REKAPITULASI

KEGIATAN : PEMBANGUNAN TANGKI SEPTIK SKALA KOMUNAL (5 - 10 KK) SWAKELOLA


PEKERJAAN : PEMBANGUNAN TANGKI SEPTIK SKALA INDIVIDU (5 - 10 KK)
LOKASI : SKOFRO
DIMENSI :2X2M
TAHUN ANGGARAN : 2021
JENIS : PENUGASAN

NO. URAIAN PEKERJAAN JUMLAH HARGA (Rp.)

I PEKERJAAN PERSIAPAN 1,000,000.00


II ADMINISTRASI KSM 14,000,000.00
III PEKERJAAN TANAH / URUGAN 14,291,514.88
IV PEKERJAAN PASANGAN 171,243,686.00
V PEKERJAAN BETON 33,543,940.49
VI PEKERJAAN KUSEN, PINTU, DAN VENTILASI 16,627,531.25
VII PEKERJAAN ATAP, KUDA-KUDA DAN PLAFOND 46,599,960.00
VIII PEKERJAAN PENGUNCI, PENGGANTUNG 4,232,000.00
IX PEKERJAAN SANITAIR 248,038,737.60
X PEKERJAAN INSTALASI LISTRIK 5,277,500.00
XI PEKERJAAN PENGECATAN 11,146,096.58
XII PEKERJAAN AKHIR 500,000.00

REAL COST 566,500,966.79


TOTAL PEMBULATAN (1 UNIT) 113,334,000.00
TOTAL COST (5 UNIT) 566,670,000.00

Terbilang :
Lima Ratus Enam Puluh Enam Juta Enam Ratus Tujuh Puluh Ribu Rupiah

Dibuat Oleh :
Kepala Seksi Perencanaan Penyediaan PSU
Bidang Prasarana, Sarana dan Utilitas Umum

MUSLIHAN, A.Md.T
Nip. 19790810 200502 1 009
REKAPITULASI TAHAP 1

KEGIATAN : PEMBANGUNAN TANGKI SEPTIK SKALA KOMUNAL (5 - 10 KK) SWAKELOLA


PEKERJAAN : PEMBANGUNAN TANGKI SEPTIK SKALA KOMUNAL (5 - 10 KK)
LOKASI : KAMPUNG PETIWE
TAHUN ANGGARAN : 2022

NO Deskripsi Produk Harga


1 PEMBERDAYAAN Rp 28,900,001
2 BAHAN TOKO Rp 50,822,701
3 MATERIAL LOKAL Rp 76,527,298
TOTAL Rp 156,250,000
PEMBULATAN Rp 156,250,000.00

ARSO, 12 JULI 2022

Di Buat Oleh :
Di Periksa Oleh : KELOMPOK SWADAYA MASYARAKAT
Fasilitator Teknik  
   
 
 
   
HARIST FIRDAUS ARIFIN ,ST .............................

   

PPK
DINAS PERUMAHAN, KAWASAN PERMUKIMAN
DAN PERTANAHAN
KABUPATEN KEEROM
 
 
 
 
EDUARDUS GOBAY, ST., MT
NIP. 19750905 200112 1 007
 
ENGINEER'S ESTIMATE TAHAP 1
KEGIATAN : PEMBANGUNAN TANGKI SEPTIK SKALA KOMUNAL (5 - 10 KK) SWAKELOLA
PEKERJAAN : PEMBANGUNAN TANGKI SEPTIK SKALA KOMUNAL (5 - 10 KK)
LOKASI : KAMPUNG PETIWE
TAHUN ANGGARAN : 2022

HARGA SATUAN
NO. URAIAN PEKERJAAN VOLUME SAT.
(Rp.)
1 2 3 4 5

I PEKERJAAN PERSIAPAN
1 Pembersihan Lokasi 5.00 Ls 300,000
2 Pemasangan Bouwplank/Pengukuran 5.00 LS 300,000
3 Transport Material Toko 3.00 LS 8,000,000

II ADMINISTRASI KSM
A BIAYA DOKUMENTASI
4 Papan Nama Program/ Kegiatan 5.00 Bh 20,000
B BIAYA ADMINISTRASI
5 Pengandaan Kontrak KSM 10.00 Paket 60,000
6 Pengandaan Laporan Termin I 10.00 Paket 60,000
7 Pengandaan Laporan Termin II 0.00 Paket 60,000
8 Pengandaan Laporan Akhir 0.00 Paket 60,000
9 Pembuatan Stampel 5.00 Bh 80,000
10 Pembukaan Rekening 5.00 Bh 40,000
11 Pembuatan Prasasti Keramik 0.00 Bh 1,000,000

II PEKERJAAN TANAH / URUGAN


1 Pek. Galian tanah 7.88 M³ 119,000
Pek. Galian Tanah Untuk Bak Ipal 0.00 M³ 119,000
2 Pek. Urugan Pilihan 0.00 M³ 404,000
3 Pek. Urugan Pasir di bawah pondasi 0.00 M³ 587,600
4 Pek. Urugan Pasir di bawah Lantai 0.00 M³ 587,600
5 Pek. Urugan tanah di bawah lantai / Peninggian lantai 0.00 M³ 404,000

III PEKERJAAN PASANGAN


1 Pek. Pasangan batu kosong (Anstamping) 7.88 M³ 1,359,150
2 Pek. Pasangan Pondasi Karang/ Kali 1 : 4 40.87 M³ 1,913,750
3 Pek. Pasangan Batu Tela 1 : 2 0.00 M² 169,850
4 Pek. Plesteran 1 : 2 0.00 M² 110,950
5 Pek. Acian 0.00 M² 51,500
6 Pas. Lantai Keramik 20/20 0.00 M² 245,125
7 Pas. Keramik Dinding 25/20 0.00 M² 233,875

IV PEKERJAAN BETON
1 Pek. Sloof beton 15/20 cm 0.00 M³ 5,086,282
2 Pek. Kolom beton 11/11 cm 0.00 M³ 9,268,586
3 Pek. Ring Balok 12/15 0.00 M³ 7,393,138
4 Pek. Coor bawah lantai & Rabat, camp. 1 : 3 : 5 0.00 M³ 1,365,250

V PEKERJAAN KUSEN, PINTU, DAN VENTILASI


1 Pek. Pasang Kusen Kayu besi 5/10 0.00 M³ 10,271,250
2 Pek. Pasang Pintu Panel 0.00 M² 1,017,500
3 Pek. Ventilasi Kayu Besi 0.00 m3 10,271,250

VI PEKERJAAN ATAP, KUDA-KUDA DAN PLAFOND


1 Pek. Kuda-kuda Balok Kayu besi 5/10 0.00 M³ 7,714,000
2 Pek. Gording Balok Kayu Matoa 5/10 0.00 M³ 6,455,000
3 Pek. Skur Angin Balok Kayu Matoa 5/10 0.00 M³ 6,455,000
4 Pek. Atap Seng Sokka Biru 0.00 M² 98,730
5 Pek. Nok Seng Sokka Biru 0.00 M' 104,710
6 Pek. Lisplank Papan Kayu Besi 2/20 0.00 M' 73,400
7 Pek. Plafond Tripleks 3mm + Rangka 0.00 M² 181,338
8 Pek. List Plafond Luar & Dalam 0.00 M' 56,800

VII PEKERJAAN PENGUNCI, PENGGANTUNG


1 Pek. Pasang Kunci tanam 2 Slaag (KM/WC) 0.00 Psg 303,250
2 Pek. Pasang Engsel pintu 0.00 Psg 86,000
HARGA SATUAN
NO. URAIAN PEKERJAAN VOLUME SAT.
(Rp.)
1 2 3 4 5

VIII PEKERJAAN SANITAIR


1 Pek. Pipa PVC Dia.1/2" 0.00 M' 34,400
3 Pek. Pipa PVC Dia.3" 0.00 M' 125,838
4 Pas. Klosed Jongkok 0.00 Bh 1,004,000
5 Pas. Floor Drain 0.00 Bh 67,750
6 Pas. Kran Air 0.00 Bh 82,250
7 Pek. Pengadaan Bak Viber 0.00 Bh 700,000
8 Sumur Dangkal 0.00 Bh 4,000,000
9 Pek. Tandon Air 1100 Liter + Dudukan 0.00 Bh 5,000,000
10 Pengadaan IPAL Bio Tank 1 Set 5.00 7,500,000
12 Pengadaan Mesin Air 0.00 Bh 800,000
13 Pasangan Batu Tela 0.00 M2 169,850
14 Cor Lantai K 175 ( T = 12 cm) 0.00 M3 1,365,250
15 Cor DaK TutuP K 175 ( T=12 cm) 0.00 M3 1,365,250

IX PEKERJAAN INSTALASI LISTRIK


1 Pasang Lampu SL 8 watt + Fitting 0.00 Titik 229,800
2 Pasang Saklar Ganda 3 0.00 Titik 283,800
3 Stop Kontak 0.00 Titik 283,300

X PEKERJAAN PENGECATAN
1 Pek. Cat Kilat Kayu 0.00 M² 60,886
2 Pek. Cat Tembok 0.00 M² 31,900
3 Pek. Cat Plafond 0.00 M² 31,905

XI PEKERJAAN AKHIR
1 Pembesihan Akhir 0.00 Ls 866,017
E TAHAP 1

JUMLAH HARGA
(Rp.)
6

1,500,000
1,500,001
24,000,000
27,000,001

100,000

600,000
600,000
-
-
400,000
200,000
-
1,900,000

937,125
-
-
-
-
-
937,125

10,703,306
78,209,567
-
-
-
-
-
88,912,874

-
-
-
-
-

-
-
-
-

-
-
-
-
-
-
-
-
-

-
-
-
JUMLAH HARGA
(Rp.)
6

-
-
-
-
-
-
-
-
37,500,000
-
-
-
-
37,500,000

-
-
-
-

-
-
-
-

-
-
RENCANA PENGGUNAAN DANA TAHAP 1
KEGIATAN : PEMBANGUNAN TANGKI SEPTIK SKALA KOMUNAL (5 - 10 KK) SWAKELOLA
PEKERJAAN : PEMBANGUNAN TANGKI SEPTIK SKALA KOMUNAL (5 - 10 KK)
LOKASI : KAMPUNG PETIWE
TAHUN ANGGARAN : 2022

JUMLAH
HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN VOLUME PENGAJUAN SAT.
(Rp.) (Rp.)
SEKARANG
1 2 3 4 5 6

I PEKERJAAN PERSIAPAN
1 Pembersihan Lokasi 5.00 5.00 Ls 300,000 1,500,000
2 Pemasangan Bouwplank/Pengukuran 5.00 5.00 LS 300,000 1,500,001
3 Transport Material Toko 3.00 3.00 LS 8,000,000 24,000,000
0
II ADMINISTRASI KSM
A BIAYA DOKUMENTASI
4 Papan Nama Program/ Kegiatan 5.00 5.00 Bh 20,000 100,000
B BIAYA ADMINISTRASI
5 Pengandaan Kontrak KSM 10.00 10.00 Paket 60,000 600,000
6 Pengandaan Laporan Termin I 10.00 10.00 Paket 60,000 600,000
7 Pengandaan Laporan Termin II 0.00 0.00 Paket 60,000 -
8 Pengandaan Laporan Akhir 0.00 0.00 Paket 60,000 -
9 Pembuatan Stampel 5.00 5.00 Bh 80,000 400,000
10 Pembukaan Rekening 5.00 5.00 Bh 40,000 200,000
11 Pembuatan Prasasti Keramik 0.00 0.00 Bh 1,000,000 -

II PEKERJAAN TANAH / URUGAN


1 Pek. Galian tanah 7.88 7.88 M³ 119,000 937,125
0 Pek. Galian Tanah Untuk Bak Ipal 0.00 0.00 M³ 119,000 -
2 Pek. Urugan Pilihan 0.00 0.00 M³ 404,000 -
3 Pek. Urugan Pasir di bawah pondasi 0.00 0.00 M³ 587,600 -
4 Pek. Urugan Pasir di bawah Lantai 0.00 0.00 M³ 587,600 -
5 Pek. Urugan tanah di bawah lantai / Peninggian lantai 0.00 0.00 M³ 404,000 -
0
III PEKERJAAN PASANGAN
1 Pek. Pasangan batu kosong (Anstamping) 7.88 7.88 M³ 1,359,150 10,703,306
2 Pek. Pasangan Pondasi Karang/ Kali 1 : 4 40.87 40.87 M³ 1,913,750 78,209,567
3 Pek. Pasangan Batu Tela 1 : 2 0.00 0.00 M² 169,850 -
4 Pek. Plesteran 1 : 2 0.00 0.00 M² 110,950 -
5 Pek. Acian 0.00 0.00 M² 51,500 -
6 Pas. Lantai Keramik 20/20 0.00 0.00 M² 245,125 -
7 Pas. Keramik Dinding 25/20 0.00 0.00 M² 233,875 -
0
IV PEKERJAAN BETON
1 Pek. Sloof beton 15/20 cm 0.00 0.00 M³ 5,086,282 -
2 Pek. Kolom beton 11/11 cm 0.00 0.00 M³ 9,268,586 -
3 Pek. Ring Balok 12/15 0.00 0.00 M³ 7,393,138 -
4 Pek. Coor bawah lantai & Rabat, camp. 1 : 3 : 5 0.00 0.00 M³ 1,365,250 -

V PEKERJAAN KUSEN, PINTU, DAN VENTILASI


1 Pek. Pasang Kusen Kayu besi 5/10 0.00 0.00 M³ 10,271,250 -
2 Pek. Pasang Pintu Panel 0.00 0.00 M² 1,017,500 -
3 Pek. Ventilasi Kayu Besi 0.00 0.00 m3 10,271,250 -

