I. PEKERJAAN PERSIAPAN
1 Papan Nama Proyek Ls 1.00
2 Administrasi dan Dokumen Proyek Ls 1.00
3 Mobilisasi dan Demobilisasi Ls 1.00
4 Pengukuran dan Pemasangan Bouwplank m2 216.00
5 Pembersihan Lokasi m2 1,892.00
B STRUKTUR ATAS
1 Pasir Urug dipadatkan memakai alat tebal 5 cm m3 88.20
2 Plat Lantai dasar tebal 10 cm level ± 0,00
a Wire mesh M 6 1 lapis m2 76.65
b Lantai kerja m3 88.20
c Beton K-250 m3 176.40
B PEKERJAAN PLAFON
Bahan plafon gypsum t = 9 mm, Rangka holloW 4/4 dan 4/2
1 Area ruang kantor m² 72.00
E PEKERJAAN SANITAIR
1 Closet duduk
pcs 1.00
2 Closet jongkok
pcs 2.00
3 Westafel
pcs 1.00
4 Kran dinding
pcs 4.00
5 Floor drain plastik
pcs 3.00
F PEKERJAAN PENGECATAN
A PEKERJAAN MEKANIKAL
49,952,240.00 22,360,000.00
2,122,428,896.35 1,759,600,091.11
514,781,274.66 476,478,380.00
3,000,000.00 500,000.00 3,500,000.00 3,500,000.00 2,500,000.00 2,500,000.00
B PEKERJAAN PLAFON
Bahan plafon gypsum t = 9 mm, Rangka holloW 4/4 dan 4/2
1 Area ruang kantor m² 72.00
2,122,428,896.35 1,759,600,091.11
E PEKERJAAN SANITAIR
1 Closet duduk
pcs 1.00
2 Closet jongkok
pcs 2.00
3 Westafel
pcs 1.00
4 Kran dinding
pcs 4.00
5 Floor drain plastik
pcs 3.00
F PEKERJAAN PENGECATAN
514,781,274.66 476,478,380.00
2 PENGADAAN FORKLIF
a FORKLIFT 5 ton pcs 1.00
b Menggunakan Hydrant
1 Pompa hydrant set 1.00
2 Pipa tegak pcs 3.00
3 Box hydrant type B pcs 3.00
4 Siamesse connection pcs 3.00
5 Plumbing set 1.00
6 Kolam pemadam (beton) pcs 1.00
7 Jasa instalasi hydrant titik 3.00
B PEKERJAAN ELEKTRIKAL
1 PEKERJAAN LITRIK
Pengadaan, pemasangan dan pengujian seluruh pekerjaan Listrik,
termasuk pekerjaan panel-panel, pekerjaan genset, Pekerjaan Istalasi
dan Armateur, lengkap dengan komponen panel dan accessories
A Pekerjaan Panel-panel
1 PHB (Panel Distribution Board), indoor panel unit 3.00
2 MCB BOX (indoor panel) unit 4.00
3 Panel penerangan luar c/w Timer Switch ls 3.00
4 Instalasi Pentanahan ls 7.00
B Pekerjaan Instalasi Kabel Permesinan
1 Kabel PHB ke mesin chipper NYFGBY 4 x95 mm2 m' 20.00
2 Kabel PHB ke mesin coarse hammer mill NYFGBY 4 x 300 mm2 m' 20.00
3 Kabel PHB ke mesin fine hammer mill NYFGBY 4 x300 mm2 m' 20.00
4 Kabel PHB ke mesin dryer NYFGBY 4 x 150 mm2 m' 30.00
C Pekerjaan Instalasi Kabel Penerangan
1 Kabel PHB ke penerangan pabrik baris 1 NYY 3 x6 mm2 m' 150.00
2 Kabel PHB ke penerangan pabrik baris 2 NYY 3 x6 mm2 m' 150.00
3 Kabel PHB ke penerangan pabrik baris 3 NYY 3 x6 mm2 m' 150.00
4 Kabel PHB ke penerangan sekeliling pabrik NYY 3 x4 mm2 m' 150.00
5 Kabel PHB ke penerangan lantai 1 pabrik NYY 3 x4 mm2 m' 150.00
6 Lampu penerangan pabrik 200 watt (LED) ttk 19.00
Lampu penerangan 30 watt (LED) ttk 3.00
Lampu penerangan 20 watt (LED) ttk 5.00
Lampu penerangan 15 watt (LED) ttk 21.00
Lampu penerangan 10 watt (LED) ttk 5.00
D Pekerjaan Instalasi Kabel AC
1 Kabel PHB ke AC kantor lantai 1 NYY 3 x6 mm2 m' 150.00
2 Kabel PHB ke AC kantor lantai 1 NYY 3 x6 mm2 m' 200.00
3 AC Split converter (11900 btu/h, COP>3), setara Daikin kantor utama pcs 2.00
4 AC Split converter (11900 btu/h, COP>3), setara Daikin ruang direktur pcs 1.00
