Anda di halaman 1dari 10

REKAPITULASI

EXTENTION JETTY PT. AGRO NUSA ABADI


DESA BAHONTALU, KECAMATAN PETASIA, KABUPATEN MOROWALI,
Item
No.

Description

Total
Rp

PENDAHULUAN

1,054,894,661.70

II

PLATFORM

6,186,725,893.70

III

SUB - PLATFORM

1,401,011,926.70

IV

TRESTLE

7,865,607,926.80

BREASTING DOLPHIN

2,446,010,274.00

VI

MOORING DOLPHIN

1,651,732,749.80

VII

CATWALK

VIII ALAT NAVIGASI

435,374,445.00
2,563,000,000.00

TOTAL

23,604,357,877.70

PPN 10%

GRAND TOTAL

25,964,793,665.47

ROUNDED

25,964,793,000.00

2,360,435,787.77

RENCANA ANGGARAN BIAYA (ENGINEERING ESTIMATE)


EXTENTION JETTY PT. AGRO NUSA ABADI
DESA BAHONTALU, KECAMATAN PETASIA, KABUPATEN MOROWALI,
PROVINSI SULAWESI TENGAH
No.
2.1.

Rincian Item Pekerjaan

Satuan Volume

Harga Satuan (Rp.)


Bahan
Upah / Alat

Jumlah Biaya (Rp.)


Bahan
Upah / Alat

Total Biaya
(Rp.)

PENDAHULUAN

I PEKERJAAN PENDAHULUAN

2.2.

Pengukuran

Mobilisasi dan Demobilisasi

Pembuatan Kantor Lapangan

Asuransi, safety dan keamanan

l.s
l.s
l.s
l.s

1.00
1.00
1.00
1.00

###
###
###
###
SUB TOTAL

###
###
###
###
I - PENDAHULUAN

55,000,000.00
825,000,000.00
82,500,000.00
92,394,661.70

###

PLATFORM

II PEKERJAAN PLATFORM 49.3 x 10m

Titik

52.00

TIANG PANCANG Diameter 600mm t=14mm


1

Transportasi tiang pancang

Kg

Loading Unloading tiang

1,456.00

###

82,500.00

120,120,000.00

120,120,000.00

Pemancangan

1,456.00

632,500.00

920,920,000.00

920,920,000.00

Pengecatan Tiang (12 m)

624.00

148,500.00

92,664,000.00

92,664,000.00

Penyambungan Tiang

Bh

104.00

825,000.00

85,800,000.00

85,800,000.00

Pemotongan Kepala Tiang

Bh

52.00

25,740,000.00

25,740,000.00

Cathodic protection

Tiang

52.00

6,700,000.00

1,250,000.00

348,400,000.00

65,000,000.00

413,400,000.00

Pile Rapping

m2

238.80

750,000.00

1,250,000.00

179,100,000.00

298,500,000.00

477,600,000.00

864,461,449.50

216,624,988.80

1,081,086,438.30

247,212,704.20

1,293,472,721.20

495,000.00

BETON BERTULANG
1

Pelat Lantai t=30 -- 10x49.3x0.3

m3

147.90

5,844,905.00

1,464,672.00

Balok 130x125 -- 1.3x0.95x10x13

m3

160.60

6,514,695.00

1,539,307.00

Balok 75x60 -- 0.75x0.3x49.3x2

m3

22.20

6,514,695.00

1,539,307.00

144,626,229.00

34,172,615.40

178,798,844.40

Balok Janggut 1.5x1.3x1.25x13

m3

38.00

6,514,695.00

1,539,307.00

247,558,410.00

58,493,666.00

306,052,076.00

Pengisi Tiang -- 0.283x1.75x52

m3

29.40

6,499,020.00

1,539,307.00

191,071,188.00

45,255,625.80

236,326,813.80

###

FASILITAS DERMAGA
1

Bollard Kapasitas 35 Ton

set

4.00

27,500,000.00

3,300,000.00

110,000,000.00

13,200,000.00

123,200,000.00

Fender V600 L2000

set

13.00

55,715,000.00

8,250,000.00

724,295,000.00

107,250,000.00

831,545,000.00

SUB TOTAL II - PLATFORM


2.3.

