Anda di halaman 1dari 3

R A B RUKOST IRAWAN TYPE 108

NO PEKERJAAN VOL SAT Harga Satuan JUMLAH

A PEKERJAAN PONDASI 1.173913043


1 Pas.Bouwplank T.1,00M/m' 66.00 m' 10,000 660,000
2 Galian Tanah Pondasi 0.00 -
pondasi Telapak 5.18 m3 35,000 181,440
Pondasi Batu Kali 5.40 m3 35,000 189,000
3 Bor Strous diameter 30 cm 54.00 m' 25,000 1,350,000
4 Cor beton strouss diameter 300cm - -
Beton 2.86 m3 850,000 2,432,126
Pembesian besi DEFORM 13 281.31 kg 9,500 2,672,435
besi 8 74.58 kg 9,500 708,537
5 Plat setempat PONDASI TELAPAK - -
Plat setempat 80 x80 - -
Beton 2.69 m3 850,000 2,284,800
Pembesian besi DEFORM 13 145.50 kg 9,500 1,382,243
besi DEFORM 13 145.50 kg 9,500 1,382,243
Plat setempat 50 x 50 - -
Beton 0.30 m3 850,000 255,000
Pembesian besi DEFORM 10 12.02 kg 9,500 114,207
besi DEFORM 10 12.02 kg 9,500 114,207
6 Pasangan Batu Kali 1:6 Pondasi Rumah 14.40 m3 650,000 9,360,000
7 Pasangan Batu Kali 1:6 Pondasi pagar Halaman 2.58 m3 650,000 1,677,000
8 Pasangan Batu Kali 1/2 camp. 1:6 5.76 m3 650,000 3,744,000
9 Tanah Urug.----diperhitungkan di fasum -
-
SUB TOTAL BIAYA PEKERJAAN PONDASI - 28,507,238
-
B PEKERJAAN STRUKTUR - `
LANTAI 1 -
1 Beton sloff 15/30 - -
Beton 2.84 m3 750,000 2,126,250
Pembesian besi DEFORM 13 262.56 kg 8,500 2,231,718
besi DEFORM 12 111.86 kg 8,500 950,791
besi 6 73.64 kg 8,500 625,937
begesting 37.80 m2 25,000 945,000
2 Beton sloff 15/20 - -
Beton 0.39 m3 750,000 290,250
Pembesian besi DEFORM 12 45.81 kg 8,500 389,372
besi 6 11.26 kg 8,500 95,721
begesting 5.16 m2 25,000 129,000
3 kolom 15/30.30 - -
Beton 1.42 m3 750,000 1,063,125
Pembesian besi DEFORM 12 149.14 kg 8,500 1,267,721
besi 6 33.87 kg 8,500 287,878
begesting 25.20 m2 50,000 1,260,000
4 kolom 15/30 - -
Beton 2.36 m3 750,000 1,771,875
Pembesian besi DEFORM 12 279.64 kg 8,500 2,376,977
besi 6 61.37 kg 8,500 521,614
begesting 23.63 m2 50,000 1,181,250
5 kolom 15/15 - -
Beton 0.47 m3 750,000 354,375
Pembesian besi 10 51.79 kg 8,500 440,181
besi 6 15.23 kg 8,500 129,413
begesting 3.60 m2 50,000 180,000
6 BALOK 15 /50 - -
Beton 5.40 m3 750,000 4,050,000
Pembesian besi 13 300.06 kg 8,500 2,550,534
besi 10 88.78 kg 8,500 754,596
besi 6 126.77 kg 8,500 1,077,563
begesting 61.20 m2 100,000 6,120,000
7 BALOK anak 15/25 - -
Beton 0.34 m3 750,000 253,125
Pembesian besi 10 22.19 kg 8,500 188,649
besi 6 9.19 kg 8,500 78,101
begesting 3.51 m2 100,000 351,000
8 Plat Lisplang - -
Beton 0.63 m3 750,000 472,500
Pembesian besi 8 16.57 kg 8,500 140,858
besi 8 23.67 kg 8,500 201,226
begesting 9.00 m2 100,000 900,000
9 Plat tangga - -
Beton 1.35 m3 750,000 1,012,500
Pembesian besi 10 36.99 kg 8,500 314,415
besi 10 36.99 kg 8,500 314,415
begesting 9.00 m2 100,000 900,000
NO PEKERJAAN VOL SAT Harga Satuan JUMLAH

