Anda di halaman 1dari 27

DINAS PEKERJAAN UMUM DAN PENATAAN

RUANG KOTA BENGKULU


JL.Wr Supratman Kota Bengkulu No 38225

INVOICE

PEKERJAAN :
PEK. PERENCANAAN PENINGKATAN/REHAB SARANA DAN
PRASARANA KANTOR SEKRETARIAT PEMKOT. BENGKULU
LOKASI :
KOTA BENGKULU

TAHUN ANGGARAN
2020
REKAPITULASI BIAYA PEKERJAAN

Kegiatan : Perencanaan Peningkatan/ Rehab Sarana dan Prasarana


Pekerjaan : Rehab Gedung Dewan Perwakilan Rakyat (DPR)
Kabupaten : Bengkulu Tengah
T.A : 2021

NO URAIAN PEKERJAN JUMLAH HARGA


1 2 3

I PEKERJAAN PERSIAPAN Rp. 23,878,462.50


II SYSTEM MANAJEMAN KESELAMATAN DAN KESEHATAN KERJA Rp. 10,425,000.00
III PEKERJAAN REHAB BANGUNAN UTAMA
A. Pekerjaan Bongkaran Rp. 67,817,800.00
C. Pekerjaan Atap dan Plafond Rp. 1,691,679,806.92
D. Pekerjaan Elektrikal Rp. 17,375,000.00
E. Pekerjaan Sanitair Rp. 11,638,021.88
F. Pekerjaan Pengecatan Rp. 149,833,395.99

IV PEKERJAAN LAIN - LAIN Rp. 196,983,346.00

(A) JUMLAH HARGA PEKERJAAN Rp . 2,169,630,833.28


(B) PAJAK PERTAMBAHAN NILAI (PPN) 10 % = (A) x 0,10 Rp . 216,963,083.33
(C) JUMLAH TOTAL = (A) + (B) Rp . 2,386,593,916.61
(D) DIBULATKAN Rp . 2,386,593,000.00

TERBILANG : Dua Milyar Tiga Ratus Delapan Puluh Enam Juta Lima Ratus Sembilan Puluh Tiga Ribu Rupiah

Bengkulu, 2021
DIBUAT OLEH :
Pejabat Pelaksanaan Teknis Kegiatan Konsultan Perencana
(PPTK) CV. GRADASI

TMS. BARIMANSYAH, SH RENDIAWAN


NIP. 19630610 199503 1 001 Direktur

Pengguna Anggaran
(PA)

H. MEIZUAR, SH., MM., MH


NIP. 19630831 199303 1 005
ENGINEERING ESTIMATE (EE)
Kegiatan : Perencanaan Peningkatan/ Rehab Sarana dan Prasarana
Pekerjaan : Rehab Gedung Dewan Perwakilan Rakyat (DPR)
Kabupaten : Bengkulu Tengah
T. A : 2021

No. URAIAN PEKERJAAN KODE VOLUME SATUAN HARGA SATUAN TOTAL HARGA

I. PEKERJAAN PERSIAPAN
1 Pek. Pembersihan Lokasi dan Pengukuran Awal Ls 1.00 unit 3,000,000.00 3,000,000.00
2 Pek. Papan Nama Proyek Ls 1.00 unit 500,000.00 500,000.00
3 Pek. Barak Kerja, Gudang dan Direksi Keet A.2.2.1.7 9.00 m2 1,153,162.50 10,378,462.50
4 Pek. Administrasi dan Dokumentasi Ls 1.00 unit 10,000,000.00 10,000,000.00
SUB TOTAL 23,878,462.50
II. SYSTEM MANAJEMAN KESELAMATAN DAN KESEHATAN KERJA
1 Penyiapan RK3K terdiri atas :
a Pembuatan Dokumen Rencana Keselamatan Konstruksi 1.00 Set 1,000,000.00 1,000,000.00

2 Sosialisasi dan Promosi K3 :

3 Alat Pelindung Kerja terdiri atas:


a Alat Pelindung Kerja (APK) antara Lain
2. Tali Keselamatan (Life Line) 4.00 Ls 150,000.00 600,000.00
3. Penahan Jatuh (Safety Deck) 4.00 Ls 90,000.00 360,000.00
6. Pelindung Jatuh (Fall Arrester) 4.00 Ls 120,000.00 480,000.00
b Alat Pelindung Diri (APD) antara lain :
1. Helm Pelindung (Safety Helmet) 10.00 Bh 65,000.00 650,000.00
6. Pelindung Pernapasan dan Mulut (Masker) 10.00 Bh 10,000.00 100,000.00
7. Sarung Tangan (Safety Gloves); 10.00 Psg 8,500.00 85,000.00
12. Rompi Keselamatan (Safety Vest) 10.00 Bh 50,000.00 500,000.00

4 Asuransi Dan Perijinan terdiri atas :


a Asuransi 1.00 Ls 3,000,000.00 3,000,000.00

5 Personil K3 terdiri atas :


c Petugas P3K 1.00 OB 1,000,000.00 1,000,000.00

6 Fasilitas sarana kesehatan :


a Peralatan K3 (Kotak P3K, Obat Luka, Perban) 1.00 Paket 750,000.00 750,000.00

7 Rambu - rambu yang diperlukan


b Rambu Larangan 2.00 Bh 50,000.00 100,000.00
c Rambu Peringatan 2.00 Bh 50,000.00 100,000.00
e Rambu Informasi 2.00 Bh 50,000.00 100,000.00
f Rambu Pekerjaan Sementara 2.00 Bh 50,000.00 100,000.00

8 Konsultasi dengan ahli terkait Keselamatan Konstruksi

9 Lain-lain terkait Pengendalian Resiko K3 :


b Alat Pemadam Api Ringan (APAR); 2.00 Bh 750,000.00 1,500,000.00
SUB TOTAL 10,425,000.00
III. PEKERJAAN REHAB BANGUNAN UTAMA
A. Pekerjaan Bongkaran
1 Pek. Pembongkaran dan Pemasangan Kembali Air Conditioner (AC) Ls 1.00 Paket 10,000,000.00 10,000,000.00
2 Pek. Pembongkaran Plafond + Rangka Ls 2,397.76 m2 10,000.00 23,977,575.00
3 Pek. Pembongkaran Atap + Reng Ls 1,404.02 m2 15,000.00 21,060,225.00
4 Pek. Pembongkaran dan Pemasangan Kembali Instalasi Downlight Ls 213.00 titik 60,000.00 12,780,000.00
Jumlah 67,817,800.00
C. Pekerjaan Atap dan Plafond
1 Pek. Penambahan Reng Baja Ringan Setara TASO A.4.6.1.26 1,404.02 m2 34,746.10 48,784,045.59
2 Pek. Penutup Atap Genteng Metal Setara Multiroof A.4.5.2.33 1,404.02 m2 292,042.50 410,032,050.64
3 Pek. Nok Atap Genteng Metal A.4.5.2.37 213.17 m' 89,872.50 19,157,973.98
4 Pek. Pemasangan Aluminium Foil/Sisalation A.4.5.2.43 1,404.02 m2 67,907.50 95,343,148.61
5 Pek. Listplang GRC A.4.6.1.31 151.90 m' 86,796.25 13,184,350.38
6 Pek. Rangka Plafond Holo A.4.2.1.21 2,623.69 m2 165,715.00 434,784,059.20
7 Pek. Plafond PVC A.4.6.1.20a 2,623.69 m2 202,388.50 531,003,793.06
8 Pek. Assesoris Cutting ACP A.4.5.1.7a 83.20 m2 467,130.00 38,863,908.04
9 Pek. List Profile Plafond PVC A.4.5.1.9a 1,860.08 m' 35,155.50 65,392,042.44
10 Pek. List Polos Plafond PVC A.4.5.1.9b 1,805.66 m' 19,458.00 35,134,434.99
No. URAIAN PEKERJAAN KODE VOLUME SATUAN HARGA SATUAN TOTAL HARGA

Jumlah 1,691,679,806.92
D. Pekerjaan Elektrikal
1 Pek. Penambahan Lampu LED 20 Watt setara panasonic Ls 65.00 titik 75,000.00 4,875,000.00
2 Pek. Pengadaan Pemasangan Mangkok/Kap Downlight Baru Ls 50.00 titik 150,000.00 7,500,000.00
3 Fitting-fitting Ls 1.00 ls 5,000,000.00 5,000,000.00
Jumlah 17,375,000.00
E. Pekerjaan Sanitair
1 Pek. Pemasangan Washtafell Merek Amstad Ls 3.00 bh 2,100,000.00 6,300,000.00
2 Pek. Keran Air Ø1/2" Setara Toto A.5.1.1.19 15.00 bh 155,868.13 2,338,021.88
3 Fitting dan Assesoris Ls 1.00 ls 3,000,000.00 3,000,000.00
Jumlah 11,638,021.88
F. Pekerjaan Pengecatan
1 Pek. Pengecatan Dinding Setara Dulux wheatershield A.4.7.1.11 4,905.86 m2 30,541.70 149,833,395.99
Jumlah 149,833,395.99
SUB TOTAL 1,938,344,024.78
IV PEKERJAAN LAIN - LAIN
1 Pek. Pemasangan Karpet Rool Setara Marina Bay 16RED A.4.4.3.44 383.00 m2 501,262.00 191,983,346.00
2 Pek. Pembersihan Akhir Ls 1.00 unit 5,000,000.00 5,000,000.00
SUB TOTAL 196,983,346.00

JUMLAH TOTAL 2,169,630,833.28

PPN 10% 216,963,083.33

JUMLAH TOTAL + PPN 10% 2,386,593,916.61

DIBULATKAN 2,386,593,000.00

Bengkulu, 2021
DIBUAT OLEH :
KONSULTAN PERENCANA
……………………..

