A PEKERJAAN SIPIL
I Pekerjaan Persiapan
1 Mobilisasi dan demobilisasi ls -
2 Pengukuran dan bouwplank ls 2,421,225
3 Air Kerja ls 1,398,930
4 Engineering dan asbuiltdrawing ls 3,500,000
5 Dokumentasi proyek ls 3,500,000
6 Keamanan proyek ls -
7 SITE SURVEY ls -
8 Soil test ls -
9 Design pondasi / Baseframe Tower ls -
Sub Total
B PEKERJAAN TOWER
I. PEKERJAAN PABRIKASI TOWER, BASEFRAME DAN RING MOUNTING
1 Pengadaan Tower / Pole ( Supply by Owner); kg
2 Pengadaan Ring Mounting 3 Set ( Supply by Owner); kg
3 Pengadaan Baseframe ( Supply by Owner); kg
Sub Total
II. PEKERJAAN ERECTION, PAINTING TOWER
1 Pengiriman material angkur&template dan tower dan ring mounting ke lokasi kg
2 Incl sorter erection
Pekerjaan & Assuransi (from Supplier/Fabricator)
tower kg 3,375
3 Pengecatan tower EX. Delta Acrylac kg 2,345
4 Pengiriman material Baseframe ke lokasi Incl sorter & Assuransi (from kg
5 Supplier/Fabricator)
Pekerjaan erection Baseframe kg
6 Pengecatan Baseframe EX. Delta Acrylac kg
7 Pengiriman Pole Pole
8 Erection / Instalasi Pole Pole
Sub Total
C PEKERJAAN MEKANIKAL DAN ELEKTRIKAL
1 Panel KWH + COS 13,2KVA (XL) POLYESTER (Go Green ) ls 850,000
2 Tiang KWH T = 6 m dia 3" (inc. Pondasi ) ls 350,000
3 Panel ACPDB Polyester (Go Green ) ls 350,000
4 Tiang ACPDB T=2,1 M, dia 3 inchi ls 605,000
5 Kabel Power NYFGBY 4x16mm2 ( Disesuaikan Dng Kondisi Lapangan ); m' 35,000
Kabelindo;
6 Kabel power Kabel Metal;
u / Tiang Supreme;
Lampu Tranka
Halaman kabel Dengan Scoen Cable &
Lengkap m' 23,000
7 Clamp
Pad lock(disesuaikan dengan
anti karat untuk kondisi
Panel Kwh lapangan)
& ACPDB, material approved ; CISA bh 75,000
8 Plat identitas tower ( stainless tebal 2 mm uk. 300x400 mm ) bh 150,000
Sub Total
D PEKERJAAN GROUNDING SYSTEM
Grounding System ( maks 1ohm )
1 Terminal Main Grounding Steel plate Galvanized (Alumunium plate) , 10x30x1 bh 118,028
cm+Isolator+14
2 Terminal Lubang
IGB, Steel platedia.
Galvanized (Alumunium plate) 10x30x1 cm+14 bh 118,028
Lubang dia.
3 Terminal EGB12Steel
mm (2x7
platezig zag )
Galvanized (Alumunium plate) 10x30x1 cm+14 bh 118,028
Lubang dia.
4 Terminal 12 mm
Upper, (2x7 dan
middle zig zag ) bar Alumunium plate
Lower bh 118,028
10x30x1cm+isolator+14
5 Copper Lubang
Rod dia 3/4" ( L 400 cm) ;dia. 12 mm
Furse; (2x7Cerah
Tokai; zig zag )
Sempurna; BMC Depth bh 214,000
6 4m
Copper Rod dia 3/4" ( L 400 cm) ; Furse; Tokai; Cerah Sempurna; BMC Depth bh 214,000
7 6m
Bak Kontrol uk 50x50x40 (see detail drawing) set 214,000
8 Grounding Labelling uk 60x20 mm (stainless) bh 118,028
9 Penarikan Kabel AAAC 70 mm2 dari splitzen ke conector bimetallic m' 10,000
10 (Kabelindo; Kabel Metal; Supreme; Tranka kabel)
Cable clam isolator bh 10,000
11 Penarikan Kabel Bc 50mm2 dari connector bimetalic (dari Splitzen ) ke m' 214,000
12 copper bonded
Cable clam rod Perimeter
isolator bh 118,028
13 Penarikan kabel AAAC 70 mm2 Dari EGB ke Bak Kontrol (Kabelindo; Kabel m' 35,000
14 Metal; Supreme;
Cable clam Tranka kabel) Dibungkus cabble flexible conduit Black Dia
isolator bh 118,028
15 3/4"
Penarikan kabel AAAC 70 mm2 Dari IGB ke Bak Kontrol (Kabelindo; Kabel m' 35,000
16 Metal; Supreme;
Cable clam Tranka kabel) Dibungkus cabble flexible conduit Black Dia
isolator bh 118,028
17 3/4"
Penarikan kabel AAAC 70 mm2 Secara paralel Dari Upper Middle Lower m' 35,000
Busbar ke kabel
18 Penarikan Bak Kontrol
AAAC (Kabelindo;
70 mm2 DariKabel
ACPDB Metal; Supreme;
ke IGB Tranka
(Kabelindo; kabel)