SUB-PLATFORM

III PEKERJAAN SUB-PLATFORM 24x4.5m


TIANG PANCANG Diameter 600mm

Titik

17.00

###

RENCANA ANGGARAN BIAYA (ENGINEERING ESTIMATE)


EXTENTION JETTY PT. AGRO NUSA ABADI
DESA BAHONTALU, KECAMATAN PETASIA, KABUPATEN MOROWALI,
PROVINSI SULAWESI TENGAH
No.

Rincian Item Pekerjaan

Satuan Volume

Harga Satuan (Rp.)


Bahan
Upah / Alat
-

Jumlah Biaya (Rp.)


Bahan
Upah / Alat
-

Total Biaya
(Rp.)

Transportation Tiang Pancang

kg

82,416.00

Loading Unloading tiang

408.00

82,500.00

33,660,000.00

33,660,000.00

Pemancangan

408.00

632,500.00

258,060,000.00

258,060,000.00

Pengecatan Tiang (12 m)

204.00

148,500.00

30,294,000.00

30,294,000.00

Penyambungan Tiang

Bh

17.00

825,000.00

14,025,000.00

14,025,000.00

Pemotongan Kepala Tiang

Bh

17.00

495,000.00

8,415,000.00

8,415,000.00

Cathodic protection

Tiang

17.00

6,700,000.00

1,250,000.00

113,900,000.00

21,250,000.00

135,150,000.00

Pile Rapping

m2

96.10

750,000.00

1,250,000.00

72,075,000.00

120,125,000.00

192,200,000.00

BETON BERTULANG
1

Pelat Lantai t=30 cm -- 4.5x24 + 2x5.1x7.4

m3

43.70

5,844,905.00

1,464,672.00

255,422,348.50

64,006,166.40

319,428,514.90

Balok 130x125 -- 1.3 x 0.85 x (5*4.5+10)

m3

40.10

6,514,695.00

1,539,307.00

261,239,269.50

61,726,210.70

322,965,480.20

Pengisi Tiang -- 0.283x2.25x52

m3

10.80

6,499,020.00

1,539,307.00

70,189,416.00

16,624,515.60

86,813,931.60

SUB TOTAL III - SUB-PLATFORM


2.4.

###

TRESTLE

IV PEKERJAAN TRESTLE L=187x4.5 m


TIANG PANCANG Diameter 508mm
Tiang L=12m

Titik

39.00

Tiang L=12 +6=18m

Titik

41.00

Tiang L=12 +12=24m

Titik

41.00

Transportation Tiang Pancang

kg

Loading Unloading tiang

2,190.00

###

82,500.00

180,675,000.00

180,675,000.00

Pemancangan

2,190.00

632,500.00

1,385,175,000.00

1,385,175,000.00

Pengecatan Tiang (12 m)

1,452.00

148,500.00

215,622,000.00

215,622,000.00

Penyambungan Tiang

Bh

82.00

825,000.00

67,650,000.00

67,650,000.00

Pemotongan Kepala Tiang

Bh

121.00

495,000.00

59,895,000.00

59,895,000.00

Cathodic protection

Tiang

121.00

6,700,000.00

1,250,000.00

810,700,000.00

151,250,000.00

961,950,000.00

Pile Rapping

m2

579.00

750,000.00

1,250,000.00

434,250,000.00

723,750,000.00

1,158,000,000.00

252.50

5,844,905.00

1,464,672.00

369,829,680.00

1,845,668,192.50

BETON BERTULANG
1

Pelat Lantai t=30 cm -- 187x4.5x0.3

m3

###

Pelat Lantai t=30 cm -- 10x1.75x2x0.3

m3

10.50

5,844,905.00

1,464,672.00

61,371,502.50

15,379,056.00

76,750,558.50

Balok 120/100 -- 0.7x1.2x4.5x39

m3

147.40

6,514,695.00

1,539,307.00

960,266,043.00

226,893,851.80

1,187,159,894.80

RENCANA ANGGARAN BIAYA (ENGINEERING ESTIMATE)


EXTENTION JETTY PT. AGRO NUSA ABADI
DESA BAHONTALU, KECAMATAN PETASIA, KABUPATEN MOROWALI,
PROVINSI SULAWESI TENGAH
No.

Rincian Item Pekerjaan

Satuan Volume

Harga Satuan (Rp.)


Bahan
Upah / Alat

Jumlah Biaya (Rp.)


