RENCANA ANGGARAN BIAYA

BILL OF QUANTITY

Pekerjaan : Gudang Pupuk Permanen (Kap. 1000 Ton)


Volume : 30 x 12 M

No. URAIAN

I PEKERJAAN PERSIAPAN

II PEKERJAAN STUKTUR

III PEKERJAAN DINDING

IV PEKERJAAN LANTAI

V PEKERJAAN INSTALASI LISTRIK

VI PEKERJAAN PINTU DAN ANGIN ANGIN

VII PEKERJAAN PENGECATAN

Terbilang : Sembilan Ratus Lima Juta Rupiah


HARGA JUMLAH
SATUAN HARGA `
( Rp. ) ( Rp. )
24,500,000 24,500,000

435,899,880 435,899,880

98,855,163 98,855,163

290,942,685 290,942,685

15,215,000 15,215,000

18,000,000 18,000,000

21,640,754 21,640,754

Grand Total 905,053,482


Dibulatkan 905,000,000

Harga / M2 2,513,888.89
RENCANA ANGGARAN BIAYA
BILL OF QUANTITY

Pekerjaan : Gudang Pupuk Permanen (Kap. 1000 Ton)


Volume : 30 x 12 M

HARGA JUMLAH
No. URAIAN VOLUME SAT SATUAN HARGA
( Rp. ) ( Rp. )
I PEKERJAAN PERSIAPAN
1 Mobilisasi Alat, Bahan dan Tenaga Kerja 1.00 Ls 15,000,000 15,000,000
2 Pembersihan Lokasi Pekerjaan 1.00 Ls 7,000,000 7,000,000
3 Pengukuran dan Pasang Bowplank 1.00 Ls 2,500,000 2,500,000
24,500,000
II PEKERJAAN STUKTUR
4 Pekerjaan Struktur Utama Gudang 360.00 m2 1,210,833 435,899,880
- Galian Pondasi Tapak, Kedalaman 1,2 m
- Lantai Kerja Pondasi Tapak 80 x 80 x 5 cm
- Pondasi Tapak 80 x 80 x 25 cm, Beton Bertulang Camp. 1 Pc : 2 Ps : 3 Kr,
Tulangan Besi Ø 12 SNI
- Sloof (25/40), Beton Bertulang Camp. 1 Pc : 2 Ps : 3 Kr, Besi Ø 12 SNI
- Kolom Pedestal (25/40) Tinggi 1.2 m, Beton Bertulang Camp. 1 Pc : 2 Ps : 3 Kr,
Tulangan Besi Ø 12 SNI
- Kolom Baja IWF 300 x 150 x 6.5 x 9, Tinggi 6 m
- Kuda - Kuda Baja IWF 250 x 125 x 6 x 9
- Gording CNP 125 x 50 x 20 x 2.3
- Ikatan Angin Besi BJTP Ø12 + Aksesoris
- Penutup Atap Zinkalume 0.35 mm AZ 150 + Nok
- Listplank GRC Lebar 25 cm
- Cat IWF dan CNP anti karat Zingkromate Ex. Kansai Grey / Green
435,899,880