VI PEKERJAAN ATAP, KUDA-KUDA DAN PLAFOND


1 Pek. Kuda-kuda Balok Kayu besi 5/10 0.00 0.00 M³ 7,714,000 -
2 Pek. Gording Balok Kayu Matoa 5/10 0.00 0.00 M³ 6,455,000 -
3 Pek. Skur Angin Balok Kayu Matoa 5/10 0.00 0.00 M³ 6,455,000 -
4 Pek. Atap Seng Sokka Biru 0.00 0.00 M² 98,730 -
5 Pek. Nok Seng Sokka Biru 0.00 0.00 M' 104,710 -
6 Pek. Lisplank Papan Kayu Besi 2/20 0.00 0.00 M' 73,400 -
7 Pek. Plafond Tripleks 3mm + Rangka 0.00 0.00 M² 181,338 -
8 Pek. List Plafond Luar & Dalam 0.00 0.00 M' 56,800 -

VII PEKERJAAN PENGUNCI, PENGGANTUNG


1 Pek. Pasang Kunci tanam 2 Slaag (KM/WC) 0.00 0.00 Psg 303,250 -
2 Pek. Pasang Engsel pintu 0.00 0.00 Psg 86,000 -
JUMLAH
HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN VOLUME PENGAJUAN SAT.
(Rp.) (Rp.)
SEKARANG
1 2 3 4 5 6

VIII PEKERJAAN SANITAIR


1 Pek. Pipa PVC Dia.1/2" 0.00 0.00 M' 34,400 -
3 Pek. Pipa PVC Dia.3" 0.00 0.00 M' 125,838 -
4 Pas. Klosed Jongkok 0.00 0.00 Bh 1,004,000 -
5 Pas. Floor Drain 0.00 0.00 Bh 67,750 -
6 Pas. Kran Air 0.00 0.00 Bh 82,250 -
7 Pek. Pengadaan Bak Viber 0.00 0.00 Bh 700,000 -
8 Sumur Dangkal 0.00 0.00 Bh 4,000,000 -
9 Pek. Tandon Air 1100 Liter + Dudukan 0.00 0.00 Bh 5,000,000 -
10 Pengadaan IPAL Bio Tank 1 Set 5.00 5.00 7,500,000 37,500,000
12 Pengadaan Mesin Air 0.00 0.00 Bh 800,000 -
13 Pasangan Batu Tela 0.00 0.00 M2 169,850 -
14 Cor Lantai K 175 ( T = 12 cm) 0.00 0.00 M3 1,365,250 -
15 Cor DaK TutuP K 175 ( T=12 cm) 0.00 0.00 M3 1,365,250 -

IX PEKERJAAN INSTALASI LISTRIK


1 Pasang Lampu SL 8 watt + Fitting 0.00 0.00 Titik 229,800 -
2 Pasang Saklar Ganda 3 0.00 0.00 Titik 283,800 -
3 Stop Kontak 0.00 0.00 Titik 283,300 -

X PEKERJAAN PENGECATAN
1 Pek. Cat Kilat Kayu 0.00 0.00 M² 60,886 -
2 Pek. Cat Tembok 0.00 0.00 M² 31,900 -
3 Pek. Cat Plafond 0.00 0.00 M² 31,905 -

XI PEKERJAAN AKHIR
1 Pembesihan Akhir 0.00 0.00 Ls 866,017 -
TOTAL DANA 100% 156,250,000
HARGA SATUAN
No. URAIAN PEKERJAAN VOLUME SATUAN JUMLAH HARGA (Rp.)
(Rp)

1 2 3 4
26 Pek. Kolom beton 11/11 cm - M3 0.000000000
Beton
4.4080 Zak. Semen Pc (50 Kg) - 100,000.00 -
0.4940 M3. Pasir Beton - 450,000.00 -
0.7410 M3. Kerikil Cor - 450,000.00 -
1.5675 OH. Pekerja - 150,000.00 -
0.2375 OH. Tukang Batu - 225,000.00 -
Kg. Besi Beton - -
1.0500 Kg. Besi Beton (Polos) - 19,000.00 -
0.0150 Kg. Kawat Beton - 30,000.00 -
0.0070 OH. Pekerja - 150,000.00 -
0.0070 OH. Tukang Batu - 225,000.00 -
1M2. Bekesting Untuk Kolom - -
0.0400 M3. Balok/Papan Kayu Kelas II - 2,000,000.00 -
0.4000 Kg. Paku Campur - 25,000.00 -
0.0150 M3. Balok Kayu Kelas II - 2,000,000.00 -
0.1604 Ltr. Minyak Bekisting - 13,653.00 -
0.6600 OH. Pekerja - 150,000.00 -
0.3300 OH. Tukang Kayu - 225,000.00 -
-
-
PEMBULATAN
27 Pek. Ring Balok 12/15 - M3 0.00
M3. Beton
4.4727 Zak. Semen Pc (50 Kg) - 100,000.00 -
0.5200 M3. Pasir Beton - 450,000.00 -
0.7519 M3. Kerikil Cor - 450,000.00 -
1.5905 OH. Pekerja - 150,000.00 -
0.2410 OH. Tukang Batu - 225,000.00 -
Kg. Besi Beton - -
1.0500 Kg. Besi Beton (Polos) - 19,000.00 -
0.0150 Kg. Kawat Beton - 30,000.00 -
0.0070 OH. Pekerja - 150,000.00 -
0.0070 OH. Tukang Batu - 225,000.00 -
1M2. Bekesting Untuk Ring Balok - -
0.0400 M3. Balok/Papan Kayu Kelas II - 2,000,000.00 -
0.4000 Kg. Paku Campur - 25,000.00 -
0.0180 M3. Balok Kayu Kelas II - 2,000,000.00 -
0.0146 Ltr. Minyak Bekisting - 13,653.00 -
0.6600 OH. Pekerja - 150,000.00 -
0.3300 OH. Tukang Kayu - 225,000.00 -
-
-
PEMBULATAN
28 Pek. Coor bawah lantai & Rabat, camp. 1 : 3 : 5 - M3
4.3600 Zak. Semen Pc (50 Kg) - 100,000.00 -
0.5200 M3. Pasir Beton - 450,000.00 -
0.8700 M3. Kerikil Cor - 450,000.00 -
1.6500 OH. Pekerja - 150,000.00 -
0.2500 OH. Tukang Batu - 225,000.00 -
-
29 0 - M3
4.3600 Zak. Semen Pc (50 Kg) - 86,000.00 -
0.5200 M3. Pasir Beton - 450,000.00 -
0.8700 M3. Kerikil Cor - 450,000.00 -
1.6500 OH. Pekerja - 150,000.00 -
0.2500 OH. Tukang Batu - 225,000.00 -
-
30 Pek. Pasang Kusen Kayu besi 5/10 - M3
1.1000 M3. Balok Kayu Besi 5/10 - 4,000,000.00 -
1.2500 Kg. Paku 10 cm - 25,000.00 -
1.0000 Kg. Lem Kayu - 65,000.00 -
7.0000 OH. Pekerja - 150,000.00 -
21.0000 OH. Tukang Kayu - 225,000.00 -
-
31 Pek. Pasang Pintu Panel - M3
0.0400 M3. Papan Kayu Kelas I - 4,000,000.00 -
0.5000 Kg. Lem Kayu - 65,000.00 -
1.0000 OH. Pekerja - 150,000.00 -
3.0000 OH. Tukang Kayu - 225,000.00 -
-
32 Pek. Ventilasi Kayu Besi - M3
1.1000 M3. Balok Kayu Besi 5/10 - 4,000,000.00 -
1.2500 Kg. Paku 10 cm - 25,000.00 -
1.0000 Kg. Lem Kayu - 65,000.00 -
7.0000 OH. Pekerja - 150,000.00 -
21.0000 OH. Tukang Kayu - 225,000.00 -
-
33 Pek. Kuda-kuda Balok Kayu besi 5/10 -
1.1000 M3. Balok Kayu Besi 5/10 - 4,000,000.00 -
0.5600 Kg. Paku 12 cm - 25,000.00 -
4.0000 OH. Pekerja - 150,000.00 -
12.0000 OH. Tukang Kayu - 225,000.00 -
-
ANALISA SATUAN PEKERJAAN

KEGIATAN : PEMBANGUNAN TANGKI SEPTIK SKALA KOMUNAL (5 - 10 KK) SWAKELOLA


PEKERJAAN : PEMBANGUNAN TANGKI SEPTIK SKALA INDIVIDU (5 - 10 KK)
LOKASI :

TAHUN ANGGARAN : 2021

HARGA SATUAN
No. URAIAN PEKERJAAN
(Rp)

1 2 3

1 1,00 M3. Galian Tanah Keras Sedalam 1 M


1.0000 OH. Pekerja 150,000.00
0.0320 OH. Mandor 260,000.00

2 1,00 M3. Galian Tanah Biasa Sedalam 1 M


0.7500 OH. Pekerja 150,000.00
0.0250 OH. Mandor 260,000.00

3 1,00 M3. Urugan Kembali Galian Tanah


0.5000 OH. Pekerja 150,000.00
0.0500 OH. Mandor 260,000.00

4 1,00 M3. Urugan Pasir


0.3000 OH. Pekerja 150,000.00
0.0100 OH. Mandor 260,000.00
1.2000 M3. Pasir Urug 450,000.00

5 1,00 M3. Urugan Timbunan Pilihan


0.2500 OH. Pekerja 150,000.00
0.0250 OH. Mandor 260,000.00
1.2000 M3. UruganTimbunan Sirtu 300,000.00

6 1,00 M1. Pek. Pasang Papan Bouwplank


0.0120 M3. Kayu Kelas II 2,000,000.00
0.0200 Kg. Paku Campur 2 - 5 cm 25,000.00
0.0070 M3. Kayu Papan Kelas II 2,000,000.00
0.1000 OH. Pekerja 150,000.00
0.1000 OH. Tukang 225,000.00

7 1,00 M3. Pek. Batu Kosong/ Aanstamping


1.2000 M3. Batu KARANG 800,000.00
0.4320 M3. Pasir Urug 450,000.00
0.7800 OH. Pekerja 150,000.00
0.3900 OH. Tukang Batu 225,000.00

8 1,00 M3. Pek. Pasangan Batu Kali/ Belah 1Pc : 4Psr


3.2600 Zak. Sement. PC. (50 Kg) 100,000.00
1.2000 M3. Batu Karang 800,000.00
0.5200 M3. Pasir Pasang 450,000.00
1.5000 OH. Pekerja 150,000.00
0.7500 OH. Tukang Batu 225,000.00
HARGA SATUAN
No. URAIAN PEKERJAAN
(Rp)

1 2 3

9 Pasangan Batu Tela


20.0000 Bh. Batu Tela 3,000.00
0.2300 Zak. Semen Pc. (50 Kg) 100,000.00
0.0430 M3. Pasir Pasang 450,000.00
0.3000 OH. Pekerja 150,000.00
0.1000 OH. Tukang Batu 225,000.00

10 1,00 M2. Pek. Plesteran 1 Pc : 2 Psr; tebal 15 mm


0.2050 Zak. Sement. PC. (50 Kg) 100,000.00
0.0260 M3. Pasir Beton 450,000.00
0.3000 OH. Pekerja 150,000.00
0.1500 OH. Tukang Batu 225,000.00

11 1,00 M2. Pek. Acian


0.0650 Zak. Sement. PC. (50 Kg) 100,000.00
0.1500 OH. Pekerja 150,000.00
0.1000 OH. Tukang Batu 225,000.00

12 1,00 M3. Beton Tumbuk Camp. 1 : 3 : 5


4.3600 Zak. Semen Pc (50 Kg) 100,000.00
0.5200 M3. Pasir Beton 450,000.00
0.8700 M3. Kerikil Cor 450,000.00
1.6500 OH. Pekerja 150,000.00
0.2500 OH. Tukang Batu 225,000.00

13 1,00 M3. Beton Bertulang Camp. 1 : 2 : 3


4.6400 Zak. Semen Pc (50 Kg) 100,000.00
0.5200 M3. Pasir Beton 450,000.00
0.7800 M3. Kerikil Cor 450,000.00
1.6500 OH. Pekerja 150,000.00
0.2500 OH. Tukang Batu 225,000.00

14 10 Kg. Pembesian (besi polos)


10.5000 Kg. Besi Beton (Polos) 19,000.00
0.1500 Kg. Kawat Beton 30,000.00
0.0700 OH. Pekerja 150,000.00
0.0700 OH. Tukang Batu 225,000.00

Per - 1 Kg

15 1M2. Bekesting Untuk SLOOF


0.0450 M3. Balok/Papan Kayu Kelas II 2,000,000.00
0.3000 Kg. Paku Campur 25,000.00
0.1000 Ltr. Minyak Bekisting 13,653.00
0.5200 OH. Pekerja 150,000.00
0.2600 OH. Tukang Kayu 225,000.00

16 1M2. Bekesting Untuk Kolom


0.0400 M3. Balok/Papan Kayu Kelas II 2,000,000.00
0.4000 Kg. Paku Campur 25,000.00
0.0150 M3. Balok Kayu Kelas II 2,000,000.00
0.2000 Ltr. Minyak Bekisting 13,653.00
0.6600 OH. Pekerja 150,000.00
0.3300 OH. Tukang Kayu 225,000.00
HARGA SATUAN
No. URAIAN PEKERJAAN
(Rp)