Bahan
Upah / Alat

Balok 120/100 -- 0.7x1.2x1.75x4

m3

5.90

6,514,695.00

1,539,307.00

38,436,700.50

9,081,911.30

47,518,611.80

Pengisi Tiang -- 0.202x2.25x121

m3

55.00

6,499,020.00

1,539,307.00

357,446,100.00

84,661,885.00

442,107,985.00

Kerb. + Tiang Railing

m3

13.40

6,514,695.00

1,539,307.00

87,296,913.00

20,626,713.80

107,923,626.80

Bantalan Pipa

m3

1.20

6,514,695.00

1,539,307.00

7,817,634.00

1,847,168.40

9,664,802.40

Pipa Railing Diameter 763 mm t=5 mm

Kg

3,252.30

23,100.00

13,750.00

75,128,130.00

44,719,125.00

119,847,255.00

SUB TOTAL IV - TRESTLE


2.5.

Total Biaya
(Rp.)

###

BREASTING DOLPHIN

V PEKERJAAN BREASTING DOLPHIN (2 Unit)

Titik

13.00

TIANG PANCANG Diameter 600 mm


1

Transportation Tiang Pancang

Kg

Loading Unloading tiang

###
624.00

82,500.00

51,480,000.00

51,480,000.00

Pemancangan

624.00

632,500.00

394,680,000.00

394,680,000.00

Pengecatan Tiang (12 m)

312.00

148,500.00

46,332,000.00

46,332,000.00

Penyambungan Tiang

Bh

26.00

825,000.00

21,450,000.00

21,450,000.00

Pemotongan Kepala Tiang

Bh

26.00

495,000.00

12,870,000.00

12,870,000.00

Cathodic protection

Bh

26.00

6,700,000.00

1,250,000.00

174,200,000.00

32,500,000.00

206,700,000.00

Pile Rapping

m2

120.30

750,000.00

1,250,000.00

90,225,000.00

150,375,000.00

240,600,000.00

m3

122.00

6,514,695.00

1,539,307.00

794,792,790.00

187,795,454.00

982,588,244.00

m3

15.00

6,514,695.00

1,539,307.00

97,720,425.00

23,089,605.00

120,810,030.00

BETON BERTULANG
1

Pile Cap

Pengisi Tiang -- 0.283x2.0x123

-- 6x6.5x1.25+1.5x6.5x1.25

FASILITAS
1

Bollard Ckapasitas 35 Ton

set

2.00

27,500,000.00

3,300,000.00

55,000,000.00

6,600,000.00

61,600,000.00

Fender V600 L3000

set

4.00

68,475,000.00

8,250,000.00

273,900,000.00

33,000,000.00

306,900,000.00

SUB TOTAL V - BREASTING DOLPHIN


2.6.

###

MOORING DOLPHIN

VI PEKERJAAN MOORING DOLPHIN (4 Unit)


TIANG PANCANG Diameter 600 mm t=24 m

Titik

Transportation Tiang Pancang

Kg

Loading Unloading tiang

6.00
###
576.00

per Dolphin
-

82,500.00

47,520,000.00

47,520,000.00

RENCANA ANGGARAN BIAYA (ENGINEERING ESTIMATE)


EXTENTION JETTY PT. AGRO NUSA ABADI
DESA BAHONTALU, KECAMATAN PETASIA, KABUPATEN MOROWALI,
PROVINSI SULAWESI TENGAH
No.

Rincian Item Pekerjaan


3

Pemancangan

4
5

Satuan Volume

Harga Satuan (Rp.)


Bahan
Upah / Alat

Jumlah Biaya (Rp.)


Bahan
Upah / Alat

Total Biaya
(Rp.)

576.00

632,500.00

364,320,000.00

364,320,000.00

Pengecatan Tiang (12 m)

288.00

148,500.00

42,768,000.00

42,768,000.00

Penyambungan Tiang

Bh

24.00

825,000.00

19,800,000.00

19,800,000.00

Pemotongan Kepala Tiang

Bh

24.00

495,000.00

11,880,000.00

11,880,000.00

Cathodic protection

Bh

24.00

6,700,000.00

1,250,000.00

160,800,000.00

30,000,000.00

190,800,000.00

Pile Rapping

m2

124.10

750,000.00

1,250,000.00

93,075,000.00

155,125,000.00

248,200,000.00

BETON BERTULANG
1

Pile Cap

m3

61.30

6,514,695.00

1,539,307.00

399,350,803.50

94,359,519.10

493,710,322.60

Pengisi Tiang -- 0.283x2.0x123

m3

13.60

6,514,695.00

1,539,307.00

88,599,852.00

20,934,575.20

109,534,427.20

set

4.00

27,500,000.00

3,300,000.00

110,000,000.00

13,200,000.00

123,200,000.00

FASILITAS
1

Bollard Kapasitas 35 Ton

SUB TOTAL VI - MOORING DOLPHIN


2.7.

