R A B RUKOST IRAWAN TYPE 92

NO PEKERJAAN VOL SAT Harga Satuan JUMLAH

A PEKERJAAN PONDASI
1 Pas.Bouwplank T.1,00M/m' 56.22 m' 10,000 562,222
2 Galian Tanah Pondasi
pondasi Telapak 4.42 m3 35,000 154,560
Pondasi Batu Kali 4.60 m3 35,000 161,000
3 Bor Strous diameter 30 cm 46.00 m' 25,000 1,150,000
4 Cor beton strouss diameter 300cm - -
Beton 2.44 m3 850,000 2,071,811
Pembesian besi DEFORM 13 239.63 kg 9,500 2,276,519
besi 8 63.53 kg 9,500 603,569
5 Plat setempat PONDASI TELAPAK - -
Plat setempat 80 x80 - -
Beton 2.29 m3 850,000 1,946,311
Pembesian besi DEFORM 13 123.94 kg 9,500 1,177,466
besi DEFORM 13 123.94 kg 9,500 1,177,466
Plat setempat 50 x 50 - -
Beton 0.26 m3 850,000 217,222
Pembesian besi DEFORM 10 10.24 kg 9,500 97,287
besi DEFORM 10 10.24 kg 9,500 97,287
6 Pasangan Batu Kali 1:6 Pondasi Rumah 12.27 m3 650,000 7,973,333
7 Pasangan Batu Kali 1:6 Pondasi pagar Halaman 2.20 m3 650,000 1,428,556
8 Pasangan Batu Kali 1/2 camp. 1:6 4.91 m3 650,000 3,189,333
9 Tanah Urug.----diperhitungkan di fasum -
-
SUB TOTAL BIAYA PEKERJAAN PONDASI - 24,283,943
-
B PEKERJAAN STRUKTUR - `
LANTAI 1 -
1 Beton sloff 15/30 - -
Beton 2.42 m3 750,000 1,811,250
Pembesian besi DEFORM 13 223.66 kg 8,500 1,901,093
besi DEFORM 12 95.29 kg 8,500 809,933
besi 6 62.73 kg 8,500 533,206
begesting 32.20 m2 25,000 805,000
2 Beton sloff 15/20 - -
Beton 0.33 m3 750,000 247,250
Pembesian besi DEFORM 12 39.02 kg 8,500 331,687
besi 6 9.59 kg 8,500 81,540
begesting 4.40 m2 25,000 109,889
3 kolom 15/30.30 - -
Beton 1.21 m3 750,000 905,625
Pembesian besi DEFORM 12 127.05 kg 8,500 1,079,911
besi 6 28.85 kg 8,500 245,230
begesting 21.47 m2 50,000 1,073,333
4 kolom 15/30 - -
Beton 2.01 m3 750,000 1,509,375
Pembesian besi DEFORM 12 238.22 kg 8,500 2,024,833
besi 6 52.28 kg 8,500 444,338
begesting 20.13 m2 50,000 1,006,250
5 kolom 15/15 - -
Beton 0.40 m3 750,000 301,875
Pembesian besi 10 44.11 kg 8,500 374,969
besi 6 12.97 kg 8,500 110,241
begesting 3.07 m2 50,000 153,333
6 BALOK 15 /50 - -
Beton 4.60 m3 750,000 3,450,000
Pembesian besi 13 255.61 kg 8,500 2,172,678
besi 10 75.62 kg 8,500 642,804
besi 6 107.99 kg 8,500 917,924
begesting 52.13 m2 100,000 5,213,333
7 BALOK anak 15/25 - -
Beton 0.29 m3 750,000 215,625
Pembesian besi 10 18.91 kg 8,500 160,701
besi 6 7.83 kg 8,500 66,530
begesting 2.99 m2 100,000 299,000
8 Plat Lisplang - -
Beton 0.54 m3 750,000 402,500
Pembesian besi 8 14.12 kg 8,500 119,990
besi 8 20.17 kg 8,500 171,414
begesting 7.67 m2 100,000 766,667
9 Plat tangga - -
Beton 1.15 m3 750,000 862,500
Pembesian besi 10 31.51 kg 8,500 267,835
besi 10 31.51 kg 8,500 267,835
begesting 7.67 m2 100,000 766,667
LANTAI 2 - -
1 Plat Lantai - -
Beton 4.75 m3 850,000 4,033,817
Pembesian besi 8 250.06 kg 8,500 2,125,539
besi 8 250.06 kg 8,500 2,125,539
begesting 46.00 m2 150,000 6,900,000
2 kolom 15/30.30 - -
Beton 1.38 m3 850,000 1,173,000
Pembesian besi DEFORM 12 145.20 kg 8,500 1,234,184
besi 6 32.97 kg 8,500 280,263
begesting 24.53 m2 50,000 1,226,667
3 kolom 15/15 - -
Beton 1.61 m3 850,000 1,368,500
Pembesian besi 10 176.46 kg 8,500 1,499,876
NO PEKERJAAN VOL SAT Harga Satuan JUMLAH

