A. PEKERJAAN SIPIL
I. PEKERJAAN PERSIAPAN
Pembersihan lokasi 140,00 m2 - -
Pemasangan Bowplank 42,00 m1 12.526,06 526.094,52
Sub Total 526.094,52
II. PEKERJAAN TANAH & URUGAN
Galian tanah pondasi + septictank 17,90 m3 - -
Urugan Tanah bekas galian 5,37 m3 - -
Sub Total -
III. PEKERJAAN PONDASI
Pasangan batu kali 12,50 m3 577.511,55 7.218.894,38
Pondasi Foot Plat (20x80x80cm) ; K-250 (f'c = 21,7 Mpa) 1,37 m3 2.020.491,18 2.772.113,90
Rolak bata merah m1 47.168,62 -
Sub Total 9.991.008,28
IV. PEKERJAAN BETON
Pedestal Kolom (25 x 25cm) 14,00 m1 82.001,91 1.148.026,74
Sloof (15 x 25cm) 2,40 m3 2.498.870,24 5.997.288,56
Kolom (25 x 25 cm) 84,00 m1 82.001,91 6.888.160,42
Kolom K2 (100 x 200cm) m1 65.601,53 -
Kolom KP (100 x 100cm) m1 49.722,16 -
Balok B1 (250 x 400cm) 16,00 m1 214.852,36 3.437.637,76
Balok B2 (150 x 350cm) m1 161.139,27 -
Balok B3 (150 x 250cm) m1 131.331,60 -
Cor Plat Lantai 2 ; tebal = 12cm 9,12 m3 2.423.181,54 22.099.415,68
Cor Plat Lantai Atap/Dak Toren ; tebal = 12cm m3 1.758.708,86 -
Ringbalk RB1 (120 x 250cm) 64,00 m1 98.941,98 6.332.286,79
Ringbalk Sopi - Sopi (100 x 100cm) m1 49.722,16 -
Plat KANOPI beton tebal 10 cm m2 221.781,73 -
Cor Tangga Beton 3,00 m3 2.199.067,46 6.597.202,37
Sub Total 45.902.815,95
V. PEKERJAAN ATAP
Pasang genteng 168,00 m2 104.250,00 17.514.000,00
Pasang Genteng Nok 30,00 m1 61.313,55 1.839.406,50
Sub Total 19.353.406,50
JUMLAH 337.017.721,460