III PEKERJAAN DINDING
5 Kolom Praktis (10/10), Beton Bertulang Camp. 1 Pc : 2 Ps : 3 Kr, 1.26 m3 9,013,843 11,357,443
Tulangan Utama 4Ø8 Sengkang Ø6-150
6 Ring Balk (10/15), Beton Bertulang Camp. 1 Pc : 2 Ps : 3 Kr, 1.58 m3 6,731,175 10,601,601
Tulangan Utama 4Ø8 Sengkang Ø6-150
7 Dinding Batu Tela 1 Pc : 4 Ps 304.00 m2 132,285 40,214,640
8 Plesteran Dinding 1 Pc : 3 Ps + Aci Halus 628.00 m2 58,410 36,681,480
98,855,163
IV PEKERJAAN LANTAI
9 Urugan Pasir dan Batu (Sirtu) dipadatkan, Tebal 15 cm 54.00 m3 208,200 11,242,800
10 Lantai Gudang 54.00 m3 4,610,643 248,974,725
- Lantai Beton Bertulang Camp. 1Pc : 2Ps : 3Kr, Tebal 15 Cm
Tulangan Rangkap Ø 10, Finishing Halus
- Papan Begisting Sekat (1/20), Kayu Kelas II
11 Lantai Selasar Tebal 10 Cm 13.50 m3 1,750,000 23,625,000
- Beton Rabat Camp. 1Pc : 3 Ps : 5 Kr
12 Parit Keliling Gudang 96.00 m1 73,960 7,100,160
- Pasangan Batako 1 Pc : 4 Ps + Aci
290,942,685
V PEKERJAAN INSTALASI LISTRIK
13 Instalasi 1 Titik Lampu Phillips 100 W + Fitting dan Kap, Kabel NYA 2 x 2.5 dengan Pipa PVC 5/8" 19.00 Titik 790,000 15,010,000
+ Saklar merek Panasonic dan Aksesoris
14 Stop Kontak merek Panasonic, Kabel NYA 2 x 2.5 dibungkus Pipa PVC 5/8" + Aksesoris 2.00 Titik 65,000 130,000
15 MCB 10 A + Box 1.00 Bh 75,000 75,000
15,215,000
VI PEKERJAAN PINTU DAN ANGIN ANGIN
16 Pintu Geser Baja ( 2 x 4 x 2 ) Tebal 5 Cm + Aksesoris 2.00 Set 9,000,000 18,000,000
17 Angin - Angin Rangka Kayu Kelas II, Isi Kawat Harmonika Tebal 50 mm 84.00 m2 -
18,000,000
VII PEKERJAAN PENGECATAN
18 Cat Dinding "Vinilex" ( 1 Lps Cat Dasar 2 Lps Cat Penutup ) 628.00 m2 32,231 20,240,754
19 Pengecatan Pintu Besi "Platone" ( 1 Lps Cat Dasar, 2 Lps Cat Penutup) 4.00 Ls 350,000 1,400,000
21,640,754
GRAND TOTAL 905,053,482
DIBULATKAN 905,000,000
RENCANA ANGGARAN BIAYA
BILL OF QUANTITY

