Anda di halaman 1dari 43

R E K A P I T U L A S I

OWNER ESTIMATE (OE)


PEKERJAAN : PEMBUATAN PLAZA PUSAT JAJANAN KULINER (2 UNIT)

LOKASI : KAWASAN WISATA DANAU LORULUNG, KEC. WERTAMBRIAN, KAB. MTB

SUMBER DANA : DANA ALOKASI KHUSUS (DAK) KAB. MTB

TAHUN : 2018

No. Uraian Pekerjaan Jumlah


1 2 3

I PEKERJAAN PENDAHULUAN Rp 20,079,724.00

II PEKERJAAN TANAH Rp 28,894,439.45

III PEKERJAAN PONDASI Rp 32,782,181.54

IV PEKERJAAN BETON DAN PEMBESIAN Rp 39,979,528.42

V PEKERJAAN DINDING DAN LANTAI Rp 100,272,055.29

VI PEKERJAAN KAYU Rp 35,169,884.15

VII PEKERJAAN PENUTUP ATAP DAN PLAFOND Rp 47,413,989.50

VIII PEKERJAAN PENGGANTUNG DAN PENGUNCI Rp 4,894,663.68

IX PEKERJAAN PENGECATAN Rp 29,782,157.40

X PEKERJAAN LISTRIK Rp 7,017,840.00

XI PEKERJAAN SANITASI Rp 8,713,618.50

BIAYA KONSTRUKSI FISIK ……………………………………………………………………… Rp 355,000,081.94

DIKALI 2 UNIT…………………………………………………………………………………………………… Rp 710,000,163.87

PPN (10%)……………………………………………………………………………………………………………
Rp 71,000,016.39

TOTAL BIAYA KESELURUHAN…………………………………………………………………… Rp 781,000,180.26

DIBULATKAN……………………………………………………………………………………………………… Rp 781,000,000.00

Terbilang : Tujuh Ratus Delapan Puluh Satu Juta Rupiah

Saumlaki, Selasa 5 Juni 2018


Disetujui :
Kepala Dinas Pariwisata
Kabupaten Maluku Tenggara Barat

Ir. MYNDRIK BATLOLONA, MT


Pembina Tk. I
NIP. 19620827 199103 1 002
OWNER ESTIMATE
(OE)
PEKERJAAN : PEMBUATAN PLAZA PUSAT JAJANAN KULINER
LOKASI : KAWASAN WISATA DANAU LORULUNG, KEC. WERTAMBRIAN, KAB. MTB
SUMBER DANA : DANA ALOKASI KHUSUS (DAK) KAB. MTB
TAHUN : 2018

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH

1 2 3 4 5 6

I PEKERJAAN PENDAHULUAN
1 Pembuatan direksi keet Ls 1.000 Rp 8,000,000.00 Rp 8,000,000.00
2 Pekerjaan pengukuran dan pemasangan bowplank M' 54.000 Rp 75,006.00 Rp 4,050,324.00
3 Pekerjaan Pembersihan awal M² 170.000 Rp 17,820.00 Rp 3,029,400.00
4 Pekerjaan Pembersihan akhir Ls 1.000 Rp 5,000,000.00 Rp 5,000,000.00
SUB TOTAL Rp 20,079,724.00

II PEKERJAAN TANAH
1 Galian tanah pondasi M³ 44.080 Rp 73,170.00 Rp 3,225,333.60
2 Urugan kembali tanah galian M³ 17.480 Rp 54,540.00 Rp 953,359.20
3 Urugan pasir bawah pondasi M³ 3.040 Rp 677,268.00 Rp 2,058,894.72
4 Pekerjaan urugan tanah peninggi lantai M³ 36.646 Rp 513,270.00 Rp 18,809,292.42
5 Pekerjaan urugan pasir bawah lantai M³ 5.681 Rp 677,268.00 Rp 3,847,559.51
SUB TOTAL Rp 28,894,439.45

III PEKERJAAN PONDASI


1 Pekerjaan pondasi batu karang M³ 16.720 Rp 1,353,742.20 Rp 22,634,569.58
2 Pekerjaan pasangan aanstamping batu karang M³ 11.400 Rp 890,141.40 Rp 10,147,611.96
SUB TOTAL Rp 32,782,181.54

IV PEKERJAAN BETON DAN PEMBESIAN


1 Pekerjaan sloof 15/20 camp. 1:2:3 (200 kg/m³) M³ 2.489 Rp 4,464,013.93 Rp 11,112,671.65
2 Pekerjaan kolom praktis 15/15 camp. 1:2:3 (150 kg/m³) M³ 1.411 Rp 5,583,456.28 Rp 7,876,860.95
3 Pekerjaan ring balk 15/20 camp. 1:2:3 (200 kg/m³) M³ 2.128 Rp 5,319,364.21 Rp 11,319,607.05
4 Pekerjaan dak beton bertulang M³ 1.795 Rp 5,387,403.21 Rp 9,670,388.77
SUB TOTAL Rp 39,979,528.42

V PEKERJAAN DINDING DAN LANTAI


1 Pasang dinding batako 1 Pc : 4 Ps M² 169.165 Rp 162,075.60 Rp 27,417,518.87
2 Plesteran dinding 1 Pc : 4 Ps tebal 15 mm M² 387.540 Rp 74,420.86 Rp 28,841,058.53
3 Pekerjaan acian dinding M² 387.540 Rp 39,322.80 Rp 15,239,157.91
10 Pasang lantai keramik 40x40 M² 66.300 Rp 206,538.12 Rp 13,693,477.36
11 Pasang keramik dinding kamar mandi 20x25 M² 24.000 Rp 194,294.16 Rp 4,663,059.84
12 Pasang lantai keramik kamar mandi 40x40 M² 4.990 Rp 206,538.12 Rp 1,030,625.22
13 Pasang lantai keramik teras 40x40 M² 45.450 Rp 206,538.12 Rp 9,387,157.55
SUB TOTAL Rp 100,272,055.29

VI PEKERJAAN KAYU
1 Pasang kusen pintu ventilasi kayu besi 5/10 M³ 0.421 Rp 8,341,110.00 Rp 3,511,607.31
2 Pasang reling teras M² 3.240 Rp 649,687.50 Rp 2,104,987.50
3 Pasang Tiang & balok teras M³ 1.148 Rp 8,341,110.00 Rp 9,575,594.28
3 Pasang pintu dan jendela panil papan M² 18.670 Rp 523,584.00 Rp 9,775,313.28
4 Pasang kaca mati 5 mm M² 0.350 Rp 272,892.24 Rp 95,512.28
5 Pekerjaan penutup plafond tripleks 4 mm M² 107.530 Rp 58,455.00 Rp 6,285,666.15
6 Pekerjaan penutup plafond tripleks 4 mm teras M² 65.370 Rp 58,455.00 Rp 3,821,203.35
SUB TOTAL Rp 35,169,884.15
NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH

1 2 3 4 5 6

VII PEKERJAAN PENUTUP ATAP DAN PLAFOND


- KUDA-KUDA KAYU
1 Pekerjaan kuda-kuda atap kayu kls I 5/10 M³ 0.820 Rp 7,622,640.00 Rp 6,246,753.48
2 Pekerjaan pasang gording kayu kls I 5/10 M³ 0.822 Rp 8,932,086.00 Rp 7,337,708.65
Pekerjaan kuda-kuda atap kayu kls I 5/10 ekspos M³ 0.284 Rp 9,406,206.00 Rp 2,673,714.06
Pekerjaan pasang gording kayu kls I 5/10 ekspos M³ 0.3497 Rp 9,406,206.00 Rp 3,288,879.93
3 Pekerjaan pasang atap Zenk Gelombang BJLS-30 M² 180.590 Rp 81,097.20 Rp 14,645,343.35
4 Pekerjaan pasang atap nok senk M1 23.200 Rp 52,806.60 Rp 1,225,113.12
- PLAFOND
5 Pekerjaan rangka plafond kayu kls II M² 107.530 Rp 111,564.00 Rp 11,996,476.92
6 Pasang list kayu profil 5 cm M1 126.200 Rp 57,213.00 Rp 7,220,280.60
7 Pasang Lisplank papan kayu kls I 2,5x25 M1 84.660 Rp 84,996.00 Rp 7,195,761.36
SUB TOTAL Rp 47,413,989.50

VIII PEKERJAAN PENGGANTUNG DAN PENGUNCI


1 Pasang engsel pintu Bh 24.000 Rp 75,522.24 Rp 1,812,533.76
2 Pasang grendel pintu biasa Bh 8.000 Rp 46,794.24 Rp 374,353.92
3 Pasang kunci pintu tanam Bh 8.000 Rp 338,472.00 Rp 2,707,776.00
4 Pasang engsel jendela Bh 54.000 Rp 57,542.40 Rp 3,107,289.60
5 Pasang grendel jendela Bh 18.000 Rp 46,794.24 Rp 842,296.32
6 Pasang tarikan jendela Bh 6.000 Rp 40,962.24 Rp 245,773.44
7 Pasang kait angin Bh 6.000 Rp 37,884.24 Rp 227,305.44
SUB TOTAL Rp 4,894,663.68

IX PEKERJAAN PENGECATAN
1 Pekerjaan pengecatan dinding luar (exterior) M² 158.960 Rp 37,109.34 Rp 5,898,900.69
2 Pekerjaan pengecetan dinding dalam (interior) M² 146.350 Rp 37,109.34 Rp 5,430,951.91
3 Pekerjaan pengecetan waterproofing dak M² 17.950 Rp 63,666.00 Rp 1,142,804.70
4 Pekerjaan pengecatan kusen pintu, jendela, ventilasi dan listplank M² 35.109 Rp 66,420.00 Rp 2,331,939.78
5 Pekerjaan pengecatan plafond M² 172.900 Rp 33,221.34 Rp 5,743,969.69
6 Pekerjaan cat list plafon kayu M² 42.330 Rp 33,221.34 Rp 1,406,259.32
7 Pekerjaan pengecatan daun pintu, daun jendela, & reling teras M² 50.120 Rp 66,420.00 Rp 3,328,970.40
8 Pekerjaan cat kuda-kuda, gording, balok, tiang teras M² 67.726 Rp 66,420.00 Rp 4,498,360.92
SUB TOTAL Rp 29,782,157.40

X PEKERJAAN LISTRIK
1 Pasang lampu SL 18 watt Bh 3.000 Rp 97,902.00 Rp 293,706.00
2 Pasang lampu SL 23 watt Bh 6.000 Rp 103,302.00 Rp 619,812.00
3 Pasang saklar Ganda Bh 4.000 Rp 54,702.00 Rp 218,808.00
4 Pasang saklar tunggal Bh 1.000 Rp 54,702.00 Rp 54,702.00
5 Pasang Stop Kontak Bh 3.000 Rp 81,702.00 Rp 245,106.00
6 Instalasi listrik Ttk 12.000 Rp 437,022.00 Rp 5,244,264.00
7 Pasang box MCB 2 group Bh 1.000 Rp 341,442.00 Rp 341,442.00
SUB TOTAL Rp 7,017,840.00

XI PEKERJAAN SANITASI
1 Kloset jongkok Bh 2.000 Rp 736,214.40 Rp 1,472,428.80
2 Washtafel Bh 1.000 Rp 1,254,792.60 Rp 1,254,792.60
3 Pemasangan kran air sink Bh 3.000 Rp 58,552.20 Rp 175,656.60
4 Pasang pipa penyalur air bersih diameter 3/4" M' 25.000 Rp 39,775.05 Rp 994,376.25
5 Pasang pipa penyalur air limbah diameter 4" M' 15.000 Rp 115,474.95 Rp 1,732,124.25
6 Pemasangan floof drain plastik Bh 2.000 Rp 42,120.00 Rp 84,240.00
7 Pembuatan septick tank dan resapan Unit 1.000 Rp 3,000,000.00 Rp 3,000,000.00
SUB TOTAL Rp 8,713,618.50
DAFTAR ANALISA SATUAN PEKERJAAN
PERMEN PUPR No. 28/PRT/M/2016

SAT. HARGA
NO. URAIAN PEKERJAAN SAT. INDEKS UPAH (Rp.) BAHAN (Rp.) JUMLAH
(Rp.)
a b c d e f=(dxe) g=(dxe) h=(f+g)
PEKERJAAN PERSIAPAN
1 1 M¹ PENGUKURAN DAN PEMASANGAN BOUWPLANK
- Bahan :
a Kayu Kelas II ( balok ) m³ 0.012 2,500,000.00 30,000.00
b Paku 2" - 3" kg 0.020 15,000.00 300.00
c Kayu Kelas II ( papan ) m³ 0.007 2,500,000.00 17,500.00
- Upah :
a Pekerja OH 0.100 85,000.00 8,500.00
b Tukang Kayu OH 0.100 110,000.00 11,000.00
c Kepala Tukang Kayu OH 0.010 135,000.00 1,350.00
d Mandor OH 0.005 160,000.00 800.00
Total 21,650.00 47,800.00
Total Harga 69,450.00
Overhead dan Profit 8% 5,556.00
Jumlah Harga 75,006.00

2 1 M² PEMBUATAN GUDANG BAHAN DAN ALAT


- Bahan :
a Kayu Dolken Ø8-10 cm btg 1.700 15,000.00 25,500.00
b Kayu Kelas II m³ 0.210 2,500,000.00 525,000.00
c Paku, 5" - 10" kg 0.300 15,000.00 4,500.00
d Semen Portland kg 10.500 1,680.00 17,640.00
e Pasir Beton m³ 0.030 500,000.00 15,000.00
f Batu Karang Pecah Tangan uk. 2/3 cm m³ 0.050 750,000.00 37,500.00
g Seng Gelombang BJLS 20 lbr 1.500 50,000.00 75,000.00
h Seng Pelat BJLS 20 lbr 0.250 55,000.00 13,750.00
- Upah :
a Pekerja OH 1.000 85,000.00 85,000.00
b Tukang Kayu OH 2.000 110,000.00 220,000.00
c Kepala Tukang Kayu OH 0.200 135,000.00 27,000.00
d Mandor OH 0.050 160,000.00 8,000.00
Total 340,000.00 713,890.00
Total Harga 1,053,890.00
Overhead dan Profit 8% 84,311.20
Jumlah Harga 1,138,201.20

3 1 M² MEMBERSIHKAN LAPANGAN DAN PERATAAN


- Upah :
a Pekerja OH 0.100 85,000.00 8,500.00
b Mandor OH 0.050 160,000.00 8,000.00
Total 16,500.00
Total Harga 16,500.00
Overhead dan Profit 8% 1,320.00
Jumlah Harga 17,820.00

