PERHITUNGAN BOQ

Type Tower : SST 42 M


KALIMANTAN/SULAWESI
No. ITEM Unit Harga satuan Volume JUMLAH
(Actual)
A PEKERJAAN SIPIL
I Pekerjaan Persiapan
1 Mobilisasi dan demobilisasi ls 10.000.000 1,00 10.000.000
2 Pengukuran dan bouwplank ls 2.690.000 1,00 2.690.000
3 Air Kerja ls 1.980.000 1,00 1.980.000
4 Engineering dan asbuiltdrawing ls 3.700.000 1,00 3.700.000
5 Dokumentasi proyek ls 1.500.000 1,00 1.500.000
6 Keamanan proyek ls 4.800.000 1,00 4.800.000
7 SITE SURVEY ls 12.500.000 1,00 12.500.000
8 Soil test ls 2.700.000 1,00 2.700.000
9 Design pondasi / Baseframe Tower ls 4.500.000 1,00 4.500.000
Sub Total 44.370.000

II Pekerjaan Tanah
1 Galian tanah pondasi m3 172.500 110,00 18.975.000
2 Urugan dan pemadatan kembali tanah pondasi (using stamper) m3 63.600 82,00 5.215.200
3 Buangan tanah ke luar lokasi m3 87.500 29,00 2.537.500
Sub Total 26.727.700
III Pekerjaan Beton
1 Lapisan pasir bawah pondasi dipadatkan tebal 10 cm m3 223.500 5,70 1.273.950
2 Lantai kerja beton 1:3 tebal 5 cm m3 1.371.583 2,90 3.977.591
3 Beton bertulang pondasi K 225 / Besi KS D 16
- Plat / Tapak Pondasi Beton bertulang K 225 / Besi KS D16 m3 4.721.675 26,00 122.763.550
- Pedestal Pondasi Beton bertulang K 225 / Besi KS D 16 m3 11.948.046 2,50 29.870.115
- Tie Beam Pondasi Beton bertulang K 225 / Besi KS D 16 m3 0
4 Borepile ( standar diameter 40 cm )
- Meter panjang m' 0
5 Penyetelan angkur dan template ls 8.000.000 1,00 8.000.000
6 Grouting pedestal di bawah base plate : Sika Grout 215 ls 580.000 1,00 580.000
7 Pasangan Bata dibawah tower m2 315.008 1,60 504.013
8 Pengadaan Beton Counter Weight (K225 Besi KS) See drawing m2 0
Sub Total 166.969.219

IV PEKERJAAN PONDASI OUTDOOR DAN RANGKA ATAP


1 Galian tanah pondasi shelter m3 86.250 0,90 77.625
2 Pasangan Aanstamping bawah pondasi batu kali tebal 10 cm m3 989.288 0,20 197.858
3 Urugan pasir bawah pondasi batu kali tebal 5 cm m3 223.500 0,10 22.350
4 Pasangan batu kali pondasi Outdoor m3 1.534.862 1,10 1.688.348
5 Urugan dan pemadatan kembali tanah pondasi m3 57.500 0,10 5.750
6 Buangan tanah ke luar lokasi m3 87.500 0,40 35.000
7 Beton bertulang pondasi K 225 / KS dia 12mm m3 1.951.268 0,36 702.457
8 Trap anak tangga m3 1.722.685 0,14 241.176
9 Plesteran dan acian pondasi shelter m2 114.140 4,60 525.044
10 Pengecatan pondasi shelter ( ICI Dulux warna hitam ) m2 66.840 4,60 307.464
11 Horizontal Cable Tray w=30 cm & support ( see drawing detail ) m3 1.680.000 8,00 13.440.000
Sub Total 17.243.071

