PERIHAL : PERMOHONAN PEKERJAAN TAMBAH KURANG (CCO)

SEHUBUNGAN DENGAN PELAKSANAAN PEKERJAAN ;

SKPD / UKPD : SUKU DINAS PENDIDIKAN WILAYAH II KOTA ADMISTRASI JAKARTA PUSAT
PAKET PEKERJAAN : REHAB BERAT GEDUNG SEKOLAH UNTUK ALIH FUNGSI TK NEGERI
KECAMATAN JOHAR BARU WILAYAH II JAKARTA PUSAT
WAKTU PELAKSANAAN : 83 (DELAPAN PULUH TIGA) HARI KALENDER)
KONTRAKTOR : PT. BANGUN TRUBUS KARYA
NO. SPK / KONTRAK : 3542 / - 076.74
Tanggal : 22 SEPTEMBER 2022

KAMI SEBAGAI KONTRAKTOR PELAKSANA MENGAJUKAN PERMOHONAN TAMBAH - KURANG (CCO)


ATAS PELAKSANAAN PEKERJAAN TERSEBUT DIATAS.

DEMIKIAN PERMOHONAN KAMI UNTUK DITINDAK LANJUTI, ATAS PERHATIANNYA KAMI UCAPKAN
TERIMA KASIH

Jakarta, 14 NOPEMBER 2022


PT BANGUN TRUBUS KARYA

CHARLES HUTADJULU
Direktur

TEMBUSAN DISAMPAIKAN :
1. KONSULTAN PENGAWAS
PT. Pande Tututuri Selaras Konsultan
2, KONSULTAN PERENCANA
PT. MITRA BINA WAHANA
3. PERTINGGAL
REKAPITULASI HARGA TAMBAH - KURANG (BALANCE BUGJED)
SKPD / UKPD : SUKU DINAS PENDIDIKAN WILAYAH II KOTA ADMISTRASI JAKARTA PUSAT
PAKET PEKERJAAN : REHAB BERAT GEDUNG SEKOLAH UNTUK ALIH FUNGSI TK NEGERI
KECAMATAN JOHAR BARU WILAYAH II JAKARTA PUSAT
KODE REKENING : 5,2,03,01,01,0010
TAHUN ANGGARAN : 2022

KEMAJUAN PEKERJAAN

S/D MINGGU MINGGU INI S/D DENGAN


No. JENIS PEKERJAAN
YANG LALU MINGGU INI
BOBOT BOBOT BOBOT
% % %

I. PEKERJAAN PERSIAPAN
II. PEKERJAAN GEDUNG UTAMA
A. PEKERJAAN BONGKARAN
B. PEKERJAAN DI BAWAH NOL (0) LANTAI
C. PEKERJAAN STRUKTUR
D. PEKERJAAN PASANGAN
E. PEKERJAAN PINTU / JENDELA
F. PEKERJAAN PENGECATAN
G. PEKERJAAN PLAFOND
H. PEKERJAAN ATAP
I. PEKERJAAN SANITAIR / PLUMBING
J. PEKERJAAN MEKANIKAL ELEKTRIKAL / LISTRIK
III. PEKERJAAN RUANG BERMAIN
A. PEKERJAAN DI BAWAH NOL (0) LANTAI
B. PEKERJAAN STRUKTUR
C. PEKERJAAN PASANGAN
D. PEKERJAAN PINTU / JENDELA
E. PEKERJAAN PENGECATAN
F. PEKERJAAN PLAFOND
G. PEKERJAAN ATAP
H. PEKERJAAN MEKANIKAL ELEKTRIKAL / LISTRIK
IV. PEKERJAAN TOILET / KM
A. PEKERJAAN DI BAWAH NOL (0) LANTAI
B. PEKERJAAN STRUKTUR
C. PEKERJAAN PASANGAN
D. PEKERJAAN PINTU / JENDELA
E. PEKERJAAN PENGECATAN
F. PEKERJAAN SANITAIR / PLUMBING
G. PEKERJAAN MEKANIKAL ELEKTRIKAL / LISTRIK
V. PEKERJAAN PAGAR DAN HALAMAN
A. PEKERJAAN PAGAR
B. PEKERJAAN HALAMAN
C. PEKERJAAN SUMUR DAN POMPA
D. PEKERJAAN TIANG BENDERA
E. PEKERJAAN PAPAN NAMA
F. PEKERJAAN SEPTICTANK
G. PEKERJAAN AKHIR

TOTAL KESELURUHAN

RENCANA PROGRESS S/D MINGGU INI


REALISASI PROGRESS S/D MINGGU INI
DEVIASI
JUMLAH HARGA DASAR
PPN 11 %
BIAYA PENYAMBUNGAN DAYA
JUMLAH

Mengetahui
SUKU DINAS / Disetujui:
PENDIDIKAN WILAYAH II KOTA
ADMISTRASI JAKARTA PUSAT
ADMISTRASI JAKARTA PUSAT
PEJABAT PENANDATANGANAN KONTRAK (PPK)

HERMAN HERBANDI
NIP. 196711071998021003
CHEK LIST
REALISASI PELAKSANAAN PEKERJAAN
SKPD / UKPD : SUKU DINAS PENDIDIKAN WILAYAH II
KOTA ADMISTRASI JAKARTA PUSAT
PAKET PEKERJAAN : REHAB BERAT GEDUNG SEKOLAH UNTUK ALIH FUNGSI TK NEGERI
LOKASI : KECAMATAN JOHAR BARU WILAYAH II JAKARTA PUSAT
TAHUN ANGGARAN : 2022

SESUAI KONTRAK REALISASI PELAKSANAAN


NO NAMA PEKERJAAN
VOLUME SAT YA TIDAK KETERANGAN
VOLUME
I PEKERJAAN PERSIAPAN

1 Pekerjaan Pasang Papan Nama Proyek Multiplek 9 mm di ### 1.00 Buah


lapis Printing Baner Plastik Konstruksi Kayu 5/7

Pekerjaan Foto Dokumentasi Dengan Camera Digital


2 Tanpa Film ### 4.00 Set

3 Pekerjaan Pekerjaan Pembuatan Gudang Semen Dan ### 9.00 M2


Peralatan
4 Pekerjaan Pembuatan Steger Perancah Dari Bambu ### 38.00 M2
5 Pekerjaan Listrik dan Air Kerja ### 1.00 Ls
6 Pekerjaan K3
6,1 Jaring Pengaman(Plastik) ### 57.00 M2
6,2 Helm Kerja ### 12.00 Unit
6,3 Sabuk Pengaman ### 12.00 Unit
6,4 Sepatu Boots ### 12.00 Psg
6,5 Jaket Rompi ### 12.00 Unit
6,6 Sarung Tangan ### 36.00 Psg
6,7 Masker ### 48.00 Unit
7 Pekerjaan SOP Protokol Kesehatan/Perlindungan Covid
7,1 Pengukur Suhu Badan/Thermoscan ### 2.00 Buah
Wastafel Pencuci Tangan Lengkap dengan
7,2 Sabun,Kran,Tangka Air dan Pipa Pembuangan ### 1.00 Set

7,3 Tes Swab Antigen ### 16.00 Test

II PEKERJAAN GEDUNG UTAMA


A PEKERJAAN BONGKARAN
1 Pekerjaan Pembongkaran Keramik/Termasuk ### 139.50 M2
Adukan/Gedung Utama
Pekerjaan Pembongkaran Beton Bertulang/Gedung
2 Utama & Pagar Existing ### 1.16 M3

3 Pekerjaan Pembongkaran Tembok Batu Bata/Gedung ### 7.01 M3


Utama,Bak Sampah & Pagar Existing

4 Pekerjaan Pembongkaran Plafond & Rangka( Bongkaran ### 139.50 M2


Tidak Dipasang Kembali)/Gedung Utama

5 Pekerjaan Pembongkaran Rangka Atap/Gedung Utama ### 155.00 M2


6 Pekerjaan Pembongkaran Kusen/Gedung Utama ### 1.05 M3
7 Pekerjaan Pembongkaran Paving/Halaman ### 168.31 M2
8 Pekerjaan Pemotongan Pohon Pilihan Diameter 30 - 50 ### 1.00 Buah
Cm/Area Depan
9 Pekerjaan Pemotongan Pohon Pilihan Diameter 50 - 75 ### 1.00 Buah
Cm/Area Belakang
10 Pekerjaan Pembersihan Lapangan Dan Perataan/Area ### 110.98 M2
Belakang

B PEKERJAAN DIBAWAH NOL(0) LANTAI


1 Pekerjaan Galian Tanah Biasa( Level 0 s/d ### 15.69 M3
1m)/Pondasi,Sloof dan Saluran Air
2 Pekerjaan Pengurugan Pasir Urug/Bawah Pondasi,Sloof ### 1.54 M3
dan Saluran Air/t: 5 cm
3 Pekerjaan Lantai Kerja B0-K 60/Bawah Pondasi,Sloof dan ### 1.54 M3
Saluran Air/t: 5 cm

C PEKERJAAN STRUKTUR
1 Pekerjaan Beton Sloof(S1)===>20x25 cm
1,1 Pekerjaan Pembuatan Beton Mutu F'C = 21,7 Mpa (K 250) ### 2.04 M3

1,2 Pekerjaan Pembesian ### 248.88 Kg

1,3 Pekerjaan Pemasangan Bekisting Untuk Sloof 3x Pakai ### 20.40 M2

2 Pekerjaan Beton Pondasi(PT2)===>60x60x20cm

2,1 Pekerjaan Pembuatan Beton Mutu F'C = 21,7 Mpa (K 250) ### 0.58 M3
2,2 Pekerjaan Pembesian ### 81.20 Kg
2,3 Pekerjaan Pemasangan Bekisting Untuk Pondasi ### 3.84 M2
3 Pekerjaan Beton Pondasi(PT3)===>112x60x20cm

3,1 Pekerjaan Pembuatan Beton Mutu F'C = 21,7 Mpa (K 250) ### 0.27 M3
3 Pekerjaan Pembesian ### 38.61 Kg
3,3 Pekerjaan Pemasangan Bekisting Untuk Pondasi ### 1.38 M2
4 Pekerjaan Beton Pondasi(PTS)===>80x80x20cm (Pondasi Sketsel)

4,1 Pekerjaan Pembuatan Beton Mutu F'C = 21,7 Mpa (K 250) ### 0.26 M3

4,2 Pekerjaan Pembesian ### 35.88 Kg


4,3 Pekerjaan Pemasangan Bekisting Untuk Pondasi ### 1.28 M2

5 Pekerjaan Beton Kolom(K1)===> 20x20 cm

5,1 Pekerjaan Pembuatan Beton Mutu F'C = 21,7 Mpa (K 250) ### 1.23 M3
5,2 Pekerjaan Pembesian ### 178.35 Kg
5,3 Pekerjaan Pemasangan Bekisting Untuk Kolom 3x Pakai ### 24.64 M2

6 Pekerjaan Beton Kolom(K2)===> 14x20 cm/Kolom Var


6,1 Pekerjaan Pembuatan Beton Mutu F'C = 21,7 Mpa (K 250) ### 0.97 M3
6,2 Pekerjaan Pembesian ### 149.38 Kg
6,3 Pekerjaan Pemasangan Bekisting Untuk Kolom 3x Pakai ### 23.56 M2

7 Pekerjaan Beton Kolom(KS)===> 20x400 cm/Kolom Sketsel

7,1 Pekerjaan Pembuatan Beton Mutu F'C = 21,7 Mpa (K 250) ### 0.38 M3
7,2 Pekerjaan Pembesian ### 64.98 Kg
7,3 Pekerjaan Pemasangan Bekisting Untuk Kolom 3x Pakai ### 5.76 M2

8 Pekerjaan Beton Balok(RB1)===> 20x25 cm

8,1 Pekerjaan Pembuatan Beton Mutu F'C = 21,7 Mpa (K 250) ### 5.61 M3
8,2 Pekerjaan Pembesian ### 880.77 Kg
8,3 Pekerjaan Pemasangan Bekisting Untuk Balok 3x Pakai ### 50.47 M2
9 Pekerjaan Beton Balok(BS)===> 20x40 cm

9,1 Pekerjaan Pembuatan Beton Mutu F'C = 21,7 Mpa (K 250) ### 0.56 M3

9,2 Pekerjaan Pembesian ### 94.08 Kg


9,3 Pekerjaan Pemasangan Bekisting Untuk Balok 3x Pakai ### 4.20 M2

10 Pekerjaan Beton Plat Kanopi t: 12 cm

10,1 Pekerjaan Pembuatan Beton Mutu F'C = 21,7 Mpa (K 250) ### 2.92 M3
10,2 Pekerjaan Pembesian ### 405.88 Kg
10,3 Pekerjaan Pemasangan Bekisting Untuk Lantai 3x Pakai ### 28.82 M2

11 Pekerjaan Beton Plat Bak Cuci /Pantry : 12 cm

11,1 Pekerjaan Pembuatan Beton Mutu F'C = 21,7 Mpa (K 250) ### 0.18 M3
11,2 Pekerjaan Pembesian ### 25.02 Kg
11,3 Pekerjaan Pemasangan Bekisting Untuk Lantai 3x Pakai ### 2.23 M2

Pekerjaan Membuat Kolom Praktis Beton Bertulang (11 X


12 11) Cm/Kp ### 38.40 M1

D PEKERJAAN PASANGAN
D.1 PEKERJAAN PASANGAN KERAMIK

1 Pekerjaan Pemasangan Lantai Homogeneus Ukuran ### 119.35 M2


60x60 cm/ Polised/Roman/Ruangan
Pekerjaan Pemasangan Lantai Homogeneus Ukuran
2 60x60 cm/ Unpolised/Roman/Selasar ### 35.00 M2

3 Pekerjaan Pemasangan Lantai Keramik Ukuran. 40X40 ### 34.39 M2


Cm / Unpolised /Roman/Motif Batu Alam/Teras

4 Pekerjaan Pemasangan Dinding Batu Andesit/Finis ### 29.95 M2


Coating

5 Pekerjaan Pemasangan Ornamen GRC Simbul T: 2 ###


Cm/Finis Coating
Pekerjaan Pemasangan Logo/Huruf Steinless Steel Tebal
6 4 Cm/Tinggi 20 Cm/TAMAN KANAK KANAK NEGERI ### 66.00 Pcs
JOHAR BARU 01

D.2 PEKERJAAN PASANGAN DINDING BATA & PLESTERAN

1 Pekerjaan Pemasangan Batu Merah Tebal 1/2 Bata (1 Pc : ### 79.29 M2


4 Ps)/Dinding/Termasuk Peninggian Elevasi Atap

2 Pekerjaan Plesteran 1 Pc : 4 Ps Tebal 15 ### 183.22 M2


Mm/Dinding/Termasuk Finishing Kolom

3 Pekerjaan Acian/Dinding/Termasuk Finishing Kolom ### 183.22 M2

4 Pekerjaan Pemasangan Saluran Air Terbuka 1/2 Ø 30 ### 38.00 M1


Cm(Termasuk Pemasangan Bata dan Plester Acian)

