REKAPITULASI

DAFTAR KUANTITAS DAN HARGA

UNIT KERJA : DINAS PENDIDIKAN KABUPATEN TANAH BUMBU


PEKERJAAN : PEMBANGUNAN RUANG KELAS BARU TK FLAMBOYAN
LOKASI : DESA MAKMUR MULIA , KECAMATAN SATUI
TAHUN ANGGARAN : 2024

NO URAIAN PEKERJAAN JUMLAH HARGA

(1) (2) (3)

I PEKERJAAN PERSIAPAN 1,500,000.00


II PEKERJAAN TANAH 12,342,449.17
III PEKERJAAN PONDASI 10,801,883.40
IV PEKERJAAN BETON 9,172,325.15
V PEKERJAAN PENULANGAN/PEMBESIAN 10,227,508.52
VI PEKERJAAN BEKISTING 8,323,131.78
VII PEKERJAAN DINDING DAN PLESTERAN 44,984,706.69
VIII PEKERJAAN KUSEN PINTU JENDELA VENTILASI 10,585,377.18
IX PEKERJAAN PASANG KUNCI DAN ALAT PENGGANTUNG 2,427,832.00
X PEKERJAAN KUDA-KUDA, PENUTUP ATAP & PLAFOND 66,407,369.78
XI PEKERJAAN INSTALASI LISTRIK 2,478,000.00
XII PEKERJAAN LAIN LAIN 450,000.00
JUMLAH 179,700,583.66
PPN 11% 19,767,064.20
TOTAL 199,467,647.86
DIBULATKAN 199,000,000.00
Terbilang: Seratus Sembilan Puluh Sembilan Juta Rupiah

Batulicin, 2024

Diperiksa : Disiapkan
Dinas Pendidikan Kab. Tanah Bumbu CV. SUKSES JAYA MUDA
Pejabat Pelaksana Teknis Kegiatan (PPTK)

MUTAWALLY, S.E SYAMSURI


NIP.19690801 200701 1 046 Direktur

Mengetahui / Menyetujui :
Dinas Pendidikan Kab. Tanah Bumbu
Pengguna Anggaran

AMILUDDIN, S.Pd. MM
NIP. 19670719 199412 1 004
DAFTAR KUANTITAS DAN HARGA

UNIT KERJA : DINAS PENDIDIKAN KABUPATEN TANAH BUMBU


PEKERJAAN : PEMBANGUNAN RUANG KELAS BARU TK FLAMBOYAN
LOKASI : DESA MAKMUR MULIA , KECAMATAN SATUI
TAHUN ANGGARAN : 2024

NO URAIAN PEKERJAAN ANLS VOLUME HARGA SATUAN JUMLAH HARGA

(1) (2) (3) (4) (5) (6)