V PEKERJAAN PAGAR DAN HALAMAN 10x10 M²


1 Galian tanah untuk pondasi batu kali menerus sekeliling pagar m3 86.250 40,00 3.450.000
2 Urugan pasir bawah pondasi batu kali tebal 10 cm m3 223.500 4,20 938.700
3 Pasangan aanstamping tebal 10 cm m3 989.288 4,20 4.155.010
4 Pondasi batu kali menerus sekeliling pagar camp. 1 : 5 m3 1.534.862 20,30 31.157.699
5 Urugan kembali tanah galian pondasi batu kali sekeliling pagar m3 57.500 19,70 1.132.750
6 Buangan tanah galian pondasi batu kali m3 87.500 28,70 2.511.250
7 Balok sloof menerus sekeliling pagar uk. 20/20 beton bertulang praktis camp 1:3:5 m3 16.725.318 2,40 40.140.763
8 Kolom praktis 20/20 Beton bertulang Praktis camp. 1:3:5 m3 21.265.230 0,40 8.506.092
9 Plesteran dan acian Balok sloof 20/20 & kolom praktis 20/20 m2 114.140 39,00 4.451.460
10 Pengecatan dan acian Balok sloof 20/20 & kolom praktis 20/20 (ICI Dulux warna Putih Weathershield ) m2 66.840 39,00 2.606.760
11 Panel pagar BRC dia 8 mm, tinggi 1900 mm : hot dipped galvanized (Hanya upah pasang) m' 30.000 38,00 1.140.000
12 Support pagar BRC, pipa 2" rol bending 45° (hanya upah pasang) bh 25.000 28,00 700.000
13 Kawat duri 5 layer + silangan Diagonal m' 36.600 40,00 1.464.000
14 Pintu pagar BRC lebar 3000 mm ( plat baja lb 2 mm + besi BRC M8 ) : hot dipped galvanized (hanya upah pasang) set 300.000 1,00 300.000
15 Pad lock anti karat untuk pintu pagar BRC, material approved ; CISA bh 395.000 1,00 395.000
16 Hamparan Gravel Untuk Halaman Tebal 10 Cm m3 364.500 10,00 3.645.000
17 Hamparan Pasir Urug di bawah Gravel Tebal 10 Cm m3 223.500 10,00 2.235.000
18 Pengadaan dan pemasangan lampu penerangan mercury (merk Armatur Philip Min IP 65, Tipe SON PRO/T220 V /150 V) Photocell 10 A + tiang ls 365.000 1,00 365.000
19 Beton Pondasi Tangga , suport tray horizontal ( see Drawing detail) m3 1.722.685 0,25 430.671
Sub Total 109.725.155

VI PEKERJAAN AKSES JALAN DAN JEMBATAN


1 Galian tanah untuk cansteen dan rabat beton akses jalan m3 43.125 0,70 30.188
2 Urugan pasir bawah rabat beton tebal 5 cm m3 223.500 0,50 111.750
3 Buangan tanah galian cansteen m3 87.500 0,20 17.500
4 Pasangan 1/2 batubata cansteen m2 315.008 3,00 945.024
5 Plesteran dan acian pasangan cansteen m2 114.140 5,20 593.528
6 Pengecatan cansteen ( ICI Dulux warna hitam Weathershield ) m2 66.840 5,20 347.568
7 Rabat beton tebal 15 cm akses jalan ( dimensi see drawing detail) m3 2.219.605 1,50 3.329.408
8 Gravel tebal 10cm m3 364.500 0,40 145.800
Sub Total 5.520.765

