REKAPITULASI

BILL OF QUANTITY (BOQ)

PEKERJAAN : BANGUNAN BIG TINGGI 250 cm


LOKASI : PELABUHAN DOBO
TAHUN ANGGARAN : 2023

BOBOT
NO. URAIAN JUMLAH HARGA (Rp.)
FISIK (%)

A PERSIAPAN 500,000.00 1.93%


B BIYAYA K3 KONSTRUKSI 12,562,096.24 48.36%
C PEMBANGUNAN GEDUNG SERVER 7,802,099.45 30.04%
D PEMBANGUNAN KANTIN 1,112,437.33 4.28%
E COVER TAMPAK DEPAN ACP 1,043,765.00 4.02%
F LANDSCAPE 1,406,850.00 5.42%
G A Parkir Mobil 2 Unit 1,246,755.60 4.80%
H B Parkir Motor 1 Unit 300,000.00 1.16%

SUB. TOTAL 25,974,003.62 100.00%


Terbilang : Dua Puluh Lima Juta Sembilan Ratus Tujuh Puluh Empat Ribu Empat Rupiah,-
BILL OF QUANTITY (BOQ)

PEKERJAAN : BANGUNAN BIG TINGGI 250 cm


LOKASI : PELABUHAN DOBO
TAHUN ANGGARAN : 2023

HARGA SATUAN
NO URAIAN PEKERJAAN VOLUME SAT JUMLAH HARGA (Rp)
(Rp)
1 2 3 4 5 6 = (3 x5)

A PEKERJAANPERSIAPAN 500,000.00
1 Listrik dan Air Kerja 1 Ls 500,000.00 500,000.00

B Pekerjaan Beton 12,562,096.24


1 Pek. Kolom 20 x 20 cm
‐ Pek Beton Mutu K.225 0.40 M3 2,168,321.43 867,328.57
‐ Pek Pembesian 29.99 Kg 17,451.00 523,295.46
‐ Pek Begesting Kolom 2x Pakai 8.00 M2 478,020.00 3,824,160.00
2 Pek. Balok 20/20 cm
‐ Pek Beton Mutu K.225 0.35 M3 2,168,321.43 758,912.50
‐ Pek Pembesian 22.13 Kg 17,451.00 386,188.61
‐ Pek Begesting Sloof 2x Pakai 3.50 M2 486,420.00 1,702,470.00
3 Pek. Beton Plat Lantai t= 12 Cm
‐ Pek Beton Mutu K.225 0.60 M3 2,168,321.43 1,291,885.91
‐ Pek Pembesian 46.44 Kg 17,451.00 810,476.79
‐ Pek Begesting Plat lantai 2x Pakai 5.84 M2 410,510.00 2,397,378.40

C Pekerjaan Pasangan Dinding dan Plesteran 7,802,099.45


1 Pek. Pasangan Dinding Batako 16.06 M2 186,888.33 3,001,426.63
2 Pek. Plesteran Dinding dan Beton 37.22 M2 78,206.00 2,910,827.32
2 Pek. Acian Semen 37.22 M2 50,775.00 1,889,845.50

D Pekerjaan Plafound 1,112,437.33


1 Rangka Plafond Hollow 4.40 M2 159,076.67 699,937.33
2 Penutup Plafound 4.40 M2 93,750.00 412,500.00

E Pekerjaan Lantai 1,043,765.00


1 Pek. Pas Keramik Lantai 40 x 40 cm Putih 3.80 M2 274,675.00 1,043,765.00

F Pekerjaan Listrik 1,406,850.00


1 Pek. Instalasi Titik Lampu 5 Bh 122,450.00 612,250.00
3 Pek. Pasang Lampu LED 12 Watt Philips 5 Bh 124,200.00 621,000.00
4 Pek. Pemasangan Stop Kontak 1 Bh 50,000.00 50,000.00
5 Pek. Saklar Tunggal 1 Bh 24,200.00 24,200.00
6 Pek. Saklar Ganda 1 Bh 30,200.00 30,200.00
7 MCB 1 Bh 69,200.00 69,200.00

G Pekerjaan Fhinising 1,246,755.60


1 Pekerjaan Pengecatan Dinding, Kusen Dan Beton 43.92 M2 24,971.67 1,096,755.60
2 Pemasangan Kusen Pintu 1.00 Bh 150,000.00 150,000.00

H PEKERJAAN LAIN‐LAIN 300,000.00


1 Pembersihan akhir 1 Ls 300,000.00 300,000.00