…………………………
Direktur
ANALISA HARGA SATUAN PEKERJAAN SERTA PERHITUNGAN KEBUTUHAN TENAGA
KERJA, BAHAN, DAN PERALATAN
PROVINSI : BENGKULU NAMA PAKET KEGIATAN : PEMBANGUNAN JEMBATAN BETON
KEBUPATEN : BENGKULU UTARA
KECAMATAN : ARGAMAKMUR LOKASI : DUSUN 2
DESA : SENALI TAHUN ANGGARAN : 2020

Jumlah
Kode Analisa Uraian Satuan Koefisien Harga Satuan Jumlah Harga Volume Pekerjaan
Kebutuhan

a b c d e f = (d) x (e) g h = (d) x (g)


PERMEN PU : 1m2 (K3) Pembersihan lapangan dan perataan
28 /PRT/M/2016 Pekerja HOK 0.10 100,000.00 Rp 10,000.00 0.000 -
A.2.2.1.9
Mandor HOK 0.05 120,000.00 Rp 6,000.00 0.000 -
PERMEN PU : 1 m3 Menggali tanah lumpur sedalam 1 m
28 /PRT/M/2016 Pekerja HOK 1.200 #REF! #REF! Err:509 Err:509
A.2.3.1.6
Mandor HOK 0.045 Rp 120,000.00 Rp 5,400.00 Err:509 Err:509
PERMEN PU : 1 m3 Pengurugan Kembali Galian Tanah
28 /PRT/M/2016 Pekerja HOK 0.500 #REF! #REF! Err:509 Err:509
A.2.3.1.9
Mandor HOK 0.050 Rp 120,000.00 Rp 6,000.00 Err:509 Err:509
PERMEN PU : 1 m3 Pemasangan Pondasi Batu Kali camp. 1sm : 3ps
28 /PRT/M/2016 Pekerja HOK 1.500 #REF! #REF! Err:509 Err:509
A.3.2.1.1
Tukang HOK 0.750 Rp 110,000.00 Rp 82,500.00 Err:509 Err:509
Kepala Tukang HOK 0.075 Rp 120,000.00 Rp 9,000.00 Err:509 Err:509
Mandor HOK 0.075 Rp 120,000.00 Rp 9,000.00 Err:509 Err:509
Batu kali m3 1.200 #REF! #REF! Err:509 Err:509
Semen zak 4.040 #REF! #REF! Err:509 Err:509
Pasir pasang m3 0.485 #REF! #REF! Err:509 Err:509
PERMEN PU : 1 m3 Pengurugan pasir
28 /PRT/M/2016 Pekerja HOK 0.300 #REF! #REF! Err:509 Err:509
A.2.3.1.11
Mandor HOK 0.010 Rp 120,000.00 Rp 1,200.00 Err:509 Err:509
Pasir pasang m3 1.200 #REF! #REF! Err:509 Err:509
PERMEN PU : 1 m3 Membuat beton mutu f’c = 12,2 Mpa = K - 150 (1 : 2,4 : 3,2)
28 /PRT/M/2016 Pekerja HOK 1.650 #REF! #REF! Err:509 Err:509
A.4.1.1.3
Tukang HOK 0.275 Rp 110,000.00 Rp 30,250.00 Err:509 Err:509
Kepala Tukang HOK 0.028 Rp 120,000.00 Rp 3,360.00 Err:509 Err:509
Mandor HOK 0.083 Rp 120,000.00 Rp 9,960.00 Err:509 Err:509
Semen zak 5.980 #REF! #REF! Err:509 Err:509
Pasir pasang m3 0.571 #REF! #REF! Err:509 Err:509
Koral m3 0.753 #REF! #REF! Err:509 Err:509
Air liter 215.000 Rp 32.00 Rp 6,880.00 Err:509 Err:509
PERMEN PU : 1 m3 Membuat beton mutu f’c = 14,5 MPa (K 175), slump (12 ± 2) cm, w/c = 0,66 (setara beton 1sm : 2ps : 3kr)
28 /PRT/M/2016 Pekerja HOK 1.650 #REF! #REF! Err:509 Err:509
A.4.1.1.5
Tukang HOK 0.275 Rp 110,000.00 Rp 30,250.00 Err:509 Err:509
Kepala Tukang HOK 0.028 Rp 120,000.00 Rp 3,360.00 Err:509 Err:509
Mandor HOK 0.083 Rp 120,000.00 Rp 9,960.00 Err:509 Err:509
Semen zak 6.520 #REF! #REF! Err:509 Err:509
B.03.b Pasir pasang m3 0.543 #REF! #REF! Err:509 Err:509
Koral m3 0.762 #REF! #REF! Err:509 Err:509
Molen / Concrete Mixer 0,3 m3 Hr 0.250 Rp 300,000.00 Rp 75,000.00 Err:509 Err:509
Air liter 215.000 Rp 32.00 Rp 6,880.00 Err:509 Err:509
PERMEN PU : 1 m3 Membuat 1 m3 beton mutu f’c = 24,0 Mpa = K - 275 (1 : 1,5 : 2,3)
28 /PRT/M/2016 Pekerja HOK 1.650 #REF! #REF! Err:509 Err:509
A.4.1.1.9
Tukang HOK 0.275 Rp 110,000.00 Rp 30,250.00 Err:509 Err:509
Kepala Tukang HOK 0.028 Rp 120,000.00 Rp 3,360.00 Err:509 Err:509
Mandor HOK 0.083 Rp 120,000.00 Rp 9,960.00 Err:509 Err:509
B.03.b Semen zak 8.120 #REF! #REF! Err:509 Err:509
Pasir pasang m3 0.489 #REF! #REF! Err:509 Err:509

HALAMAN 5
Jumlah
Kode Analisa Uraian Satuan Koefisien Harga Satuan Jumlah Harga Volume Pekerjaan
Kebutuhan

a b c d e f = (d) x (e) g h = (d) x (g)


Batu Pecah m3 0.760 #REF! #REF! Err:509 Err:509
Molen / Concrete Mixer 0,3 m3 Hr 0.250 Rp 300,000.00 Rp 75,000.00 Err:509 Err:509
Air liter 215.000 Rp 32.00 Rp 6,880.00 Err:509 Err:509
PERMEN PU : 1 kg Pembesian dengan besi polos atau besi ulir
28 /PRT/M/2016 Pekerja HOK 0.00700 #REF! #REF! Err:509 Err:509
A.4.1.1.17
Tukang HOK 0.00700 Rp 110,000.00 Rp 770.00 Err:509 Err:509
Kepala Tukang HOK 0.00070 Rp 120,000.00 Rp 84.00 Err:509 Err:509
Mandor HOK 0.00035 Rp 120,000.00 Rp 42.00 Err:509 Err:509
Besi Beton Ulir D13 kg 1.00500 #REF! #REF! Err:509 Err:509
Kawat beton glg 0.01875 Rp 28,000.00 Rp 525.00 Err:509 Err:509
PERMEN PU : 1 kg Pembesian dengan besi polos atau besi ulir
28 /PRT/M/2016 Pekerja HOK 0.00700 #REF! #REF! Err:509 Err:509
A.4.1.1.17
Tukang HOK 0.00700 Rp 110,000.00 Rp 770.00 Err:509 Err:509
Kepala Tukang HOK 0.00070 Rp 120,000.00 Rp 84.00 Err:509 Err:509
Mandor HOK 0.00035 Rp 120,000.00 Rp 42.00 Err:509 Err:509
Besi Beton Ulir D10 kg 1.00500 #REF! #REF! Err:509 Err:509
Kawat beton glg 0.01875 Rp 28,000.00 Rp 525.00 Err:509 Err:509
PERMEN PU : 1 kg Pembesian dengan besi polos atau besi ulir
28 /PRT/M/2016 Pekerja HOK 0.00700 Rp 120,000.00 Rp 840.00 Err:509 Err:509
A.4.1.1.17
Tukang HOK 0.00700 Rp 110,000.00 Rp 770.00 Err:509 Err:509
Kepala Tukang HOK 0.00070 Rp 120,000.00 Rp 84.00 Err:509 Err:509
Mandor HOK 0.00035 Rp 120,000.00 Rp 42.00 Err:509 Err:509
Besi Beton Polos Ø10 kg 1.00500 #REF! #REF! Err:509 Err:509
Kawat beton glg 0.01875 Rp 28,000.00 Rp 525.00 Err:509 Err:509
PERMEN PU : 1 kg Pembesian dengan besi polos atau besi ulir
28 /PRT/M/2016 Pekerja HOK 0.00700 #REF! #REF! Err:509 Err:509
A.4.1.1.17
Tukang HOK 0.00700 Rp 110,000.00 Rp 770.00 Err:509 Err:509
Kepala Tukang HOK 0.00070 Rp 120,000.00 Rp 84.00 Err:509 Err:509
Mandor HOK 0.00035 Rp 120,000.00 Rp 42.00 Err:509 Err:509
Besi Beton Polos Ø8 kg 1.00500 #REF! #REF! Err:509 Err:509
Kawat beton glg 0.01875 Rp 28,000.00 Rp 525.00 Err:509 Err:509
PERMEN PU : 1 m2 Pemasangan bekisting untuk pondasi
28 /PRT/M/2016 Pekerja HOK 0.520 #REF! #REF! Err:509 Err:509
A.4.1.1.20
Tukang HOK 0.260 Rp 110,000.00 Rp 28,600.00 Err:509 Err:509
Kepala Tukang HOK 0.026 Rp 120,000.00 Rp 3,120.00 Err:509 Err:509
Mandor HOK 0.026 Rp 120,000.00 Rp 3,120.00 Err:509 Err:509
Kayu Kelas III m3 0.040 Rp 2,000,000.00 Rp 80,000.00 Err:509 Err:509
Paku kg 0.300 Rp 28,000.00 Rp 8,400.00 Err:509 Err:509
Minyak Bekisting (oli bekas) liter 0.100 Rp 2,000.00 Rp 200.00 Err:509 Err:509

HALAMAN 6
Jumlah
Kode Analisa Uraian Satuan Koefisien Harga Satuan Jumlah Harga Volume Pekerjaan
Kebutuhan

a b c d e f = (d) x (e) g h = (d) x (g)


