REKAPITULASI RENCANA ANGGARAN BIAYA

PEMBANGUNAN GEDUNG KANTOR RAJAMANDALA ELECTRIC POWER


TAHUN ANGGARAN 2018

NO JENIS PEKERJAAN HARGA JUMLAH

I PEKERJAAN PERSIAPAN 42,598,629.71

II PEKERJAAN PEMATANGAN LAHAN AREA GEDUNG 53,067,950.78

III PEKERJAAN STRUKTUR


III.A PEKERJAAN SUB STRUKTUR 330,408,184.99
III.B PEKERJAAN UP STRUKTUR 364,853,373.14
III.C PEKERJAAN STRUKTUR ATAP 183,468,889.03
SUB JUMLAH. III 878,730,447.16

IV PEKERJAAN ARSITEKTUR
IV.A PEKERJAAN DINDING, PLESTERAN DAN ACIAN 265,733,140.98
IV.B PEKERJAAN LANTAI 285,012,922.91
IV.C PEKERJAAN KUSEN PINTU DAN JENDELA 496,550,955.13
IV.D PEKERJAAN PLAFOND 180,366,698.36
IV.E PEKERJAAN PENUTUP ATAP 282,546,500.44
IV.F PEKERJAAN PENGECATAN DAN FINISHING 112,414,757.43
IV.G PEKERJAAN LAIN-LAIN 49,310,982.54
SUB JUMLAH. IV 1,671,935,957.79

V PEKERJAAN MEKANIKAL
V.A PEKERJAAN SANITAIR 50,993,643.40
V.B SISTEM PENYEDIAN AIR BERSIH 86,659,246.68
V.C PENGADAAN SISTEM AIR KOTOR 26,400,000.00
V.D SISTEM PLUMBING PIPA AIR BERSIH DAN PIPA AIR KOTOR 26,943,290.51
SUB JUMLAH. V 190,996,180.59

VI PEKERJAAN ELEKTRIKAL
VI.A PEKERJAAN DAYA PLN 33,000,000.00
VI.B KABEL DAYA PERANGKAT UTAMA 6,606,000.00
VI.C SISTEM DAYA BANGUNAN 22,500,000.00
VI.D SISTEM PENERANGAN BANGUNAN 116,171,695.45
VI.E SISTEM INSTALASI TELEPON 37,048,500.00
VI.F SISTEM INSTALASI DATA 6,727,850.00
VI.G SISTEM TATA UDARA 97,650,064.00
VI.H SISTEM PROTEKSI KEBAKARAN 4,743,125.00
VI.I SISTEM PENANGKAL PETIR 34,329,570.00
SUB JUMLAH. VI 358,776,804.45

VII PEKERJAAN SITE DEVELOPMENT 541,068,851.30

TOTAL 3,737,174,821.78
DIBULATKAN 3,737,174,000.00

Terbilang :
Tiga Milyar Tujuh Ratus Tiga Puluh Tujuh Juta Seratus Tujuh Puluh Empat Ribu Rupiah

Bandung, Juni 2018


KONSULTAN PERENCANA
PT. KREASI DANURAYA CONSULTANT
……………………………
Direktur
RENCANA ANGGARAN BIAYA
PEMBANGUNAN GEDUNG KANTOR RAJAMANDALA ELECTRIC POWER
TAHUN ANGGARAN 2018

NO URAIAN PEKERJAAN VOL SAT HARGA SATUAN JUMLAH HARGA

I PEKERJAAN PERSIAPAN
1 Pengukuran dan Bouwplank 108.00 m1 65,957.83 7,123,445.21
2 Pembersihan Site 720.00 m2 19,360.00 13,939,200.00
3 Papan Nama Proyek 1.00 bh 1,035,984.51 1,035,984.51
4 Air dan Listrik Kerja 1.00 ls 3,000,000.00 3,000,000.00
5 Mobilisasi dan demobilisasi 1.00 ls 5,000,000.00 5,000,000.00
6 Administrasi dan Pelaporan 1.00 ls 3,000,000.00 3,000,000.00
7 Alat Pelindung Diri (APD) 1.00 ls 2,000,000.00 2,000,000.00
8 Direksikeet & Tempat penyimpanan sementara 1.00 ls 7,500,000.00 7,500,000.00
JUMLAH PEKERJAAN I 42,598,629.71

II PEKERJAAN PEMATANGAN LAHAN AREA


1 Urugan tanah peninggian lantai gedung 218.20 m3 182,710.00 39,866,968.00
2 Pemadatan tanah urugan 218.20 m3 60,500.00 13,200,982.78
JUMLAH PEKERJAAN II 53,067,950.78

III PEKERJAAN STRUKTUR


III.A PEKERJAAN SUB STRUKTUR
1 Pondasi Plat Setempat Type P1 120X120X40 cm
a. Pek. Galian tanah 69.12 m3 81,675.00 5,645,376.00
b. Pasir urug 1.73 m3 172,062.00 297,323.14
c. Lantai kerja 1.73 m3 1,015,797.42 1,755,297.94
d. Cor Beton k-300 13.82 m3 1,586,915.00 21,937,512.96
e. Pembesian D13-150 1,066.89 kg 20,838.23 22,232,100.02
f. Bekisting 46.08 m2 161,672.94 7,449,889.08
2 Pondasi Plat Setempat Type P2 100X100X35 cm
a. Pek. Galian tanah 6.00 m3 81,675.00 490,050.00
b. Pasir urug 0.15 m3 172,062.00 25,809.30
c. Lantai kerja 0.15 m3 1,015,797.42 152,369.61
d. Cor Beton k-300 1.05 m3 1,586,915.00 1,666,260.75
e. Pembesian D13-150 93.56 kg 20,838.23 1,949,650.96
f. Bekisting 4.20 m2 161,672.94 679,026.35
3 Pondasi Plat Setempat Type P3 80X80X35 cm
a. Pek. Galian tanah 5.76 m3 81,675.00 470,448.00
b. Pasir urug 0.19 m3 172,062.00 33,035.90
c. Lantai kerja 0.19 m3 1,015,797.42 195,033.10
d. Cor Beton k-300 1.34 m3 1,586,915.00 2,132,813.76
e. Pembesian D13-150, 1D13 132.81 kg 20,838.23 2,767,501.80
f. Bekisting 6.72 m2 161,672.94 1,086,442.16
4 Pas. Pondasi Lajur dan Setempat Batu Belah
a. Pek. Galian tanah 160.21 m3 81,675.00 13,084,988.40
b. Pasir urug 8.01 m3 172,062.00 1,378,285.44
c. Pasangan aanstamping 24.03 m3 426,289.05 10,244,237.42
d. Pasangan batu kali 51.07 m3 835,051.25 42,642,977.65
5 Pas. Pondasi Rollagh Bata
a. Pek. Galian tanah 27.58 m3 81,675.00 2,252,821.11
b. Pasir urug 1.84 m3 172,062.00 316,396.21
c. Lantai kerja 1.84 m3 1,015,797.42 1,867,899.09
d. Pasangan Rollagh Bata 91.94 m3 277,549.80 25,518,622.49
6 Sloof Beton SL-1 20/30 cm
a. Pek. Galian tanah 9.68 m3 81,675.00 790,940.70
b. Pasir urug 1.61 m3 172,062.00 277,708.07
c. Lantai kerja 1.61 m3 1,015,797.42 1,639,497.04
d. Cor Beton k-300 9.68 m3 1,586,915.00 15,367,684.86
e. Pembesian 6 D13, Ø8-150-200 2,284.59 kg 20,838.23 47,606,827.42
f. Bekisting 161.40 m2 161,672.94 26,094,012.52
7 Sloof Beton SL-2 15/20 cm
a. Cor beton k-300 4.79 m3 1,586,915.00 7,606,718.36
b. Pembesian 4 Ø12, Ø8-150 840.57 kg 20,838.23 17,516,000.70
c. Bekisting 111.85 m2 161,672.94 18,082,471.65
NO URAIAN PEKERJAAN VOL SAT HARGA SATUAN JUMLAH HARGA

8 Kolom Pedestal 20/30 CM


a. Cor beton k-300 1.44 m3 1,586,915.00 2,285,157.60
b. Pembesian 6D16, Ø10-100-150 320.97 kg 20,838.23 6,688,540.45
c. Bekisting 24.00 m2 212,314.92 5,095,558.05
9 Kolom Pedestal Bulat Ø40 CM
a. Cor beton k-300 0.19 m3 1,586,915.00 298,974.79
b. Pembesian 8D16, Ø10-150 24.12 kg 20,838.23 502,565.50
c. Bekisting 1.88 m2 212,314.92 400,001.31
10 Kolom Pedestal Bulat Ø20 CM
a. Cor beton k-300 0.61 m3 1,586,915.00 971,668.05
b. Pembesian 4D16, Ø10-150 274.10 kg 20,838.23 5,711,672.33
c. Bekisting 24.49 m2 212,314.92 5,200,016.99
JUMLAH SUB. III.A 330,408,184.99
III.B PEKERJAAN UP STRUKTUR
LANTAI - 1
1 Kolom Type K1 20/30 cm
a. Cor Beton k-300 2.88 m3 1,586,915.00 4,570,315.20
b. Pembesian 6Ø12, Ø10-100-150 641.95 m3 20,838.23 13,377,080.89
c. Bekisting 48.00 m2 212,314.92 10,191,116.10
2 Kolom Bulat Type K2 Ø40 CM
a. Cor beton k-300 0.38 m3 1,586,915.00 597,949.57
b. Pembesian 8D16, Ø10-150 48.23 kg 20,838.23 1,005,131.00
c. Bekisting 3.77 m2 212,314.92 800,002.61
3 Kolom Bulat K3 Ø20 CM
a. Cor beton k-300 0.75 m3 1,586,915.00 1,195,899.14
b. Pembesian 4D16, Ø10-100-150 337.35 kg 20,838.23 7,029,750.56
c. Bekisting 30.14 m2 212,314.92 6,400,020.91
4 Kolom Bulat K3.A Ø20 CM
a. Cor beton k-300 0.47 m3 1,586,915.00 747,436.97
b. Pembesian 4Ø12, Ø8-100-150 102.82 kg 20,838.23 2,142,635.08
c. Bekisting 18.84 m2 212,314.92 4,000,013.07
5 Kolom Praktis Type KP 15/15 cm
a. Cor beton k-175 2.63 m3 1,061,894.91 2,795,438.35
b. Pembesian 4Ø10, Ø8-150 415.47 kg 20,838.23 8,657,692.80
c. Bekisting 35.10 m2 212,314.92 7,452,253.65
6 Balok Type B1 20/35 CM
a. Cor beton k-300 8.08 m3 1,586,915.00 12,830,207.77
b. Pembesian 8D13, Ø10-100-150 1,765.90 kg 20,838.23 36,798,277.61
c. Bekisting 103.95 m2 217,033.92 22,560,675.85
7 Balok Type B2 15/30 CM
a. Cor beton k-300 0.90 m3 1,586,915.00 1,424,652.94
b. Pembesian 6D13, Ø10-100-150 208.35 kg 20,838.23 4,341,603.24
c. Bekisting 14.96 m2 217,033.92 3,247,370.01
8 Balok Type B2.A 15/30 CM
a. Cor beton k-300 1.35 m3 1,586,915.00 2,142,335.25
b. Pembesian 6D13, Ø10-100-150, Ø8-150 351.77 kg 20,838.23 7,330,364.89
c. Bekisting 31.50 m2 217,033.92 6,836,568.44
9 RingBalk Type RB-1 15/25 CM
a. Cor beton k-300 0.90 m3 1,586,915.00 1,428,223.50
b. Pembesian 6Ø12, Ø8-150-200 168.42 kg 20,838.23 3,509,589.75
c. Bekisting 15.60 m2 217,033.92 3,385,729.13
10 Ringbalk Type RB-2 15/20 CM
a. Cor beton k-300 4.82 m3 1,586,915.00 7,646,946.66
b. Pembesian 4Ø12, Ø8-150-200 845.02 kg 20,838.23 17,608,634.45
c. Bekisting 88.34 m2 217,033.92 19,173,590.26
11 Plat Lantai tebal 12 cm
a. Cor beton k-300 13.73 m3 1,586,915.00 21,785,169.12
b. Pembesian 4Ø12, Ø8-150-200 1,083.30 kg 20,838.23 22,574,132.33
c. Bekisting 114.40 m2 269,336.17 30,812,057.71
LANTAI - 2
1 Kolom Type K1.A
a. Cor Beton k-300 2.70 m3 1,586,915.00 4,284,670.50
b. Pembesian 4Ø6, Ø6-200 416.25 kg 20,838.23 8,673,879.72
c. Bekisting 45.00 m2 212,314.92 9,554,171.34
2 Kolom Praktis Type KP 15/15 cm
a. Cor beton k-175 0.95 m3 1,061,894.91 1,003,490.69
b. Pembesian 4Ø12, Ø8-150 149.14 kg 20,838.23 3,107,889.72
NO URAIAN PEKERJAAN VOL SAT HARGA SATUAN JUMLAH HARGA

c. Bekisting 12.60 m2 212,314.92 2,675,167.98


NO URAIAN PEKERJAAN VOL SAT HARGA SATUAN JUMLAH HARGA

3 RingBalk Type RB-1 15/25 CM


a. Cor beton k-300 3.00 m3 1,586,915.00 4,754,794.07
b. Pembesian 6Ø12, Ø8-150-200 560.70 kg 20,838.23 11,684,009.22
c. Bekisting 51.94 m2 217,033.92 11,271,656.57
4 Balok Type B3 15/25 CM
a. Cor beton k-300 0.79 m3 1,586,915.00 1,249,695.56
b. Pembesian 4D3 + 2Ø12, Ø8-150-200 174.52 kg 20,838.23 3,636,662.63
c. Bekisting 13.65 m2 217,033.92 2,962,512.99
5 Plat Dak tebal 10 cm
a. Cor beton K-300 0.60 m2 1,586,915.00 952,149.00
b. Pembesian Ø8-300 49.32 kg 20,838.23 1,027,741.31
c. Bekisting 6.00 m3 269,336.17 1,616,017.01
JUMLAH SUB. III. B 364,853,373.14
III.C PEKERJAAN STRUKTUR ATAP
LANTAI - 1
1 Pek. Rangka Kuda-kuda Baja Ringan 415.54 m2 238,610.76 99,151,719.72
LANTAI - 2
1 Pek. Rangka Kuda-kuda Baja Ringan 353.37 m2 238,610.76 84,317,169.31
JUMLAH SUB. III. C 183,468,889.03
JUMLAH PEKERJAAN III 878,730,447.16

IV PEKERJAAN ARSITEKTUR
IV.A PEKERJAAN DINDING, PLESTERAN DAN ACIAN
LANTAI 1
1 Pas. Dinding bata merah 1/2 bata 368.01 m2 135,280.42 49,783,992.71
2 Pas. Dinding ekspos bata merah 1/2 bata 92.27 m2 180,655.42 16,669,599.50
3 Pek. Plesteran 581.06 m2 64,923.76 37,724,327.31
4 Pek. Acian 581.06 m2 41,503.00 24,115,558.87
5 Pek. Dinding Ornamen GRC Cetak 3.88 m2 1,250,000.00 4,843,750.00
6 Pas. Keramik Dinding 30x60 (toilet) 154.96 m2 341,220.48 52,874,161.32
LANTAI 2
1 Pas. Dinding bata merah 1/2 bata 199.67 m2 135,280.42 27,010,765.06
2 Pas. Dinding ekspos bata merah 1/2 bata 9.00 m2 180,655.42 1,625,898.78
3 Pek. Plesteran 399.33 m2 64,923.76 25,926,005.08
4 Pek. Acian 399.33 m2 41,503.00 16,573,392.99
5 Pek. Pasangan Dinding Rooster 16.80 m2 511,052.94 8,585,689.36
JUMLAH SUB. IV. A 265,733,140.98
IV.B PEKERJAAN LANTAI
LANTAI 1
1 Pas. Pasir urug bawah lantai t=5 cm 22.97 m3 172,062.00 3,952,183.27
2 Pas. Lantai Kerja t=5 cm 22.97 m3 1,015,797.42 23,332,389.31
3 Pas. Lantai granite tile 60x60 cm polished 289.71 m2 443,595.95 128,512,851.56
4 Pas. Lantai granite tile 60x60 cm unpolished 77.71 m2 461,241.78 35,841,438.43
5 Pas. Lantai parquet laminated 10x40 cm 49.66 m2 497,436.01 24,703,965.56
6 Pas. Lantai Keramik 30x30 tekstur anti slip (toilet) 42.31 m2 275,470.05 11,656,405.06
7 Pek. Plint Lantai Granite tile 10x60 cm 137.30 m' 58,839.61 8,078,678.61
LANTAI 2
1 Pas. Pasir urug bawah lantai t=5 cm 5.08 m3 172,062.00 874,818.27
2 Pas. Lantai Granite tile 60x60 cm polished 101.69 m2 443,595.95 45,107,675.10
3 Pek. Plint Lantai Granite tile 10x60 cm 40.07 m' 58,839.61 2,357,703.22
4 Pek. Waterproofing coating (atap dak) 6.00 m2 99,135.75 594,814.52
JUMLAH SUB.IV. B 285,012,922.91
IV.C PEKERJAAN KUSEN PINTU DAN JENDELA
LANTAI 1
1 Kusen Pintu Type P1 2.00 unit 7,053,281.74 14,106,563.48
2 Kusen Pintu Type P2 4.00 unit 4,258,494.93 17,033,979.73
3 Kusen Pintu Type P3 1.00 unit 3,893,694.11 3,893,694.11
4 Kusen Pintu Type P4 9.00 unit 3,652,493.57 32,872,442.16
5 Kusen Pintu Type PL1 4.00 unit 15,082,200.00 60,328,800.00
6 Kusen Pintu Type PL2 4.00 unit 21,697,200.00 86,788,800.00
7 Kusen Pintu Type PL3 1.00 unit 29,899,800.00 29,899,800.00
8 Kusen Jendela Type J1 2.00 unit 7,857,408.96 15,714,817.92
9 Kusen Jendela Type J2 2.00 unit 9,281,983.89 18,563,967.77
10 Kusen Jendela Type J3 3.00 unit 10,225,233.39 30,675,700.17
11 Kusen Jendela Type J4 3.00 unit 8,774,080.31 26,322,240.92
12 Kusen Jendela Type J5 1.00 unit 8,701,522.65 8,701,522.65
13 Kusen Jendela Type J6 1.00 unit 2,023,352.51 2,023,352.51
NO URAIAN PEKERJAAN VOL SAT HARGA SATUAN JUMLAH HARGA

14 Kusen Jendela Type J7 1.00 unit 9,869,703.08 9,869,703.08


15 Kusen Jendela Type BV1 9.00 unit 662,342.36 5,961,081.27
16 Pasang Partisi Cubical toilet termasuk pintu 1.00 unit 7,260,000.00 7,260,000.00
17 Pasang Partisi R. Shower Kaca Tempered 12 mm lapis ssticker sunblast 4.20 m2 3,774,775.80 15,854,058.36
LANTAI 2
1 Kusen Pintu Type P1 1.00 unit 4,258,494.93 4,258,494.93
2 Kusen Pintu Type PL2 2.00 unit 21,697,200.00 43,394,400.00
3 Kusen Jendela Type J4 4.00 unit 8,774,080.31 35,096,321.22
4 Kusen Jendela Type J8 1.00 unit 2,756,543.12 2,756,543.12
5 Kusen Jendela Type BV2 2.00 unit 4,262,083.75 8,524,167.49
6 Kusen Jendela Type BV3 3.00 unit 5,550,168.08 16,650,504.23
JUMLAH SUB. IV. C 496,550,955.13
IV.D PEKERJAAN PLAFOND
LANTAI 1
1 Plafond gypsum board 9 mm + rangka Hollow 256.48 m2 155,237.08 39,814,584.26
2 Plafond PVC 8 mm set. Shunda Plafond berikut rangka 208.19 m2 239,244.32 49,808,489.42
3 List profil gypsum 236.41 m1 34,535.82 8,164,499.24
4 List profil PVC 228.97 m1 44,981.75 10,299,493.79
LANTAI 2
1 Plafond gypsum board 9 mm + rangka Hollow 206.30 m2 155,237.08 32,025,579.51
2 Plafond PVC 8 mm set. Shunda Plafond berikut rangka 128.77 m2 239,244.32 30,808,280.05
3 List profil gypsum 98.79 m1 34,535.82 3,411,866.18
4 List profil PVC 134.14 m1 44,981.75 6,033,905.92
JUMLAH SUB. IV. D 180,366,698.36
IV.E PEKERJAAN PENUTUP ATAP
LANTAI - 1
1 Pek. Penutup Atap PVC ex.ALDERON 415.54 m2 282,580.92 117,422,969.75
2 Pek. Pasang wuwungan (Nok) 21.53 m' 196,669.16 4,234,287.12
3 Pek. Pasang Flashing Atap 21.60 m' 117,683.63 2,541,966.45
4 Pek. Listplank GRC t= 45cm 87.08 m' 71,285.94 6,207,694.43
5 Pek. Kanopi Kaca Laminated 10 mm Rangka Hollow 28.62 m2 1,472,467.82 42,138,200.46
LANTAI - 2
1 Pek. Penutup Atap PVC ex.ALDERON 353.37 m2 282,580.92 99,854,772.55
2 Pek. Pasang wuwungan (Nok) 21.53 m' 196,669.16 4,234,287.12
3 Pek. Listplank GRC t= 45cm 82.94 m' 71,285.94 5,912,322.56
JUMLAH SUB. IV. E 282,546,500.44
IV.F PEKERJAAN PENGECATAN DAN FINISHING
LANTAI 1
1 Pengecatan dinding Interior (ICI) 377.19 m2 60,590.15 22,854,241.58
2 Pengecatan dinding Exterior (Weathershield) 203.86 m2 70,374.21 14,346,609.29
3 Pengecatan plafond 464.67 m2 61,896.95 28,761,461.55
LANTAI 2
1 Pengecatan dinding Interior (ICI) 244.29 m2 60,590.15 14,801,690.13
2 Pengecatan dinding Exterior (Weathershield) 155.04 m2 70,374.21 10,910,673.18
3 Pengecatan plafond 335.07 m2 61,896.95 20,740,081.71
JUMLAH SUB. IV. F 112,414,757.43
IV.G PEKERJAAN LAIN-LAIN
1 Pek. Tangga #1
a. Pondasi Tangga 0.24 m3 3,038,960.59 738,467.42
b. Baja WF 150x150x7x10x11 148.05 Kg 25,404.03 3,761,066.44
c. Skur Plat Besi t=10mm 178.25 Kg 25,404.03 4,528,141.09
d. Lantai kayu solid 3/25 cm 0.17 m3 15,442,927.50 2,658,113.90
2 Pek. Tangga #2
a. Pondasi Tangga 0.18 m3 3,038,960.59 547,012.91
b. Baja WF 150x150 148.05 Kg 25,404.03 3,761,066.44
c. Skur Plat Besi t=10mm 178.25 Kg 25,404.03 4,528,141.09
d. Lantai kayu solid 3/25 cm 0.13 m3 15,442,927.50 1,968,973.26
3 Pek. Railling Besi Pipa Galvanis + Kaca polos 8mm 29.80 m' 900,000.00 26,820,000.00
JUMLAH SUB. IV. G 49,310,982.54
JUMLAH PEKERJAAN IV 1,671,935,957.79

V PEKERJAAN MEKANIKAL
V.A PEKERJAAN SANITAIR
LANTAI 1
1 Kloset Duduk ex. TOTO 5.00 bh 2,836,028.25 14,180,141.25
2 Kloset Jongkok ex. TOTO 1.00 bh 898,606.50 898,606.50
3 Jet Washer 5.00 bh 369,624.75 1,848,123.75
NO URAIAN PEKERJAAN VOL SAT HARGA SATUAN JUMLAH HARGA

4 Shower 2.00 bh 1,528,199.75 3,056,399.50


5 Kran air 9.00 bh 110,896.50 998,068.50
6 Washtafel 3.00 bh 2,553,886.50 7,661,659.50
7 Urinoir 3.00 bh 3,884,100.00 11,652,300.00
8 Urinal Partition ex. TOTO A100 3.00 bh 1,440,000.00 4,320,000.00
9 Dispenser tissue Box 2.00 bh 400,000.00 800,000.00
10 Floor drain 9.00 bh 210,237.50 1,892,137.50
11 Kaca cermin 2.16 m2 648,527.50 1,400,819.40
12 Kitchen Zinc + kran leher angsa 2.00 bh 1,142,693.75 2,285,387.50
JUMLAH SUB. V. A 50,993,643.40

V.B SISTEM PENYEDIAN AIR BERSIH


1 Pipa PVC Dia. 25 mm(1") 18.00 m1 51,069.26 919,246.68
2 Gate ValveDia. 25 mm(1/2") 6.00 bh 250,000.00 1,500,000.00
3 Gate ValveDia. 40 mm(1") 3.00 bh 315,000.00 945,000.00
4 Check Valve Dia. 25 mm(11/2") 2.00 bh 200,000.00 400,000.00
5 Foot Valve Dia. 25 mm(11/2") 1.00 bh 150,000.00 150,000.00
6 Pompa Transfer Ketangki Atap Kap. 0,35KW, Sek.Shimizu 1.00 unit 1,250,000.00 1,250,000.00
7 Jet Pump Kap. 5000 Watt, Sek.Shimizu 1.00 unit 3,875,000.00 3,875,000.00
8 Pengeboran Jet pump + Casing PVC dia 4" 1.00 unit 54,000,000.00 54,000,000.00
9 Water Level Control + Kabel 2.00 unit 950,000.00 1,900,000.00
10 Tangki Kap.2 m3(Panel Fibre Reinforced Plastic) 1.00 unit 3,000,000.00 3,000,000.00
11 Header Dia. 100 (4") 1.00 unit 700,000.00 700,000.00
12 Panel Pompa Lengkap Magnetic Contactor Dan MCB 1.00 unit 2,500,000.00 2,500,000.00
13 Kabel Ke Pompa Dan Panel Pompa NYY 3 x 1,5 mm2 + Conduit Dia. 25 mm 20.00 m1 35,000.00 700,000.00
14 Kabel Panel Pompa Ke Panel SDP Gedung Lt.1 NYY 4 x 4 mm2 + Conduit Dia. 20.00 m1 98,000.00 1,960,000.00
15 Pelampung + Katup Dia. 25mm (1 ") 2.00 unit 180,000.00 360,000.00
16 GWT(Ground Water Tank) Kap.4m3 1.00 unit 5,000,000.00 5,000,000.00
17 Menara Air Tinggi 8 Meter 1.00 unit 7,500,000.00 7,500,000.00
JUMLAH SUB. V. B 86,659,246.68

V.C PENGADAAN SISTEM AIR KOTOR


Pengadaan dan instalasi pemipaan air kotor dan air bekas menggunakan pipa PVC kelas AW, lengkap dengan peralatan
dan perlengkapan pendukung, sehingga sistem bekerja dengan baik.
Pengadaan Bio Filter Ceramic & instalasinya:
1 Bio Master Type STP BCR-140, 1.00 unit 26,400,000.00 26,400,000.00
ukuran P x L x T = 257 x 107 x 215 CM Kap. 4,85 m3
JUMLAH SUB. V. C 26,400,000.00

V.D Pengadaan
SISTEM dan PLUMBING
pemasangan PIPA
pipaAIR
PVCBERSIH
Kelas AW DAN
air PIPA AIR KOTOR
1 bersih dari Sumber air ke Roof Tank.
- Diameter 1" 16.38 m 32,051.69 525,006.68
- Fitting pipa 1.00 ls 150,000.00 150,000.00
- Gatepipa
Sistem valve diameter
utama 1" dan air kotor di bangunan
air bersih 3.00 bh 315,000.00 945,000.00
2 dan site (Lantai Satu).
Perpipaan air bersih , pipa air bersih digunakan pipa PVC kelas AW setara Maspion, lengkap dengan fitting pipa dan
peralatan lainnya. Pipa supply dari Roof Tank/Tangki Atas ke site
- Diameter 1" 25.00 m 32,051.69 801,292.25
- Diameter ¾" 22.00 m 28,559.63 628,311.86
- Diameter ½" 16.00 m 25,539.47 408,631.52
- Fitting pipa 1.00 ls 150,000.00 150,000.00
- Faucet taman diameter ½" 1.00 bh 25,000.00 25,000.00
- Gate valve besi diameter 1" 2.00 bh 315,000.00 630,000.00
- Gate valve besi diameter ¾" 3.00 bh 275,000.00 825,000.00
- Gate valve besi diameter ½" 1.00 bh 250,000.00 250,000.00
3 Pekerjaan plumbing dan instalasi.
a. Lantai Satu, toilet, pipa air bersih dari PVC kelas AW, pipa air panas pipa tigris 20mm, pipa gas polyethylene (PE 80)
lengkap fitting dan peralatan lain. Pipa supply dari tangki atas ke toilet, kitchen sink dan faucet taman.
- Diameter1" 22.00 m 32,051.69 705,137.18
- Diameter ¾" 45.00 m 28,559.63 1,285,183.35
- Diameter ½" 40.00 m 25,539.47 1,021,578.80
- Fitting pipa PVC 1.00 ls 150,000.00 150,000.00
- Gate valve diameter ½" 3.00 bh 275,000.00 825,000.00
- Faucettermasuk
Kg/Cm²) taman diameter ½" peralatan lainnya setara
fitting dan 1.00 bh 25,000.00 25,000.00
b. Maspion.
- Diameter 6" 20.00 m 227,123.05 4,542,461.00
- Diameter 4" 40.00 m 133,167.76 5,326,710.40
NO URAIAN PEKERJAAN VOL SAT HARGA SATUAN JUMLAH HARGA

- Diameter 3" 50.00 m 100,701.04 5,035,052.00


- Diameter 2" 40.00 m 51,069.26 2,042,770.40
- Diameter 1" 3.00 m 32,051.69 96,155.07
- Fitting pipa 1.00 ls 300,000.00 300,000.00
- Clean Out 1.00 bh 250,000.00 250,000.00
JUMLAH SUB. V.D 26,943,290.51
JUMLAH PEKERJAAN V 190,996,180.59
VI PEKERJAAN ELEKTRIKAL
VI.A PEKERJAAN DAYA PLN
- Biaya pemasangan baru daya 3 Phase 22,000.00 watt 1,500.00 33,000,000.00
JUMLAH SUB. VI. A 33,000,000.00
VI.B KABEL DAYA PERANGKAT UTAMA
1 Pekerjaan kabel daya termasuk pengadaan dan
pemasangan sepatu kabel, cable
conduit, cable jointing, penggalian tanah serta
penimbunan kembali (perapihan), termasuk di dalam
pekerjaan ini adalah pengujian pemasangan batang
grounding dengan BC-50. tahanan isolasi kabel (megger test)