5 AC Split converter (8500 btu/h, COP>3), setara Daikin ruang k3 pcs 1.00
6 AC Split converter (11900 btu/h, COP>3), setara Daikun ruang kontrol pcs 1.00
7 Instalasi Stop Kontak u/ AC kabel 3 x 2,5 mm² + pvc 20 mm ttk 8.00
- Receptacle Tunggal 10 A bh 20.00
- Receptacle Ganda 10 A bh 20.00
- Stop Kontak 16 A bh 40.00
HARGA SATUAN HARGA SATUAN JUMLAH PELAKSANAAN
BAHAN UPAH HARGA SATUAN JUMLAH
650,000 650,000.00 650,000.00 250,000 250,000.00
230,000 230,000.00 230,000.00 200,000 200,000.00
4,500,000 4,500,000.00 4,500,000.00 2,500,000 2,500,000.00
350,000 350,000.00 350,000.00 300,000 300,000.00
2,500,000 2,500,000.00 5,000,000.00 1,200,000 2,400,000.00
2,400,000 2,400,000.00 4,800,000.00 100,000 200,000.00
2,750,000 2,750,000.00 5,500,000.00 650,000 1,300,000.00
500,000 500,000.00 500,000.00 - -
872,472,100.00 753,275,600.00
3 PEKERJAAN KOMUNIKASI
a CCTV (temasuk aksesoris)
1 Kamera CCTV indoor pcs 8.00
2 DVR 8 channel pcs 1.00
3 HDD 1 GB Sata 7200 rpm pcs 1.00
4 Monitor 32" (LED) pcs 1.00
5 Kabel koaksial RG 6 m 100.00
6 Kabel power listrik m 100.00
7 Socket BMC pcs 2.00
8 Jasa instalasi dan program titik 8.00
2,138,902,500.00 3,376,550,000.00
C JEMBATAN TIMBANG
1 Weighting Scale 40 Ton Set 1.00
V Mesin-mesin produksi
1 Opsi tanpa SCADA Set 1.00
a Main Unit
1 Drum Wood Chipper
2 Double shaft hammer mill (Coarse)
3 Rotary dryer three pass
4 Double shaft hammer mill (Fine)
5 Final Product Storage
b Full Equipment 1 line
Belt conveyor
Frequency converter
PLC Electric cabinet
Belt conveyor
Frequency converter
Permanent magnet
Pulse dust cleaner
Wood chip silo
Frequency converter
Belt conveyor
Frequency converter
Permanent Magnet
Electric Cabinet (PLC)
Heavy screw conveyor
Frequency converter
Belt conveyor
Frequency converter
Belt conveyor
Frequency converter
Permanent Magnet
PLC Electric cabinet
Fan (Negative)
Cyclone
Air lock
Dust collector
Belt conveyor
HARGA SATUAN HARGA SATUAN JUMLAH PELAKSANAAN
BAHAN UPAH HARGA SATUAN JUMLAH
63,375.00 63,375.00 114,011,625.00 25,000.00 44,975,000.00
751,320.00 68,900.00 820,220.00 156,662,020.00 350,000.00 66,850,000.00
243,500.00 13,900.00 257,400.00 73,101,600.00 135,000.00 38,340,000.00
751,320.00 68,900.00 820,220.00 194,802,250.00 350,000.00 83,125,000.00
75,000.00 25,000.00 100,000.00 117,000,000.00 75,000.00 87,750,000.00
1,095,740,595.10 862,974,000.00
Frequency converter
Bucket lift
Frequency converter
Heating stove
Biomass Burner
Sealed Belt conveyor
Frequency converter
Chips feeder
Sealed Belt conveyor
Frequency converter
Rotary valve
Air lock
Cyclone
Fan (Negative)
Electric cabinet
Sealed Belt conveyor
Frequency converter
Wood chip silo
Frequency converter
Bucket lift
Frequency converter
Electric cabinet
Air pump
Sawdust Silo
Dust collector
Platfrom
Output conveyor
Frequency converter
PENAWARAN 23,968,489,000.00
PPN (11%) (2,375,255,740.67)
PPH (3%) (647,796,997.78)
TOTAL 20,945,436,261.55
PELAKSANAAN 16,381,238,071.11
MARGIN 4,564,198,190.44
HARGA SATUAN HARGA SATUAN JUMLAH PELAKSANAAN
BAHAN UPAH HARGA SATUAN JUMLAH
11,455,000,000.00 8,380,000,000.00
21.14%