1 2 3

17 1M2. Bekesting Untuk Ring Balok


0.0400 M3. Balok/Papan Kayu Kelas II 2,000,000.00
0.4000 Kg. Paku Campur 25,000.00
0.0180 M3. Balok Kayu Kelas II 2,000,000.00
0.2000 Ltr. Minyak Bekisting 13,653.00
0.6600 OH. Pekerja 150,000.00
0.3300 OH. Tukang Kayu 225,000.00
0.0330 OH. Kepala Tukang 0.00
0.0330 OH. Mandor 0.00

18 1M3. Sloof (12/15cm)


0.98 M3. Beton 1,352,750.00
142.98 Kg. Besi Beton 23,025.00
2.00 M2. Bekesting 235,365.30

19 1M3. Kolom (11/11cm)


0.95 M3. Beton 1,352,750.00
230.08 Kg. Besi Beton 23,025.00
9.09 M2. Bekesting 295,980.60

20 1M3. Ring balok (12/15 cm)


0.963948148148148000 M3. Beton 1,352,750.00
220.74 Kg. Besi Beton 23,025.00
3.33 M2. Bekesting 301,980.60
1,677,755.60

21 1M3. Cor Plat Beton (10 cm)


1.00 M3. Beton 1,352,750.00
142.98 Kg. Besi Beton 23,025.00
3.33 M2. Bekesting 301,980.60

22 1M3. Kuda - Kuda Kayu Besi 5/10 Bentang SD 6 M


1.1000 M3. Balok Kayu Besi 5/10 4,000,000.00
0.5600 Kg. Paku 12 cm 25,000.00
4.0000 OH. Pekerja 150,000.00
12.0000 OH. Tukang Kayu 225,000.00

23 1M3. Gording Kayu Kayu Besi 5/10


1.1000 M3. Balok Kayu Besi 5/10 4,000,000.00
3.0000 Kg. Paku 12 cm 25,000.00
2.4000 OH. Pekerja 150,000.00
7.2000 OH. Tukang Kayu 225,000.00

24 1M3. Pekerjaan Kusen Kayu Kelas I


1.1000 M3. Balok Kayu Besi 5/10 4,000,000.00
1.2500 Kg. Paku 10 cm 25,000.00
1.0000 Kg. Lem Kayu 65,000.00
7.0000 OH. Pekerja 150,000.00
21.0000 OH. Tukang Kayu 225,000.00

25 1 M2. Pekerjaan Daun Pintu Panel Kayu Kelas I


0.0400 M3. Papan Kayu Kelas I 4,000,000.00
0.5000 Kg. Lem Kayu 65,000.00
1.0000 OH. Pekerja 150,000.00
3.0000 OH. Tukang Kayu 225,000.00

26 1M2. Ventilasi
1.1000 M3. Balok Kayu Besi 5/10 4,000,000.00
1.2500 Kg. Paku 10 cm 25,000.00
1.0000 Kg. Lem Kayu 65,000.00
7.0000 OH. Pekerja 150,000.00
21.0000 OH. Tukang Kayu 225,000.00
HARGA SATUAN
No. URAIAN PEKERJAAN
(Rp)

1 2 3

27 1M' Listplank 2 x (2/20)


0.0086 M3. Papan Kayu Besi 2/20 4,000,000.00
0.0600 Kg. Paku 5 cm dan 7 cm 25,000.00
0.1000 OH. Pekerja 150,000.00
0.1000 OH. Tukang Kayu 225,000.00

28 1M2 Pas. Atap Seng Sokka Kotak Biru


0.7000 Lbr. Seng Sokka Kotak Biru 95,000.00
0.0200 Kg. Paku Seng / Atap + Karet 36,500.00
0.1200 OH. Pekerja 150,000.00
0.0600 OH. Tukang Kayu 225,000.00

29 1M' Pas. Nok Seng Sokka


1.0000 Lbr. Nok Sokka Biru 65,000.00
0.0400 Kg. Paku Seng / Atap + Karet 36,500.00
0.1500 OH. Pekerja 150,000.00
0.0700 OH. Tukang Kayu 225,000.00

30 1M2 Plafond Tripleks + Rangka


a. 1M2 Rangka Langit - Langit Kayu Kelas II
0.0120 M3. Kaso-Kaso (5x5) cm 2,000,000.00
0.1000 Kg Paku 7 cm - 10 cm 25,000.00
0.1500 OH. Pekerja 150,000.00
0.2500 OH. Tukang Kayu 225,000.00

b. 1M2 Langit-langit Tripleks Uk. 120 x 240 cm tebal 3mm


0.3750 Lbr. Tripleks 3.5 mm 100,000.00
0.0300 Kg. Paku Tripleks 36,250.00
0.1000 OH. Pekerja 150,000.00
0.1000 OH. Tukang Kayu 225,000.00

Jadi 1M2 Plafond Tripleks + Rangka (a+b)

31 1 M' List Langit-langit Kayu Profil


1.0500 M' List Kayu Profil 36,000.00
0.0100 Kg. Paku 3 - 5 cm. 25,000.00
0.0500 OH. Pekerja 150,000.00
0.0500 OH. Tukang 225,000.00

32 1M2 Pengecatan Bidang Kayu Baru (1 Lps Plamur Kayu, 1 Cat Dasar, 2 Cat Penutup)
0.2000 Kg. Cat Meni 41,667.00
0.1500 Kg. Plamur / Dempul 64,000.00
0.1700 Kg. Minyak Cat (Thiner) 54,719.00
0.2600 Kg. Cat Kilat Kayu 81,250.00
0.0700 OH. Pekerja 150,000.00
0.0090 OH. Tukang Cat 225,000.00

33 1M2 Cat Dinding Tembok Baru (1xPlamir, 1x Cat Dasar, 2 Lapis Cat Penutup)
0.1000 Kg. Plamur / Dempul 64,000.00
0.1000 Kg. Cat Dasar 23,125.00
0.2600 Kg. Cat Penutup 2x 23,125.00
0.0200 OH. Pekerja 150,000.00
0.0630 OH. Tukang Cat 225,000.00

34 1M2 Cat Plafond (1 x Cat Dasar, 2 x Cat Penutup)


0.1200 Kg. Cat Dasar 23,125.00
0.1800 Kg. Cat Penutup 86,000.00
0.0280 OH. Pekerja 150,000.00
0.0420 OH. Tukang Cat 225,000.00
HARGA SATUAN
No. URAIAN PEKERJAAN
(Rp)

1 2 3

35 1BH Kunci Tanam Kamar mandi


1.0000 Psg. Kunci Tanam Kamar Mandi 190,000.00
0.0050 OH. Pekerja 150,000.00
0.5000 OH. Tukang Kayu 225,000.00

36 1BH Pasang Kunci Selot/ Grendel Pintu


1.0000 Psg. Kunci Selot/ Grendel Pintu 36,000.00
0.0200 OH. Pekerja 150,000.00
0.2000 OH. Tukang Kayu 225,000.00

37 1BH Pasang Engsel Pintu


1.0000 Psg. Engsel Kuningan (Standard) 50,000.00
0.0150 OH. Pekerja 150,000.00
0.1500 OH. Tukang Kayu 225,000.00

38 1M2 Pasangan Lantai Keramik 20 x 20 cm


1.0000 Dos. Keramik 20 x 20 cm 100,000.00
0.0450 M3. Pasir Pasang 450,000.00
0.2000 Zak.. Semen Pc (50 Kg) 100,000.00
1.0000 Kg. Semen Warna 34,000.00
0.2700 OH Pekerja 150,000.00
0.1350 OH Tukang 225,000.00

39 1M2 Pasangan Dinding Keramik 20 x 25 cm


1.0000 Dos. Keramik 20 x 40 cm 100,000.00
0.0200 M3. Pasir Pasang 450,000.00
0.2000 Zak.. Semen Pc (50 Kg) 100,000.00
1.0000 Kg. Semen Warna 34,000.00
0.2700 OH Pekerja 150,000.00
0.1350 OH Tukang 225,000.00

40 1BH Pasang Closed Jongkok


1.0000 Bh. Klosed Jongkok 500,000.00
0.1200 Zak. Semen Pc (50 Kg) 100,000.00
0.0100 M3. Pasir Beton 450,000.00
1.0000 OH. Pekerja 150,000.00
1.5000 OH. Tukang 225,000.00

41 1M' Pasang Pipa PVC tipe AW Dia.1/2"


1.2000 M'. Pipa PVC Dia. 1/2" 10,000.00
35.000 Ls. Perlengkapan (35% Harga Pipa)
0.0360 OH. Pekerja 150,000.00
0.0600 OH. Tukang Pipa 225,000.00

42 1M' Pasang Pipa PVC tipe AW Dia. 3"


1.2000 M'. Pipa PVC Dia. 3" 53,750.00
35.000 Ls. Perlengkapan (35% Harga Pipa)
0.0810 OH. Pekerja 150,000.00
0.1350 OH. Tukang Pipa 225,000.00
HARGA SATUAN
No. URAIAN PEKERJAAN
(Rp)

1 2 3

43 1M' Pasang Pipa PVC tipe AW Dia. 1"


1.2000 M'. Pipa PVC Dia. 1" 6,250.00
35.000 Ls. Perlengkapan (35% Harga Pipa)
0.0810 OH. Pekerja 150,000.00
0.1350 OH. Tukang Pipa 225,000.00

44 1BH. Pasang Floor Drain


1.0000 Bh. Floor Drain 43,750.00
0.0100 OH. Pekerja 150,000.00
0.1000 OH. Tukang 225,000.00

45 1BH. Pasang Kran Air 1/2"


1.0000 Bh. Kran Air 1/2" 57,000.00
0.0250 Bh. Isolasi Pipa 50,000.00
0.0100 OH. Pekerja 150,000.00
0.1000 OH. Tukang 225,000.00

46 1 Ttk Lampu SL 8 Watt


1.0000 Set. Lampu SL 8 Watt + Pitting Biasa 50,000.00
2.0000 M'. Kabel NYM 2 x 2,5 mm 29,900.00
0.5000 OH. Pekerja 150,000.00
0.2000 OH. Tukang 225,000.00

47 1 Ttk Saklar Ganda


1.0000 Bh. Saklar Ganda 36,500.00
2.0000 M'. Kabel NYM 2 x 2,5 mm 29,900.00
0.5000 OH. Pekerja 150,000.00
0.5000 OH. Tukang listrik 225,000.00

48 1 Ttk Saklar Tunggal


1.0000 Bh. Saklar Tunggal 36,500.00
2.0000 M'. Kabel NYM 2 x 2,5 mm 29,900.00
0.5000 OH. Pekerja 150,000.00
0.5000 OH. Tukang listrik 225,000.00

49 1 Ttk Stop Kontak


1.0000 Bh. Stop Kontak 36,000.00
2.0000 M'. Kabel NYM 2 x 2,5 mm 29,900.00
0.5000 OH. Pekerja 150,000.00
0.5000 OH. Tukang listrik 225,000.00

50 1 Unit Mesin Pompa Air


1.0000 Unit. Mesin Pompa Air 700,000.00
2.0000 M'. Kabel NYM 2 x 2,5 mm 29,900.00
1.2000 M'. Pipa PVC Dia. 1/2" 7,750.00
0.5000 OH. Pekerja 150,000.00
ANALISA SATUAN PEKERJAAN

JUMLAH HARGA
(Rp.)

150,000.00
8,320.00
158,320.00

112,500.00
6,500.00
119,000.00

75,000.00
13,000.00
88,000.00

45,000.00
2,600.00
540,000.00
587,600.00

37,500.00
6,500.00
360,000.00
404,000.00

24,000.00
500.00
14,000.00
15,000.00
22,500.00
76,000.00

960,000.00
194,400.00
117,000.00
87,750.00
1,359,150.00

326,000.00
960,000.00
234,000.00
225,000.00
168,750.00
1,913,750.00
JUMLAH HARGA
(Rp.)

60,000.00
23,000.00
19,350.00
45,000.00
22,500.00
169,850.00

20,500.00
11,700.00
45,000.00
33,750.00
110,950.00

6,500.00
22,500.00
22,500.00
51,500.00

436,000.00
234,000.00
391,500.00
247,500.00
56,250.00
1,365,250.00

464,000.00
234,000.00
351,000.00
247,500.00
56,250.00
1,352,750.00

199,500.00
4,500.00
10,500.00
15,750.00
230,250.00
23,025.00

90,000.00
7,500.00
1,365.30
78,000.00
58,500.00
235,365.30

80,000.00
10,000.00
30,000.00
2,730.60
99,000.00
74,250.00
295,980.60
JUMLAH HARGA
(Rp.)

80,000.00
10,000.00
36,000.00
2,730.60
99,000.00
74,250.00
0.00
0.00
301,980.60

1,323,488.51
3,292,063.33
470,730.60
5,086,282.45

1,280,200.86
5,297,652.89
2,690,732.73
9,268,586.48

1,303,980.86
5,082,555.56
1,006,602.00
7,393,138.41

1,352,750.00
3,292,063.33
1,006,602.00
5,651,415.33

4,400,000.00
14,000.00
600,000.00
2,700,000.00
7,714,000.00

4,400,000.00
75,000.00
360,000.00
1,620,000.00
6,455,000.00

4,400,000.00
31,250.00
65,000.00
1,050,000.00
4,725,000.00
10,271,250.00

160,000.00
32,500.00
150,000.00
675,000.00
1,017,500.00

4,400,000.00
31,250.00
65,000.00
1,050,000.00
4,725,000.00
10,271,250.00
JUMLAH HARGA
(Rp.)

