REKAPITULASI

DAFTAR KUANTITAS DAN HARGA

UNIT KERJA : DINAS PEKERJAAN UMUM DAN PENATAAN RUANG


PEKERJAAN : PEMELIHARAAN BERKALA JARINGAN IRIGASI PERMULAAN
LOKASI : DESA SARIGADUNG , KECAMATAN SIMPANG EMPAT
TAHUN ANGGARAN : 2024

NO URAIAN PEKERJAAN JUMLAH HARGA

(1) (2) (3)

I PEKERJAAN PERSIAPAN 1,500,000.00


II PEKERJAAN TANAH 3,711,867.50
III PEKERJAAN PONDASI 65,172,780.75
IV PEKERJAAN BETON 3,104,656.20
V PEKERJAAN PENULANGAN/PEMBESIAN 7,824,651.48
VI PEKERJAAN BEKISTING 1,482,671.30
VII PEKERJAAN PLESTERAN DAN ACIAN 39,152,015.10
VIII PEKERJAAN KUSEN PINTU JENDELA VENTILASI 12,411,658.55
IX PEKERJAAN LAIN LAIN 450,000.00
134,810,300.88
14,829,133.10
TOTAL 149,639,433.98
DIBULATKAN 150,000,000.00
Terbilang: Seratus Lima Puluh Juta Rupiah

PEKERJAAN BEKISTING Batulicin, 2024

Diperiksa : Disiapkan
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG CV. DIAN GEMILANG KONSULINDO
Pejabat Pelaksana Teknis Kegiatan (PPTK)

M. Hairil Bakri, ST DIAN KHAIRANA, S.H


NIP.19850301 201101 1 005 Direktur

Mengetahui / Menyetujui :
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
-

Ir. Hernadi Wibisono T, S.T,MT


NIP. 19710124 200604 1 011
DAFTAR KUANTITAS DAN HARGA

UNIT KERJA : DINAS PEKERJAAN UMUM DAN PENATAAN RUANG


PEKERJAAN : PEMELIHARAAN BERKALA JARINGAN IRIGASI PERMULAAN
LOKASI : DESA SARIGADUNG , KECAMATAN SIMPANG EMPAT
TAHUN ANGGARAN : 2024

NO URAIAN PEKERJAAN ANLS VOLUME HARGA SATUAN JUMLAH HARGA

(1) (2) (3) (4) (5) (6)

I PEKERJAAN PERSIAPAN
1 Pembersihan Lokasi Awal dan Akhir - 1.00 Ls 1,000,000.00 1,000,000.00
2 Pengukuran dan Pemasangan Bowplank - 1.00 Ls 500,000.00 500,000.00
Sub Total I 1,500,000.00
II PEKERJAAN TANAH
1 Pek. Galian Tanah Pondasi 1.7.1.a (c) 23.70 M3 94,875.00 2,248,537.50
2 Pek. Urugan Tanah Kembali 1.7.2.a (c) 7.90 M3 68,750.00 543,125.00
3 Pek. Urugan Pasir Bawah Lantai 1.7.2.d (c) 3.90 M3 235,950.00 920,205.00
Sub Total II 3,711,867.50
III PEKERJAAN PONDASI
1 Pek. Pasangan Batu Kali 2.1.1.d.(a) 61.30 M3 1,063,177.50 65,172,780.75
Sub Total II 65,172,780.75
IV PEKERJAAN BETON
1 Cor Lantai Beton Tebal 20 Cm A.4.1.1.1 0.60 M3 1,056,073.07 633,643.84
2 Pekerjaan Beton Bertulang untuk :
a. Plat Injak A.4.1.1.6 0.60 M3 1,205,371.88 723,223.13
b. Footplat A.4.1.1.6 1.45 M3 1,205,371.88 1,747,789.23
Sub Total IV 3,104,656.20
V PEKERJAAN PENULANGAN/PEMBESIAN
1 Pembesian 2.2.6.1.b.(c) 421.58 18,560.30 7,824,651.48
Sub Total V 7,824,651.48
VI PEKERJAAN BEKISTING
1 Begisting A.4.1.1.19 6.95 M2 213,334.00 1,482,671.30
Sub Total VI 1,482,671.30
VII PEKERJAAN PLESTERAN DAN ACIAN
1 Pek. Plesteran Pondasi tebal 15 mm Camp. 1 : 4 3.2.2.(c) 310.00 M2 78,441.00 24,316,710.00
2 Pek. Acian Pondasi 3.2.2.(d) 322.84 M2 45,952.50 14,835,305.10
Sub Total VII 39,152,015.10
VIII PEKERJAAN KUSEN PINTU JENDELA VENTILASI
1 Pek. Kusen Pintu Air Ulin A.4.6.1.1 0.18 M3 18,587,525.00 3,345,754.50
6 Pek. Pasangan Papan 3/20 Pintu Ulin .A.4.6.1.6 4.50 M2 457,160.00 2,057,220.00
Sub Total IX 12,411,658.55
IX PEKERJAAN LAIN LAIN
1 Pembuatan Prasasti Uk.30 cm x 20 cm - 1.00 Bh 450,000.00 450,000.00
Sub Total XI 450,000.00
134,810,300.88
PERHITUNGAN PERKIRAAN VOLUME PEKERJAAN