Pekerjaan : Gudang Pupuk Permanen (Kap. 1000 Ton)


Volume : 30 x 12 M

HARGA JUMLAH
No. URAIAN VOLUME SAT SATUAN HARGA
( Rp. ) ( Rp. )
I PEKERJAAN PERSIAPAN
1 Mobilisasi Alat, Bahan dan Tenaga Kerja 1.00 Ls 12,000,000 12,000,000
2 Pembersihan Lokasi Pekerjaan 1.00 Ls 2,000,000 2,000,000
3 Pengukuran dan Pasang Bowplank 1.00 Ls 1,000,000 1,000,000
15,000,000
II PEKERJAAN STUKTUR
4 Pekerjaan Struktur Utama Gudang 360.00 m2 1,320,000 475,200,000
- Galian Pondasi Tapak, Kedalaman 1,2 m
- Lantai Kerja Pondasi Tapak 80 x 80 x 5 cm
- Pondasi Tapak 80 x 80 x 25 cm, Beton Bertulang Camp. 1 Pc : 2 Ps : 3 Kr,
Tulangan Besi Ø 12 SNI
- Sloof (25/40), Beton Bertulang Camp. 1 Pc : 2 Ps : 3 Kr, Besi Ø 12 SNI
- Kolom Pedestal (25/40) Tinggi 1.2 m, Beton Bertulang Camp. 1 Pc : 2 Ps : 3 Kr,
Tulangan Besi Ø 12 SNI
- Kolom Baja IWF 300 x 150 x 6.5 x 9, Tinggi 6 m
- Kuda - Kuda Baja IWF 250 x 125 x 6 x 9
- Gording CNP 125 x 50 x 20 x 2.3
- Ikatan Angin Besi BJTP Ø12 + Aksesoris
- Penutup Atap Zinkalume 0.35 mm AZ 150 + Nok
- Listplank GRC Lebar 25 cm
- Cat IWF dan CNP anti karat Zingkromate Ex. Kansai Grey / Green
475,200,000
III PEKERJAAN DINDING
5 Kolom Praktis (10/10), Beton Bertulang Camp. 1 Pc : 2 Ps : 3 Kr, 1.26 m3 3,600,000 4,536,000
Tulangan Utama 4Ø8 Sengkang Ø6-150
6 Ring Balk (10/15), Beton Bertulang Camp. 1 Pc : 2 Ps : 3 Kr, 1.58 m3 3,600,000 5,670,000
Tulangan Utama 4Ø8 Sengkang Ø6-150
7 Dinding Batu Tela 1 Pc : 4 Ps 304.00 m2 140,000 42,560,000
8 Plesteran Dinding 1 Pc : 3 Ps + Aci Halus 628.00 m2 58,000 36,424,000
89,190,000
IV PEKERJAAN LANTAI
9 Urugan Pasir dan Batu (Sirtu) dipadatkan, Tebal 15 cm 54.00 m3 345,000 18,630,000
10 Lantai Gudang 54.00 m3 3,600,000 194,400,000
- Lantai Beton Bertulang Camp. 1Pc : 2Ps : 3Kr, Tebal 15 Cm
Tulangan Rangkap Ø 10, Finishing Halus
- Papan Begisting Sekat (1/20), Kayu Kelas II
11 Lantai Selasar Tebal 10 Cm 13.50 m3 1,500,000 20,250,000
- Beton Rabat Camp. 1Pc : 3 Ps : 5 Kr
12 Parit Keliling Gudang 96.00 m1 160,000 15,360,000
- Pasangan Batako 1 Pc : 4 Ps + Aci
248,640,000
V PEKERJAAN INSTALASI LISTRIK
13 Instalasi 1 Titik Lampu Phillips 100 W + Fitting dan Kap, Kabel NYA 2 x 2.5 dengan Pipa PVC 5/8" 19.00 Titik 420,000 7,980,000
+ Saklar merek Panasonic dan Aksesoris
14 Stop Kontak merek Panasonic, Kabel NYA 2 x 2.5 dibungkus Pipa PVC 5/8" + Aksesoris 2.00 Titik 160,000 320,000
15 MCB 10 A + Box 1.00 Bh 350,000 350,000
8,650,000
VI PEKERJAAN PINTU DAN ANGIN ANGIN
16 Pintu Geser Baja ( 2 x 4 x 2 ) Tebal 5 Cm + Aksesoris 2.00 Set 7,500,000 15,000,000
17 Angin - Angin Rangka Kayu Kelas II, Isi Kawat Harmonika Tebal 50 mm 84.00 m2 60,000 5,040,000
20,040,000
VII PEKERJAAN PENGECATAN
18 Cat Dinding "Vinilex" ( 1 Lps Cat Dasar 2 Lps Cat Penutup ) 628.00 m2 22,000 13,816,000
19 Pengecatan Pintu Besi "Platone" ( 1 Lps Cat Dasar, 2 Lps Cat Penutup) 4.00 Ls 500,000 2,000,000
15,816,000
GRAND TOTAL 872,536,000
DIBULATKAN 872,500,000
RENCANA ANGGARAN BIAYA