34,400.00
1,500.00
15,000.00
22,500.00
73,400.00

66,500.00
730.00
18,000.00
13,500.00
98,730.00

65,000.00
1,460.00
22,500.00
15,750.00
104,710.00

24,000.00
2,500.00
22,500.00
56,250.00
105,250.00

37,500.00
1,087.50
15,000.00
22,500.00
76,087.50
181,337.5

37,800.00
250.00
7,500.00
11,250.00
56,800.00

8,333.40
9,600.00
9,302.23
21,125.00
10,500.00
2,025.00
60,885.63

6,400.00
2,312.50
6,012.50
3,000.00
14,175.00
31,900.00

2,775.00
15,480.00
4,200.00
9,450.00
31,905.00
JUMLAH HARGA
(Rp.)

190,000.00
750.00
112,500.00
303,250.00

36,000.00
3,000.00
45,000.00
84,000.00

50,000.00
2,250.00
33,750.00
86,000.00

100,000.00
20,250.00
20,000.00
34,000.00
40,500.00
30,375.00
245,125.00

100,000.00
9,000.00
20,000.00
34,000.00
40,500.00
30,375.00
233,875.00

500,000.00
12,000.00
4,500.00
150,000.00
337,500.00
1,004,000.00

12,000.00
3,500.00
5,400.00
13,500.00
34,400.00

64,500.00
18,812.50
12,150.00
30,375.00
125,837.50
JUMLAH HARGA
(Rp.)

7,500.00
2,187.50
12,150.00
30,375.00
52,212.50

43,750.00
1,500.00
22,500.00
67,750.00

57,000.00
1,250.00
1,500.00
22,500.00
82,250.00

50,000.00
59,800.00
75,000.00
45,000.00
229,800.00

36,500.00
59,800.00
75,000.00
112,500.00
283,800.00

36,500.00
59,800.00
75,000.00
112,500.00
283,800.00

36,000.00
59,800.00
75,000.00
112,500.00
283,300.00

700,000.00
59,800.00
9,300.00
75,000.00
844,100.00
ANALISA VOLUME

KEGIATAN : PEMBANGUNAN TANGKI SEPTIK SKALA KOMUNAL (5 - 10 KK) SWAKELOLA


PEKERJAAN : PEMBANGUNAN TANGKI SEPTIK SKALA INDIVIDU (5 - 10 KK)
LOKASI :Woslay
TAHUN ANGGARAN : 2022

No. URAIAN PEKERJAAN VOLUME SATUAN HARGA SATUAN (Rp)

1 2 3

1 Pemasangan Bowplank 5.00


1.0000 OH. Pekerja 5.00 M1 300,000.24

2 Papan Nama Program/ Kegiatan 5.00


1.0000 OH. Pekerja 5.00 M1 20,000.00

3 Pengandaan Kontrak KSM 10.00 Paket


1.0000 OH. Pekerja 10.00 60,000.00

4 Pengandaan Laporan Termin I 10.00 Paket


1.0000 OH. Pekerja 10.00 60,000.00

5 Pengandaan Laporan Termin II - Paket


1.0000 OH. Pekerja - 60,000.00

6 Pengandaan Laporan Akhir - Paket 60,000.00

7 Pembuatan Stampel 5.00 Paket


1.0000 OH. Pekerja 5.00 80,000.00

8 Pembukaan Rekening 5.00 Paket


1.0000 OH. Pekerja 5.00 40,000.00

9 Pembuatan Prasasti Keramik - Paket


1.0000 OH. Pekerja - 1,000,000.00

10 Transport Material Toko 3.00 Paket


1.0000 OH. Pekerja 3.00 8,000,000.00

11 Pembersihan Lokasi 5.00 Paket


1.0000 OH. Pekerja 5.00 300,000.00

13 Pek. Galian tanah 7.88 M3


0.7500 OH. Pekerja 5.91 150,000.00
0.0250 OH. Mandor 0.20 260,000.00

13 Pek. Galian Tanah Untuk Bak Ipal - M3


0.7500 OH. Pekerja - 150,000.00
0.0250 OH. Mandor - 260,000.00

14 Pek. Urugan Pilihan - M3


0.2500 OH. Pekerja - 150,000.00
0.0250 OH. Mandor - 260,000.00
1.2000 M3. UruganTimbunan Sirtu - 300,000.00

15 Pek. Urugan Pasir di bawah pondasi - M3


0.3000 OH. Pekerja - 150,000.00
0.0100 OH. Mandor - 260,000.00
1.2000 M3. Pasir Urug - 450,000.00

16 Pek. Urugan Pasir di bawah Lantai - M3


0.3000 OH. Pekerja - 150,000.00
0.0100 OH. Mandor - 260,000.00
1.2000 M3. Pasir Urug - 450,000.00

17 Pek. Urugan tanah di bawah lantai / Peninggian lantai - M3


0.2500 OH. Pekerja - 150,000.00
0.0250 OH. Mandor - 260,000.00
1.2000 M3. UruganTimbunan Sirtu - 300,000.00

18 Pek. Pasangan batu kosong (Anstamping) 7.88 M3


1.2000 M3. Batu Karang 9.45 800,000.00
0.4320 M3. Pasir Urug 3.40 450,000.00
0.7800 OH. Pekerja 6.14 150,000.00
0.3900 OH. Tukang Batu 3.07 225,000.00
19 Pek. Pasangan Pondasi Karang/ Kali 1 : 4 40.87 M3
3.2600 Zak. Semen PC. (50 Kg) 133.23 100,000.00
1.2000 M3. Batu belah 15/20 cm 49.04 800,000.00
0.5200 M3. Pasir Pasang 21.25 450,000.00
1.5000 OH. Pekerja 61.30 150,000.00
0.7500 OH. Tukang Batu 30.65 225,000.00

20 Pek. Pasangan Batu Tela 1 : 2 - M2


20.0000 Bh. Batu Tela - 3,000.00
0.2300 Zak. Semen Pc. (50 Kg) - 100,000.00
0.0430 M3. Pasir Pasang - 450,000.00
0.3000 OH. Pekerja - 150,000.00
0.1000 OH. Tukang Batu - 225,000.00

21 Pek. Plesteran 1 : 2 - M²
0.2050 Zak. Semen PC. (50 Kg) - 100,000.00
0.0260 M3. Pasir Beton - 450,000.00
0.3000 OH. Pekerja - 150,000.00
0.1500 OH. Tukang Batu - 225,000.00

22 Pek. Acian - M²
0.0650 Zak. Semen PC. (50 Kg) - 100,000.00
0.1500 OH. Pekerja - 150,000.00
0.1000 OH. Tukang Batu - 225,000.00

23 Pas. Lantai Keramik 20/20 - M²


1.0000 Dos. Keramik 20 x 20 cm - 100,000.00
0.0450 M3. Pasir Pasang - 450,000.00
0.2000 Zak.. Semen Pc (50 Kg) - 100,000.00
1.0000 Kg. Semen Warna - 34,000.00
0.2700 OH. Pekerja - 150,000.00
0.1350 OH Tukang - 225,000.00

24 Pas. Keramik Dinding 25/20 - M²


1.0000 Dos. Keramik 20 x 25cm - 100,000.00
0.0200 M3. Pasir Pasang - 450,000.00
0.2000 Zak.. Semen Pc (50 Kg) - 100,000.00
1.0000 Kg. Semen Warna - 34,000.00
0.2700 OH. Pekerja - 150,000.00
0.1350 OH Tukang - 225,000.00

25 Pek. Sloof beton 15/20 cm - M3 0.00


Beton
4.5472 Zak. Semen Pc (50 Kg) - 100,000.00
0.5096 M3. Pasir Beton - 450,000.00
0.7644 M3. Kerikil Cor - 450,000.00
1.6170 OH. Pekerja - 150,000.00
0.2450 OH. Tukang Batu - 225,000.00
10 Kg. Pembesian (besi polos) -
1.0500 Kg. Besi Beton (Polos) - 19,000.00
0.0150 Kg. Kawat Beton - 30,000.00
0.0070 OH. Pekerja - 150,000.00
0.0070 OH. Tukang Batu - 225,000.00
1M2. Bekesting Untuk SLOOF -
0.0900 M3. Balok/Papan Kayu Kelas II - 2,000,000.00
0.6000 Kg. Paku Campur - 25,000.00
0.0384 Ltr. Minyak Bekisting - 13,653.00
1.0400 OH. Pekerja - 150,000.00
0.5200 OH. Tukang Kayu - 225,000.00

26 Pek. Kolom beton 11/11 cm - M3 0.000000000


Beton
4.4080 Zak. Semen Pc (50 Kg) - 100,000.00
0.4940 M3. Pasir Beton - 450,000.00
0.7410 M3. Kerikil Cor - 450,000.00
1.5675 OH. Pekerja - 150,000.00
0.2375 OH. Tukang Batu - 225,000.00
Kg. Besi Beton -
1.0500 Kg. Besi Beton (Polos) - 19,000.00
0.0150 Kg. Kawat Beton - 30,000.00
0.0070 OH. Pekerja - 150,000.00
0.0070 OH. Tukang Batu - 225,000.00
1M2. Bekesting Untuk Kolom -
0.0400 M3. Balok/Papan Kayu Kelas II - 2,000,000.00
0.4000 Kg. Paku Campur - 25,000.00
0.0150 M3. Balok Kayu Kelas II - 2,000,000.00
0.1604 Ltr. Minyak Bekisting - 13,653.00
0.6600 OH. Pekerja - 150,000.00
0.3300 OH. Tukang Kayu - 225,000.00

PEMBULATAN
27 Pek. Ring Balok 12/15 - M3 0.00
M3. Beton
4.4727 Zak. Semen Pc (50 Kg) - 100,000.00
0.5200 M3. Pasir Beton - 450,000.00
0.7519 M3. Kerikil Cor - 450,000.00
1.5905 OH. Pekerja - 150,000.00
0.2410 OH. Tukang Batu - 225,000.00
Kg. Besi Beton -
1.0500 Kg. Besi Beton (Polos) - 19,000.00
0.0150 Kg. Kawat Beton - 30,000.00
0.0070 OH. Pekerja - 150,000.00
0.0070 OH. Tukang Batu - 225,000.00
1M2. Bekesting Untuk Ring Balok -
0.0400 M3. Balok/Papan Kayu Kelas II - 2,000,000.00
0.4000 Kg. Paku Campur - 25,000.00
0.0180 M3. Balok Kayu Kelas II - 2,000,000.00
0.0146 Ltr. Minyak Bekisting - 13,653.00
0.6600 OH. Pekerja - 150,000.00
0.3300 OH. Tukang Kayu - 225,000.00

PEMBULATAN
28 Pek. Coor bawah lantai & Rabat, camp. 1 : 3 : 5 - M3
4.3600 Zak. Semen Pc (50 Kg) - 100,000.00
0.5200 M3. Pasir Beton - 450,000.00
0.8700 M3. Kerikil Cor - 450,000.00
1.6500 OH. Pekerja - 150,000.00
0.2500 OH. Tukang Batu - 225,000.00

29 0 - M3
4.3600 Zak. Semen Pc (50 Kg) - 86,000.00
0.5200 M3. Pasir Beton - 450,000.00
0.8700 M3. Kerikil Cor - 450,000.00
1.6500 OH. Pekerja - 150,000.00
0.2500 OH. Tukang Batu - 225,000.00

30 Pek. Pasang Kusen Kayu besi 5/10 - M3


1.1000 M3. Balok Kayu Besi 5/10 - 4,000,000.00
1.2500 Kg. Paku 10 cm - 25,000.00
1.0000 Kg. Lem Kayu - 65,000.00
7.0000 OH. Pekerja - 150,000.00
21.0000 OH. Tukang Kayu - 225,000.00

31 Pek. Pasang Pintu Panel - M3


0.0400 M3. Papan Kayu Kelas I - 4,000,000.00
0.5000 Kg. Lem Kayu - 65,000.00
1.0000 OH. Pekerja - 150,000.00
3.0000 OH. Tukang Kayu - 225,000.00

32 Pek. Ventilasi Kayu Besi - M3


1.1000 M3. Balok Kayu Besi 5/10 - 4,000,000.00
1.2500 Kg. Paku 10 cm - 25,000.00
1.0000 Kg. Lem Kayu - 65,000.00
7.0000 OH. Pekerja - 150,000.00
21.0000 OH. Tukang Kayu - 225,000.00

33 Pek. Kuda-kuda Balok Kayu besi 5/10 -


1.1000 M3. Balok Kayu Besi 5/10 - 4,000,000.00
0.5600 Kg. Paku 12 cm - 25,000.00
4.0000 OH. Pekerja - 150,000.00
12.0000 OH. Tukang Kayu - 225,000.00

34 Pek. Gording Balok Kayu 5/10 - M3


1.1000 M3. Balok Kayu Besi 5/10 - 4,000,000.00
3.0000 Kg. Paku 12 cm - 25,000.00
2.4000 OH. Pekerja - 150,000.00
7.2000 OH. Tukang Kayu - 225,000.00

35 Pek. Skur Angin Balok Kayu 5/10 - M3


1.1000 M3. Balok Kayu Besi 5/10 - 4,000,000.00
3.0000 Kg. Paku 12 cm - 25,000.00
2.4000 OH. Pekerja - 150,000.00
7.2000 OH. Tukang Kayu - 225,000.00

36 Pek. Atap Seng Sokka Biru - Lembar


0.7000 Lbr. Seng Sokka Kotak Biru - 95,000.00
0.0200 Kg. Paku Seng / Atap + Karet - 36,500.00
0.1200 OH. Pekerja - 150,000.00
0.0600 OH. Tukang Kayu - 225,000.00

37 Pek. Nok Seng Sokka Biru - M2


1.0000 Lbr. Nok Sokka Biru - 65,000.00
0.0400 Kg. Paku Seng / Atap + Karet - 36,500.00
0.1500 OH. Pekerja - 150,000.00
0.0700 OH. Tukang Kayu - 225,000.00