B PEKERJAAN TOWER
I. PEKERJAAN PABRIKASI TOWER, BASEFRAME DAN RING MOUNTING
1 Pengadaan Tower / Pole ( Supply by Owner); kg 0
2 Pengadaan Ring Mounting 3 Set ( Supply by Owner); kg
3 Pengadaan Baseframe ( Supply by Owner); kg
Sub Total 0
II. PEKERJAAN ERECTION, PAINTING TOWER
1 Pengiriman material angkur&template dan tower dan ring mounting ke lokasi Incl sorter & Assuransi (from Supplier/Fabricator) kg -
2 Pekerjaan erection tower kg 8.600 7243,00 62.289.800
3 Pengecatan tower EX. Delta Acrylac kg 18.800 7243,00 136.168.400
4 Pengiriman material Baseframe ke lokasi Incl sorter & Assuransi (from Supplier/Fabricator) kg 0
5 Pekerjaan erection Baseframe kg 0
6 Pengecatan Baseframe EX. Delta Acrylac kg 0
7 Pengiriman Pole Pole 0
8 Erection / Instalasi Pole Pole 0
Sub Total 198.458.200
C PEKERJAAN MEKANIKAL DAN ELEKTRIKAL
1 Panel KWH + COS 13,2KVA (XL) POLYESTER (Go Green ) ls 1,00 0
2 Tiang KWH T = 6 m dia 3" (inc. Pondasi ) ls 1,00 0
3 Panel ACPDB Polyester (Go Green ) ls 1,00 0
4 Tiang ACPDB T=2,1 M, dia 3 inchi ls 1,00 0
5 Kabel Power NYFGBY 4x16mm2 ( Disesuaikan Dng Kondisi Lapangan ); Kabelindo; Kabel Metal; Supreme; Tranka kabel m' 15,00 0
6 Kabel power u / Tiang Lampu Halaman Lengkap Dengan Scoen Cable & Clamp (disesuaikan dengan kondisi lapangan) m' 20,00 0
7 Pad lock anti karat untuk Panel Kwh & ACPDB, material approved ; CISA bh 2,00 0
8 Plat identitas tower ( stainless tebal 2 mm uk. 300x400 mm ) bh 1,00 0
Sub Total 0
D PEKERJAAN GROUNDING SYSTEM
Grounding System ( maks 1ohm )
1 Terminal Main Grounding Steel plate Galvanized (Alumunium plate) , 10x30x1 cm+Isolator+14 Lubang dia. bh 1,00 0
2 Terminal IGB, Steel plate Galvanized (Alumunium plate) 10x30x1 cm+14 Lubang dia. 12 mm (2x7 zig zag ) bh 1,00 0
3 Terminal EGB Steel plate Galvanized (Alumunium plate) 10x30x1 cm+14 Lubang dia. 12 mm (2x7 zig zag ) bh 1,00 0
4 Terminal Upper, middle dan Lower bar Alumunium plate 10x30x1cm+isolator+14 Lubang dia. 12 mm (2x7 zig zag ) bh 2,00 0
5 Copper Rod dia 3/4" ( L 400 cm) ; Furse; Tokai; Cerah Sempurna; BMC Depth 4m bh 4,00 0
6 Copper Rod dia 3/4" ( L 400 cm) ; Furse; Tokai; Cerah Sempurna; BMC Depth 6m bh 2,00 0
7 Bak Kontrol uk 50x50x40 (see detail drawing) set 1,00 0
8 Grounding Labelling uk 60x20 mm (stainless) bh 7,00 0
9 Penarikan Kabel AAAC 70 mm2 dari splitzen ke conector bimetallic (Kabelindo; Kabel Metal; Supreme; Tranka kabel) m' 52,00 0
10 Cable clam isolator bh 36,00 0
11 Penarikan Kabel Bc 50mm2 dari connector bimetalic (dari Splitzen ) ke copper bonded rod Perimeter m' 4,00 0
12 Cable clam isolator bh 0
13 Penarikan kabel AAAC 70 mm2 Dari EGB ke Bak Kontrol (Kabelindo; Kabel Metal; Supreme; Tranka kabel) Dibungkus cabble flexible conduit m' 8,00 0
14 Cable clam isolator bh 0
15 Penarikan kabel AAAC 70 mm2 Dari IGB ke Bak Kontrol (Kabelindo; Kabel Metal; Supreme; Tranka kabel) Dibungkus cabble flexible conduit m' 7,50 0
16 Cable clam isolator bh 0
17 Penarikan kabel AAAC 70 mm2 Secara paralel Dari Upper Middle Lower Busbar ke Bak Kontrol (Kabelindo; Kabel Metal; Supreme; Tranka m' 83,00 0
18 Penarikan kabel AAAC 70 mm2 Dari ACPDB ke IGB (Kabelindo; Kabel Metal; Supreme; Tranka kabel) Dibungkus cabble flexible conduit Black m' 10,00 0
19 Penarikan kabel Bcc 50 mm2 Dari Bak Kontrol ke copper rod, kemudian dihubungkan ke perimeter dengan cadweld (Kabelindo; Kabel Metal; m' 7,50 0
20 Penarikan kabel AAAC 70 mm2 dari Bak Kontrol ke Connector Bimetallic (Kabelindo; Kabel Metal; Supreme; Tranka kabel) Dibungkus cabble m' 0
21 Cable clam isolator bh 0
22 Penarikan kabel Bc 50 mm2 Dari kaki tower ke ring perimeter (Kabelindo; Kabel Metal; Supreme; Tranka kabel) di Cadweld m' 43,20 0
23 Penarikan kabel Bc 50 mm2 untuk ring parameter sekitar pagar (Kabelindo; Kabel Metal; Supreme; Tranka kabel) di cadweld m' 60,00 0
24 Penarikan kabel Bc 50 mm2 dari perimeter ke pagar (Kabelindo; Kabel Metal; Supreme; Tranka kabel) di cadwell dengan bungkus cabble m' 10,00 0
25 Penarikan kabel Bc 50 mm2 dari tiang box KWH meter dan panel KWH meter ke perimeter (Kabelindo; Kabel Metal; Supreme; Tranka kabel) di m' 4,00 0
26 Bimetalic (See detail Drawing) bh 1,00 0
27 Lightning Rod bh 1,00 0
28 Pengelasan Exothermic / Caldweld ttk 15,00 0
Sub Total 0
E OBSRTUCTION LIGHT
Panel lampu (fiberglass) lengkap dengan MCB 6A, Indikator lamp, trafo step up/down 100 watt, 0
1 set 1,00
Arrester OBO V20, Fotocell Lumina, terminal blok, kontaktor, wiring internal panel, kabel gland dan mounting
2 Upper OBL material approved; Avialite (Li-1016A, 25cd, 220VAC, 50/60HZ, 4.4W, IP67) & Alpha (LIA 1.220VAC Include bh 2,00 0
Lower OBL material approved; Avialite (Li-1016A, 25cd, 220VAC, 50/60HZ, 4.4W, IP67) & Alpha (LIA 1.220VAC Include bh
3 Kabel NYY 3x2,5 mm (catuan dari COS-ACPDB di shelter) m' 46,00 0
Sub Total 0
F PEKERJAAN MOUNTING ANTENNA
1 Supply dan Instalasi monting antena Microweve ( Uk. 2.5 m dia. 3" ) set 1,00 0
2 Supply dan Instalasi monting antena Sector ( Uk. 2.5 m dia. 3" ) set 3,00 0
Sub Total 0