PERMEN PU : 1 m2 Pemasangan bekisting untuk Kolom
28 /PRT/M/2016 Pekerja HOK 0.660 Rp 100,000.00 Rp 66,000.00 Err:509 Err:509
A.4.1.1.22
Tukang HOK 0.330 Rp 110,000.00 Rp 36,300.00 Err:509 Err:509
Kepala Tukang HOK 0.033 Rp 120,000.00 Rp 3,960.00 Err:509 Err:509
Mandor HOK 0.033 Rp 120,000.00 Rp 3,960.00 Err:509 Err:509
Kayu Kelas III m3 0.040 Rp 2,000,000.00 Rp 80,000.00 Err:509 Err:509
Paku kg 0.400 Rp 28,000.00 Rp 11,200.00 Err:509 Err:509
Minyak Bekisting (oli bekas) liter 0.200 Rp 2,000.00 Rp 400.00 Err:509 Err:509
Kayu Balok 5/7 m3 0.015 Rp 2,000,000.00 Rp 30,000.00 Err:509 Err:509
Triplek 3 mm keping 0.350 #REF! #REF! Err:509 Err:509
Dolken Ø (8-10) cm panjang 4 m batang 2.000 Rp 7,000.00 Rp 14,000.00 Err:509 Err:509
PERMEN PU : 1 m2 Pemasangan bekisting untuk plat lantai
28 /PRT/M/2016 Pekerja HOK 0.660 #REF! #REF! Err:509 Err:509
A.4.1.1.24
Tukang HOK 0.330 Rp 110,000.00 Rp 36,300.00 Err:509 Err:509
Kepala Tukang HOK 0.033 Rp 120,000.00 Rp 3,960.00 Err:509 Err:509
Mandor HOK 0.033 Rp 120,000.00 Rp 3,960.00 Err:509 Err:509
Kayu Papan 2/20 m3 0.040 #REF! #REF! Err:509 Err:509
Paku kg 0.400 #REF! #REF! Err:509 Err:509
Minyak Bekisting (oli bekas) liter 0.200 Rp 2,000.00 Rp 400.00 Err:509 Err:509
Kayu Balok 5/7 m3 0.015 #REF! #REF! Err:509 Err:509
Triplek 3 mm keping 0.350 #REF! #REF! Err:509 Err:509
Dolken Ø (8-10) cm panjang 4 m batang 6.000 #REF! #REF! Err:509 Err:509
PERMEN PU : 1 m2 Pemasangan plesteran 1sm : 3ps; tebal 20 mm
28 /PRT/M/2016 Pekerja HOK 0.260 #REF! #REF! Err:509 Err:509
A.4.4.2.14
Tukang HOK 0.200 Rp 110,000.00 Rp 22,000.00 Err:509 Err:509
Kepala Tukang HOK 0.020 Rp 120,000.00 Rp 2,400.00 Err:509 Err:509
Mandor HOK 0.013 Rp 120,000.00 Rp 1,560.00 Err:509 Err:509
Semen zak 0.207 #REF! #REF! Err:509 Err:509
Pasir pasang m3 0.031 #REF! #REF! Err:509 Err:509
PERMEN PU : 1 m2 Pemasangan acian
28 /PRT/M/2016 Pekerja HOK 0.200 #REF! #REF! Err:509 Err:509
A.4.4.2.27
Tukang HOK 0.100 Rp 110,000.00 Rp 11,000.00 Err:509 Err:509
Kepala Tukang HOK 0.010 Rp 120,000.00 Rp 1,200.00 Err:509 Err:509
Mandor HOK 0.010 Rp 120,000.00 Rp 1,200.00 Err:509 Err:509
Semen zak 0.065 #REF! #REF! Err:509 Err:509
PERMEN PU : 1 m2 Pengecatan permukaan Besi dengan menie besi
28 /PRT/M/2016 Pekerja HOK 0.020 #REF! #REF! Err:509 Err:509
A.4.7.1.16
Tukang HOK 0.200 Rp 110,000.00 Rp 22,000.00 Err:509 Err:509
Kepala Tukang HOK 0.020 Rp 120,000.00 Rp 2,400.00 Err:509 Err:509
Mandor HOK 0.003 Rp 120,000.00 Rp 300.00 Err:509 Err:509
Menie Besi kg 0.100 #REF! #REF! Err:509 Err:509
LS 1 LS Pengadaan Peralatan Kerja
Papan Proyek Banner buah 1.000 Rp 350,000.00 Rp 350,000.00 1.000 1.000
Benang Nilon roll 2.000 #REF! #REF! 1.000 2.000
Sendok Semen buah 3.000 #REF! #REF! 1.000 3.000
Sekop buah 2.000 #REF! #REF! 1.000 2.000
Cangkul buah 2.000 #REF! #REF! 1.000 2.000
Ember Adukan buah 5.000 Rp 25,000.00 Rp 125,000.00 1.000 5.000
Kuas 2" buah 2.000 #REF! #REF! 1.000 2.000
LS 1 LS Mobilisasi dan Demobilisasi
Mobilisasi Molen / Concrete Mixer Kali 1.000 #REF! #REF! 1.000 1.000
Demobilisasi Molen / Concrete Mixer Kali 1.000 #REF! #REF! 1.000 1.000

REKAPITULASI KEBUTUHAN UPAH, BAHAN DAN PERALATAN

HALAMAN 7
Jumlah
Kode Analisa Uraian Satuan Koefisien Harga Satuan Jumlah Harga Volume Pekerjaan
Kebutuhan

a b c d e f = (d) x (e) g h = (d) x (g)

Bahan / Material Batu kali m3 Err:509 Err:509


Koral m3 Err:509 Err:509
Batu Pecah m3 Err:509 Err:509
Dolken Ø (8-10) cm panjang 4 m batang Err:509 Err:509
Kawat beton glg Err:509 Err:509
Kayu Papan 2/20 m3 Err:509 Err:509
Kayu Balok 5/7 m3 Err:509 Err:509
Paku kg Err:509 Err:509
Pasir pasang m3 Err:509 Err:509
Semen zak Err:509 Err:509
Triplek 3 mm keping Err:509 Err:509
Besi Beton Ulir D13 btg Err:509 Err:509
Besi Beton Ulir D10 btg Err:509 Err:509
Besi Beton Polos Ø10 btg Err:509 Err:509
Besi Beton Polos Ø8 btg Err:509 Err:509
Air liter Err:509 Err:509
Minyak Bekisting (oli bekas) liter Err:509 Err:509
Kayu Kelas III m3 Err:509 Err:509
Menie Besi kg Err:509 Err:509
Pipa Besi Ø2,5" Tebal 3,2 mm P.6m btg 4.000 4.00
Pipa PVC Ø3/4" x 4 m btg 8.000 8.00
Molen / Concrete Mixer 0,3 m3 Hr Err:509 Err:509

Peralatan Kerja Papan Proyek Banner buah 1.000 1.00


Benang Nilon roll 2.000 2.00
Sendok Semen buah 3.000 3.00
Sekop buah 2.000 2.00
Cangkul buah 2.000 2.00
Ember Adukan buah 5.000 5.00
Kuas 2" buah 2.000 2.00

Upah Konstruksi Pekerja HOK Err:509 Err:509


Tukang HOK Err:509 Err:509
Mandor HOK Err:509 Err:509
Kepala Tukang HOK Err:509 Err:509

HALAMAN 8
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

Kegiatan : Perencanaan Peningkatan/ Rehab Sarana dan Prasarana


Pekerjaan : Rehab Gedung Dewan Perwakilan Rakyat (DPR)
Kabupaten : Bengkulu Tengah
T.A : 2021

A.2.2.1.7 Pembuatan 1 m2 gudang semen dan peralatan


No Uraian Kode Satuan Koefisien Harga Satuan
A Tenaga Kerja
Pekerja L.01 OH 1.00 Rp 110,000.00
Tukang kayu L.02 OH 2.00 Rp 120,000.00
Kepala tukang L.03 OH 0.20 Rp 140,000.00
Mandor L.04 OH 0.05 Rp 150,000.00
Jumlah Harga Tenaga Kerja
B Bahan
Dolken kayu O (8-10) cm,pnj 4m Batang 1.70 Rp 10,000.00
Kayu m3 0.210 Rp 2,200,000.00
Paku biasa kg 0.300 Rp 10,000.00
Semen Portlan kg 10.50 Rp 1,300.00
Pasir Beton m3 0.03 Rp 220,000.00
Batu pecah/split stone crusher m3 0.05 Rp 380,000.00
Seng gelombang lbr 1.50 Rp 54,000.00
Seng plat lbr 0.250 Rp 60,000.00
Jumlah Harga Bahan
C Peralatan
Jumlah Harga Peralatan
D Jumlah (A+B+C)
E Overhead + Profit 15% x D
F Harga Satuan Pekerjaan (D+E)

A.4.2.1.21 Pemasangan 1 m2 rangka besi hollow 1x40.40.2 mm, modul 60x60 cm, plafon
No Uraian Kode Satuan Koefisien Harga Satuan
A Tenaga Kerja
Pekerja L.01 OH 0.350 Rp 110,000.00
Tukang besi L.03 OH 0.350 Rp 120,000.00
Kepala tukang L.03 OH 0.035 Rp 140,000.00
Mandor L.04 OH 0.018 Rp 150,000.00
Jumlah Harga Tenaga Kerja
B Bahan
Rangka metal holow 40.40.2,5 mm m1 4.000 Rp 7,000.00
assesoris (perkuatan,las dll) ls 100% rangka Rp 7,000.00
Jumlah Harga Bahan
C Peralatan

Jumlah Harga Peralatan


D Jumlah (A+B+C)
E Overhead + Profit 15% x D
F Harga Satuan Pekerjaan (D+E)

A.4.6.1.20a Pemasangan 1 m² Plafond PVC


No Uraian Kode Satuan Koefisien Harga Satuan
A Tenaga Kerja
Pekerja L.01 OH 0.100 Rp 110,000.00
Tukang Plafond L.02 OH 0.250 Rp 120,000.00
Kepala tukang L.03 OH 0.050 Rp 140,000.00
Mandor L.04 OH 0.005 Rp 150,000.00
Jumlah Harga Tenaga Kerja
B Bahan
PVC Strip 0,8 mm x 20 cm m1 5.000 Rp 25,000.00
Paku Skrup Kg 0.020 Rp 112,000.00
Jumlah Harga Bahan
C Peralatan

Jumlah Harga Peralatan


D Jumlah (A+B+C)
E Overhead + Profit 15% x D
F Harga Satuan Pekerjaan (D+E)
A.4.5.1.7a Pemasangan 1 m² Plafond Alumunium Composit Panel (ACP)
No Uraian Kode Satuan Koefisien Harga Satuan
A Tenaga Kerja
Pekerja L.01 OH 0.100 Rp 110,000.00
Tukang Plafond L.02 OH 0.050 Rp 120,000.00
Kepala tukang L.03 OH 0.005 Rp 140,000.00
Mandor L.04 OH 0.005 Rp 150,000.00
Jumlah Harga Tenaga Kerja
B Bahan
Alumunium Composit Panel (ACP) m1 1.100 Rp 350,000.00
Paku Skrup Kg 0.110 Rp 25,000.00
Jumlah Harga Bahan
C Peralatan

Jumlah Harga Peralatan


D Jumlah (A+B+C)
E Overhead + Profit 15% x D
F Harga Satuan Pekerjaan (D+E)