Kabel Metal; m' 35,000
19 Dibungkus
Penarikan cabble
Supreme; Tranka
kabel flexible
kabel)
Bcc 50 mm2conduit
Dibungkus Black
Dari BakcabbleDiaflexible
Kontrol 3/4" conduit
ke copper Black
rod, Dia 3/4"
kemudian m' 35,000
dihubungkan
20 Penarikan ke AAAC
kabel perimeter dengan
70 mm2 daricadweld (Kabelindo;
Bak Kontrol Kabel Metal;
ke Connector Bimetallic m' 118,028
21 Supreme;
Cable clamTranka
(Kabelindo; Kabelkabel)
isolator Metal; Supreme; Tranka kabel) Dibungkus cabble flexible bh 118,028
22 conduit
PenarikanBlack
kabelDiaBc3/4"
50 mm2 Dari kaki tower ke ring perimeter (Kabelindo; m' 35,000
Kabel Metal;
23 Penarikan Supreme;
kabel Tranka
Bc 50 mm2 kabel)
untuk ringdiparameter
Cadweld sekitar pagar (Kabelindo; m' 35,000
Kabel Metal;
24 Penarikan Supreme;
kabel Tranka
Bc 50 mm2 kabel)
dari di cadweld
perimeter ke pagar (Kabelindo; Kabel Metal; m' 35,000
Supreme; Tranka
25 Penarikan kabel Bc kabel) di cadwell
50 mm2 dengan
dari tiang bungkus
box KWH metercabble flexible
dan panel KWHconduit
meter m' 35,000
26 Black
ke Dia (See
Bimetalic 3/4"(Kabelindo;
perimeter Kabel Metal; Supreme; Tranka kabel) di cadwell
detail Drawing) bh 35,000
27 dengan
Lightningbungkus
Rod cable flexible conduit Black Dia 3/4" bh 35,000
28 Pengelasan Exothermic / Caldweld ttk 35,000
Sub Total
E OBSRTUCTION LIGHT
Panel lampu (fiberglass) lengkap dengan MCB 6A, Indikator lamp, trafo step
1 up/down 100 watt, set 750,000
Arrester OBO V20, Fotocell Lumina, terminal blok, kontaktor, wiring internal
2 panel,
Upper kabel gland dan
OBL material mounting
approved; Avialite (Li-1016A, 25cd, 220VAC, 50/60HZ, bh 263,700
4.4W, IP67) & Alpha (LIA 1.220VAC
Lower OBL material approved; Include
Avialite (Li-1016A, 25cd, 220VAC, 50/60HZ, bh
4.4W, IP67) & Alpha (LIA 1.220VAC Include
3 Kabel NYY 3x2,5 mm (catuan dari COS-ACPDB di shelter) m' 10,000
Sub Total
F PEKERJAAN MOUNTING ANTENNA
1 Supply dan Instalasi monting antena Microweve ( Uk. 2.5 m dia. 3" ) set 575,000
2 Supply dan Instalasi monting antena Sector ( Uk. 2.5 m dia. 3" ) set 575,000
Sub Total
G PLN POWER
1 13.200 VA PLN Power 3 phasa ls 3,500,000
Sub Total
TOTAL =
PASIR BETON
SPLIT
BATU KALI
SEMEN 50KG
BESI BETON
BENDRAT
Batu bata(20x10x5)
KASO 5/7
TRIPLEKS 9mm
KAWAT DURI
I PENAWARAN (FINAL)
able dasar menunggu hasil survey actual. Variable dasar menunggu hasil survey actual.
WESI TENGGARA-KONAWE KEPULAUAN SULAWESI TENGAH
Volume JUMLAH Unit Harga satuan Volume (Actual) JUMLAH
(Actual)
1.00 0 ls - 1.00 0
1.00 2,421,225 ls 2,421,225 1.00 2,421,225
1.00 1,398,930 ls 1,398,930 1.00 1,398,930
1.00 3,500,000 ls 3,500,000 1.00 3,500,000
1.00 3,500,000 ls 3,500,000 1.00 3,500,000
1.00 0 ls - 1.00 0
1.00 0 ls - 1.00 0
1.00 0 ls - 1.00 0
1.00 0 ls - 1.00 0
10,820,155 10,820,155
0 m' 0
1.00 1,500,000 ls 1,500,000 1.00 1,500,000
1.50 709,500 ls 473,000 1.50 709,500
1.60 827,117 m2 516,948 1.60 827,117
66.58 5,392,980 m3 81,000 66.58 5,392,980
0 m2 0
149,793,303 149,793,303
0 kg 0
kg
kg
0 0
- kg -
7243.00 24,445,125 kg 3,375 7243.00 24,445,125
7243.00 16,984,835 kg 2,345 7243.00 16,984,835
0 kg 0
0 kg 0
0 kg 0
0 Pole 0
0 Pole 0
41,429,960 41,429,960
750,000 750,000
1.00 set 750,000 1.00
2.00 527,400 bh 263,700 2.00 527,400
bh
46.00 460,000 m' 10,000 46.00 460,000
1,737,400 1,737,400
al design
Rp195,000 M3
Rp120,000 M3
Rp210,000 M3
Rp76,000 SAK
Rp12.869 KG
Rp15,000 KG
Rp1,200 UNIT
Rp68,000 Batang
Rp98,000 Lembar
Rp85,000 KG
Variable dasar menunggu hasil survey actual.