LANTAI 2 - -
1 Plat Lantai - -
Beton 5.57 m3 850,000 4,735,350
Pembesian besi 8 293.55 kg 8,500 2,495,197
besi 8 293.55 kg 8,500 2,495,197
begesting 54.00 m2 150,000 8,100,000
2 kolom 15/30.30 - -
Beton 1.62 m3 850,000 1,377,000
Pembesian besi DEFORM 12 170.45 kg 8,500 1,448,824
besi 6 38.71 kg 8,500 329,004
begesting 28.80 m2 50,000 1,440,000
3 kolom 15/15 - -
Beton 1.89 m3 850,000 1,606,500
Pembesian besi 10 207.14 kg 8,500 1,760,724
besi 6 60.90 kg 8,500 517,653
begesting 16.80 m2 50,000 840,000
4 BALOK Ring 15 / 20 - -
Beton 1.62 m3 850,000 1,377,000
Pembesian besi 8 113.63 kg 8,500 965,883
besi 6 52.20 kg 8,500 443,702
begesting 21.60 m2 50,000 1,080,000
5 Plat KM dan teras serta talang Beton - -
5.a KM. kamar kost - -
Beton 0.43 m3 850,000 367,200
Pembesian besi 8 11.36 kg 8,500 96,588
besi 8 11.36 kg 8,500 96,588
begesting 4.50 m2 100,000 450,000
5.b Plat Teras depan - -
Beton 0.51 m3 850,000 433,500
Pembesian besi 8 13.42 kg 8,500 114,028
besi 8 13.42 kg 8,500 114,028
begesting 3.06 m2 100,000 306,000
5.c Plat Talang beton - -
Beton 4.68 m3 850,000 3,978,000
Pembesian besi 8 184.65 kg 8,500 1,569,560
besi 8 184.65 kg 8,500 1,569,560
begesting 46.80 m2 100,000 4,680,000
5.d Plat kanopi jendela - -
Beton 0.21 m3 850,000 175,950
Pembesian besi 8 8.17 kg 8,500 69,423
besi 8 8.17 kg 8,500 69,423
begesting 2.07 m2 100,000 207,000
SUB TOTAL BIAYA PEKERJAAN STRUKTUR - 83,606,813
C PEKERJAAN PASANGAN DINDING - -
LANTAI 1 dan 2 - -
1 Pas. Dinding bata Ringan 366.54 m2 115,000 42,152,100
- -
2 volume Kosen Almini/m' - -
148.36 m' 55,000 8,159,938
SUB TOTAL BIAYA PEKERJAAN PASANGAN DINDING - 50,312,038
- -
D PEKERJAAN RANGKA & PENUTUP ATAP - -
1 Rangka Atap Galvalum 42.77 57.00 m2 120,000 6,840,000
2 Pas.Genteng semi mantili (biji) 1,425.00 bji 1,400 1,995,000
3 Pas.Genteng Nok semi mantili /m' 120.00 bji 7,500 900,000
4 Pas.kalsi plang 30 CM 53.25 m' 20,000 1,065,000
SUB TOTAL BIAYA PEKERJAAN RANGKA & PENUTUP ATAP - 10,800,000
-
E PEKERJAAN PELAPIS DINDING - -
1 Acian dan Plesteran Tebal 23mm/m2 403.19 m2 17,500 7,055,895
2 Sekonengan Sudut Dinding/m' 45.00 m' 15,000 675,000
3 Tali Air Keliling Kosen/m' 46.28 m' 10,000 462,750
4 keramik dinding - m2 -
Pas.Keramik Dinding Lokal 20X25/m2 Mulia -Toilet lantai 1 34.65 m2 110,000 3,811,500
Pas.Keramik Dinding Lokal 20X25/m2 Mulia - Meja Dapur Lantai 1 3.75 m2 110,000 412,500
Pas.Keramik Dinding Lokal 20X25/m2 Mulia -Toilet lantai 2 34.65 m2 110,000 3,811,500
Pas.Keramik Dinding Lokal 20X25/m2 Mulia - Meja Dapur Lantai 2 - m2 110,000 -
5 Pasangan Granit dinding depan 17.50 m2 150,000 2,625,000
SUB TOTAL BIAYA PEKERJAAN PELAPIS DINDING - 16,229,145
-
F PEKERJAAN PENUTUP PLAFOND - -
1 Plafond Gypsum 9mm/m2 98.63 m2 100,000 9,862,500
2 Plafond calsiboard 4mm/m2 - m2 -
SUB TOTAL BIAYA PEKERJAAN PENUTUP PLAFOND - 9,862,500
- -
G PEKERJAAN PELAPIS LANTAI - -
Beton tumbuk lantai - -
1 Rabat Beton T.7,5cm/m2 Tanpa Tulang dgn Koral 2.93 M3 350,000 1,023,750
NO PEKERJAAN VOL SAT Harga Satuan JUMLAH