A.4.5.2.37 Pemasangan 1 m' nok genteng metal


No Uraian Kode Satuan Koefisien Harga Satuan
A Tenaga Kerja
Pekerja L.01 OH 0.250 Rp 110,000.00
Tukang kayu L.03 OH 0.150 Rp 120,000.00
Kepala tukang L.11 OH 0.015 Rp 140,000.00
Mandor L.15 OH 0.013 Rp 150,000.00
Jumlah Harga Tenaga Kerja
B Bahan
Nok genteng metal bh 1.100 Rp 25,000.00
Paku biasa 1/2"-1" kg 0.05 Rp 22,000.00
Jumlah Harga Bahan
C Peralatan

Jumlah Harga Peralatan


D Jumlah (A+B+C)
E Overhead + Profit 15% x D
F Harga Satuan Pekerjaan (D+E)

A.4.6.1.31 Pemasangan 1 m' lisplank GRC


No Uraian Kode Satuan Koefisien Harga Satuan
A Tenaga Kerja
Pekerja L.01 OH 0.100 Rp 110,000.00
Tukang kayu L.03 OH 0.200 Rp 120,000.00
Kepala tukang L.03 OH 0.020 Rp 140,000.00
Mandor L.04 OH 0.005 Rp 150,000.00
Jumlah Harga Tenaga Kerja
B Bahan
Papan GRC m 1.0500 Rp 24,500.00
Paku Skrup kg 0.100 Rp 112,000.00
Jumlah Harga Bahan
C Peralatan

Jumlah Harga Peralatan


D Jumlah (A+B+C)
E Overhead + Profit 15% x D
F Harga Satuan Pekerjaan (D+E)

A.4.7.1.11 Pengecatan 1 m2 tembok lama (1 lapis cat dasar, 2 lapis cat Penutup)
No Uraian Kode Satuan Koefisien Harga Satuan
A Tenaga Kerja
Pekerja L.01 OH 0.028 Rp 110,000.00
Tukang cat L.02 OH 0.042 Rp 120,000.00
Kepala tukang L.03 OH 0.0042 Rp 140,000.00
Mandor L.04 OH 0.003 Rp 150,000.00
Jumlah Harga Tenaga Kerja
B Bahan
Cat dasar kg 0.12 Rp 58,000.00
Cat penutup kg 0.18 Rp 58,000.00
Jumlah Harga Bahan
C Peralatan

Jumlah Harga Peralatan


D Jumlah (A+B+C)
E Overhead + Profit 15% x D
F Harga Satuan Pekerjaan (D+E)
A.5.1.1.19 Pemasangan 1 buah kran diameter ½” atau ¾ ”
No Uraian Kode Satuan Koefisien Harga Satuan
A Tenaga Kerja
Pekerja L.01 OH 0.010 Rp 110,000.00
Tukang batu L.02 OH 0.400 Rp 120,000.00
Kepala tukang L.03 OH 0.040 Rp 140,000.00
Mandor L.04 OH 0.005 Rp 150,000.00
Jumlah Harga Tenaga Kerja
B Bahan
Kran air diameter 1/2" m 1.00 Rp 80,000.00
Sealtape buah 0.025 Rp 3,500.00
Jumlah Harga Bahan
C Peralatan

Jumlah Harga Peralatan


D Jumlah (A+B+C)
E Overhead + Profit 15% x D
F Harga Satuan Pekerjaan (D+E)

A.4.4.3.44 Pemasangan 1 m2 Karpet


No Uraian Kode Satuan Koefisien Harga Satuan
A Tenaga Kerja
Pekerja L.01 OH 0.170 Rp 110,000.00
Tukang L.02 OH 0.170 Rp 120,000.00
Kepala tukang L.03 OH 0.0170 Rp 140,000.00
Mandor L.04 OH 0.009 Rp 150,000.00
Jumlah Harga Tenaga Kerja
B Bahan
Karpet Roll Marina Bay m2 1.05 Rp 320,000.00
Lem kg 0.35 Rp 88,000.00
Underlayers m2 1.05 Rp 25,000.00
Jumlah Harga Bahan
C Peralatan

Jumlah Harga Peralatan


D Jumlah (A+B+C)
E Overhead + Profit 15% x D
F Harga Satuan Pekerjaan (D+E)

A.4.6.1.26 Pemasangan 1 m² Kuda-kuda baja ringan + reng


No Uraian Kode Satuan Koefisien Harga Satuan
A Tenaga Kerja
Pekerja L.01 OH 0.033 Rp 110,000.00
Tukang Besi L.03 OH 0.075 Rp 120,000.00
Kepala Tukang L.11 OH 0.002 Rp 140,000.00
Mandor L.15 OH 0.008 Rp 150,000.00
Jumlah Harga Tenaga Kerja
B Bahan
Rangka Baja C.75.75 m 1.481 Rp -
Baut Sekrup bh 14.000 Rp 300.00
Dynabolt bh 1.600 Rp -
Reng Baja Ringan m 0.559 Rp 18,000.00
Jumlah Harga Bahan
C Peralatan
% 10 Rp 18,000.00
Jumlah Harga Peralatan
D Jumlah (A+B+C)
E Overhead + Profit 15% x D
F Harga Satuan Pekerjaan (D+E)

A.4.5.2.33 Pemasangan 1 m2 Genteng Metal Atap Jurai


No Uraian Kode Satuan Koefisien Harga Satuan
A Tenaga Kerja
Pekerja L.01 OH 0.200 Rp 110,000.00
Tukang Seng L.03 OH 0.100 Rp 120,000.00
Kepala tukang L.03 OH 0.010 Rp 140,000.00
Mandor L.04 OH 0.001 Rp 150,000.00
Jumlah Harga Tenaga Kerja
B Bahan
Genteng Metal buah 2.000 Rp 98,000.00
Paku Skrup kg 0.200 Rp 112,000.00
Jumlah Harga Bahan
C Peralatan

Jumlah Harga Peralatan


D Jumlah (A+B+C)
E Overhead + Profit 15% x D
F Harga Satuan Pekerjaan (D+E)
A.4.5.2.43 Pemasangan 1 m2 Aluminium Foil/Sisalation
No Uraian Kode Satuan Koefisien Harga Satuan
A Tenaga Kerja
Pekerja L.01 OH 0.150 Rp 110,000.00
Tukang Atap L.03 OH 0.050 Rp 120,000.00
Kepala tukang L.03 OH 0.005 Rp 140,000.00
Mandor L.04 OH 0.008 Rp 150,000.00
Jumlah Harga Tenaga Kerja
B Bahan
Aluminium Foil m2 1.050 Rp 33,000.00
Jumlah Harga Bahan
C Peralatan

Jumlah Harga Peralatan


D Jumlah (A+B+C)
E Overhead + Profit 15% x D
F Harga Satuan Pekerjaan (D+E)

A.4.5.1.9a Pemasangan 1 m' List Profile Plafond PVC


No Uraian Kode Satuan Koefisien Harga Satuan
A Tenaga Kerja
Pekerja L.01 OH 0.050 Rp 110,000.00
Tukang PVC L.03 OH 0.050 Rp 120,000.00
Kepala tukang L.03 OH 0.005 Rp 140,000.00
Mandor L.04 OH 0.003 Rp 150,000.00
Jumlah Harga Tenaga Kerja
B Bahan
PVC List Profile m1 1.050 Rp 16,000.00
Paku Skrup kg 0.010 Rp 112,000.00
Jumlah Harga Bahan
C Peralatan

Jumlah Harga Peralatan


D Jumlah (A+B+C)
E Overhead + Profit 15% x D
F Harga Satuan Pekerjaan (D+E)

A.4.5.1.9b Pemasangan 1 m' List Polos Plafond PVC


No Uraian Kode Satuan Koefisien Harga Satuan
A Tenaga Kerja
Pekerja L.01 OH 0.050 Rp 110,000.00
Tukang PVC L.03 OH 0.050 Rp 120,000.00
Kepala tukang L.03 OH 0.005 Rp 140,000.00
Mandor L.04 OH 0.003 Rp 150,000.00
Jumlah Harga Tenaga Kerja
B Bahan
PVC List Polos m1 1.050 Rp 3,000.00
Paku Skrup kg 0.010 Rp 112,000.00
Jumlah Harga Bahan
C Peralatan

Jumlah Harga Peralatan


D Jumlah (A+B+C)
E Overhead + Profit 15% x D
F Harga Satuan Pekerjaan (D+E)
PERHITUNGAN KUANTITAS / VOLUME
Kegiatan : Perencanaan Peningkatan/ Rehab Sarana dan Prasarana
Pekerjaan : Rehab Gedung Dewan Perwakilan Rakyat (DPR)
Kabupaten : Bengkulu Tengah
T. A : 2021

1. Pekerjaan Bongkaran Plafond dan Rangka


Lantai 1 Panjang Lebar
Teras = 12.80 x 10.90 = 139.52 m2
Sayap Teras 1 = 9.30 x 4.20 = 39.06 m2
Sayap Teras 2 = 9.30 x 4.20 = 39.06 m2
Lobby = 15.00 x 6.25 = 93.75 m2
R. Komisi II = 10.90 x 7.50 = 81.75 m2
R. Fraksi Hanura = 5.35 x 4.50 = 24.08 m2
R. Fraksi Perindo = 5.35 x 6.10 = 32.64 m2
Gudang = 5.35 x 6.20 = 33.17 m2
Area WC 1 = 5.35 x 4.40 = 23.54 m2
Dapur = 5.35 x 2.85 = 15.25 m2
R. Badan Kehormatan = 5.35 x 4.60 = 24.61 m2
R. Fraksi P3 = 5.35 x 5.10 = 27.29 m2
R. Fraksi Nasdem = 6.10 x 5.60 = 34.16 m2
R. Propem Perda = 7.30 x 6.00 = 43.80 m2
Free Funchtion = 12.50 x 6.10 = 76.25 m2
R. Komisi III = 13.00 x 6.10 = 79.30 m2
R. Fraksi Golkar = 6.10 x 5.35 = 32.64 m2
R. Fraksi Gerindra = 6.10 x 5.35 = 32.64 m2
R. Fraksi PDI = 6.10 x 5.50 = 33.55 m2
R. Dharma Wanita = 5.35 x 6.00 = 32.10 m2
R. Istirahat Komisi I = 5.35 x 6.00 = 32.10 m2
R. Komisi I = 5.60 x 12.20 = 68.32 m2
Selasar 1 = 24.50 x 3.50 = 85.75 m2
Selasar 2 = 24.50 x 3.50 = 85.75 m2
Lantai 2 =
R. Bukit Kandis = 12.50 x 10.70 = 133.75 m2
Atas Tangga = 12.55 x 5.30 = 66.52 m2
R. Tunggu Rapat = 6.35 x 5.10 = 32.39 m2
R. Waka II = 10.70 x 5.80 = 62.06 m2
WC Waka I = 5.80 x 2.80 = 16.24 m2
R. Waka I = 9.10 x 5.80 = 52.78 m2
R. Sidang Pleno = 20.20 x 19.00 = 383.80 m2
Pinggir Sidang Pleno = 6.30 x 5.60 = 35.28 m2
R. Tim Pakar + WC = 5.80 x 4.50 = 26.10 m2
R. Tunggu Ketua = 6.00 x 5.80 = 34.80 m2
R. Ketua = 9.10 x 5.80 = 52.78 m2
PERHITUNGAN KUANTITAS / VOLUME
R. Istirahat Ketua = 4.20 x 2.80 = 11.76 m2
Wc Ketua = 4.30 x 1.35 = 5.81 m2
Selasar 1 = 21.55 x 2.40 = 51.72 m2
Selasar 2 = 6.50 x 1.30 = 8.45 m2
Selasar 3 = 10.70 x 3.45 = 36.92 m2
Selasar 4 = 6.50 x 1.30 = 8.45 m2
Selasar 5 = 10.70 x 3.45 = 36.92 m2
Keliling Luar Bangunan = 164.00 x 0.80 = 131.20 m2 +
Luas Total Bongkaran Plafond + Rangka = 2,397.76 m2