I PEKERJAAN PERSIAPAN
1 Pembersihan Lokasi Awal dan Akhir - 1.00 Ls 1,000,000.00 1,000,000.00
2 Pengukuran dan Pemasangan Bowplank - 1.00 Ls 500,000.00 500,000.00
Sub Total I 1,500,000.00
II PEKERJAAN TANAH
1 Pek. Galian Tanah Pondasi 1.7.1.a (c) 4.30 M3 94,875.00 407,962.50
2 Pek. Urugan Tanah Kembali 1.7.2.a (c) 1.43 M3 68,750.00 98,541.67
3 Pek. Urugan Pasir Bawah Lantai 1.7.2.d (c) 3.60 M3 235,950.00 849,420.00
4 Pek. Urugan Tanah Bawah Lantai 1.7.2.e (c) 41.40 M3 265,375.00 10,986,525.00
Sub Total II 12,342,449.17
III PEKERJAAN PONDASI
1 Pek. Pasangan Batu Gunung / Kali camp 1 : 4 2.1.1.d.(a) 10.16 M3 1,063,177.50 10,801,883.40
Sub Total III 10,801,883.40
IV PEKERJAAN BETON
1 Cor Lantai Beton Tebal 5 Cm A.4.1.1.1 3.60 M3 1,056,073.07 3,801,863.06
2 Pekerjaan Beton Bertulang untuk :
a. Sloof Beton 15/20 (Mutu fc' = 16,9 Mpa) A.4.1.1.6 1.47 M3 1,205,371.88 1,771,896.67
b. Kolom Beton 20/20 (Mutu fc' = 16,9 Mpa) A.4.1.1.6 1.27 M3 1,205,371.88 1,533,233.03
c. Kolom Beton 13/13 (Mutu fc' = 16,9 Mpa) A.4.1.1.6 0.20 M3 1,205,371.88 236,301.10
d. Ringbalk 15/15 (Mutu fc' = 16,9 Mpa) A.4.1.1.6 1.52 M3 1,205,371.88 1,829,031.29
Sub Total IV 9,172,325.15
V PEKERJAAN PENULANGAN/PEMBESIAN
1 Penulangan / Pembesian
a. Sloof Beton 15/20 2.2.6.1.b.(c) 200.74 Kg 18,560.30 3,725,748.45
b. Kolom Beton 20/20 2.2.6.1.b.(c) 140.87 Kg 18,560.30 2,614,516.65
c. Kolom Beton 13/13 2.2.6.1.b.(c) 24.47 Kg 18,560.30 454,198.89
d. Ringbalk 15/15 2.2.6.1.b.(c) 184.97 Kg 18,560.30 3,433,044.53
Sub Total V 10,227,508.52
VI PEKERJAAN BEKISTING
1 Begisting
a. Sloof Beton 15/20 A.4.1.1.19 9.80 M2 213,334.00 2,090,673.20
b. Kolom Beton 20/20 A.4.1.1.20 9.68 M2 380,072.00 3,679,096.96
c. Kolom Beton 13/13 A.4.1.1.20 1.04 M2 380,072.00 395,274.88
d. Ringbalk 15/15 A.4.1.1.19 10.12 M2 213,334.00 2,158,086.74
Sub Total VI 8,323,131.78
VII PEKERJAAN DINDING DAN PLESTERAN
1 Pembongkaran 1 m3 Dinding Tembok Pagar - 5.40 M3 86,152.00 465,220.80
2 Pek. Pasang Dinding batu bata 1/2 Bata Camp. 1 : 4 A.4.4.1.9 111.62 M2 147,097.50 16,419,022.95
3 Pek. Plesteran Dinding tebal 15 mm Camp. 1 : 4 3.2.2.(c) 223.24 M2 78,441.00 17,511,168.84
4 Pek. Acian 3.2.2.(d) 230.44 M2 45,952.50 10,589,294.10
Sub Total VII 44,984,706.69
VIII PEKERJAAN KUSEN PINTU JENDELA VENTILASI