5 Pekerjaan Pemasangan Saluran Air Tertutup Ø 30 ### 9.70 M1


Cm(Termasuk Pemasangan Bata dan Plester Acian)

Pekerjaan Pemasangan Biopori Pipa PVC Type AW Dia. 4"


6 /Termasuk Pelubangan/Rucika/Jarak 1 m/Kedalaman 2 ###
m

7 Pekerjaan Pemasangan Grill/Penutup Saluran Air L 30 ### 38.00 M1


Cm+Cat

E PEKERJAAN PINTU/JENDELA
1 Pekerjaan Pintu (P1)---->5 Unit

1,1 Pekerjaan Pemasangan Besi Profil/Termasuk Pengelasan ###


& Alat Bantu/Cat/Kusen Besi Hollow 50x100x2,3 344.54 Kg

1,2 Pekerjaan Pemasangan Besi Profil/Termasuk Pengelasan ###


& Alat Bantu/Cat/Jalusi Besi Hollow 30x60x2,3 114.89 Kg

1,3 Pekerjaan Pemasangan Pintu Panil Kayu Kelas I Oven ###


Samarinda 15.00 M2

1,4 Pekerjaan Pemasangan Kaca Mati Tebal 5 mm/Assahi ### 0.60 M2

1,5 Pekerjaan Pemasangan Kunci Tanam Biasa /Deckson ### 5.00 Buah
1,6 Pekerjaan Pemasangan Engsel Pintu Kuningan 3 " ###
/Deckson 30.00 Buah
1,7 Pekerjaan Pemasangan Kunci Slot /Deckson ### 10.00 Buah
1,8 Pekerjaan Pemasangan Hendle Grid Stainless Steel 30 Cm ### 5.00 Set
1,9 Pekerjaan Mendempul Dan Menggosok Kayu ### 30.00 M2

Pekerjaan Pengecatan Cat Minyak Bidang Baru (1 Lapis


1,10 Plamir, 1 Lapis Cat Dasar, Dan 2 Lapis Cat Penutup) ### 30.00 M2

2 Pekerjaan Pintu (P1')----> 1 Unit

2,1 Pekerjaan Pemasangan Besi Profil/Termasuk Pengelasan ###


& Alat Bantu/Cat/Kusen Besi Hollow 50x100x2,3 66.07 Kg

2,2 Pekerjaan Pemasangan Besi Profil/Termasuk Pengelasan ###


& Alat Bantu/Cat/Jalusi Besi Hollow 30x60x2,3 19.91 Kg

2,3 Pekerjaan Pemasangan Pintu Panil Kayu Kelas I Oven ###


Samarinda 2.60 M2

2,4 Pekerjaan Pemasangan Kaca Mati Tebal 5 mm/Assahi ### 0.12 M2

2,5 Pekerjaan Pemasangan Kunci Tanam Biasa /Deckson ### 1.00 Buah
Pekerjaan Pemasangan Engsel Pintu Kuningan 3 "
2,6 ### 6.00 Buah
/Deckson
2,7 Pekerjaan Pemasangan Kunci Slot /Deckson ### 2.00 Buah
2,8 Pekerjaan Pemasangan Hendle Grid Stainless Steel 30 Cm ### 1.00 Set
2,9 Pekerjaan Mendempul Dan Menggosok Kayu ### 5.20 M2

2,10 Pekerjaan Pengecatan Cat Minyak Bidang Baru (1 Lapis ###


Plamir, 1 Lapis Cat Dasar, Dan 2 Lapis Cat Penutup) 5.20 M2

3 Pekerjaan Jendela (J1)----> 4 Unit


3,1 Pekerjaan Pemasangan Kusen Alluminium Warna 4" ###
(Termasuk Paku Sekrup + Sealant) /Alexindo 55.00 M1

3,2 Pekerjaan Pemasangan Jalusi Holo Alumunium 4 x 3/ 4 ###


"/Alexindo 49.00 M1
3,3 Pekerjaan Pemasangan Kaca Mati Tebal 5 mm/Assahi ### 2.64 M2
3,4 Pekerjaan Pemasangan Daun Kaca Polos + Frame/Rangka ###
Alluminium /Lengkap Karet 5.28 M2
3,5 Pekerjaan Pemasangan Engsel Casmen/Deckson ### 16.00 Buah
3,6 Pekerjaan Pemasangan Hendel Casmen/Deckson ### 8.00 Buah

4 Pekerjaan Jendela (J2)----> 3 Unit


4,1 Pekerjaan Pemasangan Kusen Alluminium Warna 4" ###
(Termasuk Paku Sekrup + Sealant) /Alexindo 27.00 M1

4,2 Pekerjaan Pemasangan Jalusi Holo Alumunium 4 x 3/ 4 ###


"/Alexindo 21.00 M1

4,3 Pekerjaan Pemasangan Kaca Mati Tebal 5 mm/Assahi ### 1.98 M2

Pekerjaan Pemasangan Daun Kaca Polos + Frame/Rangka


4,4 Alluminium /Lengkap Karet ### 1.98 M2
4,5 Pekerjaan Pemasangan Engsel Casmen/Deckson ### 6.00 Buah
4,6 Pekerjaan Pemasangan Hendel Casmen/Deckson ### 3.00 Buah
5 Pekerjaan Jendela (J3)----> 1 Unit
5,1 Pekerjaan Pemasangan Kusen Alluminium Warna 4" ###
(Termasuk Paku Sekrup + Sealant) /Alexindo 9.45 M1

5,2 Pekerjaan Pemasangan Jalusi Holo Alumunium 4 x 3/ 4 ###


"/Alexindo 7.75 M1

5,3 Pekerjaan Pemasangan Kaca Mati Tebal 5 mm/Assahi ### 0.66 M2

5,4 Pekerjaan Pemasangan Daun Kaca Polos + Frame/Rangka ###


Alluminium /Lengkap Karet 0.66 M2
5,5 Pekerjaan Pemasangan Engsel Casmen/Deckson ### 2.00 Buah
5,6 Pekerjaan Pemasangan Hendel Casmen/Deckson ### 1.00 Buah
6 Pekerjaan Jendela (J4)----> 4 Unit
6,1 Pekerjaan Pemasangan Kusen Alluminium Warna 4" ###
(Termasuk Paku Sekrup + Sealant) /Alexindo 5.30 M1

6,2 Pekerjaan Pemasangan Jalusi Holo Alumunium 4 x 3/ 4 ###


"/Alexindo 3.50 M1

6,3 Pekerjaan Pemasangan Daun Kaca Polos + Frame/Rangka ###


Alluminium /Lengkap Karet 0.66 M2

6,4 Pekerjaan Pemasangan Engsel Casmen/Deckson ### 2.00 Buah


6,5 Pekerjaan Pemasangan Hendel Casmen/Deckson ### 1.00 Buah
7 Pekerjaan Pemasangan Pintu Teakwood Rangkap ### 15.00 M2
+Rangka Lapis HPL/Sketsel/Borneo

8 Pekerjaan kolom praktis dan balok luifel kusen pintu, - 153.45 M1


jendela dan oveningan penghubung ruangan

9 Finishing oveningan (plesteran dan acian) - 153.45 M1

10 Pasang dinding diatas sketsel double rangka hollow dan - 6.60 M2


double gypsum uk. 6,5x0,90 m

F PEKERJAAN PENGECATAN
Pekerjaan Pengecatan Cat Tembok Bidang Baru( 1 Lapis
1 Plamur, 1 Lapis Cat Dasar, 2 Lapis )Cat ### 248.27 M2
Penutup/Jotun/Dinding/Kolom

Pekerjaan Pengecatan Cat Tembok Bidang Baru Weather


2 Sheid (1 Lapis Plamur, 1 Lapis Cat Dasar, 2 Lapis) Cat ### 173.65 M2
Penutup/Jotun/Dinding/KolomLisplank Motif Betawi

Pekerjaan Pengecatan Cat Tembok Bidang Baru Weather


3 Sheid (1 Lapis Plamur, 1 Lapis Cat Dasar, 2 Lapis) Cat ### 78.00 M2
Penutup/Cat Exterior/Cat Lukis Mural 3D/Mowilex

4 Pengerokan cat dinding lama 248.27 M2

G PEKERJAAN PLAFON

Pekerjaan Pemasangan Plafon PVC t: 9 mm,l 16 cm +


1 Rangka & Penggantung Hollo 40/40/0.35/Lengkap Lis ### 190.00 M2
Sudut/Sunda Plafon/Dinding/Kolom

H PEKERJAAN ATAP
Pekerjaan Pemasangan Rangka Atap Kuda Kuda Baja
1 Ringan Galvalume /Termasuk Talang Jurai,Kaso & ### 224.20 M2
Reng/Steel Truss

2 Pekerjaan Pemasangan Aluminium Foil Untuk ### 224.20 M2


Atap(Single Side 1,2 m x 50 m)
3 Pekerjaan Pemasangan Atap Genteng Bitumen Ukuran
400x1060 mm /Onduvila ### 224.20 M2
Pekerjaan Pemasangan Wuwung Nok Bitumen Ukuran l:
4 800 mm /Onduvila ### 19.00 M1

5 Pekerjaan Pemasangan Genteng Tepi/Penutup ### 23.60 M1


Lisplank/Onduvila
6 Pekerjaan Pemasangan Listplank Panel GRC Motif Betawi, ###
T: 2 Cm,Lebar 30 cm 61.60 M1

I PEKERJAAN SANITAIR/PLUMBING
1 Pekerjaan Pemasangan Pipa PVC Type AW Dia. 1/2" ### 26.00 M1
/Rucika/Air Bersih
2 Pekerjaan Pemasangan Pipa PVC Type AW Dia. 2"
/Rucika/Air Bekas ### 2.50 M1

3 Pekerjaan Pemasangan Wastafel/Lengkap Asesoris/L ### 3.00 Unit


529 V1/Toto

4 Pekerjaan Pemasangan Floor Drain 4"/TX 1 BN/Toto ### 1.00 Unit


5 Pekerjaan Pemasangan Kran Air 1/2"/T23B13VNb/Toto ### 2.00 Buah
6 Pekerjaan Pemasangan Kran Leher Angsa ### 1.00 Buah
7 Pekerjaan Pemasangan Bak Cuci Piring Stainless Steel ### 1.00 Unit

J PEKERJAAN ME/LISTRIK
J.1 Pekerjaan Instalasi Kabel

1 Pekerjaan Pemasangan Instalasi Titik Lampu Penerangan ### 41.00 Titik


Kabel Ukuran 2x2,5(Lengkap Pipa Conduit) /Eterna

Pekerjaan Pemasangan Instalasi Stop Kontak Biasa Kabel


2 Ukuran 3x2,5(Lengkap Pipa Conduit) /Eterna ### 9.00 Titik

3 Pekerjaan Pemasangan Instalasi Power AC Kabel NYM 3 x ### 2.00 Titik


4 (Lengkap Pipa Conduit) /Eterna
J.2 Pekerjaan Armarture
1 Pekerjaan Pemasangan Stop Kontak Biasa/Broco ### 9.00 Buah
2 Pekerjaan Pemasangan Stop Kontak Power(AC)/Broco ### 2.00 Buah

3 Pekerjaan Pemasangan AC Split 3/4 PK Low ###


Watt/Lengkap Asesoris/AH-AP7UHL/Sharp 2.00 Unit

4 Pekerjaan Pemasangan Lampu LED 18 Watt(Lengkap ###


Fitting)/Philips 7.00 Titik
Pekerjaan Pemasangan Lampu Down Light (Lengkap
5 Fitting)/Philips ### 34.00 Titik
6 Pekerjaan Pemasangan Saklar Ganda /Broco ### 9.00 Buah
J.3 Pekerjaan Panel+Mcb
1 Pekerjaan Pemasangan Panel Pembagi 40x60x20 cm ### 1.00 Unit
2 Pekerjaan Pasang MCB 6 A ### 3.00 Buah
3 Pekerjaan Pasang MCB 10 A ### 5.00 Buah
4 Pekerjaan Pasang MCB 25 A ### 1.00 Buah

III PEKERJAAN RUANG BERMAIN


A PEKERJAAN DIBAWAH NOL(0) LANTAI
Pekerjaan Galian Tanah Biasa( Level 0 s/d 1m)/Pondasi
1 & Sloof ### 5.03 M3

2 Pekerjaan Pengurugan Pasir Urug/Bawah Pondasi,Sloof ### 0.57 M3


dan Saluran Air/t: 5 cm
3 Pekerjaan Lantai Kerja B0-K 60/Bawah Pondasi,Sloof dan ###
Saluran Air/t: 5 cm 0.57 M3

B PEKERJAAN STRUKTUR
1 Pekerjaan Beton Sloof(S1)===>20x25 cm

1,1 Pekerjaan Pembuatan Beton Mutu F'C = 21,7 Mpa (K 250) ### 1.60 M3
1,2 Pekerjaan Pembesian ### 195.20 Kg
1,3 Pekerjaan Pemasangan Bekisting Untuk Sloof 3x Pakai ### 16.00 M2

2 Pekerjaan Beton Pondasi(PT1)===>70x70x20cm

2,1 Pekerjaan Pembuatan Beton Mutu F'C = 21,7 Mpa (K 250) ### 0.98 M3
2,2 Pekerjaan Pembesian ### 136.22 Kg
2,3 Pekerjaan Pemasangan Bekisting Untuk Pondasi ### 5.60 M2
3 Pekerjaan Beton Kolom(K1)===> 20x20 cm

3,1 Pekerjaan Pembuatan Beton Mutu F'C = 21,7 Mpa (K 250) ### 1.10 M3
3,2 Pekerjaan Pembesian ### 159.50 Kg
3,3 Pekerjaan Pemasangan Bekisting Untuk Kolom 3x Pakai ### 22.08 M2
4 Pekerjaan Beton Kolom(K2)===> 14x20 cm
4,1 Pekerjaan Pembuatan Beton Mutu F'C = 21,7 Mpa (K 250) ### 0.21 M3
4,2 Pekerjaan Pembesian ### 41.37 Kg
4,3 Pekerjaan Pemasangan Bekisting Untuk Kolom 3x Pakai ### 5.03 M2
5 Pekerjaan Beton Kolom(Kp)===> 11x11 cm
5,1 Pekerjaan Pembuatan Beton Mutu F'C = 21,7 Mpa (K 250) ### 0.09 M3
5,2 Pekerjaan Pembesian ### 26.73 Kg
5,3 Pekerjaan Pemasangan Bekisting Untuk Kolom 3x Pakai ### 3.30 M2