2. Pekerjaan Bongkaran Atap + Reng


Area 1
1/2 Lebar bawah = 7.25 m
Tinggi = 9.00 m
Jumlah Sisi = 1.00 bh
Luas = 7.25 x 9.00 x 1.00 = 65.25 m2
Area 2
Lebar (bawah+Atas) /2 = 8.75 m
Tinggi = 9.00 m
Jumlah Sisi = 2.00 bh
Luas = 8.75 x 9.00 x 2.00 = 157.50 m2
Area 3
1/2 Lebar bawah = 10.65 m
Tinggi = 11.80 m
Jumlah Sisi = 1.00 bh
Luas =( 10.65 x 11.80 x 1.00 ) - 65.25 = 60.42 m2
Area 4
1/2 Lebar bawah = 19.45 m
Tinggi = 12.75 m
Jumlah Sisi = 2.00 bh
Luas =( 19.45 x 12.75 x 2.00 ) - 180.96 = 315.02 m2
Area 5
1/2 Lebar bawah = 10.65 m
Tinggi = 11.80 m
Jumlah Sisi = 1.00 bh
Luas = 10.65 x 11.80 x 1.00 = 125.67 m2
Area 6
Lebar (bawah+Atas) /2 = 12.00 m
Tinggi = 10.40 m
Jumlah Sisi = 4.00 bh
Luas = 12.00 x 10.40 x 4.00 = 499.20 m2
PERHITUNGAN KUANTITAS / VOLUME
Area 7
1/2 Lebar bawah = 8.70 m
Tinggi = 10.40 m
Jumlah Sisi = 2.00 bh
Luas = 8.70 x 10.40 x 2.00 = 180.96 m2 +
Luas Total Area Atap = 1,404.02 m2

3. Pekerjaan Nok Atap Genteng Metal


Panjang Jumlah
Panjang 1 = 11.78 x 4.00 = 47.14 m'
Panjang 2 = 8.90 x 1.00 = 8.90 m'
Panjang 3 = 16.95 x 4.00 = 67.80 m'
Panjang 4 = 13.91 x 4.00 = 55.63 m'
Panjang 5 = 8.90 x 1.00 = 8.90 m'
Panjang 6 = 12.40 x 2.00 = 24.80 m' +
Total Panjang Nok Atap = 213.17 m'

4. Pekerjaan ListPlank GRC


Panjang 1 = 14.40 x 1.00 = 14.40 m'
Panjang 2 = 8.35 x 2.00 = 16.70 m'
Panjang 3 = 3.30 x 2.00 = 6.60 m'
Panjang 4 = 5.35 x 2.00 = 10.70 m'
Panjang 5 = 12.05 x 4.00 = 48.20 m'
Panjang 6 = 17.20 x 2.00 = 34.40 m'
Panjang 7 = 20.90 x 1.00 = 20.90 m' +
Total Panjang Nok Atap = 151.90 m'

5. Pekerjaaan Pengecatan
Lantai 1 Panjang Lebar Jumlah
Kolom Teras = 3.70 x 2.00 x 18.00 = 133.20 m2
Listplang Beton Teras = 54.20 x 1.40 x 1.00 = 75.88 m2
Kolom Struktur dan Variasi Bag. Luar type 1 = 3.55 x 0.90 x 49.00 = 156.56 m2
Kolom Struktur dan Variasi Bag. Luar type 2 = 3.55 x 0.50 x 19.00 = 33.73 m2
Dinding + Kolom + Balok Lt. 1 Bag. Luar = 175.05 x 4.55 x 1.00 = 796.48 m2
Lobby Bagian Dalam = 71.35 x 3.50 x 1.00 = 249.71 m2
Selasar Kiri Kanan = 113.64 x 3.50 x 1.00 = 397.74 m2
R. Komisi 2 + WC = 45.32 x 3.50 x 1.00 = 158.62 m2
R. Fraksi Hanura = 19.70 x 3.50 x 1.00 = 68.95 m2
R. Fraksi Perindo = 22.80 x 3.50 x 1.00 = 79.80 m2
Gudang = 18.60 x 3.50 x 1.00 = 65.10 m2
Area WC Depan Gudang = 40.87 x 3.50 x 1.00 = 143.05 m2
Dapur = 16.78 x 3.50 x 1.00 = 58.73 m2
R. Badan Kehormatan = 19.85 x 3.50 x 1.00 = 69.48 m2
R. Fraksi P3 = 22.75 x 3.50 x 1.00 = 79.63 m2
R. Fraksi Nasdem = 23.30 x 3.50 x 1.00 = 81.55 m2
R. Propem Perda = 25.95 x 3.50 x 1.00 = 90.83 m2
PERHITUNGAN KUANTITAS / VOLUME
Free Funchtion = 38.30 x 3.50 x 1.00 = 134.05 m2
R. Komisi 3 + WC = 42.19 x 3.50 x 1.00 = 147.67 m2
R. Fraksi Golkar = 23.05 x 3.50 x 1.00 = 80.68 m2
R. Fraksi Gerindra + WC = 28.90 x 3.50 x 1.00 = 101.15 m2
R. Fraksi PDI = 23.65 x 3.50 x 1.00 = 82.78 m2
WC Samping Ruang Fraksi PDI = 6.10 x 3.50 x 2.00 = 42.70 m2
R. Dharma Wanita = 23.81 x 3.50 x 1.00 = 83.34 m2
R. Istirahat Komisi 1 + WC = 28.18 x 3.50 x 1.00 = 98.63 m2
R. Komisi 1 = 35.66 x 3.50 x 1.00 = 124.81 m2
Dak Kanopi = 78.90 x 1.35 x 1.00 = 106.52 m2

Lantai 2 Panjang Lebar Jumlah


Pinggir Tiang Ornamen Bag. Bawah = 4.70 x 0.35 x 6.00 = 9.87 m2
Pinggir Tiang Ornamen Bag. Atas = 8.58 x 2.00 x 1.00 = 17.16 m2
Area Tengah Ornamen = 7.50 x 4.60 x 1.00 = 34.50 m2
Kolom Variasi Bag. Luar = 3.35 x 0.30 x 53.00 = 53.27 m2
Kolom Struktur Bag. Luar = 4.25 x 0.50 x 4.00 = 8.50 m2
Dinding + Kolom Lt. 2 Bag. Luar = 174.90 x 4.25 x 1.00 = 743.33 m2
Dinding Balkon kiri, kanan = 97.20 x 1.00 x 1.00 = 97.20 m2
R. Bukit Kandis = 50.40 x 4.40 x 1.00 = 221.76 m2
Area Ruang Tangga = 29.98 x 4.40 x 1.00 = 131.89 m2
R. Tunggu Rapat = 24.70 x 4.40 x 1.00 = 108.68 m2
R. Waka 2 = 34.04 x 4.40 x 1.00 = 149.75 m2
Area WC Samping R. Waka 1 = 44.21 x 4.40 x 1.00 = 194.50 m2
R. Waka 1 = 30.78 x 4.40 x 1.00 = 135.41 m2
R. Sidang Pleno = 86.64 x 4.40 x 1.00 = 381.22 m2
Kolom Pada Ruang Sidang = 4.90 x 4.40 x 6.00 = 129.36 m2
R. Audio Sidang = 13.34 x 4.40 x 2.00 = 117.39 m2
R. Ketua Dewan = 30.84 x 4.40 x 1.00 = 135.70 m2
R. Istirahat Ketua + WC = 27.70 x 4.40 x 1.00 = 121.88 m2
R. Tunggu Ketua = 23.66 x 4.40 x 1.00 = 104.10 m2
R. Tim Pakar + WC Samping = 41.17 x 4.40 x 1.00 = 181.15 m2
Selasar Kiri Kanan = 112.27 x 4.40 x 1.00 = 493.99 m2
Dak Kanopi 1 = 57.30 x 0.90 x 1.00 = 51.57 m2
Dak Kanopi 2 = 174.14 x 0.80 x 1.00 = 139.31 m2 +
Total Luasan = 7,502.79 m2

Luasan Jendela, Ventilasi, Pintu, Dinding HPL, Wallpaper Pada Bangunan.