1 Pek. Kusen Pintu Ulin A.4.6.1.1 0.06 M3 18,587,525.00 1,133,839.03
2 Pek. Kusen Ventilasi Kaca diatas pintu A.4.6.1.1 0.03 M3 18,587,525.00 483,275.65
3 Pek. Kusen Jendela A.4.6.1.1 0.15 M3 18,587,525.00 2,825,303.80
4 Pek. Kusen Ventilasi Kaca diatas jendela A.4.6.1.1 0.09 M3 18,587,525.00 1,710,052.30
5 Pek. Kisi-kisi Ventilasi Ulin - 4.00 Bh 85,000.00 340,000.00
6 Pek. Pasangan Daun Pintu Ulin .A.4.6.1.6 3.69 M2 457,160.00 1,686,920.40
7 Pemasangan Kaca Polos Tebal 5 mm A.4.6.2.17 3.80 M2 171,182.00 650,491.60
8 Pek.Pasangan Daun Jendela + Kaca Bening t=5mm .A.4.6.1.6 3.84 M2 457,160.00 1,755,494.40
Sub Total VIII 10,585,377.18
IX PEKERJAAN PASANG KUNCI DAN ALAT PENGGANTUNG
1 Pek.Pas.Kunci Tanam Biasa A.4.6.2.2 2.00 Bh 276,485.00 552,970.00
2 Pek.Pas.Engsel Pintu 4" A.4.6.2.5 6.00 Bh 62,557.00 375,342.00
3 Pek.Pas.Engsel Jendela 3" A.4.6.2.6 16.00 Bh 38,032.50 608,520.00
4 Pek.Pas.Pegangan Jendela - 8.00 Bh 22,000.00 176,000.00
5 Pek.Pas.Grendel Jendela - 8.00 Bh 25,000.00 200,000.00
6 Pek.Pas.Kait Angin Jendela - 16.00 Bh 30,000.00 480,000.00
7 Pek.Pas.Grendel Pintu - 1.00 Bh 35,000.00 35,000.00
Sub Total IX 2,427,832.00
X PEKERJAAN KUDA-KUDA, PENUTUP ATAP & PLAFOND
1 Pek. Rangka Atap Konstruksi Baja Ringan (Standar Pabrikasi) A.4.2.1.22. 119.08 M2 294,277.50 35,042,564.70
2 Pek. Atap genteng Metal setara multi roof A.4.5.2.1.a 119.08 M2 92,851.00 11,056,697.08
3 Pemasangan 1 m2 Rangka Besi Hollow Galvanis 40.40 mm, Modul 60 x 60 cm, untuk Plafon A.4.2.1.21 54.00 M2 173,910.00 9,391,140.00
4 Pemasangan 1 m2 Langit-Langit Papan Kalsiboard, Tebal 3,5 mm A.4.5.1.7. a 54.00 M2 57,354.00 3,097,116.00
5 Pemasangan 1 m' List Langit-Langit Kayu Profil A.4.5.1.10 108.00 M' 31,515.00 3,403,620.00
6 Pek. Pasang Nok atap genteng metal type C A.4.5.2.38. 10.40 M' 80,080.00 832,832.00
7 Pek. List Kalsiplank A.4.6.1.21. 43.70 M' 82,000.00 3,583,400.00
Sub Total X 66,407,369.78
XI PEKERJAAN INSTALASI LISTRIK
1 Pas Titik lampu - 6.00 Ttk 150,000.00 900,000.00
2 Pas. Lampu SL 40 Setara Philips - 6.00 Bh 85,000.00 510,000.00
3 Pas. Saklar Ganda - 3.00 Bh 47,000.00 141,000.00
4 Pas. Stop Kontak Setara Broco - 1.00 Bh 47,000.00 47,000.00
5 Pas. MCB - 1.00 Bh 180,000.00 180,000.00
6 Penyambungan Instalasi Listrik - 1.00 Ls 700,000.00 700,000.00
NO URAIAN PEKERJAAN ANLS VOLUME HARGA SATUAN JUMLAH HARGA