G PLN POWER
1 13.200 VA PLN Power 3 phasa ls 1,00 -
Sub Total -
TOTAL = Rp569.014.109

catatan : volume akan disesuaikan setelah ada final design


Asumsi Harga MATERIAL sbb : UPAH HARGA UNIT
PASIR PASANG Rp157.500 M3 Adukan Rp420.750 M3
PASIR BETON Rp157.500 M3 Pasang Bata Rp49.750 M2
SPLIT Rp624.000 M3 Pasang Bt.Kali Rp285.000 M3
BATU KALI Rp442.500 M3 Plester +Aci Rp57.000 M2
SEMEN 50KG Rp85.000 SAK Tukang besi Rp8.600 kg
BESI BETON Rp17.200 KG Cor beton Rp229.750 M3
BENDRAT Rp29.500 KG
Batu bata(20x10x5) Rp2.600 UNIT
KASO 5/7 Rp33.000 Batang
TRIPLEKS 9mm Rp181.000 Lembar
KAWAT DURI Rp28.000 KG

ANALISA HARGA SATUAN


MUTU BETON K225/m3 HARGA PASANGAN BATU BATA/m2 (ADUKAN 1:5)
SEMEN 371 KG 7,42 SAK Rp85.000 Rp630.700 Batu BATA 70 Rp2.600 Rp182.000
PASIR 698 KG 0,50 M3 Rp157.500 Rp78.525 adukan 0,04 Rp1.054.250 Rp42.170
SPLIT 1047 KG 0,58 M3 Rp624.000 Rp362.960 upah PASANG 1,0 Rp49.750 Rp49.750
Rp1.072.185 Rp273.920
UPAH Rp420.750 profit 15% Rp41.088
Rp1.492.935 M3 Rp315.008
ADUKAN 1:3 PLESTERAN + ACIAN/m2 (ADUKAN 1:5)
semen 50 kg 9,333 Rp85.000 793.333 SEMEN ( ACI ) 0,125 Rp85.000 Rp10.625
pasir 150 kg 0,107 m3 Rp157.500 adukan 0,03 Rp1.054.250 Rp31.628
UPAH Rp420.750 upah Plester +Aci 1,0 Rp57.000 Rp57.000
1.371.583 M3 Rp99.253
ADUKAN 1:5 profit 15% Rp14.888
semen 50 kg 5,6 476.000 Rp114.140
pasir 250 kg 0,178571429 m3 Rp157.500
UPAH Rp420.750
1.054.250 M3

PASANGAN BATU KALI/m3 (ADUKAN 1:5) Aanstamping


Batu kali 1,3 Rp442.500 575250 Rp575.250
adukan 0,45 Rp1.054.250 Rp474.413 Rp0
upah PASANG 1 Rp285.000 Rp285.000 Rp285.000
Rp1.334.663 Rp860.250
profit 15% Rp200.199 15% Rp129.038
Rp1.534.862 Rp989.288
PONDASI PELAT SST 42M = 25,92 M3 volume unit Harga Satuan jumlah
BESI D16-200 79,00 kg Rp17.200 Rp1.358.800
upah tukang besi per kg 79,00 kg Rp8.600 Rp679.400
Kawat bendrat (3 kg/ 100kg besi) 2 kg Rp29.500 Rp69.915
BETON K225 1,0 m3 Rp1.492.935 Rp1.492.935

UPAH COR 1,0 m3 Rp229.750 Rp229.750


alat bantu 1,0 ls Rp100.000 Rp100.000
BEKISTING (bisa pakai BATA) 0,6 m2 Rp315.008 Rp175.004
Total Rp4.105.804
profit 15% Rp615.871
Rp4.721.675

KOLOM PEDESTAL 4 TITIK = 2 M3 volume unit Harga Satuan jumlah


BESI 20-d16 & d10-150 + upah tukang 219,00 kg Rp25.800 Rp5.650.200
upah tukang besi per kg 219,00 kg Rp8.600 Rp1.883.400
Kawat bendrat (3 kg/ 100kg besi) 7 kg Rp29.500 Rp193.815
BETON K300 1,0 m3 Rp1.582.440 Rp1.582.440

UPAH COR 1,0 m3 Rp229.750 Rp229.750


alat bantu 1,0 ls Rp100.000 Rp100.000
BEKISTING ( 2 KALI PAKAI ) 1,0 LS Rp750.000 Rp750.000
Total Rp10.389.605
profit 15% Rp1.558.441
Rp11.948.046