I PEKERJAAN PERSIAPAN
1 Pembersihan Lokasi Awal dan Akhir - 1.00 Ls 1,000,000.00 1,000,000.00
2 Pengukuran dan Pemasangan Bowplank - 1.00 Ls 500,000.00 500,000.00
Sub Total I 1,500,000.00
II PEKERJAAN TANAH
1 Pek. Galian Tanah Pondasi 1.7.1.a (c) 23.70 M3 94,875.00 2,248,537.50
2 Pek. Urugan Tanah Kembali 1.7.2.a (c) 7.90 M3 68,750.00 543,125.00
3 Pek. Urugan Pasir Bawah Lantai 1.7.2.d (c) 3.90 M3 235,950.00 920,205.00
Sub Total II 3,711,867.50
III PEKERJAAN PONDASI
1 Pek. Pasangan Batu Kali 2.1.1.d.(a) 61.30 M3 1,063,177.50 65,172,780.75
Sub Total II 65,172,780.75
IV PEKERJAAN BETON
1 Cor Lantai Beton Tebal 20 Cm A.4.1.1.1 0.60 M3 1,056,073.07 633,643.84
2 Pekerjaan Beton Bertulang untuk :
a. Plat Injak A.4.1.1.6 0.60 M3 1,205,371.88 723,223.13
b. Footplat A.4.1.1.6 1.45 M3 1,205,371.88 1,747,789.23
Sub Total IV 3,104,656.20
V PEKERJAAN PENULANGAN/PEMBESIAN
1 Pembesian 2.2.6.1.b.(c) 421.58 18,560.30 7,824,651.48
Sub Total V 7,824,651.48
VI PEKERJAAN BEKISTING
1 Begisting A.4.1.1.19 6.95 M2 213,334.00 1,482,671.30
Sub Total VI 1,482,671.30
VII PEKERJAAN PLESTERAN DAN ACIAN
1 Pek. Plesteran Pondasi tebal 15 mm Camp. 1 : 4 3.2.2.(c) 310.00 M2 78,441.00 24,316,710.00
2 Pek. Acian Pondasi 3.2.2.(d) 322.84 M2 45,952.50 14,835,305.10
Sub Total VII 39,152,015.10
VIII PEKERJAAN KUSEN PINTU JENDELA VENTILASI
1 Pek. Kusen Pintu Air Ulin A.4.6.1.1 0.18 M3 18,587,525.00 3,345,754.50
6 Pek. Pasangan Papan 3/20 Pintu Ulin .A.4.6.1.6 4.50 M2 457,160.00 2,057,220.00
Sub Total IX 12,411,658.55
IX PEKERJAAN LAIN LAIN
1 Pembuatan Prasasti Uk.30 cm x 20 cm - 1.00 Bh 450,000.00 450,000.00
Sub Total XI 450,000.00
134,810,300.88
PERHITUNGAN PERKIRAAN VOLUME PEKERJAAN
I PEKERJAAN PERSIAPAN
II PEKERJAAN TANAH
1 Pek. Galian Tanah Pondasi 23.70 M3
- Tepi Dinding
P = 6.00 m = 6.00 x 0.50 x 0.30 0.90 M3
L = 0.50 m
T = 0.30 m
- Pondasi
P = 1.00 m = 1.00 x 1.00 x 0.30 0.30 M3
L = 1.00 m
T = 0.30 m
- Siring
P = 150.00 m = 150.00 x 0.50 x 0.30 22.50 M3
L = 0.50 m
T = 0.30 m
- Pondasi
P = 1.00 m = 1.00 x 1.00 x 0.05 0.05 M3
L = 1.00 m
T = 0.05 m
- Siring
P = 148.00 m = 148.00 x 0.50 x 0.05 3.70 M3
L = 0.50 m
T = 0.05 m
- Siring
P = 148.00 m = 148.00 x 0.80 x 1.00 x 0.50 59.20 M3
T = 0.30 m Luas = 148 M2
L = 0.50 m
T rata-rata = 1.00 m
IV PEKERJAAN BETON
1 Cor Lantai Beton Tebal 20 Cm 0.60 M3
Plat Injak
P = 3.00 m = 3.00 x 1.00 x 0.20 0.60 M3
L = 1.00 m
t = 0.20 m
2 Footplat Atas Tul. Memanjang Ø 13-100 13 1.00 0.16 1.16 45.00 1.042 2 108.40
Tul Melintang Ø 13-100 13 1.50 0.16 1.66 20.00 1.042 2 69.01
2 Footplat Bawah Tul. Utama 16 Ø 13 13 1.00 0.16 1.16 16.00 1.042 2 38.54
Tul Begel Ø 13-100 13 2.62 0.16 2.78 10.00 1.042 2 57.85
TOTAL 421.58
BETON
2 Footplat P 1
L 0.30 0.90
T 1.50
P2 1 2.00
L1 0.35 0.55
L2 0.2
TOTAL 2.05
BEKISTING
2 Footplat P 1
L 0.30 0.6
T 1.5 0.9
2
P2 1 1.54
L1 0.35 0.275 0.55
L2 0.2
TOTAL 6.95