Dari Panel PLN ke SDP :


PLN-SDP NYFGbY 4 x 10 mm2 25.00 m1 138,000.00 3,450,000.00
Dari Panel SDP ke Panel Pembagi :
SDP-PPLT1 NYY 4 x 6 mm2 24.00 m1 67,500.00 1,620,000.00
Dari Panel Panel Pembagi ke Group distribusi :
PPLT1-SK NYY 4 x 4 mm2 (stop kontak) 16.00 m1 48,000.00 768,000.00
PPLT1-LP NYY 4 x 4 mm2 (Penerangan) 16.00 m1 48,000.00 768,000.00
JUMLAH SUB. VI. B 6,606,000.00
VI.C SISTEM DAYA BANGUNAN
DAYA LANTAI 1
1 Sub Distribusi Panel (SDP) 1.00 unit 12,500,000.00 12,500,000.00
Wall-mounted type, oven painted / powder coated
Komponen Utama :
- 1 x MCCB 45 A, 3 P,25 kA
- 2 x MCCB 20 A, 3 P,25 kA
- 1 x MCCB 16 A, 3 P,25 kA
- 2x MCCB 10 A, 3 P,25 kA
- 3 x CT 250/5A
- 3 x A-meter 0 - 250 A
- 1 x V-meter 0 - 500 V + VSS 7 position
- 3 x fuse 2 A + fuse holder
- 3 x pilot lamp
- 1 lot busbar 50 A full neutral, 5 bus
- 1 lot control wiring + aksesori
- 1 lot cubicle (P x L x D) 120 x 70 x 40 cm
- 1 lot grounding
2 PP-LT-1 1.00 unit 10,000,000.00 10,000,000.00
Wall mounted (Inbow), oven painted / powder coated
Main components :
- 1 x MCCB 16 A, 3 P, 25 kA
- 1x MCB 10 A, 1 P, 10 kA
- 1 x MCB 6 A, 1 P, 10 kA
- 9 x MCB 4 A, 1 P, 10 kA
- 3 x CT 20/5A
- 3 x fuse 2 A + fuse holder
- 3 x pilot lamp
- 1 lot busbar 40 A full neutral, 5 bus
- 1 lot internal wiring + accessories
- 1 lot panel 30 x 20 x 11 cm
- 1 lot grounding
JUMLAH SUB. VI.C 22,500,000.00
VI.D SISTEM PENERANGAN BANGUNAN
LANTAI SATU dengan armature lengkap, lampu &
Sistem Penerangan
kelengkapan PHILIPS
1 Down Light LED 10 W 52.00 bh 275,000.00 14,300,000.00
2 Lampu RM 2x36 w 4.00 bh 650,000.00 2,600,000.00
3 Lampu Gantung kecil 4.00 bh 375,000.00 1,500,000.00
4 Lampu Sorot 20w 4.00 bh 450,000.00 1,800,000.00
NO URAIAN PEKERJAAN VOL SAT HARGA SATUAN JUMLAH HARGA

5 Saklar Tunggal 12.00 bh 55,000.00 660,000.00


6 Saklar Ganda 11.00 bh 75,000.00 825,000.00
7 Stop Kontak 16.00 bh 70,000.00 1,120,000.00
8 Stop Kontak Lantai 22.00 bh 840,000.00 18,480,000.00
9 Instalasi titik penerangan 64.00 titik 293,322.15 18,772,617.60
10 Instalasi titik stop kontak 38.00 titik 362,612.80 13,779,286.40
11 Instalasi titik outlet TV 3.00 titik 250,000.00 750,000.00
12 Instalasi titik outlet Infokus 1.00 titik 450,000.00 450,000.00
LANTAI DUA
Sistem Penerangan dengan armature lengkap, lampu &
kelengkapan PHILIPS
1 Down Light LED 10 W 27.00 unit 275,000.00 7,425,000.00
2 Lampu RM 2x36 w 3.00 unit 650,000.00 1,950,000.00
3 Lampu Gantung Utama uk. Dia 4 m bahan akrilik rangka besi lapis plat galvanis 1.00 unit 15,000,000.00 15,000,000.00
4 Saklar Tunggal 4.00 unit 55,000.00 220,000.00
5 Saklar Ganda 1.00 unit 75,000.00 75,000.00
6 Stop Kontak 16.00 unit 70,000.00 1,120,000.00
7 Instalasi titik penerangan 31.00 titik 293,322.15 9,092,986.65
8 Instalasi titik stop kontak 16.00 titik 362,612.80 5,801,804.80
9 Instalasi titik outlet Infokus 1.00 titik 450,000.00 450,000.00
JUMLAH SUB. VI.D 116,171,695.45
VI.E SISTEM INSTALASI TELEPON
LANTAI SATU
Pengadaan dan pemasangan sistim telepon lengkap PABX, outlet
telepon, Hand set, sistim instalasi dan kelengkapan lainnya.
1 PABX Kapasitas 12 extention, 2 incoming, 1.00 unit 25,680,000.00 25,680,000.00
a. power supply dan batery back-up, lengkap MDF.
b. termasuk instalasi dari MDF ke PABX
- 4 PSTN, 12 Extensions, Call Interuption, Call Restricion,
- Call Transfer, Password, Caller ID, Billing System
2 Main Distribution Frame (MDF), 100 pair in, 100 pair out. 1.00 unit 1,771,000.00 1,771,000.00
3 Sambungan line incoming TELKOM 2.00 line 948,750.00 1,897,500.00
4 Instalasi Titik Telepon ITC 4 x 0.6 mm2 + Conduit dia 20 mm 6.00 titik 250,000.00 1,500,000.00
5 Outlet Telepon ( RJ-11 )+ Extension Telepon (sek.panasonic) 6.00 titik 75,000.00 450,000.00
6 Terminal Box 1.00 unit 750,000.00 750,000.00
7 Testing dan commissioning 1.00 ls 5,000,000.00 5,000,000.00
JUMLAH SUB. VI.E 37,048,500.00
VI.F SISTEM INSTALASI DATA
LANTAI SATU
1 Instalasi Data / LAN 5.00 ttk 210,141.67 1,050,708.33
2 Outlet Data ( RG - 45 ) 5.00 bh 74,125.00 370,625.00
3 Hub Switch 8 Port ex 1.00 bh 2,511,125.00 2,511,125.00
LANTAI DUA
1 Instalasi Data / LAN 1.00 ttk 210,141.67 210,141.67
2 Outlet Data ( RG - 45 ) 1.00 bh 74,125.00 74,125.00
3 Hub Switch 8 Port ex 1.00 bh 2,511,125.00 2,511,125.00
JUMLAH SUB. VI.F 6,727,850.00
VI.G SISTEM TATA UDARA
LANTAI SATU
1 Stop Kontak AC 3.00 unit 54,000.00 162,000.00
2 Instalasi titik stop kontak 3.00 titik 362,612.80 1,087,838.40
3 AC LG 2 pk (18.000btu/h), 670w, Type Standard, Green filter, jetcool 3.00 unit 10,750,000.00 32,250,000.00
4 AC LG 1 pk (9.000btu/h), 670w, Type Standard, Green filter, jetcool 3.00 unit 8,750,000.00 26,250,000.00
5 Ceiling Exhaust Fan + instalasi 20.00 unit 798,500.00 15,970,000.00
LANTAI DUA
1 Stop Kontak AC 2.00 unit 54,000.00 108,000.00
2 Instalasi titik stop kontak 2.00 titik 362,612.80 725,225.60
3 AC LG 2 pk (18.000btu/h), 670w, Type Standard, Green filter, jetcool 1.00 unit 10,750,000.00 10,750,000.00
4 AC LG 1 pk (9.000btu/h), 670w, Type Standard, Green filter, jetcool 1.00 unit 8,750,000.00 8,750,000.00
5 Ceiling Exhaust Fan + instalasi 2.00 unit 798,500.00 1,597,000.00
JUMLAH SUB. VI.G 97,650,064.00
VI.H SISTEM PROTEKSI KEBAKARAN
LANTAI SATU
Fire Extunghusher
1 Pengadaan dan pemasangan alat pemadam api ringan, lengkap dengan dudukan 3.00 bh 948,625.00 2,845,875.00
Fire Extinguisher dry chemnical multi purpose type, 4 kg
(diletakkan di dalam Fire Hydrant cabinet (FHC) Indoor)
2 buah tiap FHC. Lengkap dengan braket dan dudukan.
NO URAIAN PEKERJAAN VOL SAT HARGA SATUAN JUMLAH HARGA

LANTAI DUA
Fire Extunghusher
1 Pengadaan dan pemasangan alat pemadam api ringan, lengkap dengan dudukan 2.00 bh 948,625.00 1,897,250.00
Fire Extinguisher dry chemnical multi purpose type, 4 kg
(diletakkan di dalam Fire Hydrant cabinet (FHC) Indoor)
2 buah tiap FHC. Lengkap dengan braket dan dudukan.
JUMLAH SUB. VI.H 4,743,125.00
VI.I SISTEM PENANGKAL PETIR
1 Kepala penangkal petir Type EF, radius proteksi min. 2.00 unit 10,752,500.00 21,505,000.00
25 m, dng dudukan, pipa penyangga, dan
kelengkapan lainnya, seperti pada gambar.
2 Down conductor, coaxial 50 mm2, lengkap dng 52.00 m 118,910.00 6,183,320.00
klem, kotak sambung dan pelindung pipa PVC.
3 Grounding system, batang tembaga diameter 1", 2.00 unit 2,530,000.00 5,060,000.00
panjang 6 m, sampai dicapai tahanan pentanahan
maksimum 2 Ohm. Lengkap dengan bak kontrol,
sambungan, las / klem, seperti pada gambar.
4 Accessories, alat bantu, dan kelengkapan lainya. 1.00 ls 1,581,250.00 1,581,250.00
JUMLAH SUB. VI.I 34,329,570.00
JUMLAH PEKERJAAN VI 358,776,804.45

VII PEKERJAAN SITE DEVELOPMENT


1 Pek. Perkerasan
a. Lapis Pondasi Atas (LPA) t=15 cm 86.61 m3 381,905.13 33,076,202.24
b. Pasir Urug t=10 cm 57.74 m3 172,062.00 9,934,679.21
c. Pasang Grass Block t=8 cm (Area Parkir) 547.72 m2 208,858.10 114,396,781.94
d. Pasang Batu Andesite t=10 cm 29.66 m2 289,607.45 8,591,089.16
e. Pasang Paving Block t=6 cm (Pedestrian) 16.48 m2 215,059.35 3,544,178.09
f. Rabat beton t=10 cm (Keliling Bangunan) 3.23 m3 1,036,391.62 3,344,902.13
2 Pek. Kanstin 90.69 m' 136,829.22 12,408,686.21
3 Pek. Penghijauan
a. Pek. Tanah subur t=10cm 10.81 m3 267,652.00 2,893,577.74
b. Pek. Menanam rumput gajah mini 108.11 m2 51,909.00 5,611,866.42
c. Pek. Menanam tanaman sok hawaii 100.00 polibag 19,167.00 1,916,700.50
d. Pek. Menanam tanaman plumbago ungu 100.00 polibag 11,984.45 1,198,444.50
e. Pek. Menanam tanaman hujan mas 100.00 polibag 13,117.01 1,311,700.50
f. Pek. Menanam pohon Katapang Angsana t.3 m diarea parkir 4.00 batang 378,306.50 1,513,226.00
4 Pek. Kirmir / Dinding Penahan Tanah
a. Pek. Galian tanah 42.29 m3 81,675.00 3,454,070.87
b. Pasir urug t=5 cm 3.02 m3 172,062.00 519,755.43
c. Pek. Lantai Kerja t=5 cm 3.02 m3 1,015,797.42 3,068,464.98
d. Pek. Pasangan batu kali camp. 1:5 102.71 m3 835,051.25 85,764,214.20
e. Pek. Plesteran + Acian Siar Benam 132.91 m2 106,426.76 14,145,476.54
f. Pek. Pasangan pipa sulingan PVC Ø2" jarak 100 cm + ijuk 108.75 m' 58,069.26 6,314,847.36
g. Pek. Plesteran + acian topi kirmir 30.21 m2 106,426.76 3,214,881.03
5 Pek. Saluran Drainase 125.72 m' 312,500.00 39,288,906.25
6 Pek. Grill Besi 125.72 m' 250,000.00 31,431,125.00
7 Pek. Kolam (Timur) 51.86 m2 750,000.00 38,895,075.00
8 Pek. Kolam (Barat) 41.60 m2 750,000.00 31,200,000.00
9 Pek. Penerangan jalan umum
a. Kabel NYY 4 x 10 mm2 Dari SDP ke LP-PJU 25.00 M' 150,000.00 3,750,000.00
b. Kabel NYFGbY 4 x 4 mm2 140.00 M' 98,000.00 13,720,000.00
c. Pek. Pemasangan PJU LED 40 watt IP65 Super Bright, Single Arm t= 7 m 6.00 Bh 10,260,000.00 61,560,000.00
d. Pek. Pemasangan Panel Kontrol (LP-PJU) 1.00 Unit 5,000,000.00 5,000,000.00
JUMLAH PEKERJAAN VII 541,068,851.30
HARGA SATUAN PEKERJAAN ARSITEKTUR
PEMBANGUNAN GEDUNG KANTOR RAJAMANDALA ELECTRIC POWER
TAHUN ANGGARAN 2018

No. SATUAN JENIS PEKERJAAN HARGA

1 1 M' PENGUKURAN DAN PEMASANGAN BOUWPLANK 65,957.83


2 1 M2 LOS KERJA/DIREKSI KEET 1,094,942.26
3 1 UNIT PAPAN NAMA PROYEK 80 X 120 CM 1,035,984.51
4 1 M' PAGAR PENGAMAN PROYEK 643,941.19
5 1 M2 PEMBERSIHAN LAPANGAN 19,360.00
6 1 M3 GALIAN TANAH BIASA KEDALAMAN MAX 1 M 81,675.00
7 1 M3 GALIAN TANAH BIASA KEDALAMAN MAX 2 M 88,000.00
8 1M GALIAN TANAH STRAUSS PILE DIA. 60 CM 192,500.00
9 1 M3 BUANGAN GALIAN TANAH 35,453.00
10 1 M3 URUGAN KEMBALI TANAH BEKAS GALIAN 27,218.95
11 1 M3 MENGURUG PASIR URUG 172,062.00
12 1 M3 URUGAN TANAH MERAH 196,746.00
13 1 M3 PEMADATAN TANAH (PER 20 CM) 60,500.00
14 1 M3 LANTAI KERJA (1PC : 3PS : 5KR) 1,015,797.42
15 1 M3 URUGAN SIRTU 182,710.00
16 1 M2 STONE BLOCK 20 x 20 cm T=8 cm 289,607.45
17 1 M2 PAVING BLOCK 10 x 20 cm T=6 cm 215,059.35
18 1 M2 GRASS BLOCK T=8 cm 208,858.10
19 1 M' KANSTEEN BETON 136,829.22
20 1 M3 PASANG BATU KOSONG / AANSTAMPING 426,289.05
21 1 M3 PASANG PONDASI BATU KALI (1PC : 5PS) 835,051.25
22 1 M2 PASANG PONDASI ROLLAGH BATA 277,549.80
23 1 M2 PASANG DINDING BATA I BRICK 1/2 BT (1PC : 4PS) 334,311.87
24 1 M2 PASANG DINDING BATA RINGAN (HB=100) MM 1/2 BT 158,282.21
25 1 M2 PASANG DINDING BATA MERAH 1/2 BT (1PC : 5PS) 135,280.42
26 1 M2 PASANG DINDING BATA MERAH PRESS EKSPOS 1/2 BT (1PC : 5PS) 180,655.42
27 1 M2 PASANG DINDING BATA MERAH 1 BT (1PC : 5PS) 272,738.84
28 1 M2 PLESTERAN DINDING (1PC : 5PS) 64,923.76
29 1 M2 ACIAN 41,503.00
30 1 M2 PLESTERAN SKONING 1 PC : 2 PP LEBAR 10 MM 66,610.50
31 1 M2 PLESTERAN CIPRAT (1PC : 2PS) 55,597.08
32 1 M2 PLESTERAN MENGGUNAKAN MORTAR SEMEN 90,145.00
33 1 M2 ACIAN MENGGUNAKAN MORTAR SEMEN 37,570.50
34 1 M2 PAS. DINDING BATU ALAM 291,126.00
35 1 M2 PAS. DINDING BATA BETON BERLUBANG 492,361.85
36 1 M2 PASANG GRANITE LANTAI 60 X 60 Polished 443,595.95
37 1 M2 PASANG GRANITE LANTAI 60 X 60 Unpolished 461,241.78
38 1 M2 PASANG DINDING KERAMIK 30 X 60 341,220.48
39 1 M2 LANTAI KERAMIK 30 X 30 275,470.05
40 1 M2 LANTAI PARQUET KAYU 497,436.01
41 1 M1 PLINT LANTAI PARQUET KAYU 163,459.76
42 1 M1 STEPNOSING 102,043.33
43 1 M' PASANG BORDER KERAMIK 10 x 25 cm 259,363.50
44 1 M' PASANG PLIN GRANITE TILE POLISHED 10 X 60 cm KW 1 (1PC : 4PS) 58,839.61
45 1 M2 FINISHING LANTAI FLOORHARDENER WARNA NATURAL 78,922.25
46 1 M2 PENGECATAN PLAPOND BARU 61,896.95
No. SATUAN JENIS PEKERJAAN HARGA

47 1 M2 PENGECATAN TEMBOK INTERIOR 60,590.15


48 1 M2 PENGECATAN TEMBOK / DINDING EKSTERIOR 70,374.21
49 1 M2 PENGECATAN MELAMIK KUSEN, DAUN PINTU, JENDELA DAN BOUWVENL 242,796.42
50 1 M2 PENGECATAN KAYU/BESI 67,654.61
No. SATUAN JENIS PEKERJAAN HARGA

51 1 M2 WATERPROOFING COATING 99,135.75


52 1 M2 WATERPROOFING MEMBRAN 232,850.59
53 1 M2 PEK. FLASHING ATAP 117,683.63
54 1 M2 PASANG ATAP GELOMBANG PVC 282,580.92
55 1 M2 PASANG ATAP METAL SPANDEX 131,933.86
56 1 M2 PASANG WUWUNGAN PVC 196,669.16
57 1 M2 PASANG ALUMUNIUM FOIL 54,126.21
58 1 M2 PASANGAN PLAFOND GYPSUM BERIKUT RANGKA HOLLOW ZINCROMATE 155,237.08
59 1 M2 PASANGAN PLAFOND GRC BERIKUT RANGKA HOLLOW ZINCROMATE 150,627.87
60 1 M2 PASANGAN PLAFOND PVC BERIKUT RANGKA HOLLOW ZINCROMATE 239,244.32
61 1 M' PASANG LIST PROFIL PLAFOND GYPSUM 34,535.82
62 1 M' PASANG LIST PROFIL PLAFOND PVC 44,981.75
63 1 M2 PAS. DINDING SKAT DOUBLE GYPSUM RANGKA HOLLOW 277,893.27
64 1 M1 PASANG LIST PLANK GRC 71,285.94
65 1 M1 TALANG 1/2 LINGKARAN D-20 cm, SENG PLAT BJLS 50 POWDER COATING 132,535.17
66 1 M2 PAS. ALUMUNIUM COMPOSITE PANEL 4mm 1,572,292.82
67 1 M2 PAS. CANOPI KACA 1,472,467.82
68 1 TTK PAS. INSTALASI PENERANGAN 293,322.15
69 1 TTK PAS. INSTALASI STOP KONTAK 362,612.80
70 1 TTK PAS. ARMATURE BALK 1x36 277,392.50
71 1 TTK PAS. INSTALASI KABEL DATA 327,099.30
72 1 BH PAS. CLOSET JONGKOK 898,606.50
73 1 BH PAS. CLOSET DUDUK 2,836,028.25
74 1 BH MEMASANG WASTAFEL 2,553,886.50
75 1 BH MEMASANG URINOIR 3,884,100.00
76 1 BH BAK CUCI PIRING STAINLESS-STEEL 735,680.00
77 1 M2 MEMASANG CERMIN WASTAFEL 148,527.50
78 1 BH MEMASANG KRAN Ø 1/2" ATAU Ø 3/4" 110,896.50
79 1 BH MEMASANG KRAN WASTAFEL 275,275.00
80 1 BH MEMASANG KRAN LEHER ANGSA SET. SUN EI 407,013.75
81 1 BH MEMASANG 1 BUAH JET WASHER 369,624.75
82 1 BH MEMASANG HANDSHOWER KOMBINASI KRAN 1,528,199.75
83 1 BH MEMASANG 1 BUAH FLOOR DRAIN 210,237.50
84 1 M1 MEMASANG 1 METER PIPA PVC TIPE AW Ø 1/2" 25,539.47
85 1 M1 MEMASANG 1 METER PIPA PVC TIPE AW Ø 3/4" 28,559.63
86 1 M1 MEMASANG 1 METER PIPA PVC TIPE AW Ø 1" 32,051.69
87 1 M1 MEMASANG 1 METER PIPA PVC TIPE AW Ø 1 1/2" 37,242.59
88 1 M1 MEMASANG 1 METER PIPA PVC TIPE AW Ø 2" 51,069.26
89 1 M1 MEMASANG 1 METER PIPA PVC TIPE AW Ø 3" 100,701.04
90 1 M1 MEMASANG 1 METER PIPA PVC TIPE AW Ø4" 133,167.76
91 1 M1 MEMASANG 1 METER PIPA PVC TIPE AW Ø6" 227,123.05
92 1 UNIT MEMASANG BAK KONTROL PAS. BATU BATA 45 X 45 T. 50 CM 339,006.91
93 1 M' PASANG SALURAN GRAVEL U - 20 CM 208,219.60
94 1 M' MEMASANG BUIS BETON DIA. 30 CM - 100 CM 266,460.15
95 1 M2 PASANG BATA ROOSTER 511,052.94
96 1 M3 URUGAN TANAH SUBUR 267,652.00
97 1 M2 RUMPUT GAJAH MINI 51,909.00
98 1 PLBG MENANAM TANAMAN SOKA HAWAII T=30 CM 19,167.00
99 1 PLBG MENANAM TANAMAN PLUMBAGO UNGU 11,984.45
100 1 PLBG MENANAM TANAMAN HUJAN MAS 13,117.01
101 1 BTG MENANAM POHON KATAPANG ANGSANA T=3 M, Ø BTG 7 cm 378,306.50
No. SATUAN JENIS PEKERJAAN HARGA
102 1 BTG MENANAM PALEM EKOR TUPAI T. 3 M 559,806.50
HARGA SATUAN PEKERJAAN KUSEN
PEMBANGUNAN GEDUNG KANTOR RAJAMANDALA ELECTRIC POWER
TAHUN ANGGARAN 2018

No. SATUAN JENIS PEKERJAAN HARGA

1 1 BH PINTU KACA FRAME ALUMINIUM 965,951.71


2 1 BH PINTU PANIL DOUBLE MULTIPLEK LAPIS HPL 963,895.68
3 1 BH PINTU SPANDRIL 1,025,867.04
4 1 BH JENDELA FRAME ALUMUNIUM 258,040.37
5 1M2 TEAKWOOD 6 MM 223,160.66
6 1M2 PAS. FORMIKA 206,566.24
7 1M1 PASANG KUSEN ALUMUNIUM 4" (WARNA) 163,513.35
9 1M2 PASANG KACA POLOS 5 MM 121,205.70
10 1M2 PASANG KACA POLOS 8 MM 228,562.95
11 1M2 PASANG KACA POLOS 10 MM 314,321.70
12 1M2 PASANG KACA TEMPERED 12 MM 733,586.70
13 1BH PASANG ENGSEL PINTU 87,071.60
14 1BH PASANG ENGSEL JENDELA 65,981.30
15 1BH PASANG KUNCI SLOT 76,810.80
16 1BH PASANG ENGSEL JENDELA CASEMENT 81,675.00
17 1 SET PASANG LEVER HANDLE, LOCKCASE DAN CYLINDER KUNCI PIN 1,541,189.10
18 1 BH PASANG DOOR CLOSER 648,499.50
19 1 BH PASANG FLOOR HINGE 3,176,250.00
20 1 UNIT PINTU BESI TYPE PB 24,234,000.00
21 1 UNIT PINTU TYPE P1 7,053,281.74
22 1 UNIT PINTU TYPE P2 4,258,494.93
23 1 UNIT PINTU TYPE P3 3,893,694.11
24 1 UNIT PINTU TYPE P4 3,652,493.57
25 1 UNIT JENDELA TYPE J1 7,857,408.96
26 1 UNIT JENDELA TYPE J2 9,281,983.89
27 1 UNIT JENDELA TYPE J3 10,225,233.39
28 1 UNIT JENDELA TYPE J4 8,774,080.31
29 1 UNIT JENDELA TYPE J5 8,701,522.65
30 1 UNIT JENDELA TYPE J6 2,023,352.51
29 1 UNIT JENDELA TYPE J7 9,869,703.08
30 1 UNIT JENDELA TYPE J8 2,756,543.12
31 1 UNIT BOUVENLIGHT TYPE BV1 662,342.36
32 1 UNIT BOUVENLIGHT TYPE BV2 4,262,083.75
33 1 UNIT BOUVENLIGHT TYPE BV3 5,550,168.08
34 1 UNIT PARTISI CUBICAL TOILET LENGKAP DAUN PINTU BERIKUT ACC 7,260,000.00
HARGA SATUAN PEKERJAAN STRUKTUR
PEMBANGUNAN GEDUNG KANTOR RAJAMANDALA ELECTRIC POWER
TAHUN ANGGARAN 2018

No. SATUAN JENIS PEKERJAAN HARGA

1 1 M3 LANTAI KERJA (1PC : 3PS : 5KR) 1,015,797.42


2 1 M' PENGADAAN TIANG PANCANG 211,750.00
3 1 M' PEMANCANGAN 20x20cm dengan Doly/Follower ( Hidrolik Jac 136,730.00
4 1 TITIK SAMBUNGAN MINI PILE 20X20 CM 374,047.30
5 1 TITIK PEMOTONGAN KEPALA TIANG 124,630.00
6 1 M3 MEMASANG PONDASI SIKLOP, 60% BETON CAMPURAN 1 PC 3,810,659.05
7 1 M3 COR BETON SITE MIX K-175 1,061,894.91
8 1 M3 RABAT BETON 1,036,391.62
9 1 M3 COR BETON SITE MIX K-225 1,164,802.51
10 1 M3 COR BETON READY MIX K-300 BERIKUT SLANG MIN 6 M 1,586,915.00
11 1 M2 BEKISTING BETON PONDASI POER, SLOOF 161,672.94
12 1 M2 BEKISTING KOLOM 212,314.92
13 1 M2 BEKISTING BALOK 217,033.92
14 1 M2 BEKISTING PLAT LANTAI 269,336.17
15 1 M2 BEKISTING TANGGA 220,475.31
16 1 M2 BEKISTING DINDING BETON 231,879.56
17 1 KG MENGERJAKAN BESI BETON TULANGAN 20,001.06
18 1 m2 MENGERJAKAN BESI WERMESH M 6 41,846.59
22 1 KG BESI PROFIL/SIKU/IWF/PIPA/PLAT 25,404.03
23 1 KG PEKERJAAN ERECTION KONSTRUKSI BAJA 708.05
24 1 BH PASANG ANCHOR BOLT Ø25MMX500X100 52,922.68
25 1 m2 MENGERJAKAN PLAT BONDEK 275,827.12
26 1 m3 PEKERJAAN KOLOM PRAKTIS 12 x12 cm 8,068,347.24
27 1 m3 PEKERJAAN BALOK LINTEI / PRAKTIS 12 x15 cm 6,887,369.11
28 1 m3 PEKERJAAN PLAT BETON KANOPY T.7 cm 7,749,309.52
29 1 m2 PASANG RANGKA ATAP BAJA RINGAN 238,610.76
30 1 m3 PEKERJAAN PEMASANGAN PONDASI JALAN LPB 314,878.67
31 1 m3 PEKERJAAN PEMASANGAN PONDASI JALAN LPA 381,905.13
ANALISA HARGA
PEMBANGUNAN GEDUNG KANTOR RAJAMANDALA ELECTRIC POWER
TAHUN ANGGARAN 2018

No. URAIAN SATUAN VOLUME HARGA SATUAN JUMLAH (RP) TOTAL (RP)

1 1 M' PENGUKURAN DAN PEMASANGAN BOUWPLANK 65,957.83


Kayu Terentang m³ 0.0120 2,080,000.00 24,960.00
Paku 2'' - 7" kg 0.0200 20,280.00 405.60
Kayu Papan Albasiah m³ 0.0070 1,235,000.00 8,645.00
Pekerja Orang 0.1000 85,000.00 8,500.00
Tukang Kayu Orang 0.1000 100,000.00 10,000.00
Kepala Tukang Orang 0.0100 125,000.00 1,250.00
Mandor Orang 0.0050 150,000.00 750.00
Jumlah 54,510.60
Jasa Kontraktor 5,451.06
PPn 10% 5,996.17

2 1 M2 LOS KERJA/DIREKSI KEET 1,094,942.26


Kayu Dolken / Kasau batang 1.4063 18,850.00 26,508.76
Kayu Papan 3/20 m3 0.1800 1,235,000.00 222,300.00
Paku Kg 0.8500 20,280.00 17,238.00
Besi Strip kg 1.1000 17,940.00 19,734.00
Semen PC 50 Zak 0.7000 70,000.00 49,000.00
Pasir Pasang m3 0.2500 150,000.00 37,500.00
Pasir beton I/kasar m3 0.1000 210,000.00 21,000.00
Batu pecah mesin 1 : 2 m3 0.1500 212,000.00 31,800.00
Plywoood 4 mm Lembar 0.0600 59,670.00 3,580.20
Tukang Kayu Orang 2.0000 100,000.00 200,000.00
Tukang Batu Orang 1.0000 100,000.00 100,000.00
Pekerja Orang 2.0000 85,000.00 170,000.00
Kepala Tukang Orang 0.0500 125,000.00 6,250.00
Jumlah 904,910.96
Jasa Kontraktor 90,491.10
PPn 10% 99,540.21

3 1 UNIT PAPAN NAMA PROYEK 80 X 120 CM 1,035,984.51


Bahan Kayu balok albasiah m3 0.0500 1,235,000.00 61,750.00
Seng plat BJLS 25 uk. 90 x 180 cm lbr 1.6200 53,690.00 86,977.80
Paku 4 s/d 7 cm kg 0.6000 20,280.00 12,168.00
Cat Kayu / besi kg 1.5000 49,140.00 73,710.00
Beton Cor 1 : 2 : 3 m3 0.1000 1,015,797.42 101,579.74
Upah Tukang Kayu Orang 1.0000 100,000.00 100,000.00
Tukang Cat Orang 1.0000 100,000.00 100,000.00
Pekerja Orang 2.0000 85,000.00 170,000.00
Mandor Orang 1.0000 150,000.00 150,000.00
Jumlah 856,185.54
Jasa Kontraktor 85,618.55
PPn 10% 94,180.41