PEKERJAAN TANAH
4 MENGGALI 1 M³ TANAH BIASA SEDALAM 1 METER
- Upah :
a Pekerja OH 0.750 85,000.00 63,750.00
b Mandor OH 0.025 160,000.00 4,000.00
Total 67,750.00
Total Harga 67,750.00
Overhead dan Profit 8% 5,420.00
Jumlah Harga 73,170.00

5 MENGGALI 1 M³ TANAH BIASA SEDALAM 2 METER


- Upah :
a Pekerja OH 0.900 85,000.00 76,500.00
b Mandor OH 0.045 160,000.00 7,200.00
Total 83,700.00
Total Harga 83,700.00
Overhead dan Profit 8% 6,696.00
Jumlah Harga 90,396.00

6 MENGGALI 1 M³ TANAH BIASA SEDALAM 3 METER


- Upah :
SAT. HARGA
NO. URAIAN PEKERJAAN SAT. INDEKS UPAH (Rp.) BAHAN (Rp.) JUMLAH
(Rp.)
a b c d e f=(dxe) g=(dxe) h=(f+g)
a Pekerja OH 1.050 85,000.00 89,250.00
b Mandor OH 0.067 160,000.00 10,720.00
Total 99,970.00
Total Harga 99,970.00
Overhead dan Profit 8% 7,997.60
Jumlah Harga 107,967.60

7 MENGGALI 1 M³ TANAH KERAS SEDALAM 1 METER


- Upah :
a Pekerja OH 1.000 85,000.00 85,000.00
b Mandor OH 0.032 160,000.00 5,120.00
Total 90,120.00
Total Harga 90,120.00
Overhead dan Profit 8% 7,209.60
Jumlah Harga 97,329.60

8 MENGGALI 1 M³ TANAH CADAS SEDALAM 1 METER


- Upah :
a Pekerja OH 1.500 85,000.00 127,500.00
b Mandor OH 0.060 160,000.00 9,600.00
Total 137,100.00
Total Harga 137,100.00
Overhead dan Profit 8% 10,968.00
Jumlah Harga 148,068.00

9 MENGGALI 1 M³ TANAH LUMPUR SEDALAM 1 METER


- Upah :
a Pekerja OH 1.200 85,000.00 102,000.00
b Mandor OH 0.045 160,000.00 7,200.00
Total 109,200.00
Total Harga 109,200.00
Overhead dan Profit 8% 8,736.00
Jumlah Harga 117,936.00

10 MENGERJAKAN 1 M² STIPPING TEBING SETINGGI 1 METER


- Upah :
a Pekerja OH 0.050 85,000.00 4,250.00
b Mandor OH 0.005 160,000.00 800.00
Total 5,050.00
Total Harga 5,050.00
Overhead dan Profit 8% 404.00
Jumlah Harga 5,454.00

11 MEMBUANG 1 M³ TANAH SEJAUH 30 METER


- Upah :
a Pekerja OH 0.330 85,000.00 28,050.00
b Mandor OH 0.010 160,000.00 1,600.00
Total 29,650.00
Total Harga 29,650.00
Overhead dan Profit 8% 2,372.00
Jumlah Harga 32,022.00

12 MENGURUG KEMBALI 1 M³ GALIAN


- Upah :
a Pekerja OH 0.500 85,000.00 42,500.00
b Mandor OH 0.050 160,000.00 8,000.00
Total 50,500.00
Total Harga 50,500.00
Overhead dan Profit 8% 4,040.00
Jumlah Harga 54,540.00

13 MEMADATKAN 1 M³ TANAH (PER 20 cm)


- Upah :
a Pekerja OH 0.500 85,000.00 42,500.00
b Mandor OH 0.050 160,000.00 8,000.00
Total 50,500.00
Total Harga 50,500.00
Overhead dan Profit 8% 4,040.00
Jumlah Harga 54,540.00

14 MENGURUG 1 M³ PASIR URUG


- Bahan :
a Pasir Urug m³ 1.200 500,000.00 600,000.00
- Upah :
SAT. HARGA
NO. URAIAN PEKERJAAN SAT. INDEKS UPAH (Rp.) BAHAN (Rp.) JUMLAH
(Rp.)
a b c d e f=(dxe) g=(dxe) h=(f+g)
a Pekerja OH 0.300 85,000.00 25,500.00
b Mandor OH 0.010 160,000.00 1,600.00
Total 27,100.00 600,000.00
Total Harga 627,100.00
Overhead dan Profit 8% 50,168.00
Jumlah Harga 677,268.00

15 MENGURUG 1 M³ SIRTU PADAT


- Bahan :
a Sirtu m³ 1.200 375,000.00 450,000.00
- Upah :
a Pekerja OH 0.250 85,000.00 21,250.00
b Mandor OH 0.025 160,000.00 4,000.00
Total 25,250.00 450,000.00
Total Harga 475,250.00
Overhead dan Profit 8% 38,020.00
Jumlah Harga 513,270.00

PEKERJAAN PONDASI
16 MEMASANG 1 M³ PONDASI BATU BELAH, CAMPURAN 1 PC : 3 PP
- Bahan :
a Batu Karang uk. 15-20 cm m³ 1.200 406,250.00 487,500.00
b Portland Cement kg 202.000 1,680.00 339,360.00
c Pasir Pasang m³ 0.485 500,000.00 242,500.00
- Upah :
a Pekerja OH 1.500 85,000.00 127,500.00
b Tukang Batu OH 0.750 110,000.00 82,500.00
c Kepala Tukang OH 0.075 135,000.00 10,125.00
d Mandor OH 0.075 160,000.00 12,000.00
Total 232,125.00 1,069,360.00
Total Harga 1,301,485.00
Overhead dan Profit 8% 104,118.80
Jumlah Harga 1,405,603.80

17 MEMASANG 1 M³ PONDASI BATU BELAH, CAMPURAN 1 PC : 4 PP


- Bahan :
a Batu Karang uk. 15-20 cm m³ 1.200 406,250.00 487,500.00
b Portland Cement kg 163.000 1,680.00 273,840.00
c Pasir Pasang m³ 0.520 500,000.00 260,000.00
- Upah :
a Pekerja OH 1.500 85,000.00 127,500.00
b Tukang Batu OH 0.750 110,000.00 82,500.00
c Kepala Tukang OH 0.075 135,000.00 10,125.00
d Mandor OH 0.075 160,000.00 12,000.00
Total 232,125.00 1,021,340.00
Total Harga 1,253,465.00
Overhead dan Profit 8% 100,277.20
Jumlah Harga 1,353,742.20

18 MEMASANG 1 M³ PONDASI BATU BELAH, CAMPURAN 1 PC : 5 PP


- Bahan :
a Batu Karang uk. 15-20 cm m³ 1.200 406,250.00 487,500.00
b Portland Cement kg 136.000 1,680.00 228,480.00
c Pasir Pasang m³ 0.544 500,000.00 272,000.00
- Upah :
a Pekerja OH 1.500 85,000.00 127,500.00
b Tukang Batu OH 0.750 110,000.00 82,500.00
c Kepala Tukang OH 0.075 135,000.00 10,125.00
d Mandor OH 0.075 160,000.00 12,000.00
Total 232,125.00 987,980.00
Total Harga 1,220,105.00
Overhead dan Profit 8% 97,608.40
Jumlah Harga 1,317,713.40

19 MEMASANG 1 M³ BATU KOSONG (ANSTAMPING)


- Bahan :
a Batu Karang uk. 20-30 cm m³ 1.200 406,250.00 487,500.00
b Pasir Urug m³ 0.432 500,000.00 216,000.00
- Upah :
a Pekerja OH 0.780 85,000.00 66,300.00
b Tukang Batu OH 0.390 110,000.00 42,900.00
c Kepala Tukang OH 0.039 135,000.00 5,265.00
d Mandor OH 0.039 160,000.00 6,240.00
SAT. HARGA
NO. URAIAN PEKERJAAN SAT. INDEKS UPAH (Rp.) BAHAN (Rp.) JUMLAH
(Rp.)
a b c d e f=(dxe) g=(dxe) h=(f+g)
Total 120,705.00 703,500.00
Total Harga 824,205.00
Overhead dan Profit 8% 65,936.40
Jumlah Harga 890,141.40

PEKERJAAN PLESTERAN
20 MEMBUAT 1 M² PLESTERAN 1 PC : 1 PP, TEBAL 15 mm
- Bahan :
a Portland Cement kg 15.504 1,680.00 26,046.72
b Pasir Plester m³ 0.016 500,000.00 8,000.00
- Upah :
a Pekerja OH 0.300 85,000.00 25,500.00
b Tukang Batu OH 0.150 110,000.00 16,500.00
c Kepala Tukang OH 0.015 135,000.00 2,025.00
d Mandor OH 0.015 160,000.00 2,400.00
Total 46,425.00 34,046.72
Total Harga 80,471.72
Overhead dan Profit 8% 6,437.74
Jumlah Harga 86,909.46

21 MEMBUAT 1 M² PLESTERAN 1 PC : 2 PP, TEBAL 15 mm


- Bahan :
a Portland Cement kg 10.224 1,680.00 17,176.32
b Pasir Plester m³ 0.020 500,000.00 10,000.00
- Upah :
a Pekerja OH 0.300 85,000.00 25,500.00
b Tukang Batu OH 0.150 110,000.00 16,500.00
c Kepala Tukang OH 0.015 135,000.00 2,025.00
d Mandor OH 0.015 160,000.00 2,400.00
Total 46,425.00 27,176.32
Total Harga 73,601.32
Overhead dan Profit 8% 5,888.11
Jumlah Harga 79,489.43

22 MEMBUAT 1 M² PLESTERAN 1 PC : 3 PP, TEBAL 15 mm


- Bahan :
a Portland Cement kg 7.776 1,680.00 13,063.68
b Pasir Plester m³ 0.023 500,000.00 11,500.00
- Upah :
a Pekerja OH 0.300 85,000.00 25,500.00
b Tukang Batu OH 0.150 110,000.00 16,500.00
c Kepala Tukang OH 0.015 135,000.00 2,025.00
d Mandor OH 0.015 160,000.00 2,400.00
Total 46,425.00 24,563.68
Total Harga 70,988.68
Overhead dan Profit 8% 5,679.09
Jumlah Harga 76,667.77

23 MEMBUAT 1 M² PLESTERAN 1 PC : 4 PP, TEBAL 15 mm


- Bahan :
a Portland Cement kg 6.240 1,680.00 10,483.20
b Pasir Plester m³ 0.024 500,000.00 12,000.00
- Upah :
a Pekerja OH 0.300 85,000.00 25,500.00
b Tukang Batu OH 0.150 110,000.00 16,500.00
c Kepala Tukang OH 0.015 135,000.00 2,025.00
d Mandor OH 0.015 160,000.00 2,400.00
Total 46,425.00 22,483.20
Total Harga 68,908.20
Overhead dan Profit 8% 5,512.66
Jumlah Harga 74,420.86

24 MEMBUAT 1 M² PLESTERAN 1 PC : 5 PP, TEBAL 15 mm


- Bahan :
a Portland Cement kg 5.184 1,680.00 8,709.12
b Pasir Plester m³ 0.026 500,000.00 13,000.00
- Upah :
a Pekerja OH 0.300 85,000.00 25,500.00
b Tukang Batu OH 0.150 110,000.00 16,500.00
c Kepala Tukang OH 0.015 135,000.00 2,025.00
d Mandor OH 0.015 160,000.00 2,400.00
Total 46,425.00 21,709.12
Total Harga 68,134.12
SAT. HARGA
NO. URAIAN PEKERJAAN SAT. INDEKS UPAH (Rp.) BAHAN (Rp.) JUMLAH
(Rp.)
a b c d e f=(dxe) g=(dxe) h=(f+g)
Overhead dan Profit 8% 5,450.73
Jumlah Harga 73,584.85

25 MEMBUAT 1 M² PLESTERAN 1 PC : 1 PP, TEBAL 20 mm


- Bahan :
a Portland Cement kg 13.632 1,680.00 22,901.76
b Pasir Plester m³ 0.027 500,000.00 13,500.00
- Upah :
a Pekerja OH 0.400 85,000.00 34,000.00
b Tukang Batu OH 0.200 110,000.00 22,000.00
c Kepala Tukang OH 0.020 135,000.00 2,700.00
d Mandor OH 0.022 160,000.00 3,520.00
Total 62,220.00 36,401.76
Total Harga 98,621.76
Overhead dan Profit 8% 7,889.74
Jumlah Harga 106,511.50

26 MEMBUAT 1 M² PLESTERAN 1 PC : 3 PP, TEBAL 20 mm


- Bahan :
a Portland Cement kg 10.368 1,680.00 17,418.24
b Pasir Plester m³ 0.031 500,000.00 15,500.00
- Upah :
a Pekerja OH 0.260 85,000.00 22,100.00
b Tukang Batu OH 0.200 110,000.00 22,000.00
c Kepala Tukang OH 0.020 135,000.00 2,700.00
d Mandor OH 0.013 160,000.00 2,080.00
Total 48,880.00 32,918.24
Total Harga 81,798.24
Overhead dan Profit 8% 6,543.86
Jumlah Harga 88,342.10

27 MEMBUAT 1 M² PLESTERAN 1 PC : 4 PP, TEBAL 20 mm


- Bahan :
a Portland Cement kg 8.320 1,680.00 13,977.60
b Pasir Plester m³ 0.032 500,000.00 16,000.00
- Upah :
a Pekerja OH 0.400 85,000.00 34,000.00
b Tukang Batu OH 0.200 110,000.00 22,000.00
c Kepala Tukang OH 0.020 135,000.00 2,700.00
d Mandor OH 0.022 160,000.00 3,520.00
Total 62,220.00 29,977.60
Total Harga 92,197.60
Overhead dan Profit 8% 7,375.81
Jumlah Harga 99,573.41

28 MEMBUAT 1 M² PLESTERAN 1 PC : 5 PP, TEBAL 20 mm


- Bahan :
a Portland Cement kg 6.912 1,680.00 11,612.16
b Pasir Plester m³ 0.035 500,000.00 17,500.00
- Upah :
a Pekerja OH 0.400 85,000.00 34,000.00
b Tukang Batu OH 0.200 110,000.00 22,000.00
c Kepala Tukang OH 0.020 135,000.00 2,700.00
d Mandor OH 0.022 160,000.00 3,520.00
Total 62,220.00 29,112.16
Total Harga 91,332.16
Overhead dan Profit 8% 7,306.57
Jumlah Harga 98,638.73