MALUKU UTARA - KEPULAUAN SULA
Unit Harga satuan Volume (Actual) JUMLAH
ls - 1.00 0
ls 2,421,225 1.00 2,421,225 2,421,225
ls 1,398,930 1.00 1,398,930 1,398,930
ls 3,500,000 1.00 3,500,000 3,500,000
ls 3,500,000 1.00 3,500,000 3,500,000
ls - 1.00 0
ls - 1.00 0
ls - 1.00 0
ls - 1.00 0
10,820,155
m' 0
ls 1,500,000 1.00 1,500,000 1,500,000
ls 473,000 1.50 709,500 473,000
m2 516,948 1.60 827,117 516,948
m3 81,000 66.58 5,392,980 27,000 54,000
m2 0
149,793,303
kg 0
kg
kg
0
kg -
kg 3,375 7243.00 24,445,125 3,375
kg 2,345 7243.00 16,984,835 2,345
kg 0
kg 0
kg 0
Pole 0
Pole 0
41,429,960
750,000 750,000
set 750,000 1.00
bh 263,700 2.00 527,400 263,700
bh
m' 10,000 46.00 460,000 10,000
1,737,400
ADUKAN 1:3
semen 50 kg 9.333333333
pasir 150 kg 0.107142857
ADUKAN 1:5
semen 50 kg 5.6
pasir 250 kg 0.178571429
profit
Koefisien 2020
Tanah Biasa Tanah Cadas
0.9 0.045
0.8 0.04
0.8 0.04
0.1 0.04
0.25 0.025
0.5 0.05
0.75 0.025
0.8636 0.04113
0.8636 0.04113
0.25 0.025 0.25 0.025
0.33 0.01 0.33 0.01
0.75 0.025
0.8 0.04
0.8636 0.04113
0.8636 0.04113
0.25 0.025 0.25 0.025
0.33 0.01 0.33 0.01
0.8 0.04
0.8 0.04
0.8 0.04
0.8 0.04
0.8 0.04
0.8 0.04
0.8 0.04
0.8 0.04
0.8 0.04
0.8 0.04
0.8 0.04
0.8 0.04
0.75 0.025
0.1 0.04
0.8 0.04
0.8 0.04
0.8 0.04
0.8 0.04
2 1
2 1
2 1
1.3 0.8
0.8 0.04
0.8 0.04
0.8 0.04
0.8 0.04
0.8636 0.04113
0.8636 0.04113
0.8636 0.04113
0.8636 0.04113
0.8 0.04
0.8 0.04
0.8 0.04
0.8636 0.04113
0.8636 0.04113
0.8636 0.04113
0.8 0.04
0.8636 0.04113
0.8 0.04
0.8636 0.04113
0.8 0.04
0.8636 0.04113
0.8636 0.04113
0.8 0.04
0.8 0.04
0.8636 0.04113
0.8636 0.04113
0.8 0.04
0.8 0.04
0.8 0.04
0.8 0.04
0.8636 0.04113
0.8636 0.04113
0.8 0.04
HARGA
7.42 SAK Rp76,000 Rp563,920
0.50 M3 Rp195,000 Rp97,221
0.58 M3 Rp120,000 Rp69,800
Rp730,941
UPAH Rp250,000
Rp980,941 M3
709,333
m3 Rp195,000
UPAH 25,000
929,333 M3
425,600
m3 Rp195,000
UPAH 25,000
645,600 M3
763,800
388,600
0
0
0
0
0
0
1,500,000
709,500
827,117
176,625
23,606
2,668
23,606
3,905
34,400
1,450,356
5,460
179,400
984,400
1,712,000
7,850,000
898,800
495,716
2,395,958
658,128
2,468,200
513,600
85,600
1,950,000
1,950,000
3,040,000
3,500,000
3,200,000
214,000
214,000
1,950,000
1,800,000
0
53,500
137,375
13,340
17,200
1,550,844
171,600
171,600
2,108,148
48,000
24,445,125
16,984,835
850,000
350,000
350,000
605,000
525,000
460,000
150,000
150,000
118,028
118,028
118,028
236,055
856,000
428,000
214,000
826,193
520,000
360,000
856,000
0
280,000
0
262,500
0
2,905,000
350,000
262,500
0
0
1,512,000
2,100,000
350,000
140,000
35,000
35,000
525,000
115,338,495 Rp174,858,837
18.6
x 10
250,000 250,000
150,000 150,000
105,333 421,333
Total 7,404,775
profit 15% 1,110,716
Rp8,515,491
Besi Ø<13mm (MPa) Besi Ø>13mm (MPa)
240 390
x 10 x 10
2400 3900