38 Pek. Lisplank Papan Kayu Besi 2/20 - M1


0.0086 M3. Papan Kayu Besi 2/20 - 4,000,000.00
0.0600 Kg. Paku Campur - 25,000.00
0.1000 OH. Pekerja - 150,000.00
0.1000 OH. Tukang Kayu - 225,000.00

39 Pek. Plafond Tripleks 3mm + Rangka - M2


0.0120 M3. Kayu 5/5 (5x5) cm - 2,000,000.00
0.1000 Kg. Paku Campur - 25,000.00
0.1500 OH. Pekerja - 150,000.00
0.2500 OH. Tukang Kayu - 225,000.00
0.3750 Lbr. Tripleks 3.5 mm - 100,000.00
0.0300 Kg. Paku Tripleks - 36,250.00
0.1000 OH. Pekerja - 150,000.00
0.1000 OH. Tukang Kayu - 225,000.00

40 Pek. List Plafond Luar & Dalam - M1


1.0500 M' List Kayu Profil - 36,000.00
0.0100 Kg. Paku Campur - 25,000.00
0.0500 OH. Pekerja - 150,000.00
0.0500 OH. Tukang - 225,000.00

41 Pek. Pasang Kunci tanam 2 Slaag (KM/WC) - BH


1.0000 Psg. Kunci Tanam Kamar Mandi - 190,000.00
0.0050 OH. Pekerja - 150,000.00
0.5000 OH. Tukang Kayu - 225,000.00

42 Pek. Pasang Engsel pintu - PSG


1.0000 Psg. Engsel Kuningan (Standard) - 50,000.00
0.0150 OH. Pekerja - 150,000.00
0.1500 OH. Tukang Kayu - 225,000.00

43 Pek. Pipa PVC Dia.1/2" 24.00 M1


1.2000 M'. Pipa PVC Dia. 1/2" 28.80 10,000.00
1.0000 Ls. Perlengkapan (35% Harga Pipa) 24.00 3,500.00
0.0360 OH. Pekerja 0.86 150,000.00
0.0600 OH. Tukang Pipa 1.44 225,000.00

44 Pek. Pipa PVC Dia.3" - M1


1.2000 M'. Pipa PVC Dia. 3" - 53,750.00
1.0000 Ls. Perlengkapan (35% Harga Pipa) - 18,812.50
0.0810 OH. Pekerja - 150,000.00
0.1350 OH. Tukang Pipa - 225,000.00

45 Pas. Klosed Jongkok - BH


1.0000 Bh. Klosed Jongkok - 500,000.00
0.1200 Zak. Semen Pc (50 Kg) - 100,000.00
0.0100 M3. Pasir Beton - 450,000.00
1.0000 OH. Pekerja - 150,000.00
1.5000 OH. Tukang - 225,000.00

46 Pas. Floor Drain - BH


1.0000 Bh. Floor Drain - 43,750.00
0.0100 OH. Pekerja - 150,000.00
0.1000 OH. Tukang - 225,000.00

47 Pas. Kran Air - BH


1.0000 Bh. Kran Air 1/2" - 57,000.00
0.0250 Bh. Isolasi Pipa - 50,000.00
0.0100 OH. Pekerja - 150,000.00
0.1000 OH. Tukang - 225,000.00

48 Pek. Pengadaan Bak Viber - BH


1.0000 Bak Viber - 700,000.00
49 Pek. Pengadaan Sumur Dangkal - BH
1.0000 Pengadaan Sumur - 4,000,000.00

50 Cor Lantai Kerja Bawah IPAL - M3


4.3600 Zak. Semen Pc (50 Kg) - 100,000.00
0.5200 M3. Pasir Beton - 450,000.00
0.8700 M3. Kerikil Cor - 450,000.00
1.6500 OH. Pekerja - 150,000.00
0.2500 OH. Tukang Batu - 225,000.00

51 Pengadaan Mesin Air - BH


6.0000 Mesin Pompa Air - 800,000.00

52 Pasang Lampu SL 8 watt + Fitting - BH


1.0000 Set. Lampu SL 8 Watt + Pitting Biasa - 50,000.00
2.0000 M'. Kabel NYM 2 x 2,5 mm - 29,900.00
0.5000 OH. Pekerja - 150,000.00
0.2000 OH. Tukang - 225,000.00

53 Pasang Saklar Ganda 3 - BH


1.0000 Bh. Saklar Ganda - 36,500.00
2.0000 M'. Kabel NYM 2 x 2,5 mm - 29,900.00
0.5000 OH. Pekerja - 150,000.00
0.5000 OH. Tukang listrik - 225,000.00

54 Stop Kontak - M2
1.0000 Bh. Stop Kontak - 36,000.00
2.0000 M'. Kabel NYM 2 x 2,5 mm - 29,900.00
0.5000 OH. Pekerja - 150,000.00
0.5000 OH. Tukang listrik - 225,000.00

55 Pek. Cat Kilat Kayu - M2


0.2000 Kg. Cat Meni - 41,667.00
0.1500 Kg. Plamur / Dempul - 64,000.00
0.1700 Kg. Minyak Cat (Thiner) - 54,719.00
0.2600 Kg. Cat Kilat Kayu - 81,250.00
0.0700 OH. Pekerja - 150,000.00
0.0090 OH. Tukang Cat - 225,000.00

56 Pek. Cat Tembok - BH


0.1000 Kg. Plamur / Dempul - 64,000.00
0.1000 Kg. Cat Dasar - 23,125.00
0.2600 Kg. Cat Penutup 2x - 23,125.00
0.0200 OH. Pekerja - 150,000.00
0.0630 OH. Tukang Cat - 225,000.00

57 Pek. Cat Plafond - BH


0.1200 Kg. Cat Dasar - 23,125.00
0.1800 Kg. Cat Penutup - 86,000.00
0.0280 OH. Pekerja - 150,000.00
0.0420 OH. Tukang Cat - 225,000.00

58 Pekerjaan Akhir - LS
1.0000 Pekerjaan Akhir - 866,017.01

59 Pengadaan Tandon Air Dan Dudukan - BH


1.0000 Pengadaan Tandon Air Dan Dudukan - 5,000,000.00

60 Pengadaan Tangki Ipal 5.00 BH


1.0000 Pengadaan Tangki Ipal 5.00 7,500,000.00

61 Pek. Pasangan Batu Tela 1 : 2 - M2


20.0000 Bh. Batu Tela - 3,000.00
0.2300 Zak. Semen Pc. (50 Kg) - 100,000.00
0.0430 M3. Pasir Pasang - 450,000.00
0.3000 OH. Pekerja - 150,000.00
0.1000 OH. Tukang Batu - 225,000.00

62 Cor Lantai K 175 ( T = 12 cm) - M3


4.3600 Zak. Semen Pc (50 Kg) - 100,000.00
0.5200 M3. Pasir Beton - 450,000.00
0.8700 M3. Kerikil Cor - 450,000.00
1.6500 OH. Pekerja - 150,000.00
0.2500 OH. Tukang Batu - 225,000.00
JUMLAH HARGA (Rp.)

1,500,001.20
1,500,001.20

100,000.00
100,000.00

600,000.00
600,000.00

600,000.00
600,000.00

-
-
-
-

400,000.00
400,000.00

200,000.00
200,000.00

-
-

24,000,000.00
24,000,000.00

1,500,000.00
1,500,000.00
28,900,001.20

885,937.50
51,187.50
937,125.00

-
-
-

-
-
-
-

-
-
-
-

-
-
-
-

-
-
-
-

7,560,000.00
1,530,900.00
921,375.00
691,031.25
10,703,306.25

13,322,700.97
39,232,493.66
9,562,920.33
9,195,115.70
6,896,336.78
78,209,567.45

-
-
-
-
-
-

-
-
-
-
-

-
-
-
-

-
-
-
-
-
-
-

-
-
-
-
-
-
-

-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-

-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-

-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-

-
-
-
-
-
-

-
-
-
-
-
-

-
-
-
-
-
-

-
-
-
-
-

-
-
-
-
-
-

-
-
-
-
-

-
-
-
-
-

-
-
-
-
-

-
-
-
-
-

-
-
-
-
-

-
-
-
-
-

-
-
-
-
-
-
-
-
-

-
-
-
-
-

-
-
-
-

-
-
-
-

288,000.00
84,000.00
129,600.00
324,000.00
825,600.00

-
-
-
-
-

-
-
-
-
-
-

-
-
-
-

-
-
-
-
-

-
-

-
-

-
-
-
-
-
-

-
-

-
-
-
-
-

-
-
-
-
-

-
-
-
-
-

-
-
-
-
-
-
-

-
-
-
-
-
-

-
-
-
-
-

-
-

-
-

37,500,000.00
37,500,000.00

-
-
-
-
-
-

-
-
-
-
-
-
ANALISA PEMBERDAYAAN TAHAP 1
: PEMBANGUNAN TANGKI SEPTIK SKALA KOMUNAL (5 - 10
KEGIATAN
:KK) SWAKELOLA TANGKI SEPTIK SKALA KOMUNAL (5 - 10
PEMBANGUNAN
PEKERJAAN
KK)
LOKASI : KAMPUNG PETIWE
TAHUN ANGGARAN : 2022

NO Deskripsi Produk Kuantitas SATUAN Harga /Unit Harga


1 Pemasangan Bowplank 5.00 Rp 300,000 Rp 1,500,001
2 Papan Nama Program/ Kegiatan 5.00 Rp 20,000 Rp 100,000
3 Pengandaan Kontrak KSM 10.00 Rp 60,000 Rp 600,000
4 Pengandaan Laporan Termin I 10.00 Rp 60,000 Rp 600,000
5 Pengandaan Laporan Termin II 0.00 Rp 60,000 Rp -
6 Pengandaan Laporan Akhir 0.00 Rp 60,000 Rp -
7 Pembuatan Stampel Dan BOP KSM 5.00 Rp 80,000 Rp 400,000
8 Pembukaan Rekening 5.00 Rp 40,000 Rp 200,000
9 Pembuatan Prasasti Keramik 0.00 Rp 1,000,000 Rp -
10 Transport Material Toko 3.00 Rp 8,000,000 Rp 24,000,000
11 Pembersihan Lokasi 5.00 Rp 300,000 Rp 1,500,000
TOTAL Subtotal (Rp) 28,900,001.20
RENCANA PENGGUNAAN DANA T AHAP 1
KEGIATAN : PEMBANGUNAN TANGKI SEPTIK SKALA KOMUNAL (5 - 10 KK) SWAKELOLA
PEKERJAAN : PEMBANGUNAN TANGKI SEPTIK SKALA INDIVIDU (5 - 10 KK)
LOKASI : KAMPUNG…......
TAHUN ANGGARAN : 2020

JUMLAH PENGAJUAN HARGA SATUAN JUMLAH HARGA


NO. URAIAN PEKERJAAN VOLUME SAT.
SEKARANG (Rp.) (Rp.)
1 2 3 4 5 6

### PEKERJAAN PERSIAPAN


### #REF! #REF! #REF! #REF! #REF! #REF!
### #REF! #REF! #REF! #REF! #REF! #REF!
#REF!
### #REF!
### #REF!
### #REF! #REF! #REF! #REF! #REF! #REF!
### #REF!
### #REF! #REF! #REF! #REF! #REF! #REF!
### #REF! #REF! #REF! #REF! #REF! #REF!
### #REF! #REF! #REF! #REF! #REF! #REF!
### #REF! #REF! #REF! #REF! #REF! #REF!
### #REF! #REF! #REF! #REF! #REF! #REF!
### #REF! #REF! #REF! #REF! #REF! #REF!
### #REF! #REF! #REF! #REF! #REF! #REF!
### #REF! #REF! #REF! #REF! #REF! #REF!

### #REF! #REF!


### #REF! #REF! #REF! #REF! #REF! #REF!
### #REF! #REF! #REF! #REF! #REF! #REF!
### #REF! #REF! #REF! #REF! #REF! #REF!
### #REF! #REF! #REF! #REF! #REF! #REF!
### #REF! #REF! #REF! #REF! #REF! #REF!
### #REF! #REF! #REF! #REF! #REF! #REF!

### #REF! #REF!


### #REF! #REF! #REF! #REF! #REF! #REF!
### #REF! #REF! #REF! #REF! #REF! #REF!
### #REF! #REF! #REF! #REF! #REF! #REF!
### #REF! #REF! #REF! #REF! #REF! #REF!
### #REF! #REF! #REF! #REF! #REF! #REF!
### #REF! #REF! #REF! #REF! #REF! #REF!
### #REF! #REF! #REF! #REF! #REF! #REF!

### #REF! #REF!


1 #REF! #REF! #REF! #REF! #REF! #REF!
2 #REF! #REF! #REF! #REF! #REF! #REF!
3 #REF! #REF! #REF! #REF! #REF! #REF!
4 #REF! #REF! #REF! #REF! #REF! #REF!
5 #REF! #REF! #REF! #REF! #REF! #REF!

### #REF! #REF!


### #REF! #REF! #REF! #REF! #REF! #REF!
### #REF! #REF! #REF! #REF! #REF! #REF!
### #REF! #REF! #REF! #REF! #REF! #REF!

### #REF! #REF!


### #REF! #REF! #REF! #REF! #REF! #REF!
### #REF! #REF! #REF! #REF! #REF! #REF!
### #REF! #REF! #REF! #REF! #REF! #REF!
### #REF! #REF! #REF! #REF! #REF! #REF!
### #REF! #REF! #REF! #REF! #REF! #REF!
### #REF! #REF! #REF! #REF! #REF! #REF!
### #REF! #REF! #REF! #REF! #REF! #REF!
### #REF! #REF! #REF! #REF! #REF! #REF!