6 Pekerjaan Beton Balok(RB1)===> 20x25 cm

6,1 Pekerjaan Pembuatan Beton Mutu F'C = 21,7 Mpa (K 250) ### 1.20 M3
6,2 Pekerjaan Pembesian ### 146.40 Kg
6,3 Pekerjaan Pemasangan Bekisting Untuk Balok 3x Pakai ### 12.00 M2
7 Pekerjaan Beton Balok(RB)===> 11x15 cm
7,1 Pekerjaan Pembuatan Beton Mutu F'C = 21,7 Mpa (K 250) ### 0.18 M3
7,2 Pekerjaan Pembesian ### 41.76 Kg
7,3 Pekerjaan Pemasangan Bekisting Untuk Balok 3x Pakai ### 3.24 M2
8 Pekerjaan Beton Plat Kanopi t: 12 cm
8,1 Pekerjaan Pembuatan Beton Mutu F'C = 21,7 Mpa (K 250) ### 2.66 M3
8,2 Pekerjaan Pembesian ### 369.74 Kg
8,3 Pekerjaan Pemasangan Bekisting Untuk Lantai 3x Pakai ### 29.01 M2

8,4 Pekerjaan Pemasangan Water Proofing Coating 3x/Sika ### 27.71 M2


8,5 Pekerjaan Screeding Tebal 3 cm ### 27.71 M2

C PEKERJAAN PASANGAN
C.1 PEKERJAAN PASANGAN KERAMIK

1 Pekerjaan Pemasangan Lantai Homogeneus Ukuran ### 32.00 M2


60x60 cm/ Polised/Roman/Ruangan

2 Pekerjaan Pemasangan Lantai Keramik Ukuran. 40X40 ### 19.68 M2


Cm / Unpolised /Roman/Motif Batu Alam/Teras

3 Pekerjaan Urugan pasir tebal 5 cm 12.73 m3


C.2 PEKERJAAN PASANGAN DINDING BATA & PLESTERAN
1 Pekerjaan Pemasangan Batu Merah Tebal 1/2 Bata (1 Pc : ### 47.90 M2
4 Ps)
2 Pekerjaan Plesteran 1 Pc : 4 Ps Tebal 15 Mm ### 95.80 M2
3 Pekerjaan Acian ### 95.80 M2
Pekerjaan Pemasangan Saluran Air Terbuka 1/2 Ø 30
4 Cm(Termasuk Pemasangan Bata dan Plester Acian) ### 39.66 M1

D PEKERJAAN PINTU/JENDELA
1 Pekerjaan Pintu (P1)===> 1 Unit

1,1 Pekerjaan Pemasangan Besi Profil/Termasuk Pengelasan ###


& Alat Bantu/Cat/Kusen Besi Hollow 50x100x2,3 68.91 Kg

Pekerjaan Pemasangan Besi Profil/Termasuk Pengelasan


1,2 & Alat Bantu/Cat/Jalusi Besi Hollow 30x60x2,3 ### 22.98 Kg

1,3 Pekerjaan Pemasangan Pintu Panil Kayu Kelas I Oven ###


Samarinda 3.00 M2

1,4 Pekerjaan Pemasangan Kaca Mati Tebal 5 mm/Assahi ### 0.12 M2

1,5 Pekerjaan Pemasangan Kunci Tanam Biasa /Deckson ### 1.00 Buah

1,6 Pekerjaan Pemasangan Engsel Pintu Kuningan 3 " ###


/Deckson 6.00 Buah
1,7 Pekerjaan Pemasangan Kunci Slot /Deckson ### 2.00 Buah
1,8 Pekerjaan Pemasangan Hendle Grid Stainless Steel 30 Cm ### 1.00 Set
1,9 Pekerjaan Mendempul Dan Menggosok Kayu ### 6.00 M2

1,10 Pekerjaan Pengecatan Cat Minyak Bidang Baru (1 Lapis ###


Plamir, 1 Lapis Cat Dasar, Dan 2 Lapis Cat Penutup) 6.00 M2

2 Pekerjaan Jendela (J1)===> 3 Unit


2,1 Pekerjaan Pemasangan Kusen Alluminium Warna 4" ###
(Termasuk Paku Sekrup + Sealant) /Alexindo 41.25 M1

2,2 Pekerjaan Pemasangan Jalusi Holo Alumunium 4 x 3/ 4 ###


"/Alexindo 36.75 M1

2,3 Pekerjaan Pemasangan Kaca Mati Tebal 5 mm/Assahi ### 1.98 M2

2,4 Pekerjaan Pemasangan Daun Kaca Polos + Frame/Rangka ###


Alluminium /Lengkap Karet 3.96 M2
2,5 Pekerjaan Pemasangan Engsel Casmen/Deckson ### 12.00 Buah
2,6 Pekerjaan Pemasangan Hendel Casmen/Deckson ### 6.00 Buah
3 Pekerjaan Jendela (J1')===> 2 Unit

3,1 Pekerjaan Pemasangan Kusen Alluminium Warna 4" ###


(Termasuk Paku Sekrup + Sealant) /Alexindo 40.80 M1

Pekerjaan Pemasangan Jalusi Holo Alumunium 4 x 3/ 4


3,2 "/Alexindo ### 36.00 M1

3,3 Pekerjaan Pemasangan Kaca Mati Tebal 5 mm/Assahi ### 1.98 M2

3,4 Pekerjaan Pemasangan Daun Kaca Polos + Frame/Rangka ###


Alluminium /Lengkap Karet 3.96 M2
3,5 Pekerjaan Pemasangan Engsel Casmen/Deckson ### 12.00 Buah
3,6 Pekerjaan Pemasangan Hendel Casmen/Deckson ### 6.00 Buah

E PEKERJAAN PENGECATAN
Pekerjaan Pengecatan Cat Tembok Bidang Baru( 1 Lapis
1 Plamur, 1 Lapis Cat Dasar, 2 Lapis )Cat ### 75.61 M2
Penutup/Jotun/Teramsuk Plat Dak Beton

Pekerjaan Pengecatan Cat Tembok Bidang Baru Weather


2 Sheid (1 Lapis Plamur, 1 Lapis Cat Dasar, 2 Lapis) Cat ### 41.11 M2
Penutup/Jotun

Pekerjaan Pengecatan Cat Tembok Bidang Baru Weather


3 Sheid (1 Lapis Plamur, 1 Lapis Cat Dasar, 2 Lapis) Cat ### 34.50 M2
Penutup/Cat Exterior/Cat Lukis Mural 3D/Mowilex

F PEKERJAAN PLAFON

Pekerjaan Pemasangan Plafon PVC t: 9 mm,l 16 cm +


1 Rangka & Penggantung Hollo 40/40/0.35/Lengkap Lis ### 32.00 M2
Sudut/Sunda Plafon/Dinding/Kolom

G PEKERJAAN ATAP
Pekerjaan Pemasangan Rangka Atap Kuda Kuda Baja
1 Ringan Galvalume /Termasuk Talang Jurai,Kaso & ### 48.00 M2
Reng/Steel Truss

2 Pekerjaan Pemasangan Atap Genteng Bitumen Ukuran


400x1060 mm /Onduvila ### 48.00 M2

3 Pekerjaan Pemasangan Wuwung Nok Bitumen Ukuran l: ### 8.00 M1


800 mm /Onduvila
4 Pekerjaan Pemasangan Genteng Tepi/Penutup ### 16.00 M1
Lisplank/Onduvila
5 Pekerjaan Pemasangan Listplank Panel GRC Motif Betawi, ### 28.00 M1
T: 2 Cm,Lebar 30 cm

H PEKERJAAN ME/LISTRIK
H.1.1 Pekerjaan Instalasi Kabel

1 Pekerjaan Pemasangan Instalasi Titik Lampu Penerangan ### 8.00 Titik


Kabel Ukuran 2x2,5(Lengkap Pipa Conduit) /Eterna

Pekerjaan Pemasangan Instalasi Stop Kontak Biasa Kabel


2 Ukuran 3x2,5(Lengkap Pipa Conduit) /Eterna ### 2.00 Titik

H.1.2 Pekerjaan Armarture


1 Pekerjaan Pemasangan Stop Kontak Biasa/Broco ### 2.00 Buah
2 Pekerjaan Pemasangan Lampu Down Light (Lengkap ### 8.00 Titik
Fitting)/Philips
3 Pekerjaan Pemasangan Saklar Ganda /Broco ### 1.00 Buah

IV PEKERJAAN TOILET/KM
A PEKERJAAN DIBAWAH NOL(0) LANTAI
1 Pekerjaan Galian Tanah Biasa( Level 0 s/d 1m)/Pondasi ### 3.00 M3
& Sloof
2 Pekerjaan Pengurugan Pasir Urug/Bawah Pondasi,Sloof ### 0.41 M3
dan Saluran Air/t: 5 cm
3 Pekerjaan Lantai Kerja B0-K 60/Bawah Pondasi,Sloof dan ### 0.41 M3
Saluran Air/t: 5 cm

B PEKERJAAN STRUKTUR
1 Pekerjaan Beton Sloof(S1)===>20x25 cm

1,1 Pekerjaan Pembuatan Beton Mutu F'C = 21,7 Mpa (K 250) ### 1.49 M3
1,2 Pekerjaan Pembesian ### 181.78 Kg

1,3 Pekerjaan Pemasangan Bekisting Untuk Sloof 3x Pakai ### 14.85 M2

2 Pekerjaan Beton Pondasi(PT2)===>60x60x20cm

2,1 Pekerjaan Pembuatan Beton Mutu F'C = 21,7 Mpa (K 250) ### 0.43 M3

2,2 Pekerjaan Pembesian ### 60.20 Kg


2,3 Pekerjaan Pemasangan Bekisting Untuk Pondasi ### 2.88 M2
3 Pekerjaan Beton Kolom(K1)===> 20x20 cm

3,1 Pekerjaan Pembuatan Beton Mutu F'C = 21,7 Mpa (K 250) ### 0.83 M3
3,2 Pekerjaan Pembesian ### 120.35 Kg
3,3 Pekerjaan Pemasangan Bekisting Untuk Kolom 3x Pakai ### 16.56 M2
4 Pekerjaan Beton Kolom(Kp)===> 11x11 cm

4,1 Pekerjaan Pembuatan Beton Mutu F'C = 21,7 Mpa (K 250) ### 0.41 M3
4,2 Pekerjaan Pembesian ### 120.13 Kg
4,3 Pekerjaan Pemasangan Bekisting Untuk Kolom 3x Pakai ### 14.85 M2
5 Pekerjaan Beton Balok(RB1)===> 20x25 cm

5,1 Pekerjaan Pembuatan Beton Mutu F'C = 21,7 Mpa (K 250) ### 1.49 M3

5,2 Pekerjaan Pembesian ### 181.78 Kg


5,3 Pekerjaan Pemasangan Bekisting Untuk Balok 3x Pakai ### 14.85 M2
6 Pekerjaan Beton Plat Kanopi t: 12 cm

6,1 Pekerjaan Pembuatan Beton Mutu F'C = 21,7 Mpa (K 250) ### 2.12 M3

6,2 Pekerjaan Pembesian ### 294.68 Kg


6,3 Pekerjaan Pemasangan Bekisting Untuk Lantai 3x Pakai ### 19.88 M2

6,4 Pekerjaan Pemasangan Water Proofing Coating 3x/Sika ### 5.52 M2


6,5 Pekerjaan Screeding Tebal 3 cm ### 5.52 M2

C PEKERJAAN PASANGAN
C.1 PEKERJAAN PASANGAN KERAMIK
1 Pekerjaan Pemasangan Lantai Keramik Ukuran.30X30 Cm ###
/ Unpolised/Roman 14.17 M2
Pekerjaan Pemasangan Keramik Dinding Ukuran.30x60
2 cm//Polised/Roman ### 63.56 M2

3 Pekerjaan Pemasangan Dinding Terawang/Roster ### 0.52 M2

C.2 PEKERJAAN PASANGAN DINDING BATA & PLESTERAN


1 Pekerjaan Pemasangan Batu Merah Tebal 1/2 Bata (1 Pc : ### 70.86 M2
4 Ps)
2 Pekerjaan Plesteran 1 Pc : 4 Ps Tebal 15 Mm ### 141.72 M2
3 Pekerjaan Acian ### 78.16 M2

D PEKERJAAN PINTU/JENDELA
1 Pekerjaan Pintu (P2)----> 1 Unit

1,1 Pekerjaan Pemasangan Besi Profil/Termasuk Pengelasan ###


& Alat Bantu/Cat/Kusen Besi Hollow 50x100x2,3 60.38 Kg

1,2 Pekerjaan Pemasangan Besi Profil/Termasuk Pengelasan ###


& Alat Bantu/Cat/Jalusi Besi Hollow 30x60x2,3 13.79 Kg

1,3 Pekerjaan Pemasangan Daun Pintu Alumunium/Spandrel ### 3.60 M2

1,4 Pekerjaan Pemasangan Kunci Tanam Biasa /Deckson ### 1.00 Buah

1,5 Pekerjaan Pemasangan Engsel Pintu Kuningan 3 " ###


/Deckson 3.00 Buah
1,6 Pekerjaan Pemasangan Kunci Slot /Deckson ### 1.00 Buah
2 Pekerjaan Pintu (P3)----> 2 Unit

2,1 Pekerjaan Pemasangan Besi Profil/Termasuk Pengelasan ###


& Alat Bantu/Cat/Kusen Besi Hollow 50x100x2,3 51.86 Kg

2,2 Pekerjaan Pemasangan Besi Profil/Termasuk Pengelasan ###


& Alat Bantu/Cat/Jalusi Besi Hollow 30x60x2,3 10.72 Kg

2,3 Pekerjaan Pemasangan Daun Pintu Alumunium/Spandrel ### 2.80 M2

2,4 Pekerjaan Pemasangan Kunci Tanam Biasa /Deckson ### 1.00 Buah

2,5 Pekerjaan Pemasangan Engsel Pintu Kuningan 3 " ###


/Deckson 3.00 Buah
2,6 Pekerjaan Pemasangan Kunci Slot /Deckson ### 1.00 Buah

E PEKERJAAN PENGECATAN
Pekerjaan Pengecatan Cat Tembok Bidang Baru( 1 Lapis
1 Plamur, 1 Lapis Cat Dasar, 2 Lapis )Cat ### 16.70 M2
Penutup/Jotun/Dak
Pekerjaan Pengecatan Cat Tembok Bidang Baru Weather
2 Sheid (1 Lapis Plamur, 1 Lapis Cat Dasar, 2 Lapis) Cat ### 22.50 M2
Penutup/Jotun

F PEKERJAAN SANITAIR/PLUMBING
1 Pekerjaan Pemasangan Pipa PVC Type AW Dia. 1/2" ###
/Rucika/Air Bersih 1.20 M1