PEKERJAAN : PEMELIHARAAN BERKALA JARINGAN IRIGASI PERMULAAN


LOKASI : DESA SARIGADUNG , KECAMATAN SIMPANG EMPAT
TAHUN ANGGARAN : 2024

NO URAIAN PERHITUNGAN VOLUME SATUAN

I PEKERJAAN PERSIAPAN

1 Pembersihan Lokasi Awal dan Akhir 1.00 Ls

2 Pengukuran dan Pemasangan Bowplank 34.00 m'


P = 8.00 m = 8.00 + 8.00 + 9.00 + 9.00 + 9.00
L = 9.00 m

II PEKERJAAN TANAH
1 Pek. Galian Tanah Pondasi 23.70 M3
- Tepi Dinding
P = 6.00 m = 6.00 x 0.50 x 0.30 0.90 M3
L = 0.50 m
T = 0.30 m

- Pondasi
P = 1.00 m = 1.00 x 1.00 x 0.30 0.30 M3
L = 1.00 m
T = 0.30 m

- Siring
P = 150.00 m = 150.00 x 0.50 x 0.30 22.50 M3
L = 0.50 m
T = 0.30 m

2 Pek. Urugan Tanah Kembali = Total Pekerjaan Galian Tanah 7.90 M3

3 Pek. Urugan Pasir Bawah


- Tepi Dinding 3.90 M3
P = 6.00 m = 6.00 x 0.50 x 0.05 0.15 M3
L = 0.50 m
T rata-rata = 0.05 m

- Pondasi
P = 1.00 m = 1.00 x 1.00 x 0.05 0.05 M3
L = 1.00 m
T = 0.05 m

- Siring
P = 148.00 m = 148.00 x 0.50 x 0.05 3.70 M3
L = 0.50 m
T = 0.05 m

III PEKERJAAN PONDASI


1 Pek. Pasangan Batu Gunung / Kali camp 1 : 4 61.30 M3
- Tepi Dinding
P = 4.00 m = 4.00 x 0.50 x 0.60 x 1.75 2.10 M3
La = 0.50 m Luas = 7 M2
Lb = 0.60 m
T rata-rata = 1.75 m

- Siring
P = 148.00 m = 148.00 x 0.80 x 1.00 x 0.50 59.20 M3
T = 0.30 m Luas = 148 M2
L = 0.50 m
T rata-rata = 1.00 m

IV PEKERJAAN BETON
1 Cor Lantai Beton Tebal 20 Cm 0.60 M3
Plat Injak
P = 3.00 m = 3.00 x 1.00 x 0.20 0.60 M3
L = 1.00 m
t = 0.20 m

V PEKERJAAN PLESTERAN DAN ACIAN


1 Pek. Plesteran Siring Camp. 1 : 4 = Luasan x 2 310.00 m2

2 Pek. Acian Pondasi = Luasan Plesteran 322.84 m2

3 Pek. Acian Plat Injak = 3.00 + 0.20 + 0.60 x 2 7.60 m2

4 Pek. Acian Footplat = 0.90 + 0.55 + 0.40 + 0.77 x 2 5.24 m2

VI PEKERJAAN PENUTUP PINTU AIR ULIN

1 Pek. Kusen Pintu Air Ulin


P = 18.00 m = 18.00 x 0.10 x 0.10 x 1.00 0.18 m3
L = 0.10 m
T = 0.10 m
N = 1.00 bh

2 Pek. Pasangan Papan 3/20 Pintu Ulin 4.50 M2


T = 1.50 m = 1.50 x 3.00 x 1.00 4.50 M2
L = 3.00 m
N = 1.00 bh
DAFTAR TULANGAN
UKURAN ( M ) PANJANG JUMLAH BERAT / M BERAT
NO TULANGAN TYPE Ø (mm) PER BUAH PER (Kg/m) JUMLAH TOTAL
a b c d kait
(m) SEGMEN (Kg)
1 Plat Injak Tul. Memanjang Ø 13-100 13 1.00 0.31 1.31 30.00 1.042 2 82.02
Tul Melintang Ø 13-100 13 3.00 0.16 3.16 10.00 1.042 2 65.76

2 Footplat Atas Tul. Memanjang Ø 13-100 13 1.00 0.16 1.16 45.00 1.042 2 108.40
Tul Melintang Ø 13-100 13 1.50 0.16 1.66 20.00 1.042 2 69.01

2 Footplat Bawah Tul. Utama 16 Ø 13 13 1.00 0.16 1.16 16.00 1.042 2 38.54
Tul Begel Ø 13-100 13 2.62 0.16 2.78 10.00 1.042 2 57.85

TOTAL 421.58

BETON

NO TULANGAN TYPE (m) JUMLAH V

1 Plat Injak P 3.00


L 1.00 1.00 0.60
T 0.20

2 Footplat P 1
L 0.30 0.90
T 1.50
P2 1 2.00
L1 0.35 0.55
L2 0.2

TOTAL 2.05

BEKISTING

NO TULANGAN TYPE (m) JUMLAH L

1 Plat Injak P 3 6.00


L 1 0.4 1 6.40
T 0.2

2 Footplat P 1
L 0.30 0.6
T 1.5 0.9
2
P2 1 1.54
L1 0.35 0.275 0.55
L2 0.2

TOTAL 6.95