### #REF! #REF!


### #REF! #REF! #REF! #REF! #REF! #REF!
### #REF! #REF! #REF! #REF! #REF! #REF!
JUMLAH PENGAJUAN HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN VOLUME SAT.
SEKARANG (Rp.) (Rp.)
1 2 3 4 5 6

### #REF! #REF!


### #REF! #REF! #REF! #REF! #REF! #REF!
### #REF! #REF! #REF! #REF! #REF! #REF!
### #REF! #REF! #REF! #REF! #REF! #REF!
### #REF! #REF! #REF! #REF! #REF! #REF!
### #REF! #REF! #REF! #REF! #REF! #REF!
### #REF! #REF! #REF! #REF! #REF! #REF!
### #REF! #REF! #REF! #REF! #REF! #REF!
### #REF! #REF! #REF! #REF! #REF! #REF!
### #REF! #REF! #REF! #REF! #REF! #REF!
### #REF! #REF! #REF! #REF! #REF! #REF!
### #REF! #REF! #REF! #REF! #REF! #REF!
### #REF! #REF! #REF! #REF! #REF! #REF!
### #REF! #REF! #REF! #REF! #REF! #REF!
### #REF! #REF! #REF!

### #REF! #REF!


### #REF! #REF! #REF! #REF! #REF! #REF!
### #REF! #REF! #REF! #REF! #REF! #REF!
### #REF! #REF! #REF! #REF! #REF! #REF!

### #REF! #REF!


### #REF! #REF! #REF! #REF! #REF! #REF!
### #REF! #REF! #REF! #REF! #REF! #REF!
### #REF! #REF! #REF! #REF! #REF! #REF!
#REF!

### #REF!
### #REF! #REF! #REF! #REF! #REF! #REF!
#REF!
TOTAL DANA 50% #REF!
TOTAL PEMBULATAN #REF!
ANALISA BAHAN LOKAL TAHAP 1

: PEMBANGUNAN TANGKI SEPTIK SKALA KOMUNAL (5 - 10 KK)


KEGIATAN
SWAKELOLA
PEKERJAAN : PEMBANGUNAN TANGKI SEPTIK SKALA KOMUNAL (5 - 10 KK)
LOKASI : KAMPUNG PETIWE
TAHUN ANGGARAN : 2022

NO Deskripsi Produk Kuantitas SATUAN Harga /Unit Harga


1 Pekerja 73.35 OH Rp 150,000 Rp 11,002,428
2 Tukang 33.72 OH Rp 225,000 Rp 7,587,368
3 Mandor 0.20 OH Rp 260,000 Rp 51,188
4 Bh. Batu Tela 0.00 BH Rp 3,000 Rp -
5 Batu Karang/ Kali 9.45 M3 Rp 800,000 Rp 7,560,000
6 Baru Karang / Kali 49.04 M3 Rp 800,000 Rp 39,232,494
7 Pasir 24.65 M3 Rp 450,000 Rp 11,093,820
8 sirtu 0.00 M3 Rp 300,000 Rp -
9 Kerikil Cor 0.00 M3 Rp 450,000 Rp -
10 Kayu Kelas II 0.00 M3 Rp 2,000,000 Rp -
11 kayu kelas I 0.00 M3 Rp 4,000,000 Rp -
12 Papan Kayu Besi 2/20 0.00 M3 Rp 4,000,000 Rp -
13 Kayu Besi 5/10 0.00 M3 Rp 4,000,000 Rp -
14 Pengadaan Sumur 0.00 BH Rp 4,000,000 Rp -
Pengadaan Tandon Air Dan
15 0.00 BH Rp 5,000,000 Rp -
Dudukan
16 Kayu 5/5 0.00 M3 Rp 2,000,000 Rp -
17 Pekerjaan Akhir 0.00 LS Rp 866,017 Rp -
TOTAL Subtotal (Rp) 76,527,297.72
ANALISA BAHAN TOKO TAHAP 1
: PEMBANGUNAN TANGKI SEPTIK SKALA KOMUNAL (5 - 10 KK)
KEGIATAN
SWAKELOLA
PEKERJAAN : PEMBANGUNAN TANGKI SEPTIK SKALA KOMUNAL (5 - 10 KK)
LOKASI : KAMPUNG PETIWE
TAHUN ANGGARAN : 2022

NO Deskripsi Produk Kuantitas SATUAN Harga /Unit Harga


1 Semen PC 133.23 ZAK Rp 100,000 Rp 13,322,701
2 Semen Warna 0.00 KG Rp 34,000 Rp -
3 Keramik 20 x 20 0.00 DOS Rp 100,000 Rp -
4 Keramik 20 x 25 0.00 DOS Rp 100,000 Rp -
5 Besi BETON POLOS 0.00 KG Rp 19,000 Rp -
6 Kawat Beton 0.00 KG Rp 30,000 Rp -
7 Minyak Bekesting 0.00 LTR Rp 13,653 Rp -
8 Paku 10 CM 0.00 KG Rp 25,000 Rp -
9 Paku Campur 0.00 KG Rp 25,000 Rp -
10 Paku Seng 0.00 KG Rp 36,500 Rp -
11 Paku 12 0.00 KG Rp 25,000 Rp -
12 Paku Triplek 0.00 KG Rp 36,250 Rp -
13 Lem Kayu 0.00 KANTONG Rp 65,000 Rp -
14 Seng Soka Gelombang Biru 0.00 M2 Rp 95,000 Rp -
15 Nok Seng 0.00 M1 Rp 65,000 Rp -
16 Triplek 3.5 mm 0.00 M2 Rp 100,000 Rp -
17 List Kayu Plafond 0.00 M1 Rp 36,000 Rp -
18 Kunci Tanam 2 Slag 0.00 BH Rp 190,000 Rp -
19 Engsel Kuningan 0.00 BH Rp 50,000 Rp -
20 Pipa PVC 1/2 0.00 M1 Rp 10,000 Rp -
21 Perlengkapan (Pipa 1/2) 0.00 LS Rp 3,500 Rp -
22 Pipa PCV 3 '' 0.00 M1 Rp 53,750 Rp -
23 Perlengkapan (Pipa 3'') 0.00 LS Rp 18,813 Rp -
24 Kloset Jongkok 0.00 BH Rp 500,000 Rp -
25 Floordrain 0.00 BH Rp 43,750 Rp -
26 Kran Air 1/2 0.00 BH Rp 57,000 Rp -
27 Isolasi/ Seltip 0.00 M1 Rp 50,000 Rp -
28 Bak Viber 0.00 BH Rp 700,000 Rp -
29 Pengadaan Mesin Pompa 0.00 BH Rp 800,000 Rp -
30 Lampu 8 Watt + Fitting 0.00 BH Rp 50,000 Rp -
31 Kabel NYM 2 X 2,5 mm 0.00 M1 Rp 29,900 Rp -
32 Stop Kontak 0.00 BH Rp 36,000 Rp -
33 Saklar Ganda 0.00 BH Rp 36,500 Rp -
34 Cat Meni 0.00 M1 Rp 41,667 Rp -
35 Dempul/ Plamur 0.00 KG Rp 64,000 Rp -
36 Cat Tembok Dasar 0.00 KG Rp 23,125 Rp -
37 Cat Penutup 2x 0.00 KG Rp 23,125 Rp -
38 Cat Kilat Kayu 0.00 KG Rp 81,250 Rp -
39 Cat Penutup 0.00 KG Rp 86,000 Rp -
40 Tiner 0.00 LTR Rp 54,719 Rp -
41 Pengadaan Tank Ipal 5.00 BH Rp 7,500,000 Rp 37,500,000
TOTAL Subtotal (Rp) 50,822,700.97
ANALISA BAHAN KESELURUHAN TAHAP 1
KEGIATAN : PEMBANGUNAN TANGKI SEPTIK SKALA KOMUNAL (5 - 10 KK) SW
PEKERJAAN : PEMBANGUNAN TANGKI SEPTIK SKALA KOMUNAL (5 - 10 KK)
LOKASI : KAMPUNG PETIWE
TAHUN ANGGARAN : 2022

NO Deskripsi Produk Kuantitas SATUAN Harga /Unit Harga


1 Pekerja 73.35 OH Rp 150,000 Rp 11,002,428
2 Tukang 33.72 OH Rp 225,000 Rp 7,587,368
3 Mandor 0.20 OH Rp 260,000 Rp 51,188
4 Bh. Batu Tela 0.00 BH Rp 3,000 Rp -
5 Batu Karang/ Kali 9.45 M3 Rp 800,000 Rp 7,560,000
6 Baru Karang / Kali 49.04 M3 Rp 800,000 Rp 39,232,494
7 Semen PC 133.23 ZAK Rp 100,000 Rp 13,322,701
8 Semen Warna 0.00 KG Rp 34,000 Rp -
9 Pasir 24.65 M3 Rp 450,000 Rp 11,093,820
10 sirtu 0.00 M3 Rp 300,000 Rp -
11 Keramik 20 x 20 0.00 DOS Rp 100,000 Rp -
12 Keramik 20 x 25 0.00 DOS Rp 100,000 Rp -
13 Kerikil Cor 0.00 M3 Rp 450,000 Rp -
14 Besi BETON POLOS 0.00 KG Rp 19,000 Rp -
15 Kawat Beton 0.00 KG Rp 30,000 Rp -
16 Kayu Kelas II 0.00 M3 Rp 2,000,000 Rp -
17 Minyak Bekesting 0.00 LTR Rp 13,653 Rp -
18 kayu kelas I 0.00 M3 Rp 4,000,000 Rp -
19 Paku 10 CM 0.00 KG Rp 25,000 Rp -
20 Paku Campur 0.00 KG Rp 25,000 Rp -
21 Paku Seng 0.00 KG Rp 36,500 Rp -
22 Paku 12 0.00 KG Rp 25,000 Rp -
23 Paku Triplek 0.00 KG Rp 36,250 Rp -
24 Lem Kayu 0.00 KANTONG Rp 65,000 Rp -
25 Papan Kayu Besi 2/20 0.00 M3 Rp 4,000,000 Rp -
26 Kayu Besi 5/10 0.00 M3 Rp 4,000,000 Rp -
27 Seng Soka Gelombang Biru 0.00 M2 Rp 95,000 Rp -
28 Nok Seng 0.00 M1 Rp 65,000 Rp -
29 Triplek 3.5 mm 0.00 M2 Rp 100,000 Rp -
30 List Kayu Plafond 0.00 M1 Rp 36,000 Rp -
31 Kunci Tanam 2 Slag 0.00 BH Rp 190,000 Rp -
32 Engsel Kuningan 0.00 BH Rp 50,000 Rp -
33 Pipa PVC 1/2 0.00 M1 Rp 10,000 Rp -
34 Perlengkapan (Pipa 1/2) 0.00 LS Rp 3,500 Rp -
35 Pipa PCV 3 '' 0.00 M1 Rp 53,750 Rp -
36 Perlengkapan (Pipa 3'') 0.00 LS Rp 18,813 Rp -
37 Kloset Jongkok 0.00 BH Rp 500,000 Rp -
38 Floordrain 0.00 BH Rp 43,750 Rp -
39 Kran Air 1/2 0.00 BH Rp 57,000 Rp -
40 Isolasi/ Seltip 0.00 M1 Rp 50,000 Rp -
41 Bak Viber 0.00 BH Rp 700,000 Rp -
42 Pengadaan Sumur 0.00 BH Rp 4,000,000 Rp -
43 Pengadaan Mesin Pompa 0.00 BH Rp 800,000 Rp -
44 Lampu 8 Watt + Fitting 0.00 BH Rp 50,000 Rp -
45 Kabel NYM 2 X 2,5 mm 0.00 M1 Rp 29,900 Rp -
46 Stop Kontak 0.00 BH Rp 36,000 Rp -
47 Saklar Ganda 0.00 BH Rp 36,500 Rp -
48 Cat Meni 0.00 M1 Rp 41,667 Rp -
49 Dempul/ Plamur 0.00 KG Rp 64,000 Rp -
50 Cat Tembok Dasar 0.00 KG Rp 23,125 Rp -
51 Cat Penutup 2x 0.00 KG Rp 23,125 Rp -
52 Cat Kilat Kayu 0.00 KG Rp 81,250 Rp -
53 Cat Penutup 0.00 KG Rp 86,000 Rp -
54 Pengadaan Tandon Air Dan Du 0.00 BH Rp 5,000,000 Rp -
55 Tiner 0.00 LTR Rp 54,719 Rp -
56 Pengadaan Tank Ipal 5.00 BH Rp 7,500,000 Rp 37,500,000
57 Kayu 5/5 0.00 M3 Rp 2,000,000 Rp -
58 Pekerjaan Akhir 0.00 LS Rp 866,017 Rp -

Catatan: Subtotal (Rp) 127,349,998.70


Mohon lakukan pembayaran maks. 30 hari Pemberdayaan 28,900,001.20
setelah PO ini dikirim Total (Rp) 156,249,999.90
PEMBULATAN 156,249,999.90
ANALISA VOLUME

KEGIATAN : PEMBANGUNAN TANGKI SEPTIK SKALA KOMUNAL (5 - 10 KK) SWAKELOLA


PEKERJAAN : PEMBANGUNAN TANGKI SEPTIK SKALA INDIVIDU (5 - 10 KK)
LOKASI :Woslay
TAHUN ANGGARAN : 2022

HARGA SATUAN
No. URAIAN PEKERJAAN VOLUME SATUAN
(Rp)

