150 Kg Plamir @ Rp. 25,000.00 = Rp 3,750.00
0.170 Kg Cat dasar @ Rp. 58,500.00 = Rp 9,945.00
0.100 lbr Kertas Gosok @ Rp. 3,500.00 = Rp 350.00
0.260 Kg Cat penutup 2x @ Rp. 58,500.00 = Rp 15,210.00
= Rp 34,455.00
Upah An. SNI 6.8.2
0.070 Oh Pekerja @ Rp. 70,000.00 = Rp 4,900.00
0.009 Oh Tukang cat @ Rp. 85,000.00 = Rp 765.00
0.0060 Oh Kepala tukang @ Rp. - = Rp -
0.0025 Oh Mandor @ Rp. - = Rp -
. = Rp 5,665.00
Total harga = Rp 40,120.00

۞ 1 m2 Pengecatan tembok baru & plafond ( 1x plamir , 1x cat dasar, 4x cat penutup )
Bahan An. SNI 6.14.1
0.100 Kg Plamir @ Rp. 29,000.00 = Rp 2,900.00
0.100 lbr Kertas Gosok @ Rp. 3,500.00 = Rp 350.00
0.100 Kg Cat dasar @ Rp. 18,800.00 = Rp 1,880.00
0.520 Kg Cat penutup 4x @ Rp. 18,800.00 = Rp 9,776.00
= Rp 14,906.00
Upah An. SNI 6.14.2
0.020 Oh Pekerja @ Rp. 70,000.00 = Rp 1,400.00
0.063 Oh Tukang cat @ Rp. 85,000.00 = Rp 5,355.00
0.0063 Oh Kepala tukang @ Rp. - = Rp -
0.0025 Oh Mandor @ Rp. - = Rp -
. = Rp 6,755.00
Total harga = Rp 21,661.00
PEKERJAAN SANITAIR

۞ Memasang 1 buah kloset jongkok


Bahan An. SNI 6.1.1
1.000 Bh Kloset jongkok @ Rp. 120,000.00 = Rp 120,000.00
6% harga kloset = Perlengkapan @ Rp. 7,200.00 = Rp 7,200.00
= Rp 127,200.00
Upah An. SNI 6.1.2
3.300 Oh Pekerja @ Rp. 70,000.00 = Rp 231,000.00
1.100 Oh Tukang batu @ Rp. 85,000.00 = Rp 93,500.00
0.001 Oh Kepala tukang @ Rp. - = Rp -
0.1600 Oh Mandor @ Rp. - = Rp -
= Rp 324,500.00
Total harga = Rp 451,700.00

۞ Memasang 1 m' pipa PVC tipe AW ø 3/4"


Bahan An. SNI ( Revisi ) 6.26.1
1.200 m' Pipa PVC @ Rp. 6,875.00 = Rp 8,250.00
35% harga pipa = Perlengkapan @ Rp. 2,406.25 = Rp 2,406.25
= Rp 10,656.25
Upah An. SNI ( Revisi ) 6.26.2
0.036 Oh Pekerja @ Rp. 70,000.00 = Rp 2,520.00
0.060 Oh Tukang batu @ Rp. 85,000.00 = Rp 5,100.00
0.006 Oh Kepala tukang @ Rp. - = Rp -
0.0018 Oh Mandor @ Rp. - = Rp -
= Rp 7,620.00
Total harga = Rp 18,276.25

۞ Memasang 1 m' pipa PVC tipe AW ø 3"


Bahan An. SNI ( Revisi ) 6.31.1
1.200 m' Pipa PVC @ Rp. 41,250.00 = Rp 49,500.00
35% harga pipa = Perlengkapan @ Rp. 7,425.00 = Rp 7,425.00
= Rp 56,925.00
Upah An. SNI ( Revisi ) 6.31.2
0.081 Oh Pekerja @ Rp. 70,000.00 = Rp 5,670.00
0.135 Oh Tukang batu @ Rp. 85,000.00 = Rp 11,475.00
0.0135 Oh Kepala tukang @ Rp. - = Rp -
0.0041 Oh Mandor @ Rp. - = Rp -
= Rp 17,145.00
Total harga = Rp 74,070.00