2 Pas. Granit 60 x 60 standart - -


lantai 1 58.50 m2 90,000 5,265,000
lantai 2 44.63 m2 90,000 4,016,250
3 Pas. Granit 60 x 60 kw standart meja dapur Lantai 1 dan 2 - -
lantai 1 0.90 m2 110,000 99,000
4 Pas.Keramik KM lantai Lokal 20X20/m2 Mulia - -
lantai 1 5.20 m2 105,000 545,738
tangga 9.00 m2 105,000 945,000
lantai 2 5.20 m2 105,000 545,738
SUB TOTAL BIAYA PEKERJAAN PELAPIS LANTAI - 12,440,475
- -
H PEKERJAAN PINTU, JENDELA, KACA - -
- -
1 Daun Pintu Almini 11.00 BH 550,000 6,050,000
2 Pintu toilet 10.00 BH 400,000 4,000,000
3 Jendela Rangka Almini kaca 8 mm 12.00 BH 250,000 3,000,000
SUB TOTAL BIAYA PEKERJAAN PINTU, JENDELA, KACA - 13,050,000
- -
I PEKERJAAN ENGSEL & KUNCI - -
1 Kunci Pintu /bh Lainnya 10.57 bh 100,000 1,056,522
2 Kunci Pintu K.Mandi Lain/bh 7.04 bh 65,000 457,826
3 Engsel pintu 10.57 set 75,000 792,391
4 Engsel jendela 14.09 set 50,000 704,348
SUB TOTAL BIAYA PEKERJAAN ENGSEL & KUNCI - 3,011,087
- -
J PEKERJAAN PENGECATAN - -
- -
1 Cat Tembok Dalam/m2 366.54 m2 15,000 5,498,100
2 Cat Tembok Luar/m2 183.27 m2 25,000 4,581,750
3 Cat plafond 98.63 m2 12,500 1,232,813
4 Cat genteng 57.00 m2 17,000 969,000
SUB TOTAL BIAYA PEKERJAAN PENGECATAN - 12,281,663
- -
K PEKERJAAN INSTALASI SANITASI - -
Air Bersih lantai 1 dan 2 - -
1 Pengeboran sumur air bersih dan pompa air - -
2 Pemipaan PVC D dia 3/4"/m' 88.04 m' 15,000 1,320,652
3 kran air biasa 23.48 bj 25,000 586,957
kitchen zink 1.17 bj 50,000 58,696
4 kitchen zink 1.17 bh 250,000 293,478
Air Kotor - -
1 Pemipaan PVC AW dia 3"/m' (Bawah Lantai) lantai 1 dan 2 52.83 m' 25,000 1,320,652
2 Pemipaan PVC AW dia 4"/m' (Bawah Lantai) Lantai 1 dan 2 64.57 m' 35,000 2,259,783
3 avour kamar mandi 10.00 m' 50,000 500,000
4 closet duduk 10.00 750,000 7,500,000
5 Septic Tank buis beton 4 bh dim 1 m 6.00 bh 250,000 1,500,000
6 Resapan Air kotor buis beton dim 1 m 6.00 bh 250,000 1,500,000
SUB TOTAL BIAYA PEKERJAAN INSTALASI SANITASI - 16,840,217
-
L PEKERJAAN INSTALASI LISTRIK -
Lantai 1 dan 2 -
1 Titik Lampu Dalam/ttk Bawah Plafond 18.00 ttk 100,000 1,800,000
2 Titik Lampu Luar 5.00 ttk 125,000 625,000
3 Titik Stop Kontak Biasa/ttk 12.00 ttk 85,000 1,020,000
4 Saklar 10.00 ttk 75,000 750,000
SUB TOTAL BIAYA PEKERJAAN INSTALASI LISTRIK - 4,195,000
-
M PEKERJAAN LAIN-LAIN Lantai 1 dan 2 -
1 Sun Screen Galvalum - -
lantai 1 4.11 m' 250,000 1,027,174
lantai 2 kamar kost luar 4.11 m' 85,000 349,239
exhoust fan 6.00 bh 250,000 1,500,000
2 Raling Tangga 15.00 m' 275,000 4,125,000
0

SUB TOTAL BIAYA PEKERJAAN LAIN - LAIN 7,001,413

TOTAL BIAYA PEKERJAAN 269,450,088

harga per m2 2,494,908.22

Anda mungkin juga menyukai