4 1 M' PAGAR PENGAMAN PROYEK 643,941.19


Dolken dia. 8 s/d 10 cm Btg 1.2500 18,850.00 23,562.50
Semen PC 50 kg Zak 0.0500 70,000.00 3,500.00
Seng gelombang 3"-5" Lbr 1.2000 77,480.00 92,976.00
Pasir beton I/kasar m3 m3 1.2000 210,000.00 252,000.00
Batu pecah mesin 1 : 2 m3 m3 0.0090 212,000.00 1,908.00
Kayu papan albasiah m3 m3 0.0720 1,235,000.00 88,920.00
Paku 4 s/d 7 cm kg Kg 0.0600 20,280.00 1,216.80
Meni kayu / besi Bola Mas Kg 0.4500 19,110.00 8,599.50
Pekerja oh 0.4000 85,000.00 34,000.00
Tukang Kayu oh 0.2000 100,000.00 20,000.00
Kepala Tukang Kayu oh 0.0200 125,000.00 2,500.00
Mandor oh 0.0200 150,000.00 3,000.00
Jumlah 532,182.80
Jasa Kontraktor 53,218.28
PPn 10% 58,540.11

5 1 M2 PEMBERSIHAN LAPANGAN 19,360.00


Upah Pekerja Orang 0.1000 85,000.00 8,500.00
Mandor Orang 0.0500 150,000.00 7,500.00
Jumlah 16,000.00
Jasa Kontraktor 1,600.00
PPn 10% 1,760.00

6 1 M3 GALIAN TANAH BIASA KEDALAMAN MAX 1 M 81,675.00


Pekerja Orang 0.7500 85,000.00 63,750.00
Mandor Orang 0.0250 150,000.00 3,750.00
Jumlah 67,500.00
Jasa Kontraktor 6,750.00
PPn 10% 7,425.00
No. URAIAN SATUAN VOLUME HARGA SATUAN JUMLAH (RP) TOTAL (RP)

7 1 M3 GALIAN TANAH BIASA KEDALAMAN MAX 2 M 88,000.00


Pekerja Orang 0.8000 85,000.00 68,000.00
Mandor Orang 0.0800 150,000.00 12,000.00
Jumlah 80,000.00
Jasa Kontraktor 8,000.00

8 1M GALIAN TANAH STRAUSS PILE DIA. 60 CM 192,500.00


Upah Ls 1.0000 145,000.00 145,000.00
Sewa Mesin Bor Ls 1.0000 30,000.00 30,000.00

Jumlah 175,000.00
Jasa Kontraktor 17,500.00

9 1 M3 BUANGAN GALIAN TANAH 35,453.00


Pekerja Orang 0.3300 85,000.00 28,050.00
Mandor Orang 0.0100 125,000.00 1,250.00
Jumlah 29,300.00
Jasa Kontraktor 2,930.00
PPn 10% 3,223.00

10 1 M3 URUGAN KEMBALI TANAH BEKAS GALIAN 27,218.95


Pekerja Orang 0.2500 85,000.00 21,250.00
Mandor Orang 0.0083 150,000.00 1,245.00
Jumlah 22,495.00
Jasa Kontraktor 2,249.50
PPn 10% 2,474.45

11 1 M3 MENGURUG PASIR URUG 172,062.00


Pasir Urug m3 1.2000 96,000.00 115,200.00
Pekerja Orang 0.3000 85,000.00 25,500.00
Mandor Orang 0.0100 150,000.00 1,500.00
Jumlah 142,200.00
Jasa Kontraktor 14,220.00
PPn 10% 15,642.00

12 1 M3 URUGAN TANAH MERAH 196,746.00


tanah subur M3 1.2000 113,000.00 135,600.00
Pekerja Orang 0.3000 85,000.00 25,500.00
Mandor Orang 0.0100 150,000.00 1,500.00
Jumlah 162,600.00
Jasa Kontraktor 16,260.00
PPn 10% 17,886.00

13 1 M3 PEMADATAN TANAH (PER 20 CM) 60,500.00


Pekerja Orang 0.5000 85,000.00 42,500.00
Mandor Orang 0.0500 150,000.00 7,500.00
Jumlah 50,000.00
Jasa Kontraktor 5,000.00
PPn 10% 5,500.00

14 1 M3 LANTAI KERJA (1PC : 3PS : 5KR) 1,015,797.42


Semen PC 50 kg Zak 4.9400 70,000.00 345,800.00
Batu pecah mesin 1/2 : 1 m3 0.7400 172,000.00 127,280.00
Pasir beton I/kasar m3 0.6207 210,000.00 130,347.00
Air ltr 215.0000 100.00 21,500.00
Pekerja Orang 1.6500 85,000.00 140,250.00
Tukang Batu Orang 0.2750 100,000.00 27,500.00
Kepala Tukang Batu Orang 0.2750 125,000.00 34,375.00 ###
Mandor Orang 0.0830 150,000.00 12,450.00
Jumlah 839,502.00
Jasa Kontraktor 83,950.20
PPn 10% 92,345.22

15 1 M3 URUGAN SIRTU 182,710.00


Sirtu m3 1.2000 105,000.00 126,000.00
Pekerja Orang 0.2500 85,000.00 21,250.00
Mandor Orang 0.0250 150,000.00 3,750.00
Jumlah 151,000.00
Jasa Kontraktor 15,100.00
PPn 10% 16,610.00

16 1 M2 STONE BLOCK 20 x 20 cm T=8 cm 289,607.45


Stone block tebal 8 cm m2 1.0100 186,000.00 187,860.00
Abu batu m3 0.0600 156,000.00 9,360.00
Pekerja Orang 0.3500 85,000.00 29,750.00
Tukang Batu Orang 0.0350 100,000.00 3,500.00
Kepala Tukang Batu Orang 0.0350 125,000.00 4,375.00
Mandor Orang 0.0300 150,000.00 4,500.00
Jumlah 239,345.00
Jasa Kontraktor 23,934.50
PPn 10% 26,327.95

17 1 M2 PAVING BLOCK 10 x 20 cm T=6 cm 215,059.35


Paving block tebal 6 cm m2 1.0100 125,000.00 126,250.00
Abu batu m3 0.0600 156,000.00 9,360.00
No. URAIAN SATUAN VOLUME HARGA SATUAN JUMLAH (RP) TOTAL (RP)

Pekerja Orang 0.3500 85,000.00 29,750.00


Tukang Batu Orang 0.0350 100,000.00 3,500.00
Kepala Tukang Batu Orang 0.0350 125,000.00 4,375.00
Mandor Orang 0.0300 150,000.00 4,500.00
Jumlah 177,735.00
Jasa Kontraktor 17,773.50
PPn 10% 19,550.85

18 1 M2 GRASS BLOCK T=8 cm 208,858.10


Grass block tebal 8 cm m2 6.2500 20,800.00 130,000.00
Abu batu m3 0.0600 156,000.00 9,360.00
Pekerja Orang 0.3500 85,000.00 29,750.00
Tukang Batu Orang 0.0350 100,000.00 3,500.00
Kepala Tukang Batu Orang 0.0350 125,000.00 4,375.00
Mandor Orang 0.0300 150,000.00 4,500.00
Jumlah 172,610.00
Jasa Kontraktor 17,261.00
PPn 10% 18,987.10
No. URAIAN SATUAN VOLUME HARGA SATUAN JUMLAH (RP) TOTAL (RP)

19 1 M' KANSTEEN BETON 136,829.22


Kanstein 400 x 60 x 155 mm bh 2.5000 29,900.00 74,750.00
Semen PC 50 kg zak 0.2276 70,000.00 15,932.00
Pasir Pasang m3 0.0420 150,000.00 6,300.00
Pekerja Orang 0.0350 85,000.00 2,975.00
Tukang Batu Orang 0.0350 100,000.00 3,500.00
Kepala Tukang Orang 0.0350 125,000.00 4,375.00
Mandor Orang 0.0350 150,000.00 5,250.00
Jumlah 113,082.00
Jasa Kontraktor 11,308.20
PPn 10% 12,439.02

20 1 M3 PASANG BATU KOSONG / AANSTAMPING 426,289.05


Batu Belah m3 1.2000 162,500.00 195,000.00
Pasir Urug m3 0.4300 96,000.00 41,280.00
Pekerja Orang 0.7800 85,000.00 66,300.00
Tukang Batu Orang 0.3900 100,000.00 39,000.00
Kepala Tukang Batu Orang 0.0390 125,000.00 4,875.00
Mandor Orang 0.0390 150,000.00 5,850.00
Jumlah 352,305.00
Jasa Kontraktor 35,230.50
PPn 10% 38,753.55

21 1 M3 PASANG PONDASI BATU KALI (1PC : 5PS) 835,051.25


Semen PC 50 kg zak 2.7200 70,000.00 190,400.00
Batu Belah m3 1.2000 162,500.00 195,000.00
Pasir Pasang Pondasi m3 0.5440 150,000.00 81,600.00
Pekerja Orang 1.5000 85,000.00 127,500.00
Tukang Batu Orang 0.7500 100,000.00 75,000.00
Kepala Tukang Orang 0.0750 125,000.00 9,375.00
Mandor Orang 0.0750 150,000.00 11,250.00
Jumlah 690,125.00
Jasa Kontraktor 69,012.50
PPn 10% 75,913.75

22 1 M2 PASANG PONDASI ROLLAGH BATA 277,549.80


Semen PC 50kg zak 0.4440 70,000.00 31,080.00
Bata Merah Buah 140.0000 750.00 105,000.00
Pasir Pasang m3 0.1020 150,000.00 15,300.00
Pekerja Orang 0.6000 85,000.00 51,000.00
Tukang Batu Orang 0.2000 100,000.00 20,000.00
Kepala Tukang Orang 0.0200 125,000.00 2,500.00
Mandor Orang 0.0300 150,000.00 4,500.00
Jumlah 229,380.00
Jasa Kontraktor 22,938.00
PPn 10% 25,231.80

23 1 M2 PASANG DINDING BATA I BRICK 1/2 BT (1PC : 4PS) 334,311.87


Semen PC 50kg kg 24.2600 1,400.00 33,964.00
Bata I Brick Buah 12.5000 5,850.00 73,125.00
Pasir Pasang m3 0.7720 150,000.00 115,800.00
Angkur besi kg 0.2800 14,560.00 4,076.80
Pekerja Orang 0.3500 85,000.00 29,750.00
Tukang Batu Orang 0.1500 100,000.00 15,000.00
Kepala Tukang Orang 0.0150 125,000.00 1,875.00
Mandor Orang 0.0180 150,000.00 2,700.00
Jumlah 276,290.80
Jasa Kontraktor 27,629.08
PPn 10% 30,391.99

24 1 M2 PASANG DINDING BATA RINGAN (HB=100) MM 1/2 BT 158,282.21


Semen Mortar (MU-380) kg 6.0000 3,750.00 22,500.00
Bata Ringan Tebal 10 cm Buah 8.5000 8,674.70 73,734.94
Angkur besi kg 0.2800 14,560.00 4,076.80
Pekerja Orang 0.2000 85,000.00 17,000.00
Tukang Batu Orang 0.1000 100,000.00 10,000.00
Kepala Tukang Orang 0.0100 125,000.00 1,250.00
Mandor Orang 0.0150 150,000.00 2,250.00
Jumlah 130,811.74
Jasa Kontraktor 13,081.17
PPn 10% 14,389.29

25 1 M2 PASANG DINDING BATA MERAH 1/2 BT (1PC : 5PS) 135,280.42


Semen PC 50kg Sak 0.1936 70,000.00 13,552.00
Bata Merah Buah 70.0000 750.00 52,500.00
Pasir Pasang m3 0.0450 150,000.00 6,750.00
Pekerja Orang 0.3000 85,000.00 25,500.00
Tukang Batu Orang 0.1000 100,000.00 10,000.00
Kepala Tukang Orang 0.0100 125,000.00 1,250.00
Mandor Orang 0.0150 150,000.00 2,250.00
Jumlah 111,802.00
Jasa Kontraktor 11,180.20
PPn 10% 12,298.22
No. URAIAN SATUAN VOLUME HARGA SATUAN JUMLAH (RP) TOTAL (RP)

26 1 M2 PASANG DINDING BATA MERAH PRESS EKSPOS 1/2 BT (1PC : 5PS) 180,655.42
Semen PC 50kg Sak 0.1936 70,000.00 13,552.00
Bata Merah Buah 60.0000 1,500.00 90,000.00
Pasir Pasang m3 0.0450 150,000.00 6,750.00
Pekerja Orang 0.3000 85,000.00 25,500.00
Tukang Batu Orang 0.1000 100,000.00 10,000.00
Kepala Tukang Orang 0.0100 125,000.00 1,250.00
Mandor Orang 0.0150 150,000.00 2,250.00
Jumlah 149,302.00
Jasa Kontraktor 14,930.20
PPn 10% 16,423.22

27 1 M2 PASANG DINDING BATA MERAH 1 BT (1PC : 5PS) 272,738.84


Semen PC 50kg Sak 0.3872 70,000.00 27,104.00
Bata Merah Buah 140.0000 750.00 105,000.00
Pasir Pasang m3 0.1020 150,000.00 15,300.00
Pekerja Orang 0.6000 85,000.00 51,000.00
Tukang Batu Orang 0.2000 100,000.00 20,000.00
Kepala Tukang Orang 0.0200 125,000.00 2,500.00
Mandor Orang 0.0300 150,000.00 4,500.00
Jumlah 225,404.00
Jasa Kontraktor 22,540.40
PPn 10% 24,794.44

28 1 M2 PLESTERAN DINDING (1PC : 5PS) 64,923.76


Semen PC 50kg Zak 0.1458 70,000.00 10,206.00
Pasir Pasang m3 0.0230 150,000.00 3,450.00
Pekerja Orang 0.2500 85,000.00 21,250.00
Tukang Batu Orang 0.1500 100,000.00 15,000.00
Kepala Tukang Orang 0.0150 125,000.00 1,875.00
Mandor Orang 0.0125 150,000.00 1,875.00
Jumlah 53,656.00
Jasa Kontraktor 5,365.60
PPn 10% 5,902.16
No. URAIAN SATUAN VOLUME HARGA SATUAN JUMLAH (RP) TOTAL (RP)

29 1 M2 ACIAN 41,503.00
Semen PC 50kg Zak 0.0650 70,000.00 4,550.00
Pekerja Orang 0.2000 85,000.00 17,000.00
Tukang Batu Orang 0.1000 100,000.00 10,000.00
Kepala Tukang Orang 0.0100 125,000.00 1,250.00
Mandor Orang 0.0100 150,000.00 1,500.00
Jumlah 34,300.00
Jasa Kontraktor 3,430.00
PPn 10% 3,773.00

30 1 M2 PLESTERAN SKONING 1 PC : 2 PP LEBAR 10 MM 66,610.50


Semen PC 50kg Zak 0.0100 70,000.00 700.00
Pasir Pasang m3 0.0130 150,000.00 1,950.00
Pekerja Orang 0.0800 85,000.00 6,800.00
Tukang Batu Orang 0.4000 100,000.00 40,000.00
Kepala Tukang Orang 0.0400 125,000.00 5,000.00
Mandor Orang 0.0040 150,000.00 600.00
Jumlah 55,050.00
Jasa Kontraktor 5,505.00
PPn 10% 6,055.50

31 1 M2 PLESTERAN CIPRAT (1PC : 2PS) 55,597.08


Semen PC 50kg Zak 0.0864 70,000.00 6,048.00
Pasir Pasang m3 0.0060 150,000.00 900.00
Pekerja Orang 0.3000 85,000.00 25,500.00
Tukang Batu Orang 0.1000 100,000.00 10,000.00
Kepala Tukang Orang 0.0100 125,000.00 1,250.00
Mandor Orang 0.0150 150,000.00 2,250.00
Jumlah 45,948.00
Jasa Kontraktor 4,594.80
PPn 10% 5,054.28

32 1 M2 PLESTERAN MENGGUNAKAN MORTAR SEMEN 90,145.00


Semen Mortar (Skim Coat) Kg 11.0000 4,000.00 44,000.00
Pekerja Orang 0.2000 85,000.00 17,000.00
Tukang Batu Orang 0.1000 100,000.00 10,000.00
Kepala Tukang Batu Orang 0.0100 125,000.00 1,250.00
Mandor Orang 0.0150 150,000.00 2,250.00
Jumlah 74,500.00
Jasa Kontraktor 7,450.00
PPn 10% 8,195.00

33 1 M2 ACIAN MENGGUNAKAN MORTAR SEMEN 37,570.50


Semen Mortar MU 200 Kg 0.3250 4,000.00 1,300.00
Pekerja Orang 0.2000 85,000.00 17,000.00
Tukang Batu Orang 0.1000 100,000.00 10,000.00
Kepala Tukang Batu Orang 0.0100 125,000.00 1,250.00
Mandor Orang 0.0100 150,000.00 1,500.00
Jumlah 31,050.00
Jasa Kontraktor 3,105.00
PPn 10% 3,415.50

34 1 M2 PAS. DINDING BATU ALAM 291,126.00


Batu Templeks Andesit m2 1.0500 71,500.00 75,075.00
PC ( 50 kg ) zak 0.2350 70,000.00 16,450.00
Pasir Pasang m3 0.3500 150,000.00 52,500.00
Pekerja Orang 0.6200 85,000.00 52,700.00
Tk. Batu Orang 0.3500 100,000.00 35,000.00
Kepala Tukang Batu Orang 0.0350 125,000.00 4,375.00
Mandor Orang 0.0300 150,000.00 4,500.00
Jumlah 240,600.00
Jasa Kontraktor 24,060.00
PPn 10% 26,466.00

35 1 M2 PAS. DINDING BATA BETON BERLUBANG 492,361.85


Bata beton berlubang 390x190x190mm bh 5.5696 8,450.00 47,063.12
Bata beton berlubang 190x190x90mm bh 4.1772 6,500.00 27,151.80
Roster beton 300x90x140mm bh 20.8861 12,000.00 250,633.20
Semen intan perekat bata Zak 0.2500 16,250.00 4,062.50
Pekerja Orang 0.6000 85,000.00 51,000.00
Tukang Batu Orang 0.2000 100,000.00 20,000.00
Kepala Tukang Orang 0.0200 125,000.00 2,500.00
Mandor Orang 0.0300 150,000.00 4,500.00
Jumlah 406,910.62
Jasa Kontraktor 40,691.06
PPn 10% 44,760.17

36 1 M2 PASANG GRANITE LANTAI 60 X 60 Polished 443,595.95


Granite Lantai 60 x 60 bh 2.9167 78,333.33 228,472.22
Semen PC 50 kg kg 8.1900 1,400.00 11,466.00
Pasir Pasang m3 0.0450 150,000.00 6,750.00
Semen Warna Kg 1.6200 9,750.00 15,795.00
Pekerja Orang 0.7000 85,000.00 59,500.00
Tukang Batu Orang 0.3500 100,000.00 35,000.00
Kepala Tukang Batu Orang 0.0350 125,000.00 4,375.00
No. URAIAN SATUAN VOLUME HARGA SATUAN JUMLAH (RP) TOTAL (RP)

Mandor oh Orang 0.0350 150,000.00 5,250.00


Jumlah 366,608.22
Jasa Kontraktor 36,660.82
PPn 10% 40,326.90
No. URAIAN SATUAN VOLUME HARGA SATUAN JUMLAH (RP) TOTAL (RP)

37 1 M2 PASANG GRANITE LANTAI 60 X 60 Unpolished 461,241.78


Granite Lantai 60 x 60 bh 2.9167 83,333.33 243,055.56
Semen PC 50 kg kg 8.1900 1,400.00 11,466.00
Pasir Pasang m3 0.0450 150,000.00 6,750.00
Semen Warna Kg 1.6200 9,750.00 15,795.00
Pekerja Orang 0.7000 85,000.00 59,500.00
Tukang Batu Orang 0.3500 100,000.00 35,000.00
Kepala Tukang Batu Orang 0.0350 125,000.00 4,375.00
Mandor oh Orang 0.0350 150,000.00 5,250.00
Jumlah 381,191.56
Jasa Kontraktor 38,119.16
PPn 10% 41,931.07

38 1 M2 PASANG DINDING KERAMIK 30 X 60 341,220.48


Keramik dinding 30/60, corak warna m2 1.0100 125,000.00 126,250.00
Semen PC 50 kg Zak 0.1860 1,400.00 260.40
Pasir Pasang m3 0.0180 150,000.00 2,700.00
Semen Warna Kg 1.9400 9,750.00 18,915.00
Pekerja Orang 0.9000 85,000.00 76,500.00
Tukang Batu Orang 0.4500 100,000.00 45,000.00
Kepala Tukang Batu Orang 0.0450 125,000.00 5,625.00
Mandor Orang 0.0450 150,000.00 6,750.00
Jumlah 282,000.40
Jasa Kontraktor 28,200.04
PPn 10% 31,020.04

39 1 M2 LANTAI KERAMIK 30 X 30 275,470.05


Keramik dinding 30/30, corak warna, anti slip setara Roman M2 1.0600 95,000.00 100,700.00
Semen PC 50 kg Zak 0.2080 1,400.00 291.20
Pasir Pasang m3 0.0450 150,000.00 6,750.00
Semen Warna Kg 1.6200 9,750.00 15,795.00
Pekerja Orang 0.7000 85,000.00 59,500.00
Tukang Batu Orang 0.3500 100,000.00 35,000.00
Kepala Tukang Batu Orang 0.0350 125,000.00 4,375.00
Mandor Orang 0.0350 150,000.00 5,250.00
Jumlah 227,661.20
Jasa Kontraktor 22,766.12
PPn 10% 25,042.73

40 1 M2 LANTAI PARQUET KAYU 497,436.01


Lantai Parquet Kayu Laminated Uk.10x40 cm M2 1.0500 260,000.00 273,000.00
Lem Kg 0.6000 41,730.00 25,038.00
Alat Bantu lot 0.0300 298,038.00 8,941.14
Pekerja Orang 0.7000 85,000.00 59,500.00
Tukang Kayu Orang 0.3500 100,000.00 35,000.00
Kepala Tukang Kayu Orang 0.0350 125,000.00 4,375.00
Mandor Orang 0.0350 150,000.00 5,250.00
Jumlah 411,104.14
Jasa Kontraktor 41,110.41
PPn 10% 45,221.46

41 1 M1 PLINT LANTAI PARQUET KAYU 163,459.76


Plint Lantai Parquet Kayu M1 1.0600 26,000.00 27,560.00
Lem Kg 0.0600 41,730.00 2,503.80
Alat Bantu lot 0.0300 30,063.80 901.91
Pekerja Orang 0.7000 85,000.00 59,500.00
Tukang Kayu Orang 0.3500 100,000.00 35,000.00
Kepala Tukang Kayu Orang 0.0350 125,000.00 4,375.00
Mandor Orang 0.0350 150,000.00 5,250.00
Jumlah 135,090.71
Jasa Kontraktor 13,509.07
PPn 10% 14,859.98

42 1 M1 STEPNOSING 102,043.33
Stepnosing bh 1.6667 35,000.00 58,333.33
Semen PC 50 kg 2.5000 1,400.00 3,500.00
Pasir Pasang m3 0.0200 150,000.00 3,000.00
Semen Warna Kg 0.1000 9,750.00 975.00
Pekerja Orang 0.0900 85,000.00 7,650.00 ###
Tukang Batu Orang 0.0900 100,000.00 9,000.00
Kepala Tukang Batu Orang 0.0090 125,000.00 1,125.00
Mandor Orang 0.0050 150,000.00 750.00
Jumlah 84,333.33
Jasa Kontraktor 8,433.33
PPn 10% 9,276.67
No. URAIAN SATUAN VOLUME HARGA SATUAN JUMLAH (RP) TOTAL (RP)

43 1 M' PASANG BORDER KERAMIK 10 x 25 cm 259,363.50


Border Keramik 10 x 25 cm bh 4.0000 45,000.00 180,000.00
Semen PC 50kg Kg 2.5000 1,400.00 3,500.00
Pasir Pasang m3 0.0200 150,000.00 3,000.00
Semen warna Kg 0.1000 9,750.00 975.00
Pekerja Orang 0.1000 85,000.00 8,500.00
Tukang Batu Orang 0.1500 100,000.00 15,000.00
Kepala Tukang Orang 0.0150 125,000.00 1,875.00
Mandor Orang 0.0100 150,000.00 1,500.00
Jumlah 214,350.00
Jasa Kontraktor 21,435.00 ###
PPn 10% 23,578.50
###
44 1 M' PASANG PLIN GRANITE TILE POLISHED 10 X 60 cm KW 1 (1PC : 4PS) 58,839.61
###
Plin Keramik 10 x 60 cm Bh 1.8500 13,055.56 24,152.78
Semen PC kg 2.5000 1,400.00 3,500.00
Pasir Pasang m3 0.0200 150,000.00 3,000.00
Semen warna Kg 0.1000 9,750.00 975.00
Pekerja Orang 0.1000 85,000.00 8,500.00
Tukang Batu Orang 0.0500 100,000.00 5,000.00
Kepala Tukang Orang 0.0100 125,000.00 1,250.00
Mandor Orang 0.0150 150,000.00 2,250.00
Jumlah 48,627.78
Jasa Kontraktor 4,862.78
PPn 10% 5,349.06

45 1 M2 FINISHING LANTAI FLOORHARDENER WARNA NATURAL 78,922.25


Floorhardener kg 5.0000 8,000.00 40,000.00
Curing Compound m2 0.1250 5,000.00 625.00
Pekerja Orang 0.1200 85,000.00 10,200.00
Tukang batu Orang 0.1200 100,000.00 12,000.00
Kepala Tukang Orang 0.0120 125,000.00 1,500.00
Mandor Orang 0.0060 150,000.00 900.00
Jumlah 65,225.00
Jasa Kontraktor 6,522.50
PPn 10% 7,174.75

46 1 M2 PENGECATAN PLAPOND BARU 61,896.95


Dempul Tembok (plamuur) kg 0.1000 27,690.00 2,769.00
Cat dasar interior ICI ltr 0.1100 20,800.00 2,288.00
Cat tembok interior ICI ltr 0.2800 54,000.00 15,120.00
Pekerja Orang 0.1040 85,000.00 8,840.00
Tukang Cat Orang 0.1820 100,000.00 18,200.00
Kepala Tukang Cat Orang 0.0195 125,000.00 2,437.50
Mandor Orang 0.0100 150,000.00 1,500.00
Jumlah 51,154.50
Jasa Kontraktor 5,115.45
PPn 10% 5,627.00

47 1 M2 PENGECATAN TEMBOK INTERIOR 60,590.15


Dempul Tembok (plamuur) kg 0,1000 kg 0.1000 27,690.00 2,769.00
Cat dasar Alkali ltr 0.1100 20,800.00 2,288.00
Cat tembok ICI Interior ltr 0.2600 54,000.00 14,040.00
Pekerja Orang 0.1040 85,000.00 8,840.00
Tukang Cat Orang 0.1820 100,000.00 18,200.00
Kepala Tukang Cat Orang 0.0195 125,000.00 2,437.50
Mandor Orang 0.0100 150,000.00 1,500.00
Jumlah 50,074.50
Jasa Kontraktor 5,007.45
PPn 10% 5,508.20

48 1 M2 PENGECATAN TEMBOK / DINDING EKSTERIOR 70,374.21


Dempul Tembok (plamuur) kg 0.1000 27,690.00 2,769.00
Cat dasar eksterior ltr 0.1100 23,400.00 2,574.00
Cat tembok eksterior ICI ltr 0.2600 84,000.00 21,840.00
Pekerja Orang 0.1040 85,000.00 8,840.00
Tukang Cat Orang 0.1820 100,000.00 18,200.00
Kepala Tukang Cat Orang 0.0195 125,000.00 2,437.50
Mandor Orang 0.0100 150,000.00 1,500.00
Jumlah 58,160.50
Jasa Kontraktor 5,816.05
PPn 10% 6,397.66

49 1 M2 PENGECATAN MELAMIK KUSEN, DAUN PINTU, JENDELA DAN BOUWVENLIGHT 242,796.42


Dempul halus / Impra (Wood Filler) kg 0.2800 53,690.00 15,033.20
Wood Stain kg 0.3000 51,350.00 15,405.00
Melamin Sending Siller MSS 123 kg 0.2200 51,350.00 11,297.00
Thinner A Ltr 1.3000 26,260.00 34,138.00
Ampelas lbr 4.0000 3,640.00 14,560.00
Compresor Air 210 m3 / H jam 0.2000 154,375.00 30,875.00
Pekerja Orang 0.4200 85,000.00 35,700.00
Tukang cat Orang 0.3600 100,000.00 36,000.00
Kepala tukang cat Orang 0.0360 125,000.00 4,500.00
Mandor Orang 0.0210 150,000.00 3,150.00
No. URAIAN SATUAN VOLUME HARGA SATUAN JUMLAH (RP) TOTAL (RP)

Jumlah 200,658.20
Jasa Kontraktor 20,065.82
PPn 10% 22,072.40

50 1 M2 PENGECATAN KAYU/BESI 67,654.61


Meni kayu / besi Bola Mas kg 0.2000 19,110.00 3,822.00
Cat kayu / besi Seiv kg 0.2600 49,140.00 12,776.40
Terpentin ( minyak cat) Ltr 0.1500 14,430.00 2,164.50
Pekerja Orang 0.0700 85,000.00 5,950.00
Tukang Cat Orang 0.3000 100,000.00 30,000.00
Kepala Tukang Cat Orang 0.0060 125,000.00 750.00
Mandor oh Orang 0.0030 150,000.00 450.00
Jumlah 55,912.90
Jasa Kontraktor 5,591.29
PPn 10% 6,150.42

51 1 M2 WATERPROOFING COATING 99,135.75


WaterProofing coating Kg 1.5000 51,350.00 77,025.00
Peralatan & Ongkos Pasang ls 0.1500 7,702.50 1,155.38
Ongkos pasang lot 0.1500 25,000.00 3,750.00
Jumlah 81,930.38
Jasa Kontraktor 8,193.04
PPn 10% 9,012.34

52 1 M2 WATERPROOFING MEMBRAN 232,850.59


WaterProofing membran kg 1.1000 169,000.00 185,900.00
Peralatan lbr 0.1500 18,590.00 2,788.50
Ongkos pasang bh 0.1500 25,000.00 3,750.00
Jumlah 192,438.50
Jasa Kontraktor 19,243.85
PPn 10% 21,168.24