29 MEMBUAT 1 M' PLESTERAN SKONING LEBAR 10 mm CAMPURAN 1 PC : 3 PP LEBAR 10 CM


- Bahan :
a Portland Cement kg 0.500 1,680.00 840.00
b Pasir Plester m³ 0.013 500,000.00 6,500.00
- Upah :
a Pekerja OH 0.080 85,000.00 6,800.00
b Tukang Batu OH 0.400 110,000.00 44,000.00
c Kepala Tukang OH 0.040 135,000.00 5,400.00
d Mandor OH 0.004 160,000.00 640.00
Total 56,840.00 7,340.00
Total Harga 64,180.00
Overhead dan Profit 8% 5,134.40
Jumlah Harga 69,314.40

30 MEMBUAT 1 M² ACIAN
SAT. HARGA
NO. URAIAN PEKERJAAN SAT. INDEKS UPAH (Rp.) BAHAN (Rp.) JUMLAH
(Rp.)
a b c d e f=(dxe) g=(dxe) h=(f+g)
- Bahan :
a Portland Cement kg 3.250 1,680.00 5,460.00
- Upah :
a Pekerja OH 0.200 85,000.00 17,000.00
b Tukang Batu OH 0.100 110,000.00 11,000.00
c Kepala Tukang OH 0.010 135,000.00 1,350.00
d Mandor OH 0.010 160,000.00 1,600.00
Total 30,950.00 5,460.00
Total Harga 36,410.00
Overhead dan Profit 8% 2,912.80
Jumlah Harga 39,322.80

PEKERJAAN LANGIT-LANGIT
31 MEMASANG 1 M² LANGIT-LANGIT TRIPLEKS UK. (120x240) cm TEBAL 3 mm
- Bahan :
a Tripleks 3 mm Lembar 0.375 59,000.00 22,125.00
b Paku Tripleks kg 0.030 20,000.00 600.00
- Upah :
a Pekerja OH 0.100 85,000.00 8,500.00
b Tukang Kayu OH 0.100 110,000.00 11,000.00
c Kepala Tukang OH 0.010 135,000.00 1,350.00
d Mandor OH 0.005 160,000.00 800.00
Total 21,650.00 22,725.00
Total Harga 44,375.00
Overhead dan Profit 8% 3,550.00
Jumlah Harga 47,925.00

32 MEMASANG 1 M² LANGIT-LANGIT TRIPLEKS UK. (120x240) cm TEBAL 4 mm


- Bahan :
a Tripleks 4 mm Lembar 0.375 85,000.00 31,875.00
b Paku Tripleks kg 0.030 20,000.00 600.00
- Upah :
a Pekerja OH 0.100 85,000.00 8,500.00
b Tukang Kayu OH 0.100 110,000.00 11,000.00
c Kepala Tukang OH 0.010 135,000.00 1,350.00
d Mandor OH 0.005 160,000.00 800.00
Total 21,650.00 32,475.00
Total Harga 54,125.00
Overhead dan Profit 8% 4,330.00
Jumlah Harga 58,455.00

32 MEMASANG 1 M² LANGIT-LANGIT ETERNIT/GRC UK. (120x240) cm TEBAL 4 mm


- Bahan :
a Eternit Klas I 4 mm Lembar 1.100 85,000.00 93,500.00
b Paku kg 0.010 20,000.00 200.00
- Upah :
a Pekerja OH 0.030 85,000.00 2,550.00
b Tukang Kayu OH 0.070 110,000.00 7,700.00
c Kepala Tukang OH 0.007 135,000.00 945.00
d Mandor OH 0.004 160,000.00 640.00
Total 11,835.00 93,700.00
Total Harga 105,535.00
Overhead dan Profit 8% 8,442.80
Jumlah Harga 113,977.80

33 MEMASANG 1 M² LANGIT-LANGIT GYPSUM BOARD TEBAL 9 mm


- Bahan :
a Gypsum board 9 mm Lembar 0.364 95,000.00 34,580.00
c Sekrub kg 0.110 35,000.00 3,850.00
- Upah :
a Pekerja OH 0.100 85,000.00 8,500.00
b Tukang Kayu OH 0.050 110,000.00 5,500.00
c Kepala Tukang OH 0.005 135,000.00 675.00
d Mandor OH 0.005 160,000.00 800.00
Total 15,475.00 38,430.00
Total Harga 53,905.00
Overhead dan Profit 8% 4,312.40
Jumlah Harga 58,217.40

33 MEMASANG 1 M² LANGIT-LANGIT LAMBRISERING KAYU TEBAL 9 mm


- Bahan :
a Kayu Papan Kelas I m³ 0.015 4,000,000.00 60,000.00
c Paku Tripleks kg 0.010 20,000.00 200.00
SAT. HARGA
NO. URAIAN PEKERJAAN SAT. INDEKS UPAH (Rp.) BAHAN (Rp.) JUMLAH
(Rp.)
a b c d e f=(dxe) g=(dxe) h=(f+g)
- Upah :
a Pekerja OH 0.800 85,000.00 68,000.00
b Tukang Kayu OH 0.800 110,000.00 88,000.00
c Kepala Tukang OH 0.080 135,000.00 10,800.00
d Mandor OH 0.040 160,000.00 6,400.00
Total 173,200.00 60,200.00
Total Harga 233,400.00
Overhead dan Profit 8% 18,672.00
Jumlah Harga 252,072.00

34 MEMASANG 1 M' LIST PLAFOND GYPSUM PROFIL


- Bahan :
a List Gypsum Profil m' 1.050 50,000.00 52,500.00
b Tepung Gypsum kg 0.150 6,000.00 900.00
- Upah :
a Pekerja OH 0.060 85,000.00 5,100.00
b Tukang Kayu OH 0.060 110,000.00 6,600.00
c Kepala Tukang OH 0.006 135,000.00 810.00
d Mandor OH 0.003 160,000.00 480.00
Total 12,990.00 53,400.00
Total Harga 66,390.00

34 MEMASANG 1 M' LIST PLAFOND KAYU PROFIL TEBAL 5 cm


- Bahan :
a List Kayu Profil 5 cm m' 1.050 40,000.00 42,000.00
b Paku kg 0.010 15,000.00 150.00
- Upah :
a Pekerja OH 0.050 85,000.00 4,250.00
b Tukang Kayu OH 0.050 110,000.00 5,500.00
c Kepala Tukang OH 0.005 135,000.00 675.00
d Mandor OH 0.003 160,000.00 400.00
Total 10,825.00 42,150.00
Total Harga 52,975.00
Overhead dan Profit 8% 4,238.00
Jumlah Harga 57,213.00

35 MEMASANG 1 M' LIST PLAFOND KAYU PROFIL TEBAL 7 cm


- Bahan :
a List Kayu Profil 7 cm m' 1.050 50,000.00 52,500.00
b Paku kg 0.010 15,000.00 150.00
- Upah :
a Pekerja OH 0.050 85,000.00 4,250.00
b Tukang Kayu OH 0.050 110,000.00 5,500.00
c Kepala Tukang OH 0.005 135,000.00 675.00
d Mandor OH 0.003 160,000.00 400.00
Total 10,825.00 52,650.00
Total Harga 63,475.00
Overhead dan Profit 8% 5,078.00
Jumlah Harga 68,553.00

PEKERJAAN KAYU
36 MEMBUAT DAN MEMASANG 1 M³ KUSEN PINTU DAN KUSEN JENDELA, KAYU KELAS I
- Bahan :
a Balok Kayu Kelas I m³ 1.100 4,000,000.00 4,400,000.00
b Paku 10 cm kg 1.250 15,000.00 18,750.00
c Lem Kayu kg 1.000 60,000.00 60,000.00
- Upah :
a Pekerja OH 7.000 85,000.00 595,000.00
b Tukang Kayu OH 21.000 110,000.00 2,310,000.00
c Kepala Tukang OH 2.100 135,000.00 283,500.00
d Mandor OH 0.350 160,000.00 56,000.00
Total 3,244,500.00 4,478,750.00
Total Harga 7,723,250.00
Overhead dan Profit 8% 617,860.00
Jumlah Harga 8,341,110.00

37 MEMBUAT DAN MEMASANG 1 M³ KUSEN PINTU DAN KUSEN JENDELA, KAYU KELAS II ATAU III
- Bahan :
a Balok Kayu Kelas II atau III m³ 1.200 2,500,000.00 3,000,000.00
b Paku 10 cm kg 1.250 15,000.00 18,750.00
c Lem Kayu kg 1.000 60,000.00 60,000.00
- Upah :
a Pekerja OH 6.000 85,000.00 510,000.00
SAT. HARGA
NO. URAIAN PEKERJAAN SAT. INDEKS UPAH (Rp.) BAHAN (Rp.) JUMLAH
(Rp.)
a b c d e f=(dxe) g=(dxe) h=(f+g)
b Tukang Kayu OH 18.000 110,000.00 1,980,000.00
c Kepala Tukang OH 1.800 135,000.00 243,000.00
d Mandor OH 0.300 160,000.00 48,000.00
Total 2,781,000.00 3,078,750.00
Total Harga 5,859,750.00
Overhead dan Profit 8% 468,780.00
Jumlah Harga 6,328,530.00

38 MEMBUAT DAN MEMASANG 1 M² DAUN PINTU PANEL, KAYU KELAS I


- Bahan :
a Papan Kayu Kelas I m³ 0.040 4,000,000.00 160,000.00
b Lem Kayu kg 0.500 60,000.00 30,000.00
- Upah :
a Pekerja OH 1.000 85,000.00 85,000.00
b Tukang Kayu OH 3.000 110,000.00 330,000.00
c Kepala Tukang OH 0.300 135,000.00 40,500.00
d Mandor OH 0.050 160,000.00 8,000.00
Total 463,500.00 190,000.00
Total Harga 653,500.00
Overhead dan Profit 8% 52,280.00
Jumlah Harga 705,780.00

39 MEMBUAT DAN MEMASANG 1 M² DAUN PINTU PANEL, KAYU KELAS II


- Bahan :
a Papan Kayu Kelas II m³ 0.040 2,500,000.00 100,000.00
b Lem Kayu kg 0.500 60,000.00 30,000.00
- Upah :
a Pekerja OH 1.000 85,000.00 85,000.00
b Tukang Kayu OH 3.000 110,000.00 330,000.00
c Kepala Tukang OH 0.300 135,000.00 40,500.00
d Mandor OH 0.050 160,000.00 8,000.00
Total 463,500.00 130,000.00
Total Harga 593,500.00
Overhead dan Profit 8% 47,480.00
Jumlah Harga 640,980.00

40 MEMBUAT DAN MEMASANG 1 M² PINTU DAN JENDELA KACA, KAYU KELAS I


- Bahan :
a Papan Kayu Kelas I m³ 0.024 4,000,000.00 96,000.00
b Lem Kayu kg 0.300 60,000.00 18,000.00
- Upah :
a Pekerja OH 0.800 85,000.00 68,000.00
b Tukang Kayu OH 2.400 110,000.00 264,000.00
c Kepala Tukang OH 0.240 135,000.00 32,400.00
d Mandor OH 0.040 160,000.00 6,400.00
Total 370,800.00 114,000.00
Total Harga 484,800.00
Overhead dan Profit 8% 38,784.00
Jumlah Harga 523,584.00

41 MEMBUAT DAN MEMASANG 1 M² PINTU DAN JENDELA KACA, KAYU KELAS II


- Bahan :
a Papan Kayu Kelas II m³ 0.024 2,500,000.00 60,000.00
b Lem Kayu kg 0.300 60,000.00 18,000.00
- Upah :
a Pekerja OH 0.800 85,000.00 68,000.00
b Tukang Kayu OH 2.400 110,000.00 264,000.00
c Kepala Tukang OH 0.240 135,000.00 32,400.00
d Mandor OH 0.040 160,000.00 6,400.00
Total 370,800.00 78,000.00
Total Harga 448,800.00
Overhead dan Profit 8% 35,904.00
Jumlah Harga 484,704.00

42 MEMBUAT DAN MEMASANG 1 M² PINTU DAN JENDELA JALUSI, KAYU KELAS I


- Bahan :
a Papan Kayu Kelas I m³ 0.064 4,000,000.00 256,000.00
b Lem Kayu kg 0.500 60,000.00 30,000.00
- Upah :
a Pekerja OH 1.000 85,000.00 85,000.00
b Tukang Kayu OH 3.000 110,000.00 330,000.00
c Kepala Tukang OH 0.300 135,000.00 40,500.00
d Mandor OH 0.050 160,000.00 8,000.00
Total 463,500.00 286,000.00
SAT. HARGA
NO. URAIAN PEKERJAAN SAT. INDEKS UPAH (Rp.) BAHAN (Rp.) JUMLAH
(Rp.)
a b c d e f=(dxe) g=(dxe) h=(f+g)
Total Harga 749,500.00
Overhead dan Profit 8% 59,960.00
Jumlah Harga 809,460.00

43 MEMASANG 1 M² JALUSI KUSEN, KAYU KELAS I


- Bahan :
a Papan Kayu Kelas I m³ 0.060 4,000,000.00 240,000.00
b Paku 1 - 2,5 cm kg 0.150 26,750.00 4,012.50
- Upah :
a Pekerja OH 0.670 85,000.00 56,950.00
b Tukang Kayu OH 2.000 110,000.00 220,000.00
c Kepala Tukang OH 0.200 135,000.00 27,000.00
d Mandor OH 0.335 160,000.00 53,600.00
Total 357,550.00 244,012.50
Total Harga 601,562.50
Overhead dan Profit 8% 48,125.00
Jumlah Harga 649,687.50

44 MEMASANG 1 M³ KONSTRUKSI KUDA-KUDA KONVENSIONAL, KAYU KELAS I BENTANG 6 METER


- Bahan :
a Balok Kayu Kelas I m³ 1.100 4,000,000.00 4,400,000.00
b Besi Strip Tebal 5 mm kg 15.000 48,000.00 720,000.00
c Paku 12 cm kg 5.600 15,000.00 84,000.00
- Upah :
a Pekerja OH 4.000 85,000.00 340,000.00
b Tukang Kayu OH 12.000 110,000.00 1,320,000.00
c Kepala Tukang OH 1.200 135,000.00 162,000.00
d Mandor OH 0.200 160,000.00 32,000.00
Total 1,854,000.00 5,204,000.00
Total Harga 7,058,000.00
Overhead dan Profit 8% 564,640.00
Jumlah Harga 7,622,640.00