###

CATWALK

VII PEKERJAAN CATWALK (2 Unit)


Struktur Baja
1

WF 300x150

Kg

5,285.00

15,950.00

8,250.00

84,295,750.00

43,601,250.00

127,897,000.00

Siku 60x60x6

Kg

780.00

15,950.00

8,250.00

12,441,000.00

6,435,000.00

18,876,000.00

Kanal C-150x7.5x9 - 24 kg/m'

Kg

1,728.00

15,950.00

8,250.00

27,561,600.00

14,256,000.00

41,817,600.00

Pengecatan Baja Profil

Ls

1.00

49,500,000.00

49,500,000.00

Railing - Pipa Dia. 76.3mm t=5 mm - Galvanis

Kg

2,707.00

25,410.00

15,125.00

68,784,870.00

40,943,375.00

109,728,245.00

Grating - Galvanis

Kg

2,160.00

25,410.00

15,125.00

54,885,600.00

32,670,000.00

87,555,600.00

49,500,000.00

SUB TOTAL VII - CATWALK


2.8.

###

ALAT NAVIGASI

VIII ALAT NAVIGASI


1

Light Bouy

unit

6.00

247,500,000.00

165,000,000.00

Lampu Suar

unit

1.00

82,500,000.00

5,500,000.00

###
82,500,000.00

990,000,000.00

2,475,000,000.00

5,500,000.00

88,000,000.00

SUB TOTAL VIII - ALAT NAVIGASI


SUB TOTAL I + II + III + IV + V + VI + VII + VIII

###
###

PEKERJAAN PEMBANGUNAN PERPANJANGAN DERMAGA UTARA PELABUHAN BATU AMPAR - BATAM

No.

Uraian

Sat

EE
Hrg Sat

Vol

CE
Jumlah

Vol

Hrg Sat

10000

GENERAL

10001
10002
10003
10004
10005

Mobilisasi & Demobilisasi


Stakeout and positioning
Penerangan & Keselamatan Kerja
Fasilitas Sementara (direksi kit, mess, dll)
Dokumentasi/As built drawing

l.s
l.s
l.s
l.s
l.s

20000
21000
21100
21101
21102
21003
21004
21005
21006
21007

DERMAGA-1 (7577.92 m2 ), SISTEM DECK ON PILE


Pekerjaan Pemancangan (Total = 253 nos)
Panjang Tiang = 24m
- Steel Pipe Pile (SPP =812 t=16mm)
ton
- Transport Ke Lokasi dan Positioning
m'
- Pemancangan
m'
- Pemotongan Tiang
nos
- Beton Pengisi Tiang
m
- Pelindung Tiang (HDPE)
m2
- Cathodic protection (alluminium anode)
nos

1,273.94
4,056.00
4,056.00
169.00
161.51
1,508.90
169.00

12,734,100.00
114,438.83
765,027.25
469,600.00
8,267,800.00
2,823,500.00
22,616,500.00

16,222,537,329.56
464,163,908.00
3,102,950,526.00
79,362,400.00
1,335,321,216.49
4,260,381,037.04
3,822,188,500.00

1,273.94
4,056.00
4,056.00
169.00
161.51
1,508.90
169.00

12,734,100.00
114,438.83
765,027.25
469,600.00
8,267,800.00
2,823,500.00
22,616,500.00

16,222,537,329.56
464,163,908.00
3,102,950,526.00
79,362,400.00
1,335,321,216.49
4,260,381,037.04
3,822,188,500.00

21200
21201
21202
21203
21204
21205
21206
21207

Panjang Tiang = 22m


- Steel Pipe Pile (SPP =812 t=16mm)
- Transport Ke Lokasi dan Positioning
- Pemancangan
- Pemotongan Tiang
- Beton Pengisi Tiang
- Pelindung Tiang (HDPE)
- Cathodic protection (alluminium anode)

580.44
1,848.00
1,848.00
84.00
80.28
749.99
84.00

12,734,100.00
114,438.83
765,027.25
469,600.00
8,267,800.00
2,823,500.00
22,616,500.00