2 Pekerjaan Pemasangan Pipa PVC Type AW Dia. 3/4" ###


/Rucika/Air Bersih 31.30 M1

3 Pekerjaan Pemasangan Pipa PVC Type AW Dia. 1" ###


/Rucika/Distribusi Air Bersih 21.60 M1

4 Pekerjaan Pemasangan Pipa PVC Type AW Dia. 3" ###


/Rucika/Air Bekas/Talang Tegak 20.60 M1

5 Pekerjaan Pemasangan Pipa PVC Type AW Dia. 4" ###


/Rucika/Air Kotor/Klosed 7.00 M1

6 Pekerjaan Pemasangan Kloset Duduk ### 1.00 Unit


/Disabilitas/Lengkap Asesoris/CW705ELNJ/Toto

7 Pekerjaan Pemasangan Kloset Duduk/Lengkap


Asesoris/CW 420 J/Toto ### 1.00 Buah

8 Pekerjaan Pemasangan Kloset Jongkok Flush/CE 9/Toto ### 1.00 Unit

9 Pekerjaan Pemasangan Urinoir/Lengkap Asesoris/U57M ### 2.00 Unit

10 Pekerjaan Pemasangan Wastafel/Lengkap Asesoris/L ### 4.00 Unit


529 V1/Toto/Out Door/Prokes

11 Pekerjaan Pemasangan Jet Washer/THX20MCRB/Toto ### 2.00 Set


12 Pekerjaan Pemasangan Floor Drain 4"/TX 1 BN/Toto ### 1.00 Unit
13 Pekerjaan Pemasangan Hand ### 1.00 Unit
Drail/Disabilitas/TX3A1/Toto/Disabilitas

14 Pekerjaan Pemasangan Kran Air 1/2"/T23B13VNb/Toto ### 3.00 Buah

G PEKERJAAN ME/LISTRIK
G.1.1 Pekerjaan Instalasi Kabel

1 Pekerjaan Pemasangan Instalasi Titik Lampu Penerangan ### 4.00 Titik


Kabel Ukuran 2x2,5(Lengkap Pipa Conduit) /Eterna

G.1.2 Pekerjaan Armarture

1 Pekerjaan Pemasangan Lampu LED 18 Watt(Lengkap ### 4.00 Titik


Fitting)/Philips
2 Pekerjaan Pemasangan Saklar Tunggal /Broco ### 4.00 Buah

V PEKERJAAN PAGAR & HALAMAN


A PEKERJAAN PAGAR
1 Pekerjaan Galian Tanah Biasa( Level 0 s/d
1m)/Pondasi,Sloof dan Saluran Air ### 7.36 M3

2 Pekerjaan Pengurugan Pasir Urug/Bawah Pondasi,Sloof ### 0.82 M3


dan Saluran Air/t: 5 cm

3 Pekerjaan Lantai Kerja B0-K 60/Bawah Pondasi,Sloof dan ### 0.82 M3


Saluran Air/t: 5 cm
4 Beton Bertulang Ram/Akses Pintu Masuk

4,1 Pekerjaan Pembuatan Beton Mutu Ad 1 Pc : 2 Ps : 3 Krl ### 1.42 M3


4,2 Pekerjaan Pembesian ### 284.00 Kg

4,3 Pekerjaan Pemasangan Bekisting Untuk Lantai 3x Pakai ### 9.47 M2

5 Pekerjaan Beton Pondasi(PT2)===>60x60x20cm


5,1 Pekerjaan Pembuatan Beton Mutu Ad 1 Pc : 2 Ps : 3 Krl ### 1.44 M3
5,2 Pekerjaan Pembesian ### 201.60 Kg
5,3 Pekerjaan Pemasangan Bekisting Untuk Pondasi ### 9.60 M2
6 Pekerjaan Beton Sloof(S1)===>20x25 cm

6,1 Pekerjaan Pembuatan Beton Mutu Ad 1 Pc : 2 Ps : 3 Krl ### 2.32 M3

6,2 Pekerjaan Pembesian ### 283.04 Kg


6,3 Pekerjaan Pemasangan Bekisting Untuk Sloof 3x Pakai ### 23.15 M2

7 Beton Bertulang Kolom(K1a)====> 20/20 cm

7,1 Pekerjaan Pembuatan Beton Mutu Ad 1 Pc : 2 Ps : 3 Krl ### 2.28 M3


7,2 Pekerjaan Pembesian ### 328.32 Kg
7,3 Pekerjaan Pemasangan Bekisting Untuk Kolom 3x Pakai ### 22.80 M2

8 Pekerjaan Pemasangan Batu Merah Tebal 1/2 Bata (1 Pc : ### 38.07 M2


4 Ps)

9 Pekerjaan Plesteran 1 Pc : 4 Ps Tebal 15 Mm/Termasuk ### 100.94 M2


Kolom
10 Pekerjaan Acian/Termasuk Kolom ### 100.94 M2
11 Pekerjaan Plesteran dan Aci Skoning 1Pc : 3Ps Lebar 10 ### 16.00 M1
Cm
12 Pekerjaan Pemasangan Tralis Pagar /Detail sesuai ### 33.44 M2
gambar/+Cat
Pekerjaan Pengecatan Cat Tembok Bidang Baru Weather
13 Sheid (1 Lapis Plamur, 1 Lapis Cat Dasar, 2 Lapis) Cat ### 100.94 M2
Penutup/Jotun
14 Pasang Pintu gerbang sesuai gambar 1.00 unit

B PEKERJAAN HALAMAN
1 Pekerjaan Pengadaan dan Pemasangan Conblok Tipe Veta ### 149.94 M2
8, Warna Abu-abu, tebal 8 cm, K-400 + Abu batu

2 Pekerjaan Pemasangan Batu Merah Tebal 1 Bata (1 Pc : 4 ### 8.40 M2


Ps)/Rolag Pohon
3 Pekerjaan Plesteran 1 Pc : 4 Ps Tebal 15 Mm/Rolag Pohon ### 8.40 M2
4 Pekerjaan Acian/Rolag Pohon ### 8.40 M2

5 Pekerjaan Pondasi Sumuran/Sumur Resapan/Termasuk ### 7.07 M3


Injuk,Pasir,Kerikil,Batu Kali

C PEKERJAAN SUMUR & POMPA


1 Pekerjaan Pembuatan Sumur Pantek/Lengkap Pipa ### 22.00 M1
pipa/PVC 1",1.5",4"/Klas AW/RUCIKA
2 Pekerjaan Pemasangan Pompa /Jet Pump ### 1.00 Set
CHJ4-40/Groundfose
3 Pekerjaan Pemasangan Tangki Air( Lengkap Dengan ### 1.00 Set
Accesories) Kapasitas 1000 Liter/Excel

4 Pasang rumah pompa lengkap tutup dari besi plat 1.00 unit

D PEKERJAAN TIANG BENDERA


1 Pekerjaan Galian Tanah Biasa( Level 0 s/d 1m) ### 0.15 M3
Pekerjaan Pembuatan Beton Mutu Ad 1 Pc : 2 Ps : 3
2 Krl/Umpak Beton ### 0.15 M3
3 Pekerjaan Pemasangan Angkur Besi ### 6.00 Buah
4 Pekerjaan Pemasangan Mur Baut Dia 16 mm ### 3.00 Buah
5 Pekerjaan Pemasangan Pipa Staeinless Steel 2" t: 1 mm ### 4.00 M1
6 Pekerjaan Pemasangan Pipa Staeinless Steel 2.5" t: 1 mm ### 4.00 M1
7 Pekerjaan Pemasangan Pipa Staeinless Steel 3" t: 1 mm ### 6.00 M1

E PEKERJAAN PAPAN NAMA


1 Pekerjaan Galian Tanah Biasa( Level 0 s/d 1m) ### 0.30 M3
2 Pekerjaan Pembuatan Beton Mutu Ad 1 Pc : 2 Ps : 3 ### 0.30 M3
Krl/Umpak Beton
3 Pekerjaan Pemasangan Angkur Besi ### 4.00 Buah

4 Pekerjaan Pemasangan Besi Profil/Termasuk Pengelasan ### 39.10 Kg


& Alat Bantu/Tiang Besi Pipa Dia 1.5 Inch

5 Pekerjaan Pemasangan Besi Profil/Termasuk Pengelasan ### 43.60 Kg


& Alat Bantu/Plat Besi t: 2,3 mm

Pekerjaan Pengecatan Cat Minyak Bidang Baru (1 Lapis


6 Plamir, 1 Lapis Cat Dasar, Dan 2 Lapis Cat Penutup) ### 4.40 M2

F PEKERJAAN SEPITANK
1 Pekerjaan Galian Tanah Biasa( Level 0 s/d 2m) ### 6.75 M3
2 Pekerjaan Pemasangan Batu Merah Tebal 1/2 Bata (1 Pc : ###
4 Ps) 14.40 M2
3 Pekerjaan Plesteran 1 Pc : 4 Ps Tebal 15 Mm ### 14.40 M2
4 Pekerjaan Pengurugan Pasir Urug ### 3.15 M3
5 Pekerjaan Beton Plat /Besi 1 Lapis

5,1 Pekerjaan Pembuatan Beton Mutu Ad 1 Pc : 2 Ps : 3 Krl ### 0.36 M3


5,2 Pekerjaan Pembesian ### 24.84 Kg
5,3 Pekerjaan Pemasangan Bekisting Untuk Lantai 3x Pakai ### 3.96 M2

6 Pekerjaan Pemasangan Besi Profil/Termasuk Pengelasan ### 16.93 Kg


& Alat Bantu/Mainhole
7 Pekerjaan
M3/Biotech
Pemasangan Septic Tank Biokimia Kapasitas 6 ###
1.00 Set

G PEKERJAAN AKHIR
1 Pekerjaan Pengadaan Playground Jumbo/ Perosotan
Pabrikan/Indoor/Uk P:2,5 L:0,9 T:1,8 M ###

2 Pekerjaan Angkutan Puing/Bekas Bongkaran Sejauh 10 ### 76.85 M3


Km (Dengan Dump Truck)

Jakarta, NOPEMBER 2022

Diperiksa Oleh
NAMA TANDA TANGAN

1
2
3
4
5
ses
URAIAN PEKERJAAN TAMBAH - KURANG (CCO) - BALANCE BUGJED
SKPD / UKPD : SUKU DINAS PENDIDIKAN WILAYAH II KOTA ADMISTRASI JAKARTA PUSAT
PAKET PEKERJAAN : REHAB BERAT GEDUNG SEKOLAH UNTUK ALIH FUNGSI TK NEGERI
LOKASI : KECAMATAN JOHAR BARU WILAYAH II JAKARTA PUSAT
TAHUN ANGGARAN : 2022

PEKERJAAN KURANG PEKERJAAN TAMBAH


NO NAMA PEKERJAAN HARGA JUMLAH HARGA JUMLAH
VOLUME SATUAN VOLUME SATUAN
SATUAN HARGA SATUAN HARGA
A. PEKERJAAN TAMBAH
I PEKERJAAN OVENINGAN PINTU, JENDELA DAN RUANGAN
Pekerjaan kolom praktis dan balok luifel kusen pintu,
1 jendela dan oveningan penghubung ruangan 153.45 M1 78,954.20 12,115,521.99
2 Finishing oveningan (plesteran dan acian) 153.45 M1 74,159.47 11,379,773.20
II PEKERJAAN LANTAI
1 Pekerjaan Urugan pasir tebal 5 cm 12.73 m3 332,590.55 4,234,376.59
III PEKERJAAN LAIN-LAIN
2 Pasang rumah pompa lengkap tutup dari besi plat 1.00 unit 999,246.68 999,246.68
3 Pasang Pintu gerbang sesuai gambar 1.00 unit 9,500,000.00 9,500,000.00
4 Pengerokan cat dinding lama 248.27 M2 26,846.34 6,665,140.83
6 Pasang dinding sketsel double rangka hollow dan gypsum 6.60 M2 308,200.00 2,034,120.00
uk. 6,5x0,90 m
B. PEKERJAAN KURANG
1 Pekerjaan Pengadaan Playground Jumbo/ Perosotan 1.00 Set 11,707,000.00 11,707,000.00
Pabrikan/Indoor/Uk P:2,5 L:0,9 T:1,8 M

2 Pek. Pemasangan Biopori Pipa PVC Type AW Dia. 4" /


Termasuk Pelubangan/Rucika/Jarak 1 m/Kedalaman 2m 76.00 M1 124,058.27 9,428,428.52

Pekerjaan Pemasangan Ornamen GRC Simbul T: 2


3 Cm/Finis Coating 2.00 Unit 310,281.60 620,563.20
Pekerjaan Pemasangan Saluran Air Terbuka 1/2 Ø 30
4 Cm(Termasuk Pemasangan Bata dan Plester Acian) 56.14 M1 307,635.21 17,270,640.69
5 Pasang conblok 32.00 m2 246,923.34 7,901,546.88
JUMLAH 46,928,179.29 46,928,179.29

Disetujui : Diperiksa Oleh Jakarta, N0PEMBER 2022


SUKU DINAS PENDIDIKAN WILAYAH II KOTA ADMISTRASI
JAKARTA PUSAT PT. Pande Tututuri Selaras Konsultan Dibuat oleh
PEJABAT PENANDATANGANAN KONTRAK (PPK) PT BANGUN TRUBUS KARYA

Page 19
NO NAMA PEKERJAAN HARGA JUMLAH HARGA JUMLAH
VOLUME SATUAN VOLUME SATUAN
SATUAN HARGA SATUAN HARGA

HERMAN HERBANDI Parulian Napitupulu, ST CHARLES HUTADJULU


NIP. 196711071998021003 Direktur Utama Direktur

Page 20
BACK - UP PERHITUNGAN VOLUME TAMBAH - KURANG (CCO)

1 KOLOM PRAKTIS DAN BALOK LUIFEL KUSEN PINTU, JENDELA


A. KUSEN PINTU TYPE ; P1 = 5 UNIT B. KUSEN PINTU TYPE ; P1' = 1 UNIT

VOLUME = 2,8 X 2 + 1,5 VOLUME = 2,8 X 2 + 1,5


VOLUME = 2,8 X 2 + 1,6 = 7,1 M' 1 UNIT = 7,1 m'
5 UNIT = 7,1 X 5
= 35,5 M'

C. KUSEN JNDELA TYPE ; J1 = 4 UNIT D. KUSEN JNDELA TYPE ; J2 = 3 UNIT


VOLUME = 1,6 X 2 + 2,45 X 2 VOLUME = 1,6 X 2 + 1,4 X 2
= 8,10 M' = 6,00 M'
4 UNIT = 8,10 X 4 3 UNIT = 6,00 X 3
= 32,40 M' = 18,00 M'