45 MEMASANG 1 M³ KONSTRUKSI KUDA-KUDA EXPOSE, KAYU KELAS I


- Bahan :
a Balok Kayu Kelas I m³ 1.200 4,000,000.00 4,800,000.00
b Besi Strip Tebal 5 mm kg 15.000 48,000.00 720,000.00
c Paku 12 cm kg 5.600 15,000.00 84,000.00
- Upah :
a Pekerja OH 6.700 85,000.00 569,500.00
b Tukang Kayu OH 20.100 110,000.00 2,211,000.00
c Kepala Tukang OH 2.010 135,000.00 271,350.00
d Mandor OH 0.335 160,000.00 53,600.00
Total 3,105,450.00 5,604,000.00
Total Harga 8,709,450.00
Overhead dan Profit 8% 696,756.00
Jumlah Harga 9,406,206.00

46 MEMASANG 1 M³ KONSTRUKSI GORDING, KAYU KELAS I


- Bahan :
a Balok Kayu Kelas I m³ 1.100 4,000,000.00 4,400,000.00
b Besi Strip Tebal 5 mm kg 15.000 48,000.00 720,000.00
c Paku 12 cm kg 3.000 15,000.00 45,000.00
- Upah :
a Pekerja OH 6.700 85,000.00 569,500.00
b Tukang Kayu OH 20.100 110,000.00 2,211,000.00
c Kepala Tukang OH 2.010 135,000.00 271,350.00
d Mandor OH 0.335 160,000.00 53,600.00
Total 3,105,450.00 5,165,000.00
Total Harga 8,270,450.00
Overhead dan Profit 8% 661,636.00
Jumlah Harga 8,932,086.00

47 MEMASANG 1 M² RANGKA LANGIT-LANGIT (50x100) cm, KAYU KELAS II


- Bahan :
a Balok Kayu Kelas II m³ 0.0154 2,500,000.00 38,500.00
b Paku 7 - 10 cm kg 0.200 15,000.00 3,000.00
- Upah :
a Pekerja OH 0.150 85,000.00 12,750.00
b Tukang Kayu OH 0.300 110,000.00 33,000.00
c Kepala Tukang OH 0.030 135,000.00 4,050.00
d Mandor OH 0.075 160,000.00 12,000.00
Total 61,800.00 41,500.00
Total Harga 103,300.00
SAT. HARGA
NO. URAIAN PEKERJAAN SAT. INDEKS UPAH (Rp.) BAHAN (Rp.) JUMLAH
(Rp.)
a b c d e f=(dxe) g=(dxe) h=(f+g)
Overhead dan Profit 8% 8,264.00
Jumlah Harga 111,564.00

48 MEMASANG 1 M' LISPLANK UKURAN (3x20) cm, KAYU KELAS I


- Bahan :
a Papan Kayu Kelas I m³ 0.0108 4,000,000.00 43,200.00
b Paku 5 - 7 cm kg 0.100 15,000.00 1,500.00
- Upah :
a Pekerja OH 0.100 85,000.00 8,500.00
b Tukang Kayu OH 0.200 110,000.00 22,000.00
c Kepala Tukang OH 0.020 135,000.00 2,700.00
d Mandor OH 0.005 160,000.00 800.00
Total 34,000.00 44,700.00
Total Harga 78,700.00
Overhead dan Profit 8% 6,296.00
Jumlah Harga 84,996.00

49 MEMASANG 1 M' LISPLANK UKURAN (3x30) cm, KAYU KELAS I


- Bahan :
a Papan Kayu Kelas I m³ 0.011 4,000,000.00 44,000.00
b Paku 5 - 7 cm kg 0.050 15,000.00 750.00
- Upah :
a Pekerja OH 0.100 85,000.00 8,500.00
b Tukang Kayu OH 0.200 110,000.00 22,000.00
c Kepala Tukang OH 0.020 135,000.00 2,700.00
d Mandor OH 0.005 160,000.00 800.00
Total 34,000.00 44,750.00
Total Harga 78,750.00
Overhead dan Profit 8% 6,300.00
Jumlah Harga 85,050.00

49 MEMASANG 1 M² RANGKA DINDING PEMISAH (60X120) CM KAYU KELAS I


- Bahan :
a Balok Kayu Kelas I m³ 0.028 4,000,000.00 112,000.00
b Paku 5 - 7 cm kg 0.150 15,000.00 2,250.00
- Upah :
a Pekerja OH 0.150 85,000.00 12,750.00
b Tukang Kayu OH 0.450 110,000.00 49,500.00
c Kepala Tukang OH 0.045 135,000.00 6,075.00
d Mandor OH 0.008 160,000.00 1,280.00
Total 69,605.00 114,250.00
Total Harga 183,855.00
Overhead dan Profit 8% 14,708.40
Jumlah Harga 198,563.40

49 MEMASANG 1 M² DINDING LAMBRISERING DARI PAPAN KAYU KELAS I


- Bahan :
a Papan Kayu Kelas I m³ 0.007 4,000,000.00 28,000.00
b Paku 5 - 10 cm kg 0.100 15,000.00 1,500.00
c Paku Sekrup 10 cm/ulir kg 0.150 35,000.00 5,250.00
- Upah :
a Pekerja OH 0.600 85,000.00 51,000.00
b Tukang Kayu OH 1.800 110,000.00 198,000.00
c Kepala Tukang OH 0.180 135,000.00 24,300.00
d Mandor OH 0.030 160,000.00 4,800.00
Total 278,100.00 34,750.00
Total Harga 312,850.00
Overhead dan Profit 8% 25,028.00
Jumlah Harga 337,878.00

49 MEMASANG 1 M² LANTAI PAPAN KAYU KELAS I


- Bahan :
b Papan Kayu Kelas I m³ 0.030 4,000,000.00 120,000.00
c Paku 2 - 7 cm kg 0.100 15,000.00 1,500.00
- Upah :
a Pekerja OH 0.150 85,000.00 12,750.00
b Tukang Kayu OH 0.450 110,000.00 49,500.00
c Kepala Tukang OH 0.045 135,000.00 6,075.00
d Mandor OH 0.075 160,000.00 12,000.00
Total 80,325.00 121,500.00
Total Harga 201,825.00
Overhead dan Profit 8% 16,146.00
Jumlah Harga 217,971.00
SAT. HARGA
NO. URAIAN PEKERJAAN SAT. INDEKS UPAH (Rp.) BAHAN (Rp.) JUMLAH
(Rp.)
a b c d e f=(dxe) g=(dxe) h=(f+g)
49 MEMASANG 1 M³ KONSTRUKSI TIANG KAYU KELAS I
- Bahan :
a Balok Kayu Kelas I m³ 1.100 4,000,000.00 4,400,000.00
b Baut Diameter 19 mm m³ 24.000 8,000.00 192,000.00
c Paku 5 - 10 cm kg 3.000 15,000.00 45,000.00
- Upah :
a Pekerja OH 4.000 85,000.00 340,000.00
b Tukang Kayu OH 12.000 110,000.00 1,320,000.00
c Kepala Tukang OH 1.200 135,000.00 162,000.00
d Mandor OH 0.020 160,000.00 3,200.00
Total 1,825,200.00 4,637,000.00
Total Harga 6,462,200.00
Overhead dan Profit 8% 516,976.00
Jumlah Harga 6,979,176.00

49 MEMASANG 1 M³ KONSTRUKSI BALOK GELAGAR KAYU KELAS I


- Bahan :
a Balok Kayu Kelas I m³ 1.100 4,000,000.00 4,400,000.00
b Baut Diameter 19 mm m³ 34.000 8,000.00 272,000.00
c Paku 5 - 10 cm kg 3.000 15,000.00 45,000.00
- Upah :
a Pekerja OH 4.000 85,000.00 340,000.00
b Tukang Kayu OH 12.000 110,000.00 1,320,000.00
c Kepala Tukang OH 1.200 135,000.00 162,000.00
d Mandor OH 0.020 160,000.00 3,200.00
Total 1,825,200.00 4,717,000.00
Total Harga 6,542,200.00
Overhead dan Profit 8% 523,376.00
Jumlah Harga 7,065,576.00

49 MEMASANG 1 M³ KONSTRUKSI BALOK LANTAI KAYU KELAS I


- Bahan :
a Balok Kayu Kelas I m³ 1.100 4,000,000.00 4,400,000.00
c Paku 5 - 10 cm kg 3.000 15,000.00 45,000.00
- Upah :
a Pekerja OH 4.000 85,000.00 340,000.00
b Tukang Kayu OH 12.000 110,000.00 1,320,000.00
c Kepala Tukang OH 1.200 135,000.00 162,000.00
d Mandor OH 0.020 160,000.00 3,200.00
Total 1,825,200.00 4,445,000.00
Total Harga 6,270,200.00
Overhead dan Profit 8% 501,616.00
Jumlah Harga 6,771,816.00

36 MEMBUAT DAN MEMASANG 1 M³ REALLING PENGAMAN KAYU KELAS I


- Bahan :
a Balok Kayu Kelas I m³ 1.100 4,000,000.00 4,400,000.00
b Paku 10 cm kg 1.250 15,000.00 18,750.00
c Lem Kayu kg 1.000 60,000.00 60,000.00
- Upah :
a Pekerja OH 7.000 85,000.00 595,000.00
b Tukang Kayu OH 21.000 110,000.00 2,310,000.00
c Kepala Tukang OH 2.100 135,000.00 283,500.00
d Mandor OH 0.350 160,000.00 56,000.00
Total 3,244,500.00 4,478,750.00
Total Harga 7,723,250.00
Overhead dan Profit 8% 617,860.00
Jumlah Harga 8,341,110.00

PEKERJAAN DINDING
53 MEMASANG 1 M² DINDING BATAKO UKURAN (8X15X30) cm TEBAL 1/4 BATU, CAMPURAN 1 PC : 2 PP
- Bahan :
a Batako uk. 8x15x30 Buah 23.000 5,000.00 115,000.00
b Portland Cement kg 18.950 1,680.00 31,836.00
c Pasir Pasang m³ 0.038 500,000.00 19,000.00
- Upah :
a Pekerja OH 0.300 85,000.00 25,500.00
b Tukang Batu OH 0.100 110,000.00 11,000.00
c Kepala Tukang OH 0.010 135,000.00 1,350.00
d Mandor OH 0.015 160,000.00 2,400.00
Total 40,250.00 165,836.00
Total Harga 206,086.00
Overhead dan Profit 8% 16,486.88
SAT. HARGA
NO. URAIAN PEKERJAAN SAT. INDEKS UPAH (Rp.) BAHAN (Rp.) JUMLAH
(Rp.)
a b c d e f=(dxe) g=(dxe) h=(f+g)
Jumlah Harga 222,572.88

54 MEMASANG 1 M² DINDING BATAKO UKURAN (8X15X30) cm TEBAL 1/4 BATU, CAMPURAN 1 PC : 3 PP


- Bahan :
a Batako uk. 8x15x30 Buah 23.000 3,000.00 69,000.00
b Portland Cement kg 14.370 1,680.00 24,141.60
c Pasir Pasang m³ 0.040 500,000.00 20,000.00
- Upah :
a Pekerja OH 0.300 85,000.00 25,500.00
b Tukang Batu OH 0.100 110,000.00 11,000.00
c Kepala Tukang OH 0.010 135,000.00 1,350.00
d Mandor OH 0.015 160,000.00 2,400.00
Total 40,250.00 113,141.60
Total Harga 153,391.60
Overhead dan Profit 8% 12,271.33
Jumlah Harga 165,662.93

55 MEMASANG 1 M² DINDING BATAKO UKURAN (8X15X30) cm TEBAL 1/4 BATU, CAMPURAN 1 PC : 4 PP


- Bahan :
a Batako uk. 8x15x30 Buah 23.000 3,000.00 69,000.00
b Portland Cement kg 11.500 1,680.00 19,320.00
c Pasir Pasang m³ 0.043 500,000.00 21,500.00
- Upah :
a Pekerja OH 0.300 85,000.00 25,500.00
b Tukang Batu OH 0.100 110,000.00 11,000.00
c Kepala Tukang OH 0.010 135,000.00 1,350.00
d Mandor OH 0.015 160,000.00 2,400.00
Total 40,250.00 109,820.00
Total Harga 150,070.00
Overhead dan Profit 8% 12,005.60
Jumlah Harga 162,075.60

53 MEMASANG 1 M² DINDING BATA MERAH UKURAN (5X11X22) cm TEBAL 1/2 BATA, CAMPURAN 1 PC : 2 PP
- Bahan :
a Bata Merah Buah 70.000 3,000.00 210,000.00
b Portland Cement kg 18.950 1,680.00 31,836.00
c Pasir Pasang m³ 0.038 500,000.00 19,000.00
- Upah :
a Pekerja OH 0.300 85,000.00 25,500.00
b Tukang Batu OH 0.100 110,000.00 11,000.00
c Kepala Tukang OH 0.010 135,000.00 1,350.00
d Mandor OH 0.015 160,000.00 2,400.00
Total 40,250.00 260,836.00
Total Harga 301,086.00
Overhead dan Profit 8% 24,086.88
Jumlah Harga 325,172.88

54 MEMASANG 1 M² DINDING BATA MERAH UKURAN (5X11X22) cm TEBAL 1/2 BATA, CAMPURAN 1 PC : 3 PP
- Bahan :
a Bata Merah Buah 70.000 3,000.00 210,000.00
b Portland Cement kg 14.370 1,680.00 24,141.60
c Pasir Pasang m³ 0.040 500,000.00 20,000.00
- Upah :
a Pekerja OH 0.300 85,000.00 25,500.00
b Tukang Batu OH 0.100 110,000.00 11,000.00
c Kepala Tukang OH 0.010 135,000.00 1,350.00
d Mandor OH 0.015 160,000.00 2,400.00
Total 40,250.00 254,141.60
Total Harga 294,391.60
Overhead dan Profit 8% 23,551.33
Jumlah Harga 317,942.93

55 MEMASANG 1 M² DINDING BATA MERAH UKURAN (5X11X22) cm TEBAL 1/2 BATA, CAMPURAN 1 PC : 4 PP
- Bahan :
a Bata Merah Buah 70.000 3,000.00 210,000.00
b Portland Cement kg 11.500 1,680.00 19,320.00
c Pasir Pasang m³ 0.043 500,000.00 21,500.00
- Upah :
a Pekerja OH 0.300 85,000.00 25,500.00
b Tukang Batu OH 0.100 110,000.00 11,000.00
c Kepala Tukang OH 0.010 135,000.00 1,350.00
d Mandor OH 0.015 160,000.00 2,400.00
Total 40,250.00 250,820.00
Total Harga 291,070.00
SAT. HARGA
NO. URAIAN PEKERJAAN SAT. INDEKS UPAH (Rp.) BAHAN (Rp.) JUMLAH
(Rp.)
a b c d e f=(dxe) g=(dxe) h=(f+g)
Overhead dan Profit 8% 23,285.60
Jumlah Harga 314,355.60