7,391,333,576.19
211,482,964.00
1,413,770,358.00
39,446,400.00
663,709,953.76
2,117,585,840.90
1,899,786,000.00

580.44
1,848.00
1,848.00
84.00
80.28
749.99
84.00

12,734,100.00
114,438.83
765,027.25
469,600.00
8,267,800.00
2,823,500.00
22,616,500.00

7,391,333,576.19
211,482,964.00
1,413,770,358.00
39,446,400.00
663,709,953.76
2,117,585,840.90
1,899,786,000.00

22000
22001
22002
22003
22004

Pekerjaan Beton Bertulang K 450 - Insitu f'c 35 Mpa (K 430)


Pile cap (HS)
m
Balok Memanjang (LB)
m
Balok Melintang (CB)
m
Slab t=400mm
m

1,641.58
1,713.95
884.70
1,808.34

5,085,500.00
6,914,900.00
6,914,900.00
4,780,600.00

8,348,242,477.96
11,851,827,360.35
6,117,591,285.30
8,644,928,022.02

1,641.58
1,713.95
884.70
1,808.34

5,085,500.00
6,914,900.00
6,914,900.00
4,780,600.00

8,348,242,477.96
11,851,827,360.35
6,117,591,285.30
8,644,928,022.02

23000
23001
23002

Sistem Fender
Pengadaan fender Type Cell 1450H (incl. frontal fra nos
Bollard 100 Ton
nos

16.00
8.00

424,800,000.00
40,000,000.00

6,796,800,000.00
320,000,000.00

16.00
8.00

424,800,000.00
40,000,000.00

6,796,800,000.00
320,000,000.00

ton
m'
m'
nos
m
m2
nos

2,013,959,500.00

Jumlah

1.00
1.00
1.00
1.00
1.00

1,207,356,400.00
196,647,100.00
169,956,000.00
340,000,000.00
100,000,000.00

1,207,356,400.00
196,647,100.00
169,956,000.00
340,000,000.00
100,000,000.00

6,286,803,100.00
1.00
1.00
1.00
1.00
1.00

5,480,200,000.00
196,647,100.00
169,956,000.00
340,000,000.00
100,000,000.00

85,103,409,155.57

5,480,200,000.00
196,647,100.00
169,956,000.00
340,000,000.00
100,000,000.00

85,103,409,155.57

30000
31000
31100
31101
31102
31103
31104
31105
31106
31107

EE
Vol
Hrg Sat
DERMAGA-2 ( 6338.5 m2 ), SISTEM DECK ON PILE DENGAN DEAD ANCHORAGE
Pekerjaan Pemancangan (Total = 210 nos)
Panjang Tiang = 22m
- Steel Pipe Pile (SPP =812 t=16mm)
ton
338.59
12,734,100.00
- Transport Ke Lokasi dan Positioning
m'
1,078.00
114,438.83
- Pemancangan
m'
1,078.00
765,027.25
- Pemotongan Tiang
nos
49.00
469,600.00
- Beton Pengisi Tiang
m
46.83
8,267,800.00
- Pelindung Tiang (HDPE)
m2
437.49
2,823,500.00
- Cathodic protection (alluminium anode)
nos
49.00
22,616,500.00

31200
31201
31202
31203
31204
31205
31206
31207
31208
31209

Panjang Tiang = 20m (dengan dead anchor 3 m)


- Steel Pipe Pile (SPP =812 t=16mm)
- Transport Ke Lokasi dan Positioning
- Pemancangan
- Pemotongan Tiang
- Beton Pengisi Tiang
- Pelindung Tiang (HDPE)
- Cathodic protection (alluminium anode)
- Pengeboran Tanah Keras @ L=3.5 m'
- Beton Bertulang K 450 Untuk Dead Anchor

ton
m'
m'
nos
m
m2
nos
m'
m

351.78
1,120.00
1,120.00
56.00
53.52
499.99
56.00
196.00
187.31

31300
31301
31302
31303
31304
31305
31306
31307
31308
31309

Panjang Tiang = 19m (dengan dead anchor 3 m)


- Steel Pipe Pile (SPP =812 t=16mm)
- Transport Ke Lokasi dan Positioning
- Pemancangan
- Pemotongan Tiang
- Beton Pengisi Tiang
- Pelindung Tiang (HDPE)
- Cathodic protection (alluminium anode)
- Pengeboran Tanah Keras @ L=3.5 m'
- Beton Bertulang K 450 Untuk Dead Anchor

ton
m'
m'
nos
m
m2
nos
m'
m

32000
32001
32002
32003
32004

Pekerjaan Beton Bertulang K 450 - Insitu f'c 35 Mpa (K 430)


Pile cap (HS)
m
Balok Memanjang (LB)
m
Balok Melintang (CB)
m
Slab t=400mm
m

33000
33001
33002

Sistem Fender
Pengadaan fender Type Cell 1450H (incl. frontal fra nos
Bollard 100 Ton
nos

No.