۞ Memasang 1 buah kran ø 3/4" atau 1/2"


Bahan An. SNI ( Revisi ) 6.35.1
1.000 Bh Kran air @ Rp. 28,750.00 = Rp 28,750.00
0.025 Bh Seal tape @ Rp. 3,450.00 = Rp 86.25
= Rp 28,836.25
Upah An. SNI ( Revisi ) 6.35.2
0.010 Oh Pekerja @ Rp. 70,000.00 = Rp 700.00
0.100 Oh Tukang batu @ Rp. 85,000.00 = Rp 8,500.00
0.010 Oh Kepala tukang @ Rp. - = Rp -
0.005 Oh Mandor @ Rp. - = Rp -
= Rp 9,200.00
Total harga = Rp 38,036.25

۞ Memasang 1 buah floor drain


Bahan An. SNI ( Revisi ) 6.36.1
1.000 Bh Floor drain @ Rp. 23,000.00 = Rp 23,000.00
= Rp 23,000.00
Upah An. SNI ( Revisi ) 6.36.2
0.010 Oh Pekerja @ Rp. 70,000.00 = Rp 700.00
0.100 Oh Tukang batu @ Rp. 85,000.00 = Rp 8,500.00
0.010 Oh Kepala tukang @ Rp. - = Rp -
0.005 Oh Mandor @ Rp. - = Rp -
= Rp 9,200.00
Total harga = Rp 32,200.00
PEKERJAAN ATAP

۞ 1 m3 Pasang konstruksi gordeng kayu kelas II


Bahan An. SNI 6.15
1.100 m3 Kayu kruing, balok @ Rp. 5,600,000.00 = Rp 6,160,000.00
7.500 Kg Besi strip @ Rp. 15,000.00 = Rp 112,500.00
0.800 Kg Paku biasa 2" - 5" @ Rp. 12,500.00 = Rp 10,000.00
= Rp 6,282,500.00
Upah An. SNI 6.15
2.400 Oh Pekerja @ Rp. 70,000.00 = Rp 168,000.00
7.200 Oh Tukang kayu @ Rp. 85,000.00 = Rp 612,000.00
0.720 Oh Kepala tukang @ Rp. - = Rp -
0.120 Oh Mandor @ Rp. - = Rp -
= Rp 780,000.00
Total harga = Rp 7,062,500.00

۞ 1 m2 Pasang usuk + reng galvalume


Bahan An. SNI 6.17
2.750 m' Usuk galvalume @ Rp. 25,000.00 = Rp 68,750.00
3.5500 m' Reng galvalume @ Rp. 14,000.00 = Rp 49,700.00
0.250 Kg Paku Sekrup @ Rp. 30,000.00 = Rp 7,500.00
= Rp 125,950.00
Upah An. SNI 6.17
0.400 Oh Pekerja @ Rp. 70,000.00 = Rp 28,000.00
0.100 Oh Tukang kayu @ Rp. 85,000.00 = Rp 8,500.00
0.010 Oh Kepala tukang @ Rp. - = Rp -
0.005 Oh Mandor @ Rp. - = Rp -
= Rp 36,500.00
Total harga = Rp 162,450.00

۞ 1 m2 Pasang atap genteng


Bahan An. SNI 6.2.1
25.000 Bh Genteng plenthong @ Rp. 3,500.00 = Rp 87,500.00
= Rp 87,500.00
Upah An. SNI ( Revisi ) 6.2.2
0.150 Oh Pekerja @ Rp. 70,000.00 = Rp 10,500.00
0.075 Oh Tukang kayu @ Rp. 85,000.00 = Rp 6,375.00
0.008 Oh Kepala tukang @ Rp. - = Rp -
0.008 Oh Mandor @ Rp. - = Rp -
= Rp 16,875.00
Total harga = Rp 104,375.00
۞ 1 m' Pasang genteng bubungan
Bahan An. SNI 6.5.1
5.000 Bh Genteng bubung plenthong kecil@ Rp. 6,000.00 = Rp 30,000.00
8.000 Kg Semen portland @ Rp. 1,200.00 = Rp 9,600.00
0.032 m3 Pasir pasang @ Rp. 650.00 = Rp 20.80
= Rp 39,620.80
Upah An. SNI 6.5.2
0.400 Oh Pekerja @ Rp. 70,000.00 = Rp 28,000.00
0.200 Oh Tukang kayu @ Rp. 85,000.00 = Rp 17,000.00
0.020 Oh Kepala tukang @ Rp. - = Rp -
0.002 Oh Mandor @ Rp. - = Rp -
= Rp 45,000.00
Total harga = Rp 84,620.80
KEBUTUHAN BAHAN TAHAP I