Pekerjaan : Barak Sementara


Lokasi : Afdeling IV - KHB
Volume : 5 x 30 M
Tahun : 2016

HARGA SATUAN JUMLAH HARGA


No. URAIAN VOLUME SAT
( Rp. ) ( Rp. )
I PEKERJAAN PONDASI
1 Balok Pondasi, Kayu Kelas II (5/7) 9.00 #REF! Rp 50,000.00 Rp 450,000.00
2 Paku Kayu 4" 2.00 #REF! Rp 20,000.00 Rp 40,000.00
Rp 490,000.00
II PEKERJAAN DINDING
1 Tiang Dinding, Kayu Kelas II (8/8) 33.00 #REF! Rp 50,000.00 Rp 1,650,000.00
2 Tiang Dinding, Kayu Kelas II (5/7) 42.00 #REF! Rp 21,000.00 Rp 882,000.00
3 Balok Dinding, Kayu Kelas II (5/7) 55.00 #REF! Rp 21,000.00 Rp 1,155,000.00
4 Dinding Papan, Kayu Kelas II (2/20) 530.00 #REF! Rp 18,000.00 Rp 9,540,000.00
5 Paku Kayu 4" 3.00 #REF! Rp 20,000.00 Rp 60,000.00
6 Paku Kayu 3" 3.00 #REF! Rp 20,000.00 Rp 60,000.00
7 Paku Kayu 2" 8.00 #REF! Rp 20,000.00 Rp 160,000.00
Rp 13,507,000.00
III PEKERJAAN LANTAI
1 Balok Lantai Kayu Kelas II (8/8) 29.00 #REF! Rp 50,000.00 Rp 1,450,000.00
2 Balok Lantai Kayu Kelas II (5/7) 17.00 #REF! Rp 23,000.00 Rp 391,000.00
3 Papan Kayu Kelas II (3/20) 188.00 #REF! Rp 18,000.00 Rp 3,384,000.00
4 Paku Kayu 3" 3.00 #REF! Rp 20,000.00 Rp 60,000.00
5 Paku Kayu 2" 4.00 #REF! Rp 20,000.00 Rp 80,000.00
Rp 5,365,000.00
IV PEKERJAAN ATAP
1 Konstruksi Kuda-kuda, Kayu Kelas II (5/7) 35.00 #REF! Rp 21,000.00 Rp 735,000.00
2 Ring Balok, Kayu Kelas II (5/7) 31.00 #REF! Rp 21,000.00 Rp 651,000.00
3 Gording, Kayu Kelas II (4/6) 46.00 #REF! Rp 18,000.00 Rp 828,000.00
4 Atap Seng Gelombang 247.00 #REF! Rp 56,000.00 Rp 13,832,000.00
5 Rabung Seng Gelombang 35.00 #REF! Rp 10,000.00 Rp 350,000.00
6 Papan Listplank, Kayu Kelas II (2/20) 20.00 #REF! Rp 18,000.00 Rp 360,000.00
7 Paku Kayu 3" 5.00 #REF! Rp 20,000.00 Rp 100,000.00
8 Paku Kayu 2" 2.00 #REF! Rp 20,000.00 Rp 40,000.00
9 Paku Seng / Payung 2" 5.00 #REF! Rp 20,000.00 Rp 100,000.00
Rp 16,996,000.00
V PEKERJAAN PINTU DAN JENDELA
1 Kusen Pintu, Kayu Kelas II (5/7) + Jalusi 20.00 #REF! Rp 35,000.00 Rp 700,000.00
2 Kusen Jendela, Kayu Kelas II (5/7) + Jalusi 40.00 #REF! Rp 35,000.00 Rp 1,400,000.00
3 Daun Pintu, Kayu Kelas II 20.00 #REF! Rp 35,000.00 Rp 700,000.00
4 Set Jendela Nako, Kaca Rayben 5 MM 40.00 #REF! Rp 35,000.00 Rp 1,400,000.00
5 Engsel Pintu 4" 40.00 #REF! Rp 12,000.00 Rp 480,000.00
6 Paku Kayu 3" 3.00 #REF! Rp 20,000.00 Rp 60,000.00
7 Paku Kayu 2" 3.00 #REF! Rp 20,000.00 Rp 60,000.00
Rp 4,800,000.00
VI TENAGA KERJA
1 Upah / Jasa Kontraktor 150.00 m2 Rp 150,000.00 Rp 22,500,000.00
Rp 22,500,000.00
GRAND TOTAL Rp 63,658,000.00
RENCANA ANGGARAN BIAYA

Pekerjaan : Barak Sementara


Lokasi : Afdeling IV - KHB
Volume : 5 x 30 M
Tahun : 2016

HARGA SATUAN JUMLAH HARGA


No. URAIAN VOLUME SAT
( Rp. ) ( Rp. )
DIBULATKAN Rp 63,600,000.00
Tiap 1 M3 Kolom Praktis (10/10) butuh: Rp 9,013,843.37
Bahan
15.0000 M2 Bekisting @Rp 320,921.43 Rp 4,813,821.43
14.8148 Lnjr Besi Beton @Rp 18,500.00 Rp 274,074.07
111.3333 Lnjr Besi Beton @Rp 18,500.00 Rp 2,059,666.67
2.6760 Kg Kawat Beto @Rp 11,200.00 Rp 29,971.20
1.0000 M3 Beton 1:2:3 @Rp ### Rp 1,203,000.00
Rp 8,380,533.37
Tenaga Kerja
4.8500 Org Pekerja @Rp 90,000.00 Rp 436,500.00
1.4000 Org Tukang Besi @Rp 100,000.00 Rp 140,000.00
0.3310 Org Kepala Tuk @Rp 110,000.00 Rp 36,410.00
0.1700 Org Mandor @Rp 120,000.00 Rp 20,400.00
Rp 633,310.00
Alat
Rp 0.00