Panjang Lebar Jumlah Sisi
Jendela Type 1 = 7.00 x 0.90 x 6.00 x 2 = 75.60 m2
Jendela Type 2 = 2.65 x 1.00 x 44.00 x 2 = 233.20 m2
Jendela Type 3 = 2.65 x 0.90 x 13.00 x 2 = 62.01 m2
Jendela Type 4 = 1.50 x 0.80 x 38.00 x 2 = 91.20 m2
Jendela Type 5 = 2.20 x 3.00 x 4.00 x 2 = 52.80 m2
Jendela Type 6 = 2.65 x 3.50 x 2.00 x 2 = 37.10 m2
Jendela Type 7 = 2.65 x 1.00 x 2.00 x 2 = 10.60 m2
PERHITUNGAN KUANTITAS / VOLUME
Ventilasi = 1.00 x 1.00 x 22.00 x 2 = 44.00 m2
Pintu Masuk Utama 2 Pintu = 3.00 x 3.60 x 3.00 x 2 = 64.80 m2
Pintu Ruangan Type 1 = 3.00 x 1.00 x 23.00 x 2 = 138.00 m2
Pintu Masuk Ruangan 2 Pintu Type 1 = 3.00 x 1.90 x 7.00 x 2 = 79.80 m2
Pintu Ruangan Type 2 = 2.00 x 1.00 x 11.00 x 2 = 44.00 m2
Pintu Masuk Ruangan 2 Pintu Type 2 = 3.00 x 1.90 x 2.00 x 2 = 22.80 m2
Pintu WC = 2.00 x 0.80 x 16.00 x 2 = 51.20 m2
Keramik Dinding WC Lt. 1 = 34.30 x 2.00 x 1.00 x 1 = 68.60 m2
Keramik Dinding WC Lt. 2 = 63.28 x 2.00 x 1.00 x 1 = 126.56 m2
HPL, R. Bukit Kandis = 56.20 x 4.40 x 1.00 x 1 = 247.28 m2
HPL, R. Sidang Pleno = 27.56 x 4.40 x 1.00 x 1 = 121.26 m2
HPL, R. Komisi 1 = 35.66 x 3.50 x 1.00 x 1 = 124.81 m2
HPL, R. Istirahat Komisi 1 = 22.78 x 3.50 x 1.00 x 1 = 79.73 m2
HPL, R. Fraksi PDI = 23.65 x 3.50 x 1.00 x 1 = 82.78 m2
HPL, R. Komisi 3 = 41.59 x 3.50 x 1.00 x 1 = 145.57 m2
HPL, R. Fraksi Nasdem = 23.30 x 3.50 x 1.00 x 1 = 81.55 m2
HPL, R. Propem Perda = 25.95 x 3.50 x 1.00 x 1 = 90.83 m2
HPL, R. Ketua Dewan = 30.84 x 4.40 x 1.00 x 1 = 135.70 m2
HPL, R. Waka 1 = 30.78 x 4.40 x 1.00 x 1 = 135.41 m2
HPL, R. Waka 2 = 34.04 x 4.40 x 1.00 x 1 = 149.75 m2 +
Total Luasan = 2,596.93 m2
Luasan Total Area Pek. Cat = 7,502.79 - 2,596.93 = 4,905.86 m2

6. Pekerjaan Plafond PVC dan Rangka


Lantai 1 Luasan Diukur Dari Aplikasi Autocad
Teras Depan = 197.47 m2
Lobby = 112.41 m2
R. Komisi 2 + WC = 80.27 m2
R. Fraksi Hanura = 26.41 m2
R. Fraksi Perindo = 35.28 m2
Gudang = 35.82 m2
Area WC Depan Gudang = 21.85 m2
Dapur = 15.14 m2
R. Badan Kehormatan = 26.90 m2
R. Fraksi P3 = 35.07 m2
R. Fraksi Nasdem = 36.93 m2
R. Propem Perda = 46.87 m2
Free Fuchtion = 83.03 m2
R. Komisi 3 + WC = 85.33 m2
R. Fraksi Golkar = 43.10 m2
R. Fraksi Gerindra + WC = 35.64 m2
R. Fraksi PDI = 34.97 m2
WC Samping Fraksi PDI = 4.62 m2
R. Dharma Wanita = 35.70 m2
R. Istirahat Komisi 1 + WC = 34.99 m2
R. Komisi 1 = 72.27 m2
PERHITUNGAN KUANTITAS / VOLUME
Selasar Kiri Kanan = 233.29 m2
Lantai 2
R. Bukit Kandis = 164.61 m2
Area Atas Tangga = 102.70 m2
R. Tunggu Rapat = 37.10 m2
R. Waka 2 = 68.38 m2
Area Wc Samping R. Waka 1 = 18.99 m2
R. Waka 1 = 52.23 m2
R. Sidang Pleno = 403.48 m2
R. Audio = 21.26 m2
R. Ketua = 59.11 m2
R. Istirahat Ketua + WC = 20.96 m2
R. Tunggu Ketua = 39.40 m2
R. Tim Pakar + WC Samping = 23.94 m2
Selasar Kiri Kanan = 146.87 m2
Bawah Cucuran Atap Luar Bangunan = 131.28 m2 +
Lasan Total Pekerjaan Pafon PVC + Rangka Hollow = 2,623.69 m2

7. Pekerjaan Assesoris Cutting ACP


Lantai 1 Panjang Lebar Jumlah
Lobby Model 1 = 2.50 x 0.82 x 6.00 = 12.30 m2
Lobby Model 2 = 2.50 x 2.30 x 1.00 = 5.75 m2
Selasar Kiri Kanan = 1.50 x 0.48 x 22.00 = 15.84 m2
Lantai 2
Area Atas Tangga Model 1 = 3.20 x 0.92 x 1.00 = 2.94 m2
Area Atas Tangga Model 2 = 2.00 x 0.66 x 3.00 = 3.96 m2
R. Bukit Kandis = 1.47 x 0.48 x 6.00 = 4.23 m2
R. Sidang Pleno Model 1 = 3.97 x 1.35 x 4.00 = 21.44 m2
R. Sidang Pleno Model 2 = 2.66 x 2.13 x 2.00 = 11.33 m2
Selasar Kiri Kanan = 1.50 x 0.45 x 8.00 = 5.40 m2 +
Luasan Total = 83.20 m2

8. Pekerjaan List Profile Plafond PVC


Lantai 1 Panjang
Lobby = 186.77 m'
Selasar Kiri Kanan = 479.88 m'
Lantai 2
R. Bukit Kandis = 149.96 m'
Area Atas Tangga = 155.26 m'
R. Waka 2 = 81.74 m'
R. Waka 1 = 67.18 m'
R. Sidang Pleno = 396.53 m'
R. Ketua = 74.06 m'
Selasar Kiri Kanan = 268.70 m' +
Total Panjang Pekerjaan List Profile Plafond PVC = 1,860.08 m2
PERHITUNGAN KUANTITAS / VOLUME
9. Pekerjaan List Polos Plafond PVC
Lantai 1 Panjang
Teras Depan = 94.56 m'
R. Komisi 2 + WC = 97.60 m'
R. Fraksi Hanura = 43.78 m'
R. Fraksi Perindo = 52.60 m'
Gudang = 50.32 m'
Area WC Depan Gudang = 40.87 m'
Dapur = 16.78 m'
R. Badan Kehormatan = 43.57 m'
R. Fraksi P3 = 52.15 m'
R. Fraksi Nasdem = 53.82 m'
R. Propem Perda = 62.59 m'
Free Fuchtion = 91.98 m'
R. Komisi 3 + WC = 102.19 m'
R. Fraksi Golkar = 54.37 m'
R. Fraksi Gerindra + WC = 60.78 m'
R. Fraksi PDI = 54.93 m'
WC Samping Fraksi PDI = 6.10 m'
R. Dharma Wanita = 55.73 m'
R. Istirahat Komisi 1 + WC = 59.38 m'
R. Komisi 1 = 91.54 m'
Lantai 2
R. Tunggu Rapat = 81.26 m'
Area Wc Samping R. Waka 1 = 44.21 m'
R. Audio Sidang = 13.34 m'
R. Istirahat Ketua + WC = 27.70 m'
R. Tunggu Ketua = 84.22 m'
R. Tim Pakar + WC Samping = 41.17 m'
Bawah Cucuran Atap Luar Bangunan = 328.12 m' +
Total Panjang Pekerjaan List olos Plafond PVC = 1,805.66 m2
DAFTAR HARGA UPAH DAN MATERIAL
PEKERJAAN : PEK. PERENCANAAN PENINGKATAN/REHAB SARANA DAN PRASARANA
KANTOR SEKRETARIAT PEMKOT. BENGKULU
LOKASI : KOTANBENGKULU
T. ANGGARAN : 2020

A. DAFTAR HARGA SATUAN UPAH KERJA


No Uraian Satuan Harga Satuan Keterangan
1 Pekerja OH Rp 100,000.00
2 Tukang OH Rp 150,000.00
3 Kepala tukang OH Rp 165,000.00
4 Mandor OH Rp 165,000.00
5 Operator OH Rp 210,000.00
6 Operator crane OH Rp 210,000.00
7 Operator alat berat OH Rp 210,000.00
8 Pembantu operator crane OH Rp 100,000.00