KEGIATAN : REHABILITASI SEDANG/BERAT GEDUNG SEKOLAH


LOKASI : SMKN GUDO
TAHUN ANGGARA : 2014

NO URAIAN PEKERJAAN Volume Harga yang


dipakai untuk SUB TOTAL JUMLAH HARGA
Total Total SAT
Dari Dana penyusunan (Rp) ( Rp. )
Keseluruha Pengeluar KAKS (Rp)
APBD
n an
1 2 3 4 5 6 7 8 9

I PEKERJAAN PERSIAPAN
1 Pembongkaran dan pembersihan lokasi 1.00 1.00 1.00 ls 2,400,000.00 2,400,000.00

2 Pasang papan nama 1.00 1.00 1.00 bh 300,000.00 300,000.00


Sub jumlah 2,700,000.00

II PEKERJAAN TANAH
1 Galian tanah pondasi 28.40 m3
Upah : Pekerja 21.30 Oh 70,000.00 1,491,000.00

2 Urugan tanah kembali 9.47 m3


Upah : Pekerja 2.37 Oh 70,000.00 165,666.67

3 Urugan pasir bawah pondasi dan lantai 0.36 m3


Bahan : Pasir Pasang 0.43 m3 197,000.00 85,104.00
Upah : Pekerja 0.11 Oh 70,000.00 7,560.00
Sub jumlah 1,749,330.67

III PEKERJAAN PONDASI


1 Pasangan anstampeng 1.44 m3 -
Bahan : Batu belah ( 15/20 ) 1.73 m3 194,000.00 335,232.00
Pasir pasang 0.43 m3 197,000.00 85,104.00

Upah : Pekerja 1.12 Oh 70,000.00 78,624.00


Tukang batu 0.56 Oh 85,000.00 47,736.00

2 Pondasi batu kali 1Pc:6Ps 2.77 m3


Bahan : Batu belah ( 15/20 ) 3.33 m3 194,000.00 645,321.60
Semen porland 324.32 Kg 1,200.00 389,188.80
Pasir pasang 1.56 m3 197,000.00 306,353.12

Upah : Pekerja 4.16 Oh 70,000.00 291,060.00


Tukang batu 2.08 Oh 85,000.00 176,715.00
Sub jumlah 2,355,334.52

IV PEKERJAAN BETON STRUKTUR


1 Lantai kerja di bawah pondasi dan lantai 2.05 m3
Bahan : Semen portland 9.43 Zak 48,000.00 452,640.00
Pasir beton 1.31 m3 197,000.00 257,598.61
Kerikil ( Maksimum 30 mm ) 1.56 m3 249,000.00 388,320.11

Upah : Pekerja 2.46 Oh 70,000.00 172,200.00


Tukang batu 0.41 Oh 85,000.00 34,850.00

2 Pondasi beton 110/100/30 5.61 m3


Besi beton 298.29
Bahan : Besi beton ( polos/ulir ) 1,757.06 Kg 8,500.00 14,935,024.40
Kawat beton 25.10 Kg 12,500.00 313,761.02
Upah : Pekerja 11.71 Oh 70,000.00 819,962.12
Tukang besi 11.71 Oh 85,000.00 995,668.29
Spesi beton K-225 1.00
Bahan : Semen portland 2,081.31 Kg 1,200.00 2,497,572.00
NO URAIAN PEKERJAAN Volume Harga yang
dipakai untuk SUB TOTAL JUMLAH HARGA
Total Total SAT
Dari Dana penyusunan (Rp) ( Rp. )
Keseluruha Pengeluar KAKS (Rp)
APBD
n an
1 2 3 4 5 6 7 8 9
Pasir beton 2.80 m3 197,000.00 551,006.19
Kerikil ( Maksimum 30 mm ) 4.35 m3 249,000.00 1,083,365.80
Upah : Pekerja 9.26 Oh 70,000.00 647,955.00
Tukang batu 1.54 Oh 85,000.00 131,133.75
Cetakan bekisting
Bahan : Kayu terentang 16.00 3.59 m3 4,850,000.00 17,413,440.00
Paku biasa 2" - 5" 26.93 Kg 12,500.00 336,600.00
Minyak bekisting 8.98 Ltr 6,550.00 58,792.80
Upah : Pekerja 46.68 Oh 70,000.00 3,267,264.00
Tukang batu 23.34 Oh 85,000.00 1,983,696.00