E. KUSEN JNDELA TYPE ; J3 = 1 UNIT F. KUSEN JNDELA TYPE ; J4 = 4 UNIT

VOLUME = 1,6 X 2 + 1,55 X 2 VOLUME = 1,6 X 2 + 0,7 X 2


1 UNIT = 6,30 M' = 4,60 M'
4 UNIT = 4,60 X 4
= 18,40 M'

G. Pekerjaan Pintu (P2)----> 1 Unit H. Pekerjaan Pintu (P3)----> 2 Unit

VOLUME = 2,4 X 1 + 0,85 X 1 VOLUME = 2,4 X 1 + 0,85 X 1


1 UNIT = 3,25 M' 2 UNIT = 6,50 M'

2. OVENINGAN TANPA PINTU

VOLUME = 2,8 X 2 + 0,9 X 1 = 6,5 M'


4 UNIT = 26,00 M'
280

90

TOTAL VOLUME KOLOM PRAKTIS DAN BALOK LUIFEL = P1 + P1' + J1 + J2 + J3 + J4 + P2 + P3 + OVENINGAN TANPA PINTU
= 35,5 M' + 7,1 M' + 32,4 M' + 18,00 M' + 6,30 M' + 18,40 M' + 3,25 M' + 6,50 M' + 26,00 M' = 153,45 M'

3. Perhitungan volume Urugan Pasir dan Lantai kerja dibawah lantai keramik
Luas lantai keramik sesuai BQ = 51,68 + 14,17 + 188,78 = 254,63 m2
4. PASANG BAK SAMPAH:
Harga satuan 1 m2 dinding bak sampah :
a. Pasang dinding 1/2 bata = Rp. 169.343,83
b. Plesteran dinding bagian dalam dan luar = Rp. 84.264,74 x 2 = Rp. 168.529,48
c. Acian plesteran bagian dalam dan luar = Rp. 50.570,69 x 2 = Rp. 101.141,38
Harga satuan 1 m2 dinding bak sampah : Rp. 439.014,69
ANALISA HARGA SATUAN
PEKERJAAN TAMBAH - KURANG (CCO)
SKPD / UKPD : SUKU DINAS PENDIDIKAN WILAYAH II KOTA ADMISTRASI JAKARTA PUSAT
PAKET PEKERJAAN : REHAB BERAT GEDUNG SEKOLAH UNTUK ALIH FUNGSI TK NEGERI
LOKASI : KECAMATAN JOHAR BARU WILAYAH II JAKARTA PUSAT
TAHUN ANGGARAN : 2022

NO URAIAN Satuan Harga Kofesien Total


1. 1 M2 - Pekerjaan Mengikis Mengerok Permukaan Cat Tembok Lama
Tenaga:
Mandor OH 211,379.00 0.003 634.14
Pekerja OH 174,748.00 0.150 26,212.20
Jumlah 26,846.34

3 1 m' - Harga Satuan Finishing oveningan (plesteran dan acian)


a. Plesteran = 0,55 m2 x Rp. 84.264,74 = Rp. 46.345, 60
b. Acian = 0,55 m2 x Rp. 50.570,69 = Rp. 27.813,87
Jadi Harga satuan 1m' Finishing oveningan = Rp. 74.159,47
NO.
URAIAN PEKERJAAN Satuan Volume Harga satuTotal (Rp.)
URAIAN PEKERJAAN TAMBAH - KURANG (CCO) - BALANCE BUGJED

SKPD / UKPD : SUKU DINAS PENDIDIKAN WILAYAH II KOTA


ADMISTRASI JAKARTA PUSAT
PAKET PEKERJAAN : REHAB BERAT GEDUNG SEKOLAH UNTUK ALIH
FUNGSI TK NEGERI
LOKASI : KECAMATAN JOHAR BARU WILAYAH II
JAKARTA PUSAT
TAHUN ANGGARAN : 2022

LAPORAN KEMAJUAN PEKERJAAN MINGGUAN


REKAPITULASI KEMAJUAN PEKERJAAN MINGGUAN
SUKU DINAS PENDIDIKAN

SKPD / UKPD : SUKU DINAS PENDIDIKAN WILAYAH II KOTA ADMISTRASI JAKARTA PUSAT
PAKET PEKERJAAN : REHAB BERAT GEDUNG SEKOLAH UNTUK ALIH FUNGSI TK NEGERI
LOKASI : KECAMATAN JOHAR BARU WILAYAH II JAKARTA PUSAT
TAHUN ANGGARAN : 2022

SESUAI KONTRAK REALISASI PELAKSANAAN


NO
NAMA PEKERJAAN
VOLUME SAT VOLUME SAT
I PEKERJAAN PERSIAPAN

Pekerjaan Pasang Papan Nama Proyek Multiplek 9 mm


1 1.00 Buah 1.00 Buah
di lapis Printing Baner Plastik Konstruksi Kayu 5/7

Pekerjaan Foto Dokumentasi Dengan Camera Digital


2 4.00 Set 4.00 Set
Tanpa Film
Pekerjaan Pekerjaan Pembuatan Gudang Semen Dan
3 9.00 M2 9.00 M2
Peralatan
4 Pekerjaan Pembuatan Steger Perancah Dari Bambu 38.00 M2 38.00 M2
5 Pekerjaan Listrik dan Air Kerja 1.00 Ls 1.00 Ls
6 Pekerjaan K3
6,1 Jaring Pengaman(Plastik) 57.00 M2 57.00 M2
6,2 Helm Kerja 12.00 Unit 12.00 Unit
6,3 Sabuk Pengaman 12.00 Unit 12.00 Unit
6,4 Sepatu Boots 12.00 Psg 12.00 Psg
6,5 Jaket Rompi 12.00 Unit 12.00 Unit
6,6 Sarung Tangan 36.00 Psg 36.00 Psg
6,7 Masker 48.00 Unit 48.00 Unit
Pekerjaan SOP Protokol Kesehatan/Perlindungan
7
Covid
7,1 Pengukur Suhu Badan/Thermoscan 2.00 Buah 2.00 Buah
Wastafel Pencuci Tangan Lengkap dengan
7,2 1.00 Set 1.00 Set
Sabun,Kran,Tangka Air dan Pipa Pembuangan
7,3 Tes Swab Antigen 16.00 Test 16.00 Test

II PEKERJAAN GEDUNG UTAMA


A PEKERJAAN BONGKARAN
Pekerjaan Pembongkaran Keramik/Termasuk
1 139.50 M2 139.50 M2
Adukan/Gedung Utama
Pekerjaan Pembongkaran Beton Bertulang/Gedung
2 1.16 M3 1.16 M3
Utama & Pagar Existing

Pekerjaan Pembongkaran Tembok Batu Bata/Gedung


3 7.01 M3 7.01 M3
Utama,Bak Sampah & Pagar Existing

Pekerjaan Pembongkaran Plafond &


4 Rangka( Bongkaran Tidak Dipasang Kembali)/Gedung 139.50 M2 139.50 M2
Utama
Pekerjaan Pembongkaran Rangka Atap/Gedung
5 155.00 M2 155.00 M2
Utama
Page 26
NO
NAMA PEKERJAAN
VOLUME SAT VOLUME SAT
6 Pekerjaan Pembongkaran Kusen/Gedung Utama 1.05 M3 1.05 M3
7 Pekerjaan Pembongkaran Paving/Halaman 168.31 M2 168.31 M2
Pekerjaan Pemotongan Pohon Pilihan Diameter 30 - 50
8 1.00 Buah 1.00 Buah
Cm/Area Depan
Pekerjaan Pemotongan Pohon Pilihan Diameter 50 - 75
9 1.00 Buah 1.00 Buah
Cm/Area Belakang
Pekerjaan Pembersihan Lapangan Dan Perataan/Area
10 110.98 M2 110.98 M2
Belakang

Page 27
NO
NAMA PEKERJAAN
VOLUME SAT VOLUME SAT
B PEKERJAAN DIBAWAH NOL(0) LANTAI
Pekerjaan Galian Tanah Biasa( Level 0 s/d
1 15.69 M3 15.69 M3
1m)/Pondasi,Sloof dan Saluran Air
Pekerjaan Pengurugan Pasir Urug/Bawah
2 1.54 M3 1.54 M3
Pondasi,Sloof dan Saluran Air/t: 5 cm
Pekerjaan Lantai Kerja B0-K 60/Bawah Pondasi,Sloof
3 1.54 M3 1.54 M3
dan Saluran Air/t: 5 cm

C PEKERJAAN STRUKTUR
1 Pekerjaan Beton Sloof(S1)===>20x25 cm
Pekerjaan Pembuatan Beton Mutu F'C = 21,7 Mpa (K
1,1 2.04 M3 2.04 M3
250)
1,2 Pekerjaan Pembesian 248.88 Kg 248.88 Kg

1,3 Pekerjaan Pemasangan Bekisting Untuk Sloof 3x Pakai 20.40 M2 20.40 M2

2 Pekerjaan Beton Pondasi(PT2)===>60x60x20cm

Pekerjaan Pembuatan Beton Mutu F'C = 21,7 Mpa (K


2,1 0.58 M3 0.58 M3
250)
2,2 Pekerjaan Pembesian 81.20 Kg 81.20 Kg
2,3 Pekerjaan Pemasangan Bekisting Untuk Pondasi 3.84 M2 3.84 M2

3 Pekerjaan Beton Pondasi(PT3)===>112x60x20cm

Pekerjaan Pembuatan Beton Mutu F'C = 21,7 Mpa (K


3,1 0.27 M3 0.27 M3
250)
3 Pekerjaan Pembesian 38.61 Kg 38.61 Kg
3,3 Pekerjaan Pemasangan Bekisting Untuk Pondasi 1.38 M2 1.38 M2
4 Pekerjaan Beton Pondasi(PTS)===>80x80x20cm (Pondasi Sketsel)

Pekerjaan Pembuatan Beton Mutu F'C = 21,7 Mpa (K


4,1 0.26 M3 0.26 M3
250)
4,2 Pekerjaan Pembesian 35.88 Kg 35.88 Kg

4,3 Pekerjaan Pemasangan Bekisting Untuk Pondasi 1.28 M2 1.28 M2

5 Pekerjaan Beton Kolom(K1)===> 20x20 cm

Pekerjaan Pembuatan Beton Mutu F'C = 21,7 Mpa (K


5,1 1.23 M3 1.23 M3
250)
5,2 Pekerjaan Pembesian 178.35 Kg 178.35 Kg
Pekerjaan Pemasangan Bekisting Untuk Kolom 3x
5,3 24.64 M2 24.64 M2
Pakai
6 Pekerjaan Beton Kolom(K2)===> 14x20 cm/Kolom Vareasi
Pekerjaan Pembuatan Beton Mutu F'C = 21,7 Mpa (K
6,1 0.97 M3 0.97 M3
250)
6,2 Pekerjaan Pembesian 149.38 Kg 149.38 Kg
Pekerjaan Pemasangan Bekisting Untuk Kolom 3x
6,3 23.56 M2 23.56 M2
Pakai

7 Pekerjaan Beton Kolom(KS)===> 20x400 cm/Kolom Sketsel


Pekerjaan Pembuatan Beton Mutu F'C = 21,7 Mpa (K
7,1 0.38 M3 0.38 M3
250)
7,2 Pekerjaan Pembesian 64.98 Kg 64.98 Kg
Pekerjaan Pemasangan Bekisting Untuk Kolom 3x
7,3 5.76 M2 5.76 M2
Pakai

8 Pekerjaan Beton Balok(RB1)===> 20x25 cm


Pekerjaan Pembuatan Beton Mutu F'C = 21,7 Mpa (K
8,1 5.61 M3 5.61 M3
250)
8,2 Pekerjaan Pembesian 880.77 Kg 880.77 Kg
Pekerjaan Pemasangan Bekisting Untuk Balok 3x
8,3 50.47 M2 50.47 M2
Pakai
Page 28
NO
NAMA PEKERJAAN
VOLUME SAT VOLUME SAT

9 Pekerjaan Beton Balok(BS)===> 20x40 cm


Pekerjaan Pembuatan Beton Mutu F'C = 21,7 Mpa (K
9,1 0.56 M3 0.56 M3
250)
9,2 Pekerjaan Pembesian 94.08 Kg 94.08 Kg

Page 29
NO
NAMA PEKERJAAN
VOLUME SAT VOLUME SAT

Pekerjaan Pemasangan Bekisting Untuk Balok 3x


9,3 4.20 M2 4.20 M2
Pakai

10 Pekerjaan Beton Plat Kanopi t: 12 cm


Pekerjaan Pembuatan Beton Mutu F'C = 21,7 Mpa (K
10,1 2.92 M3 2.92 M3
250)
10,2 Pekerjaan Pembesian 405.88 Kg 405.88 Kg
Pekerjaan Pemasangan Bekisting Untuk Lantai 3x
10,3 28.82 M2 28.82 M2
Pakai
11 Pekerjaan Beton Plat Bak Cuci /Pantry : 12 cm
Pekerjaan Pembuatan Beton Mutu F'C = 21,7 Mpa (K
11,1 0.18 M3 0.18 M3
250)
11,2 Pekerjaan Pembesian 25.02 Kg 25.02 Kg
Pekerjaan Pemasangan Bekisting Untuk Lantai 3x
11,3 2.23 M2 2.23 M2
Pakai
Pekerjaan Membuat Kolom Praktis Beton Bertulang
12 38.40 M1 38.40 M1
(11 X 11) Cm/Kp

D PEKERJAAN PASANGAN
D.1 PEKERJAAN PASANGAN KERAMIK
Pekerjaan Pemasangan Lantai Homogeneus Ukuran
1 119.35 M2 119.35 M2
60x60 cm/ Polised/Roman/Ruangan
Pekerjaan Pemasangan Lantai Homogeneus Ukuran
2 35.00 M2 35.00 M2
60x60 cm/ Unpolised/Roman/Selasar

Pekerjaan Pemasangan Lantai Keramik Ukuran.


3 40X40 Cm / Unpolised /Roman/Motif Batu 34.39 M2 34.39 M2
Alam/Teras

Pekerjaan Pemasangan Dinding Batu Andesit/Finis


4 29.95 M2 29.95 M2
Coating

Pekerjaan Pemasangan Ornamen GRC Simbul T: 2


5 2.00 Unit
Cm/Finis Coating
Pekerjaan Pemasangan Logo/Huruf Steinless Steel
6 Tebal 4 Cm/Tinggi 20 Cm/TAMAN KANAK KANAK 66.00 Pcs 66.00 Pcs
NEGERI JOHAR BARU 01

D.2 PEKERJAAN PASANGAN DINDING BATA & PLESTERAN

Pekerjaan Pemasangan Batu Merah Tebal 1/2 Bata (1


1 79.29 M2 79.29 M2
Pc : 4 Ps)/Dinding/Termasuk Peninggian Elevasi Atap

Pekerjaan Plesteran 1 Pc : 4 Ps Tebal 15


2 183.22 M2 183.22 M2
Mm/Dinding/Termasuk Finishing Kolom

3 Pekerjaan Acian/Dinding/Termasuk Finishing Kolom 183.22 M2 183.22 M2

Pekerjaan Pemasangan Saluran Air Terbuka 1/2 Ø 30


4 38.00 M1 38.00 M1
Cm(Termasuk Pemasangan Bata dan Plester Acian)

Pekerjaan Pemasangan Saluran Air Tertutup Ø 30


5 9.70 M1 9.70 M1
Cm(Termasuk Pemasangan Bata dan Plester Acian)

Pekerjaan Pemasangan Biopori Pipa PVC Type AW Dia.