Uraian

Sat

CE
Jumlah
72,195,724,277.74

Vol

Hrg Sat

Jumlah
72,195,724,277.74

4,311,611,252.78
123,365,062.33
824,699,375.50
23,010,400.00
387,164,139.69
1,235,258,407.19
1,108,208,500.00

338.59
1,078.00
1,078.00
49.00
46.83
437.49
49.00

12,734,100.00
114,438.83
765,027.25
469,600.00
8,267,800.00
2,823,500.00
22,616,500.00

4,311,611,252.78
123,365,062.33
824,699,375.50
23,010,400.00
387,164,139.69
1,235,258,407.19
1,108,208,500.00

12,734,100.00
114,438.83
765,027.25
469,600.00
8,267,800.00
2,823,500.00
22,616,500.00
1,603,200.00
4,977,700.00

4,479,596,106.78
128,171,493.33
856,830,520.00
26,297,600.00
442,473,302.51
1,411,723,893.93
1,266,524,000.00
314,227,200.00
932,381,982.22

351.78
1,120.00
1,120.00
56.00
53.52
499.99
56.00
196.00
187.31

12,734,100.00
114,438.83
765,027.25
469,600.00
8,267,800.00
2,823,500.00
22,616,500.00
1,603,200.00
4,977,700.00

4,479,596,106.78
128,171,493.33
856,830,520.00
26,297,600.00
442,473,302.51
1,411,723,893.93
1,266,524,000.00
314,227,200.00
932,381,982.22

626.61
1,995.00
1,995.00
105.00
100.35
937.48
105.00
367.50
351.21

12,734,100.00
114,438.83
765,027.25
469,600.00
8,267,800.00
2,823,500.00
22,616,500.00
1,603,200.00
4,977,700.00

7,979,280,565.21
228,305,472.50
1,526,229,363.75
49,308,000.00
829,637,442.20
2,646,982,301.12
2,374,732,500.00
589,176,000.00
1,748,216,216.66

626.61
1,995.00
1,995.00
105.00
100.35
937.48
105.00
367.50
351.21

12,734,100.00
114,438.83
765,027.25
469,600.00
8,267,800.00
2,823,500.00
22,616,500.00
1,603,200.00
4,977,700.00

7,979,280,565.21
228,305,472.50
1,526,229,363.75
49,308,000.00
829,637,442.20
2,646,982,301.12
2,374,732,500.00
589,176,000.00
1,748,216,216.66

1,385.86
1,516.70
711.65
1,506.86

5,085,500.00
6,914,900.00
6,914,900.00
4,780,600.00

7,047,785,563.09
10,487,862,436.41
4,920,954,010.50
7,203,711,170.04

1,385.86
1,516.70
711.65
1,506.86

5,085,500.00
6,914,900.00
6,914,900.00
4,780,600.00

7,047,785,563.09
10,487,862,436.41
4,920,954,010.50
7,203,711,170.04

15.00
8.00

424,800,000.00
40,000,000.00

6,372,000,000.00
320,000,000.00

15.00
8.00

424,800,000.00
40,000,000.00

6,372,000,000.00
320,000,000.00

No.

Uraian

Sat

40000
41000
41001
41002

Vol
DERMAGA-3 (29725.42 m2), SISTEM TURAP TYPE SECANT PILE
Pekerjaan Reklamasi
Timbunan tanah
m
236,000.00
Pengambilan timbunan tanah di depan secant pile da m
31,350.00

42000
42100
42110
42111
42112

Secant Pile
a. Primary Pile (L=24 m)
Zona 1
- Bored Pile =880mm L=12m - Tanah Lunak
- Bored Pile =880mm L=12m - Tanah Keras

m'
m'

42120
42121
42122
42123
42124

Zona 2
- Bored Pile =880mm L=16m - Tanah Lunak
- Bored Pile =880mm L=8m - Tanah Keras
- Beton Tanpa Tulangan
- Pemotongan Tiang