3 Sloof beton 15/25 0.27 m3


4 Kolom beton 30/30 7.80 m3
5 Balok beton 25/50 4.60 m3
6 Balok beton 15/30 2.68 m3
7 Balok beton 15/25 0.71 m3
8 Konsol 15/30 0.63 m3
9 Balok beton 15/20 0.57 m3
10 Plat deck 12 cm 20.98 m3
11 Lisplank beton t=5cm 0.48 m3
Sub jumlah -

V PEKERJAAN PASANGAN & PLESTERAN


1 Pasangan 1/2 bata 1Pc : 3Ps 29.80 m2 100,124.00 2,983,695.20
2 Plesteran 1Pc : 3Ps tebal 15mm 59.60 m2 45,269.00 2,698,032.40
3 Pasangan 1/2 bata 1Pc : 6Ps 152.47 m2 94,637.00 14,428,886.99
4 Plesteran 1Pc : 6Ps tebal 15mm 304.93 m2 35,697.00 10,885,129.05
7. Benangan/Tali air 66.89 m' 12,387.00 828,581.29
Sub jumlah 31,824,324.93

VI PEKERJAAN KUSEN
1 Pasang kusen pintu dan jendela 0.92 m3 11,577,625.00 10,657,435.37
2 Pasang daun pintu panil 5.60 m2 671,000.00 3,757,600.00
3 Pasang Daun Jendela kaca 11.40 m2 467,600.00 5,330,640.00
4 Pasang kunci tanam biasa 2.00 bh 104,200.00 208,400.00
5 Pasang engsel pintu 6.00 set 36,300.00 217,800.00
6 Pasang engsel jendela 16.00 set 25,200.00 403,200.00
7 Pasang grendel 18.00 bh 27,400.00 493,200.00
8 Pasang kaca jendela, tebal 5 mm 28.66 m2 110,600.00 3,169,796.00
Sub jumlah 24,238,071.37

VII PEKERJAAN LANTAI DAN DINDING


1 Pasang lantai keramik 30/30 27.00 m2 160,115.00 4,323,105.00
Sub jumlah 4,323,105.00

VIII PEKERJAAN PENGECATAN


1 Pengecatan dinding baru 304.93 m2 21,661.00 6,605,114.72
2 Pengecatan plat 174.80 m2 21,661.00 3,786,342.80
3 Pengecatan kayu baru 50.22 m2 40,120.00 2,014,649.87
Sub jumlah 12,406,107.40

IX PEKERJAAN LISTRIK
1 Pasang instalasi listrik 16.00 ttk 125,000.00 2,000,000.00
2 Pasang lampu TL 12.00 bh 200,000.00 2,400,000.00
NO URAIAN PEKERJAAN Volume Harga yang
dipakai untuk SUB TOTAL JUMLAH HARGA
Total Total SAT
Dari Dana penyusunan (Rp) ( Rp. )
Keseluruha Pengeluar KAKS (Rp)
APBD
n an
1 2 3 4 5 6 7 8 9
3 Pasang lampu SL 2.00 bh 25,000.00 50,000.00
4 Pasang stop kontak 2.00 bh 14,000.00 28,000.00
5 Pasang saklar tunggal 1.00 bh 12,500.00 12,500.00
6 Pasang saklar ganda 2.00 bh 15,000.00 30,000.00
Sub jumlah 4,520,500.00