PEKERJAAN BETON
56 MEMBUAT 1 M³ BETON MUTU F'C = 7,4 Mpa
- Bahan :
a Portland Cement kg 247.000 1,680.00 414,960.00
b Pasir Beton kg 869.000 277.78 241,388.89
c Batu Karang Pecah Tangan uk. 2/3 cm kg 999.000 375.00 374,625.00
d Air liter 215.000 75.00 16,125.00
- Upah :
a Pekerja OH 1.650 85,000.00 140,250.00
b Tukang Batu OH 0.275 110,000.00 30,250.00
c Kepala Tukang OH 0.028 135,000.00 3,780.00
d Mandor OH 0.083 160,000.00 13,280.00
Total 187,560.00 1,047,098.89
Total Harga 1,234,658.89
Overhead dan Profit 8% 98,772.71
Jumlah Harga 1,333,431.60

56 MEMBUAT 1 M³ BETON MUTU F'C = 24,0 Mpa


- Bahan :
a Portland Cement kg 406.000 1,680.00 682,080.00
b Pasir Beton kg 684.000 277.78 190,000.00
c Batu Karang Pecah Tangan uk. 2/3 cm kg 1,026.000 375.00 384,750.00
d Air liter 215.000 75.00 16,125.00
- Upah :
a Pekerja OH 1.650 85,000.00 140,250.00
b Tukang Batu OH 0.275 110,000.00 30,250.00
c Kepala Tukang OH 0.028 135,000.00 3,780.00
d Mandor OH 0.083 160,000.00 13,280.00
Total 187,560.00 1,272,955.00
Total Harga 1,460,515.00
Overhead dan Profit 8% 116,841.20
Jumlah Harga 1,577,356.20

58 PEMBESIAN 10 KG DENGAN BESI POLOS ATAU BESI ULIR


- Bahan :
d Besi Beton Polos kg 10.500 12,706.14 133,414.44
e Kawat Beton kg 0.150 26,000.00 3,900.00
- Upah :
a Pekerja OH 0.070 85,000.00 5,950.00
b Tukang Besi OH 0.070 110,000.00 7,700.00
c Kepala Tukang OH 0.007 135,000.00 945.00
d Mandor OH 0.004 160,000.00 640.00
Total 15,235.00 137,314.44
Total Harga 152,549.44
Overhead dan Profit 8% 12,203.95
Jumlah Harga 164,753.39
@ PEMBESIAN UNTUK 1 KG 16,475.34

59 PEMASANGAN 1 M² BEKESTING UNTUK PONDASI


- Bahan :
a Kayu Bekesting m³ 0.040 1,500,000.00 60,000.00
b Paku 5-10 cm kg 0.300 15,000.00 4,500.00
c Minyak Bekesting liter 0.100 35,000.00 3,500.00
- Upah :
a Pekerja OH 0.520 85,000.00 44,200.00
b Tukang Kayu OH 0.260 110,000.00 28,600.00
c Kepala Tukang OH 0.026 135,000.00 3,510.00
d Mandor OH 0.026 160,000.00 4,160.00
Total 80,470.00 68,000.00
Total Harga 148,470.00
Overhead dan Profit 8% 11,877.60
Jumlah Harga 160,347.60
@ UNTUK 2 KALI PEMAKAIAN / 40% 64,139.04

59 PEMASANGAN 1 M² BEKESTING UNTUK SLOOF


- Bahan :
a Kayu Bekesting m³ 0.045 1,500,000.00 67,500.00
b Paku 5-10 cm kg 0.300 15,000.00 4,500.00
c Minyak Bekesting liter 0.100 35,000.00 3,500.00
- Upah :
SAT. HARGA
NO. URAIAN PEKERJAAN SAT. INDEKS UPAH (Rp.) BAHAN (Rp.) JUMLAH
(Rp.)
a b c d e f=(dxe) g=(dxe) h=(f+g)
a Pekerja OH 0.520 85,000.00 44,200.00
b Tukang Kayu OH 0.260 110,000.00 28,600.00
c Kepala Tukang OH 0.026 135,000.00 3,510.00
d Mandor OH 0.026 160,000.00 4,160.00
Total 80,470.00 75,500.00
Total Harga 155,970.00
Overhead dan Profit 8% 12,477.60
Jumlah Harga 168,447.60
@ UNTUK 2 KALI PEMAKAIAN / 40% 67,379.04

59 PEMASANGAN 1 M² BEKESTING UNTUK KOLOM


- Bahan :
a Kayu Bekesting m³ 0.040 1,500,000.00 60,000.00
b Paku 5-10 cm kg 0.400 15,000.00 6,000.00
c Minyak Bekesting liter 0.200 35,000.00 7,000.00
d Balok Kayu Kelas II m³ 0.015 2,500,000.00 37,500.00
e Plywood Tebal 9 mm lbr 0.350 150,000.00 52,500.00
f Kayu Dolken Ø8-10 cm Panjang 4 m btg 2.000 15,000.00 30,000.00
- Upah :
a Pekerja OH 0.660 85,000.00 56,100.00
b Tukang Kayu OH 0.330 110,000.00 36,300.00
c Kepala Tukang OH 0.033 135,000.00 4,455.00
d Mandor OH 0.033 160,000.00 5,280.00
Total 102,135.00 193,000.00
Total Harga 295,135.00
Overhead dan Profit 8% 23,610.80
Jumlah Harga 318,745.80
@ UNTUK 2 KALI PEMAKAIAN / 40% 127,498.32

59 PEMASANGAN 1 M² BEKESTING UNTUK BALOK


- Bahan :
a Kayu Bekesting m³ 0.040 1,500,000.00 60,000.00
b Paku 5-10 cm kg 0.400 15,000.00 6,000.00
c Minyak Bekesting liter 0.200 35,000.00 7,000.00
d Balok Kayu Kelas II m³ 0.018 2,500,000.00 45,000.00
e Plywood Tebal 9 mm lbr 0.350 150,000.00 52,500.00
f Kayu Dolken Ø8-10 cm Panjang 4 m btg 2.000 15,000.00 30,000.00
- Upah :
a Pekerja OH 0.660 85,000.00 56,100.00
b Tukang Kayu OH 0.330 110,000.00 36,300.00
c Kepala Tukang OH 0.033 135,000.00 4,455.00
d Mandor OH 0.033 160,000.00 5,280.00
Total 102,135.00 200,500.00
Total Harga 302,635.00
Overhead dan Profit 8% 24,210.80
Jumlah Harga 326,845.80
@ UNTUK 2 KALI PEMAKAIAN / 40% 130,738.32

59 PEMASANGAN 1 M² BEKESTING UNTUK LANTAI


- Bahan :
a Kayu Bekesting m³ 0.040 1,500,000.00 60,000.00
b Paku 5-10 cm kg 0.400 15,000.00 6,000.00
c Minyak Bekesting liter 0.200 35,000.00 7,000.00
d Balok Kayu Kelas II m³ 0.015 2,500,000.00 37,500.00
e Plywood Tebal 9 mm lbr 0.350 150,000.00 52,500.00
f Kayu Dolken Ø8-10 cm Panjang 4 m btg 6.000 15,000.00 90,000.00
- Upah :
a Pekerja OH 0.660 85,000.00 56,100.00
b Tukang Kayu OH 0.330 110,000.00 36,300.00
c Kepala Tukang OH 0.033 135,000.00 4,455.00
d Mandor OH 0.033 160,000.00 5,280.00
Total 102,135.00 253,000.00
Total Harga 355,135.00
Overhead dan Profit 8% 28,410.80
Jumlah Harga 383,545.80
@ UNTUK 2 KALI PEMAKAIAN / 40% 153,418.32

64 MEMBUAT 1 M³ SLOOF UK. 15/20 CM


a Beton Mutu 24,0 Mpa m³ 1.000 1,577,356.20 1,577,356.20
b Pembesian Dengan Besi Polos Atau Ulir kg 120.000 16,475.34 1,977,040.69
c Pemasangan Bekesting Untuk Sloof m² 13.500 67,379.04 909,617.04
Jumlah Harga 4,464,013.93

64 MEMBUAT 1 M³ KOLOM PRAKTIS UK. 15/15 CM


SAT. HARGA
NO. URAIAN PEKERJAAN SAT. INDEKS UPAH (Rp.) BAHAN (Rp.) JUMLAH
(Rp.)
a b c d e f=(dxe) g=(dxe) h=(f+g)
a Beton Mutu 24,0 Mpa m³ 1.000 1,577,356.20 1,577,356.20
b Pembesian Dengan Besi Polos Atau Ulir kg 140.000 16,475.34 2,306,547.48
c Pemasangan Bekesting Untuk Kolom m² 13.330 127,498.32 1,699,552.61
Jumlah Harga 5,583,456.28

64 MEMBUAT 1 M³ RING BALOK UK. 15/20 CM


a Beton Mutu 24,0 Mpa m³ 1.000 1,577,356.20 1,577,356.20
b Pembesian Dengan Besi Polos Atau Ulir kg 120.000 16,475.34 1,977,040.69
c Pemasangan Bekesting Untuk Balok m² 13.500 130,738.32 1,764,967.32
Jumlah Harga 5,319,364.21

64 MEMBUAT 1 M³ PLAT LANTAI TEBAL 12 CM


a Beton Mutu 24,0 Mpa m³ 1.000 1,577,356.20 1,577,356.20
b Pembesian Dengan Besi Polos Atau Ulir kg 140.000 16,475.34 2,306,547.48
c Pemasangan Bekesting Untuk Balok m² 9.800 153,418.32 1,503,499.54
Jumlah Harga 5,387,403.21

PEKERJAAN PENUTUP LANTAI DAN DINDING


72 MEMASANG 1 M² LANTAI KERAMIK UKURAN 20/20 cm ANTI SLIP
- Bahan :
a Keramik 20 x 20 Anti Slip Bh 26.500 2,720.00 72,080.00
b Portland Cement kg 10.400 1,680.00 17,472.00
c Pasir Pasang m³ 0.045 500,000.00 22,500.00
d Semen Warna kg 1.000 27,000.00 27,000.00
- Upah :
e Pekerja OH 0.270 85,000.00 22,950.00
f Tukang Batu OH 0.135 110,000.00 14,850.00
g Kepala Tukang Batu OH 0.014 135,000.00 1,890.00
h Mandor OH 0.014 160,000.00 2,240.00
Total 41,930.00 139,052.00
Total Harga 180,982.00
Overhead dan Profit 8% 14,478.56
Jumlah Harga 195,460.56

73 MEMASANG 1 M² LANTAI KERAMIK UKURAN 60/60 cm


- Bahan :
a Keramik 60 x 60 Bh 3.100 95,000.00 294,500.00
b Portland Cement kg 9.600 1,680.00 16,128.00
c Pasir Pasang m³ 0.045 500,000.00 22,500.00
d Semen Warna kg 1.500 27,000.00 40,500.00
- Upah :
e Pekerja OH 0.240 85,000.00 20,400.00
f Tukang Batu OH 0.120 110,000.00 13,200.00
g Kepala Tukang Batu OH 0.012 135,000.00 1,620.00
h Mandor OH 0.012 160,000.00 1,920.00
Total 37,140.00 373,628.00
Total Harga 410,768.00
Overhead dan Profit 8% 32,861.44
Jumlah Harga 443,629.44

74 MEMASANG 1 M² PLINT KERAMIK UKURAN 10/40 cm


- Bahan :
a Keramik 10 x 40 Bh 2.650 31,666.67 83,916.67
b Portland Cement kg 1.140 1,680.00 1,915.20
c Pasir Pasang m³ 0.003 500,000.00 1,500.00
d Semen Warna kg 0.100 27,000.00 2,700.00
- Upah :
e Pekerja OH 0.090 85,000.00 7,650.00
f Tukang Batu OH 0.090 110,000.00 9,900.00
g Kepala Tukang Batu OH 0.009 135,000.00 1,215.00
h Mandor OH 0.005 160,000.00 800.00
Total 19,565.00 90,031.87
Total Harga 109,596.87
Overhead dan Profit 8% 8,767.75
Jumlah Harga 118,364.62

72 MEMASANG 1 M² LANTAI KERAMIK UKURAN 40/40 cm ANTI SLIP


- Bahan :
a Keramik 40 x 40 Anti Slip Bh 6.630 14,666.67 97,240.00
b Portland Cement kg 9.800 1,680.00 16,464.00
c Pasir Pasang m³ 0.045 500,000.00 22,500.00
d Semen Warna kg 0.600 27,000.00 16,200.00
- Upah :
SAT. HARGA
NO. URAIAN PEKERJAAN SAT. INDEKS UPAH (Rp.) BAHAN (Rp.) JUMLAH
(Rp.)
a b c d e f=(dxe) g=(dxe) h=(f+g)
e Pekerja OH 0.250 85,000.00 21,250.00
f Tukang Batu OH 0.125 110,000.00 13,750.00
g Kepala Tukang Batu OH 0.013 135,000.00 1,755.00
h Mandor OH 0.013 160,000.00 2,080.00
Total 38,835.00 152,404.00
Total Harga 191,239.00
Overhead dan Profit 8% 15,299.12
Jumlah Harga 206,538.12

75 MEMASANG 1 M² LANTAI KERAMIK UKURAN 30/30 cm


- Bahan :
a Keramik 30 x 30 Bh 11.870 5,897.22 70,000.00
b Portland Cement kg 10.000 1,680.00 16,800.00
c Pasir Pasang m³ 0.045 500,000.00 22,500.00
d Semen Warna kg 0.600 27,000.00 16,200.00
- Upah :
e Pekerja OH 0.260 85,000.00 22,100.00
f Tukang Batu OH 0.130 110,000.00 14,300.00
g Kepala Tukang Batu OH 0.013 135,000.00 1,755.00
h Mandor OH 0.013 160,000.00 2,080.00
Toral 40,235.00 125,500.00
Total Harga 165,735.00
Overhead dan Profit 8% 13,258.80
Jumlah Harga 178,993.80