53 1 M2 PEK. FLASHING ATAP 117,683.63


Seng plat BJLS 30 lebar 90 cm (1 roll 50 m) m1 1.0000 13,130.00 13,130.00
Paku 4 s/d 7 cm kg 0.0150 20,280.00 304.20
Kayu papan albasiah m3 0.0190 1,235,000.00 23,465.00
Plint coat kg 0.3000 14,950.00 4,485.00
Pekerja Orang 0.1500 85,000.00 12,750.00
Tukang kayu Orang 0.4000 100,000.00 40,000.00
Kepala tukang kayu Orang 0.0250 125,000.00 3,125.00
Jumlah 97,259.20
Jasa Kontraktor 9,725.92
PPn 10% 10,698.51

54 1 M2 PASANG ATAP GELOMBANG PVC 282,580.92


Penutup Atap Gelombang PVC Rooftop M2 1.0500 192,771.08 202,409.64
Assesories Ls 0.0286 48,192.77 1,378.31
Pekerja orang 0.2000 85,000.00 17,000.00
Tukang Kayu orang 0.1000 100,000.00 10,000.00
Kepala Tukang orang 0.0100 125,000.00 1,250.00
Mandor orang 0.0100 150,000.00 1,500.00
Jumlah 233,537.95
Jasa Kontraktor 23,353.80
PPn 10% 25,689.17

55 1 M2 PASANG ATAP METAL SPANDEX 131,933.86


Penutup Atap Gelombang PVC Rooftop Transparan M2 1.0500 75,000.00 78,750.00
Assesories Ls 0.0286 18,750.00 536.25
Pekerja orang 0.2000 85,000.00 17,000.00
Tukang Kayu orang 0.1000 100,000.00 10,000.00
Kepala Tukang orang 0.0100 125,000.00 1,250.00
Mandor orang 0.0100 150,000.00 1,500.00
Jumlah 109,036.25
Jasa Kontraktor 10,903.63
PPn 10% 11,993.99

56 1 M2 PASANG WUWUNGAN PVC 196,669.16


Wuwungan PVC M1 1.2000 110,000.00 132,000.00
Assesories Ls 0.0286 27,500.00 786.50
Pekerja orang 0.2000 85,000.00 17,000.00
Tukang Kayu orang 0.1000 100,000.00 10,000.00
Kepala Tukang orang 0.0100 125,000.00 1,250.00
Mandor orang 0.0100 150,000.00 1,500.00
Jumlah 162,536.50
Jasa Kontraktor 16,253.65
PPn 10% 17,879.02

57 1 M2 PASANG ALUMUNIUM FOIL 54,126.21


Alumunium Foil / Sisalation m2 1.0500 5,000.00 5,250.00
Wiremesh M.5 m2 1.0500 18,959.44 19,907.41
Pekerja orang 0.1500 85,000.00 12,750.00
Tukang Kayu orang 0.0500 100,000.00 5,000.00
No. URAIAN SATUAN VOLUME HARGA SATUAN JUMLAH (RP) TOTAL (RP)

Kepala Tukang Kayu orang 0.0050 125,000.00 625.00


Mandor orang 0.0080 150,000.00 1,200.00
Jumlah 44,732.41
Jasa Kontraktor 4,473.24
PPn 10% 4,920.56
No. URAIAN SATUAN VOLUME HARGA SATUAN JUMLAH (RP) TOTAL (RP)

58 1 M2 PASANGAN PLAFOND GYPSUM BERIKUT RANGKA HOLLOW ZINCROMATE 155,237.08


Gypsum 120 x 240 cm ex DN lbr 0.3640 78,000.00 28,392.00
Hollow 4/4 dizincromate btg 0.4150 71,500.00 29,672.50
Hollow 2/4 dizincromate btg 0.1500 97,500.00 14,625.00
Paku gipsum anti karat (20.00 m2/kg) kg 0.1100 53,690.00 5,905.90
Cotton Plaster Paper m1 0.0720 5,980.00 430.56
Tepung gypsum kg 0.1250 20,280.00 2,535.00
Besi Jaster/Penggantung bh 4.0000 7,500.00 30,000.00
Upah Pasang dan alat lot 0.1500 111,560.96 16,734.14
Jumlah 128,295.10
Jasa Kontraktor 12,829.51
PPn 10% 14,112.46

59 1 M2 PASANGAN PLAFOND GRC BERIKUT RANGKA HOLLOW ZINCROMATE 150,627.87


G R C t=4mm lbr 0.3640 68,900.00 25,079.60
Hollow 2/4 dizincromate btg 0.4150 71,500.00 29,672.50
Hollow 4/4 dizincromate btg 0.1500 97,500.00 14,625.00
Paku gipsum anti karat (20.00 m2/kg) kg 0.1100 53,690.00 5,905.90
Cotton Plaster Paper m1 0.0720 5,980.00 430.56
Tepung gypsum kg 0.1250 20,280.00 2,535.00
Besi Jaster/Penggantung bh 4.0000 7,500.00 30,000.00
Upah Pasang dan alat lot 0.1500 108,248.56 16,237.28
Jumlah 124,485.84
Jasa Kontraktor 12,448.58
PPn 10% 13,693.44

60 1 M2 PASANGAN PLAFOND PVC BERIKUT RANGKA HOLLOW ZINCROMATE 239,244.32


Plafond PVC m2 1.0500 91,000.00 95,550.00
Hollow 2/4 dizincromate btg 0.4150 71,500.00 29,672.50
Hollow 4/4 dizincromate btg 0.1500 97,500.00 14,625.00
Paku /Skrup anti karat (20.00 m2/kg) kg 0.1100 53,690.00 5,905.90
Besi Jaster/Penggantung bh 4.0000 7,500.00 30,000.00
Upah Pasang dan alat lot 0.1250 175,753.40 21,969.18
Jumlah 197,722.57
Jasa Kontraktor 19,772.26
PPn 10% 21,749.48

61 1 M' PASANG LIST PROFIL PLAFOND GYPSUM 34,535.82


List Gypsum 5 cm m1 1.1000 12,000.00 13,200.00
Tepung gypsum kg 0.1500 20,280.00 3,042.00
Pekerja Orang 0.0600 85,000.00 5,100.00
Tukang Kayu Orang 0.0600 100,000.00 6,000.00
Kepala Tukang Kayu Orang 0.0060 125,000.00 750.00
Mandor Orang 0.0030 150,000.00 450.00
Jumlah 28,542.00
Jasa Kontraktor 2,854.20
PPn 10% 3,139.62

62 1 M' PASANG LIST PROFIL PLAFOND PVC 44,981.75


Plafond PVC (setara shunda plafond, LS 301-1 min Silver Metalic m2 1.0000 16,000.00 16,000.00
Skrup buah 18.0000 350.00 6,300.00
Pekerja Orang 0.1000 85,000.00 8,500.00
Tukang Kayu Orang 0.0500 100,000.00 5,000.00
Kepala Tukang Kayu Orang 0.0050 125,000.00 625.00
Mandor Orang 0.0050 150,000.00 750.00
Jumlah 37,175.00
Jasa Kontraktor 3,717.50
PPn 10% 4,089.25

63 1 M2 PAS. DINDING SKAT DOUBLE GYPSUM RANGKA HOLLOW 277,893.27


Hollow 2/4 dizincromate Btg 0.1667 71,500.00 11,919.05
Hollow 4/4 dizincromate Btg 0.1667 97,500.00 16,253.25
Paku anti karat u/ genteng metal (35.00 m2/kg) Kg 0.1000 53,690.00 5,369.00
Lem putih fox Kg 0.5600 41,730.00 23,368.80
Gypsum 120 x 240 cm ex DN lbr 0.6944 78,000.00 54,163.20
Paku gipsum anti karat (20.00 m2/kg) Kg 1.2500 25,000.00 31,250.00
Cotton Plaster Paper m1 0.0720 5,980.00 430.56
Kumpon Kg 0.1250 7,280.00 910.00
Pekerja Orang 0.2000 85,000.00 17,000.00
Tukang kayu Orang 0.6000 100,000.00 60,000.00
Kepala tukang kayu Orang 0.0600 125,000.00 7,500.00
Mandor Orang 0.0100 150,000.00 1,500.00
Jumlah 229,663.86
Jasa Kontraktor 22,966.39
PPn 10% 25,263.02

64 1 M1 PASANG LIST PLANK GRC 71,285.94


GRC lbr 0.1875 68,900.00 12,918.75
Paku 4 s/d 7 cm kg 0.0250 20,280.00 507.00
Pekerja Orang 0.0750 85,000.00 6,375.00
Tukang Kayu Orang 0.2250 100,000.00 22,500.00
Kepala Tukang Kayu Orang 0.0225 125,000.00 2,812.50
Mandor Orang 0.0025 150,000.00 375.00
Peralatan (Scafolding, dll) Lot 1.0000 13,425.75 13,425.75
Jumlah 58,914.00
No. URAIAN SATUAN VOLUME HARGA SATUAN JUMLAH (RP) TOTAL (RP)

Jasa Kontraktor 5,891.40


PPn 10% 6,480.54

65 1 M1 TALANG 1/2 LINGKARAN D-20 cm, SENG PLAT BJLS 50 POWDER COATING 132,535.17
Talang metal galvanize tebal 0,5 mm lebar 45 cm m1 1.0500 35,880.00 37,674.00
Paku 1 s/d 3 cm kg 0.0100 23,920.00 239.20
Besi strip uk, 3 x 30 mm x 6 m kg 0.5000 17,940.00 8,970.00
Finishing powder coating lot 1.0000 14,950.00 14,950.00
Pekerja Orang 0.1500 85,000.00 12,750.00
Tukang Kayu Orang 0.3000 100,000.00 30,000.00
Kepala Tukang Kayu Orang 0.0300 125,000.00 3,750.00
Mandor Orang 0.0080 150,000.00 1,200.00
Jumlah 109,533.20
Jasa Kontraktor 10,953.32
PPn 10% 12,048.65

66 1 M2 PAS. ALUMUNIUM COMPOSITE PANEL 4mm 1,572,292.82


Rangka hollo besi 40 x 60 m1 2.10 42,250.00 88,725.00
Rangka hollo besi 40 x 40 m1 1.10 24,375.00 26,812.50
Braket siku besi 40 x 4 m1 4.00 1,250.00 5,000.00
Brazing set 1.00 45,300.00 45,300.00
Sealen tube 0.25 20,000.00 5,000.00
Sekrup kg 0.30 47,710.00 14,313.00
Braket ACP bh 1.0000 7,500.00 7,500.00
Alluminium Composite Panel 4mm m2 1.0000 975,000.00 975,000.00
Sewa scafolding + bongkar pasang ls 1.0000 15,000.00 15,000.00 TAHUN AN
Upah Pasang ls 1.0000 116,765.05 116,765.05
Jumlah 1,299,415.55
Jasa Kontraktor 129,941.56
PPn 10% 142,935.71
No. URAIAN SATUAN VOLUME HARGA SATUAN JUMLAH (RP) TOTAL (RP)

67 1 M2 PAS. CANOPI KACA 1,472,467.82


Rangka hollo besi 40 x 60 m1 2.10 42,250.00 88,725.00
Rangka hollo besi 40 x 40 m1 1.10 24,375.00 26,812.50
Braket siku besi 40 x 4 m1 4.00 1,250.00 5,000.00
Brazing set 1.00 45,300.00 45,300.00
Sealen tube 0.25 20,000.00 5,000.00
Sekrup kg 0.30 47,710.00 14,313.00
Braket bh 1.0000 7,500.00 7,500.00
Kaca Laminated 10mm m2 1.0000 900,000.00 900,000.00
Sewa scafolding + bongkar pasang ls 1.0000 15,000.00 15,000.00 TAHUN AN
Upah Pasang ls 1.0000 109,265.05 109,265.05
Jumlah 1,216,915.55
Jasa Kontraktor 121,691.56
PPn 10% 133,860.71

68 1 TTK PAS. INSTALASI PENERANGAN 293,322.15


Kabel listrik NYM 2 x 1,5 mm m1 12.0000 9,945.00 119,340.00
condoit dia 20 mm( 3/4 inch ) m1 12.0000 1,852.50 22,230.00
Saklar lampu bh 1.0000 33,345.00 33,345.00
Tukang Listrik Orang 0.2500 100,000.00 25,000.00
Pekerja Orang 0.5000 85,000.00 42,500.00
Jumlah 242,415.00
Jasa Kontraktor 24,241.50
PPn 10% 26,665.65

69 1 TTK PAS. INSTALASI STOP KONTAK 362,612.80


Kabel listrik NYM 3 x 2,5 mm m1 12.0000 14,202.50 170,430.00
condoit dia 20 mm( 3/4 inch ) m1 12.0000 1,852.50 22,230.00
Stop kontak bh 1.0000 39,520.00 39,520.00
Tukang Listrik Orang 0.2500 100,000.00 25,000.00
Pekerja Orang 0.5000 85,000.00 42,500.00
Jumlah 299,680.00
Jasa Kontraktor 29,968.00
PPn 10% 32,964.80

70 1 TTK PAS. ARMATURE BALK 1x36 277,392.50


Armature Balk, TLD 1x36 W, Philips set 1.0000 175,000.00 175,000.00
Peralatan bantu ls 1.0000 17,500.00 17,500.00
Pekerja Orang 0.1500 85,000.00 12,750.00
Tukang Orang 0.2000 100,000.00 20,000.00
Kepala Tukang Orang 0.0200 125,000.00 2,500.00
Mandor Orang 0.0100 150,000.00 1,500.00
Jumlah 229,250.00
Jasa Kontraktor 22,925.00
PPn 10% 25,217.50

71 1 TTK PAS. INSTALASI KABEL DATA 327,099.30


Kabel UTP cat 5e per 15 meter + jack RJ45 bh 1.0000 37,667.50 37,667.50
condoit dia 20 mm( 3/4 inch ) m1 15.0000 1,852.50 27,787.50
Wall Outlet LAN bh 1.0000 154,375.00 154,375.00
Tukang Listrik Orang 0.2500 100,000.00 25,000.00
Pekerja Orang 0.3000 85,000.00 25,500.00
Jumlah 270,330.00
Jasa Kontraktor 27,033.00
PPn 10% 29,736.30

72 1 BH PAS. CLOSET JONGKOK 898,606.50


Kloset jongkok bh 1.0000 455,000.00 455,000.00
Semen PC 50 kg zak 0.1200 70,000.00 8,400.00
Pasir pasang m3 0.0100 150,000.00 1,500.00
Pekerja Orang 1.0000 85,000.00 85,000.00
Tukang batu Orang 1.5000 100,000.00 150,000.00
Kepala tukang batu Orang 0.1500 125,000.00 18,750.00
Mandor Orang 0.1600 150,000.00 24,000.00
Jumlah 742,650.00
Jasa Kontraktor 74,265.00
PPn 10% 81,691.50

73 1 BH PAS. CLOSET DUDUK 2,836,028.25


Kloset duduk lengkap bh 1.0000 1,820,000.00 1,820,000.00
Perlengkapan 6 % harga closet set 0.0600 1,820,000.00 109,200.00
Pekerja Orang 3.3000 85,000.00 280,500.00
Tukang batu Orang 1.1000 100,000.00 110,000.00
Kepala tukang batu Orang 0.0010 125,000.00 125.00
Mandor Orang 0.1600 150,000.00 24,000.00
Jumlah 2,343,825.00
Jasa Kontraktor 234,382.50
PPn 10% 257,820.75

74 1 BH MEMASANG WASTAFEL 2,553,886.50


Wastafel lengkap bh 1.0000 1,625,000.00 1,625,000.00
No. URAIAN SATUAN VOLUME HARGA SATUAN JUMLAH (RP) TOTAL (RP)

Perlengkapan 12% harga wastafel set 0.1200 1,625,000.00 195,000.00


Semen PC 50 kg zak 0.1200 70,000.00 8,400.00
Pasir pasang m3 0.0100 150,000.00 1,500.00 ###
Pekerja Orang 1.2000 85,000.00 102,000.00
Tukang batu Orang 1.4500 100,000.00 145,000.00
Kepala tukang batu Orang 0.1500 125,000.00 18,750.00
Mandor Orang 0.1000 150,000.00 15,000.00
Jumlah 2,110,650.00
Jasa Kontraktor 211,065.00
PPn 10% 232,171.50

75 1 BH MEMASANG URINOIR 3,884,100.00


Urinoir lengkap bh 1.0000 2,275,000.00 2,275,000.00
Perlengkapan 30% harga urinoir set 0.3000 2,275,000.00 682,500.00
Pekerja Orang 1.0000 125,000.00 125,000.00
Tukang batu Orang 1.0000 100,000.00 100,000.00
Kepala tukang batu Orang 0.1000 125,000.00 12,500.00
Mandor Orang 0.1000 150,000.00 15,000.00
Jumlah 3,210,000.00
Jasa Kontraktor 321,000.00
PPn 10% 353,100.00

76 1 BH BAK CUCI PIRING STAINLESS-STEEL 735,680.00


Kitchen zink stainless standard 1 lobang bh 1.0000 568,750.00 568,750.00
Water drain + asesories set 1.0000 10,000.00 10,000.00
Tukang batu Orang 0.3000 85,000.00 25,500.00
Kepala tukang batu Orang 0.0300 125,000.00 3,750.00
Jumlah 608,000.00
Jasa Kontraktor 60,800.00
PPn 10% 66,880.00
No. URAIAN SATUAN VOLUME HARGA SATUAN JUMLAH (RP) TOTAL (RP)

77 1 M2 MEMASANG CERMIN WASTAFEL 148,527.50


Cermin wastafel m2 0.3500 195,000.00 68,250.00
Pekerja Orang 0.5000 85,000.00 42,500.00
Tukang batu Orang 0.1000 100,000.00 10,000.00
Kepala tukang batu Orang 0.0100 125,000.00 1,250.00 ###
Mandor Orang 0.0050 150,000.00 750.00
Jumlah 122,750.00
Jasa Kontraktor 12,275.00
PPn 10% 13,502.50

78 1 BH MEMASANG KRAN Ø 1/2" ATAU Ø 3/4" 110,896.50


Kran tembok dia. 1/2" bh 1.0000 80,275.00 80,275.00
Seal tape set set 0.0250 5,000.00 125.00
Tukang batu Orang 0.1000 100,000.00 10,000.00
Kepala tukang batu Orang 0.0100 125,000.00 1,250.00
Jumlah 91,650.00
Jasa Kontraktor 9,165.00
PPn 10% 10,081.50

79 1 BH MEMASANG KRAN WASTAFEL 275,275.00


Kran air untuk wastafel bh 1.0000 216,125.00 216,125.00
Seal tape set set 0.0250 5,000.00 125.00
Tukang batu Orang 0.1000 100,000.00 10,000.00
Kepala tukang batu Orang 0.0100 125,000.00 1,250.00
Jumlah 227,500.00
Jasa Kontraktor 22,750.00
PPn 10% 25,025.00

80 1 BH MEMASANG KRAN LEHER ANGSA SET. SUN EI 407,013.75


Kran air leher angsa dia. 1/2" bh 1.0000 325,000.00 325,000.00
Seal tape set set 0.0250 5,000.00 125.00
Tukang batu Orang 0.1000 100,000.00 10,000.00
Kepala tukang batu Orang 0.0100 125,000.00 1,250.00
Jumlah 336,375.00
Jasa Kontraktor 33,637.50
PPn 10% 37,001.25

81 1 BH MEMASANG 1 BUAH JET WASHER 369,624.75


Jet washer bh 1.0000 292,500.00 292,500.00
Seal tape set set 0.0250 5,000.00 125.00
Pekerja Orang 0.0100 85,000.00 850.00 ###
Tukang batu Orang 0.1000 100,000.00 10,000.00
Kepala tukang batu Orang 0.0100 125,000.00 1,250.00
Mandor Orang 0.0050 150,000.00 750.00
Jumlah 305,475.00
Jasa Kontraktor 30,547.50
PPn 10% 33,602.25

82 1 BH MEMASANG HANDSHOWER KOMBINASI KRAN 1,528,199.75


Handshower kombinasi kran bh 1.0000 1,250,000.00 1,250,000.00
Seal tape set set 0.0250 5,000.00 125.00
Pekerja Orang 0.0100 85,000.00 850.00 ###
Tukang batu Orang 0.1000 100,000.00 10,000.00
Kepala tukang batu Orang 0.0100 125,000.00 1,250.00
Mandor Orang 0.0050 150,000.00 750.00
Jumlah 1,262,975.00
Jasa Kontraktor 126,297.50
PPn 10% 138,927.25

83 1 BH MEMASANG 1 BUAH FLOOR DRAIN 210,237.50


Floor drain bh 1.0000 162,500.00 162,500.00
Tukang batu Orang 0.1000 100,000.00 10,000.00
Kepala tukang batu Orang 0.0100 125,000.00 1,250.00
Jumlah 173,750.00
Jasa Kontraktor 17,375.00
PPn 10% 19,112.50

84 1 M1 MEMASANG 1 METER PIPA PVC TIPE AW Ø 1/2" 25,539.47


Pipa pralon PVC. (AW) dia. 1/2 inch, sekualitas btg Maspion btg 0.3000 25,090.00 7,527.00
Perlengkapan set 0.3500 10,000.00 3,500.00
Pekerja Orang 0.0360 85,000.00 3,060.00 ###
Tukang batu Orang 0.0600 100,000.00 6,000.00
Kepala tukang batu Orang 0.0060 125,000.00 750.00
Mandor Orang 0.0018 150,000.00 270.00
Jumlah 21,107.00
Jasa Kontraktor 2,110.70
PPn 10% 2,321.77

85 1 M1 MEMASANG 1 METER PIPA PVC TIPE AW Ø 3/4" 28,559.63


Pipa pralon PVC. (AW) dia. 3/4 inch, sekualitas btg Maspion btg 0.3000 33,410.00 10,023.00
Perlengkapan set 0.3500 10,000.00 3,500.00
Pekerja Orang 0.0360 85,000.00 3,060.00 ###
Tukang batu Orang 0.0600 100,000.00 6,000.00
Kepala tukang batu Orang 0.0060 125,000.00 750.00
Mandor Orang 0.0018 150,000.00 270.00
No. URAIAN SATUAN VOLUME HARGA SATUAN JUMLAH (RP) TOTAL (RP)

Jumlah 23,603.00
Jasa Kontraktor 2,360.30
PPn 10% 2,596.33
No. URAIAN SATUAN VOLUME HARGA SATUAN JUMLAH (RP) TOTAL (RP)

86 1 M1 MEMASANG 1 METER PIPA PVC TIPE AW Ø 1" 32,051.69


Pipa pralon PVC. (AW) dia. 1 inch, sekualitas btg Maspion btg 0.3000 43,030.00 12,909.00
Perlengkapan set 0.3500 10,000.00 3,500.00
Pekerja Orang 0.0360 85,000.00 3,060.00 ###
Tukang batu Orang 0.0600 100,000.00 6,000.00
Kepala tukang batu Orang 0.0060 125,000.00 750.00
Mandor Orang 0.0018 150,000.00 270.00
Jumlah 26,489.00
Jasa Kontraktor 2,648.90
PPn 10% 2,913.79

87 1 M1 MEMASANG 1 METER PIPA PVC TIPE AW Ø 1 1/2" 37,242.59


Pipa pralon PVC. (AW) dia. 1 1/2 inch, sekualitas btg Maspion btg 0.3000 57,330.00 17,199.00
Perlengkapan set 0.3500 10,000.00 3,500.00
Pekerja Orang 0.0360 85,000.00 3,060.00 ###
Tukang batu Orang 0.0600 100,000.00 6,000.00
Kepala tukang batu Orang 0.0060 125,000.00 750.00
Mandor Orang 0.0018 150,000.00 270.00
Jumlah 30,779.00
Jasa Kontraktor 3,077.90
PPn 10% 3,385.69

88 1 M1 MEMASANG 1 METER PIPA PVC TIPE AW Ø 2" 51,069.26


Pipa pralon PVC. (AW) dia 2 inch, sekualitas btg Maspion btg 0.3000 95,420.00 28,626.00
Perlengkapan set 0.3500 10,000.00 3,500.00
Pekerja Orang 0.0360 85,000.00 3,060.00 ###
Tukang batu Orang 0.0600 100,000.00 6,000.00
Kepala tukang batu Orang 0.0060 125,000.00 750.00
Mandor Orang 0.0018 150,000.00 270.00
Jumlah 42,206.00
Jasa Kontraktor 4,220.60
PPn 10% 4,642.66

89 1 M1 MEMASANG 1 METER PIPA PVC TIPE AW Ø 3" 100,701.04


Pipa pralon PVC. (AW) dia. 3 inch, sekualitas btg Maspion btg 0.3000 220,480.00 66,144.00
Perlengkapan set 0.3500 20,000.00 7,000.00
Pekerja Orang 0.0360 85,000.00 3,060.00 ###
Tukang batu Orang 0.0600 100,000.00 6,000.00
Kepala tukang batu Orang 0.0060 125,000.00 750.00
Mandor Orang 0.0018 150,000.00 270.00
Jumlah 83,224.00
Jasa Kontraktor 8,322.40
PPn 10% 9,154.64

90 1 M1 MEMASANG 1 METER PIPA PVC TIPE AW Ø4" 133,167.76


Pipa pralon PVC. (AW) dia. 4 inch, sekualitas btg Maspion btg 0.3000 309,920.00 92,976.00
Perlengkapan set 0.3500 20,000.00 7,000.00
Pekerja Orang 0.0360 85,000.00 3,060.00 ###
Tukang batu Orang 0.0600 100,000.00 6,000.00
Kepala tukang batu Orang 0.0060 125,000.00 750.00
Mandor Orang 0.0018 150,000.00 270.00
Jumlah 110,056.00
Jasa Kontraktor 11,005.60
PPn 10% 12,106.16

91 1 M1 MEMASANG 1 METER PIPA PVC TIPE AW Ø6" 227,123.05


Pipa pralon PVC. (AW) dia. 6 inch, sekualitas btg Maspion btg 0.3000 568,750.00 170,625.00
Perlengkapan set 0.3500 20,000.00 7,000.00
Pekerja Orang 0.0360 85,000.00 3,060.00 ###
Tukang batu Orang 0.0600 100,000.00 6,000.00
Kepala tukang batu Orang 0.0060 125,000.00 750.00
Mandor Orang 0.0018 150,000.00 270.00
Jumlah 187,705.00
Jasa Kontraktor 18,770.50
PPn 10% 20,647.55

92 1 UNIT MEMASANG BAK KONTROL PAS. BATU BATA 45 X 45 T. 50 CM 339,006.91


Bata merah bakar kelas I bh 122.5000 750.00 91,875.00
Semen PC 50 kg Zak 1.5400 70,000.00 107,800.00
Pasir pasang m3 0.1300 150,000.00 19,500.00
Batu pecah mesin 1 : 2 m3 0.0200 212,000.00 4,240.00
Besi baja beton kg 2.6000 14,560.00 37,856.00
Pasir beton I/kasar m3 0.0900 210,000.00 18,900.00
Pekerja Orang 1.4200 85,000.00 120,700.00
Tukang batu Orang 0.4730 100,000.00 47,300.00
Kepala tukang batu Orang 0.0470 125,000.00 5,875.00
Mandor Orang 0.0700 150,000.00 10,500.00
Jumlah 280,171.00
Jasa Kontraktor 28,017.10
PPn 10% 30,818.81

93 1 M' PASANG SALURAN GRAVEL U - 20 CM 208,219.60


Galian Tanah m3 0.2700 81,675.00 22,052.25
Urugan pasir m3 0.0500 172,062.00 8,603.10
Grevel U - 20 cm bh 1.1000 39,000.00 42,900.00
No. URAIAN SATUAN VOLUME HARGA SATUAN JUMLAH (RP) TOTAL (RP)

Pas. 1/2 Bata 1 : 3 m3 0.5000 135,280.42 67,640.21


Plesteran + Acian 1 : 3 m2 0.8000 64,923.76 51,939.01
Alat bantu Ls 1.0000 1,000.00 1,000.00
Jumlah 172,082.32
Jasa Kontraktor 17,208.23
PPn 10% 18,929.05
No. URAIAN SATUAN VOLUME HARGA SATUAN JUMLAH (RP) TOTAL (RP)

94 1 M' MEMASANG BUIS BETON DIA. 30 CM - 100 CM 266,460.15


Buis beton dia. 30 cm - 100 cm bh 1.1000 184,730.00 203,203.00
Semen PC 50 kg zak 0.0174 70,000.00 1,218.00
Pasir pasang m3 0.0140 150,000.00 2,100.00
Pasir urug m3 0.0140 96,000.00 1,344.00
Pekerja Orang 0.0800 85,000.00 6,800.00
Tukang batu Orang 0.0400 100,000.00 4,000.00
Kepala tukang batu Orang 0.0040 125,000.00 500.00
Mandor Orang 0.0070 150,000.00 1,050.00
Jumlah 220,215.00
Jasa Kontraktor 22,021.50
PPn 10% 24,223.65

95 1 M2 PASANG BATA ROOSTER 511,052.94


Rooster uk. 150 x 200 mm bh 34.0000 12,000.00 408,000.00
Spesi 1Pc : 2Ps
- Semen Portland zak 0.3270 1,400.00 457.80
- Pasir Pasang m³ 0.0260 150,000.00 3,900.00
Sealant m' 0.1500 25,000.00 3,750.00
Upah pasang ls 0.2500 25,000.00 6,250.00
Jumlah 422,357.80
Jasa Kontraktor 42,235.78
PPn 10% 46,459.36

96 1 M3 URUGAN TANAH SUBUR 267,652.00


Tanah subur/gembur m³ 1.2000 120,000.00 144,000.00
Pekerja org 0.8200 85,000.00 69,700.00
Mandor org 0.0500 150,000.00 7,500.00
Jumlah 221,200.00
Jasa Kontraktor 22,120.00
PPn 10% 24,332.00

97 1 M2 RUMPUT GAJAH MINI 51,909.00


Rumput Gajah Mini Lempengan m² 1.0000 35,000.00 35,000.00
Pekerja org 0.0400 85,000.00 3,400.00
Tukang tanam org 0.0300 100,000.00 3,000.00
Mandor org 0.0100 150,000.00 1,500.00
Jumlah 42,900.00
Jasa Kontraktor 4,290.00
PPn 10% 4,719.00

98 1 PLBG MENANAM TANAMAN SOKA HAWAII T=30 CM 19,167.00


Tanaman Soka Hawaii t=30 cm polibag 1.0000 15,000.00 15,000.00
Pekerja org 0.0033 85,000.00 280.50
Tukang tanam org 0.0044 100,000.00 440.00
Mandor org 0.0008 150,000.00 120.00
Jumlah 15,840.50
Jasa Kontraktor 1,584.05
PPn 10% 1,742.46

99 1 PLBG MENANAM TANAMAN PLUMBAGO UNGU 11,984.45


Plumbago pol Ø 20 cm polibag 1.0000 9,500.00 9,500.00
Pekerja org 0.0017 85,000.00 144.50
Tukang tanam org 0.0020 100,000.00 200.00
Mandor org 0.0004 150,000.00 60.00
Jumlah 9,904.50
Jasa Kontraktor 990.45
PPn 10% 1,089.50

100 1 PLBG MENANAM TANAMAN HUJAN MAS 13,117.01


Hujan Mas pol Ø 20 cm polibag 1.0000 10,000.00 10,000.00
Pekerja org 0.0033 85,000.00 280.50
Tukang tanam org 0.0044 100,000.00 440.00
Mandor org 0.0008 150,000.00 120.00
Jumlah 10,840.50
Jasa Kontraktor 1,084.05
PPn 10% 1,192.46

101 1 BTG MENANAM POHON KATAPANG ANGSANA T=3 M, Ø BTG 7 cm 378,306.50


Katapang Angsana t. 3 m Ø btg 7 cm Btg 1.0000 300,000.00 300,000.00
Pekerja org 0.0500 85,000.00 4,250.00
Tukang tanam org 0.0600 100,000.00 6,000.00
Mandor org 0.0160 150,000.00 2,400.00
Jumlah 312,650.00
Jasa Kontraktor 31,265.00
PPn 10% 34,391.50

102 1 BTG MENANAM PALEM EKOR TUPAI T. 3 M 559,806.50


Palem Ekor Tupai t. 3 m Btg 1.0000 450,000.00 450,000.00
Pekerja org 0.0500 85,000.00 4,250.00
Tukang tanam org 0.0600 100,000.00 6,000.00
Mandor org 0.0160 150,000.00 2,400.00
Jumlah 462,650.00
Jasa Kontraktor 46,265.00
No. URAIAN SATUAN VOLUME HARGA SATUAN JUMLAH (RP) TOTAL (RP)

PPn 10% 50,891.50

1M PASANG GRILL SALURAN #REF!


