1 PEKERJAAN PERSIAPAN
1.1 Pembersihan lokasi m2 153.00
1.2 Pasang bouwplank m1 60.00
3 PEKERJAAN BETON
3.1 PONDASI SETEMPAT
3.1.1 PONDASI SETEMPAT PT.1 ( 1000 x 1000 x 300 )
- Bekesting bataco m2 3.60
- Pembesian D. 13 mm - 150 kg 135.00
- Beton Readymix K. 350 m3 0.90
3.4 KOLOM
3.4.1 BETON KOLOM K.1 ( 40 X 40 ) 13
- Bekesting m2 104.00
- Pembesian 6 D 16 mm kg 615.51
- Beugel Ø 10 mm - 150 kg 264.48
- Beton Readymix K. 350 m3 10.40
3.5 BALOK
3.5.1 BALOK INDUK B.1 ( 200 X 450 ) 51
- Bekesting m2 56.10
- Pembesian 6 D 16 mm kg 507.09
- Beugel Ø 10 mm - 150 kg 226.38
- Beton Readymix K. 350 m3 4.59
3.7 LISPLANK
3.7.1 BETON BALOK LISPLANK ( 150 X 200 ) 28
- Bekesting m2 21.00
- Tulangan pokok 4 D 13 mm kg 122.53
- Beugel Ø 8 mm - 150 kg 39.77
- Beton Readymix K. 350 m3 0.84
6 PEKERJAAN ARSITEKTUR
6.1 PEKERJAAN PASANGAN 78
6.1.1 - Pasang dinding bata ringan tebal 10 cm m2 312.00
6.1.2 - Plesteran dinding m2 624.00
6.1.3 - Acian dinding m2 624.00
6.1.4 - Kolom praktis 15 x 15 cm m1 40.00
6.1.5 - Balok praktis 15 x 20 cm m1 52.00
6.1.6 - Pasang Pipa air hujan PVC Ø 4" Klas AW m1 24.00
6.1.7 - Pasang Roof drain Ø 4" PVC bh 4.00