EE
Hrg Sat

CE
Jumlah
128,317,180,313.56

Vol

Hrg Sat

Jumlah
164,497,233,629.26

75,800.00
28,694.74

17,888,800,000.00
899,580,084.29

236,000.00
31,350.00

166,589.00
100,650.00

39,315,004,000.00
3,155,377,500.00

1,296.00
1,296.00

1,054,600.00
1,603,200.00

1,366,761,600.00
2,077,747,200.00

1,296.00
1,296.00

1,565,000.00
2,235,000.00

2,028,240,000.00
2,896,560,000.00

m'
m'
m
nos

2,096.00
1,048.00
2,761.89
239.00

1,054,600.00
1,603,200.00
2,291,500.00
332,900.00

2,210,441,600.00
1,680,153,600.00
6,328,876,035.09
79,563,100.00

2,096.00
1,048.00
2,761.89
239.00

1,565,000.00
2,235,000.00
2,291,500.00
332,900.00

3,280,240,000.00
2,342,280,000.00
6,328,876,035.09
79,563,100.00

42200
42210
42211
42212

b. Secondary Pile (L=24 m)


Zona 1
- Bored Pile =1200mm L=12m - Tanah Lunak & Co m'
- Bored Pile =1200mm L=12m - Tanah Keras & Con m'

1,296.00
1,296.00

1,746,100.00
2,022,700.00

2,262,945,600.00
2,621,419,200.00

1,296.00
1,296.00

2,224,000.00
3,176,000.00

2,882,304,000.00
4,116,096,000.00

42220
42221
42222
42223
42224

Zona 2
- Bored Pile =1200mm L=16m - Tanah Lunak & Co m'
- Bored Pile =1200mm L=8m - Tanah Keras & Conc m'
- Beton Bertulang K 450
m
- Pemotongan Tiang
nos

2,096.00
1,048.00
6,081.81
239.00

1,746,100.00
2,022,700.00
5,577,500.00
332,900.00

3,659,825,600.00
2,119,789,600.00
33,921,290,913.87
79,563,100.00

2,096.00
1,048.00
6,081.81
239.00

2,224,000.00
3,176,000.00
5,577,500.00
332,900.00

4,661,504,000.00
3,328,448,000.00
33,921,290,913.87
79,563,100.00

43000
43001
43002
43003
43004

Crane Foundation (secant pile)


- Bored Pile =880mm L=13m - Tanah Lunak
- Bored Pile =880mm L=2m - Tanah Keras
- Beton Bertulang K 450
- Pemotongan Tiang

m'
m'
m
nos

1,176.00
588.00
766.35
84.00

1,054,600.00
1,603,200.00
5,577,500.00
332,900.00

1,240,209,600.00
942,681,600.00
4,274,303,435.28
27,963,600.00

1,176.00
588.00
766.35
84.00

1,565,000.00
2,235,000.00
5,577,500.00
332,900.00

1,840,440,000.00
1,314,180,000.00
4,274,303,435.28
27,963,600.00

44000
44001
44002
44003
44004
44005

Pekerjaan Beton Bertulang - Insitu (K 450)


Caping beam Untuk secant pile
- Block Fender
Pile Cap Untuk Crane Foundation
Balok Crane
Rigid pavement

m
m
m
m
m

1,996.41
213.75
332.64
451.93
4,239.90

4,878,400.00
4,356,500.00
4,018,300.00
6,914,900.00
3,313,100.00

9,739,283,655.73
931,201,875.00
1,336,647,312.00
3,125,030,012.30
14,047,212,690.00

1,996.41
213.75
332.64
451.93
4,239.90

4,878,400.00
4,356,500.00
4,018,300.00
6,914,900.00
3,313,100.00

9,739,283,655.73
931,201,875.00
1,336,647,312.00
3,125,030,012.30
14,047,212,690.00

45000

Ground Anchor

unit

117.00

332,900.00

38,949,300.00

117.00

34,433,200.00

4,028,684,400.00

46000
46001
46002

Sistem Fender
Pengadaan fender Type Cell 1450H (incl. frontal fra nos
Bollard 100 Ton
nos

25.00
12.00

424,800,000.00
40,000,000.00

10,620,000,000.00
480,000,000.00

25.00
12.00

424,800,000.00
40,000,000.00

10,620,000,000.00
480,000,000.00

46003

Geobag

14,389.80

300,000.00

4,316,940,000.00

14,389.80

300,000.00

4,316,940,000.00

287,630,273,246.86

328,083,170,162.57

Analisa
Jenis Pekerjaan
Satuan Pekerjaan
Jumlah Harga Satuan

N0.