2,478,000.00
XII PEKERJAAN LAIN LAIN
1 Pembuatan Prasasti Uk.30 cm x 20 cm - 1.00 Bh 450,000.00 450,000.00
Sub Total XI 450,000.00
179,700,583.66
PERHITUNGAN PERKIRAAN VOLUME PEKERJAAN

PEKERJAAN : PEMBANGUNAN RUANG KELAS BARU TK FLAMBOYAN


LOKASI : DESA MAKMUR MULIA , KECAMATAN SATUI
TAHUN ANGGARAN : 2024

NO URAIAN PERHITUNGAN VOLUME SATUAN

I PEKERJAAN PERSIAPAN

1 Pembersihan Lokasi Awal dan Akhir 1.00 Ls

2 Pengukuran dan Pemasangan Bowplank 34.00 m'


P = 8.00 m = 8.00 + 8.00 + 9.00 + 9.00 + 9.00
L = 9.00 m

II PEKERJAAN TANAH
1 Pek. Galian Tanah Pondasi 4.30 M3
- Ruangan
P = 30.00 m = 30.00 x 0.50 x 0.20 3.00 M3
L = 0.50 m
T = 0.20 m

- Teras
P = 13.00 m = 13.00 x 0.50 x 0.20 1.30 M3
L = 0.50 m
T = 0.20 m

2 Pek. Urugan Tanah Kembali = Total Pekerjaan Galian Tanah 1.43 M3

4 Pek. Urugan Pasir Bawah Lantai


Ruangan 3.60 M3
P = 6.00 m = 6.00 x 9.00 x 0.05 2.70 M3
L = 9.00 m
T rata-rata = 0.05 m

Teras
P = 2.00 m = 2.00 x 9.00 x 0.05 0.90 M3
L = 9.00 m
T = 0.05 m

5 Pek.Urugan Tanah Bawah Lantai


Ruangan 41.40 M3
P = 6.00 m = 6.00 x 9.00 x 0.60 32.40 M3
L = 9.00 m
T rata-rata = 0.60 m

Teras
P = 2.00 m = 2.00 x 9.00 x 0.50 9.00 M3
L = 9.00 m
T = 0.50 m
III PEKERJAAN PONDASI
1 Pek. Pasangan Batu Gunung / Kali camp 1 : 4 10.16 M3
Pondasi Bangunan
P = 30.00 m = 30.00 x 0.30 x 0.50 x 0.60 7.20 M3
La = 0.30 m
Lb = 0.50 m
T rata-rata = 0.60 m

Pondasi Teras
P = 13.00 m = 13.00 x 0.30 x 0.50 x 0.50 2.60 M3
La = 0.30 m
Lb = 0.50 m
T rata-rata = 0.50 m

IV PEKERJAAN BETON
1 Cor Lantai Beton Tebal 5 Cm 3.60 M3
Ruangan
P = 6.00 m = 6.00 x 9.00 x 0.05 2.70 M3
L = 9.00 m
t = 0.05 m

Teras
P = 2.00 m = 2.00 x 9.00 x 0.05 0.90 M3
L = 9.00 m
t = 0.05 m

3 Pekerjaan Beton Bertulang untuk :


a. Sloof Beton 15/20 (Mutu fc' = 16,9 Mpa) 1.47 M3
P = 49.00 m = 49.00 x 0.15 x 0.20 1.47 M3
L = 0.15 m
H = 0.20 m

b. Kolom Beton 20/20 (Mutu fc' = 16,9 Mpa) 1.27 M3


N = 6.00 bh = 0.20 x 0.20 x 3.80 x 6.00 0.91 M3
L1 = 0.20 m
L2 = 0.20 m
H = 3.80 m
N = 3.00 bh = 0.20 x 0.20 x 3.00 x 3.00 0.36 M3
L1 = 0.20 m
L2 = 0.20 m
H = 3.00 m

c. Kolom Beton 13/13 (Mutu fc' = 16,9 Mpa) 0.20 M3


N = 2.00 bh = 0.13 x 0.13 x 5.80 x 2.00 0.20 M3
L1 = 0.13 m
L2 = 0.13 m
H = 5.80 m
d. Ringbalk 15/15 (Mutu fc' = 16,9 Mpa) 1.52 M3
P = 67.44 m = 0.15 x 0.15 x 67.44 1.52 M3
L1 = 0.15 m
L2 = 0.15 m

V PEKERJAAN PENULANGAN/PEMBESIAN
a. Sloof Beton 15/20 200.74 Kg
P = 49.00 m
L = 0.15 m
T = 0.20 m

Tulangan dia 10 mm = 49.00 x 4.00 x 0.616 120.78 Kg


P = 49.00 m
n = 4.00 btg
Bj = 0.616 kg/m'

Tulangan dia 8 mm = 327.0 x 0.39 x 0.620 79.96 Kg


P = 0.62 m
n = 327.00 btg
Bj = 0.394 kg/m'
Pb = 0.62 m

b. Kolom Beton 20/20 140.87 Kg


N = 6.00 Bh
L1 = 0.20 m
L2 = 0.20 m
H = 3.80 m
N 3.00 bh
L1 = 0.20 m
L2 = 0.20 m
H = 3.00 m

Tulangan dia 10 mm = 3.80 x 4.00 x 0.616 x 6.00 56.20 Kg


P = 3.80 m
n = 4.00 btg
Bj = 0.616 kg/m'