76 MEMASANG 1 M² DINDING KERAMIK UKURAN 20/25 cm


- Bahan :
a Keramik 20 x 25 Bh 21.250 3,341.18 71,000.00
b Portland Cemen kg 10.400 1,680.00 17,472.00
c Pasir Pasang m³ 0.045 500,000.00 22,500.00
d Semen Warna kg 1.000 27,000.00 27,000.00
- Upah :
e Pekerja OH 0.270 85,000.00 22,950.00
f Tukang Batu OH 0.135 110,000.00 14,850.00
g Kepala Tukang Batu OH 0.014 135,000.00 1,890.00
h Mandor OH 0.014 160,000.00 2,240.00
Total 41,930.00 137,972.00
Total Harga 179,902.00
Overhead dan Profit 8% 14,392.16
Jumlah Harga 194,294.16

PEKERJAAN PENGGANTUNG DAN PENGUNCI


77 MEMASANG 1 BUAH KUNCI TANAM BIASA
- Bahan :
a Kunci Tanam Bh 1.000 250,000.00 250,000.00
- Upah :
a Pekerja OH 0.010 85,000.00 850.00
b Tukang Kayu OH 0.500 110,000.00 55,000.00
c Kepala Tukang OH 0.050 135,000.00 6,750.00
d Mandor OH 0.005 160,000.00 800.00
Total 63,400.00 250,000.00
Total Harga 313,400.00
Overhead dan Profit 8% 25,072.00
Jumlah Harga 338,472.00

78 MEMASANG 1 BUAH ENGSEL PINTU


- Bahan :
a Engsel Pintu Bh 1.000 50,000.00 50,000.00
- Upah :
a Pekerja OH 0.015 85,000.00 1,275.00
b Tukang Kayu OH 0.150 110,000.00 16,500.00
c Kepala Tukang OH 0.015 135,000.00 2,025.00
d Mandor OH 0.0008 160,000.00 128.00
Total 19,928.00 50,000.00
Total Harga 69,928.00
Overhead dan Profit 8% 5,594.24
Jumlah Harga 75,522.24

79 MEMASANG 1 BUAH ENGSEL JENDELA


- Bahan :
a Engsel Jendela Bh 1.000 40,000.00 40,000.00
- Upah :
a Pekerja OH 0.010 85,000.00 850.00
SAT. HARGA
NO. URAIAN PEKERJAAN SAT. INDEKS UPAH (Rp.) BAHAN (Rp.) JUMLAH
(Rp.)
a b c d e f=(dxe) g=(dxe) h=(f+g)
b Tukang Kayu OH 0.100 110,000.00 11,000.00
c Kepala Tukang OH 0.010 135,000.00 1,350.00
d Mandor OH 0.0005 160,000.00 80.00
Total 13,280.00 40,000.00
Total Harga 53,280.00
Overhead dan Profit 8% 4,262.40
Jumlah Harga 57,542.40

80 MEMASANG 1 BUAH KAIT ANGIN


- Bahan :
a Kait angin / Hak Angin Bh 1.000 30,000.00 30,000.00
- Upah :
a Pekerja OH 0.015 85,000.00 1,275.00
b Tukang Kayu OH 0.015 110,000.00 1,650.00
c Kepala Tukang OH 0.015 135,000.00 2,025.00
d Mandor OH 0.0008 160,000.00 128.00
Total 5,078.00 30,000.00
Total Harga 35,078.00
Overhead dan Profit 8% 2,806.24
Jumlah Harga 37,884.24

81 MEMASANG 1 BUAH GRENDEL PINTU & JENDELA


- Bahan :
a Grendel Pintu Bh 1.000 30,000.00 30,000.00
- Upah :
a Pekerja OH 0.010 85,000.00 850.00
b Tukang Kayu OH 0.100 110,000.00 11,000.00
c Kepala Tukang OH 0.010 135,000.00 1,350.00
d Mandor OH 0.0008 160,000.00 128.00
Total 13,328.00 30,000.00
Total Harga 43,328.00
Overhead dan Profit 8% 3,466.24
Jumlah Harga 46,794.24

82 MEMASANG 1 BUAH TARIKAN JENDELA


- Bahan :
a Tarikan Jendela Bh 1.000 18,000.00 18,000.00
- Upah :
a Pekerja OH 0.015 85,000.00 1,275.00
b Tukang Kayu OH 0.150 110,000.00 16,500.00
c Kepala Tukang OH 0.015 135,000.00 2,025.00
d Mandor OH 0.0008 160,000.00 128.00
Total 19,928.00 18,000.00
Total Harga 37,928.00
Overhead dan Profit 8% 3,034.24
Jumlah Harga 40,962.24

83 MEMASANG 1 M² KACA TEBAL 5 MM


- Bahan :
a Kaca Polos 5 mm m² 1.100 210,000.00 231,000.00
b Sealant kg 0.050 35,000.00 1,750.00
- Upah :
a Pekerja OH 0.015 85,000.00 1,275.00
b Tukang Kayu OH 0.150 110,000.00 16,500.00
c Kepala Tukang OH 0.015 135,000.00 2,025.00
d Mandor OH 0.0008 160,000.00 128.00
Total 19,928.00 232,750.00
Total Harga 252,678.00
Overhead dan Profit 8% 20,214.24
Jumlah Harga 272,892.24

83 MEMASANG 1 M² KACA CERMIN TEBAL 5 MM


- Bahan :
a Kaca Cermin 5 mm m² 1.100 325,000.00 357,500.00
- Upah :
a Pekerja OH 0.015 85,000.00 1,275.00
b Tukang Kayu OH 0.150 110,000.00 16,500.00
c Kepala Tukang OH 0.015 135,000.00 2,025.00
d Mandor OH 0.008 160,000.00 1,280.00
Total 21,080.00 357,500.00
Total Harga 378,580.00
Overhead dan Profit 8% 30,286.40
Jumlah Harga 408,866.40
SAT. HARGA
NO. URAIAN PEKERJAAN SAT. INDEKS UPAH (Rp.) BAHAN (Rp.) JUMLAH
(Rp.)
a b c d e f=(dxe) g=(dxe) h=(f+g)
PEKERJAAN PENGECATAN
84 MENGECAT 1 M² KAYU BARU ( 1 Lapis plamir, 1 lapis cat dasar 3 lapis cat penutup )
- Bahan :
a Meni Kayu kg 0.200 25,000.00 5,000.00
b Plamir Kayu kg 0.150 60,000.00 9,000.00
c Cat Dasar kg 0.170 54,000.00 9,180.00
d Cat Penutup kg 0.350 50,000.00 17,500.00
e Kuas Bh 0.010 20,000.00 200.00
f Pengencer kg 0.030 30,000.00 900.00
g Ampelas lbr 0.200 6,000.00 1,200.00
- Upah :
a Pekerja OH 0.070 85,000.00 5,950.00
b Tukang Cat OH 0.105 110,000.00 11,550.00
c Kepala Tukang Cat OH 0.004 135,000.00 540.00
d Mandor OH 0.003 160,000.00 480.00
Total 18,520.00 42,980.00
Total Harga 61,500.00
Overhead dan Profit 8% 4,920.00
Jumlah Harga 66,420.00

85 MENGECAT 1 M² DINDING BARU INTERIOR ( 1 Lapis Plamir, 1 Lapis Cat dasar, 2 Lapis Cat Penutup )
- Bahan :
a Plamir kg 0.100 10,000.00 1,000.00
b Cat Dasar kg 0.100 65,000.00 6,500.00
c Cat Penutup 2x kg 0.260 65,000.00 16,900.00
- Upah :
a Pekerja OH 0.020 85,000.00 1,700.00
b Tukang Cat OH 0.063 110,000.00 6,930.00
c Kepala Tukang Cat OH 0.0063 135,000.00 850.50
d Mandor OH 0.003 160,000.00 480.00
Total 9,960.50 24,400.00
Total Harga 34,360.50
Overhead dan Profit 8% 2,748.84
Jumlah Harga 37,109.34

86 MENGECAT 1 M² DINDING BARU EKSTERIOR ( 1 Lapis Plamir, 1 Lapis Cat dasar, 2 Lapis Cat Penutup )
- Bahan :
a Plamir kg 0.100 10,000.00 1,000.00
b Cat Dasar kg 0.100 65,000.00 6,500.00
c Cat Penutup 2x kg 0.260 65,000.00 16,900.00
- Upah :
a Pekerja OH 0.020 85,000.00 1,700.00
b Tukang Cat OH 0.063 110,000.00 6,930.00
c Kepala Tukang Cat OH 0.0063 135,000.00 850.50
d Mandor OH 0.003 160,000.00 480.00
Total 9,960.50 24,400.00
Total Harga 34,360.50
Overhead dan Profit 8% 2,748.84
Jumlah Harga 37,109.34

87 MENGECAT 1 M² PLAFOND BARU ( 1 Lapis Plamir, 1 Lapis Cat dasar, 2 Lapis Cat Penutup )
- Bahan :
a Plamir kg 0.100 10,000.00 1,000.00
b Cat Dasar kg 0.100 55,000.00 5,500.00
c Cat Penutup 2x kg 0.260 55,000.00 14,300.00
- Upah :
a Pekerja OH 0.020 85,000.00 1,700.00
b Tukang Cat OH 0.063 110,000.00 6,930.00
c Kepala Tukang Cat OH 0.0063 135,000.00 850.50
d Mandor OH 0.003 160,000.00 480.00
Total 9,960.50 20,800.00
Total Harga 30,760.50
Overhead dan Profit 8% 2,460.84
Jumlah Harga 33,221.34

88 MENGECAT 1 M² BESI / ALUMINIUM ( 1 Lapis Plamir, 1 Lapis Cat dasar, 2 Lapis Cat Penutup )
- Bahan :
a Cat Meni Besi Anti Karat kg 0.100 29,000.00 2,900.00
b Cat Dasar kg 0.170 56,000.00 9,520.00
c Cat Penutup 2x kg 0.260 56,000.00 14,560.00
- Upah :
a Pekerja OH 0.070 85,000.00 5,950.00
b Tukang Cat OH 0.090 110,000.00 9,900.00
SAT. HARGA
NO. URAIAN PEKERJAAN SAT. INDEKS UPAH (Rp.) BAHAN (Rp.) JUMLAH
(Rp.)
a b c d e f=(dxe) g=(dxe) h=(f+g)
c Kepala Tukang Cat OH 0.006 135,000.00 810.00
d Mandor OH 0.003 160,000.00 480.00
Total 17,140.00 26,980.00
Total Harga 44,120.00
Overhead dan Profit 8% 3,529.60
Jumlah Harga 47,649.60

89 MENGECAT 1 M² PERMUKAAN ATAP SENG


- Bahan :
a Cat Atap kg 0.300 56,000.00 16,800.00
- Upah :
a Pekerja OH 0.006 85,000.00 510.00
b Tukang Cat OH 0.060 110,000.00 6,600.00
c Kepala Tukang Cat OH 0.012 135,000.00 1,620.00
d Mandor OH 0.006 160,000.00 960.00
Total 9,690.00 16,800.00
Total Harga 26,490.00
Overhead dan Profit 8% 2,119.20
Jumlah Harga 28,609.20

PEKERJAAN ATAP
90 MEMASANG 1 M² ATAP SENG GELOMBANG BJLS 30
- Bahan :
a Seng Gelombang BJLS 30 Lembar 0.700 80,000.00 56,000.00
b Paku Seng kg 0.020 26,000.00 520.00
- Upah :
a Pekerja OH 0.120 85,000.00 10,200.00
b Tukang Kayu OH 0.060 110,000.00 6,600.00
c Kepala Tukang Kayu OH 0.006 135,000.00 810.00
d Mandor OH 0.006 160,000.00 960.00
Total 18,570.00 56,520.00
Total Harga 75,090.00
Overhead dan Profit 8% 6,007.20
Jumlah Harga 81,097.20

91 MEMASANG 1 M¹ ATAP NOK SENG


- Bahan :
a Seng Plat BJLS 30 Lembar 0.300 85,000.00 25,500.00
b Paku Seng kg 0.040 26,000.00 1,040.00
- Upah :
a Pekerja OH 0.150 85,000.00 12,750.00
b Tukang Kayu OH 0.070 110,000.00 7,700.00
c Kepala Tukang Kayu OH 0.007 135,000.00 945.00
d Mandor OH 0.006 160,000.00 960.00
Total 22,355.00 26,540.00
Total Harga 48,895.00
Overhead dan Profit 8% 3,911.60
Jumlah Harga 52,806.60

92 MEMASANG 1 M² RANGKA ATAP SIRAP KAYU KELAS I


- Bahan :
a Kayu Kelas m³ 0.014 4,000,000.00 56,000.00
c Paku Biasa kg 0.057 15,000.00 855.00
- Upah :
a Pekerja OH 0.120 85,000.00 10,200.00
b Tukang Kayu OH 0.120 110,000.00 13,200.00
c Kepala Tukang OH 0.012 135,000.00 1,620.00
d Mandor OH 0.006 160,000.00 960.00
Total 25,980.00 56,855.00
Total Harga 82,835.00
Overhead dan Profit 8% 6,626.80
Jumlah Harga 89,461.80

92 MEMASANG 1 M² ATAP SIRAP KAYU


- Bahan :
a Sirap Kayu Bh 30.000 10,500.00 315,000.00
c Paku Biasa kg 0.200 15,000.00 3,000.00
- Upah :
a Pekerja OH 0.166 85,000.00 14,110.00
b Tukang Kayu OH 0.250 110,000.00 27,500.00
c Kepala Tukang OH 0.025 135,000.00 3,375.00
d Mandor OH 0.008 160,000.00 1,280.00
Total 46,265.00 318,000.00
SAT. HARGA
NO. URAIAN PEKERJAAN SAT. INDEKS UPAH (Rp.) BAHAN (Rp.) JUMLAH
(Rp.)
a b c d e f=(dxe) g=(dxe) h=(f+g)
Total Harga 364,265.00
Overhead dan Profit 8% 29,141.20
Jumlah Harga 393,406.20

92 MEMASANG 1 M² RANGKA ATAP GENTENG ( Kaso + Reng )


- Bahan :
a Kayu 5/5 Kelas I/ Usuk m³ 0.014 4,000,000.00 56,000.00
b Papan Kayu Kelas I/ Reng 3/4 m³ 0.057 4,000,000.00 228,000.00
c Paku Biasa kg 0.250 15,000.00 3,750.00
- Upah :
a Pekerja OH 0.100 85,000.00 8,500.00
b Tukang Kayu OH 0.100 110,000.00 11,000.00
c Kepala Tukang OH 0.010 135,000.00 1,350.00
d Mandor OH 0.005 160,000.00 800.00
Total 21,650.00 287,750.00
Total Harga 309,400.00
Overhead dan Profit 8% 24,752.00
Jumlah Harga 334,152.00