:
:
:
:

URAIAN

ANL. 07
Balok beton bertulang (250 kg besi + bekisting) (pengisi tiang)
m2
Rp. 8,038,327

SATUAN

HARGA
KOEFISIE
SATUAN
N
(Rp.)

TENAGA KERJA
1 Upah pengecoran
m3
1.00
265,039
2 Upah pembesian
kg
250.00
1,649
3 Upah bekisting
m2
1.00
111,911
Sub Jumlah.
B. BAHAN
1 Pengecoran
1.00
m3
1,545,170
2 Pembesian
250.00
kg
17,922
3 Bekisting
1.00
m2
473,275
Sub Jumlah.
C. PERALATAN
1 Pengecoran
ls
1.0000
750,000
2 Pembesian
ls
1.0000
3 Bekisting
ls
1.0000
Sub Jumlah.
D. Jumlah

JUMLAH
HARGA
(Rp.)

KETERANGAN

A.

Analisa
Jenis Pekerjaan
Satuan Pekerjaan
Jumlah Harga Satuan

N0.

URAIAN

:
:
:
:

265,039
412,357
111,911
789,307

1,545,170
4,480,575
473,275
6,499,020

750,000
750,000.00
C
8,038,327 D = A + B + C

ANL. 08
Plat beton bertulang (150 kg besi + bekisting) (plat lantai)
m3
Rp. 7,309,577

SATUAN

HARGA
KOEFISIE
SATUAN
N
(Rp.)

TENAGA KERJA
1 Upah pengecoran
m3
1.00
267,977
2 Upah pembesian
kg
200.00
1,668
3 Upah bekisting
m2
1.00
113,151
Sub Jumlah.
B. BAHAN
1 Pengecoran
1.00
m3
1,545,170
2 Pembesian
200.00
kg
17,922
3 Bekisting
1.00
m2
715,275
Sub Jumlah.
C. PERALATAN
1 Pengecoran
ls
1.0000
750,000
2 Pembesian
ls
1.0000
3 Bekisting
ls
1.0000
Sub Jumlah.
D. Jumlah

JUMLAH
HARGA
(Rp.)

KETERANGAN

A.

267,977
333,543
113,151
714,672

1,545,170
3,584,460
715,275
5,844,905

750,000
750,000.00
C
7,309,577 D = A + B + C

DAFTAR MATERIAL
No
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40

Uraian
Harga
Satuan
50,000
bh
Nok Genteng metal tebal
Rabung atap type deck t
45,000
m
34,000
kg
Baut atap komplit ring kar
55,000
lbr
Plywood 4'x8'x6mm
25,000
lbr
List kayu profil
Ubin keramik 30x30 cm
3,500
bh
1,500
kg
Semen warna
Ubin kramik 20x25
3,000
bh
Cat menie
45,000
kg
Plamir
25,000
kg
Cat dasar kuda terbang
25,000
kg
Cat penutup 2 kali kuda t
25,000
kg
35,000
kg
Cat dasar Avitex
42,000
kg
Cat penutup Avitex
20,000
kg
Cat Tembok veoteks
Closet Jongkok Porselin
250,000
bh
Urinoir
400,000
bh
Wastafel
300,000
bh
Pipa PVC tipe AW diameter 30,000
m
Door holder
60,000
bh
Kait angin
22,000
bh
Engsel angin
32,000
bh
Engsel pintu
15,000
bh
Besi profil
10,000
kg
Pipa Pesat
15,000
kg
Meni besi
15,000
kg
Floor drain
15,000
bh
Pipa GIP dia. 3"
65,000
m
Pipa PVC tipe AW 3"
15,000
m
Pintu besi lipat
250,000
m2
Kayu sembarang keras pa 4 Unit
m2
Kawat nyamuk
55,000
m2
Kawat Bronjong
15,000
m2
Seng plat 3'x6' bjls 20
50,000
lbr
Pipa PVC tipe AW 2"
20,000
m
Kunci tanam biasa
75,000
bh
Geotekstile
12,500
m2
Rangka Plafond
60,000
m2
Upah Jahit
3,000
m
Anchor bolt 16
6,000
bh

Anda mungkin juga menyukai