B. DAFTAR HARGA MATERIAL


NO Uraian Satuan Harga Satuan Keterangan
1 Air liter Rp 130.00
2 Allumunium strip m Rp 53,000.00
3 Alumunium foil m2 Rp 32,000.00
4 Almn gel tbl 0.55 lbr Rp 106,000.00
5 Ampelas Lbr Rp 7,000.00
6 Bak fibreglass unit Rp 1,200,000.00
7 Bak cuci piring unit Rp 465,000.00
8 Bata merah buah Rp 600.00
9 Batu belah m 3
Rp 265,000.00
10 Batu Pecah/split stone crusher m3 Rp 380,000.00
11 Bata rooster m3 Rp 832,000.00
12 Batu tempel hitam m2 Rp 220,000.00
13 Baja strip (0.2x2) cm kg Rp 11,900.00
14 Baja tulangan kg Rp 12,000.00
15 Besi beton kg Rp 11,800.00
16 Besi profil kg Rp 11,800.00
17 Besi strip kg Rp 11,800.00
18 Cat Kg Rp 30,000.00
19 Cat Antara Kg Rp 30,000.00
20 Cat Dasar kg Rp 25,000.00
21 Cat Dasar (weathershield) kg Rp 80,000.00
22 Cat penutup Aquaproof kg Rp 90,000.00
22 Cat menie Kayu Kg Rp 55,000.00
23 Cat menie Besi Kg Rp 50,000.00
24 Cat Penutup Kayu Kg Rp 75,000.00
25 Cat Penutup (weathershield) Kg Rp 80,000.00
26 Dempul kg Rp 7,000.00
27 Door stop Buah Rp 55,000.00
28 Dolken kayu O (8-10) cm,pnj 4m btg Rp 10,000.00
29 Door Closer bh Rp 180,000.00
30 Door Holder bh Rp 100,000.00
31 Engsel kupu-kupu bh Rp 14,000.00
32 Engsel Angin bh Rp 50,000.00
33 Engsel Jendela bh Rp 25,000.00
34 Engsel Pintu bh Rp 50,000.00
35 Floor drain unit Rp 80,000.00
36 Kait angin bh Rp 23,000.00
37 Genteng metal m2 Rp 85,000.00
38 Gypsum board Lembar Rp 65,000.00
39 Plavond PVC m2 Rp 29,000.00
40 Rangka Metal Hollow 40.40.2 m Rp 7,250.00
39 Karpet Roll Marina Bay m2 Rp 395,000.00
40 Underlayers m2 Rp 95,000.00
41 Kaca cermin 5 mm m2 Rp 150,000.00
42 Kaca tebal 5 mm m2 Rp 175,000.00
43 Kawat beton kg Rp 23,000.00
44 kawat las kg Rp 45,000.00
45 Kayu bekisting m2 Rp 1,870,000.00
46 Kayu 5/7 m3 Rp 2,200,000.00
47 Kerikil m 3
Rp 230,000.00
48 Balok Kayu Klas II m3 Rp 2,600,000.00
49 Closet duduk setara TOTO bh Rp 2,660,000.00
50 Closet jongkok bh Rp 300,000.00
51 Kran Air BH Rp 80,000.00
52 Pek. Exhaust WC + Instalasi BH Rp 500,000.00
52 Kuas Bh Rp 17,000.00
53 Kunci tanam antik Bh Rp 235,000.00
54 Kunci tanam biasa Bh Rp 160,000.00
55 Kunci slot bh Rp 42,000.00
56 Kunci silinder bh Rp 120,000.00
57 Lem Karpet kg Rp 82,000.00
58 Lem kg Rp 30,000.00
59 Lem kayu kg Rp 40,000.00
60 List profil gypsum m' Rp 21,000.00
61 Menie Besi Lt Rp 43,900.00
62 Minyak bekisting Liter Rp 3,000.00
63 Minyak pelumas Liter Rp 20,000.00
64 Sunscreen Allumunium m2 Rp 800,000.00
65 Nok genteng metal m' Rp 80,000.00
66 Paku kg Rp 17,000.00
67 Papan GRC m Rp 33,000.00
68 Pasir beton m3 Rp 220,000.00
69 Pasir pasang m3 Rp 200,000.00
70 Pasir urug m3 Rp 180,000.00
71 Beton Ready Mix K250 m3 Rp 1,150,000.00
72 Paving block m2 Rp 68,000.00
73 Grass block m2 Rp 74,000.00
74 Kusen pintu allumunium m' Rp 103,000.00
75 Politur ltr Rp 80,000.00
76 Politur jadi ltr Rp 92,000.00
77 Pengencer kg Rp 12,000.00
78 Pipa PVC 1/2" m' Rp 6,700.000
79 Pipa PVC 3/4" m' Rp 11,000.00
80 Pipa PVC 1" m' Rp 14,000.00
81 Pipa PVC 1 1/2" m' Rp 18,000.00
82 Pipa PVC 2" m' Rp 25,000.00
83 Pipa PVC 2 1/2" m' Rp 28,000.00
84 Pipa PVC 3" m' Rp 57,000.00
85 Pipa PVC 4" m' Rp 45,000.00
86 Pipa beton dia 15-20 cm bh Rp 59,000.00
87 Pipa beton dia 100 cm bh Rp 500,000.00
88 Lampu Downlight 40 Watt Inbouw merek panasonic bh Rp 170,000.00
89 Lampu LED 20 Watt setara panasonic bh Rp 170,000.00
90 Stop Kontak merek panasonic bh Rp 45,000.00
91 Saklar Ganda merek panasonic bh Rp 55,000.00
92 Saklar Tunggal merek panasonic bh Rp 30,000.00
93 Box Panel MCB isi 3 ( 10 Amphere dan Breaker 60 Amphere) bh Rp 2,500,000.00
88 Plamuur kg Rp 20,000.00
89 Plamuur (weathershield) kg Rp 45,000.00
90 Plywood 6mm Lembar Rp 100,000.00
91 Plywood tebal 6mm Lembar Rp 150,000.00
92 Profil kaca m' Rp 45,000.00
93 Jendela allumunium m2 Rp 790,000.00
94 Rambuncis bh Rp 70,000.00
95 Rangka metal holow 40.40.2 mm m1 Rp 12,000.00
96 Residu liter Rp 10,000.00
97 Sealtape bh Rp 3,000.00
98 Sealant tube Rp 50,000.00
99 Semen portlan Kg Rp 1,300.00
100 Semen warna kg Rp 2,200.00
101 Seng Gelombang lbr Rp 54,000.00
102 Seng plat m’ Rp 60,000.00
103 Sirtu m3 Rp 170,000.00
104 Skrup fixer Buah Rp 7,500.00
105 Solar Liter Rp 7,500.00
106 Spring knip bh Rp 22,500.00
107 Teak oil/vernis ltr Rp 82,000.00
108 Tanah urug didatangkan m3 Rp 43,000.00
109 Rel pintu sorong bh Rp 210,000.00
110 Urinoir bh Rp 2,450,000.00
111 Washtafel Setara Amstad set Rp 1,500,000.00
112 Waterdrain bh Rp 87,000.00
113 Rangka atap baja ringan m2 Rp 260,000.00
114 Granit tile 600x600 ex. Essenza bh Rp 90,000.00
115 Granit tile 400x400 ex. Indogress bh Rp 26,000.00
116 Keramik Ukuran 400x400 ex. Platinum bH Rp 14,000.00
117 Keramik Ukuran 300x300 ex. Platinum bh Rp 8,000.00
118 Keramik Ukuran 200x200 ex. Platinum bh Rp 3,500.00
119 Plint granit 10x600 bh Rp 10,000.00
120 Stepnose 97x600 granit hitam polos bh Rp 60,000.00
121 Keramik ukuran 200X400 gloss, ex. Roman bh Rp 8,000.00
122 Keramik ukuran 300x600, ex. Platinum bh Rp 15,000.00
123 Kalsiboard 4mm lbr Rp 55,000.00
124 Keran washtafel ex. Toto TX 123 LESV4 bh Rp 1,100,000.00
125 Cat perlindungan Batu Alam ex. Propan kg Rp 80,000.00
126 Aluminium Composit Panel ex. Alucobond PVDF m2 Rp 1,050,000.00
127 Cat duco kg Rp 80,000.00
128 Thinner ltr Rp 28,000.00
129 Polycarbonat flat Warna m2 Rp 88,000.00
130 Rooster beton minimalis 200x400 bh Rp 45,000.00
131 Bath shower set ex. Toto TS309RYN (set incl. keran) bh Rp 2,100,000.00
132 Glasslock polos ex. Mulia wave bh Rp 34,000.00
133 Keran dapur leher angsa bh Rp 200,000.00

C. DAFTAR HARGA PERALATAN


1 Sewa alat (mesin las, takal dll) Jam Rp 70,000
2 Sewa tripot/tackel & handie crane hari Rp 200,000
3 Sewa excavator type 225 kap hari Rp 3,000,000
4 Peralatan potong pipa T1/manual hari Rp 180,000
5 Peralatan potong pipa T2 hari Rp 280,000
6 Sewa tripot/tackel & hari Rp 200,000
7 Mobile crane = < 3 ton hari Rp 2,000,000
8 Peralatan potong pipa T2/mekanik hari Rp 350,000
9 Sewa genset 1500 watt hari Rp 120,000
10 Sewa pompa submersible 3 m3/h hari Rp 170,000
11 Sewa tripot/tackel &handle crane 2T hari Rp 260,000
DAFTAR HARGA BAHAN DAN UPAH PEKERJA

Kegiatan : Perencanaan Peningkatan/ Rehab Sarana dan Prasarana


Pekerjaan : Rehab Gedung Dewan Perwakilan Rakyat (DPR)
Kabupaten : Bengkulu Tengah
T.A : 2021