6 4" /Termasuk Pelubangan/Rucika/Jarak 1 76.00 M1
m/Kedalaman 2 m
Pekerjaan Pemasangan Grill/Penutup Saluran Air L
7 38.00 M1 38.00 M1
30 Cm+Cat

E PEKERJAAN PINTU/JENDELA
1 Pekerjaan Pintu (P1)---->5 Unit
Page 30
NO
NAMA PEKERJAAN
VOLUME SAT VOLUME SAT

Pekerjaan Pemasangan Besi Profil/Termasuk


1,1 Pengelasan & Alat Bantu/Cat/Kusen Besi Hollow 344.54 Kg 344.54 Kg
50x100x2,3

Pekerjaan Pemasangan Besi Profil/Termasuk


1,2 Pengelasan & Alat Bantu/Cat/Jalusi Besi Hollow 114.89 Kg 114.89 Kg
30x60x2,3

Page 31
NO
NAMA PEKERJAAN
VOLUME SAT VOLUME SAT
Pekerjaan Pemasangan Pintu Panil Kayu Kelas I Oven
1,3 15.00 M2 15.00 M2
Samarinda

1,4 Pekerjaan Pemasangan Kaca Mati Tebal 5 mm/Assahi 0.60 M2 0.60 M2

1,5 Pekerjaan Pemasangan Kunci Tanam Biasa /Deckson 5.00 Buah 5.00 Buah

Pekerjaan Pemasangan Engsel Pintu Kuningan 3 "


1,6 30.00 Buah 30.00 Buah
/Deckson
1,7 Pekerjaan Pemasangan Kunci Slot /Deckson 10.00 Buah 10.00 Buah
Pekerjaan Pemasangan Hendle Grid Stainless Steel 30
1,8 5.00 Set 5.00 Set
Cm
1,9 Pekerjaan Mendempul Dan Menggosok Kayu 30.00 M2 30.00 M2
Pekerjaan Pengecatan Cat Minyak Bidang Baru (1
1,10 Lapis Plamir, 1 Lapis Cat Dasar, Dan 2 Lapis Cat 30.00 M2 30.00 M2
Penutup)
2 Pekerjaan Pintu (P1')----> 1 Unit
Pekerjaan Pemasangan Besi Profil/Termasuk
2,1 Pengelasan & Alat Bantu/Cat/Kusen Besi Hollow 66.07 Kg 66.07 Kg
50x100x2,3

Pekerjaan Pemasangan Besi Profil/Termasuk


2,2 Pengelasan & Alat Bantu/Cat/Jalusi Besi Hollow 19.91 Kg 19.91 Kg
30x60x2,3

Pekerjaan Pemasangan Pintu Panil Kayu Kelas I Oven


2,3 2.60 M2 2.60 M2
Samarinda

2,4 Pekerjaan Pemasangan Kaca Mati Tebal 5 mm/Assahi 0.12 M2 0.12 M2

2,5 Pekerjaan Pemasangan Kunci Tanam Biasa /Deckson 1.00 Buah 1.00 Buah
Pekerjaan Pemasangan Engsel Pintu Kuningan 3 "
2,6 6.00 Buah 6.00 Buah
/Deckson
2,7 Pekerjaan Pemasangan Kunci Slot /Deckson 2.00 Buah 2.00 Buah
Pekerjaan Pemasangan Hendle Grid Stainless Steel 30
2,8 1.00 Set 1.00 Set
Cm
2,9 Pekerjaan Mendempul Dan Menggosok Kayu 5.20 M2 5.20 M2
Pekerjaan Pengecatan Cat Minyak Bidang Baru (1
2,10 Lapis Plamir, 1 Lapis Cat Dasar, Dan 2 Lapis Cat 5.20 M2 5.20 M2
Penutup)
3 Pekerjaan Jendela (J1)----> 4 Unit
Pekerjaan Pemasangan Kusen Alluminium Warna 4"
3,1 55.00 M1 55.00 M1
(Termasuk Paku Sekrup + Sealant) /Alexindo
Pekerjaan Pemasangan Jalusi Holo Alumunium 4 x 3/
3,2 49.00 M1 49.00 M1
4 "/Alexindo
3,3 Pekerjaan Pemasangan Kaca Mati Tebal 5 mm/Assahi 2.64 M2 2.64 M2
Pekerjaan Pemasangan Daun Kaca Polos +
3,4 5.28 M2 5.28 M2
Frame/Rangka Alluminium /Lengkap Karet
3,5 Pekerjaan Pemasangan Engsel Casmen/Deckson 16.00 Buah 16.00 Buah
3,6 Pekerjaan Pemasangan Hendel Casmen/Deckson 8.00 Buah 8.00 Buah

4 Pekerjaan Jendela (J2)----> 3 Unit


Pekerjaan Pemasangan Kusen Alluminium Warna 4"
4,1 27.00 M1 27.00 M1
(Termasuk Paku Sekrup + Sealant) /Alexindo
Pekerjaan Pemasangan Jalusi Holo Alumunium 4 x 3/
4,2 21.00 M1 21.00 M1
4 "/Alexindo

4,3 Pekerjaan Pemasangan Kaca Mati Tebal 5 mm/Assahi 1.98 M2 1.98 M2

Pekerjaan Pemasangan Daun Kaca Polos +


4,4 1.98 M2 1.98 M2
Frame/Rangka Alluminium /Lengkap Karet
4,5 Pekerjaan Pemasangan Engsel Casmen/Deckson 6.00 Buah 6.00 Buah
4,6 Pekerjaan Pemasangan Hendel Casmen/Deckson 3.00 Buah 3.00 Buah
5 Pekerjaan Jendela (J3)----> 1 Unit
Page 32
NO
NAMA PEKERJAAN
VOLUME SAT VOLUME SAT
Pekerjaan Pemasangan Kusen Alluminium Warna 4"
5,1 9.45 M1 9.45 M1
(Termasuk Paku Sekrup + Sealant) /Alexindo
Pekerjaan Pemasangan Jalusi Holo Alumunium 4 x 3/
5,2 7.75 M1 7.75 M1
4 "/Alexindo

Page 33
NO
NAMA PEKERJAAN
VOLUME SAT VOLUME SAT

5,3 Pekerjaan Pemasangan Kaca Mati Tebal 5 mm/Assahi 0.66 M2 0.66 M2


Pekerjaan Pemasangan Daun Kaca Polos +
5,4 0.66 M2 0.66 M2
Frame/Rangka Alluminium /Lengkap Karet
5,5 Pekerjaan Pemasangan Engsel Casmen/Deckson 2.00 Buah 2.00 Buah
5,6 Pekerjaan Pemasangan Hendel Casmen/Deckson 1.00 Buah 1.00 Buah
6 Pekerjaan Jendela (J4)----> 4 Unit
Pekerjaan Pemasangan Kusen Alluminium Warna 4"
6,1 5.30 M1 5.30 M1
(Termasuk Paku Sekrup + Sealant) /Alexindo
Pekerjaan Pemasangan Jalusi Holo Alumunium 4 x 3/
6,2 3.50 M1 3.50 M1
4 "/Alexindo
Pekerjaan Pemasangan Daun Kaca Polos +
6,3 0.66 M2 0.66 M2
Frame/Rangka Alluminium /Lengkap Karet
6,4 Pekerjaan Pemasangan Engsel Casmen/Deckson 2.00 Buah 2.00 Buah
6,5 Pekerjaan Pemasangan Hendel Casmen/Deckson 1.00 Buah 1.00 Buah
Pekerjaan Pemasangan Pintu Teakwood Rangkap
7 15.00 M2 15.00 M2
+Rangka Lapis HPL/Sketsel/Borneo

Pekerjaan kolom praktis dan balok luifel kusen pintu,


8 - - 153.45 M1
jendela dan oveningan penghubung ruangan

9 Finishing oveningan (plesteran dan acian) - - 153.45 M1

Pasang dinding diatas sketsel double rangka hollow


10 - - 6.60 M2
dan double gypsum uk. 6,5x0,90 m

F PEKERJAAN PENGECATAN
Pekerjaan Pengecatan Cat Tembok Bidang Baru( 1
1 Lapis Plamur, 1 Lapis Cat Dasar, 2 Lapis )Cat 248.27 M2 248.27 M2
Penutup/Jotun/Dinding/Kolom

Pekerjaan Pengecatan Cat Tembok Bidang Baru


Weather Sheid (1 Lapis Plamur, 1 Lapis Cat Dasar, 2
2 173.65 M2 173.65 M2
Lapis) Cat Penutup/Jotun/Dinding/KolomLisplank
Motif Betawi

Pekerjaan Pengecatan Cat Tembok Bidang Baru


Weather Sheid (1 Lapis Plamur, 1 Lapis Cat Dasar, 2
3 78.00 M2 78.00 M2
Lapis) Cat Penutup/Cat Exterior/Cat Lukis Mural
3D/Mowilex

4 Pengerokan cat dinding lama 248.27 M2

G PEKERJAAN PLAFON
Pekerjaan Pemasangan Plafon PVC t: 9 mm,l 16 cm +
1 Rangka & Penggantung Hollo 40/40/0.35/Lengkap 190.00 M2 190.00 M2
Lis Sudut/Sunda Plafon/Dinding/Kolom

H PEKERJAAN ATAP
Pekerjaan Pemasangan Rangka Atap Kuda Kuda Baja
1 Ringan Galvalume /Termasuk Talang Jurai,Kaso & 224.20 M2 224.20 M2
Reng/Steel Truss
Pekerjaan Pemasangan Aluminium Foil Untuk
2 224.20 M2 224.20 M2
Atap(Single Side 1,2 m x 50 m)
Pekerjaan Pemasangan Atap Genteng Bitumen Ukuran
3 224.20 M2 224.20 M2
400x1060 mm /Onduvila
Pekerjaan Pemasangan Wuwung Nok Bitumen Ukuran
4 19.00 M1 19.00 M1
l: 800 mm /Onduvila
Pekerjaan Pemasangan Genteng Tepi/Penutup
5 23.60 M1 23.60 M1
Lisplank/Onduvila
Pekerjaan Pemasangan Listplank Panel GRC Motif
6 61.60 M1 61.60 M1
Betawi, T: 2 Cm,Lebar 30 cm

Page 34
NO
NAMA PEKERJAAN
VOLUME SAT VOLUME SAT
I PEKERJAAN SANITAIR/PLUMBING
Pekerjaan Pemasangan Pipa PVC Type AW Dia.
1 26.00 M1 26.00 M1
1/2" /Rucika/Air Bersih
Pekerjaan Pemasangan Pipa PVC Type AW Dia. 2"
2 2.50 M1 2.50 M1
/Rucika/Air Bekas
Pekerjaan Pemasangan Wastafel/Lengkap Asesoris/L
3 3.00 Unit 3.00 Unit
529 V1/Toto

4 Pekerjaan Pemasangan Floor Drain 4"/TX 1 BN/Toto 1.00 Unit 1.00 Unit
Pekerjaan Pemasangan Kran Air
5 2.00 Buah 2.00 Buah
1/2"/T23B13VNb/Toto
6 Pekerjaan Pemasangan Kran Leher Angsa 1.00 Buah 1.00 Buah

7 Pekerjaan Pemasangan Bak Cuci Piring Stainless Steel 1.00 Unit 1.00 Unit

J PEKERJAAN ME/LISTRIK
J.1 Pekerjaan Instalasi Kabel
Pekerjaan Pemasangan Instalasi Titik Lampu
1 Penerangan Kabel Ukuran 2x2,5(Lengkap Pipa 41.00 Titik 41.00 Titik
Conduit) /Eterna

Pekerjaan Pemasangan Instalasi Stop Kontak Biasa


2 9.00 Titik 9.00 Titik
Kabel Ukuran 3x2,5(Lengkap Pipa Conduit) /Eterna

Pekerjaan Pemasangan Instalasi Power AC Kabel NYM


3 2.00 Titik 2.00 Titik
3 x 4 (Lengkap Pipa Conduit) /Eterna
J.2 Pekerjaan Armarture
1 Pekerjaan Pemasangan Stop Kontak Biasa/Broco 9.00 Buah 9.00 Buah
2 Pekerjaan Pemasangan Stop Kontak Power(AC)/Broco 2.00 Buah 2.00 Buah
Pekerjaan Pemasangan AC Split 3/4 PK Low
3 2.00 Unit 2.00 Unit
Watt/Lengkap Asesoris/AH-AP7UHL/Sharp
Pekerjaan Pemasangan Lampu LED 18 Watt(Lengkap
4 7.00 Titik 7.00 Titik
Fitting)/Philips
Pekerjaan Pemasangan Lampu Down Light (Lengkap
5 34.00 Titik 34.00 Titik
Fitting)/Philips
6 Pekerjaan Pemasangan Saklar Ganda /Broco 9.00 Buah 9.00 Buah
J.3 Pekerjaan Panel+Mcb
1 Pekerjaan Pemasangan Panel Pembagi 40x60x20 cm 1.00 Unit 1.00 Unit
2 Pekerjaan Pasang MCB 6 A 3.00 Buah 3.00 Buah
3 Pekerjaan Pasang MCB 10 A 5.00 Buah 5.00 Buah
4 Pekerjaan Pasang MCB 25 A 1.00 Buah 1.00 Buah

III PEKERJAAN RUANG BERMAIN


A PEKERJAAN DIBAWAH NOL(0) LANTAI
Pekerjaan Galian Tanah Biasa( Level 0 s/d
1 5.03 M3 5.03 M3
1m)/Pondasi & Sloof
Pekerjaan Pengurugan Pasir Urug/Bawah
2 0.57 M3 0.57 M3
Pondasi,Sloof dan Saluran Air/t: 5 cm
Pekerjaan Lantai Kerja B0-K 60/Bawah Pondasi,Sloof
3 0.57 M3 0.57 M3
dan Saluran Air/t: 5 cm

B PEKERJAAN STRUKTUR
1 Pekerjaan Beton Sloof(S1)===>20x25 cm
Pekerjaan Pembuatan Beton Mutu F'C = 21,7 Mpa (K
1,1 1.60 M3 1.60 M3
250)
1,2 Pekerjaan Pembesian 195.20 Kg 195.20 Kg
1,3 Pekerjaan Pemasangan Bekisting Untuk Sloof 3x Pakai 16.00 M2 16.00 M2