besi 6 51.88 kg 8,500 440,964


begesting 14.31 m2 50,000 715,556
4 BALOK Ring 15 / 20 - -
Beton 1.38 m3 850,000 1,173,000
Pembesian besi 8 96.80 kg 8,500 822,789
besi 6 44.47 kg 8,500 377,969
begesting 18.40 m2 50,000 920,000
5 Plat KM dan teras serta talang Beton - -
5.a KM. kamar kost - -
Beton 0.37 m3 850,000 312,800
Pembesian besi 8 9.68 kg 8,500 82,279
besi 8 9.68 kg 8,500 82,279
begesting 3.83 m2 100,000 383,333
5.b Plat Teras depan - -
Beton 0.43 m3 850,000 369,278
Pembesian besi 8 11.43 kg 8,500 97,135
besi 8 11.43 kg 8,500 97,135
begesting 2.61 m2 100,000 260,667
5.c Plat Talang beton - -
Beton 3.99 m3 850,000 3,388,667
Pembesian besi 8 157.30 kg 8,500 1,337,032
besi 8 157.30 kg 8,500 1,337,032
begesting 39.87 m2 100,000 3,986,667
5.d Plat kanopi jendela - -
Beton 0.18 m3 850,000 149,883
Pembesian besi 8 6.96 kg 8,500 59,138
besi 8 6.96 kg 8,500 59,138
begesting 1.76 m2 100,000 176,333
SUB TOTAL BIAYA PEKERJAAN STRUKTUR - 71,220,619
C PEKERJAAN PASANGAN DINDING - -
LANTAI 1 dan 2 - -
1 Pas. Dinding bata Ringan 335.70 m2 115,000 38,605,244
- -
2 volume Kosen Almini/m' - -
128.05 m' 55,000 7,042,750
SUB TOTAL BIAYA PEKERJAAN PASANGAN DINDING - 45,647,994
- -
D PEKERJAAN RANGKA & PENUTUP ATAP - -
1 Rangka Atap Galvalum 42.77 48.56 m2 120,000 5,826,667
2 Pas.Genteng semi mantili (biji) 1,213.89 bji 1,400 1,699,444
3 Pas.Genteng Nok semi mantili /m' 102.22 bji 7,500 766,667
4 Pas.kalsi plang 30 CM 45.36 m' 20,000 907,222
SUB TOTAL BIAYA PEKERJAAN RANGKA & PENUTUP ATAP - 9,200,000
-
E PEKERJAAN PELAPIS DINDING - -
1 Acian dan Plesteran Tebal 23mm/m2 369.27 m2 17,500 6,462,182
2 Sekonengan Sudut Dinding/m' 38.33 m' 15,000 575,000
3 Tali Air Keliling Kosen/m' 39.42 m' 10,000 394,194
4 keramik dinding - m2 -
Pas.Keramik Dinding Lokal 20X25/m2 Mulia -Toilet lantai 1 29.52 m2 110,000 3,246,833
Pas.Keramik Dinding Lokal 20X25/m2 Mulia - Meja Dapur Lantai 1 3.19 m2 110,000 351,389
Pas.Keramik Dinding Lokal 20X25/m2 Mulia -Toilet lantai 2 29.52 m2 110,000 3,246,833
Pas.Keramik Dinding Lokal 20X25/m2 Mulia - Meja Dapur Lantai 2 - m2 110,000 -
5 Pasangan Granit dinding depan 14.91 m2 150,000 2,236,111
SUB TOTAL BIAYA PEKERJAAN PELAPIS DINDING - 14,276,432
-
F PEKERJAAN PENUTUP PLAFOND - -
1 Plafond Gypsum 9mm/m2 84.01 m2 100,000 8,401,389
2 Plafond calsiboard 4mm/m2 - m2 -
SUB TOTAL BIAYA PEKERJAAN PENUTUP PLAFOND - 8,401,389
- -
NO PEKERJAAN VOL SAT Harga Satuan JUMLAH