Jombang, 2016
Dibuat oleh :
Perencana

0
HITUNGAN VOLUME
KEGIATAN #REF!
LOKASI #REF!
TAHUN #REF!

1 P2
Kusen 4.400 4.200 1.000 bh = 8.600 m1

Daun Pintu 2.200 X 2.000 1.000 bh = 4.400 m2


Kaca Daun Pintu 2.000 X 0.800 1.000 bh = 1.600 m2
Kaca Jendela 2.650 X 0.350 1.000 bh = 0.928 m2
Kaca Bovelight 0.500 X 2.000 1.000 bh = 1.000 m2
Sanblast 1.000 X 0.700 2.000 bh = 1.400 m2

2 P3
Kusen 4.400 1.000 3.000 bh = 16.200 m1

Daun Pintu 2.200 X 0.900 3.000 bh = 5.940 m2


Kaca Daun Pintu 2.000 X 0.700 3.000 bh = 4.200 m2
Sanblast 1.000 X 0.700 3.000 bh = 2.100 m2

3 P4
Kusen 4.400 1.000 1.000 bh = 5.400 m1

Daun Pintu 2.200 X 0.900 1.000 bh = 1.980 m2


Kaca Daun Pintu 2.000 X 0.700 1.000 bh = 1.400 m2
Sanblast 1.900 X 0.700 1.000 bh = 1.330 m2

4 J1
Kusen 8.880 5.700 4.000 bh = 58.320 m1

Kaca 2.220 X 0.860 12.000 bh = 22.910 m2

5 J2
Kusen 8.880 4.700 1.000 bh = 13.580 m1

Kaca 2.220 X 0.720 3.000 bh = 4.795 m2

8 J3
Kusen 3.680 1.000 8.000 bh = 37.440 m1

Daun Jendela 0.400 X 1.850 8.000 bh = 5.920 m2


Kaca Jendela 1.700 X 0.250 8.000 bh = 3.400 m2

9 J4
Kusen 4.500 4.050 3.000 bh = 25.650 m1

Daun Bovenlight 0.600 X 0.430 6.000 bh = 1.548 m2


Daun Jendela 0.600 X 1.020 6.000 bh = 3.672 m2
Kaca Bovenlight 0.300 X 0.450 6.000 bh = 0.810 m2
Kaca Jendela 0.450 X 0.860 6.000 bh = 2.322 m2

12 B1
Kusen 1.060 1.200 1.000 bh = 2.260 m1

Kaca 0.600 X 0.240 2.000 bh = 0.288 m2

2 JP
Kusen 7.060 3.980 3.000 bh = 33.120 m1

Daun Pintu 2.200 X 0.900 3.000 bh = 5.940 m2


Kaca Daun Pintu 2.000 X 0.700 3.000 bh = 4.200 m2
Sanblast 1.000 X 0.700 3.000 bh = 2.100 m2
Daun Jendela 1.330 X 0.700 6.000 bh = 5.586 m2
Kaca Jendela 0.550 X 1.170 6.000 bh = 3.861 m2
DOKUMENTASI FOTO
JL. DARUREJO - PURISEMANDING

#REF! : #REF!
#REF! : #REF!
#REF! : #REF!
0 : 0

STA 0+000

STA 0+050
STA 0+100
DOKUMENTASI FOTO
JL. DARUREJO - PURISEMANDING

#REF! : #REF!
#REF! : #REF!
#REF! : #REF!
0 : 0

STA 0+150

STA 0+200
STA 0+235
BACK UP VOLUME

KEGIATAN : REHABILITASI SEDANG/BERAT GEDUNG SEKOLAH


LOKASI : SMKN GUDO
TAHUN ANGGARAN : 2014

NO URAIAN PEKERJAAN PERHITUNGAN VOLUME VOL. SAT

1 2 3 4 5

I PEKERJAAN PERSIAPAN
1 Pembongkaran dan pembersihan lokasi =1 1.00 ls
2 Pasang papan nama =1 1.00 bh

II PEKERJAAN TANAH
1 Galian tanah pondasi =(0,95*1)*7,2+(1,1*1*1,4)*14 28.40 m3
2 Urugan tanah kembali =1/3*28,40 9.47 m3
3 Urugan pasir bawah pondasi dan lantai =(0,05*1)*7,2 0.36 m3