2 Pekerjaan Beton Pondasi(PT1)===>70x70x20cm

Pekerjaan Pembuatan Beton Mutu F'C = 21,7 Mpa (K


2,1 0.98 M3 0.98 M3
250)
2,2 Pekerjaan Pembesian 136.22 Kg 136.22 Kg
Page 35
NO
NAMA PEKERJAAN
VOLUME SAT VOLUME SAT

2,3 Pekerjaan Pemasangan Bekisting Untuk Pondasi 5.60 M2 5.60 M2

3 Pekerjaan Beton Kolom(K1)===> 20x20 cm


Pekerjaan Pembuatan Beton Mutu F'C = 21,7 Mpa (K
3,1 1.10 M3 1.10 M3
250)
3,2 Pekerjaan Pembesian 159.50 Kg 159.50 Kg
Pekerjaan Pemasangan Bekisting Untuk Kolom 3x
3,3 22.08 M2 22.08 M2
Pakai
4 Pekerjaan Beton Kolom(K2)===> 14x20 cm

Page 36
NO
NAMA PEKERJAAN
VOLUME SAT VOLUME SAT

Pekerjaan Pembuatan Beton Mutu F'C = 21,7 Mpa (K


4,1 0.21 M3 0.21 M3
250)
4,2 Pekerjaan Pembesian 41.37 Kg 41.37 Kg
Pekerjaan Pemasangan Bekisting Untuk Kolom 3x
4,3 5.03 M2 5.03 M2
Pakai
5 Pekerjaan Beton Kolom(Kp)===> 11x11 cm
Pekerjaan Pembuatan Beton Mutu F'C = 21,7 Mpa (K
5,1 0.09 M3 0.09 M3
250)
5,2 Pekerjaan Pembesian 26.73 Kg 26.73 Kg
Pekerjaan Pemasangan Bekisting Untuk Kolom 3x
5,3 3.30 M2 3.30 M2
Pakai
6 Pekerjaan Beton Balok(RB1)===> 20x25 cm
Pekerjaan Pembuatan Beton Mutu F'C = 21,7 Mpa (K
6,1 1.20 M3 1.20 M3
250)
6,2 Pekerjaan Pembesian 146.40 Kg 146.40 Kg
Pekerjaan Pemasangan Bekisting Untuk Balok 3x
6,3 12.00 M2 12.00 M2
Pakai
7 Pekerjaan Beton Balok(RB)===> 11x15 cm
Pekerjaan Pembuatan Beton Mutu F'C = 21,7 Mpa (K
7,1 0.18 M3 0.18 M3
250)
7,2 Pekerjaan Pembesian 41.76 Kg 41.76 Kg
Pekerjaan Pemasangan Bekisting Untuk Balok 3x
7,3 3.24 M2 3.24 M2
Pakai
8 Pekerjaan Beton Plat Kanopi t: 12 cm
Pekerjaan Pembuatan Beton Mutu F'C = 21,7 Mpa (K
8,1 2.66 M3 2.66 M3
250)
8,2 Pekerjaan Pembesian 369.74 Kg 369.74 Kg
Pekerjaan Pemasangan Bekisting Untuk Lantai 3x
8,3 29.01 M2 29.01 M2
Pakai
Pekerjaan Pemasangan Water Proofing Coating
8,4 27.71 M2 27.71 M2
3x/Sika
8,5 Pekerjaan Screeding Tebal 3 cm 27.71 M2 27.71 M2

C PEKERJAAN PASANGAN
C.1 PEKERJAAN PASANGAN KERAMIK

Pekerjaan Pemasangan Lantai Homogeneus Ukuran


1 32.00 M2 32.00 M2
60x60 cm/ Polised/Roman/Ruangan

Pekerjaan Pemasangan Lantai Keramik Ukuran.


2 40X40 Cm / Unpolised /Roman/Motif Batu 19.68 M2 19.68 M2
Alam/Teras
3 Pekerjaan Urugan pasir tebal 5 cm 12.73 m3
C.2 PEKERJAAN PASANGAN DINDING BATA & PLESTERAN
Pekerjaan Pemasangan Batu Merah Tebal 1/2 Bata (1
1 47.90 M2 47.90 M2
Pc : 4 Ps)
2 Pekerjaan Plesteran 1 Pc : 4 Ps Tebal 15 Mm 95.80 M2 95.80 M2
3 Pekerjaan Acian 95.80 M2 95.80 M2

Pekerjaan Pemasangan Saluran Air Terbuka 1/2 Ø 30


4 95.80 M1 39.66 M1
Cm(Termasuk Pemasangan Bata dan Plester Acian)

D PEKERJAAN PINTU/JENDELA
1 Pekerjaan Pintu (P1)===> 1 Unit
Pekerjaan Pemasangan Besi Profil/Termasuk
1,1 Pengelasan & Alat Bantu/Cat/Kusen Besi Hollow 68.91 Kg 68.91 Kg
50x100x2,3

Pekerjaan Pemasangan Besi Profil/Termasuk


1,2 Pengelasan & Alat Bantu/Cat/Jalusi Besi Hollow 22.98 Kg 22.98 Kg
30x60x2,3

Page 37
NO
NAMA PEKERJAAN
VOLUME SAT VOLUME SAT

Pekerjaan Pemasangan Pintu Panil Kayu Kelas I Oven


1,3 3.00 M2 3.00 M2
Samarinda

1,4 Pekerjaan Pemasangan Kaca Mati Tebal 5 mm/Assahi 0.12 M2 0.12 M2

1,5 Pekerjaan Pemasangan Kunci Tanam Biasa /Deckson 1.00 Buah 1.00 Buah

Pekerjaan Pemasangan Engsel Pintu Kuningan 3 "


1,6 6.00 Buah 6.00 Buah
/Deckson
1,7 Pekerjaan Pemasangan Kunci Slot /Deckson 2.00 Buah 2.00 Buah
Pekerjaan Pemasangan Hendle Grid Stainless Steel 30
1,8 1.00 Set 1.00 Set
Cm
1,9 Pekerjaan Mendempul Dan Menggosok Kayu 6.00 M2 6.00 M2
Pekerjaan Pengecatan Cat Minyak Bidang Baru (1
1,10 Lapis Plamir, 1 Lapis Cat Dasar, Dan 2 Lapis Cat 6.00 M2 6.00 M2
Penutup)
2 Pekerjaan Jendela (J1)===> 3 Unit
Pekerjaan Pemasangan Kusen Alluminium Warna 4"
2,1 41.25 M1 41.25 M1
(Termasuk Paku Sekrup + Sealant) /Alexindo
Pekerjaan Pemasangan Jalusi Holo Alumunium 4 x 3/
2,2 36.75 M1 36.75 M1
4 "/Alexindo

2,3 Pekerjaan Pemasangan Kaca Mati Tebal 5 mm/Assahi 1.98 M2 1.98 M2

Pekerjaan Pemasangan Daun Kaca Polos +


2,4 3.96 M2 3.96 M2
Frame/Rangka Alluminium /Lengkap Karet
2,5 Pekerjaan Pemasangan Engsel Casmen/Deckson 12.00 Buah 12.00 Buah
2,6 Pekerjaan Pemasangan Hendel Casmen/Deckson 6.00 Buah 6.00 Buah
3 Pekerjaan Jendela (J1')===> 2 Unit
Pekerjaan Pemasangan Kusen Alluminium Warna 4"
3,1 40.80 M1 40.80 M1
(Termasuk Paku Sekrup + Sealant) /Alexindo
Pekerjaan Pemasangan Jalusi Holo Alumunium 4 x 3/
3,2 36.00 M1 36.00 M1
4 "/Alexindo

3,3 Pekerjaan Pemasangan Kaca Mati Tebal 5 mm/Assahi 1.98 M2 1.98 M2

Pekerjaan Pemasangan Daun Kaca Polos +


3,4 3.96 M2 3.96 M2
Frame/Rangka Alluminium /Lengkap Karet
3,5 Pekerjaan Pemasangan Engsel Casmen/Deckson 12.00 Buah 12.00 Buah
3,6 Pekerjaan Pemasangan Hendel Casmen/Deckson 6.00 Buah 6.00 Buah

E PEKERJAAN PENGECATAN
Pekerjaan Pengecatan Cat Tembok Bidang Baru( 1
1 Lapis Plamur, 1 Lapis Cat Dasar, 2 Lapis )Cat 75.61 M2 75.61 M2
Penutup/Jotun/Teramsuk Plat Dak Beton

Pekerjaan Pengecatan Cat Tembok Bidang Baru


2 Weather Sheid (1 Lapis Plamur, 1 Lapis Cat Dasar, 2 41.11 M2 41.11 M2
Lapis) Cat Penutup/Jotun

Pekerjaan Pengecatan Cat Tembok Bidang Baru


Weather Sheid (1 Lapis Plamur, 1 Lapis Cat Dasar, 2
3 34.50 M2 34.50 M2
Lapis) Cat Penutup/Cat Exterior/Cat Lukis Mural
3D/Mowilex

F PEKERJAAN PLAFON

Pekerjaan Pemasangan Plafon PVC t: 9 mm,l 16 cm +


1 Rangka & Penggantung Hollo 40/40/0.35/Lengkap 32.00 M2 32.00 M2
Lis Sudut/Sunda Plafon/Dinding/Kolom

G PEKERJAAN ATAP

Page 38
NO
NAMA PEKERJAAN
VOLUME SAT VOLUME SAT
Pekerjaan Pemasangan Rangka Atap Kuda Kuda Baja
1 Ringan Galvalume /Termasuk Talang Jurai,Kaso & 48.00 M2 48.00 M2
Reng/Steel Truss
Pekerjaan Pemasangan Atap Genteng Bitumen Ukuran
2 48.00 M2 48.00 M2
400x1060 mm /Onduvila
Pekerjaan Pemasangan Wuwung Nok Bitumen Ukuran
3 8.00 M1 8.00 M1
l: 800 mm /Onduvila
Pekerjaan Pemasangan Genteng Tepi/Penutup
4 16.00 M1 16.00 M1
Lisplank/Onduvila
Pekerjaan Pemasangan Listplank Panel GRC Motif
5 28.00 M1 28.00 M1
Betawi, T: 2 Cm,Lebar 30 cm

H PEKERJAAN ME/LISTRIK
H.1.1 Pekerjaan Instalasi Kabel
Pekerjaan Pemasangan Instalasi Titik Lampu
1 Penerangan Kabel Ukuran 2x2,5(Lengkap Pipa 8.00 Titik 8.00 Titik
Conduit) /Eterna

Pekerjaan Pemasangan Instalasi Stop Kontak Biasa


2 2.00 Titik 2.00 Titik
Kabel Ukuran 3x2,5(Lengkap Pipa Conduit) /Eterna

H.1.2 Pekerjaan Armarture


1 Pekerjaan Pemasangan Stop Kontak Biasa/Broco 2.00 Buah 2.00 Buah
Pekerjaan Pemasangan Lampu Down Light (Lengkap
2 8.00 Titik 8.00 Titik
Fitting)/Philips
3 Pekerjaan Pemasangan Saklar Ganda /Broco 1.00 Buah 1.00 Buah

IV PEKERJAAN TOILET/KM
A PEKERJAAN DIBAWAH NOL(0) LANTAI
Pekerjaan Galian Tanah Biasa( Level 0 s/d
1 3.00 M3 3.00 M3
1m)/Pondasi & Sloof
Pekerjaan Pengurugan Pasir Urug/Bawah
2 0.41 M3 0.41 M3
Pondasi,Sloof dan Saluran Air/t: 5 cm
Pekerjaan Lantai Kerja B0-K 60/Bawah Pondasi,Sloof
3 0.41 M3 0.41 M3
dan Saluran Air/t: 5 cm

B PEKERJAAN STRUKTUR
1 Pekerjaan Beton Sloof(S1)===>20x25 cm
Pekerjaan Pembuatan Beton Mutu F'C = 21,7 Mpa (K
1,1 1.49 M3 1.49 M3
250)
1,2 Pekerjaan Pembesian 181.78 Kg 181.78 Kg

1,3 Pekerjaan Pemasangan Bekisting Untuk Sloof 3x Pakai 14.85 M2 14.85 M2

2 Pekerjaan Beton Pondasi(PT2)===>60x60x20cm

Pekerjaan Pembuatan Beton Mutu F'C = 21,7 Mpa (K


2,1 0.43 M3 0.43 M3
250)
2,2 Pekerjaan Pembesian 60.20 Kg 60.20 Kg
2,3 Pekerjaan Pemasangan Bekisting Untuk Pondasi 2.88 M2 2.88 M2
3 Pekerjaan Beton Kolom(K1)===> 20x20 cm

Pekerjaan Pembuatan Beton Mutu F'C = 21,7 Mpa (K


3,1 0.83 M3 0.83 M3
250)
3,2 Pekerjaan Pembesian 120.35 Kg 120.35 Kg
Pekerjaan Pemasangan Bekisting Untuk Kolom 3x
3,3 16.56 M2 16.56 M2
Pakai
4 Pekerjaan Beton Kolom(Kp)===> 11x11 cm
Pekerjaan Pembuatan Beton Mutu F'C = 21,7 Mpa (K
4,1 0.41 M3 0.41 M3
250)
4,2 Pekerjaan Pembesian 120.13 Kg 120.13 Kg
Pekerjaan Pemasangan Bekisting Untuk Kolom 3x
4,3 14.85 M2 14.85 M2
Pakai
Page 39
NO
NAMA PEKERJAAN
VOLUME SAT VOLUME SAT

5 Pekerjaan Beton Balok(RB1)===> 20x25 cm

Pekerjaan Pembuatan Beton Mutu F'C = 21,7 Mpa (K


5,1 1.49 M3 1.49 M3
250)
5,2 Pekerjaan Pembesian 181.78 Kg 181.78 Kg
Pekerjaan Pemasangan Bekisting Untuk Balok 3x
5,3 14.85 M2 14.85 M2
Pakai
6 Pekerjaan Beton Plat Kanopi t: 12 cm
Pekerjaan Pembuatan Beton Mutu F'C = 21,7 Mpa (K
6,1 2.12 M3 2.12 M3
250)
6,2 Pekerjaan Pembesian 294.68 Kg 294.68 Kg
Pekerjaan Pemasangan Bekisting Untuk Lantai 3x
6,3 19.88 M2 19.88 M2
Pakai
Pekerjaan Pemasangan Water Proofing Coating
6,4 5.52 M2 5.52 M2
3x/Sika
6,5 Pekerjaan Screeding Tebal 3 cm 5.52 M2 5.52 M2

C PEKERJAAN PASANGAN
C.1 PEKERJAAN PASANGAN KERAMIK
Pekerjaan Pemasangan Lantai Keramik Ukuran.30X30
1 14.17 M2 14.17 M2
Cm / Unpolised/Roman
Pekerjaan Pemasangan Keramik Dinding
2 63.56 M2 63.56 M2
Ukuran.30x60 cm//Polised/Roman
3 Pekerjaan Pemasangan Dinding Terawang/Roster 0.52 M2 0.52 M2