1 2 3

1 Pemasangan Bowplank 5.00


1.0000 OH. Pekerja 5.00 M1 300,000.24

2 Papan Nama Program/ Kegiatan 5.00


1.0000 OH. Pekerja 5.00 M1 20,000.00

3 Pengandaan Kontrak KSM 10.00 Paket


1.0000 OH. Pekerja 10.00 60,000.00

4 Pengandaan Laporan Termin I 10.00 Paket


1.0000 OH. Pekerja 10.00 60,000.00

5 Pengandaan Laporan Termin II - Paket


1.0000 OH. Pekerja - 60,000.00

6 Pengandaan Laporan Akhir - Paket 60,000.00

7 Pembuatan Stampel 5.00 Paket


1.0000 OH. Pekerja 5.00 80,000.00

8 Pembukaan Rekening 5.00 Paket


1.0000 OH. Pekerja 5.00 40,000.00

9 Pembuatan Prasasti Keramik - Paket


1.0000 OH. Pekerja - 1,000,000.00

10 Err:509 Err:509 Paket


1.0000 OH. Pekerja Err:509 Err:509

11 Transport Material Toko 3.00 Paket


1.0000 OH. Pekerja 3.00 8,000,000.00

12 Pembersihan Lokasi 5.00 Paket


1.0000 OH. Pekerja 5.00 300,000.00

13 Pek. Galian tanah 7.88 M3


0.7500 OH. Pekerja 5.91 150,000.00
0.0250 OH. Mandor 0.20 210,000.00

13 Pek. Galian Tanah Untuk Bak Ipal - M3


0.7500 OH. Pekerja - 150,000.00
0.0250 OH. Mandor - 210,000.00

14 Pek. Urugan Pilihan - M3


0.5000 OH. Pekerja - 150,000.00
0.0500 OH. Mandor - 210,000.00
15 Pek. Urugan Pasir di bawah pondasi - M3
0.3000 OH. Pekerja - 150,000.00
0.0100 OH. Mandor - 260,000.00
1.2000 M3. Pasir Urug - 450,000.00

16 Pek. Urugan Pasir di bawah Lantai - M3


0.3000 OH. Pekerja - 150,000.00
0.0100 OH. Mandor - 260,000.00
1.2000 M3. Pasir Urug - 450,000.00

Pek. Urugan tanah di bawah lantai / Peninggian


17 - M3
lantai
0.2500 OH. Pekerja - 150,000.00
0.0250 OH. Mandor - 260,000.00
1.2000 M3. UruganTimbunan Sirtu - 300,000.00

18 Pek. Pasangan batu kosong (Anstamping) 7.88 M3


1.2000 M3. Batu belah 15/20 cm 9.45 800,000.00
0.4320 M3. Pasir Urug 3.40 450,000.00
0.7800 OH. Pekerja 6.14 150,000.00
0.3900 OH. Tukang Batu 3.07 225,000.00

19 Pek. Pasangan Pondasi Karang/ Kali 1 : 4 40.87 M3


3.2600 Zak. Semen PC. (50 Kg) 133.23 100,000.00
1.2000 M3. Batu belah 15/20 cm 49.04 800,000.00
0.5200 M3. Pasir Pasang 21.25 450,000.00
1.5000 OH. Pekerja 61.30 150,000.00
0.7500 OH. Tukang Batu 30.65 225,000.00

20 Pek. Pasangan Batu Tela 1 : 2 - M2


20.0000 Bh. Batu Tela - 3,000.00
0.2300 Zak. Semen Pc. (50 Kg) - 100,000.00
0.0430 M3. Pasir Pasang - 450,000.00
0.3000 OH. Pekerja - 150,000.00
0.1000 OH. Tukang Batu - 225,000.00

21 Pek. Plesteran 1 : 2 - M²
0.2050 Zak. Semen PC. (50 Kg) - 86,000.00
0.0260 M3. Pasir Beton - 450,000.00
0.3000 OH. Pekerja - 150,000.00
0.1500 OH. Tukang Batu - 225,000.00

22 Pek. Acian - M²
0.0650 Zak. Semen PC. (50 Kg) - 86,000.00
0.1500 OH. Pekerja - 150,000.00
0.1000 OH. Tukang Batu - 225,000.00

23 Pas. Lantai Keramik 20/20 - M²


1.0000 Dos. Keramik 20 x 20 cm - 100,000.00
0.0450 M3. Pasir Pasang - 450,000.00
0.2000 Zak.. Semen Pc (50 Kg) - 86,000.00
1.0000 Kg. Semen Warna - 34,000.00
0.2107 OH. Pekerja - 150,000.00
0.1390 OH Tukang - 225,000.00

24 Pas. Keramik Dinding 25/20 - M²


1.0000 Dos. Keramik 20 x 25cm - 95,000.00
0.0200 M3. Pasir Pasang - 450,000.00
0.2000 Zak.. Semen Pc (50 Kg) - 86,000.00
1.0000 Kg. Semen Warna - 34,000.00
0.2160 OH. Pekerja - 150,000.00
0.1350 OH Tukang - 225,000.00

25 Pek. Sloof beton 15/20 cm #REF! M3 0.00


Beton
#REF! Zak. Semen Pc (50 Kg) #REF! 86,000.00
#REF! M3. Pasir Beton #REF! 450,000.00
#REF! M3. Kerikil Cor #REF! 450,000.00
#REF! OH. Pekerja #REF! 150,000.00
#REF! OH. Tukang Batu #REF! 200,000.00
10 Kg. Pembesian (besi polos) #REF!
#REF! Kg. Besi Beton (Polos) #REF! 19,000.00
#REF! Kg. Kawat Beton #REF! 30,000.00
#REF! OH. Pekerja #REF! 150,000.00
#REF! OH. Tukang Batu #REF! 200,000.00
1M2. Bekesting Untuk SLOOF #REF!
#REF! M3. Balok/Papan Kayu Kelas II #REF! 2,000,000.00
#REF! Kg. Paku Campur #REF! 25,000.00
#REF! Ltr. Minyak Bekisting #REF! 13,653.00
#REF! OH. Pekerja #REF! 150,000.00
#REF! OH. Tukang Kayu #REF! 200,000.00

26 Pek. Kolom beton 11/11 cm #REF! M3 0.000000000


Beton
4.6400 Zak. Semen Pc (50 Kg) #REF! 86,000.00
0.5200 M3. Pasir Beton #REF! 450,000.00
0.7800 M3. Kerikil Cor #REF! 450,000.00
1.6500 OH. Pekerja #REF! 150,000.00
0.2500 OH. Tukang Batu #REF! 200,000.00
Kg. Besi Beton #REF!
1.0500 Kg. Besi Beton (Polos) #REF! 19,000.00
0.0150 Kg. Kawat Beton #REF! 30,000.00
0.0070 OH. Pekerja #REF! 150,000.00
0.0070 OH. Tukang Batu #REF! 200,000.00
1M2. Bekesting Untuk Kolom #REF!
#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!

PEMBULATAN
27 Pek. Kolom beton 11/11 cm #REF! M3 0.00
M3. Beton
4.6400 Zak. Semen Pc (50 Kg) #REF! 86,000.00
0.5200 M3. Pasir Beton #REF! 450,000.00
0.7800 M3. Kerikil Cor #REF! 450,000.00
1.6500 OH. Pekerja #REF! 150,000.00
0.2500 OH. Tukang Batu #REF! 200,000.00
Kg. Besi Beton #REF!
1.0500 Kg. Besi Beton (Polos) #REF! 19,000.00
0.0150 Kg. Kawat Beton #REF! 30,000.00
0.0070 OH. Pekerja #REF! 150,000.00
0.0070 OH. Tukang Batu #REF! 200,000.00
1M2. Bekesting Untuk Ring Balok #REF!
#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!

PEMBULATAN
28 Pek. Coor bawah lantai & Rabat, camp. 1 : 3 : 5 - M3
4.3600 Zak. Semen Pc (50 Kg) - 86,000.00
0.5200 M3. Pasir Beton - 450,000.00
0.8700 M3. Kerikil Cor - 450,000.00
1.6500 OH. Pekerja - #REF!
0.2500 OH. Tukang Batu - #REF!

29 Err:509 Err:509 M3
4.3600 Zak. Semen Pc (50 Kg) Err:509 86,000.00
0.5200 M3. Pasir Beton Err:509 450,000.00
0.8700 M3. Kerikil Cor Err:509 450,000.00
1.6500 OH. Pekerja Err:509 #REF!
0.2500 OH. Tukang Batu Err:509 #REF!

30 Pek. Pasang Kusen Kayu besi 5/10 - M3


1.1000 M3. Balok Kayu Besi 5/10 - 4,000,000.00
1.2500 Kg. Paku 10 cm - 25,000.00
1.0000 Kg. Lem Kayu - 65,000.00
7.0000 OH. Pekerja - #REF!
21.0000 OH. Tukang Kayu - #REF!

31 Pek. Pasang Pintu Panel - M3


0.0400 M3. Papan Kayu Kelas I - 4,000,000.00
0.5000 Kg. Lem Kayu - 65,000.00
1.0000 OH. Pekerja - #REF!
3.0000 OH. Tukang Kayu - #REF!

32 Pek. Ventilasi Kayu Besi - M3


1.1000 M3. Balok Kayu Besi 5/10 - 4,000,000.00
1.2500 Kg. Paku 10 cm - 25,000.00
1.0000 Kg. Lem Kayu - 65,000.00
7.0000 OH. Pekerja - #REF!
21.0000 OH. Tukang Kayu - #REF!

33 Pek. Kuda-kuda Balok Kayu besi 5/10 -


1.1000 M3. Balok Kayu Besi 5/10 - 4,000,000.00
0.5600 Kg. Paku 12 cm - 25,000.00
4.0000 OH. Pekerja - 150,000.00
12.0000 OH. Tukang Kayu - 225,000.00

34 Pek. Gording Balok Kayu 5/10 - M3


1.1000 M3. Balok Kayu Besi 5/10 - 4,000,000.00
3.0000 Kg. Paku 12 cm - 25,000.00
2.4000 OH. Pekerja - 150,000.00
7.2000 OH. Tukang Kayu - 225,000.00

35 Pek. Skur Angin Balok Kayu 5/10 - M3


1.1000 M3. Balok Kayu Besi 5/10 - 4,000,000.00
3.0000 Kg. Paku 12 cm - 25,000.00
2.4000 OH. Pekerja - 150,000.00
7.2000 OH. Tukang Kayu - 225,000.00

36 Pek. Atap Seng Sokka Biru - Lembar


0.7000 Lbr. Seng Sokka Kotak Biru - 95,000.00
0.0200 Kg. Paku Seng / Atap + Karet - 36,500.00
0.1200 OH. Pekerja - 150,000.00
0.0600 OH. Tukang Kayu - 225,000.00

37 Pek. Nok Seng Sokka Biru - M2


1.0000 Lbr. Nok Sokka Biru - 65,000.00
0.0400 Kg. Paku Seng / Atap + Karet - 36,500.00
0.1500 OH. Pekerja - 150,000.00
0.0700 OH. Tukang Kayu - 225,000.00

38 Pek. Lisplank Papan Kayu Besi 2/20 - M1


0.0086 M3. Papan Kayu Besi 2/20 - 4,000,000.00
0.0600 Kg. Paku Campur - 25,000.00
0.1000 OH. Pekerja - 150,000.00
0.1000 OH. Tukang Kayu - 225,000.00

39 Pek. Plafond Tripleks 3mm + Rangka - M2


0.0120 M3. Kayu 5/5 (5x5) cm - 2,000,000.00
0.1000 Kg. Paku Campur - 25,000.00
0.1500 OH. Pekerja - 150,000.00
0.2500 OH. Tukang Kayu - 225,000.00
0.3750 Lbr. Tripleks 3.5 mm - 100,000.00
0.0300 Kg. Paku Tripleks - 36,250.00
0.1000 OH. Pekerja - 150,000.00
0.1000 OH. Tukang Kayu - 225,000.00

40 Pek. List Plafond Luar & Dalam - M1


1.0500 M' List Kayu Profil - 36,000.00
0.0100 Kg. Paku Campur - 25,000.00
0.0500 OH. Pekerja - 150,000.00
0.0500 OH. Tukang - 225,000.00

41 Pek. Pasang Kunci tanam 2 Slaag (KM/WC) - BH


1.0000 Psg. Kunci Tanam Kamar Mandi - 185,000.00
0.0040 OH. Pekerja - 150,000.00
0.5000 OH. Tukang Kayu - 225,000.00

42 Pek. Pasang Engsel pintu - PSG


1.0000 Psg. Engsel Kuningan (Standard) - 45,000.00
0.0120 OH. Pekerja - 150,000.00
0.1500 OH. Tukang Kayu - 225,000.00

43 Pek. Pipa PVC Dia.1/2" - M1


1.2000 M'. Pipa PVC Dia. 1/2" - 7,750.00
1.0000 Ls. Perlengkapan (35% Harga Pipa) - 2,712.50
0.0288 OH. Pekerja - 150,000.00
0.0600 OH. Tukang Pipa - 225,000.00

44 Pek. Pipa PVC Dia.3" - M1


1.2000 M'. Pipa PVC Dia. 3" - 87,500.00
1.0000 Ls. Perlengkapan (35% Harga Pipa) - 30,625.00
0.0648 OH. Pekerja - 150,000.00
0.1350 OH. Tukang Pipa - 225,000.00

45 Pas. Klosed Jongkok - BH


1.0000 Bh. Klosed Jongkok - 650,000.00
0.1200 Zak. Semen Pc (50 Kg) - 86,000.00
0.0100 M3. Pasir Beton - 450,000.00
0.8000 OH. Pekerja - 150,000.00
1.5000 OH. Tukang - 225,000.00