Tiap 1 M3 Beton 1Pc : 2 Ps : 3Kr butuh: Rp 1,203,000.00


Bahan
4.6400 Zak 232.0000 Kg Tonasa Seme @Rp 85,000.00 Rp 394,400.00
0.5200 M3 Pasir Beton @Rp 400,000.00 Rp 208,000.00
0.7800 M3 Kerikil Bet @Rp 500,000.00 Rp 390,000.00
Rp 992,400.00
Tenaga Kerja
1.6500 Org Pekerja @Rp 90,000.00 Rp 148,500.00
0.2500 Org Tukang Bat @Rp 100,000.00 Rp 25,000.00
0.2500 Org Kepala Tuk @Rp 110,000.00 Rp 27,500.00
0.0800 Org Mandor @Rp 120,000.00 Rp 9,600.00
Rp 210,600.00

Tiap 1 M2 Bekisting Kolom butuh: Rp 320,921.43


Bahan
0.3500 Lbr Playwood @Rp 100,800.00 Rp 35,280.00
3.2857 Btg 0.0180 M3 Balok Merant @Rp 65,000.00 Rp 213,571.43
0.4000 kg Paku @Rp 9,800.00 Rp 3,920.00
0.2000 Lt Minyak Beki @Rp 10,000.00 Rp 2,000.00
Rp 254,771.43
Tenaga Kerja
0.3200 Org Pekerja @Rp 90,000.00 Rp 28,800.00
0.3300 Org Tukang Kay @Rp 100,000.00 Rp 33,000.00
0.0330 Org Kepala Tuk @Rp 110,000.00 Rp 3,630.00
0.0060 Org Mandor @Rp 120,000.00 Rp 720.00
Rp 66,150.00

Tiap 1 M3 ring Balok 15/20 butuh: Rp 6,731,175.00


Bahan
12.6700 M2 Bekisting @Rp 215,000.00 Rp 2,724,050.00
2.2200 Lnjr Besi Beton @Rp 18,500.00 Rp 41,070.00
111.3300 Lnjr Besi Beton @Rp 18,500.00 Rp 2,059,605.00
2.0040 Kg Kawat Beto @Rp 35,000.00 Rp 70,140.00
1.0000 M3 Beton 1:2:3 @Rp ### Rp 1,203,000.00
Rp 6,097,865.00
Tenaga Kerja
4.8500 Org Pekerja @Rp 90,000.00 Rp 436,500.00
1.4000 Org Tukang Besi @Rp 100,000.00 Rp 140,000.00
0.3310 Org Kepala Tuk @Rp 110,000.00 Rp 36,410.00
0.1700 Org Mandor @Rp 120,000.00 Rp 20,400.00
Rp 633,310.00

Tiap 1 M3 Plat Beton butuh: Rp 4,610,643.06


Bahan
2.2000 M2 Bekisting @Rp 847,180.00 Rp 1,863,796.00
0.9167 Lnjr Besi Beton @Rp 32,462.24 Rp 29,757.06
3.0000 Kg Kawat Beto @Rp 11,200.00 Rp 33,600.00
1.0000 M3 Beton 1:2:3 @Rp ### Rp 1,203,000.00
Rp 3,130,153.06
Tenaga Kerja
4.8500 Org Pekerja @Rp 90,000.00 Rp 436,500.00
1.4000 Org Tukang Besi @Rp 100,000.00 Rp 140,000.00
0.3310 Org Kepala Tuk @Rp 110,000.00 Rp 36,410.00
0.1700 Org Mandor @Rp 120,000.00 Rp 20,400.00
Rp 633,310.00

Tiap 1 M2 Bekisting Plat Lantai butuh: Rp 847,180.00

0.3500 Lbr Playwood @Rp 100,800.00 Rp 35,280.00


1.5625 Btg 0.0150 M3 Kayu Merant @Rp 300,000.00 Rp 468,750.00
6.0000 Btg Balok Merant @Rp 45,000.00 Rp 270,000.00
0.4000 Kg Paku @Rp 12,500.00 Rp 5,000.00
0.2000 Lt Minyak Beki @Rp 10,000.00 Rp 2,000.00
Rp 781,030.00
Tenaga Kerja
0.3200 Org Pekerja @Rp 90,000.00 Rp 28,800.00
0.3300 Org Tukang Kay @Rp 100,000.00 Rp 33,000.00
0.0330 Org Kepala Tuk @Rp 110,000.00 Rp 3,630.00
0.0060 Org Mandor @Rp 120,000.00 Rp 720.00
Rp 66,150.00
13 1M2 PASANGAN BATU TELA 1 PC : 2 PSR (SNI 2008)
20.0000 Bh
18.9500 Kg
0.0380 M3
0.3000 h/o
0.1000 h/o
0.0100 h/o
0.0005 h/o

