LANTAI 2 - -
1 Plat Lantai - -
Beton 5.57 m3 850,000 4,735,350
Pembesian besi 8 293.55 kg 8,500 2,495,197
besi 8 293.55 kg 8,500 2,495,197
begesting 54.00 m2 150,000 8,100,000
2 kolom 15/30.30 - -
Beton 1.62 m3 850,000 1,377,000
Pembesian besi DEFORM 12 170.45 kg 8,500 1,448,824
besi 6 38.71 kg 8,500 329,004
begesting 28.80 m2 50,000 1,440,000
3 kolom 15/15 - -
Beton 1.89 m3 850,000 1,606,500
Pembesian besi 10 207.14 kg 8,500 1,760,724
besi 6 60.90 kg 8,500 517,653
begesting 16.80 m2 50,000 840,000
4 BALOK Ring 15 / 20 - -
Beton 1.62 m3 850,000 1,377,000
Pembesian besi 8 113.63 kg 8,500 965,883
besi 6 52.20 kg 8,500 443,702
begesting 21.60 m2 50,000 1,080,000
5 Plat KM dan teras serta talang Beton - -
5.a KM. kamar kost - -
Beton 0.43 m3 850,000 367,200
Pembesian besi 8 11.36 kg 8,500 96,588
besi 8 11.36 kg 8,500 96,588
begesting 4.50 m2 100,000 450,000
5.b Plat Teras depan - -
Beton 0.51 m3 850,000 433,500
Pembesian besi 8 13.42 kg 8,500 114,028
besi 8 13.42 kg 8,500 114,028
begesting 3.06 m2 100,000 306,000
5.c Plat Talang beton - -
Beton 4.68 m3 850,000 3,978,000
Pembesian besi 8 184.65 kg 8,500 1,569,560
besi 8 184.65 kg 8,500 1,569,560
begesting 46.80 m2 100,000 4,680,000
5.d Plat kanopi jendela - -
Beton 0.21 m3 850,000 175,950
Pembesian besi 8 8.17 kg 8,500 69,423
besi 8 8.17 kg 8,500 69,423
begesting 2.07 m2 100,000 207,000
SUB TOTAL BIAYA PEKERJAAN STRUKTUR - 83,606,813
C PEKERJAAN PASANGAN DINDING - -
LANTAI 1 dan 2 - -
1 Pas. Dinding bata Ringan 366.54 m2 115,000 42,152,100
- -
2 volume Kosen Almini/m' - -
148.36 m' 55,000 8,159,938
SUB TOTAL BIAYA PEKERJAAN PASANGAN DINDING - 50,312,038
- -
D PEKERJAAN RANGKA & PENUTUP ATAP - -
1 Rangka Atap Galvalum 42.77 57.00 m2 120,000 6,840,000
2 Pas.Genteng semi mantili (biji) 1,425.00 bji 1,400 1,995,000
3 Pas.Genteng Nok semi mantili /m' 120.00 bji 7,500 900,000
4 Pas.kalsi plang 30 CM 53.25 m' 20,000 1,065,000
SUB TOTAL BIAYA PEKERJAAN RANGKA & PENUTUP ATAP - 10,800,000
-
E PEKERJAAN PELAPIS DINDING - -
1 Acian dan Plesteran Tebal 23mm/m2 403.19 m2 17,500 7,055,895
2 Sekonengan Sudut Dinding/m' 45.00 m' 15,000 675,000
3 Tali Air Keliling Kosen/m' 46.28 m' 10,000 462,750
4 keramik dinding - m2 -
Pas.Keramik Dinding Lokal 20X25/m2 Mulia -Toilet lantai 1 34.65 m2 110,000 3,811,500
Pas.Keramik Dinding Lokal 20X25/m2 Mulia - Meja Dapur Lantai 1 3.75 m2 110,000 412,500
Pas.Keramik Dinding Lokal 20X25/m2 Mulia -Toilet lantai 2 34.65 m2 110,000 3,811,500
Pas.Keramik Dinding Lokal 20X25/m2 Mulia - Meja Dapur Lantai 2 - m2 110,000 -
5 Pasangan Granit dinding depan 17.50 m2 150,000 2,625,000
SUB TOTAL BIAYA PEKERJAAN PELAPIS DINDING - 16,229,145
-
F PEKERJAAN PENUTUP PLAFOND - -
1 Plafond Gypsum 9mm/m2 98.63 m2 100,000 9,862,500
2 Plafond calsiboard 4mm/m2 - m2 -
SUB TOTAL BIAYA PEKERJAAN PENUTUP PLAFOND - 9,862,500
- -
G PEKERJAAN PELAPIS LANTAI - -
Beton tumbuk lantai - -
1 Rabat Beton T.7,5cm/m2 Tanpa Tulang dgn Koral 2.93 M3 350,000 1,023,750
NO PEKERJAAN VOL SAT Harga Satuan JUMLAH