Besi Unp 50 x 50 x 5 kg 16.3333 #REF! #REF!
Besi Unp 100 x 50 x 5 kg 7.0250 #REF! #REF!
Upah Pengelasan cm 35.0000 1,500.00 52,500.00
Alat Bantu lot 0.0500 3,500.00 175.00
Upah Pasang+Stel+Pabrikasi lot 0.1000 25,000.00 2,500.00
Jumlah #REF!
Jasa Kontraktor #REF!
ANALISA HARGA PEKERJAAN KUSEN & PARTISI
PEMBANGUNAN GEDUNG KANTOR RAJAMANDALA ELECTRIC POWER
TAHUN ANGGARAN 2018

No. URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH (Rp) TOTAL (Rp)

1 1 BH PINTU KACA FRAME ALUMINIUM 965,951.71


Frame kayu daun pintu m3 5.8800 65,650.00 386,022.00
Kaca 10mm m2 0.9360 230,000.00 215,280.00
Aksesories lot 1.0000 60,130.20 60,130.20
Pekerja oh 0.7500 85,000.00 63,750.00
Tukang Kayu oh 0.6000 100,000.00 60,000.00
Kepala Tukang kayu oh 0.0600 125,000.00 7,500.00
Mandor oh 0.0375 150,000.00 5,625.00
Jumlah 798,307.20
Jasa Kontraktor 79,830.72
PPn 10% 87,813.79
2 1 BH PINTU PANIL DOUBLE MULTIPLEK LAPIS HPL 963,895.68
kayu papan m3 0.0188 11,050,000.00 207,187.50
Multiplek 6mm lbr 1.2250 104,000.00 127,400.00
HPL lbr 1.2250 250,000.00 306,250.00
Paku 4 s/d 7 cm Kg 0.0500 20,280.00 1,014.00
Lem Putih Fox Kg 0.2500 41,730.00 10,432.50
Aksesories lot 0.0500 148,980.00 7,449.00
Pekerja oh 0.7500 85,000.00 63,750.00
Tukang Kayu oh 0.6000 100,000.00 60,000.00
Kepala Tukang kayu oh 0.0600 125,000.00 7,500.00
Mandor oh 0.0375 150,000.00 5,625.00
Jumlah 796,608.00
Jasa Kontraktor 79,660.80
PPn 10% 87,626.88
3 1 BH PINTU SPANDRIL 1,025,867.04
SPANDREL m2 6.7000 105,000.00 703,500.00
Aksesories lot 0.0500 148,980.00 7,449.00
Pekerja oh 0.7500 85,000.00 63,750.00
Tukang Besi Fropil/Tukang Las oh 0.6000 100,000.00 60,000.00
Kepala Tukang Besi Profil oh 0.0600 125,000.00 7,500.00
Mandor oh 0.0375 150,000.00 5,625.00
Jumlah 847,824.00
Jasa Kontraktor 84,782.40
PPn 10% 93,260.64
4 1 BH JENDELA FRAME ALUMUNIUM 258,040.37
Frame Alumunium daun jendela m' 1.0500 65,650.00 68,932.50
Aksesories lot 0.0500 148,980.00 7,449.00
Pekerja oh 0.7500 85,000.00 63,750.00
Tukang Kayu oh 0.6000 100,000.00 60,000.00
Kepala Tukang kayu oh 0.0600 125,000.00 7,500.00
Mandor oh 0.0375 150,000.00 5,625.00
Jumlah 213,256.50
Jasa Kontraktor 21,325.65
PPn 10% 23,458.22
5 1M2 TEAKWOOD 6 MM 223,160.66
Teakwood 6 mm, uk. 1,20 x 2,40 Lbr 0.3472 104,000.00 36,108.80
Paku 4 s/d 7 cm Kg 0.0500 20,280.00 1,014.00
Lem Putih Fox Kg 0.2500 41,730.00 10,432.50
Pekerja oh 0.7500 85,000.00 63,750.00
Tukang Besi Fropil/Tukang Las oh 0.6000 100,000.00 60,000.00
Kepala Tukang Besi Profil oh 0.0600 125,000.00 7,500.00
Mandor oh 0.0375 150,000.00 5,625.00
Jumlah 184,430.30
Jasa Kontraktor 18,443.03
No. URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH (Rp) TOTAL (Rp)

PPn 10% 20,287.33


No. URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH (Rp) TOTAL (Rp)

6 1M2 PAS. FORMIKA 206,566.24


Formika Putih Polos, uk. 1,20 x 2,40 Lbr 0.3472 64,500.00 22,394.40
Paku 4 s/d 7 cm Kg 0.0500 20,280.00 1,014.00
Lem Putih Fox Kg 0.2500 41,730.00 10,432.50
Pekerja oh 0.7500 85,000.00 63,750.00
Tukang Besi Fropil/Tukang Las oh 0.6000 100,000.00 60,000.00
Kepala Tukang Besi Profil oh 0.0600 125,000.00 7,500.00
Mandor oh 0.0375 150,000.00 5,625.00
Jumlah 170,715.90
Jasa Kontraktor 17,071.59
PPn 10% 18,778.75
7 1M1 PASANG KUSEN ALUMUNIUM 4" (WARNA) 163,513.35
Alumunium profil uk.4inch 4.00m (bahan kusen) brown btg 1.1000 117,000.00 128,700.00
Accecories dan Ongkos pasang Lot 0.0500 128,700.00 6,435.00
Jumlah 135,135.00
Jasa Kontraktor 13,513.50
PPn 10% 14,864.85
8 1M3 PASANG KUSEN KAYU KELAS II (OVEN) 15,442,927.50
Kusen Kayu kelas II (Oven) m3 1.1000 11,050,000.00 12,155,000.00
Accecories dan Ongkos pasang Lot 0.0500 12,155,000.00 607,750.00
Jumlah 12,762,750.00
Jasa Kontraktor 1,276,275.00
PPn 10% 1,403,902.50
9 1M2 PASANG KACA POLOS 5 MM 121,205.70
Kaca Polos 5 mm m2 1.0500 78,000.00 81,900.00
Pekerja oh 0.0150 85,000.00 1,275.00
Tukang Besi Fropil/Tukang Las oh 0.1500 100,000.00 15,000.00
Kepala Tukang Besi Profil oh 0.0150 125,000.00 1,875.00
Mandor oh 0.0008 150,000.00 120.00
Jumlah 100,170.00
Jasa Kontraktor 10,017.00
PPn 10% 11,018.70
10 1M2 PASANG KACA POLOS 8 MM 228,562.95
Kaca Polos 8 mm m2 1.0500 162,500.00 170,625.00
Pekerja oh 0.0150 85,000.00 1,275.00
Tukang Besi Fropil/Tukang Las oh 0.1500 100,000.00 15,000.00
Kepala Tukang Besi Profil oh 0.0150 125,000.00 1,875.00
Mandor oh 0.0008 150,000.00 120.00
Jumlah 188,895.00
Jasa Kontraktor 18,889.50
PPn 10% 20,778.45
11 1M2 PASANG KACA POLOS 10 MM 314,321.70
Kaca Polos 10 mm m2 1.0500 230,000.00 241,500.00
Pekerja oh 0.0150 85,000.00 1,275.00
Tukang Besi Fropil/Tukang Las oh 0.1500 100,000.00 15,000.00
Kepala Tukang Besi Profil oh 0.0150 125,000.00 1,875.00
Mandor oh 0.0008 150,000.00 120.00
Jumlah 259,770.00
Jasa Kontraktor 25,977.00
PPn 10% 28,574.70
12 1M2 PASANG KACA TEMPERED 12 MM 733,586.70
Kaca Tempered 12 mm m2 1.0500 460,000.00 483,000.00
Sticker Sunblast m2 1.0500 100,000.00 105,000.00
Pekerja oh 0.0150 85,000.00 1,275.00
Tukang Besi Fropil/Tukang Las oh 0.1500 100,000.00 15,000.00
Kepala Tukang Besi Profil oh 0.0150 125,000.00 1,875.00
Mandor oh 0.0008 150,000.00 120.00
Jumlah 606,270.00
Jasa Kontraktor 60,627.00
PPn 10% 66,689.70
13 1BH PASANG ENGSEL PINTU 87,071.60
No. URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH (Rp) TOTAL (Rp)

Engsel Pintu psng 1.0000 53,690.00 53,690.00


Pekerja oh 0.0150 85,000.00 1,275.00
Tukang Besi Fropil/Tukang Las oh 0.1500 100,000.00 15,000.00
Kepala Tukang Besi Profil oh 0.0150 125,000.00 1,875.00
Mandor oh 0.0008 150,000.00 120.00
Jumlah 71,960.00
Jasa Kontraktor 7,196.00
PPn 10% 7,915.60
14 1BH PASANG ENGSEL JENDELA 65,981.30
Engsel Jendela psng 1.0000 41,730.00 41,730.00
Pekerja oh 0.0100 85,000.00 850.00
Tukang Besi Fropil/Tukang Las oh 0.1000 100,000.00 10,000.00
Kepala Tukang Besi Profil oh 0.0150 125,000.00 1,875.00
Mandor oh 0.0005 150,000.00 75.00
Jumlah 54,530.00
Jasa Kontraktor 5,453.00
PPn 10% 5,998.30
No. URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH (Rp) TOTAL (Rp)

15 1BH PASANG KUNCI SLOT 76,810.80


Grendel Jendela bh 1.0000 39,130.00 39,130.00
Pekerja oh 0.0200 85,000.00 1,700.00
Tukang Besi Fropil/Tukang Las oh 0.2000 100,000.00 20,000.00
Kepala Tukang Besi Profil oh 0.0200 125,000.00 2,500.00
Mandor oh 0.0010 150,000.00 150.00
Jumlah 63,480.00
Jasa Kontraktor 6,348.00
PPn 10% 6,982.80
16 1BH PASANG ENGSEL JENDELA CASEMENT 81,675.00
Hak Angin Casement bh 1.0000 50,000.00 50,000.00
Assesories dan Ongkos Pasang lot 0.3500 50,000.00 17,500.00
Jumlah 67,500.00
Jasa Kontraktor 6,750.00
PPn 10% 7,425.00
17 1 SET PASANG LEVER HANDLE, LOCKCASE DAN CYLINDER KUNCI PINTU 1,541,189.10
Pull Handle bh 1.0000 750,000.00 750,000.00
Lever Handle bh 1.0000 172,900.00 172,900.00
Lockcase bh 1.0000 148,980.00 148,980.00
Cylinder bh 1.0000 148,980.00 148,980.00
Pekerja oh 0.0100 85,000.00 850.00
Tukang Besi Fropil/Tukang Las oh 0.5000 100,000.00 50,000.00
Kepala Tukang Besi Profil oh 0.0100 125,000.00 1,250.00
Mandor oh 0.0050 150,000.00 750.00
Jumlah 1,273,710.00
Jasa Kontraktor 127,371.00
PPn 10% 140,108.10
18 1 BH PASANG DOOR CLOSER 648,499.50
Door Closer set 1.0000 475,000.00 475,000.00
Pekerja oh 0.0500 85,000.00 4,250.00
Tukang Besi Fropil/Tukang Las/Tukang kayu oh 0.5000 100,000.00 50,000.00
Kepala Tukang Besi Profil/Tukang kayu oh 0.0500 125,000.00 6,250.00
Mandor oh 0.0030 150,000.00 450.00
Jumlah 535,950.00
Jasa Kontraktor 53,595.00
PPn 10% 58,954.50
19 1 BH PASANG FLOOR HINGE 3,176,250.00
Engsel Pintu (floor Hinge), Ex Dorma, Uk. Pintu Standar bh 1.0000 1,750,000.00 1,750,000.00
Assesories (Fixed top pin, top patch fitting, bottom patch fiting, lot 0.1500 1,750,000.00 262,500.00
bottom lock fiting) 0.00
Assesories dan Ongkos Pasang lot 0.3500 1,750,000.00 612,500.00
Jumlah 2,625,000.00
Jasa Kontraktor 262,500.00
PPn 10% 288,750.00
No. URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH (Rp) TOTAL (Rp)

20 1 UNIT PINTU BESI TYPE PB 24,234,000.00


Kusen Baja + Daun Pintu Double Plat Besi Rangka Baja bh 1.0000 22,080,000.00 22,080,000.00
Aksesories (rel pintu, kunci, handle, dll) set 1.0000 1,000,000.00 1,000,000.00
Ongkos Pasang lot 0.0500 23,080,000.00 1,154,000.00
Jumlah 24,234,000.00
21 1 UNIT PINTU TYPE P1 7,053,281.74
Kusen Alumunium 4 " (warna) m' 5.6500 163,513.35 923,850.43
Daun Pintu Kaca 10mm Frame Aluminium bh 2.0000 965,951.71 1,931,903.42
Pull Handle, Lever handle, Lockcase dan cylinder kunci pintu set 2.0000 1,541,189.10 3,082,378.20
Engsel Pintu psg 3.0000 87,071.60 261,214.80
Door Closer bh 1.0000 648,499.50 648,499.50
Ongkos Pasang lot 0.0300 6,847,846.35 205,435.39
Jumlah 7,053,281.74
22 1 UNIT PINTU TYPE P2 4,258,494.93
Kusen Alumunium 4 " (warna) m' 5.2000 163,513.35 850,269.42
Daun Pintu Panil Kayu bh 1.0000 963,895.68 963,895.68
Pull Handle, Lever handle, Lockcase dan cylinder kunci pintu set 1.0000 1,541,189.10 1,541,189.10
Engsel Pintu psg 1.5000 87,071.60 130,607.40
Door Closer bh 1.0000 648,499.50 648,499.50
Ongkos Pasang lot 0.0300 4,134,461.10 124,033.83
Jumlah 4,258,494.93
23 1 UNIT PINTU TYPE P3 3,893,694.11
Kusen Alumunium 4 " (warna) m' 5.2000 163,513.35 850,269.42
Daun Pintu Kaca Frame Kayu bh 1.0000 965,951.71 965,951.71
Pull Handle, Lever handle, Lockcase dan cylinder kunci pintu set 1.0000 1,541,189.10 1,541,189.10
Engsel Pintu psg 1.5000 87,071.60 130,607.40
Finishing cat minyak m2 4.3200 67,654.61 292,267.91
Ongkos Pasang lot 0.0300 3,780,285.54 113,408.57
Jumlah 3,893,694.11
24 1 UNIT PINTU TYPE P4 3,652,493.57
Kusen Alumunium 4 " (warna) m3 5.1000 163,513.35 833,918.09
Daun Pintu Frame Alumunium Lapis Multi+formika bh 1.0000 963,895.68 963,895.68
Lever handle, Lockcase dan cylinder kunci pintu set 1.0000 1,541,189.10 1,541,189.10
Engsel Pintu psg 1.5000 87,071.60 130,607.40
Aksesories (karet, Silent, Klose, dll) m1 10.2000 7,500.00 76,500.00
Ongkos Pasang lot 0.0300 3,546,110.27 106,383.31
Jumlah 3,652,493.57
No. URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH (Rp) TOTAL (Rp)

25 1 UNIT JENDELA TYPE J1 7,857,408.96


Kusen Alumunium 4 " (warna) m' 10.4000 163,513.35 1,700,538.84
Daun Jendela Frame Aluminium m' 12.0000 258,040.37 3,096,484.38
Kaca polos 10mm m2 3.5100 314,321.70 1,103,269.17
Rel Sliding psg 2.0000 825,000.00 1,650,000.00
Rambucis bh 2.0000 39,130.00 78,260.00
Ongkos Pasang lot 0.0300 7,628,552.39 228,856.57
Jumlah 7,857,408.96
26 1 UNIT JENDELA TYPE J2 9,281,983.89
Kusen Alumunium 4 " (warna) m' 12.4000 163,513.35 2,027,565.54
Daun Jendela Frame Aluminium m' 13.9000 258,040.37 3,586,761.07
Kaca polos 10mm m2 5.3100 314,321.70 1,669,048.23
Rel Sliding psg 2.0000 825,000.00 1,650,000.00
Rambucis bh 2.0000 39,130.00 78,260.00
Ongkos Pasang lot 0.0300 9,011,634.84 270,349.05
Jumlah 9,281,983.89
27 1 UNIT JENDELA TYPE J3 10,225,233.39
Kusen Alumunium 4 " (warna) m' 13.7000 163,513.35 2,240,132.90
Daun Jendela Frame Aluminium m' 15.2000 258,040.37 3,922,213.55
Kaca polos 10mm m2 6.4800 314,321.70 2,036,804.62
Rel Sliding psg 2.0000 825,000.00 1,650,000.00
Rambucis bh 2.0000 39,130.00 78,260.00
Ongkos Pasang lot 0.0300 9,927,411.06 297,822.33
Jumlah 10,225,233.39
28 1 UNIT JENDELA TYPE J4 8,774,080.31
Kusen Alumunium 4 " (warna) m' 11.7000 163,513.35 1,913,106.20
Daun Jendela Frame Aluminium m' 13.2000 258,040.37 3,406,132.82
Kaca polos 10mm m2 4.6800 314,321.70 1,471,025.56
Rel Sliding psg 2.0000 825,000.00 1,650,000.00
Rambucis bh 2.0000 39,130.00 78,260.00
Ongkos Pasang lot 0.0300 8,518,524.57 255,555.74
Jumlah 8,774,080.31
29 1 UNIT JENDELA TYPE J5 8,701,522.65
Kusen Alumunium 4 " (warna) m' 11.6000 163,513.35 1,896,754.86
Daun Jendela Frame Aluminium m' 13.1000 258,040.37 3,380,328.78
Kaca polos 10mm m2 4.5900 314,321.70 1,442,736.60
Rel Sliding psg 2.0000 825,000.00 1,650,000.00
Rambucis bh 2.0000 39,130.00 78,260.00
Ongkos Pasang lot 0.0300 8,448,080.24 253,442.41
Jumlah 8,701,522.65
30 1 UNIT JENDELA TYPE J6 2,023,352.51
Kusen Alumunium 4 " (warna) m' 4.5200 163,513.35 739,080.34
Daun Jendela Frame Aluminium m' 4.1200 258,040.37 1,063,126.30
Kaca polos 5mm m2 0.6712 121,205.70 81,353.27
Engsel jendela psg 1.0000 41,730.00 41,730.00
Rambucis bh 1.0000 39,130.00 39,130.00
Ongkos Pasang lot 0.0300 1,964,419.91 58,932.60
Jumlah 2,023,352.51
29 1 UNIT JENDELA TYPE J7 9,869,703.08
Kaca Tempered 12 mm m2 5.8650 733,586.70 4,302,486.00
Ornamen GRC cetak m2 3.8750 1,250,000.00 4,843,750.00
List alumunium "U" 1cm m' 13.4400 25,000.00 336,000.00
Sealant & asesoris ls 1.0000 100,000.00 100,000.00
Ongkos Pasang lot 0.0300 9,582,236.00 287,467.08
Jumlah 9,869,703.08
30 1 UNIT JENDELA TYPE J8 2,756,543.12
Kusen Alumunium 4 " (warna) m' 6.0000 163,513.35 981,080.10
Daun Jendela Frame Aluminium m' 5.4000 258,040.37 1,393,417.97
Kaca polos 5mm m2 1.8225 121,205.70 220,897.39
Engsel jendela psg 1.0000 41,730.00 41,730.00
Rambucis bh 1.0000 39,130.00 39,130.00
No. URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH (Rp) TOTAL (Rp)

Ongkos Pasang lot 0.0300 2,676,255.46 80,287.66


Jumlah 2,756,543.12
31 1 UNIT BOUVENLIGHT TYPE BV1 662,342.36
Kusen Alumunium 4 " (warna) m' 3.0000 163,513.35 490,540.05
Kaca Polos 5mm m2 0.3375 121,205.70 40,906.92 TAHUN ANGG
Ongkos Pasang lot 0.0300 531,446.97 15,943.41
Jumlah 547,390.38
Jasa Kontraktor 54,739.04
PPn 10% 60,212.94
32 1 UNIT BOUVENLIGHT TYPE BV2 4,262,083.75
Kusen Alumunium 4 " (warna) m' 5.8000 163,513.35 948,377.43
Daun Jendela Frame Aluminium m' 5.9000 258,040.37 1,522,438.15
Kaca polos 5mm m2 0.7000 121,205.70 84,843.99 TAHUN ANGG
Rel Sliding kecil psg 2.0000 412,500.00 825,000.00
Rambucis bh 1.0000 39,130.00 39,130.00
Ongkos Pasang lot 0.0300 3,419,789.57 102,593.69
Jumlah 3,522,383.26
Jasa Kontraktor 352,238.33
PPn 10% 387,462.16
33 1 UNIT BOUVENLIGHT TYPE BV3 5,550,168.08
Kusen Alumunium 4 " (warna) m' 7.9500 163,513.35 1,299,931.13
Daun Jendela Frame Aluminium m' 8.2000 258,040.37 2,115,930.99
Kaca polos 5mm m2 1.4300 121,205.70 173,324.15 TAHUN ANGG
Rel Sliding psg 2.0000 412,500.00 825,000.00
Rambucis bh 1.0000 39,130.00 39,130.00
Ongkos Pasang lot 0.0300 4,453,316.28 133,599.49
Jumlah 4,586,915.76
Jasa Kontraktor 458,691.58
PPn 10% 504,560.73
34 1 UNIT PARTISI CUBICAL TOILET LENGKAP DAUN PINTU BERIKUT ACCESSORIES (TERPASANG) 7,260,000.00
Partisi cubical lengkap : unit 1.0000 6,000,000.00 6,000,000.00
- Partisi Phenolic resin Board ex. D'CUBICS tebal 12mm, (100% kedap air )
- Pintu Phenolic resin Board ex. D'CUBICS uk. 800x1800x12 mm,(100% kedap air )
- Door hardware stainless steel accessories
- Rangka frame alumunium N/A
- Kaki pedestal dan Screw conection stainless steel
Jumlah 6,000,000.00
Jasa Kontraktor 600,000.00
PPn 10% 660,000.00
ANALISA HARGA PEKERJAAN STRUKTUR
PEMBANGUNAN GEDUNG KANTOR RAJAMANDALA ELECTRIC POWER
TAHUN ANGGARAN 2018

No. URAIAN SATUAN VOLUME HARGA SATUAN JUMLAH (RP) TOTAL (RP)

1 1 M3 LANTAI KERJA (1PC : 3PS : 5KR) 1,015,797.42


Semen PC 50 kg Zak 4.9400 70,000.00 345,800.00
Batu pecah mesin 1/2 : 1 m3 0.7400 172,000.00 127,280.00
Pasir beton I/kasar m3 0.6207 210,000.00 130,347.00
Air ltr 215.0000 100.00 21,500.00
Pekerja oh 1.6500 85,000.00 140,250.00
Tukang Batu oh 0.2750 100,000.00 27,500.00
Kepala Tukang Batu oh 0.2750 125,000.00 34,375.00
Mandor oh 0.0830 150,000.00 12,450.00
Jumlah 839,502.00
Jasa Kontraktor 83,950.20
PPn 10% 92,345.22
2 1 M' PENGADAAN TIANG PANCANG 211,750.00
Tiang pancang ukuran 20x20 cm m1 1.0000 175,000.00 175,000.00
Jumlah 175,000.00
Jasa Kontraktor 17,500.00
PPn 10% 19,250.00
3 1 M' PEMANCANGAN 20x20cm dengan Doly/Follower ( Hidrolik Jack ) 136,730.00
Pemancangan m1 1.0000 90,000.00 90,000.00
Handling tiang di lokasi proyek m1 1.0000 11,500.00 11,500.00
Unloading / penurunan tiang m1 1.0000 11,500.00 11,500.00
Jumlah 113,000.00
Jasa Kontraktor 11,300.00
PPn 10% 12,430.00
4 1 TITI SAMBUNGAN MINI PILE 20X20 CM 374,047.30
1. Bahan :
- Joint plate Sq. 250 Titik 1.0000 187,030.00 187,030.00
2. Upah :
- Sambungan las tiang pancang Titik 1.0000 122,100.00 122,100.00
Jumlah 309,130.00
Jasa Kontraktor 30,913.00
PPn 10% 34,004.30
5 1 TITI PEMOTONGAN KEPALA TIANG 124,630.00
Pekerja Orang 1.0000 100,000.00 100,000.00
Mandor Orang 0.0200 150,000.00 3,000.00
Jumlah 103,000.00
Jasa Kontraktor 10,300.00
PPn 10% 11,330.00
6 1 M3 MEMASANG PONDASI SIKLOP, 60% BETON CAMPURAN 1 PC : 2 PB : 3 KR 3,810,659.05
Semen PC 50 kg Zak 3.8800 70,000.00 271,600.00
Batu pecah mesin 2/3 m3 0.4680 195,000.00 91,260.00
Pasir beton I/kasar m3 0.3120 210,000.00 65,520.00
Batu belah 15 cm/20 cm m3 0.4800 162,500.00 78,000.00
Air ltr 215.0000 100.00 21,500.00
Besi beton Kg 126.0000 14,560.00 1,834,560.00
Kawat Beton Kg 18.0000 20,930.00 376,740.00
Pekerja oh 3.4000 85,000.00 289,000.00
Tukang Batu oh 0.8500 100,000.00 85,000.00
Kepala Tukang Batu oh 0.0850 125,000.00 10,625.00
Mandor oh 0.1700 150,000.00 25,500.00
Jumlah 3,149,305.00
Jasa Kontraktor 314,930.50
No. URAIAN SATUAN VOLUME HARGA SATUAN JUMLAH (RP) TOTAL (RP)

PPn 10% 346,423.55


7 1 M3 COR BETON SITE MIX K-175 1,061,894.91
Semen PC 50kg zak 5.8000 70,000.00 406,000.00
Split 1/2 Pecah Mesin m3 0.8300 172,000.00 142,760.00
Pasir Beton m3 0.5400 210,000.00 113,400.00
Air ltr 215.0000 100.00 21,500.00
Pekerja Orang 1.5000 85,000.00 127,500.00
Tukang Batu Orang 0.5000 100,000.00 50,000.00
Kepala Tukang Orang 0.0500 125,000.00 6,250.00
Mandor Orang 0.0100 150,000.00 1,500.00
Peralatan lot 0.0100 868,910.00 8,689.10
Jumlah 877,599.10
Jasa Kontraktor 87,759.91
PPn 10% 96,535.90
8 1 M3 RABAT BETON 1,036,391.62
Semen PC 50 kg Zak 4.9400 70,000.00 345,800.00
Batu pecah mesin 2 : 3 m3 0.7400 195,000.00 144,300.00
Pasir beton I/kasar m3 0.6207 210,000.00 130,347.00
Air ltr 215.0000 100.00 21,500.00
Pekerja oh 1.6500 85,000.00 140,250.00
Tukang Batu oh 0.2750 100,000.00 27,500.00
Kepala Tukang Batu oh 0.2750 125,000.00 34,375.00
Mandor oh 0.0830 150,000.00 12,450.00
Jumlah 856,522.00
Jasa Kontraktor 85,652.20
PPn 10% 94,217.42
9 1 M3 COR BETON SITE MIX K-225 1,164,802.51
Semen PC 50 kg Zak 7.4200 70,000.00 519,400.00
Batu pecah mesin 1/2 : 1 m3 0.7756 172,000.00 133,403.20
Pasir beton I/kasar m3 0.4986 210,000.00 104,706.00
Air ltr 215.0000 100.00 21,500.00
Pekerja oh 1.6500 85,000.00 140,250.00
Tukang Batu oh 0.2750 100,000.00 27,500.00
Kepala Tukang Batu oh 0.0275 125,000.00 3,437.50
Mandor oh 0.0830 150,000.00 12,450.00
Jumlah 962,646.70
Jasa Kontraktor 96,264.67
PPn 10% 105,891.14
10 1 M3 COR BETON READY MIX K-300 BERIKUT SLANG MIN 6 M3 1,586,915.00
Beton Ready Mix K-300 m3 1.0000 1,050,000.00 1,050,000.00
Pekerja m3 1.5000 85,000.00 127,500.00
Tukang Batu m3 0.2500 100,000.00 25,000.00
Kepala Tukang Orang 0.1000 125,000.00 12,500.00
Mandor Orang 0.0100 150,000.00 1,500.00
Peralatan (Pompa + vibrator+tes lab) m3 1.0000 95,000.00 95,000.00
Jumlah 1,311,500.00
Jasa Kontraktor 131,150.00
PPn 10% 144,265.00
10 1 M3 COR BETON READY MIX K-250 BERIKUT SLANG MIN 6 M3 1,496,165.00
Beton Ready Mix K-250 m3 1.0000 975,000.00 975,000.00
Pekerja m3 1.5000 85,000.00 127,500.00
Tukang Batu m3 0.2500 100,000.00 25,000.00
Kepala Tukang Orang 0.1000 125,000.00 12,500.00
Mandor Orang 0.0100 150,000.00 1,500.00
Peralatan (Pompa + vibrator+tes lab) m3 1.0000 95,000.00 95,000.00
Jumlah 1,236,500.00
Jasa Kontraktor 123,650.00
PPn 10% 136,015.00
No. URAIAN SATUAN VOLUME HARGA SATUAN JUMLAH (RP) TOTAL (RP)