46 Pas. Floor Drain - BH


1.0000 Bh. Floor Drain - 43,750.00
0.0080 OH. Pekerja - 150,000.00
0.1000 OH. Tukang - 225,000.00

47 Pas. Kran Air - BH


1.0000 Bh. Kran Air 1/2" - 31,000.00
0.0250 Bh. Isolasi Pipa - 50,000.00
0.0080 OH. Pekerja - 150,000.00
0.1000 OH. Tukang - 225,000.00

48 Pek. Pengadaan Bak Viber - BH


1.0000 Bak Viber - 600,000.00

49 Pek. Pengadaan Sumur Dangkal - BH


1.0000 Pengadaan Sumur - 4,000,000.00
50 Cor Lantai Kerja Bawah IPAL Err:509 M3
4.3600 Zak. Semen Pc (50 Kg) Err:509 86,000.00
0.5200 M3. Pasir Beton Err:509 450,000.00
0.8700 M3. Kerikil Cor Err:509 450,000.00
1.6500 OH. Pekerja Err:509 150,000.00
0.2500 OH. Tukang Batu Err:509 225,000.00

51 Pengadaan Mesin Air - BH


6.0000 Mesin Pompa Air - 800,000.00

52 Pasang Lampu SL 8 watt + Fitting - BH


1.0000 Set. Lampu SL 8 Watt + Pitting Biasa - 32,000.00
2.0000 M'. Kabel NYM 2 x 2,5 mm - 29,900.00
0.4000 OH. Pekerja - 150,000.00
0.2000 OH. Tukang - 225,000.00

53 Pasang Saklar Ganda 3 - BH


1.0000 Bh. Saklar Ganda - 36,500.00
2.0000 M'. Kabel NYM 2 x 2,5 mm - 29,900.00
0.4000 OH. Pekerja - 150,000.00
0.5000 OH. Tukang listrik - 225,000.00

54 Stop Kontak - M2
1.0000 Bh. Stop Kontak - 36,500.00
2.0000 M'. Kabel NYM 2 x 2,5 mm - 29,900.00
0.3967 OH. Pekerja - 150,000.00
0.5000 OH. Tukang listrik - 225,000.00

55 Pek. Cat Kilat Kayu - M2


0.2000 Kg. Cat Meni - 41,667.00
0.1500 Kg. Plamur / Dempul - 64,000.00
0.1700 Kg. Minyak Cat (Thiner) - 54,719.00
0.2600 Kg. Cat Kilat Kayu - 81,250.00
0.0560 OH. Pekerja - 150,000.00
0.0090 OH. Tukang Cat - 225,000.00

56 Pek. Cat Tembok - BH


0.1000 Kg. Plamur / Dempul - 64,000.00
0.1000 Kg. Cat Dasar - 23,125.00
0.2600 Kg. Cat Penutup 2x - 23,125.00
0.0160 OH. Pekerja - 150,000.00
0.0630 OH. Tukang Cat - 225,000.00

57 Pek. Cat Plafond - BH


0.1200 Kg. Cat Dasar - 23,125.00
0.1800 Kg. Cat Penutup - 86,000.00
0.0224 OH. Pekerja - 150,000.00
0.0420 OH. Tukang Cat - 225,000.00

58 Pekerjaan Akhir - LS
1.0000 Pekerjaan Akhir - 0.00

59 Pengadaan Tandon Air Dan Dudukan - BH


1.0000 Pengadaan Tandon Air Dan Dudukan - 3,000,000.00

60 Pengadaan Tangki Ipal 5.00 BH


1.0000 Pengadaan Tangki Ipal 5.00 7,500,000.00

61 Pek. Pasangan Batu Tela 1 : 2 - M2


20.0000 Bh. Batu Tela - 3,000.00
0.2300 Zak. Semen Pc. (50 Kg) - 100,000.00
0.0430 M3. Pasir Pasang - 450,000.00
0.3000 OH. Pekerja - 150,000.00
0.1000 OH. Tukang Batu - 225,000.00
62 Cor Lantai K 175 ( T = 12 cm) - M3
4.3600 Zak. Semen Pc (50 Kg) - 100,000.00
0.5200 M3. Pasir Beton - 450,000.00
0.8700 M3. Kerikil Cor - 450,000.00
1.6500 OH. Pekerja - 150,000.00
0.2500 OH. Tukang Batu - 225,000.00

15 jt
#REF!
JUMLAH HARGA (Rp.)

1,500,001.20
1,500,001.20

100,000.00
100,000.00

600,000.00
600,000.00

600,000.00
600,000.00

-
-
-
-

400,000.00
400,000.00

200,000.00
200,000.00

-
-

Err:509
Err:509

24,000,000.00
24,000,000.00

1,500,000.00
1,500,000.00
Err:509 Err:509

885,937.50
41,343.75
927,281.25 927,281.25

-
-
- 0.00

-
-
- 0.00

-
-
-
- 0.00

-
-
-
- 0.00

-
-
-
- 0.00

7,560,000.00
1,530,900.00
921,375.00
691,031.25
10,703,306.25 10,703,306.25

13,322,700.97
39,232,493.66
9,562,920.33
9,195,115.70
6,896,336.78
78,209,567.45 78,209,567.45

-
-
-
-
-
- 0.00

-
-
-
-
- 0.00

-
-
-
- 0.00

-
-
-
-
-
-
- 0.00

-
-
-
-
-
-
- 0.00
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF! #REF!

#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF! #REF!

#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF! #REF!

-
-
-
#REF!
#REF!
#REF! #REF!

Err:509
Err:509
Err:509
Err:509
Err:509
Err:509 Err:509

-
-
-
#REF!
#REF!
#REF! #REF!

-
-
#REF!
#REF!
#REF! #REF!

-
-
-
#REF!
#REF!
#REF! #REF!

-
-
-
-
- 0.00

-
-
-
-
- 0.00

-
-
-
-
- 0.00

-
-
-
-
- 0.00

-
-
-
-
- 0.00

-
-
-
-
- 0.00

-
-
-
-
-
-
-
-
- 0.00

-
-
-
-
- 0.00

-
-
-
- 0.00

-
-
-
- 0.00

-
-
-
-
- 0.00

-
-
-
-
- 0.00

-
-
-
-
-
- 0.00

-
-
-
- 0.00

-
-
-
-
- 0.00

-
- 0.00

-
- 0.00
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509 Err:509

-
- 0.00

-
-
-
-
- 0.00

-
-
-
-
- 0.00

-
-
-
-
- 0.00

-
-
-
-
-
-
- 0.00

-
-
-
-
-
- 0.00

-
-
-
-
- 0.00

-
- 0.00

-
- 0.00

37,500,000.00
37,500,000.00 37,500,000.00

-
-
-
-
-
- 0.00
-
-
-
-
-
- 0.00
Err:509
Err:509
156,249,999.90
Err:509
DAFTAR HARGA BAHAN, UPAH & PERALATAN
: PEMBANGUNAN TANGKI SEPTIK SKALA KOMUNAL (5 - 10 KK)
KEGIATAN SWAKELOLA
PEKERJAAN : PEMBANGUNAN TANGKI SEPTIK SKALA KOMUNAL (5 - 10 KK)
LOKASI
T. ANGGARAN

I. DAFTAR BAHAN/MATERIAL

No. URAIAN SATUAN HARGA


(Rp)
A. MATERIAL TANAH, BATU DAN PASIR
1 Batu Karang M3 800,000
2 Batu tela pres Bh 3,000
3 Pasir pasang M3 450,000
4 Pasir pasang Kg 850
5 Kerikil tersaring M3 450,000
6 Batu pecah 2/3 M3 800,000
7 Batu pecah 2/3 Kg 765
8 Pasir urug M3 450,000
9 Karang timbun/sirtu/urugan Pilihan M3 300,000
10 Tanah timbunan biasa M3 159,250
11 Tanah hitam/humus M3 300,000
12 Batu kerawang Bh 44,000
13 Paving blok Bh 10,000

B. BAHAN KAYU
1 Balok/papan Bekesting M3 2,000,000
2 Balok/papan Kayu Matoa M3 2,000,000
3 Balok Kayu Besi M3 4,000,000
4 Papan Kayu Besi M3 4,000,000
5 Dolken Kayu steger/buah dia 8-10 cm, panjang 4m Btg 60,000
6 Kayu list kaca Btg 28,000
7 List plafond kayu matoa diprofil Btg 36,000

C. KELOMPOK BAHAN TOKO


1 Semen Portland (PC) 50 Kg Zak 100,000
2 Semen Portland (PC) Kg 2,000
3 Semen warna Kg 34,000
4 Besi Beton polos Kg 19,000
5 Besi Beton ulir Kg 26,240
6 Kawat Ikat Kg 20,000
7 Tripleks tebal 3 mm Lmbr 70,000
8 Lem kayu Kg 65,000
9 Paku campuran Kg 27,000
10 Paku seng Kg 36,500
11 Paku tripleks Kg 36,250
12 Karet paku Bh 50
13 Keramik 20 x 20 cm M2 100,000
14 Keramik 20 x 25 cm M2 100,000
15 Kunci tanam 2 slaag Yalle / sejenisnya Bh 190,000
16 Engsel pintu ring nilon kuningan 4" Psg 50,000
17 Grendel kuningan Psg 36,000
18 Plamur tembok Kg 64,000
19 Dempul kayu Kg 56,250
20 Amplas kayu Lmbr 20,000
21 Amplas besi Lmbr 20,000
22 Cat tembok Kg 30,000
23 Cat Meni Kayu Kg 41,667
24 Cat kilap kayu Kg 81,250
25 Cat kilap besi Kg 81,250
26 Minyak cat Liter 54,719
27 Vernis/Politur Liter 81,250
28 Residu/teer Liter 13,653
29 Minyak pelumas Liter 28,000
30 Atap Seng Biru Lmbr 95,000
31 Nok Seng Sokka M 40,000
32 Besi Beton Polos Kg 19,000
33 Besi Beton Ulir Kg 19,750
34 Lem pipa PVC Klg 50,000
35 Pipa PVC dia 1/2" (AW) M 10,000
36 Pipa PVC dia 3/4" (AW) Btg 28,332
37 Pipa PVC dia 1" (AW) Btg 37,500
38 Pipa PVC dia 1,5" (AW) Btg 62,500
39 Pipa PVC dia 2" (AW) Btg 110,000

40 Pipa PVC dia 3" (Tipis) Btg 120,000


41 Pipa PVC dia 3" (AW) M 53,750
42 Pipa PVC dia 4" (AW) Btg 350,000
43 Pipa Limbah PVC dia 4" (AW) Btg 490,000
44 Assesoris pipa PVC (shok, elbow, tee dll) 2" Bh 15,000
45 Assesoris pipa PVC (shok, elbow, tee dll) 4" Bh 45,000
46 Assesoris pipa PVC (shok, elbow, tee dll) 6" Bh 75,000
47 Kloset jongkok setara KIA Standar + Assesoris Set 500,000
48 Floor drain stainless Bh 43,750
49 Kran air kepala putih Bh 57,000
50 Bio Tank Viber Uk. 5 - 10 KK Unit 45,000,000
51 Lampu SL Philips 8 watt + fiting ulir Set 50,000
52 Lampu Tanam (Down laight) Philips SL 18 watt Set 385,000
53 Lampu Hologen 500 Watt Set 250,000
54 Kabel Listrik NYM 3 x 2,5 mm M¹ 19,000
55 Stop Kontak Bh 36,000
56 Saklar Tunggal Bh 36,500
57 Saklar Ganda Bh 36,500
58 Sekring Khass 2 Group + ACC Bh 64,000
59 Pipa kabel PVC ½" - 4 mm Btg 27,000
60 Fitting Lampu Bh 9,000
61 Kipas Exhaust Ceiling Bh 975,000
62 Baut Bh 350
63 Box Panel MCB Unit 750,000
64 Box Panel uk. 80 x 60 x 40 cm Unit 7,112,300
65 Kabel NYY 4 x 70 mm² M' 729,750
66 Kabel NYY 4 x 35 mm² M' 143,000
1 Pekerja Tak Terlatih H/O 150,000
2 Pekerja Terlatih H/O 180,000
3 Tukang H/O 225,000
4 Kepala Tukang H/O 250,000
5 Mandor H/O 260,000

III. DAFTAR PERALATAN

No. URAIAN SATUAN HARGA


(Rp)

1 Bulldozer Unit/Jam 638,129


2 Motor grader Unit/Jam 511,384
3 Vibrator Roller Unit/Jam 402,286
4 Compactor 0,5~1,0 ton Unit/Jam 98,236
5 D.Truck Unit/Jam 277,485
6 Loader Unit/Jam 314,031
7 Excavator Unit/Jam 543,376
8 Truck Tangki air 3000-4500L Unit/Jam 276,527
9 Water pump Unit/Jam 96,911
10 Mixer Concrete (molen) 0,3-0,6 M3 Unit/Jam 104,652
11 Conrete Vibrator Unit/Jam 93,668
12 Generator Set 5 KVA Unit/Jam 341,799
13 Mesin Las listrik Unit/Jam 140,896
14 Hammer Kobelco K-35 Unit/Jam 289,269
15 Track crane Unit/Jam 467,627
16 Crane 10-15 Ton Unit/Jam 489,372
17 Trailler Unit/Jam 418,649
18 Forklift Unit/Jam 348,205
19 Theodolite Unit/Jam 31,250
20 Waterpass Unit/Jam 18,750
21 Alat Bantu Set 50,000