93 MEMASANG 1 M² ATAP GENTENG RAINBOW


- Bahan :
a Genteng Rainbow Lembar 1.300 40,000.00 52,000.00
b Paku 2" - 5" kg 0.200 15,000.00 3,000.00
- Upah :
a Pekerja OH 0.200 85,000.00 17,000.00
b Tukang Kayu OH 0.100 110,000.00 11,000.00
c Kepala Tukang Kayu OH 0.010 135,000.00 1,350.00
d Mandor OH 0.001 160,000.00 160.00
Total 29,510.00 55,000.00
Total Harga 84,510.00
Overhead dan Profit 8% 6,760.80
Jumlah Harga 91,270.80

94 MEMASANG 1 M¹ NOK GENTENG RAINBOW


- Bahan :
a Nok Genteng Rainbow Lembar 1.100 40,000.00 44,000.00
b Paku 2" - 5" kg 0.050 15,000.00 750.00
- Upah :
a Pekerja OH 0.250 85,000.00 21,250.00
b Tukang Kayu OH 0.150 110,000.00 16,500.00
c Kepala Tukang OH 0.015 135,000.00 2,025.00
d Mandor OH 0.013 160,000.00 2,080.00
Total 41,855.00 44,750.00
Total Harga 86,605.00
Overhead dan Profit 8% 6,928.40
Jumlah Harga 93,533.40

94 MEMASANG 1 M² LAPISAN PEREDAM BAWAH ATAP


- Bahan :
a Alumunium Foil Lembar 1.080 26,000.00 28,080.00
- Upah :
a Pekerja OH 0.020 85,000.00 1,700.00
b Tukang Kayu OH 0.950 110,000.00 104,500.00
c Kepala Tukang OH 0.090 135,000.00 12,150.00
d Mandor OH 0.010 160,000.00 1,600.00
Total 119,950.00 28,080.00
Total Harga 148,030.00
Overhead dan Profit 8% 11,842.40
Jumlah Harga 159,872.40

94 MEMASANG 1 M² WATERPROOFING DAK ATAP


- Bahan :
a Waterproofing m² 1.050 18,000.00 18,900.00
- Upah :
a Pekerja OH 0.020 85,000.00 1,700.00
b Tukang Cat OH 0.150 110,000.00 16,500.00
c Kepala Tukang OH 0.150 135,000.00 20,250.00
d Mandor OH 0.010 160,000.00 1,600.00
Total 40,050.00 18,900.00
Total Harga 58,950.00
Overhead dan Profit 8% 4,716.00
Jumlah Harga 63,666.00
SAT. HARGA
NO. URAIAN PEKERJAAN SAT. INDEKS UPAH (Rp.) BAHAN (Rp.) JUMLAH
(Rp.)
a b c d e f=(dxe) g=(dxe) h=(f+g)
PEKERJAAN LISTRIK
95 MEMASANG 1 BUAH BOX SEKRING MCB
- Material
a Box Sekring MCB 2 group Set 1.000 7,000.00 7,000.00
b MCB 1P/6A, 6 KA Bh 2.000 69,000.00 138,000.00
c MCB 1P/10A, 6 KA Bh 2.000 69,000.00 138,000.00
- Tenaga
a Tukang Listrik OH 0.170 110,000.00 18,700.00
b Pekerja OH 0.170 85,000.00 14,450.00
Total 33,150.00 283,000.00
Total Harga Set 316,150.00
Overhead dan Profit 8% 25,292.00
Jumlah Harga 341,442.00

96 MEMASANG INSTALASI LISTRIK


- Material
a Kabel NYM 3 x 25 m 21.000 14,000.00 294,000.00
b Kanduit 20 mm m 5.600 12,500.00 70,000.00
c Alat Bantu ( isolasi, clamp dan lain-lain ) Ls 1.000 7,500.00 7,500.00
- Tenaga
a Tukang Listrik OH 0.170 110,000.00 18,700.00
b Pekerja OH 0.170 85,000.00 14,450.00
Total 33,150.00 371,500.00
Total Harga Titik 404,650.00
Overhead dan Profit 8% 32,372.00
Jumlah Harga 437,022.00

97 MEMASANG 1 BUAH LAMPU PHILIPS 18 WATT


- Material
a Lampu SL 18 Watt Bh 1.000 40,000.00 40,000.00
b Fitting Tempel Bh 1.000 10,000.00 10,000.00
c Alat Bantu ( Isolasi, clamp, dan lain-lain ) Ls 1.000 7,500.00 7,500.00
- Tenaga
a Tukang Listrik OH 0.170 110,000.00 18,700.00
b Pekerja OH 0.170 85,000.00 14,450.00
Total 33,150.00 57,500.00
Total Harga Set 90,650.00
Overhead dan Profit 8% 7,252.00
Jumlah Harga 97,902.00

98 MEMASANG 1 BUAH LAMPU SL PHILIPS 23 WATT


- Material
a Lampu SL Philips 23 Watt Bh 1.000 45,000.00 45,000.00
b Fitting Tempel Bh 1.000 10,000.00 10,000.00
c Alat Bantu ( Isolasi, clamp, dan lain-lain ) Ls 1.000 7,500.00 7,500.00
- Tenaga
a Tukang Listrik OH 0.170 110,000.00 18,700.00
b Pekerja OH 0.170 85,000.00 14,450.00
Total 33,150.00 62,500.00
Total Harga Set 95,650.00
Overhead dan Profit 8% 7,652.00
Jumlah Harga 103,302.00

98 MEMASANG 1 BUAH LAMPU DINDING


- Material
a Lampu Dinding + Fitting Bh 1.000 350,000.00 350,000.00
c Alat Bantu ( Isolasi, clamp, dan lain-lain ) Ls 1.000 35,000.00 35,000.00
- Tenaga
a Tukang Listrik OH 0.170 110,000.00 18,700.00
b Pekerja OH 0.170 85,000.00 14,450.00
Total 33,150.00 385,000.00
Total Harga Set 418,150.00
Overhead dan Profit 8% 33,452.00
Jumlah Harga 451,602.00

99 MEMASANG 1 BUAH STOP KONTAK


- Material
a Stop Kontak Komplit Bh 1.000 35,000.00 35,000.00
b Alat Bantu ( isolasi, clamp dan lain-lain ) Ls 1.000 7,500.00 7,500.00
- Tenaga
a Tukang Listrik OH 0.170 110,000.00 18,700.00
b Pekerja OH 0.170 85,000.00 14,450.00
Total 33,150.00 42,500.00
SAT. HARGA
NO. URAIAN PEKERJAAN SAT. INDEKS UPAH (Rp.) BAHAN (Rp.) JUMLAH
(Rp.)
a b c d e f=(dxe) g=(dxe) h=(f+g)
Total Harga Set 75,650.00
Overhead dan Profit 8% 6,052.00
Jumlah Harga 81,702.00

100 MEMASANG 1 BUAH LIMIT SAKLAR


- Material
a Limit Saklar Bh 1.000 70,000.00 70,000.00
b Alat Bantu ( isolasi, clamp dan lain-lain ) Ls 1.000 7,500.00 7,500.00
- Tenaga
a Tukang Listrik OH 0.170 110,000.00 18,700.00
b Pekerja OH 0.170 85,000.00 14,450.00
Total 33,150.00 77,500.00
Total Harga Set 110,650.00
Overhead dan Profit 8% 8,852.00
Jumlah Harga 119,502.00

101 MEMASANG 1 BUAH SAKLAR TUNGGAL


- Material
a Saklar Engkel Bh 1.000 10,000.00 10,000.00
b Alat Bantu ( isolasi, clamp dan lain-lain ) Ls 1.000 7,500.00 7,500.00
- Tenaga
a Tukang Listrik OH 0.170 110,000.00 18,700.00
b Pekerja OH 0.170 85,000.00 14,450.00
Total 33,150.00 17,500.00
Total Harga Set 50,650.00
Overhead dan Profit 8% 4,052.00
Jumlah Harga 54,702.00

102 MEMASANG 1 BUAH SAKLAR GANDA


- Material
a Saklar Ganda Bh 1.000 10,000.00 10,000.00
b Alat Bantu ( isolasi, clamp dan lain-lain ) Ls 1.000 7,500.00 7,500.00
- Tenaga
a Tukang Listrik OH 0.170 110,000.00 18,700.00
b Pekerja OH 0.170 85,000.00 14,450.00
Total 33,150.00 17,500.00
Total Harga Set 50,650.00
Overhead dan Profit 8% 4,052.00
Jumlah Harga 54,702.00

102 MEMASANG 1 BUAH LAMPU TL 1 x 40 WATT


- Material
a Lampu Philps 40 W/ 220 V, komplit kapasitor Bh 1.000 175,000.00 175,000.00
b Alat Bantu ( isolasi, clamp dan lain-lain ) Ls 1.000 7,500.00 7,500.00
- Tenaga
a Tukang Listrik OH 0.170 110,000.00 18,700.00
b Pekerja OH 0.170 85,000.00 14,450.00
Total 33,150.00 182,500.00
Total Harga Set 215,650.00
Overhead dan Profit 8% 17,252.00
Jumlah Harga 232,902.00

103 MEMASANG KABEL SUPLAY MAIN KE SUB PANIL


- Material
a Kanduit 20 mm Bh 5.600 12,500.00 70,000.00
b Alat Bantu ( isolasi, clamp dan lain-lain ) Ls 1.000 7,500.00 7,500.00
- Tenaga
a Tukang Listrik OH 0.030 110,000.00 3,300.00
b Pekerja OH 0.030 85,000.00 2,550.00
Total 5,850.00 77,500.00
Total Harga M' 83,350.00
Overhead dan Profit 8% 6,668.00
Jumlah Harga 90,018.00

PEKERJAAN BAJA
104 PEMASANGAN BAJA STRUKTUR (Kg)
- Bahan :
a Baja Struktur kg 1.050 20,500.00 21,525.00
b Kawat Las kg 0.022 220,000.00 4,840.00
c Mesin Las Jam 0.022 350,000.00 7,700.00
- Upah :
a Pekerja OH 0.020 85,000.00 1,700.00
b Tukang Besi OH 0.030 110,000.00 3,300.00
SAT. HARGA
NO. URAIAN PEKERJAAN SAT. INDEKS UPAH (Rp.) BAHAN (Rp.) JUMLAH
(Rp.)
a b c d e f=(dxe) g=(dxe) h=(f+g)
c Kepala Tukang Besi OH 0.010 135,000.00 1,350.00
d Mandor OH 0.005 160,000.00 800.00
Total 7,150.00 34,065.00
Total Harga 41,215.00
Overhead dan Profit 8% 3,297.20
Jumlah Harga 44,512.20

105 MEMASANG 1 M² RANGKA LANGIT-LANGIT BESI HOLLOW 1X40X40X2 MM (60X120 CM)


- Bahan :
a Rangka Metal Hollow 40x40x2 mm m' 3.500 12,600.00 44,100.00
b Assesoris Ls 1.000 1,260.00 1,260.00
- Upah :
a Pekerja OH 0.250 85,000.00 21,250.00
b Tukang Kayu OH 0.250 110,000.00 27,500.00
c Kepala Tukang OH 0.025 135,000.00 3,375.00
d Mandor OH 0.013 160,000.00 2,080.00
Total 54,205.00 45,360.00
Total Harga 99,565.00
Overhead dan Profit 8% 7,965.20
Jumlah Harga 107,530.20

PEKERJAAN SANITASI
106 MEMASANG 1 M¹ SALURAN PINGGIR BANGUNAN
- Bahan :
a Batu Bata Bh 35.000 5,000.00 175,000.00
b Portland Cement kg 10.000 1,680.00 16,800.00
c Pasir Pasang m³ 0.038 500,000.00 19,000.00
d Plesteran m² 0.850 73,601.32 62,561.12
e Acian m² 0.850 36,410.00 30,948.50
- Upah :
a Pekerja OH 0.100 85,000.00 8,500.00
b Tukang Batu OH 0.150 110,000.00 16,500.00
c Kepala Tukang Batu OH 0.049 135,000.00 6,615.00
d Mandor OH 0.012 160,000.00 1,920.00
Total 33,535.00 304,309.62
Total Harga 337,844.62
Overhead dan Profit 8% 27,027.57
Jumlah Harga 364,872.19

107 MEMASANG 1 BUAH CLOSET DUDUK


- Bahan :
a Kloset Duduk Bh 1.000 6,000,000.00 6,000,000.00
b Portland Cemen kg 6.000 1,680.00 10,080.00
c Pasir Pasang m³ 0.010 500,000.00 5,000.00
- Upah :
a Pekerja OH 1.200 85,000.00 102,000.00
b Tukang Batu OH 1.450 110,000.00 159,500.00
c Kepala Tukang Batu OH 0.145 135,000.00 19,575.00
d Mandor OH 0.100 160,000.00 16,000.00
Total 297,075.00 6,015,080.00
Total Harga 6,312,155.00
Overhead dan Profit 8% 504,972.40
Jumlah Harga 6,817,127.40

107 MEMASANG 1 BUAH CLOSET JONGKOK


- Bahan :
a Kloset Jongkok Bh 1.000 300,000.00 300,000.00
b Portland Cemen kg 6.000 1,680.00 10,080.00
c Pasir Pasang m³ 0.010 500,000.00 5,000.00
- Upah :
a Pekerja OH 1.000 85,000.00 85,000.00
b Tukang Batu OH 1.100 110,000.00 121,000.00
c Kepala Tukang Batu OH 1.000 135,000.00 135,000.00
d Mandor OH 0.160 160,000.00 25,600.00
Total 366,600.00 315,080.00
Total Harga 681,680.00
Overhead dan Profit 8% 54,534.40
Jumlah Harga 736,214.40

108 MEMASANG 1 M¹ PIPA PVC DIA 1/2"


- Bahan :
a Pipa PVC 1/2" m¹ 1.200 7,750.00 9,300.00
b Perlengkapan Set 0.350 2,712.50 949.38
SAT. HARGA
NO. URAIAN PEKERJAAN SAT. INDEKS UPAH (Rp.) BAHAN (Rp.) JUMLAH
(Rp.)
a b c d e f=(dxe) g=(dxe) h=(f+g)
- Upah :
a Pekerja OH 0.081 85,000.00 6,885.00
b Tukang Batu OH 0.135 110,000.00 14,850.00
c Kepala Tukang Batu OH 0.014 135,000.00 1,890.00
d Mandor OH 0.004 160,000.00 640.00
Total 24,265.00 10,249.38
Total Harga 34,514.38
Overhead dan Profit 8% 2,761.15
Jumlah Harga 37,275.53