11 1 M2 BEKISTING BETON PONDASI POER, SLOOF 161,672.94


Bahan Kayu Papan albasiah m3 0.0400 1,235,000.00 49,400.00
Paku kg 0.3000 20,280.00 6,084.00
Minyak Bekisting liter 0.1000 7,800.00 780.00
Upah Pekerja Orang 0.5200 85,000.00 44,200.00
Tukang Batu Orang 0.2600 100,000.00 26,000.00
Kepala Tukang Batu Orang 0.0260 125,000.00 3,250.00
Mandor Orang 0.0260 150,000.00 3,900.00
Jumlah 133,614.00
Jasa Kontraktor 13,361.40
PPn 10% 14,697.54
12 1 M2 BEKISTING KOLOM 212,314.92
Bahan Kayu papan albasiah m3 0.0400 1,235,000.00 49,400.00
Paku 4 s/d 7 cm kg 0.4000 20,280.00 8,112.00
Minyak pelumas ltr 0.2000 7,800.00 1,560.00
Kayu terentang m3 0.0150 2,080,000.00 31,200.00
Multipek 9mm, uk. 1,20 x 2,40 lbr 0.3500 156,000.00 54,600.00
Dolken dia. 8 s/d 10 cm btg 2.0000 18,850.00 37,700.00
Upah Pekerja Orang 0.6600 85,000.00 56,100.00
Tukang Batu Orang 0.3300 100,000.00 33,000.00
Kepala Tukang Batu Orang 0.0330 125,000.00 4,125.00
Mandor Orang 0.0330 150,000.00 4,950.00
Jumlah 280,747.00
Jasa Kontraktor 28,074.70
PPn 10% 30,882.17
Dua Kali Pakai 62.50%
13 1 M2 BEKISTING BALOK 217,033.92
Bahan Kayu papan albasiah m3 0.0400 1,235,000.00 49,400.00
Paku 4 s/d 7 cm kg 0.4000 20,280.00 8,112.00
Minyak pelumas ltr 0.2000 7,800.00 1,560.00
Kayu terentang m3 0.0180 2,080,000.00 37,440.00
Multipek 9mm, uk. 1,20 x 2,40 lbr 0.3500 156,000.00 54,600.00
Dolken dia. 8 s/d 10 cm btg 2.0000 18,850.00 37,700.00
Upah Pekerja Orang 0.6600 85,000.00 56,100.00
Tukang Batu Orang 0.3300 100,000.00 33,000.00
Kepala Tukang Batu Orang 0.0330 125,000.00 4,125.00
Mandor Orang 0.0330 150,000.00 4,950.00
Jumlah 286,987.00
Jasa Kontraktor 28,698.70
PPn 10% 31,568.57
Dua Kali Pakai 62.50%
14 1 M2 BEKISTING PLAT LANTAI 269,336.17
Bahan Kayu papan albasiah m3 0.0400 1,235,000.00 49,400.00
Paku 4 s/d 7 cm kg 0.4000 20,280.00 8,112.00 Kayu papa
Minyak pelumas ltr 0.2000 7,800.00 1,560.00 Paku 4 s/d
Kayu terentang m3 0.0150 2,080,000.00 31,200.00 Minyak pe
Multipek 9mm, uk. 1,20 x 2,40 lbr 0.3500 156,000.00 54,600.00 Kayu teren
Dolken dia. 8 s/d 10 cm btg 6.0000 18,850.00 113,100.00 Multipek 9
Upah Pekerja Orang 0.6600 85,000.00 56,100.00 Dolken dia
Tukang Batu Orang 0.3300 100,000.00 33,000.00 Upah Peke
Kepala Tukang Batu Orang 0.0330 125,000.00 4,125.00 Tukang Ka
Mandor Orang 0.0330 150,000.00 4,950.00 Kepala Tu
Jumlah 356,147.00
Jasa Kontraktor 35,614.70
PPn 10% 39,176.17
Dua Kali Pakai 62.50%
No. URAIAN SATUAN VOLUME HARGA SATUAN JUMLAH (RP) TOTAL (RP)

15 1 M2 BEKISTING TANGGA 220,475.31


Bahan Kayu papan albasiah m3 0.0300 1,235,000.00 37,050.00
Paku 4 s/d 7 cm kg 0.4000 20,280.00 8,112.00
Minyak pelumas ltr 0.2000 7,800.00 1,560.00
Kayu terentang m3 0.0200 2,080,000.00 41,600.00
Upah Multipek 9mm, uk. 1,20 x 2,40 lbr 0.3500 156,000.00 54,600.00
Dolken dia. 8 s/d 10 cm btg 2.0000 18,850.00 37,700.00
Formite/penjaga jarak bekisting/spacer bh 4.0000 8,450.00 33,800.00
Pekerja Orang 0.7500 85,000.00 63,750.00
Tukang Batu Orang 0.5000 100,000.00 50,000.00
Kepala Tukang Batu Orang 0.0500 125,000.00 6,250.00
Mandor Orang 0.2000 150,000.00 30,000.00
Jumlah 364,422.00
Jasa Kontraktor 36,442.20
PPn 10% 40,086.42
16 1 M2 BEKISTING DINDING BETON 231,879.56
Bahan Kayu papan albasiah m3 0.0300 1,235,000.00 37,050.00
Paku 4 s/d 7 cm kg 0.4000 20,280.00 8,112.00
Minyak pelumas ltr 0.2000 7,800.00 1,560.00
Kayu terentang m3 0.0200 2,080,000.00 41,600.00
Multipek 9mm, uk. 1,20 x 2,40 lbr 0.3500 156,000.00 54,600.00
Dolken dia. 8 s/d 10 cm btg 3.0000 18,850.00 56,550.00
Formite/penjaga jarak bekisting/spacer bh 4.0000 8,450.00 33,800.00
Pekerja Orang 0.7500 85,000.00 63,750.00
Upah Tukang Batu Orang 0.5000 100,000.00 50,000.00
Kepala Tukang Batu Orang 0.0500 125,000.00 6,250.00
Mandor Orang 0.2000 150,000.00 30,000.00
Jumlah 383,272.00
Jasa Kontraktor 38,327.20
PPn 10% 42,159.92
17 1 KG MENGERJAKAN BESI BETON TULANGAN 20,001.06
Bahan Besi Kg 1.0500 14,560.00 15,288.00
Kawat Beton / Bendrat Kg 0.0100 20,930.00 209.30
Upah Tukang Besi Orang 0.0050 100,000.00 500.00
Kepala Tukang Besi Orang 0.0005 125,000.00 62.50
Pekerja Orang 0.0050 85,000.00 425.00
Mandor Orang 0.0003 150,000.00 45.00
Jumlah 16,529.80
Jasa Kontraktor 1,652.98
PPn 10% 1,818.28

18 1 m2 MENGERJAKAN BESI WERMESH M 6 41,846.59


Bahan Besi wermes M 6 m2 1.0500 27,777.78 29,166.67
Kawat Beton / Bendrat Kg 0.0750 20,930.00 1,569.75
Upah Tukang Besi Orang 0.0200 100,000.00 2,000.00
Kepala Tukang Besi Orang 0.0020 125,000.00 250.00
Pekerja Orang 0.0100 85,000.00 850.00
Mandor Orang 0.0001 150,000.00 15.00
Alat Lot 0.0500 30,736.42 1,536.82
Jumlah 35,388.24
Jasa Kontraktor 2,654.12
PPn 10% 3,804.24
19 1 m2 MENGERJAKAN BESI WERMESH M 7 54,492.77
Bahan Besi wermes M 7 Kg 1.0500 37,477.95 39,351.85
Kawat Beton / Bendrat Kg 0.0750 20,930.00 1,569.75
Upah Tukang Besi Orang 0.0200 100,000.00 2,000.00
Kepala Tukang Besi Orang 0.0020 125,000.00 250.00
Pekerja Orang 0.0100 85,000.00 850.00
No. URAIAN SATUAN VOLUME HARGA SATUAN JUMLAH (RP) TOTAL (RP)

Mandor Orang 0.0001 150,000.00 15.00


Alat Lot 0.0500 40,921.60 2,046.08
Jumlah 46,082.68
Jasa Kontraktor 3,456.20
PPn 10% 4,953.89

20 1 m2 MENGERJAKAN BESI WERMESH M 8 68,863.43


Bahan Besi wermes M 8 Kg 1.0500 48,500.88 50,925.93
Kawat Beton / Bendrat Kg 0.0750 20,930.00 1,569.75
Upah Tukang Besi Orang 0.0200 100,000.00 2,000.00
Kepala Tukang Besi Orang 0.0020 125,000.00 250.00
Pekerja Orang 0.0100 85,000.00 850.00
Mandor Orang 0.0001 150,000.00 15.00
Alat Lot 0.0500 52,495.68 2,624.78
Jumlah 58,235.46
Jasa Kontraktor 4,367.66
PPn 10% 6,260.31

21 1 KG MENGERJAKAN BESI BETON U 24 20,838.23


Bahan Besi Beton Kg 1.0500 14,560.00 15,288.00
Kawat Beton Kg 0.0100 20,930.00 209.30
Upah Tukang Besi Orang 0.0070 100,000.00 700.00
Kepala Tukang Besi Orang 0.0007 125,000.00 87.50
Pekerja Orang 0.0070 85,000.00 595.00
Mandor Orang 0.0003 150,000.00 45.00
Alat Lot 0.0450 15,497.30 697.38
Jumlah 17,622.18
Jasa Kontraktor 1,321.66
PPn 10% 1,894.38
22 1 KG BESI PROFIL/SIKU/IWF/PIPA/PLAT 25,404.03
BESI Profil/Siku/WF/Pipa/Plat Kg 1.0100 11,700.00 11,817.00
Meni Besi kg 0.0800 19,110.00 1,528.80
Kawat Las kg 0.0850 11,700.00 994.50
Pekerja Orang 0.0600 85,000.00 5,100.00
Tukang Besi Orang 0.0040 100,000.00 400.00
Kepala Tukang Orang 0.0010 125,000.00 125.00
Mandor Orang 0.0002 150,000.00 30.00
Peralatan Lot 1.0000 999.77 999.77
Jumlah 20,995.07
Jasa Kontraktor 2,099.51
PPn 10% 2,309.46
23 1 KG PEKERJAAN ERECTION KONSTRUKSI BAJA 708.05
crane ls 0.0002 369,000.00 73.80
BBM solar ltr 0.0100 7,500.00 75.00
Pelumas ltr 0.0010 25,000.00 25.00
Pekerja Orang 0.0010 85,000.00 85.00
Tukang Besi Orang 0.0010 100,000.00 100.00
Kepala Tukang Orang 0.0002 125,000.00 25.00
Mandor Orang 0.0001 150,000.00 15.00
operator Orang 0.0010 150,000.00 150.00
pembantu operator Orang 0.0001 85,000.00 8.50
Peralatan Lot 1.0000 27.87 27.87
Jumlah 585.17
Jasa Kontraktor 58.52
PPn 10% 64.37
24 1 BH PASANG ANCHOR BOLT Ø25MMX500X100 52,922.68
Anchor Bolt Ø22MMX500X100 bh 1.0000 36,000.00 36,000.00
Pekerja Orang 0.0600 85,000.00 5,100.00
Tukang Besi Orang 0.0040 100,000.00 400.00
Kepala Tukang Orang 0.0010 125,000.00 125.00
Mandor Orang 0.0002 150,000.00 30.00
Peralatan Lot 1.0000 2,082.75 2,082.75
Jumlah 43,737.75
Jasa Kontraktor 4,373.78
No. URAIAN SATUAN VOLUME HARGA SATUAN JUMLAH (RP) TOTAL (RP)

PPn 10% 4,811.15


No. URAIAN SATUAN VOLUME HARGA SATUAN JUMLAH (RP) TOTAL (RP)

25 1 m2 MENGERJAKAN PLAT BONDEK 275,827.12


Bahan Plat Bondek t=0.75 m2 1.0100 141,300.00 142,713.00
Dolken dia. 8 s/d 10 cm btg 3.0000 18,850.00 56,550.00 Multipek 9
Upah Pekerja Orang 0.0600 125,000.00 7,500.00
Tukang Besi Orang 0.0040 85,000.00 340.00
Kepala Tukang Orang 0.0010 100,000.00 100.00
Mandor Orang 0.0002 150,000.00 30.00
Peralatan Lot 0.1000 207,233.00 20,723.30
Jumlah 227,956.30
Jasa Kontraktor 22,795.63
PPn 10% 25,075.19
26 1 m3 PEKERJAAN KOLOM PRAKTIS 12 x12 cm 8,068,347.24
Beton K-175 site mix m3 1.0000 1,061,895 1,061,895
Besi kg 215.0000 20,001 4,300,227
Bekisting m2 16.6000 121,255 2,012,828
Pekerja Orang 1.6000 85,000 136,000
Tukang kayu Orang 1.2000 100,000 120,000
Kepala tukang Orang 0.6000 125,000 75,000
Mandor Orang 0.1600 150,000 24,000
Jumlah 6,668,055.57
Jasa Kontraktor 666,805.56
PPn 10% 733,486.11
27 1 m3 PEKERJAAN BALOK LINTEI / PRAKTIS 12 x15 6,887,369.11
Beton K-175 site mix m3 1.0000 1,061,895 1,061,895
Besi kg 185.0000 20,001 3,700,196
Bekisting m2 13.3000 121,255 1,612,688
Pekerja Orang 1.6000 85,000 136,000
Tukang kayu Orang 1.2000 100,000 120,000
Kepala tukang Orang 0.6000 150,000 90,000
Mandor Orang 0.1600 207,233 33,157
Jumlah 5,692,040.59
Jasa Kontraktor 569,204.06
PPn 10% 626,124.46
28 1 m3 PEKERJAAN PLAT BETON KANOPY T.7 cm 7,749,309.52
Beton K-175 site mix m3 1.0000 1,061,895 1,061,895
Besi kg 145.0000 20,001 2,900,153
Bekisting m2 23.3000 121,255 2,825,235
Perancah btg 12.0000 27,000 324,000
Pekerja Orang 1.6000 85,000 136,000
Tukang kayu Orang 1.2000 100,000 120,000
Kepala tukang Orang 0.6000 125,000 75,000
Mandor Orang 0.1600 150,000 24,000
Jumlah 6,404,388.04
Jasa Kontraktor 640,438.80
PPn 10% 704,482.68
29 1 m2 PASANG RANGKA ATAP BAJA RINGAN 238,610.76
Bahan baja ringan profil C.75, 0.8 m' 1.4880 16,000.00 23,808.00
baja ringan profil C.75, 0.6 m' 2.2320 13,500.00 30,132.00
Baut (screw driver) bh 38.0000 350.00 13,300.00
Dynabolt bh 1.6000 3,500.00 5,600.00
Reng m' 5.4000 8,000.00 43,200.00
Talang Jurai m' 0.1240 50,000.00 6,200.00
Upah Pekerja Orang 0.2000 125,000.00 25,000.00
Tukang Besi Orang 0.4500 85,000.00 38,250.00
Kepala Tukang Orang 0.0100 100,000.00 1,000.00
Mandor Orang 0.0500 150,000.00 7,500.00
Peralatan Lot 0.1000 77,950.00 7,795.00
Jumlah 201,785.00
Jasa Kontraktor 15,133.88
PPn 10% 21,691.89
F
30 1 m3 PEKERJAAN PEMASANGAN PONDASI JALAN LPB 314,878.67
Bahan Batu Belah 10/15 cm m3 1.2000 200,000.00 240,000.00
Alat bantu Lot 0.0050 240,000.00 1,200.00
Dump Truck Jam 0.0297 113,400.00 3,367.98
Tandem Roller Jam 0.0535 191,600.00 10,250.60
Motor Grader Jam 0.0013 208,000.00 277.33
Vibrator Roller Jam 192,000.00 -
No. URAIAN SATUAN VOLUME HARGA SATUAN JUMLAH (RP) TOTAL (RP)

Water Tank Jam 0.0211 81,600.00 1,721.76


Upah Pekerja Oh 0.0400 85,000.00 3,400.00
Operator Oh 0.0133 150,000.00 1,995.00
Pembantu Operator Oh 0.0195 85,000.00 1,657.50
Supir Truk Oh 0.0067 125,000.00 837.50
Pembantu Supir Oh 0.0067 85,000.00 569.50
Mandor Oh 0.0067 150,000.00 1,005.00
Jumlah 266,282.17
Jasa Kontraktor 19,971.16
PPn 10% 28,625.33
F
31 1 m3 PEKERJAAN PEMASANGAN PONDASI JALAN LPA 381,905.13
Bahan Batu Belah 5/7 cm m3 1.2000 247,000.00 296,400.00
Alat bantu Lot 0.0050 296,400.00 1,482.00
Dump Truck Jam 0.0297 113,400.00 3,367.98
Tandem Roller Jam 0.0535 191,600.00 10,250.60
Motor Grader Jam 0.0013 208,000.00 277.33
Vibrator Roller Jam 192,000.00 -
Water Tank Jam 0.0211 81,600.00 1,721.76
Upah Pekerja Oh 0.0400 85,000.00 3,400.00
Operator Oh 0.0133 150,000.00 1,995.00
Pembantu Operator Oh 0.0195 85,000.00 1,657.50
Supir Truk Oh 0.0067 125,000.00 837.50
Pembantu Supir Oh 0.0067 85,000.00 569.50
Mandor Oh 0.0067 150,000.00 1,005.00
Jumlah 322,964.17
Jasa Kontraktor 24,222.31
PPn 10% 34,718.65
F
HARGA BAHAN DAN UPAH
NO URAIAN BAHAN SATUAN HARGA

A. JENIS AGREGAT KASAR, BAHAN PEREKAT & BAHAN JADI


1 Pasir Urug M3 96,000.00
2 sirtu M3 105,000.00
3 Tanah Merah M3 113,000.00
4 Abu Batu M3 156,000.00
5 Pasir Pasang M3 150,000.00
6 Pasir Beton M3 210,000.00
7 Batu Belah M3 162,500.00
8 Batu Pecah Mesin 0,5:1 M3 172,000.00
9 Batu Pecah Mesin 1:2 M3 212,000.00
10 Batu Pecah Mesin 2:3 M3 195,000.00
11 Batu Belah 5/7 cm M3 247,000.00
12 Batu Belah 10/15 cm M3 200,000.00
13 Semen ( PC ) zak 70,000.00
14 Semen instan perekat bata Kg 16,250.00
15 Semen Mortar MU-380 Kg 3,750.00
16 Semen Mortar MU-200 Kg 4,000.00
17 Semen Warna Kg 9,750.00
18 13 Lem putih fox Kg 41,730.00

B BAHAN PENUTUP DINDING


1 Bata merah bakar kelas I bh 750.00
2 Bata merah press 21x10x5 bh 1,500.00
3 Bata I Brick bh 5,850.00
4 Bata Ringan 20x60x10 cm bh 8,674.70
5 Batu alam andesit m2 71,500.00
6 Bata beton berlubang 390x190x190mm (bond beam) bh 8,450.00
7 Bata beton berlubang 190x190x90mm bh 6,500.00
8 Roster beton 150x200x140mm bh 12,000.00

C BAHAN LOGAM DAN BAHAN JADINYA


1 Besi baja beton Kg 14,560.00
2 BESI Profil/Siku/WF/Pipa/Plat Kg 11,700.00
3 Seng plat BJLS 30 lebar 90 cm (1 roll 50 m) m1 13,130.00
4 Seng plat BJLS 25 uk. 90 x 180 cm lbr 53,690.00
5 Seng gelombang 3"-5" lbr 77,480.00
6 Talang metal galvanize tebal 0,5 mm lebar 45 cm m1 35,880.00
7 Besi strip uk, 3 x 30 mm x 6 m Kg 17,940.00
8 Kawat beton Kg 20,930.00
9 Kawat las Kg 11,700.00
10 Hollow 20x40x0.8 mm zincromate btg 71,500.00
11 Hollow 40x40x0.8 mm zincromate btg 97,500.00
12 Hollow 4x6x1.1 mm zincromate btg 169,000.00
13 Paku 1 s/d 3 cm Kg 23,920.00
14 Paku 4 s/d 7 cm Kg 20,280.00
15 Paku skrup 10 cm Kg 47,710.00
16 Baut (screw driver) bh 350.00
17 Anchor Bolt Ø22MMX500X100 bh 36,000.00
18 Dynabolt bh 3,500.00
19 Formite/penjaga jarak bekisting/spacer bh 8,450.00
20 Paku anti karat u/ genteng metal (35.00 m2/kg) kg 53,690.00
NO URAIAN BAHAN SATUAN HARGA
21 Wiremesh M5 uk. 2,1m x 5,4m m2 18,959.44
22 Wiremesh M6 uk. 2,1m x 5,4m m2 27,777.78
23 Wiremesh M7 uk. 2,1m x 5,4m m2 37,477.95
24 Wiremesh M8 uk. 2,1m x 5,4m m2 48,500.88
25 Baja Ringan Profil C.75, 0.8 m' 16,000.00
26 Baja Ringan Profil C.75, 0.8 m' 13,500.00
27 Baja Ringan Reng 0.45 m' 8,000.00
28 Plat Bondek t=0.75 m2 141,300.00
NO URAIAN BAHAN SATUAN HARGA
D BAHAN PENGUNCI/PENGGANTUNG DAN KACA

1 Engsel pintu Psg 53,690.00


2 Engsel Jendela Psg 41,730.00
3 Engsel pintu (floor hinge), ex Dorma set 1,750,000.00
4 Pull Handle Psg 750,000.00
5 Over panel set 950,000.00
6 Top Patch Fitting set 847,000.00
7 Bottom patch fitting set 847,000.00
8 Bottom patch lock + cylinder set 1,250,000.00
9 Lever Handle bh 172,900.00
10 Lockcase bh 148,980.00
11 Cylinder bh 148,980.00
12 Rambucis bh 39,130.00
13 Door Closer set 475,000.00
14 Engsel Jendela Casement bh 50,000.00
15 Rel Sleading psg 825,000.00
16 Tarikan Jendela Alumunium psg 37,620.00
17 Kaca Stopsol 8mm m2 1,100,000.00
18 Kaca Polos Tempered 12mm m2 460,000.00
19 Kaca Polos 10mm m2 230,000.00
20 Kaca Polos 8mm m2 162,500.00
21 Kaca Polos 5mm m2 78,000.00
22 Kaca Laminated 10 mm m2 900,000.00
23 Kusen Alumunium 4" warna m' 117,000.00
24 Kusen Alumunium 4" Anodize m' 83,460.00
25 Kusen Alumunium 3" warna m' 77,480.00
26 Kusen Alumunium3" Anodize m' 71,630.00
27 Rangka Aluminium daun pintu m' 65,650.00
28 Rangkan 'Aluminium daun jendela m' 65,650.00
29 Alumunium Composite Panel t=4mm, alu=0.5mm m2 975,000.00
30 Sticker Sunblast m2 100,000.00

E BAHAN KAYU/KAYU LAPIS DAN PLAPOND

1 Kayu balok Albasiah m3 1,235,000.00


2 Kayu papan Albasiah m3 1,235,000.00
3 Kayu terentang m3 2,080,000.00
4 Kayu kamper samarinda oven m3 11,050,000.00
5 List Profile 2/3 Kayu kamper samarinda oven m' 50,000.00
6 Dolken dia. 8 s/d 10 cm btg 18,850.00
7 triplek 4mm, uk. 1,20 x 2,40 lbr 59,670.00
8 Multiplek 6mm, uk. 1,20 x 2,40 lbr 104,000.00
9 Multipek 9mm, uk. 1,20 x 2,40 lbr 156,000.00
10 Teakwood 3mm, uk. 1,20 x 2,40 lbr 71,630.00
11 HPL lbr 250,000.00
12 Parquet Lantai Kayu Laminated Uk. 10x40 cm m2 260,000.00
13 Gypsum 120 x 240 cm ex DN t=9mm lbr 78,000.00
14 G R C 120 x 240 cm t=4mm lbr 68,900.00
15 Plafond PVC m2 91,000.00
16 List Gypsum 5 cm m1 12,000.00
17 List Plafond PVC (setara shunda plafond, LS 301-1 min Silver Metalic) m1 16,000.00
18 Cotton Plaster Paper m1 5,980.00
19 Tepung gypsum kg 20,280.00
NO URAIAN BAHAN SATUAN HARGA

F BAHAN PENUTUP ATAP

1 Atap Gelombang PVC Rooftop m2 192,771.08


2 Atap Metal Spandex t=0.35 m2 75,000.00
3 Wuwungan PVC m' 110,000.00
4 Alumunium Foil / Sisalation m2 5,000.00
NO URAIAN BAHAN SATUAN HARGA
BAHAN PENUTUP LANTAI

1 Keramik dinding 30/60, corak warna m2 125,000.00


2 Keramik 30/30, (KM) warna / corak, anti slip m2 95,000.00
3 Border Keramik 10/25 bh 45,000.00
4 Homogenous tile 60 x 60 cm Polished m2 235,000.00
5 Homogenous tile 60 x 60 cm Unpolished m2 250,000.00
6 Stepnosing bh 35,000.00
7 Stone block 20 x 20 x 8 cm m2 186,000.00
8 Paving block tebal 6 cm m2 125,000.00
9 Grass block tebal 8 cm bh 20,800.00
10 Kanstein 400 x 60 x 155 mm bh 29,900.00
11 Floor Hardener kg 8,000.00
12 Curing Compound m2 5,000.00

BAHAN FINISHING

1 Cat dasar eksterior ltr 23,400.00


2 Cat dasar interior ltr 20,800.00
3 Cat tembok eksterior ltr 84,000.00
4 Cat tembok interior ltr 54,000.00
5 Cat kayu / besi Seiv kg 49,140.00
6 Kumpon kg 7,280.00
7 Meni kayu / besi Bola Mas kg 19,110.00
8 Dempul Tembok (plamuur) kg 27,690.00
9 Dempul halus / Impra (Wood Filler) kg 53,690.00
10 Terpentin ( minyak cat) ltr 14,430.00
11 Minyak pelumas ltr 7,800.00
12 Thinner A ltr 26,260.00
13 Wood Stain kg 51,350.00
14 Melamin Sending Siller MSS 123 kg 51,350.00
15 Ampelas lbr 3,640.00
16 Plint coat kg 14,950.00
17 WaterProofing coating kg 65,000.00
18 WaterProofing membran kg 169,000.00
19 BBM Pelumas kg 7,500.00
20 Pelumas kg 25,000.00

BAHAN PERPIPAAN

1 Pipa pralon PVC. (AW) dia. 1/2 inch, sekualitas Maspion (abu-abu) btg 25,090.00
2 Pipa pralon PVC. (AW) dia. 3/4 inch, sekualitas Maspion (abu-abu) btg 33,410.00
3 Pipa pralon PVC. (AW) dia. 1 inch, sekualitas Maspion (abu-abu) btg 43,030.00
4 Pipa pralon PVC. (AW) dia. 1 1/4 inch, sekualitas Maspion (abu-abu) btg 57,330.00
5 Pipa pralon PVC. (AW) dia. 1 1/2 inch, sekualitas Maspion (abu-abu) btg 77,480.00
6 Pipa pralon PVC. (AW) dia. 2 inch, sekualitas Maspion (abu-abu) btg 95,420.00
7 Pipa pralon PVC. (AW) dia. 2 1/2 inch, sekualitas Maspion (abu-abu) btg 119,210.00
8 Pipa pralon PVC. (AW) dia. 3 inch, sekualitas Maspion (abu-abu) btg 220,480.00
9 Pipa pralon PVC. (AW) dia. 4 inch, sekualitas Maspion (abu-abu) btg 309,920.00
10 Pipa pralon PVC. (AW) dia. 6 inch, sekualitas Maspion (abu-abu) btg 603,200.00
11 Buis beton dia. 30 cm - 100 cm bh 184,730.00
12 Buis beton dia. 20 cm - 100 cm bh 39,000.00
NO URAIAN BAHAN SATUAN HARGA
BAHAN / ALAT - ALAT SANITAIR

1 Kloset duduk lengkap bh 1,820,000.00


2 Kloset jongkok bh 455,000.00
3 Wastafel lengkap bh 1,625,000.00
4 Urinoir bh 2,275,000.00
5 Cermin wastafel m2 195,000.00
6 Kitchen zink stainless standard 1 lobang bh 568,750.00
7 Kran air leher angsa dia. 1/2" bh 325,000.00
8 Kran air untuk wastafel bh 216,125.00
9 Kran tembok dia. 1/2" bh 80,275.00
10 Floor drain bh 162,500.00
11 Jet Washer bh 292,500.00
12 Handshower kombinasi kran bh 1,250,000.00

BAHAN MEKANIKAL, ELEKTRIKAL DAN PJU

1 Kable listrik NYFGbY 4 x 10 mm2 m1 92,000.00


2 Kable listrik NYFGbY 4 x 6 mm2 m1 72,000.00
3 Kable listrik NYY 4 x 6 mm2 m1 45,000.00
4 Kable listrik NYY 4 x 4 mm2 m1 32,000.00
5 Kabel listrik NYM 4 x 4 mm2 m1 55,575.00
6 Kabel listrik NYM 3 x 2,5 mm m1 14,202.50
7 Kabel listrik NYM 3 x 1,5 mm m1 12,967.50
8 Kabel listrik NYM 2 x 1,5 mm m1 9,945.00
9 Saklar lampu bh 33,345.00
10 Stop kontak bh 39,520.00
11 Armatur Balk, TLD 1x36 w, ex Philips set 175,000.00
12 Wall Outlet LAN bh 154,375.00
13 Kabel UTP cat 5e per 15 meter + jack RJ45 bh 37,667.50
14 Condoit dia 20 mm( 3/4 inch ) m1 1,852.50
15 Compresor Air 210 m3 / H jam 154,375.00

BAHAN BETON READY MIX

1 Beton Ready Mix K-175 m3 850,000.00


2 Beton Ready Mix K-200 m3 900,000.00
3 Beton Ready Mix K-225 m3 950,000.00
4 Beton Ready Mix K-250 m3 975,000.00
5 Beton Ready Mix K-275 m3 1,000,000.00
6 Beton Ready Mix K-300 m3 1,050,000.00
7 Beton Ready Mix K-325 m3 1,200,000.00
8 Beton Ready Mix K-350 m3 1,250,000.00
9 Beton Ready Mix K-375 m3 1,280,000.00
10 Beton Ready Mix K-400 m3 1,290,000.00
11 Beton Ready Mix K-425 m3 1,300,000.00
12 Mini Pile Segi Empat 20x20 cm, 6 m Batang 1,050,000.00
13 Mini Pile Segi Empat 20x20 cm, 3 m Batang 540,000.00
14 Biaya pemancangan Mini Pile 20x20cm dengan Dolly ( Hidrolik Jack 7 ton m' 90,000.00
15 Handling tiang pancang 20x20cm m' 11,500.00
16 Joint plate SQ.250 Titik 187,030.00
17 Biaya pengelasan penyambungan mini pile 20x20cm Titik 122,100.00
18 Biaya pemotongan alat pancang Titik 146,520.00
19 Sewa Alat Pompa Beton m3 95,000.00
NO URAIAN BAHAN SATUAN HARGA