UPAH PEKERJA
1 Pekerja 110,000.00 /hari
2 Tukang Gali 120,000.00 /hari
3 Tukang Batu 120,000.00 /hari
4 Tukang Kayu 120,000.00 /hari
5 Tukang Besi 120,000.00 /hari
6 Tukang Cat 120,000.00 /hari
7 KepalaTukang 140,000.00 /hari
8 Mandor 150,000.00 /hari
HARGA BAHAN / METERIAL
A BAHAN BATU DAN PASIR
1 Tanah urug 37,000.00 /m3
2 Pasir urug 127,000.00 /m3
3 Pasir pasang 144,000.00 /m3
4 Pasir beton 144,000.00 /m3
5 Bata Ringan 979,000.00 m3
6 Bata Ringan 8,800.00 Bh
7 Bata Biasa 700.00 Bh
8 Batu kali 288,000.00 /m3
9 Batu Belah 230,000.00 /m3
10 Batu Gunung 288,000.00 /m3
11 Sirtu 201,000.00 /m3
12 Koral 345,000.00 /m3
13 Batu Endesit /m2
14 Split 1/2 - 2/3 345,000.00 /m3
15 Floor Harderner /kg
16 Semen Portland 1,600.00 /kg
17 Mortar 1,800.00 /kg
18 Semen putih/semen warna 2,400.00 /kg
19 Buis Beton 1/2 Dia 30 /buah
20 Jalusi Lobang ( Roster ) /buah
21 Paving block 10 x 20 T. 6 cm /buah
B HARGA BAHAN KAYU
1 Plywood 4 mm 58,000.00 /lbr
2 Plywood 9 mm 140,000.00 /lbr
3 GRC 4 mm /lbr
4 GRC 5 mm (List Plank) 24,500.00 /m
5 GRC 6 mm /lbr
6 Gypsum 9 mm 78,100.00 /lbr
7 Plafond PVC 6 mm /lbr
8 Plafond PVC 8 mm /lbr
9 PVC Strip 0,8 mm x 20 cm 25,000.00 /m1
10 Alumunium Composit Panel (ACP) (Cutting) 350,000.00 /m2
11 Multyplek 9 mm /lbr
12 Teakwood 12 mm /lbr
13 List Gypsum Profil 12,000.00 /m'
14 List Kayu Profil A 4 /m'
15 List PVC Polos 4 m 3,000.00 /m'
16 List PVC Profile Motif Hologram 4 m 14,000.00 /m'
17 List PVC Profile Motif Pigura 4 m 16,000.00 /m'
18 Balok Kayu 2,200,000.00 /m3
19 Kayu kelas lV ( bekisting ) 2,200,000.00 /m3
20 Kayu kelas IV /m3
21 Kayu kelas II /m3
22 Kayu Balok 5/7 2,200,000.00 /m3
23 Kayu dolcen 10,000.00 /btg
C HARGA BAHAN KACA DAN BESI
1 Rangka Hollow 40 x 40 x 2,5 7,000.00 /m
2 Seng Talang Galvalum 90,000.00 /m
3 Kaca bening 8 mm 372,600.00 /m2
4 Kaca Panashap / Temperlite 12 mm /m2
5 Kaca Raybend 5 mm /m2
6 Kaca Panasap 5 mm /m
7 Besi Beton 12,500.00 /kg
8 Besi Profil /kg
9 Besi Strip /kg
10 Besi Siku L 30. 30. 3 /btg
11 Besi Siku L 40. 40. 4 /btg
12 Besi Siku L 50. 50. 5 /btg
13 Besi Siku L 60. 60. 6 /btg
14 Besi Siku L 70. 70. 7 /btg
15 Besi Plat Baja /lbr
16 Besi Hollow /m'
17 C 125.65.6.8 16,500.00 /kg
18 Baja WF 250.120.6.9 16,500.00 /kg
19 Baja Ringan C75 22,000.00 /m
20 Baut Sekrup 300.00 /bh
21 Reng Baja Ringan 18,000.00 /m
22 Dynabolt 2,000.00 /bh
23 Kawat Beton 22,000.00 /kg
24 Kawat las /kg
25 Profil Alluminium 4" 138,500.00 /m'
26 Alumunium Strip /m'
27 Profil Allumunium Pintu 138,000.00 /m'
28 Profil Allumunium Jendela 115,000.00 /m'
29 Skrup Fixer /buah
30 Grill Alumunium /m'
31 Kisi - Kisi /m'
32 Paku halus /kg
33 Paku atap genteng metal /kg
34 Kawat Duri /m'
35 Paku 5" 7" 22,000.00 /kg
36 Paku 2" 3" 22,000.00 /kg
37 Paku seng /kg
38 Kawat Las /kg
39 Paku macam-macam ukuran /kg
40 Paku sekrup 112,000.00 /kg
41 Folding Door 0.5 mm 518,000.00 /m2
42 Rolling Door Besi 0.6mm 525,000.00 /m2
D HARGA BAHAN PENUTUP LANTAI
1 Keramik Lantai 40 x 40 cm 10,800.00 /buah
2 Keramik Lantai 40 x 40 cm ( anti slip ) Essenza 29,000.00 /buah
3 Keramik Lantai 30 x 30 cm 2,800.00 /buah
4 Keramik Lantai 20 x 20 cm 2,000.00 /buah
5 Keramik Lantai 20 x 20 cm (anti slip) 2,240.00 /buah
6 Keramik dinding 20 x 25 cm 2,900.00 /buah
7 Keramik Dinding 20 x 20 cm 2,600.00 /buah
8 Keramik Plin Dinding 10 x 40 cm /buah
9 Keramik lantai 30 x 30 cm ( anti slip ) /buah
10 Kuku Macan ( Kuku Keramik ) /m'
11 Granit 40 x 40 cm /buah
12 Granit 60 x 60 cm 220,000.00 /buah
13 Granit 60 x 60 cm ( Anti Slip ) /buah
14 Batu Tempel/Batu Alam /m2
15 Karpet Roll Marina Bay RED 320,000.00 /m2
16 Underlayers Karpet 25,000.00 /m2
17 Lem Karpet Crona 88,000.00 /kg
E HARGA BAHAN PENUTUP ATAP
1 Genteng metal Colour T. 0.25 /bh
2 Genteng metal Colour Berpasir 1 x 4, T. 0.30 (0.77 x 1 x 0.35) 98,000.00 /bh
3 Atap Spandek 64,000.00 /lbr
4 Atap PVC Alderon 120,000.00 /lbr
5 6 /lbr
6 Nok Atap 12,000.00 /m
7 Flashing Zinkcalum /m
8 Nok Atas Bulat genteng metal Colour /bh
9 Nok Tepi Genteng Metal Colour /bh
10 Nok Atas Bulat genteng metal Colour Berpasir 25,000.00 /bh
11 Nok Tepi Genteng Metal Colour Berpasir /bh
12 Nok Alumunium /bh
13 Moncrete Aluminium Foil Single Side 1.25 x 60 m 4,300.00 /m2
14 Moncrete Aluminium Foil Double Side 1.20 x 50 m 7,200.00 /m2
15 Moncrete Aluminium Foil Double Side 1 x 30 m x 3 mm 15,200.00 /m2
16 Protect Foil Aluminium Foil Buble Single Side 1.2 x 50 m 4,400.00 /m2
17 Protect Foil Aluminium Foil Double Side 1 m x 30 m x 4 mm 33,000.00 /m2
18 Seng Alumunium /lbr
19 Seng Gelombang Warna 54,000.00 /lbr
20 Rangka Hollow Plafond 9,000.00 /m
21 Seng Plat Bjls 28 /lbr
F HARGA BAHAN KUNCI / PENGGANTUNG
1 Kunci Tanam Besar /buah
2 Kunci Tanam Kecil /buah
3 Pas. Kunci Pintu Frame Less /buah
4 Kunci Double Cylinder setara " Dekson " /buah
5 Kunci Double Cylinder + Handle on Plate setara " Dekson " /buah
6 Engsel Casement 10" setara " Dekson " /pasang
7 Engsel Casement 16" setara " Dekson " /pasang
8 Engsel Pintu Alumunium setara "Dekson" 21,000.00 /buah
9 Engsel Jendela setara "Dekson" /buah
10 Engsel Hidrolik 38,000.00 /buah
11 Ikatan Angin /buah
12 Grendel Jendela /buah
13 Tarikan Jendela /buah
14 Handel Tongkat Pintu Kaca /pasang
15 Handel Pintu Swing Alumunium 68,000.00 /pasang
16 Hak Angin 15,000.00 /buah
17 Rambuncis /buah
18 Doorcloser Pintu Alumunium setara " Dekson" /buah
19 Floor Hingers setaraf " DORMA BTS.84 " lengkap Assesorisnya /buah
20 Gerendel Pintu Tanam setara "Dekson" /buah
21 Alumunium Door Lock 160,000.00 /buah
22 Kunci Sliding Al Dekson 120,000.00 /buah
23 Rel Pintu Sliding / Geser 1,250,000.00 /Set
24 Rambuncis Kanan 8,500.00 /buah
25 Gerendel Jendela Casement setara "Dekson" /buah
G HARGA BAHAN LISTRIK
1 Lampu Downlight PLC 18 Watt 120,000.00 /buah
2 Lampu Spot Light PAR-38 angle 120 Watt /buah
3 Lampu Adjustable Downlight Dichroic 12V/50 Watt /buah
4 Lampu SL 13 watt /buah
5 Lampu SL 18 watt /buah
6 Lampu Pijar 15 watt + fiting setara Philip /buah
7 Lampu Gantung + Kap 150 watt /buah
8 Lampu Baret 18 watt /buah
9 Lampu LED Bulb 13 Watt /buah
10 Handle Switch 16 A Ø 1 Phase /buah
11 Shaklar Tunggal 25,000.00 /buah
12 Shaklar Ganda 43,000.00 /buah
13 Stop kontak 32,000.00 /buah
14 Stop kontak AC 58,000.00 /buah
15 Instalasi titik api /titik
16 Box Zekring + MCB 2 Group setara "Merlin Gerin" /unit
17 Panel Box 3 phase + MCB 6 Group setara "Merlin Gerin" /unit
H HARGA BAHAN SANITASI /SANITAIR
1 Kloset Duduk setara American Standard /set
2 Kloset Jongkok setara American standard 300,000.00 /set
3 Kran Air Steinles 1/2 toto 80,000.00 /set
4 Floor drain 35,000.00 /set
5 Roof Drain /set
6 Kaca Cermin uk 800 x 1.200 /set
7 Kaca Cermin uk 1.200 x 1.200 mm /set
8 Wastafel setara American standard /set
9 Urinoir setara American standard /set
10 Penyekat Porslin /bh
11 Shower Dinding /bh
12 Kitchen Sink single bowl /buah
13 Bak Air Sudut 63 x 63 x 70 753,000.00 /buah
14 Seal tape 3,500.00 /buah
15 Sealent /tube
16 Pipa PVC 1/2" 6,700.00 /m'
17 Pipa PVC 3/4" 11,000.00 /m'
18 Pipa PVC 1" 11,250.00 /m'
19 Pipa PVC 1 1/2" 19,000.00 /m'
20 Pipa PVC 2" 24,000.00 /m'
21 Pipa PVC 3" 47,000.00 /m'
22 Pipa PVC 4" 78,000.00 /m'
23 Pipa PVC 5" 129,000.00 /m'
24 Pipa Galvanis 1/2" 47,500.00 /m'
25 Pipa Galvanis 3/4" 61,000.00 /m'
26 Pipa Galvanis 1" 91,500.00 /m'
27 Pipa Galvanis Medium 2" 188,500.00 /m'
28 Pipa Galvanis Medium 3" 309,500.00 /m'
29 Pipa Galvanis Medium 4" 446,250.00 /m'
30 Mesin Pompa Air submersible /m'
31 Pompa Air Submersibre /bh
32 Pompa Air Jet Pum /bh
33 Ijuk /kg
I HARGA BAHAN CAT ( PELAPIS )
1 Cat Dasar Kayu /kg
2 Cat Kayu/Besi setara BEE BRAND /kg
3 Cat Tembok Dulux Wheatershield 58,000.00 /kg
4 Cat Plafond "setara Metrolit " /kg
5 Cat Tembok 60,000.00 /kg
6 Cat Besi Anti Karat /kg
7 Cat Dasar Waterproofing 80,000.00 /kg
8 Cat Penutup Aquaproof 90,000.00 /kg
9 Base Epoxy Enamel /kg
10 Top Coat Epoxy Enamel /kg
11 Hardener u/ Epoxy Enamel /kg
12 Politur /ltr
13 Vernis /ltr
14 Residu/Ter /ltr
15 Dempul /kg
16 Plamir 20,000.00 /kg
17 Amplas /lbr
18 Meny Kayu /kg
19 Meny Besi 38,000.00 /kg
20 Kuas 6,000.00 /bh
21 Alumunium Composit Panel 138,000.00 /m2
22 Minyak cat /ltr
23 Thinner /ltr
24 Lem kayu /kg
25 Compound /kg
26 Solar /liter
27 Minyak Pelumas /liter
28 Minyak bekisting 3,000.00 /liter

Anda mungkin juga menyukai