III PEKERJAAN PONDASI


1 Pasangan anstampeng =(0,2*1)*7,2 1.44 m3
2 Pondasi batu kali 1Pc:6Ps =(0,5*(0,3+0,8)*0,7)*7,2 2.77 m3

IV PEKERJAAN BETON STRUKTUR


1 Lantai kerja di bawah pondasi dan lantai =(0,1*1,1*1)*17+(0,05*7,2)*0,5 2.05 m3
2 Pondasi beton 110/100/30 =(1,1*1*0,3)*17 5.61 m3
3 Sloof beton 15/25 =(0,15*0,25)*7,2 0.27 m3
4 Kolom beton 30/30 =(0,3*0,3)*(17*5,1) 7.80 m3
5 Balok beton 25/50 =(0,25*0,5)*(9,2*4) 4.60 m3
6 Balok beton 15/30 =(0,15*0,3)*(19*2+7,2*3) 2.68 m3
7 Balok beton 15/25 =(0,15*0,25)*(19) 0.71 m3
8 Konsol 15/30 =(0,15*0,3)*(2*7) 0.63 m3
9 Balok beton 15/20 =(0,15*0,2)*(19) 0.57 m3
10 Plat deck 12 cm =19*9,2*0,12 20.98 m3
11 Lisplank beton t=5cm =(0,05*0,5*19) 0.48 m3

V PEKERJAAN PASANGAN & PLESTERAN


1 Pasangan 1/2 bata 1Pc : 3Ps =(19*2+7,2*3)*0,5 29.80 m2
2 Plesteran 1Pc : 3Ps tebal 15mm =29,80*2 59.60 m2
3 Pasangan 1/2 bata 1Pc : 6Ps =(19*2+7,2*3)*3-26,33 152.47 m2
4 Plesteran 1Pc : 6Ps tebal 15mm =152,47*2 304.93 m2
7. Benangan/Tali air =((2,47*2+1,52)*2+(1,59*1,48)*8)*2+3,4 66.89 m'

VI PEKERJAAN KUSEN
1 Pasang kusen pintu dan jendela =102,28*0,06*0,15 0.92 m3
2 Pasang daun pintu panil =(1,4*2)*2 5.60 m2
3 Pasang Daun Jendela kaca =(0,75*0,95)*(8*2) 11.40 m2
4 Pasang kunci tanam biasa =2 2.00 bh
5 Pasang engsel pintu =6 6.00 set
6 Pasang engsel jendela =16 16.00 set
7 Pasang grendel =18 18.00 bh
NO URAIAN PEKERJAAN PERHITUNGAN VOLUME VOL. SAT

1 2 3 4 5
8 Pasang kaca jendela, tebal 5 mm =(0,75*0,95+0,25*0,75*2)*(8*2)+(0,85*0,95+0,25*0,85*2)*8 28.66 m2
+(1,4*0,25*2*2)

VII PEKERJAAN LANTAI DAN DINDING


1 Pasang lantai keramik 30/30 =(1,2*1,2)*14+(0,6*7,2)+(0,6*0,6)*7 27.00 m2
NO URAIAN PEKERJAAN PERHITUNGAN VOLUME VOL. SAT

1 2 3 4 5
VIII PEKERJAAN PENGECATAN
1 Pengecatan dinding baru =152,47*2 304.93 m2
2 Pengecatan plat =19*9,2 174.80 m2
3 Pengecatan kayu baru =102,28*0,27+5,6*2+11,4 50.22 m2

IX PEKERJAAN LISTRIK
1 Pasang instalasi listrik =16 16.00 ttk
2 Pasang lampu TL =12 12.00 bh
3 Pasang lampu SL =2 2.00 bh
4 Pasang stop kontak =2 2.00 bh
5 Pasang saklar tunggal =1 1.00 bh
6 Pasang saklar ganda =2 2.00 bh
DAFTAR HARGA SATUAN BAHAN & UPAH TENAGA KERJA
KEGIATAN #REF!
LOKASI #REF!
TAHUN #REF!