Tulangan dia 8 mm = 6.00 x 19.00 x 0.394 x 0.72 32.37 Kg


n = 19.00 btg
Bj = 0.394 kg/m'
Pb = 0.72 m

Tulangan dia 10 mm = 3.00 x 4.00 x 0.616 x 4.00 29.58 Kg


P = 3.00 m
n = 4.00 btg
Bj = 0.616 kg/m'

Tulangan dia 8 mm = 4.00 x 20.00 x 0.394 x 0.72 22.72 Kg


n = 20.00 btg
Bj = 0.394 kg/m'
Pb = 0.72 m
c. Kolom Beton 13/13 24.47 Kg
P = 5.90 m
L1 = 0.13 m
L2 = 0.13 m
N = 2.00 bh

Tulangan dia = 8 mm = 5.90 x 4.00 x 0.394 x 2.00 18.61 Kg


P = 5.90 m
n = 4.00 btg
Bj = 0.394 kg/m'

Tulangan dia = 6 mm = 0.44 x 30.00 x 0.222 x 2.00 5.86 Kg


P = 0.44 m
n = 30.00 btg
Bj = 0.222 kg/m'

d. Ringbalk 15/15 184.97 Kg


P = 85.88 m
L1 = 0.15 m
L2 = 0.15 m

Tulangan dia = 8 mm = 85.88 x 4.00 x 0.394 135.48 Kg


P = 85.88 m
n = 4.00 btg
Bj = 0.394 kg/m'

Tulangan dia = 6 mm = 0.52 x 429.00 x 0.222 49.49 Kg


P = 0.52 m
n = 429.00 btg
Bj = 0.222 kg/m'

VI PEKERJAAN BEKISTING
a. Sloof Beton 15/20 9.80 m2
P = 49.00 m
L = 0.15 m
H = 0.20 m

Begisting
P = 49.00 m = 49.00 x 0.40 2 x pakai 9.80 m2
H = 0.40 m
b. Kolom Beton 20/20 9.68 m2
N = 6.00 bh
L1 = 0.20 m
L2 = 0.20 m
H = 3.80 m
Begisting
H = 3.80 m = 3.80 x 0.80 x 6.00 3 x pakai 6.08 m2
L = 0.80 m

N = 3.00 bh
L1 = 0.20 m
L2 = 0.20 m
H = 3.00 m
Begisting
H = 3.00 m = 3.00 x 0.80 x 3.00 2 x pakai 3.60 m2
L = 0.80 m

c. Kolom Beton 13/13 1.04 m2


P = 4.00 m
L1 = 0.13 m
L2 = 0.13 m
N = 2.00 bh
Begisting
P = 4.00 m = 4.00 x 0.26 x 2.00 2 x pakai 1.04 m2
L = 0.26 m

d. Ringbalk 15/15 10.12 m2


P = 67.44 m
L1 = 0.15 m
L2 = 0.15 m

Begisting
P = 67.44 m = 67.44 x 0.30 2 x pakai 10.12 m2
L = 0.30 m

VII PEKERJAAN DINDING DAN PLESTERAN


1 Pembongkaran 1 m3 Dinding Tembok Pagar
P = 24.00 M = 24.00 x 1.50 x 0.15 5.40 m3
L = 1.50 M
T = 0.15 M

2 Pek. Pasang Dinding batu bata 1/2 Bata Camp. 1 : 4 111.62 m2


P = 30.00 m = 30.00 x 3.80 114.00 m2
T = 3.80 m
Dinding Layar
L = 6.00 m = 6.00 x 2.00 x / 2 x 2 12.00 m2
T = 2.00 m
N = 2.00 bh
Luasan pengurang dinding 14.38 m2
Pintu+Ventilasi Kaca
TP = 2.50 m = 2.50 x 1.00 + - X - 2.50 m2
LP = 1.00 m

