Anda di halaman 1dari 3

RENCANA ANGGARAN BIAYA (RAB)

HARGA SATUAN
NO URAIAN SATUAN VOLUME JUMLAH HARGA (Rp)
(Rp)

IX FOOD COURT - 15 Unit

A PEKERJAAN TANAH 26,139,187.83


1 Galian tanah sedalam 1 M m3 240.00 61,869.59 14,848,700.42

2 Urugan Pasir bawah pondasi & lantai m3 21.75 179,572.35 3,905,698.56

3 Urugan Tanah Biasa m3 134.40 54,946.35 7,384,788.84

B PEKERJAAN PONDASI 116,990,102.08


1 Pasangan pondasi batu kali 1 Pc : 5 Ps m3 105.60 1,107,860.82 116,990,102.08

C PEKERJAAN PASANGAN DINDING 113,289,043.12


1 Pemasangan dinding HEBEL (Bata ringan) teb. 10 cm m2 720.00 157,345.89 113,289,043.12

D PEKERJAAN PLESTERAN 77,512,488.95


1 Plesteran 1 Pc : 3 Ps tebal 15 mm m2 720.00 67,676.18 48,726,850.25
2 Acian dinding m2 720.00 39,980.05 28,785,638.69

E PEKERJAAN BETON BERTULANG 162,776,157.07


1 Beton bertulang sloof (200 kg +bekisting) m3 9.00 6,392,616.23 57,533,546.10
2 Beton bertulang Kolom (150 kg + bekisting) m3 4.05 7,672,278.04 31,072,726.06
3 Beton bertulang Balok (200 kg besi + bekisting) m3 9.00 8,241,098.32 74,169,884.90
4 Kolom Praktis

F PEKERJAAN LANTAI 143,562,437.84


1 Pasang ubin teraso 40 x 40 cm m2 225.00 208,995.39 47,023,962.06
2 Plat Lantai 1 beton K275 t.30 cm m3 67.50 1,176,753.64 79,430,870.38
3 Wiremesh M8 m2 225.00 76,033.80 17,107,605.40

G PEKERJAAN ATAP 358,349,220.23


1 Pasang atap Aluminium Gelombang m2 359.10 285,192.78 102,412,728.51
2 Pasang nok atap aluminium m2 275.00 210,000.00 57,748,950.00
3 Pasang Langit-langit Gypsum tebal 9 mm m2 225.00 50,625.52 11,390,741.72
4 Rangka besi hollow 1x40.40.2mm, modul 60 x 60 cm, plafon m2 225.00 195,000.00 43,875,000.00
5 Kuda-kuda rangka Atap baja ringan m2 359.10 398,000.00 142,921,800.00
ITEM BARU
Pek. Atap Zinkcalume Berpasir 0,45 mm
Pek. Pipa PVC 4" Texture Motif Bambu
Pek. Kisi Kisi Hollow 4x4 Motif Kayu + Pengecatan
Pek. Realing Hollow + Pengecatan
Pek. Plafond PVC Ex. Sunda
RENCANA ANGGARAN BIAYA (RAB)

HARGA SATUAN
NO URAIAN SATUAN VOLUME JUMLAH HARGA (Rp)
(Rp)
Pek. Pasangan Batu Alam Andesit
Pek. Kalisplank GRC Motif Kayu

H PEKERJAAN DAN PENGGANTUNG PENGUNCI 3,596,614.74


1 Pasang kunci tanam biasa unit 15.00 185,512.22 2,782,683.30
2 Pasang engsel pintu unit 15.00 54,262.10 813,931.45
ITEM BARU
Pek. Pintu P1
Pek. Jendela J1
Pek. Jendela J2

I PEKERJAAN CAT 20,088,000.00


1 Pengecatan bidang Tembok Baru non plamir (vinilex) m2 720.00 27,900.00 20,088,000.00

J PEKERJAAN LAIN LAIN 15,316,166.32


1 Pasang Instalasi Lampu unit 15.00 229,011.92 3,435,178.74
2 Pasang Instalasi Stop Kontak unit 15.00 257,062.48 3,855,937.21
3 Pasang Stop Kontak unit 15.00 71,796.56 1,076,948.37
4 Pasang Saklar tunggal unit 15.00 53,582.30 803,734.50
5 Pasang Lampu V shape 1 x 20 Watt unit 15.00 190,543.40 2,858,151.04
6 Pasang panel MCB unit 15.00 116,421.49 1,746,322.36
7 Pasang Box MCB unit 15.00 102,659.61 1,539,894.10
RENCANA ANGGARAN BIAYA (RAB)

HARGA SATUAN
NO URAIAN SATUAN VOLUME JUMLAH HARGA (Rp)
(Rp)
K PEKERJAAN PIPA DAN SANITASI 107,822,597.41
1 Pasang whastafel unit 15.00 2,369,548.08 35,543,221.15
2 Pasang bak cuci stainless steel unit 15.00 927,176.58 13,907,648.63
3 Pas. Sal. Air Bersih PVC tipe AW Ø 3/4" m 75.00 24,000.00 1,800,000.00
4 Pas. Sal. Air kotor PVC tipe AW Ø 2" m 150.00 52,369.03 7,855,354.20
5 Pas. Sal. Air Limbah PVC tipe AW Ø 3" m 150.00 100,000.00 15,000,000.00
6 Pas. Sal. Air Kotor PVC tipe AW Ø 4" m 150.00 158,311.00 23,746,649.39
7 Pasang kran dia Ø 3/4" unit 15.00 297,959.97 4,469,399.50
8 Pasang Floor Drain unit 15.00 366,688.30 5,500,324.55

TOTAL JUMLAH HARGA FOOD COURT 1,145,442,015.59