Harga
No. Jenis Bahan Satuan Satuan
1 2 3 4

A. Bahan Pasir dan Tanah


1. Pasir Pasang m3 130,000.00
2. Pasir Cor / Beton m3 130,000.00
3. Pasir Urug m3 110,000.00
4. Tanah Urug m3 65,000.00
B. Bahan Batu
1. Batu Kali Pecah 2/3 ( mesin ) m3 210,000.00
2. Batu Bata merah ( kelas I ) bh 600.00
3. Batu Belah 15/20 m3 140,000.00
C. Bahan Semen
1. Semen Warna kg 14,000.00
2. Semen PC SNI 40 kg zak 57,000.00
D. Bahan kapur
1. Kapur Padam m3 250,000.00
E. Bahan Lantai
1. Lantai keramik polos 30x30 cm m2 45,000.00
2. Lantai keramik motif 20x20 cm m2 50,000.00
3. Dinding keramik motif 20x25 cm m2 52,000.00
4. Lantai Granite(Ex China) 60x60 cm m2 150,000.00
F. Bahan Kayu
1. Kayu Kamfer balok 6/15 m3 8,280,000.00
2. Kayu kamfer papan 3/30/300 m3 9,315,000.00
3. Kayu kruing balok 8/12,6/12 m3 5,485,000.00
4. Kayu meranti / berneo balok 8/12, 6/15 m3 4,970,000.00
5. Kayu meranti papan begesting m3 1,500,000.00
6. Kayu kruing usuk 5/7 m3 4,815,000.00
8. Triplek 120,240,6 mm lbr 120,000.00
9. List kayu profil 5cm-1cm m' 10,000.00
10. Bambu bongkotan btg 18,500.00
G. Bahan Besi
1. Besi beton Polos kg 9,000.00
1. Besi strip kg 15,000.00
2. Kawat bendrat kg 15,000.00
3. Paku 2" - 5" kg 12,500.00
4. Talang plat BJLS 28 lbr' 52,500.00
Harga
No. Jenis Bahan Satuan Satuan
1 2 3 4

H. Bahan Penutup
1. Genteng kodok bh 1,800.00
2. Bubungan genteng kodok bh 5,000.00
3 Asbes Eternit lbr 15,500.00
I. Bahan Cat
1. Plamur tembok kg 15,000.00
2. Plamur kayu " PEDANG " kg 25,000.00
3. Cat kayu / besi EMCO/setara kg 53,000.00
4. Cat tembok "DECOLITH" kg 16,500.00
5. Cat meni "PEDANG" kg 22,500.00
6. Dempul kayu kg 20,000.00
7. Minyak cat / thiner B ltr 15,500.00
8. Lem kayu ltr 11,500.00
9. Residu / Ter ltr 10,000.00
10. Minyak Begisting ltr 10,000.00
11. Ampelas / kertas gosok lbr 3,500.00
12. Kuas cat bh 15,000.00
J. Bahan Kaca
1. Kaca bening 5 mm m2 77,500.00
K. Bahan Accecoris Kusen
1. Kunci tanam bh 78,000.00
2. Engsel pintu bh 30,500.00
3. Engsel jendela bh 18,000.00
4. Grendel pintu / jendela bh 10,000.00
L. Bahan lampu dan instalasi listrik
1. Pasang Instalasi Listrik + Ongkos Pasang ttk 125,000.00
2. Pasang lampu downlight 6" lengkap (lampu+accesoris) bh 200,000.00
3. Lampu SL 15 w PHILIPS + Ongkos Pasang + Accecoris bh 25,000.00
4. Stop Kontak "BROCO" + Ongkos Pasang bh 14,000.00
5. Saklar tunggal "BROCO" + Ongkos Pasang bh 12,500.00
6. Saklar ganda " BROCO " + Ongkos Pasang bh 15,000.00
7. Sekering ganda "LN" bh 17,500.00
8. Panel MCB unit 91,000.00
M. Harga upah tenaga kerja
1. Mandor Org/hr -
2. Kepala Tukang Org/hr -
3. Tukang Batu Org/hr 65,000.00
4. Tukang Kayu Org/hr 65,000.00
5. Tukang Cat Org/hr 65,000.00
6. Tukang Besi Org/hr 65,000.00
7. Pekerja Org/hr 55,000.00

Anda mungkin juga menyukai