Jendela + Ventilasi Kaca


T = 1.35 m = 1.35 x 2.00 x 4.00 10.80 m2
L = 2.00 m
N = 4.00 bh

Ventilasi
T1 = 0.75 m = 0.75 + 0.60 x 0.40 x 0.50 x 4.00 1.08 m2
T2 = 0.60 m
L = 0.40 m
N = 4.00 bh

3 Pek. Plesteran Dinding tebal 15 mm Camp. 1 : 4 = Luasan Dinding x 2 223.24 m2

4 Pek. Acian = Luasan Plesteran 230.44 m2


Kolom Teras = 0.80 x 3.00 x 3.00 7.20 m2

VIII PEKERJAAN KUSEN PINTU JENDELA VENTILASI


1 Pek. Kusen Pintu Ulin
P = 6.10 m = 6.10 x 0.10 x 0.05 x 2.00 0.06 m3
L = 0.10 m
T = 0.05 m
N = 2.00 bh

2 Pek. Kusen Ventilasi Kaca diatas pintu


P = 2.60 m = 2.60 x 0.10 x 0.05 x 2.00 0.03 m3
L = 0.10 m
T = 0.05 m
N = 2.00 bh

3 Pek. Kusen Jendela


P = 7.60 m = 7.60 x 0.10 x 0.05 x 4.00 0.15 m3
L = 0.10 m
T = 0.05 m
N = 4.00 bh

4 Pek. Kusen Ventilasi Kaca diatas jendela


P = 4.60 m = 4.60 x 0.10 x 0.05 x 4.00 0.09 m3
L = 0.10 m
T = 0.05 m total panjang kusen
N = 4.00 bh 20.90 m'
5 Pemasangan Kaca Ventilasi Pintu+Jendela Mati Polos Tebal 5 mm 3.80 M2
P = 0.90 M = 0.90 x 0.20 x 2.00 0.36
L = 0.20
N = 2.00
P = 1.90 M = 1.90 x 0.20 x 4.00 1.52 M2
L = 0.20
N = 4.00

6 Pemasangan Kaca Jendela Mati Polos Tebal 5 mm


T = 0.80 m = 0.80 x 0.60 x 4.00 1.92 M2
L = 0.60 m
N = 4.00 bh

7 Pek. Kisi-kisi Ventilasi Ulin 4.00 Bh


N = 4.00 bh

8 Pek. Pasangan Daun Pintu Ulin


T = 2.05 m = 2.05 x 0.90 x 2.00 3.69 M2
L = 0.90 m
N = 2.00 bh

9 Pek.Pasangan Daun Jendela + Kaca Bening t=5mm


T = 0.80 m = 0.80 x 0.60 x 8.00 3.84 M2
L = 0.60 m
N = 8.00 bh

IX PEKERJAAN PASANG KUNCI DAN ALAT PENGGANTUNG


1 Pek.Pas.Kunci Tanam Biasa 2.00 Bh
2 Pek.Pas.Engsel Pintu 4" 6.00 Bh
3 Pek.Pas.Engsel Jendela 3" 16.00 Bh
4 Pek.Pas.Pegangan Jendela 8.00 Bh
5 Pek.Pas.Grendel Jendela 8.00 Bh
6 Pek.Pas.Kait Angin Jendela 16.00 Bh
7 Pek.Pas.Grendel Pintu 2.00 Bh

X PEK. RANGKA KAP ATAP DAN PENUTUP ATAP


1 Pek.Rangka Atap Konstruksi Baja Ringan (Standar Pabrikasi) 119.08 m2
P = 10.40 m
L = 6.20 m = 10.40 x 6.20 x 1.00 64.48 m2
N = 1.00 bh

P = 10.40 m = 10.40 x 5.25 x 1.00 54.60 m2


L 5.25 m
N = 1.00 bh

2 Pek.Atap genteng Metal setara multi roof = Luasan rangka atap 119.08 m2

3 Pemasangan 1 m2 Rangka Besi Hollow Galvanis 40.40 mm, Modul 60 x 60 cm, untuk Plafon
P = 6.00 m
L = 9.00 m = 6.00 x 9.00 54.00 m2