BAHAN TANAMAN

1 Tanah Subur/gembur m3 120,000.00


2 Rumput gajah mini m2 35,000.00
3 Tanaman hujan mas Polibag 10,000.00
4 Tanaman euforbhia Polibag 10,000.00
5 Tanaman soka hawai Polibag 15,000.00
6 Tanaman plumbago ungu Polibag 9,500.00
7 Pohon palm ekor tupai btg 450,000.00
8 Pohon Katapang angsana btg 300,000.00
9 Pohon sawo kecik btg 250,000.00
10 Angsana (2 s/d 3m) btg 197,580.00

BAHAN ALAT BERAT

1 Asphalt Finisher /Jam 614,000.00


2 Asphalt Mixing Plant 30 T /Jam 185,310.00
3 Asphalt Sprayer /jam 44,800.00
4 Asphalt Sprayer Towed 350 L /Jam 87,800.00
5 Blower /Jam 22,365.00
6 Bulldozer 100-150 HP /jam 576,500.00
7 Compressor 4000-6500 L\M /Jam 95,000.00
8 Compressor Air /Jam 74,000.00
9 Concrete Mixer 0,3-0,6 m3 /Jam 197,000.00
10 Concrete Mixer 250 L /Jam 45,000.00
11 Concrete pump 100 HP /Jam 375,000.00
12 Concrete Vibrator /Jam 24,000.00
13 Cordrill DLL /Jam 185,000.00
14 Crane 10-15 Ton /Jam 369,000.00
15 Crane 30 Ton /Jam 725,000.00
16 Motor Grader /Jam 208,000.00
17 Roller 3 Wheel /Jam 94,400.00
18 Tandem Roller /Jam 191,600.00
19 Vibrator Roler /Jam 192,000.00
20 Water Tank Truck /Jam 81,600.00
21 Dump Truck 3.5 - 4 T /Jam 113,400.00
HARGA BAHAN DAN UPAH

NO NAMA PEKERJA SATUAN HARGA

1 Pekerja Org/hr 85,000.00


2 Tukang kayu Org/hr 100,000.00
3 Kepala Tukang kayu Org/hr 125,000.00
4 Tukang batu Org/hr 100,000.00
5 Kepala Tukang Batu Org/hr 125,000.00
6 Tukang besi Org/hr 100,000.00
7 Kepala tukang besi Org/hr 125,000.00
8 Tukang cat Org/hr 100,000.00
9 Kepala tukang cat Org/hr 125,000.00
10 Tukang pipa Org/hr 100,000.00
11 Kepala tukang pipa Org/hr 125,000.00
12 Mandor Org/hr 150,000.00
13 Mekanik Org/hr 150,000.00
14 Operator Org/hr 150,000.00
15 Pembantu Operator Org/hr 85,000.00
16 Supir Truk Org/hr 125,000.00
17 Kenek Truk Org/hr 85,000.00
18 Penjaga Malam Org/hr 100,000.00
1 -
85000
100000
125000
100000
125000
100000
125000
100000
125000
100000
125000
150000
150000
150000
85000
125000
85000
100000
Terjemahan kedalam kalimat

3,737,174,000.00 1 <=== Bahasa <1> Indonesia, <2> Inggris

terbilang =
Tiga Milyar Tujuh Ratus Tiga Puluh Tujuh Juta Seratus Tujuh Puluh Empat Ribu Rupiah

BASIC => satu dua tiga empat lima enam tujuh delapan @@@@@
ribu juta milyar triliyun @@@@@
003737174000 @@@@@
@ @@@@@@@@@ @@@@@ @@@@@ @@@@@ @@@@@@@@@@
basic @ 000 1 @@@@@
perhitungan @ 0 @@@@@
angka @ sepuluh @@@@@
@ 0 @@@@@
@ 0 @@@@@
@ @@@@@
@ @@@@@
@ @@@@@
@ @@@@@
@ 174 2 @@@@@
@ 1 tujuh puluh @@@@@
@ seratus empat belas @@@@@
@ 7 empat @@@@@
@ 4 tujuh puluh empat @@@@@
@ tujuh puluh empat tujuh puluh empat @@@@@
@ seratus tujuh puluh empat ribu @@@@@
@ @@@@@
@ @@@@@
@ 737 3 @@@@@
@ 7 tiga puluh @@@@@
@ tujuh ratus tujuh belas @@@@@
@ 3 tujuh @@@@@
@ 7 tiga puluh tujuh @@@@@
@ tiga puluh tujuh tiga puluh tujuh @@@@@
@ tujuh ratus tiga puluh tujuh juta @@@@@
@ @@@@@
@ @@@@@
@ 003 4 @@@@@
@ 0 @@@@@
@ tiga belas @@@@@
@ 0 tiga @@@@@
@ 3 tiga @@@@@
@ tiga tiga @@@@@
@ tiga milyar @@@@@
@ @@@@@
@ 000 1 @@@@@
@ 0 @@@@@
@ sepuluh @@@@@
@ 0 @@@@@@@@@@
@ 0 @@@@@
@ @@@@@
@ @@@@@
@ ***
@
@ 83 00
@ tiga milyar tujuh ratu tiga milyar tujuh ratus tiga puluh tujuh juta seratus tujuh puluh empat ribu rupiah
@ tiga milyar tujuh ratus tiga puluh tujuh juta seratus tujuh puluh empat ribu rupiah
@ Tiga milyar tujuh ratus tiga puluh tujuh juta seratus tujuh puluh empat ribu rupiah
mpat ribu rupiah
DENGAN PENDEKATAN PERHITUNGAN DI LAPANGAN
Dia Kg/m' Dia Kg/m' Dia Kg/m'
8 0.395 kg 13 1.042 kg 22 2.984 kg
10 0.617 kg 16 1.578 kg 25 3.853 kg
12 0.89 kg 19 2.226 kg 29 5.185 kg

A 1 M3 KOLOM K1 20 X 30
1 M3 KOLOM K1 20 X 30 0.2 X 0.3 cover beton = 0.025 m
Panjang 1 : 0.2 : 0.3 = 16.67 M1
50
Besi dia 16 6 dia 16
Besi dia 10 0 dia 0
Begel dia 10 - 0.15 10 50

Besi dia 16 16.67 X 6 X 1.58 KG = = 157.824


Besi dia 10 16.67 X 0 X 0 KG = = 0.000
Begel dia 10 - ( 16.67 : 0.15 ) X ( 0.175 + 0.27 + 0.20 + 0.30 )] X 0.6165 = 65.075
222.899
Bekisting 16.67 X ( 0.2 + 0.3 + 0.2 + 0.3 ) = 16.667 m2

Beton K275 1.00 X = -


Besi Polos 65.075 X = -
Besi Ulir 157.824 X = -
Bekisting 16.667 X = -
Jumlah -
Jumlah Total -
DIBULATKAN - ok

A 1 M3 KOLOM K1.A 20 X 30
1 M3 KOLOM K1.A 20 X 30 0.2 X 0.3 cover beton = 0.025 m
Panjang 1 : 0.2 : 0.3 = 16.67 M1
50
Besi dia 13 6 dia 13
Besi dia 10 0 dia 0
Begel dia 8 - 0.125 8 50

Besi dia 13 16.67 X 6 X 1.04 KG = = 104.189


Besi dia 10 16.67 X 0 X 0 KG = = 0.000
Begel dia 8 - ( 16.67 : 0.125 ) X ( 0.175 + 0.27 + 0.20 + 0.30 )] X 0.39456 = 49.978
154.166
Bekisting 16.67 X ( 0.2 + 0.3 + 0.2 + 0.3 ) = 16.667 m2

Beton K275 1.00 X = -


Besi Polos 49.978 X = -
Besi Ulir 104.189 X = -
Bekisting 16.667 X = -
Jumlah -
Jumlah Total -
DIBULATKAN - ok
B 1 M3 KOLOM Ø40
1 M3 KOLOM Ø40 3.14 X 0.2 cover beton = 0.025 m
Panjang 1 : 3.14 : 0.2 = 7.96 M1
50
Besi dia 13 8 dia 13
Besi dia 10 0 dia 0
Begel dia 10 - 0.1 10 50

Besi dia 13 7.96 X 8 X 1.042 KG = = 66.362


Besi dia 10 7.96 X 0 X 0 KG = = 0.000
Begel dia 10 - ( 7.96 : 0.1 ) X ( 1.26 + )] X 0.6165 = 61.650
128.012
Bekisting 7.96 X ( 1.256 ) = 10.000 m2

Beton K275 1.00 X = -


Besi Polos 61.650 X = -
Besi Ulir 66.362 X = -
Bekisting 10.000 X = -
Jumlah -
Jumlah Total -
DIBULATKAN - ok

C 1 M3 KOLOM K3 Ø20
1 M3 KOLOM K3 Ø20 3.14 X 0.1 cover beton = 0.025 m
Panjang 1 : 3.14 : 0.1 = 31.85 M1
50
Besi dia 16 4 dia 16
Besi dia 10 0 dia 0
Begel dia 10 - 0.1 10 50

Besi dia 16 31.85 X 4 X 1.578 KG = = 201.050


Besi dia 10 31.85 X 0 X 0 KG = = 0.000
Begel dia 10 - ( 31.85 : 0.1 ) X ( 1.26 + )] X 0.6165 = 246.600
447.650
Bekisting 31.85 X ( 1.256 ) = 40.000 m2
Beton K275 1.00 X = -
Besi Polos 246.600 X = -
Besi Ulir 201.050 X = -
Bekisting 40.000 X = -
Jumlah -
Jumlah Total -
DIBULATKAN - ok

D 1 M3 KOLOM K3.A Ø20


1 M3 KOLOM K3.A Ø20 3.14 X 0.1 cover beton = 0.025 m
Panjang 1 : 3.14 : 0.1 = 31.85 M1
50
Besi dia 12 4 dia 12
Besi dia 10 0 dia 0
Begel dia 8 - 0.15 8 50

Besi dia 12 31.85 X 4 X 0.888 KG = = 113.090


Besi dia 10 31.85 X 0 X 0 KG = = 0.000
Begel dia 8 - ( 31.85 : 0.15 ) X ( 1.26 + )] X 0.39456 = 105.216
218.306
Bekisting 31.85 X ( 1.256 ) = 40.000 m2

Beton K275 1.00 X = -


Besi Polos 105.216 X = -
Besi Ulir 113.090 X = -
Bekisting 40.000 X = -
Jumlah -
Jumlah Total -
DIBULATKAN - ok

C 1 M3 KOLOM 40 X 25 (K2)
1 M3 KOLOM 45 X 25 0.4 X 0.25 cover beton = 0.025 m
Panjang 1 : 0.4 : 0.25 = 10.00 M1
50
Besi dia 6 4 dia 6
Besi dia 10 0 dia 0
Begel dia 6 - 0.2 6 50
Besi dia 6 10.00 X 4 X 0.222 KG = = 8.878
Besi dia 10 10.00 X 0 X 0 KG = = 0.000
Begel dia 6 - ( 10.00 : 0.2 ) X ( 0.375 + 0.23 + 0.40 + 0.25 )] X 0.22194 = 13.871
22.749
Bekisting 10.00 X ( 0.4 + 0.25 + 0.4 + 0.25 ) = 13.000 m2

Beton K275 1.00 X = -


Besi Polos 13.871 X = -
Besi Ulir 8.878 X = -
Bekisting 13.000 X = -
Jumlah -
Jumlah Total -
DIBULATKAN - ok

D 1 M3 KOLOM 30 X 30 (K1)
1 M3 KOLOM 30 X 30 (K1) 0.3 X 0.3 cover beton = 0.025 m
Panjang 1 : 0.3 : 0.3 = 11.11 M1
45
Besi dia 6 8 dia 6
Besi dia 10 0 dia 0
Begel dia 6 - 0.15 6 45

Besi dia 6 11.11 X 8 X 0.222 KG = = 19.728


Besi dia 10 11.11 X 0 X 0 KG = = 0.000
Begel dia 6 - ( 11.11 : 0.15 ) X ( 0.275 + 0.27 + 0.30 + 0.30 )] X 0.22194 = 18.906
38.634
Bekisting 11.11 X ( 0.3 + 0.3 + 0.3 + 0.3 ) = 13.333 m2
Beton K275 1.00 X = -
Besi Polos 18.906 X = -
Besi Ulir 19.728 X = -
Bekisting 13.333 X = -
Jumlah -
Jumlah Total -
DIBULATKAN - ok

E 1 M3 KOLOM 45 X 45 (K1' Lt1)


1 M3 KOLOM 45 X 45 0.45 X 0.45 cover beton = 0.025 m
Panjang 1 : 0.45 : 0.45 = 4.94 M1
45
Besi dia 22 12 dia 22
Besi dia 10 0 dia 0
Begel dia 10 - 0.15 10 45

Besi dia 22 4.94 X 12 X 2.984 KG = = 176.821


Besi dia 10 4.94 X 0 X 0 KG = = 0.000
Begel dia 10 - ( 4.94 : 0.15 ) X ( 0.425 + 0.43 + 0.45 + 0.45 )] X 0.6165 = 35.519
212.340
Bekisting 4.94 X ( 0.45 + 0.45 + 0.45 + 0.45 ) = 8.889 m2

Beton K275 1.00 X = -


Besi Polos 35.519 X = -
Besi Ulir 176.821 X = -
Bekisting 8.889 X = -
Jumlah -
Jumlah Total -
DIBULATKAN - ok
F 1 M3 KOLOM 45 X 45 (K1' Lt2, Lt3, Lt4, Lt5, Lt6, TR)
1 M3 KOLOM 45 X 45 0.45 X 0.45 cover beton = 0.025 m
Panjang 1 : 0.45 : 0.45 = 4.94 M1
45
Besi dia 22 8 dia 22
Besi dia 10 0 dia 0
Begel dia 10 - 0.15 10 45

Besi dia 22 4.94 X 8 X 2.984 KG = = 117.881


Besi dia 10 4.94 X 0 X 0 KG = = 0.000
Begel dia 10 - ( 4.94 : 0.15 ) X ( 0.425 + 0.43 + 0.45 + 0.45 )] X 0.6165 = 35.519
153.399
Bekisting 4.94 X ( 0.45 + 0.45 + 0.45 + 0.45 ) = 8.889 m2

Beton K275 1.00 X = -


Besi Polos 35.519 X = -
Besi Ulir 117.881 X = -
Bekisting 8.889 X = -
Jumlah -
Jumlah Total -
DIBULATKAN - ok

H 1 M3 KOLOM K2 25 X 25
1 M3 KOLOM 25 X 25 0.25 X 0.25 cover beton = 0.025 m
Panjang 1 : 0.25 : 0.25 = 16.00 M1
30
Besi dia 16 8 dia 16
Besi dia 10 0 dia 0
Begel dia 10 - 0.175 10 30

Besi dia 16 16.00 X 8 X 1.578 KG = = 202.015


Besi dia 10 16.00 X 0 X 0 KG = = 0.000
Begel dia 10 - ( 16.00 : 0.175 ) X ( 0.225 + 0.23 + 0.25 + 0.25 )] X 0.6165 = 53.547
255.562
Bekisting 16.00 X ( 0.25 + 0.25 + 0.25 + 0.25 ) = 16.000 m2
Beton K275 1.00 X = -
Besi Polos 53.547 X = -
Besi Ulir 202.015 X = -
Bekisting 16.000 X = -
Jumlah -
Jumlah Total -
DIBULATKAN - ok

I 1 M3 KOLOM K3 20 X 20
1 M3 KOLOM 20 X 20 0.2 X 0.2 cover beton = 0.025 m
Panjang 1 : 0.2 : 0.2 = 25.00 M1
30
Besi dia 13 4 dia 13
Besi dia 10 0 dia 0
Begel dia 10 - 0.175 10 30

Besi dia 13 25.00 X 4 X 1.042 KG = = 104.188


Besi dia 10 25.00 X 0 X 0 KG = = 0.000
Begel dia 10 - ( 25.00 : 0.175 ) X ( 0.175 + 0.18 + 0.20 + 0.20 )] X 0.6165 = 66.054
170.242
Bekisting 25.00 X ( 0.2 + 0.2 + 0.2 + 0.2 ) = 20.000 m2

Beton K275 1.00 X = -


Besi Polos 66.054 X = -
Besi Ulir 104.188 X = -
Bekisting 20.000 X = -
Jumlah -
Jumlah Total -
DIBULATKAN - ok

I 1 M3 KOLOM K4 20 X 20
1 M3 KOLOM 20 X 20 0.2 X 0.2 cover beton = 0.025 m
Panjang 1 : 0.2 : 0.2 = 25.00 M1
30
Besi dia 13 4 dia 13
Besi dia 10 0 dia 0
Begel dia 8 - 0.175 8 30

Besi dia 13 25.00 X 4 X 1.042 KG = = 104.188


Besi dia 10 25.00 X 0 X 0 KG = = 0.000
Begel dia 8 - ( 25.00 : 0.175 ) X ( 0.175 + 0.18 + 0.20 + 0.20 )] X 0.39456 = 42.274
146.463
Bekisting 25.00 X ( 0.2 + 0.2 + 0.2 + 0.2 ) = 20.000 m2

Beton K275 1.00 X = -


Besi Polos 42.274 X = -
Besi Ulir 104.188 X = -
Bekisting 20.000 X = -
Jumlah -
Jumlah Total -
DIBULATKAN - ok

J 1 M3 KOLOM 30 X 30 (K2" TR)


1 M3 KOLOM 30 X 30 0.3 X 0.3 cover beton = 0.025 m
Panjang 1 : 0.3 : 0.3 = 11.11 M1
30
Besi dia 19 8 dia 19
Besi dia 10 0 dia 0
Begel dia 10 - 0.15 10 30

Besi dia 19 11.11 X 8 X 2.226 KG = = 197.828


Besi dia 10 11.11 X 0 X 0 KG = = 0.000
Begel dia 10 - ( 11.11 : 0.15 ) X ( 0.275 + 0.27 + 0.30 + 0.30 )] X 0.6165 = 52.517
250.345
Bekisting 11.11 X ( 0.3 + 0.3 + 0.3 + 0.3 ) = 13.333 m2

Beton K275 1.00 X = -


Besi Polos 52.517 X = -
Besi Ulir 197.828 X = -
Bekisting 13.333 X = -
Jumlah -
Jumlah Total -
DIBULATKAN - ok
K 1 M3 KOLOM 30 X 30 (K2"' Lt1, Lt2, TR)
1 M3 KOLOM 30 X 30 0.3 X 0.3 cover beton = 0.025 m
Panjang 1 : 0.3 : 0.3 = 11.11 M1
30
Besi dia 19 8 dia 19
Besi dia 10 0 dia 0
Begel dia 10 - 0.15 10 30

Besi dia 19 11.11 X 8 X 2.226 KG = = 197.828


Besi dia 10 11.11 X 0 X 0 KG = = 0.000
Begel dia 10 - ( 11.11 : 0.15 ) X ( 0.275 + 0.27 + 0.30 + 0.30 )] X 0.6165 = 52.517
250.345
Bekisting 11.11 X ( 0.3 + 0.3 + 0.3 + 0.3 ) = 13.333 m2

Beton K275 1.00 X = -


Besi Polos 52.517 X = -
Besi Ulir 197.828 X = -
Bekisting 13.333 X = -
Jumlah -
Jumlah Total -
DIBULATKAN - ok

L 1 M3 KOLOM 30 X 30 (K2"' Lt3, Lt4, Lt5, Lt6)


1 M3 KOLOM 30 X 30 0.3 X 0.3 cover beton = 0.025 m
Panjang 1 : 0.3 : 0.3 = 11.11 M1
30
Besi dia 19 4 dia 19
Besi dia 10 0 dia 0
Begel dia 10 - 0.15 10 30

Besi dia 19 11.11 X 4 X 2.226 KG = = 98.914


Besi dia 10 11.11 X 0 X 0 KG = = 0.000
Begel dia 10 - ( 11.11 : 0.15 ) X ( 0.275 + 0.27 + 0.30 + 0.30 )] X 0.6165 = 52.517
151.431
Bekisting 11.11 X ( 0.3 + 0.3 + 0.3 + 0.3 ) = 13.333 m2
Beton K275 1.00 X = -
Besi Polos 52.517 X = -
Besi Ulir 98.914 X = -
Bekisting 13.333 X = -
Jumlah -
Jumlah Total -
DIBULATKAN - ok

M 1 M3 KOLOM 30 X 100 (K3 Lt1)


1 M3 KOLOM 30 X 100 0.3 X 1 cover beton = 0.025 m
Panjang 1 : 0.3 : 1= 3.33 M1

Besi dia 16 40 dia 16


Besi dia 10 0 dia 0
Begel dia 10 - 0.15 10 100

Besi dia 16 3.33 X 40 X 1.578 KG = = 210.432


Besi dia 10 3.33 X 0 X 0 KG = = 0.000
Begel dia 10 - ( 3.33 : 0.15 ) X ( 0.275 + 0.98 + 0.30 + 1.00 )] X 0.6165 = 34.935
245.367
Bekisting 3.33 X ( 0.3 + 1+ 0.3 + 1) = 8.667 m2

Beton K275 1.00 X = -


Besi Polos 34.935 X = -
Besi Ulir 210.432 X = -
Bekisting 8.667 X = -
Jumlah -
Jumlah Total -
DIBULATKAN - ok

N 1 M3 KOLOM 30 X 100 (K3 Lt2)


1 M3 KOLOM 30 X 100 0.3 X 1 cover beton = 0.025 m
Panjang 1 : 0.3 : 1= 3.33 M1

Besi dia 16 32 dia 19


Besi dia 10 0 dia 0
Begel dia 10 - 0.15 10 100

Besi dia 16 3.33 X 32 X 2.226 KG = = 237.394


Besi dia 10 3.33 X 0 X 0 KG = = 0.000
Begel dia 10 - ( 3.33 : 0.15 ) X ( 0.275 + 0.98 + 0.30 + 1.00 )] X 0.6165 = 34.935
272.329
Bekisting 3.33 X ( 0.3 + 1+ 0.3 + 1) = 8.667 m2

Beton K275 1.00 X = -


Besi Polos 34.935 X = -
Besi Ulir 237.394 X = -
Bekisting 8.667 X = -
Jumlah -
Jumlah Total -
DIBULATKAN - ok

O 1 M3 KOLOM 30 X 100 (K3 Lt3, Lt4, Lt5, Lt6, TR)


1 M3 KOLOM 30 X 100 0.3 X 1 cover beton = 0.025 m
Panjang 1 : 0.3 : 1= 3.33 M1

Besi dia 16 16 dia 19


Besi dia 10 0 dia 0
Begel dia 10 - 0.15 10 100

Besi dia 16 3.33 X 16 X 2.226 KG = = 118.697


Besi dia 10 3.33 X 0 X 0 KG = = 0.000
Begel dia 10 - ( 3.33 : 0.15 ) X ( 0.275 + 0.98 + 0.30 + 1.00 )] X 0.6165 = 34.935
153.632
Bekisting 3.33 X ( 0.3 + 1+ 0.3 + 1) = 8.667 m2

Beton K275 1.00 X = -


Besi Polos 34.935 X = -
Besi Ulir 118.697 X = -
Bekisting 8.667 X = -
Jumlah -
Jumlah Total -
DIBULATKAN - ok

P
1 M3 BALOK B1 30 X 60 0.3 X 0.6 cover beton = 0.025 m

Panjang 1 : 0.3 : 0.6 = 5.56 M1

Besi dia 16 11 dia 16


Besi dia 13 4 dia 13
Begel dia 8 - 0.15 dia 8

Besi dia 16 5.56 X 11 X 1.578 KG = = 96.448


Besi dia 13 5.56 X 4 X 1.042 KG = = 23.153
Begel dia 8 - ( 5.56 : 0.15 ) X ( 0.275 + 0.58 + 0.3 + 0.6 )] X 0.39456 = 25.573
145.174
Bekisting 5.56 X ( 0.3 + 0.6 + 0.3 + 0.6 ) = 10.000 m2
Beton K275 1.00 X = -
Besi Polos 48.726 X = -
Besi Ulir 96.448 X = -
Bekisting 10.000 X = -
Jumlah -
Keuntungan -
Jumlah Total -
DIBULATKAN - OK
Q
1 M3 BALOK B2 25 X 50 0.25 X 0.5 cover beton = 0.025 m

Panjang 1 : 0.25 : 0.5 = 8.00 M1

Besi dia 16 8 dia 16


Besi dia 10 4 dia 10
Begel dia 8 - 0.15 8

Besi dia 16 8.00 X 8 X 1.578 KG = = 101.007


Besi dia 10 8.00 X 4 X 0.616 KG = = 19.728
Begel dia 8 - ( 8.00 : 0.150 ) X ( 0.225 + 0.48 + 0.25 + 0.5 )] X 0.39456 = 30.513
151.248
Bekisting 8.00 X ( 0.25 + 0.5 + 0.25 + 0.5 ) = 12.000 m2

Beton K275 1.00 X = -


Besi Polos 50.241 X = -
Besi Ulir 101.007 X = -
Bekisting 12.000 X = -
Jumlah -
Keuntungan -
Jumlah Total -
DIBULATKAN - OK
R
1 M3 BALOK B1 20 X 35 0.2 X 0.35 cover beton = 0.025 m

Panjang 1 : 0.2 : 0.35 = 14.29 M1

Besi dia 13 8 dia 13


Besi dia 12 2 dia 12
Begel dia 10 - 0.125 10

Besi dia 13 14.29 X 8 X 1.042 KG = = 119.073


Besi dia 12 14.29 X 2 X 0.888 KG = = 25.365
Begel dia 10 - ( 14.29 : 0.125 ) X ( 0.175 + 0.32 + 0.2 + 0.35 )] X 0.6165 = 73.980
218.417
Bekisting 14.29 X ( 0.2 + 0.35 + 0 + 0.35 ) = 12.857 m2

Beton K275 1.00 X = -


Besi Polos 99.345 X = -
Besi Ulir 119.073 X = -
Bekisting 12.857 X = -
Jumlah -
Keuntungan -
Jumlah Total -
DIBULATKAN - OK
S
1 M3 BALOK B2 15 X 30 0.15 X 0.3 cover beton = 0.025 m

Panjang 1 : 0.15 : 0.3 = 22.22 M1

Besi dia 13 6 dia 13


Besi dia 12 dia 111 x 0.45 50 + ### 0.39456 28.50
Begel dia 10 - 0.125 10
Besi dia 13 22.22 X 6 X 1.042 KG = = 138.918
Besi dia 12 22.22 X 0 X 0 KG = = 0.000
Begel dia 10 - ( 22.22 : 0.125 ) X ( 0.125 + 0.27 + 0.15 + 0.3 )] X 0.6165 = 93.160
232.078
Bekisting 22.22 X ( 0.15 + 0.3 + 0 + 0.3 ) = 16.667 m2
0.3 23.333 m2
Beton K275 1.00 X = - K2.A 260.574
Besi Polos 93.160 X = -
Besi Ulir 138.918 X = -
Bekisting 16.667 X = -
Jumlah -
Keuntungan -
Jumlah Total -
DIBULATKAN - OK
T
1 M3 BALOK B3 15 X 25 0.15 X 0.25 cover beton = 0.025 m

Panjang 1 : 0.15 : 0.25 = 26.67 M1

Besi dia 13 4 dia 13


Besi dia 12 2 dia 12
Begel dia 8 - 0.125 8

Besi dia 13 26.67 X 4 X 1.042 KG = = 111.134


Besi dia 12 26.67 X 2 X 0.888 KG = = 47.347
Begel dia 8 - ( 26.67 : 0.125 ) X ( 0.125 + 0.23 + 0.15 + 0.25 )] X 0.39456 = 63.130
221.611
Bekisting 26.67 X ( 0.15 + 0.25 + 0 + 0.25 ) = 17.333 m2

Beton K275 1.00 X = -


Besi Polos 110.477 X = -
Besi Ulir 111.134 X = -
Bekisting 17.333 X = -
Jumlah -
Keuntungan -
Jumlah Total -
DIBULATKAN - OK
T
1 M3 BALOK RB-1 15 X 25 0.15 X 0.25 cover beton = 0.025 m

Panjang 1 : 0.15 : 0.25 = 26.67 M1

Besi dia 13 dia


Besi dia 12 6 dia 12
Begel dia 8 - 0.175 8

Besi dia 13 26.67 X 0 X 0 KG = = 0.000


Besi dia 12 26.67 X 6 X 0.888 KG = = 142.042
Begel dia 8 - ( 26.67 : 0.175 ) X ( 0.125 + 0.23 + 0.15 + 0.25 )] X 0.39456 = 45.093
187.134
Bekisting 26.67 X ( 0.15 + 0.25 + 0 + 0.25 ) = 17.333 m2
Beton K275 1.00 X = -
Besi Polos 187.134 X = -
Besi Ulir 0.000 X = -
Bekisting 17.333 X = -
Jumlah -
Keuntungan -
Jumlah Total -
DIBULATKAN - OK
U
1 M3 RINGBALK RB-2 15 X 20 0.15 X 0.2 cover beton = 0.025 m

Panjang 1 : 0.15 : 0.2 = 33.33 M1

Besi dia 12 4 dia 12


Besi dia 10 dia
Begel dia 8 - 0.15 dia 8

Besi dia 12 33.33 X 4 X 0.888 KG = = 118.368


Besi dia 10 33.33 X 0 X 0 KG = = 0.000
Begel dia 8 - ( 33.33 : 0.15 ) X ( 0.125 + 0.18 + 0.15 + 0.2 )] X 0.39456 = 56.992
175.360
Bekisting 33.33 X ( 0.15 + 0.2 + 0 + 0.2 ) = 18.333 m2

Beton K275 1.00 X = -


Besi Polos 56.992 X = -
Besi Ulir 118.368 X = -
Bekisting 18.333 X = -
Jumlah -
Keuntungan -
Jumlah Total -
DIBULATKAN - OK
V
1 M3 BALOK B5A 20 X 35 0.2 X 0.35 cover beton = 0.025 m