G PEKERJAAN PELAPIS LANTAI - -


Beton tumbuk lantai - -
1 Rabat Beton T.7,5cm/m2 Tanpa Tulang dgn Koral 2.49 M3 350,000 872,083
2 Pas. Granit 60 x 60 standart - -
lantai 1 49.83 m2 90,000 4,485,000
lantai 2 38.01 m2 90,000 3,421,250
3 Pas. Granit 60 x 60 kw standart meja dapur Lantai 1 dan 2 - -
lantai 1 0.77 m2 110,000 84,333
4 Pas.Keramik KM lantai Lokal 20X20/m2 Mulia - -
lantai 1 4.43 m2 105,000 464,888
tangga 7.67 m2 105,000 805,000
lantai 2 4.43 m2 105,000 464,888
SUB TOTAL BIAYA PEKERJAAN PELAPIS LANTAI - 10,597,442
- -
H PEKERJAAN PINTU, JENDELA, KACA - -
- -
1 Daun Pintu Almini 9.00 BH 550,000 4,950,000
2 Pintu toilet 8.00 BH 400,000 3,200,000
3 Jendela Rangka Almini kaca 8 mm 12.00 BH 250,000 3,000,000
SUB TOTAL BIAYA PEKERJAAN PINTU, JENDELA, KACA - 11,150,000
- -
I PEKERJAAN ENGSEL & KUNCI - -
1 Kunci Pintu /bh Lainnya 9.00 bh 100,000 900,000
2 Kunci Pintu K.Mandi Lain/bh 6.00 bh 65,000 390,000
3 Engsel pintu 9.00 set 75,000 675,000
4 Engsel jendela 12.00 set 50,000 600,000
SUB TOTAL BIAYA PEKERJAAN ENGSEL & KUNCI - 2,565,000
- -
J PEKERJAAN PENGECATAN - -
- -
1 Cat Tembok Dalam/m2 335.70 m2 15,000 5,035,467
2 Cat Tembok Luar/m2 167.85 m2 25,000 4,196,222
3 Cat plafond 84.01 m2 12,500 1,050,174
4 Cat genteng 48.56 m2 17,000 825,444
SUB TOTAL BIAYA PEKERJAAN PENGECATAN - 11,107,307
- -
K PEKERJAAN INSTALASI SANITASI - -
Air Bersih lantai 1 dan 2 - -
1 Pengeboran sumur air bersih dan pompa air -
2 Pemipaan PVC D dia 3/4"/m' 75.00 m' 15,000 1,125,000
3 kran air biasa 20.00 bj 25,000 500,000
kitchen zink 1.00 bj 50,000 50,000
4 kitchen zink 1.00 bh 250,000 250,000
Air Kotor - -
1 Pemipaan PVC AW dia 3"/m' (Bawah Lantai) lantai 1 dan 2 45.00 m' 25,000 1,125,000
2 Pemipaan PVC AW dia 4"/m' (Bawah Lantai) Lantai 1 dan 2 55.00 m' 35,000 1,925,000
3 avour kamar mandi 8.00 m' 50,000 400,000
4 closet duduk 8.00 750,000 6,000,000
5 Septic Tank buis beton 4 bh dim 1 m 6.00 bh 250,000 1,500,000
6 Resapan Air kotor buis beton dim 1 m 6.00 bh 250,000 1,500,000
SUB TOTAL BIAYA PEKERJAAN INSTALASI SANITASI - 14,375,000
-
L PEKERJAAN INSTALASI LISTRIK -
Lantai 1 dan 2 -
1 Titik Lampu Dalam/ttk Bawah Plafond 16.00 ttk 100,000 1,600,000
2 Titik Lampu Luar 4.00 ttk 125,000 500,000
3 Titik Stop Kontak Biasa/ttk 10.00 ttk 85,000 850,000
4 Saklar 7.00 ttk 75,000 525,000
SUB TOTAL BIAYA PEKERJAAN INSTALASI LISTRIK - 3,475,000
-
M PEKERJAAN LAIN-LAIN Lantai 1 dan 2 -
1 Sun Screen Galvalum - -
lantai 1 3.50 m' 250,000 875,000
lantai 2 kamar kost luar 3.50 m' 85,000 297,500
exhoust fan 5.11 bh 250,000 1,277,778
2 Raling Tangga 12.78 m' 275,000 3,513,889

SUB TOTAL BIAYA PEKERJAAN LAIN - LAIN 5,964,167

TOTAL BIAYA PEKERJAAN 233,382,348

harga per m2 2,536,764.65