1m2 PLESTERAN 1pc:4psr T=1.5 CM


6.2400 Kg
0.0240 M3
0.3000 h/o
0.1500 h/o
0.0150 h/o
0.0150 h/o

1m3 URUGAN PASIR


1.2000 M3
0.3000 h/o
0.0100 h/o

1 m² Pasang Dinding Bataco Uk. 20 cm x 40 cm, 1 PC : 4 Ps


13.0000 bh Bataco
5.8333 kg Semen PC @ 50 k
0.0133 m³ Pasir pasang
0.0833 Oh Pekerja tak terlatih
0.0833 Oh Tukang batu
0.0083 Oh Kepala tukang
0.0080 Oh Mandor

1Titik PASANG LAMPU TL 100WATT


1.0000 bh
9.0000 m'
0.5000 set
1.0000 set
1.0000 m'
1.0000 buah
1.2500 h/o
0.1250 h/o
0.7500 h/o
0.0375 h/o
ANALISA 001 1 m² Pengecatan Tembok Baru ( 1 Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup )
Bahan
Plamir 0.100
Cat Dasar 0.100
Cat Tembok vinilex 0.260
Tenaga
Pekerja 0.0200
Tukang Cat 0.063
Kepala Tukang 0.0063
Mandor 0.0025

ANALISA 001 1 m² Pengecatan Permukaan Baja dengan Meni Besi


Bahan
Meni Besi 0.100
Kuas 0.010
Cat Besi 0.100
Tenaga
Pekerja 0.0200
Tukang Cat 0.200
Kepala Tukang 0.0200
Mandor 0.0100
Batu tela 3,000.00 60,000.00
Semen 1,500.00 28,425.00
Pasir pasang 150,000.00 5,700.00
Pekerja 90,000.00 27,000.00
Tukang batu 100,000.00 10,000.00
Kepala Tukang 110,000.00 1,100.00
Mandor 120,000.00 60.00

Jumlah (A+B+C)
132,285.00

Semen 1,500.00 9360


Pasir pasang 150,000.00 3600
Pekerja 90,000.00 27000
Tukang 100,000.00 15000
Kepala tukang 110,000.00 1650
Mandor 120,000.00 1800

Jumlah (A+B+C) 58,410.00

Pasir urug 150,000.00 180000


Pekerja 90,000.00 27000
Mandor 120,000.00 1200

Jumlah (A+B+C) 208200

3,500.00 45,500.00
Semen PC @ 50 k 1,500.00 8,750.00
Pasir pasang 150,000.00 2,000.00
Pekerja tak terlatih 90,000.00 7,500.00
100,000.00 8,333.33
Kepala tukang 110,000.00 916.67
120,000.00 960.00
73,960.00

Lampu TL Office 1x100w philipps 145,000.00 145000


Kabel NYA 2x2.5 35,000.00 315000
Alat bantu 10,000.00 5000
Accesoriis 65,000.00 65000
Pipa PVC 5/8' 13,000.00 13000
Saklar 35,000.00 35000
Tukang 90,000.00 112500
Kepala tukang 100,000.00 12500
Pekerja 110,000.00 82500
Mandor 120,000.00 4500

Jumlah (A+B+C) 790000


is Cat Penutup )

kg 31,710.00 3,171.00
kg 34,500.00 3,450.00
kg 63,525.00 16,516.50

oh 90,000.00 1,800.00
oh 100,000.00 6,300.00
oh 110,000.00 693.00
oh 120,000.00 300.00
32,230.50

kg 33,600.00 3,360.00
bh 35,000.00 350.00
65,000.00 6,500.00

oh 90,000.00 1,800.00
oh 100,000.00 20,000.00
oh 110,000.00 2,200.00
oh 120,000.00 1,200.00
35,410.00
NO URAIAN PEKERJAAN SATUAN HARGA ( Rp.)