Panjang 1 : 0.2 : 0.35 = 14.29 M1

Besi dia 16 5 dia 16


Besi dia 12 0 dia 12
Begel dia 8 - 0.1 8

Besi dia 16 14.29 X 5 X 1.578 KG = = 112.731


Besi dia 12 14.29 X 0 X 0.888 KG = = 0.000
Begel dia 8 - ( 14.29 : 0.1 ) X ( 0.175 + 0.32 + 0.2 + 0.35 )] X 0.39456 = 59.184
171.915
Bekisting 14.29 X ( 0.2 + 0.35 + 0.2 + 0.35 ) = 15.714 m2

Beton K275 1.00 X = -


Besi Polos 59.184 X = -
Besi Ulir 112.731 X = -
Bekisting 15.714 X = -
Jumlah -
Keuntungan -
Jumlah Total -
DIBULATKAN - OK
W
1 M3 BALOK B.LIN 12 X 12 0.12 X 0.12 cover beton = 0.025 m

Panjang 1 : 0.12 : 0.12 = 69.44 M1

Besi dia 10 dia 19


Besi dia 10 4 dia 10
Begel dia 8 0.15 8
Besi dia 10 69.44 X 0 X 2.226 KG = = 0.000
Besi dia 10 69.44 X 4 X 0.616 KG = = 171.250
Begel dia 8 ( 69.44 : 0.15 ) X ( 0.095 + 0.1 + 0.12 + 0.12 )] X 0.39456 = 78.547
249.797
Bekisting 69.44 X ( 0.12 + 0.12 + 0.12 + 0.12 ) = 33.333 m2

Beton K275 1.00 X = -


Besi ulir 0.000 X = -
Besi polos 249.797 X = -
Bekisting 33.333 X = -
Jumlah -
Keuntungan -
Jumlah Total -
DIBULATKAN - ok

X 1 M3 TIE BEAM TB1 25 X 40 0.25 X 0.4 cover beton = 0.025 m

Panjang 1 : 0.25 : 0.4 = 10.00 M1

Besi dia 16 8 dia 16


Besi dia 12 2 dia 12
Begel dia 10 0.15 10

Besi dia 16 10.00 X 8 X 1.578 KG = = 126.259


Besi dia 12 10.00 X 2 X 0.888 KG = = 17.755
Begel dia 10 ( 10.00 : 0.15 ) X ( 0.225 + 0.38 + 0.25 + 0.4 )] X 0.6165 = 51.375
195.389
Bekisting 10.00 X ( 0+ 0.4 + 0 + 0.4 ) = 8.000 m2
Beton K275 1.00 X = -
Besi Polos 69.130 X = -
Besi Ulir 126.259 X = -
Bekisting 8.000 X = -
Jumlah -
Keuntungan -
Jumlah Total -
DIBULATKAN -

Y 1 M3 SLOOF S2 15 X 20 0.15 X 0.2 cover beton = 0.025 m

Panjang 1 : 0.15 : 0.2 = 33.33 M1

Besi dia 12 4 dia 12


Besi dia 12 dia
Begel dia 8 0.15 8

Besi dia 12 33.33 X 4 X 0.888 KG = = 118.368


Besi dia 12 33.33 X 0 X 0 KG = = 0.000
Begel dia 8 ( 33.33 : 0.15 ) X ( 0.125 + 0.18 + 0.15 + 0.2 )] X 0.39456 = 56.992
175.360
Bekisting 33.33 X ( 0.15 + 0.2 + 0.15 + 0.2 ) = 23.333 m2

Beton K275 1.00 X = -


Besi Polos 56.992 X = -
Besi Ulir 118.368 X = -
Bekisting 23.333 X = -
Jumlah -
Keuntungan -
Jumlah Total -
DIBULATKAN -
Y 1 M3 SLOOF S1 20 X 30 0.2 X 0.3 cover beton = 0.025 m

Panjang 1 : 0.2 : 0.3 = 16.67 M1

Besi dia 16 6 dia 16


Besi dia 12 0 dia 12
Begel dia 10 0.125 dia 10

Besi dia 16 16.67 X 6 X 1.578 KG = = 157.824


Besi dia 12 16.67 X 0 X 0.888 KG = = 0.000
Begel dia 10 ( 16.67 : 0.125 ) X ( 0.175 + 0.27 + 0.2 + 0.3 )] X 0.6165 = 78.090
235.914
Bekisting 16.67 X ( 0.2 + 0.3 + 0.2 + 0.3 ) = 16.667 m2

Beton K275 1.00 X = -


Besi Polos 78.090 X = -
Besi Ulir 157.824 X = -
Bekisting 16.667 X = -
Jumlah -
Keuntungan -
Jumlah Total -
DIBULATKAN -

V 1 M3 PLAT LANTAI T = 10 CM 1 : 0.100 = 10.000 M2


1 M2
10 cm
Panjang 1.00 M1
Lebar 1.00 M1
1.000
Besi dia 10 - 150 6.667 dia 10 1m
Besi dia 10 - 150 6.667 dia 10

Besi dia 10 - 150 1.00 X 6.667 X 0.616 KG = = 4.110


Besi dia 10 - 150 1.00 X 6.667 X 0.616 KG = = 4.110
8.220
1 M3 = 82.200
Bekisting 1.00 : 0.1 = 10.000 m2

Beton K275 1.00 X = -


Besi POLOS 82.200 X = -
Bekisting 10.000 X = -
Jumlah -
Jumlah Total -
DIBULATKAN - OK

V 1 M3 PLAT LANTAI T = 12 CM 1 : 0.120 = 8.333 M2


1 M2
10 cm
Panjang 1.00 M1
Lebar 1.00 M1
1.000
Besi dia 8 - 200 6.000 dia 8 1m
Besi dia 8 - 200 6.000 dia 8

Besi dia 8 - 200 2.00 X 6.000 X 0.395 KG = = 4.735


Besi dia 8 - 200 2.00 X 6.000 X 0.395 KG = = 4.735
9.469
78.912
Bekisting 1.00 : 0.120 = 8.333 m2

Beton K275 1.00 X = -


Besi POLOS 9.469 X = -
Bekisting #REF! X = #REF!
Jumlah #REF!
Jumlah Total #REF!
DIBULATKAN #REF! OK

W 1 M3 PLAT DINDING T = 15 CM 1 : 0.15 = 6.667 M2


1 M2
Panjang 1.00 M1
Lebar 1.00 M1
Besi dia 12 - 150 5.000 dia 12
Besi dia 12 - 150 5.000 dia 12

Besi dia 12 - 150 2.00 X 5.000 X 0.888 KG = = 8.878


Besi dia 12 - 150 2.00 X 5.000 X 0.888 KG = = 4.439
13.316
1 M3 = 88.776
Bekisting 2.00 : 0.15 = 13.333 m2

Beton K225 1.00 X = -


Besi Polos 88.776 X = -
Besi Ulir 0.000 X = -
Bekisting 13.333 X = -
Jumlah -
Jumlah Total -
DIBULATKAN -

1 M3 PLAT BORDES T = 15 CM 1 : 0.15 = 6.667 M2


1 M2
Panjang 1.00 M1
Lebar 1.00 M1
Besi dia 13 - 150 6.667 dia 13
Besi dia 10 - 150 6.667 dia 10

Besi dia 13 - 150 1.00 X 6.667 X 1.042 KG = = 6.946


Besi dia 10 - 150 1.00 X 6.667 X 0.616 KG = = 4.110
11.056
1 M3 = 73.706
Bekisting 1.00 : 0.15 = 6.667 m2
1 M3 PLAT TANGGA T = 17 CM 1 : 0.17 = 5.882 M2
1 M2
Panjang 1.00 M1
Lebar 1.00 M1

Besi dia 16 - 200 5.000 dia 16


Besi dia 13 - 150 6.667 dia 13
Besi dia 10 - 150 6.667 dia 10
Besi dia 8 - 150 6.667 dia 8

Besi dia 16 - 200 1.00 X 5.000 X 1.578 KG = = 7.890


Besi dia 13 - 150 1.00 X 6.667 X 1.042 KG = = 6.947
Besi dia 10 - 150 1.00 X 6.667 X 0.617 KG = = 4.113
Besi dia 8 - 150 1.00 X 6.667 X 0.395 KG = = 2.633
21.583
1 M3 = 126.961
Bekisting 1.00 : 0.17 = 5.882 m2

1 M3 PLAT JEMBATANT = 15 1 : 0.15 = 6.667 M2


1 M2
Panjang 1.00 M1
Lebar 1.00 M1

Besi dia 10 - 150 6.667 dia 10


Besi dia 10 - 150 6.667 dia 10

Besi dia 10 - 10= 1.00 X 6.667 X 0.616 KG = = 4.110


Besi dia 10 - 10= 1.00 X 6.667 X 0.616 KG = = 4.110
8.220
1 M3 = 54.800
Bekisting 1.00 : 0.15 = 6.667 m2

A1 1 M3 Pondasi PILE CAP P1 1 : 0.5 = 2.000 M2


1 M2
Panjang 1.00 M1
Lebar 1.00 M1

Besi dia 19 - 150 6.667 dia 19


Besi dia 19 - 150 6.667 dia 19

Besi dia 19 - 150 2.00 X 6.667 X 2.226 KG = = 29.674


Besi dia 19 - 150 2.00 X 6.667 X 2.226 KG = = 29.674
59.348
1 M3 = 118.697
Bekisting 2.00 : 0.5 = 4.000 m2

Beton K225 1.00 X = -


Besi Polos X = -
Besi Ulir 118.697 X -
Bekisting 4.000 X = -
Jumlah -
Keuntungan
Jumlah Total -
DIBULATKAN -

A1 1 M3 Pondasi PILE CAP P1 1 : 0.5 = 2.000 M2


1 M2
Panjang 1.00 M1
Lebar 1.00 M1

Besi dia 19 - 150 6.667 dia 19


Besi dia 19 - 150 6.667 dia 19

Besi dia 19 - 150 2.00 X 6.667 X 2.226 KG = = 29.674


Besi dia 19 - 150 2.00 X 6.667 X 2.226 KG = = 29.674
59.348
1 M3 = 118.697
Bekisting 2.00 : 0.5 = 4.000 m2

Beton K225 1.00 X = -


Besi Polos X = -
Besi Ulir 118.697 X -
Bekisting 4.000 X = -
Jumlah -
Keuntungan
Jumlah Total -
DIBULATKAN -

A2 1 M3 Pondasi P2 1.4 X 3.6 cover beton = 0.03 m

Panjang 1 : 1.4 : 0.8 = 0.89 M3

Besi dia 19 dia 19 22.4


Besi dia 16 dia 16 57.6
Begel dia 8 - 0 8

Besi dia 19 0.89 X 0 X 2.226 KG = = 0.000


Besi dia 16 0.89 X 0 X 1.578 KG = = 0.000
Begel dia 8 - ( 0.89 : 0) X ( 1.37 + 3.57 + 1.40 + 3.60 )] X 0.39456 = #DIV/0!
#DIV/0!
Bekisting 0.89 X ( 1.4 + 0.8 + 3.60 + 0.8 ) = 5.893 m2

Beton K225 1.00 X = -


Besi Polos #DIV/0! X = #DIV/0!
Besi Ulir 0.000 X -
Bekisting 5.893 X = -
Jumlah #DIV/0!
Keuntungan
Jumlah Total #DIV/0!
DIBULATKAN #DIV/0!

A3 1 M3 Pondasi P TANGGA 0.6 X 0.6 cover beton = 0.03 m

Panjang 1 : 0.6 : 0.6 = 2.78 M1

Besi dia 16 46.08 dia 19 25.6


Besi dia 16 46.08 dia 16 25.6
Begel dia 8 - 0 8
Besi dia 16 2.78 X 46.08 X 2.226 KG = = 284.872
Besi dia 16 2.78 X 46.08 X 1.578 KG = = 202.015
Begel dia 8 - ( 2.78 : 0) X ( 0.57 + 0.57 + 0.60 + 0.60 )] X 0.39456 = #DIV/0!
#DIV/0!
Bekisting 2.78 X ( 0.6 + 0.6 + 0.60 + 0.6 ) = 6.667 m2

Beton K225 1.00 X = -


Besi Polos #DIV/0! X - = #DIV/0!
Besi Ulir 486.887 X - -
Bekisting 6.667 X = -
Jumlah #DIV/0!
Keuntungan
Jumlah Total #DIV/0!
DIBULATKAN #DIV/0!

A1 1 M3 Pondasi PILE CAP P3 1 : 0.22 = 4.464 M2


1 M2
Panjang 0.80 M1
Lebar 0.80 M1
Tinggi 0.35 M1

Besi dia 12 - 150 6.333 dia 12


Besi dia 12 - 150 6.333 dia 12
Besi dia 12 - 150 3.333 dia 12

Besi dia 12 - 150 1.60 X 6.333 X 0.888 KG = = 8.996


Besi dia 12 - 150 1.60 X 6.333 X 0.888 KG = = 8.996
Besi dia 12 - 150 1.40 X 3.333 X 0.888 KG = = 4.143
22.135
1 M3 = 98.816
Bekisting 1.12 : 0.224 = 5.000 m2
Beton K225 1.00 X = -
Besi Polos X = -
Besi Ulir 98.816 X -
Bekisting 5.000 X = -
Jumlah -
Keuntungan
Jumlah Total -
DIBULATKAN -

A1 1 M3 Pondasi PILE CAP P1 1 : 0.58 = 1.736 M2


1 M2
Panjang 1.20 M1
Lebar 1.20 M1
Tinggi 0.40 M1

Besi dia 13 - 150 8.000 dia 13


Besi dia 13 - 150 8.000 dia 13
Besi dia 13 - 150 2.667 dia 13

Besi dia 13 - 150 2.40 X 8.000 X 1.042 KG = = 20.004


Besi dia 13 - 150 2.40 X 8.000 X 1.042 KG = = 20.004
Besi dia 13 - 150 1.60 X 2.667 X 1.042 KG = = 4.445
44.454
1 M3 = 77.177
Bekisting 1.92 : 0.576 = 3.333 m2

Beton K225 1.00 X = -


Besi Polos X = -
Besi Ulir 77.177 X -
Bekisting 3.333 X = -
Jumlah -
Keuntungan
Jumlah Total -
DIBULATKAN -

A1 1 M3 Pondasi PILE CAP P2 1 : 0.35 = 2.857 M2


1 M2
Panjang 1.00 M1
Lebar 1.00 M1
Tinggi 0.35 M1

Besi dia 13 - 150 6.667 dia 13


Besi dia 13 - 150 6.667 dia 13
Besi dia 13 - 150 2.333 dia 13

Besi dia 13 - 150 2.00 X 6.667 X 1.042 KG = = 13.892


Besi dia 13 - 150 2.00 X 6.667 X 1.042 KG = = 13.892
Besi dia 13 - 150 1.40 X 2.333 X 1.042 KG = = 3.403
31.187
1 M3 = 89.106
Bekisting 1.40 : 0.35 = 4.000 m2

Beton K225 1.00 X = -


Besi Polos X = -
Besi Ulir 89.106 X -
Bekisting 4.000 X = -
Jumlah -
Keuntungan
Jumlah Total -
DIBULATKAN -

A1 1 M3 Pondasi PILE CAP TANG 1 : 0.2 = 5.000 M2


1 M2
Panjang 0.60 M1
Lebar 0.60 M1

Besi dia 16 - 150 4.000 dia 16


Besi dia 16 - 150 4.000 dia 16

Besi dia 16 - 150 1.20 X 4.000 X 1.578 KG = = 7.576


Besi dia 16 - 150 1.20 X 4.000 X 1.578 KG = = 7.576
15.151
1 M3 = 75.756
Bekisting 2.00 : 0.2 = 10.000 m2
Beton K225 1.00 X = -
Besi Polos X = -
Besi Ulir 75.756 X -
Bekisting 10.000 X = -
Jumlah -
Keuntungan
Jumlah Total -
DIBULATKAN -

G 1 titik pondasi Strauss


1 TITik pondasi Strauss DIA 100 0.4 X 0.4 cover beton = 0.025 m
Panjang 5 :

Besi dia 16 6 dia 16


Besi dia 13 dia
Begel dia 8 - 0.15 8

Besi dia 16 5.00 X 6 X 1.578 KG = = 47.347


Besi dia 13 0.00 X 0 X 0 KG = = 0.000
Begel dia 8 - ( 5.00 : 0.15 ) X ( 0.375 + 0.38 + 0.38 + 0.38 )] X 0.39456 = 20.320
67.667
Bekisting 0.00 X ( 0.4 + 0.4 + 0.4 + 0.4 ) = 0.000 m2
2.512
Beton K300 0.28 X = - Per m3 26.938
Besi Polos 20.320 X = -
Besi Ulir 47.347 X = -
Bekisting 0.000 X = -
Jumlah -
Jumlah Total -
DIBULATKAN - ok

1 TITik pondasi Strauss DIA 60 0.4 X 0.6 cover beton = 0.025 m


Panjang 5 : 0.5024 9.95

Besi dia 16 10 dia 10


Besi dia 13 dia
Begel dia 10 - 0.15 10
Besi dia 16 9.95 X 10 X 0.616 KG = = 61.355
Besi dia 13 9.95 X 0 X 0 KG = = 0.000
Begel dia 10 - ( 9.95 : 0.15 ) X ( 0.375 + 0.58 + 0.38 + 0.58 )] X 0.6165 = 78.888
140.244
Bekisting 9.95 X ( 0.4 + 0.6 + 0.4 + 0.6 ) = 19.904 m2
1.413
Beton K300 0.00 X = - Per m3 99.253
Besi Polos 78.888 X = -
Besi Ulir 61.355 X = -
Bekisting 19.904 X = -
Jumlah -
Jumlah Total -
DIBULATKAN - ok

C 1 M3 KOLOM 15 X 15 (KP)
1 M3 KOLOM 15 X 15 0.15 X 0.15 cover beton = 0.025 m
Panjang 1 : 0.15 : 0.15 = 44.44 M1
45
Besi dia 10 0 dia 0
Besi dia 10 4 dia 10
Begel dia 8 - 0.2 8 45

Besi dia 10 44.44 X 0 X 0 KG = = 0.000


Besi dia 10 44.44 X 4 X 0.616 KG = = 109.600
Begel dia 8 - ( 44.44 : 0.2 ) X ( 0.125 + 0.13 + 0.15 + 0.15 )] X 0.39456 = 48.224
157.824
Bekisting 44.44 X ( 0.15 + 0.15 + 0.15 + 0.15 ) = 26.667 m2

Beton K275 1.00 X = -


Besi Polos 157.824 X = -
Besi Ulir 0.000 X = -
Bekisting 26.667 X = -
Jumlah -
Jumlah Total -
DIBULATKAN - ok
BESI BETON ( P = 12 m ) BESI SIKU

UKURAN JENIS BERAT/m' BERAT/6m


UKURAN
DIAMETER kg kg
f 6 mm polos 0.2217 20.20.3 mm 5.31
f 8 mm polos 0.3950 25.25.3 mm 6.72
f 10 mm polos 0.6167 7.4 25.25.5 mm 10.60
f 12 mm polos 0.8917 30.30.3 mm 8.16
f 13 mm ulir 1.0417 40.40.3 mm 11.00
f 14 mm polos 1.2083 40.40.4 mm 14.50
f 16 mm polos 1.5833 19.000 40.40.5 mm 18.00
f 16 mm ulir 1.5833 45.45.4 mm 16.44
f 19 mm ulir 2.2300 45.45.5 mm 20.50
f 22 mm ulir 2.9800 50.50.4 mm 18.40
f 25 mm ulir 3.8500 50.50.5 mm 22.50
f 32 mm ulir 6.3125 50.50.6 mm 27.58
60.60.5 mm 27.30
BESI PLAT HITAM 60.60.6 mm 32.52
65.65.6 mm 35.46
BERAT/lbr 70.70.6 mm 38.28
UKURAN
kg 70.70.7 mm 44.28
1,2 X 1200 X 2400 mm 28.00 75.75.6 mm 41.22
1,4 X 1200 X 2400 mm 33.00 75.75.7 mm 45.00
1,5 X 1200 X 2400 mm 35.00 75.75.8 mm 54.18
1,8 X 1200 X 2400 mm 42.00 75.75.9 mm 59.80
1,9 X 1200 X 2400 mm 44.50 80.80.8 mm 57.96
2 X 1200 X 2400 mm 46.70 90.90.7 mm 57.54
2,3 X 1200 X 2400 mm 54.00 90.90.9 mm 73.20
2,6 X 1200 X 2400 mm 60.70 90.90.10 mm 79.80
2,8 X 1200 X 2400 mm 65.30 100.100.7 mm 64.25
2,9 X 1200 X 2400 mm 67.60 100.100.10 mm 90.60
3 X 1200 X 2400 mm 70.00 120.120.11 mm 119.40
3,2 X 1200 X 2400 mm 74.70 120.120.12 mm 130.00
4 X 1200 X 2400 mm 93.30 125.125.12 mm 140.00
4,5 X 1200 X 2400 mm 105.00 130.130.9 mm 107.10
5 X 1200 X 2400 mm 117.00 130.130.12 mm 140.10
6 X 1200 X 2400 mm 140.00 150.150.10 mm 140.00
8 X 1200 X 2400 mm 187.00 150.150.12 mm 164.00
9 X 1200 X 2400 mm 210.00 150.150.15 mm 202.00
10 X 1200 X 2400 mm 233.00 80.90 200.200.15 mm 272.00
12 X 1200 X 2400 mm 280.00 200.200.20 mm 358.00
13 X 1200 X 2400 mm 303.00 200.200.25 mm 442.00
15 X 1200 X 2400 mm 350.00 250.250.25 mm 562.00
16 X 1200 X 2400 mm 373.00
18 X 1200 X 2400 mm 420.00
19 X 1200 X 2400 mm 443.00
20 X 1200 X 2400 mm 467.00
21 X 1200 X 2400 mm 490.00
22 X 1200 X 2400 mm 513.00
25 X 1200 X 2400 mm 583.00
28 X 1200 X 2400 mm 653.00
30 X 1200 X 2400 mm 700.00
32 X 1200 X 2400 mm 747.00
38 X 1200 X 2400 mm 887.00
42 X 1200 X 2400 mm 980.00
45 X 1200 X 2400 mm 1,050.00
50 X 1200 X 2400 mm 1,167.00
65 X 1200 X 2400 mm 1,516.00
75 X 1200 X 2400 mm 1,750.00
85 X 1200 X 2400 mm 1,983.00
100 X 1200 X 2400 mm 2,333.00
BESI KANAL UNP BESI KANAL "C" LIP

BERAT/6m BERAT/6m
UKURAN UKURAN
kg kg
50.36.5 mm 33.50 60.30.10.1,2 7.44
65.42.5,5 mm 42.50 60.30.10.2,3
75.40.5 mm 41.50 75.35.10.1,6 13.90
80.45.5 mm 47.00 75.45.15.2,3 19.50
100.50.5 mm 56.20 100.50.20.2,3 24.40
120.55.6 mm 75.00 100.50.20.3,2 33.00
125.55.6 mm 80.40 125.50.20.2,3 27.10
140.60.7 mm 96.00 125.50.20.3,2 36.80
150.75.6,5 mm 112.00 150.50.20.2,3 30.00
160.66.7 mm 115.50 150.50.20.3,2 40.60
180.75.7 mm 132.00 150.65.20.2,3 33.00
200.80.7,5 mm 152.00 150.65.20.3,2 45.10
220.80.9 mm 187.50 200.75.20.3,2 56.00
240.85.9,5 mm 205.00
250.80.7,1 mm 182.50
250.90.9 mm 208.00
260.90.10 mm 114.00
300.90.9 mm 229.00
300.100.10 mm 278.00
380.100.10,5 mm 337.50
PIPA PERSEGI

BESI WIREMESH UKURAN ( mm ) TEBAL ( mm )


BERAT/6m
kg
BERAT/M2 12,5 X 12,5 0.90 0.3320
UKURAN
kg 15 X 15 0.90 0.4030
M 5 (2.1 M x 5.4 m) 2.05 20 X 20 0.90 0.5440
M 6 (2.1 M x 5.4 m) 2.95 25 X 25 1.00 0.7590
M 7 (2.1 M x 5.4 m) 4.02 30 X 30 1.00 0.9150
M 8 (2.1 M x 5.4 m) 5.25 40 X 40 1.20 1.4680
M 9 (2.1 M x 5.4 m) 6.64 10 X 20 0.90 0.4030
12,5 X 27,5 0.90 0.5440
15 X 30 0.90 0.6150
20 X 40 1.00 0.9150
25 X 50 1.40 1.5970
20 X 60 1.40 1.9260
LEBAR PANJANG BERAT/lbr
mm mm kg 30,000,000.00
16 6000 2.3 60,000,000.00
19 6000 2.7 1,250,000.00
25 6000 3.53
32 6000 4.52
38 6000 5.37
19 6000 4.03
25 6000 5.4
32 6000 6.8
38 6000 8.3
50 6000 10.6
19 6000 5.4
25 6000 7.1
32 6000 9.2
38 6000 10.7
50 6000 14.5
65 6000 18.5
75 6000 21.5
85 6000 25.5
100 6000 28.5
150 6000 44.5 12.15
25 6000 10.6
32 6000 14
38 6000 16.1 16.22
50 6000 21.2
65 6000 27.5
75 6000 32
85 6000 38.3
100 6000 42.5
150 6000 64
25 6000 14.2
38 6000 21.5
50 6000 28.5
65 6000 37
75 6000 42.5
100 6000 56.5
150 6000 85
38 6000 29
50 6000 38
100 6000 76
150 6000 113
38 6000 34
50 6000 45
65 6000 58.5
75 6000 67.5
100 6000 89.5
125 6000 112
150 6000 134

BESI W.F

UKURAN TEBAL PANJANG BERAT/Btg


cm mm M' kg
100 X 50 X 5 7 12 112
125X 60 X 6 8 12 158.4
148X 100 X 6 9 12 253.2
150X 75 X 5 7 12 168
175X 90 X 5 8 12 217.2
198X 99 X 4.5 7 12 218.4
200X 100 X 3.2 4.5 12 143
200X 100 X 5.5 8 12 256
248 X 124 X 5 8 12 308.4
250 X 125 X 6 9 12 355.2
298 X 149 X 6 8 12 384
300 X 150 X 6.5 9 12 440.4
346 X 174 X 6 9 12 497
350 X 175 X 7 11 12 595.2
396 X 199 X 7 11 12 679.5
400 X 200 X 8 13 12 792
446 X 1990 X 8 12 12 794.4
450 X 200 X 98 14 12 912
496 X 199 X 9 14 12 954
500 X 200 X 10 16 12 1075
588 X 300 X 10 16 12 1812
596 X 199 X 9 14 12 1135
600 X 200 X 11 17 12 1272
600 X 300 X 13 20 12 1992 166.00
700 X 300 X 13 24 12 2290
800 X 300 X 14 26 12 2520

BESI I.N.P

UKURAN TEBAL PANJANG BERAT/Btg


cm mm M' kg
80 x 42 x 3.9 x 5.9 2.3 6 38.5
100 x 50 x 4.5 x 6.8 2.7 6 50.6
120 x 58 x 5.1 x 7.7 3.1 6 67.5
120 x 58 x 5.1 x 8.6 3.4 6 87.5
160 x 74 x 6.5 x 9.5 3.8 6 108.5
180 x 82 x 6.9 x 10.4 4.1 6 270
200 x 90 x 7.5 x 11.3 4.5 6 315
220 x 98 x 8.1 x 12.2 4.9 6 373
240 x 106 x 8.7 x 13.1 5.2 6 435
250 x 125 x 7.5 x 12.5 6 460
260 x 113 x 9.4 x 14.1 5.6 6 503
280 x 119 x 10.1 x 15.2 6.1 6 580
300 x 125 x 10.8 x 16.2 6.5 6 661
320 x 131 x 11.3x 17.3 6.9 6 760
340 x 137 x 12.2x 18.3 7.3 6 833
360 x 143 x 13 x 19.5 7.8 6 926
380 x 149 x 13.7x 20.5 7.8 6 1026
400 x 155 x 14.4 x 21.6 8.6 6 1136.5
450 x 170 x 16.2 x 24.3 9.7 6 1400
500 x 185 x 18 x 27 10.8 6 1707
LBK LANTAI 1
NO TYPE KUSEN LUAS L K QTT JML. LUAS L K SAT
1 P1 3.00 2.00 6.00 m2
2 P2 1.94 4.00 7.74 m2
3 P3 1.94 1.00 1.94 m2
4 P4 1.83 9.00 16.45 m2
5 PL1 5.97 4.00 23.89 m2
6 PL2 8.61 4.00 34.44 m2
7 PL3 11.87 1.00 11.87 m2
8 J1 4.40 2.00 8.79 m2
9 J2 6.40 2.00 12.80 m2
10 J3 7.70 3.00 23.10 m2
11 J4 5.70 3.00 17.10 m2
12 J5 5.71 1.00 5.71 m2
13 J6 0.90 1.00 0.90 m2
14 J7 10.61 1.00 10.61 m2
15 BV1 0.54 9.00 4.86 m2
JUMLAAH TOTAL 186.19 m2

LUASAN POLA LANTAI LT. 1


NO TYPE KUSEN LUAS LANTAI
1 LT.60X60 POLIS 289.71
2 LT.60X60 UN 77.71
3 LT.30X30 42.31
4 PARQUET 49.66
5 PLINT 10X60 137.30

LUASAN POLA LANTAI LT. 2


NO TYPE KUSEN LUAS LANTAI
1 LT.60X60 POLIS 101.69
2 LT.60X60 UN -
3 LT.30X30 -
4 PARQUET -
5 PLINT 10X60 40.07

LUASAN PLAFOND LANTAI LT. 1


NO TYPE KUSEN LUAS LANTAI
1 GYPSUM 256.48
2 PVC 208.19
3 LIST PROFIL GYPSUM 236.41
4 LIST PROFIL PVC 228.97

LUASAN PLAFOND LANTAI LT. 2


NO TYPE KUSEN LUAS LANTAI
1 GYPSUM 206.30
2 PVC 128.77
3 LIST PROFIL 98.79
4 LIST PROFIL PVC 134.14
PANJANG KUSEN LUAS KACA
5.65 1.75
5.19 -
5.19 1.14
5.14 -
7.05 3.29
8.30 5.99
9.85 7.76
10.40 3.51
12.40 5.31
13.70 6.48
11.70 4.68
11.60 4.59
4.52 0.67
- 6.66
3.00 0.34
LBK LANTAI 2
NO TYPE KUSENLUAS L K QTT LUAS L K LUAS KACA
SATPANJANG KUSEN
1 P1 3.00 1.00 3.00 m2 5.194 1.14
2 PL2 8.61 2.00 17.22 m2 8.3 5.9892
3 J4 5.70 4.00 22.80 m2 11.70 4.68
4 J8 2.25 1.00 2.25 m2 6 1.8225
5 BV2 1.20 2.00 2.40 m2 5.8 0.7
6 BV3 2.14 3.00 6.41 m2 7.95 1.43
JUMLAH TOTAL 54.08