RENCANA ANGGARAN BIAYA (RAB )

PROYEK : TPS & BAK KONTROL


LOKASI : IUP PT. AKM-TAMIYANG PROJECT

I.1 COST OF TPS (5 X 8 Meter) MATERIAL


AMMOUNT
No. DESCRIPTION
QTY UNIT
1 BATAKO 550 PCS
2 PASIR 2 RIT
3 KERIKIL 1 RIT
4 TIANG SUDUT 4 PCS
5 TIANG BANTU dan RANGKA ATAP 76 PCS
6 SENG / ATAP 55 LBR
7 SEMEN 45 SAK
8 KAWAT 52 MTR
9 JASA TUKANG (Borongan) 1
TOTAL COST

I.2 COST OF BAK KONTROL 2 UNT (1,5 X 1 Meter) MATERIAL


AMMOUNT
No. DESCRIPTION
QTY UNIT
1 BATAKO 240 PCS
2 SEMEN 20 SAK
TOTAL COST
PRICE OF ITEM COST AMMOUNT

Rp 4,000 Rp 2,200,000
Rp 800,000 Rp 1,600,000
Rp 1,500,000 Rp 1,500,000
Rp 250,000 Rp 1,000,000
Rp 65,000 Rp 4,940,000
Rp 60,000 Rp 3,300,000
Rp 55,000 Rp 2,475,000
Rp 65,000 Rp 3,380,000
Rp 14,500,000 Rp 14,500,000
Rp 34,895,000

PRICE OF ITEM COST AMMOUNT

Rp 4,000 Rp 960,000
Rp 55,000 Rp 1,100,000
Rp 2,060,000