A. DAFTAR UPAH
Mandor h/o 120,000
Kepala tukang h/o 110,000
Tukang h/o 100,000
Pekerja h/o 90,000

B. DAFTAR BAHAN
1 Pasir beton kg 400.00
2 Pasir pasang m3 300,000.00
3 Pasir urug m3 100,000.00
4 Kerikil kg 500.00
5 Batu pecah 2/3 cm kg 900.00
6 Batu kali m3 800,000.00
7 Batu tela bh 3,000.00
8 Batu Apung Habel bh 18,900.00
9 Sirtu gunung m3 300,000.00
10 Batu Alam m2 12,000.00
11 Semen kg 1,700.00
12 Semen putih kg 23,000.00
13 Papan matoa m3 3,000,000.00
14 Kayu matoa steger btg 68,250.00
15 Kayu besi m3 4,000,000.00
16 Papan kayu besi m3 4,000,000.00
17 Kayu matoa m3 3,000,000.00
18 Kayu perancah m3 1,800,000.00
19 Kayu tiang pancang 10/10 m' 100,000.00
33 Cat kapur plafond kg 48,000.00
34 Cat tembok exterior (Jotun) kg 102,800.00
35 Meni (Jotun) kg 33,600.00
36 Tinner (Jotun) Ltr 60,375.00
37 Cat tembok Cansay kg 63,525.00
38 Cat tembok interior kg 6,000.00
39 Cat kayu kg 58,250.00
40 Minyak cat ltr 33,075.00
41 Meni kayu kg 33,600.00
42 Politur ltr 65,000.00
43 Cat Besi ltr 65,000.00
44 Aquaproof kg 47,775.00
45 Ampelas lbr 7,000.00
46 Lem kayu kg 60,000.00
47 Dempul/plamir kg 31,710.00
48 Paku kg 28,612.50
49 Skrup Gypsum kg 1,260.00
50 Besi beton ulir kg 18,500.00
51 Besi beton polos kg 18,500.00
52 Kawat ikat kg 35,000.00
53 Besi Hollow 40/40 m' 37,500.00
54 Besi Hollow 20/40 m' 35,000.00
55 Besi Strep kg 63,000.00
56 Kaca 5 mm m2 120,000.00
57 Kaca Ryben 5 mm m2 256,750.00
58 Kosen Almunium m' 335,000.00
59 Skrup fixer Bh 2,567.00
60 Sealent Tube 2,887.50
61 Rangka pintu almunium m' 98,175.00
61 Rangka Jendela Nako m 225,000.00
62 Almunium strip m' 202,125.00
63 Pintu Lipat (Folding door) m2 78,225.00
64 Pintu Fiber m2 1,923,375.00
64 Kosen Pintu Lipat (Folding door) m' 400,000.00
65 Rel Pintu Lipat (Folding door) m' 98,175.00
66 Kait angin psg 132,825.00
67 Kunci Pintu Utama 2 slag psg 126,250.00
68 Kunci 2 slag mutu baik bh 165,000.00
68 Grendel Jendel bh 35,000.00
69 Gerendel panjang bh 65,000.00
70 Engsel Ring Nilon bh 26,500.00
70 Engsel pintu 4" psg 127,500.00
71 Engsel jendela psg 58,000.00
72 Grendel bh 37,275.00
72 Pegangan/handle besar bh 30,975.00
73 Pegangan/handle bh 275,000.00
74 Granit 60x60 bh 21,000.00
75 Plin Granit 10x60 bh 125,000.00
76 Keramik 60x60 bh 45,000.00
77 Keramik 40x40 bh 98,500.00
78 Keramik 33x33 bh 23,625.00
79 Keramik 20x20 bh 12,705.00
80 Keramik 20x25 bh 4,725.00
81 Keramik 20x40 bh 5,775.00
82 Plint keramik 10x40 bh 17,692.50
83 Stop nosing bh 4,725.00
84 Washtafel bh 12,075.00
84 Wasbak steilisteel bh 945,000.00
85 Urinoir bh 590,000.00
86 Kran air bh 85,000.00
87 Kloset jongkok keramik bh 425,000.00
88 Kloset duduk keramik kia bh 635,000.00
89 Bak Air Fiber 200 ltr 525,000.00
90 Pompa air 3.5 PK 2,100,000.00
91 Floor drain bh 76,500.00
92 Pipa Gip dia 1/2" btg 99,750.00
93 Pipa Gip dia 3/4" btg 145,000.00
94 Atap ZinkCalum Color 40 m2 185,000.00
95 Nok Atap ZinkCalum Color 40 m' 210,000.00