C.2 PEKERJAAN PASANGAN DINDING BATA & PLESTERAN


Pekerjaan Pemasangan Batu Merah Tebal 1/2 Bata (1
1 70.86 M2 70.86 M2
Pc : 4 Ps)
2 Pekerjaan Plesteran 1 Pc : 4 Ps Tebal 15 Mm 141.72 M2 141.72 M2
3 Pekerjaan Acian 78.16 M2 78.16 M2

D PEKERJAAN PINTU/JENDELA
1 Pekerjaan Pintu (P2)----> 1 Unit
Pekerjaan Pemasangan Besi Profil/Termasuk
1,1 Pengelasan & Alat Bantu/Cat/Kusen Besi Hollow 60.38 Kg 60.38 Kg
50x100x2,3
Pekerjaan Pemasangan Besi Profil/Termasuk
1,2 Pengelasan & Alat Bantu/Cat/Jalusi Besi Hollow 13.79 Kg 13.79 Kg
30x60x2,3
Pekerjaan Pemasangan Daun Pintu
1,3 3.60 M2 3.60 M2
Alumunium/Spandrel

1,4 Pekerjaan Pemasangan Kunci Tanam Biasa /Deckson 1.00 Buah 1.00 Buah

Pekerjaan Pemasangan Engsel Pintu Kuningan 3 "


1,5 3.00 Buah 3.00 Buah
/Deckson
1,6 Pekerjaan Pemasangan Kunci Slot /Deckson 1.00 Buah 1.00 Buah
2 Pekerjaan Pintu (P3)----> 2 Unit

Pekerjaan Pemasangan Besi Profil/Termasuk


2,1 Pengelasan & Alat Bantu/Cat/Kusen Besi Hollow 51.86 Kg 51.86 Kg
50x100x2,3

Pekerjaan Pemasangan Besi Profil/Termasuk


2,2 Pengelasan & Alat Bantu/Cat/Jalusi Besi Hollow 10.72 Kg 10.72 Kg
30x60x2,3

Pekerjaan Pemasangan Daun Pintu


2,3 2.80 M2 2.80 M2
Alumunium/Spandrel

2,4 Pekerjaan Pemasangan Kunci Tanam Biasa /Deckson 1.00 Buah 1.00 Buah

Pekerjaan Pemasangan Engsel Pintu Kuningan 3 "


2,5 3.00 Buah 3.00 Buah
/Deckson
2,6 Pekerjaan Pemasangan Kunci Slot /Deckson 1.00 Buah 1.00 Buah
Page 40
NO
NAMA PEKERJAAN
VOLUME SAT VOLUME SAT

E PEKERJAAN PENGECATAN
Pekerjaan Pengecatan Cat Tembok Bidang Baru( 1
1 Lapis Plamur, 1 Lapis Cat Dasar, 2 Lapis )Cat 16.70 M2 16.70 M2
Penutup/Jotun/Dak
Pekerjaan Pengecatan Cat Tembok Bidang Baru
2 Weather Sheid (1 Lapis Plamur, 1 Lapis Cat Dasar, 2 22.50 M2 22.50 M2
Lapis) Cat Penutup/Jotun

F PEKERJAAN SANITAIR/PLUMBING
Pekerjaan Pemasangan Pipa PVC Type AW Dia.
1 1.20 M1 1.20 M1
1/2" /Rucika/Air Bersih
Pekerjaan Pemasangan Pipa PVC Type AW Dia.
2 31.30 M1 31.30 M1
3/4" /Rucika/Air Bersih
Pekerjaan Pemasangan Pipa PVC Type AW Dia. 1"
3 21.60 M1 21.60 M1
/Rucika/Distribusi Air Bersih
Pekerjaan Pemasangan Pipa PVC Type AW Dia. 3"
4 20.60 M1 20.60 M1
/Rucika/Air Bekas/Talang Tegak
Pekerjaan Pemasangan Pipa PVC Type AW Dia. 4"
5 7.00 M1 7.00 M1
/Rucika/Air Kotor/Klosed
Pekerjaan Pemasangan Kloset Duduk
6 1.00 Unit 1.00 Unit
/Disabilitas/Lengkap Asesoris/CW705ELNJ/Toto
Pekerjaan Pemasangan Kloset Duduk/Lengkap
7 1.00 Buah 1.00 Buah
Asesoris/CW 420 J/Toto
Pekerjaan Pemasangan Kloset Jongkok Flush/CE
8 1.00 Unit 1.00 Unit
9/Toto
Pekerjaan Pemasangan Urinoir/Lengkap
9 2.00 Unit 2.00 Unit
Asesoris/U57M
Pekerjaan Pemasangan Wastafel/Lengkap Asesoris/L
10 4.00 Unit 4.00 Unit
529 V1/Toto/Out Door/Prokes
Pekerjaan Pemasangan Jet
11 2.00 Set 2.00 Set
Washer/THX20MCRB/Toto
12 Pekerjaan Pemasangan Floor Drain 4"/TX 1 BN/Toto 1.00 Unit 1.00 Unit
Pekerjaan Pemasangan Hand
13 1.00 Unit 1.00 Unit
Drail/Disabilitas/TX3A1/Toto/Disabilitas

Pekerjaan Pemasangan Kran Air


14 3.00 Buah 3.00 Buah
1/2"/T23B13VNb/Toto

G PEKERJAAN ME/LISTRIK
G.1.1 Pekerjaan Instalasi Kabel
Pekerjaan Pemasangan Instalasi Titik Lampu
1 Penerangan Kabel Ukuran 2x2,5(Lengkap Pipa 4.00 Titik 4.00 Titik
Conduit) /Eterna
G.1.2 Pekerjaan Armarture
Pekerjaan Pemasangan Lampu LED 18 Watt(Lengkap
1 4.00 Titik 4.00 Titik
Fitting)/Philips
2 Pekerjaan Pemasangan Saklar Tunggal /Broco 4.00 Buah 4.00 Buah

V PEKERJAAN PAGAR & HALAMAN


A PEKERJAAN PAGAR
Pekerjaan Galian Tanah Biasa( Level 0 s/d
1 7.36 M3 7.36 M3
1m)/Pondasi,Sloof dan Saluran Air
Pekerjaan Pengurugan Pasir Urug/Bawah
2 0.82 M3 0.82 M3
Pondasi,Sloof dan Saluran Air/t: 5 cm
Pekerjaan Lantai Kerja B0-K 60/Bawah Pondasi,Sloof
3 0.82 M3 0.82 M3
dan Saluran Air/t: 5 cm
4 Beton Bertulang Ram/Akses Pintu Masuk
Pekerjaan Pembuatan Beton Mutu Ad 1 Pc : 2 Ps : 3
4,1 1.42 M3 1.42 M3
Krl
Page 41
NO
NAMA PEKERJAAN
VOLUME SAT VOLUME SAT
4,2 Pekerjaan Pembesian 284.00 Kg 284.00 Kg
Pekerjaan Pemasangan Bekisting Untuk Lantai 3x
4,3 9.47 M2 9.47 M2
Pakai
5 Pekerjaan Beton Pondasi(PT2)===>60x60x20cm
Pekerjaan Pembuatan Beton Mutu Ad 1 Pc : 2 Ps : 3
5,1 1.44 M3 1.44 M3
Krl
5,2 Pekerjaan Pembesian 201.60 Kg 201.60 Kg
5,3 Pekerjaan Pemasangan Bekisting Untuk Pondasi 9.60 M2 9.60 M2
6 Pekerjaan Beton Sloof(S1)===>20x25 cm

Pekerjaan Pembuatan Beton Mutu Ad 1 Pc : 2 Ps : 3


6,1 2.32 M3 2.32 M3
Krl
6,2 Pekerjaan Pembesian 283.04 Kg 283.04 Kg

6,3 Pekerjaan Pemasangan Bekisting Untuk Sloof 3x Pakai 23.15 M2 23.15 M2

7 Beton Bertulang Kolom(K1a)====> 20/20 cm


Pekerjaan Pembuatan Beton Mutu Ad 1 Pc : 2 Ps : 3
7,1 2.28 M3 2.28 M3
Krl
7,2 Pekerjaan Pembesian 328.32 Kg 328.32 Kg
Pekerjaan Pemasangan Bekisting Untuk Kolom 3x
7,3 22.80 M2 22.80 M2
Pakai
Pekerjaan Pemasangan Batu Merah Tebal 1/2 Bata (1
8 38.07 M2 38.07 M2
Pc : 4 Ps)
Pekerjaan Plesteran 1 Pc : 4 Ps Tebal 15
9 100.94 M2 100.94 M2
Mm/Termasuk Kolom
10 Pekerjaan Acian/Termasuk Kolom 100.94 M2 100.94 M2
Pekerjaan Plesteran dan Aci Skoning 1Pc : 3Ps Lebar
11 16.00 M1 16.00 M1
10 Cm
Pekerjaan Pemasangan Tralis Pagar /Detail sesuai
12 33.44 M2 33.44 M2
gambar/+Cat
Pekerjaan Pengecatan Cat Tembok Bidang Baru
13 Weather Sheid (1 Lapis Plamur, 1 Lapis Cat Dasar, 2 100.94 M2 100.94 M2
Lapis) Cat Penutup/Jotun
14 Pasang Pintu gerbang sesuai gambar 1.00 unit

B PEKERJAAN HALAMAN

Pekerjaan Pengadaan dan Pemasangan Conblok Tipe


1 181.94 M2 149.94 M2
Veta 8, Warna Abu-abu, tebal 8 cm, K-400 + Abu batu

Pekerjaan Pemasangan Batu Merah Tebal 1 Bata (1 Pc


2 8.40 M2 8.40 M2
: 4 Ps)/Rolag Pohon
Pekerjaan Plesteran 1 Pc : 4 Ps Tebal 15 Mm/Rolag
3 8.40 M2 8.40 M2
Pohon
4 Pekerjaan Acian/Rolag Pohon 8.40 M2 8.40 M2
Pekerjaan Pondasi Sumuran/Sumur
5 7.07 M3 7.07 M3
Resapan/Termasuk Injuk,Pasir,Kerikil,Batu Kali

C PEKERJAAN SUMUR & POMPA


Pekerjaan Pembuatan Sumur Pantek/Lengkap Pipa
1 22.00 M1 22.00 M1
pipa/PVC 1",1.5",4"/Klas AW/RUCIKA
Pekerjaan Pemasangan Pompa /Jet Pump CHJ4-
2 1.00 Set 1.00 Set
40/Groundfose
Pekerjaan Pemasangan Tangki Air( Lengkap Dengan
3 1.00 Set 1.00 Set
Accesories) Kapasitas 1000 Liter/Excel

4 Pasang rumah pompa lengkap tutup dari besi plat 1.00 unit

D PEKERJAAN TIANG BENDERA


1 Pekerjaan Galian Tanah Biasa( Level 0 s/d 1m) 0.15 M3 0.15 M3
Pekerjaan Pembuatan Beton Mutu Ad 1 Pc : 2 Ps : 3
2 0.15 M3 0.15 M3
Krl/Umpak Beton
Page 42
NO
NAMA PEKERJAAN
VOLUME SAT VOLUME SAT
3 Pekerjaan Pemasangan Angkur Besi 6.00 Buah 6.00 Buah
4 Pekerjaan Pemasangan Mur Baut Dia 16 mm 3.00 Buah 3.00 Buah
Pekerjaan Pemasangan Pipa Staeinless Steel 2" t: 1
5 4.00 M1 4.00 M1
mm
Pekerjaan Pemasangan Pipa Staeinless Steel 2.5" t: 1
6 4.00 M1 4.00 M1
mm
Pekerjaan Pemasangan Pipa Staeinless Steel 3" t: 1
7 6.00 M1 6.00 M1
mm

E PEKERJAAN PAPAN NAMA


1 Pekerjaan Galian Tanah Biasa( Level 0 s/d 1m) 0.30 M3 0.30 M3
Pekerjaan Pembuatan Beton Mutu Ad 1 Pc : 2 Ps : 3
2 0.30 M3 0.30 M3
Krl/Umpak Beton
3 Pekerjaan Pemasangan Angkur Besi 4.00 Buah 4.00 Buah

Pekerjaan Pemasangan Besi Profil/Termasuk


4 39.10 Kg 39.10 Kg
Pengelasan & Alat Bantu/Tiang Besi Pipa Dia 1.5 Inch

Pekerjaan Pemasangan Besi Profil/Termasuk


5 43.60 Kg 43.60 Kg
Pengelasan & Alat Bantu/Plat Besi t: 2,3 mm
Pekerjaan Pengecatan Cat Minyak Bidang Baru (1
6 Lapis Plamir, 1 Lapis Cat Dasar, Dan 2 Lapis Cat 4.40 M2 4.40 M2
Penutup)

F PEKERJAAN SEPITANK
1 Pekerjaan Galian Tanah Biasa( Level 0 s/d 2m) 6.75 M3 6.75 M3
Pekerjaan Pemasangan Batu Merah Tebal 1/2 Bata (1
2 14.40 M2 14.40 M2
Pc : 4 Ps)
3 Pekerjaan Plesteran 1 Pc : 4 Ps Tebal 15 Mm 14.40 M2 14.40 M2
4 Pekerjaan Pengurugan Pasir Urug 3.15 M3 3.15 M3
5 Pekerjaan Beton Plat /Besi 1 Lapis
Pekerjaan Pembuatan Beton Mutu Ad 1 Pc : 2 Ps : 3
5,1 0.36 M3 0.36 M3
Krl
5,2 Pekerjaan Pembesian 24.84 Kg 24.84 Kg
Pekerjaan Pemasangan Bekisting Untuk Lantai 3x
5,3 3.96 M2 3.96 M2
Pakai
Pekerjaan Pemasangan Besi Profil/Termasuk
6 16.93 Kg 16.93 Kg
Pengelasan & Alat Bantu/Mainhole
Pekerjaan Pemasangan Septic Tank Biokimia
7 1.00 Set 1.00 Set
Kapasitas 6 M3/Biotech

G PEKERJAAN AKHIR
Pekerjaan Pengadaan Playground Jumbo/ Perosotan
1 1.00 Set
Pabrikan/Indoor/Uk P:2,5 L:0,9 T:1,8 M
Pekerjaan Angkutan Puing/Bekas Bongkaran Sejauh
2 76.85 M3 76.85 M3
10 Km (Dengan Dump Truck)

JUMLAH

RENCANA PROGESS S/D MINGGU INI


REALISASI PROGRESS S/D MINGGU INI
DEVIASI

Mengetahui
SUKU DINAS PENDIDIKAN / Disetujui:
WILAYAH II KOTA ADMISTRASI
JAKARTA PUSAT
ADMISTRASI JAKARTA PUSAT
PEJABAT PENANDATANGANAN KONTRAK (PPK)

HERMAN HERBANDI
NIP. 196711071998021003
Page 43

Anda mungkin juga menyukai