Jumlah Harga
No Uraian Pekerjaan
(Rp)
I. PEKERJAAN KONSTRUKSI
B. PEKERJAAN LANTAI I
I. PEKERJAAN GALIAN TANAH DAN URUGAN 16,122,415.00
II. PEKERJAAN PONDASI DAN BETON 483,618,512.13
III. PEKERJAAN DINDING DAN PLESTERAN 428,997,122.00
IV. PEKERJAAN PINTU DAN JENDELA 195,637,573.90
V. PEKERJAAN PINTU LAPIS Pb 52,762,500.00
VI. PEKERJAAN PLAFOND 46,099,200.00
VII. PEKERJAAN TIMBAL 152,704,437.50
VIII. PEKERJAAN PELAPIS LANTAI DAN DINDING 106,380,130.00
IX. PEKERJAAN ELEKTRIK 51,667,140.00
X. PEKERJAAN PENGECATAN 85,105,048.00
XI. PEKERJAAN SANITAIR 41,218,400.00
C. PEKERJAAN LANTAI II
I. PEKERJAAN PONDASI DAN BETON 79,036,228.12
II. PEKERJAAN DINDING DAN PLESTERAN 73,136,198.00
III. PEKERJAAN PINTU DAN JENDELA 51,612,128.08
IV. PEKERJAAN ATAP 69,167,644.00
V. PEKERJAAN PLAFOND 32,566,400.00
VI. PEKERJAAN PELAPIS LANTAI DAN DINDING 38,079,530.00
VII. PEKERJAAN ELEKTRIKAL 9,197,750.00
VIII. PEKERJAAN PENGECATAN 15,596,856.00
IX. PEKERJAAN SANITAIR 19,867,100.00
X. PEKERJAAN LAIN-LAIN 16,567,053.91
JU M LAH I 2,257,130,868.60
JU M LAH 2,272,727,868.60
P P N 10 % 227,272,786.86
JU M LAH T O T AL 2,500,000,655.46
D IB U LAT K AN 2,500,000,000.00
HARGA JUMLAH
NO. URAIAN PEKERJAAN VOLUME SATUAN HARGA
(Rp) (Rp)
I. PEKERJAAN KONSTRUKSI
A. PEKERJAAN PERSIAPAN
1 Pasang papan nama proyek 1.00 bh 350,000.00 350,000.00
2 Pek. Bongkaran 1.00 ls 10,000,000.00 10,000,000.00
3 Pek. Pengukuran kembali dan pas. bouwplank 55 2/3 m1 69,800.00 3,885,533.33
4 Pembuatan los kerja/gudang semen dan peralatan (3 X 3 M) 9.00 m2 959,900.00 8,639,100.00
5 Pengadaan air dan listrik kerja 1.00 ls 1,000,000.00 1,000,000.00
6 Biaya pelaporan dan dokumentasi 1.00 ls 3,000,000.00 3,000,000.00
7 Biaya As built drawing 1.00 ls 1,500,000.00 1,500,000.00
JU M LAH I 28,374,633.33
B. PEKERJAAN LANTAI I
C. PEKERJAAN LANTAI II