108 MEMASANG 1 M¹ PIPA PVC DIA 3/4"


- Bahan :
a Pipa PVC 3/4" m¹ 1.200 9,500.00 11,400.00
b Perlengkapan Set 0.350 3,325.00 1,163.75
- Upah :
a Pekerja OH 0.081 85,000.00 6,885.00
b Tukang Batu OH 0.135 110,000.00 14,850.00
c Kepala Tukang Batu OH 0.014 135,000.00 1,890.00
d Mandor OH 0.004 160,000.00 640.00
Total 24,265.00 12,563.75
Total Harga 36,828.75
Overhead dan Profit 8% 2,946.30
Jumlah Harga 39,775.05

109 MEMASANG 1 M¹ PIPA PVC DIA 3"


- Bahan :
a Pipa PVC 3" m¹ 1.200 25,000.00 30,000.00
b Perlengkapan Set 0.350 8,750.00 3,062.50
- Upah :
a Pekerja OH 0.081 85,000.00 6,885.00
b Tukang Batu OH 0.135 110,000.00 14,850.00
c Kepala Tukang Batu OH 0.014 135,000.00 1,890.00
d Mandor OH 0.004 160,000.00 640.00
Total 24,265.00 33,062.50
Total Harga 57,327.50
Overhead dan Profit 8% 4,586.20
Jumlah Harga 61,913.70

110 MEMASANG 1 M¹ PIPA PVC DIA 4"


- Bahan :
a Pipa PVC 4" m¹ 1.200 62,500.00 75,000.00
b Perlengkapan Set 0.350 21,875.00 7,656.25
- Upah :
a Pekerja OH 0.081 85,000.00 6,885.00
b Tukang Batu OH 0.135 110,000.00 14,850.00
c Kepala Tukang Batu OH 0.014 135,000.00 1,890.00
d Mandor OH 0.004 160,000.00 640.00
Total 24,265.00 82,656.25
Total Harga 106,921.25
Overhead dan Profit 8% 8,553.70
Jumlah Harga 115,474.95

111 MEMASANG 1 BUAH WHASTAVEL LENGKAP


- Bahan :
a Whastavel Bh 1.000 1,000,000.00 1,000,000.00
b Portland Cement kg 6.000 1,680.00 10,080.00
c Pasir Pasang m³ 0.010 500,000.00 5,000.00
d Perlengkapan Set 0.350 350,000.00 122,500.00
- Upah :
a Pekerja OH 0.081 85,000.00 6,885.00
b Tukang Batu OH 0.135 110,000.00 14,850.00
c Kepala Tukang Batu OH 0.014 135,000.00 1,890.00
d Mandor OH 0.004 160,000.00 640.00
Total 24,265.00 1,137,580.00
Total Harga 1,161,845.00
Overhead dan Profit 8% 92,947.60
Jumlah Harga 1,254,792.60

112 MEMASANG 1 BUAH KRAN AIR DIA 3/4" ATAU 1/2"


- Bahan :
a Kran Air 3/4" atau 1/2" Bh 1.000 40,000.00 40,000.00
b Seal Tape Bh 0.025 15,000.00 375.00
- Upah :
a Pekerja OH 0.010 85,000.00 850.00
SAT. HARGA
NO. URAIAN PEKERJAAN SAT. INDEKS UPAH (Rp.) BAHAN (Rp.) JUMLAH
(Rp.)
a b c d e f=(dxe) g=(dxe) h=(f+g)
b Tukang Batu OH 0.100 110,000.00 11,000.00
c Kepala Tukang Batu OH 0.010 135,000.00 1,350.00
d Mandor OH 0.004 160,000.00 640.00
Total 13,840.00 40,375.00
Total Harga 54,215.00
Overhead dan Profit 8% 4,337.20
Jumlah Harga 58,552.20

113 MEMASANG I BUAH FLOOR DRAIN


- Bahan :
a Floor Drain Bh 1.000 25,000.00 25,000.00
- Upah :
a Pekerja OH 0.010 85,000.00 850.00
b Tukang Batu OH 0.100 110,000.00 11,000.00
c Kepala Tukang Batu OH 0.010 135,000.00 1,350.00
d Mandor OH 0.005 160,000.00 800.00
Total 14,000.00 25,000.00
Total Harga 39,000.00
Overhead dan Profit 8% 3,120.00
Jumlah Harga 42,120.00

112 MEMASANG 1 BUAH SHOWER SPRAY


- Bahan :
a Shower Spray Bh 1.000 1,600,000.00 1,600,000.00
b Seal Tape Bh 0.025 15,000.00 375.00
- Upah :
a Pekerja OH 0.010 85,000.00 850.00
b Tukang Batu OH 0.100 110,000.00 11,000.00
c Kepala Tukang Batu OH 0.010 135,000.00 1,350.00
d Mandor OH 0.004 160,000.00 640.00
Total 13,840.00 1,600,375.00
Total Harga 1,614,215.00
Overhead dan Profit 8% 129,137.20
Jumlah Harga 1,743,352.20

113 MEMASANG 1 BUAH URINOIR


- Bahan :
a Urinoir Bh 1.000 2,500,000.00 2,500,000.00
b Portland Cemen kg 6.000 1,680.00 10,080.00
c Pasir Pasang m³ 0.010 500,000.00 5,000.00
- Upah :
a Pekerja OH 1.200 85,000.00 102,000.00
b Tukang Batu OH 1.450 110,000.00 159,500.00
c Kepala Tukang Batu OH 0.145 135,000.00 19,575.00
d Mandor OH 0.100 160,000.00 16,000.00
Total 297,075.00 2,515,080.00
Total Harga 2,812,155.00
Overhead dan Profit 8% 224,972.40
Jumlah Harga 3,037,127.40

114 MEMASANG 1 KITCHENSINK


- Bahan :
a Kitchensink Bh 1.000 575,000.00 575,000.00
b Portland Cemen kg 6.000 1,680.00 10,080.00
c Pasir Pasang m³ 0.010 500,000.00 5,000.00
- Upah :
a Pekerja OH 1.200 85,000.00 102,000.00
b Tukang Batu OH 1.450 110,000.00 159,500.00
c Kepala Tukang Batu OH 0.145 135,000.00 19,575.00
d Mandor OH 0.100 160,000.00 16,000.00
Total 297,075.00 590,080.00
Total Harga 887,155.00
Overhead dan Profit 8% 70,972.40
Jumlah Harga 958,127.40
PEDOMAN HARGA SATUAN UPAH DAN BAHAN MATERIAL LOKAL
KECAMATAN WERTAMRIAN
KABUPATEN MALUKU TENGGARA BARAT
TRIWULAN IV ( OKTOBER-DESEMBER ) 2017

HARGA DASAR
NO URAIAN SATUAN KETERANGAN
(Rp.)
1 2 4 5 8

I UPAH KERJA

- Mandor Org / hari 160,000.00 Satuan Harga Kec. Tansel


- Mekanik Org / hari 145,000.00 Satuan Harga Kec. Tansel
- Pembantu Mekanik Org / hari 135,000.00 Satuan Harga Kec. Tansel
- Operator Org / hari 105,000.00 Satuan Harga Kec. Tansel
- Pembantu Operator Org / hari 85,000.00 Satuan Harga Kec. Tansel
- Sopir Org / hari 100,000.00 Satuan Harga Kec. Tansel
- Pembantu Supir Org / hari 85,000.00 Satuan Harga Kec. Tansel
- Kepala Tukang Org / hari 135,000.00 Satuan Harga Kec. Tansel
- Tukang Org / hari 110,000.00 Satuan Harga Kec. Tansel
- Pekerja Org / hari 85,000.00 Satuan Harga Kec. Tansel
- Tukang Ahli Org / hari 145,000.00 Satuan Harga Kec. Tansel
- Tukang Lapangan Tidak Terlatih Org / hari
II. BAHAN BANGUNAN

1. Batu Karang
- Batu uk. 20 - 30 cm M3 373,750.00
- Batu uk. 15 - 20 cm M3 373,750.00
- Batu uk. 5/7 cm M3 373,750.00
- Batu uk. 3/5 cm M3 373,750.00
- Batu uk. 2/3 cm M3 373,750.00
- Batu uk. 1/2 cm M3 373,750.00
- Spilt 0,5/1 cm M3 373,750.00

- Batu Nama * Buah 3,450,000.00 Satuan Harga Kec. Tansel

Batu Karang Pecah Mesin


- Batu uk. 3/5 cm M3 862,500.00 Satuan Harga Kec. Tansel
- Batu uk. 2/3 cm M3 862,500.00 Satuan Harga Kec. Tansel
- Batu uk. 1/2 cm M3 862,500.00 Satuan Harga Kec. Tansel

Batu Karang Pecah Tangan


- Batu uk. 3/5 cm M3 690,000.00 Satuan Harga Kec. Tansel
- Batu uk. 2/3 cm M3 690,000.00 Satuan Harga Kec. Tansel
- Batu uk. 1/2 cm M3 690,000.00 Satuan Harga Kec. Tansel

2. Batu Kali
- Batu uk. 20 - 30 cm M3 460,000.00 Satuan Harga Kec. Tansel
- Batu uk. 15 - 20 cm M3 460,000.00 Satuan Harga Kec. Tansel
- Batu uk. 5/7 cm M3 488,750.00 Satuan Harga Kec. Tansel
- Batu uk. 3/5 cm M3 517,500.00 Satuan Harga Kec. Tansel
- Batu uk. 2/3 cm M3 546,250.00 Satuan Harga Kec. Tansel
- Batu uk. 1/2 cm M3 546,250.00 Satuan Harga Kec. Tansel
- Spilt 0,5/1 cm M3 546,250.00 Satuan Harga Kec. Tansel
HARGA DASAR
NO URAIAN SATUAN KETERANGAN
(Rp.)
1 2 4 5 8

Batu Pecah Impor Mesin


- Batu uk. 3/5 cm M3 1,380,000.00 Satuan Harga Kec. Tansel
- Batu uk. 2/3 cm M3 1,380,000.00 Satuan Harga Kec. Tansel
- Batu uk. 1/2 cm M3 1,380,000.00 Satuan Harga Kec. Tansel

- Pasir Urug M3 460,000.00 Satuan Harga Kec. Tansel


- Pasir Pasang M3 460,000.00 Satuan Harga Kec. Tansel
- Tanah Urug M3 287,500.00 Satuan Harga Kec. Tansel
- Urugan Pilihan M3 345,000.00 Satuan Harga Kec. Tansel
- Sirtu M3 345,000.00 Satuan Harga Kec. Tansel
- Agregat Klas A M3 1,380,000.00 Satuan Harga Kec. Tansel
- Agregat Klas B M3 1,150,000.00 Satuan Harga Kec. Tansel
- Agregat Klas C M3 920,000.00 Satuan Harga Kec. Tansel
- Abu Batu (Filler) M3 1,380,000.00 Satuan Harga Pemprov Jatim

III BATU BATA / BATAKO

- Bata Buah 8,000.00 Satuan Harga Kota Ambon


- Batako Semen Buah 5,000.00 Satuan Harga Kec. Tansel
- Batako (Pres) uk. 8 x 30 x 15 Buah 3,000.00 Satuan Harga Kec. Tansel
- Batako (Pres) uk. 10 x 30 x 15 Buah 5,000.00 Satuan Harga Kec. Tansel
- Batu Angin (Bahan Semen) Buah 85,000.00 Satuan Harga Kec. Tansel

IV SEMEN

- Semen Warna (Ex Putih) kg 27,000.00 Satuan Harga Kec. Tansel


- Semen Portland 50 Kg Zak 84,000.00 Satuan Harga Kec. Tansel

V BAHAN ATAP

- Atap Nipa / Rumbia Lembar -


- Genteng Metal Arista Buah 39,000.00 Satuan Harga Kec. Tansel
- Nok Bubungan Genteng Rainbow Buah 40,000.00 Satuan Harga Kec. Tansel
- Nok Pinggir Genteng Rainbow Buah 40,000.00 Satuan Harga Kec. Tansel
- Nok Onduline Buah 85,000.00 Satuan Harga Kec. Tansel
- Atap onduline Lembar 148,000.00 Satuan Harga Kec. Tansel
- Genteng Aspal m2 165,000.00 Satuan Harga Kec. Tansel

1. Bahan Asbes Gelombang

- Asbes Gelombang Kecil Lembar 49,000.00 Satuan Harga Kec. Tansel


- Asbes Gelombang Besar Lembar 62,000.00 Satuan Harga Kec. Tansel
- Nok Asbes /Karet Meter 18,000.00 Satuan Harga Kec. Tansel

2. Bahan Senk Gelombang

- Senk Gelombang BJLS 0,20 Lembar 50,000.00 Satuan Harga Kec. Tansel
- Senk Gelombang BJLS 0,25 Lembar 54,000.00 Satuan Harga Kec. Tansel
- Senk Gelombang BJLS 0,30 Lembar 80,000.00 Satuan Harga Kec. Tansel
- Senk Gelombang Warna Lembar 60,000.00 Satuan Harga Kec. Tansel
HARGA DASAR
NO URAIAN SATUAN KETERANGAN
(Rp.)
1 2 4 5 8

3. Bahan Senk Plat

- Senk Plat BJLS 0,20 Lembar 55,000.00 Satuan Harga Kec. Tansel
- Senk Plat BJLS 0,25 Lembar 58,000.00 Satuan Harga Kec. Tansel
- Senk Plat BJLS 0,30 Lembar 85,000.00 Satuan Harga Kec. Tansel
- Senk Galvalum 0,3 M2 70,000.00 Satuan Harga Kec. Tansel

- Nok Senk Plat BJLS 0,20 M' 25,000.00 Satuan Harga Kec. Tansel
- Nok Senk Plat BJLS 0,25 M' 25,000.00 Satuan Harga Kec. Tansel

VI BAHAN KAYU

1. Kayu Klas I (ex. Kayu Besi, Lenggua)


- 10 / 10 x 4 M' M3 4,000,000.00
- 5 / 10 x 4 M' M3 4,000,000.00
- 6 / 12 x 4 M' M3 4,000,000.00
- 7 / 13 x 4 M' M3 4,000,000.00
- 8 / 8 x 4 M' M3 4,000,000.00

2. Papan Kayu Klas I (ex. Kayu Besi, Lenggua)


- 0,02 / 0,20 x 4 M' M3 4,000,000.00
- 0,03 / 0,20 x 4 M' M3 4,000,000.00
- 0,04 / 0,20 x 4 M' M3 4,000,000.00
- 0,05 / 0,20 x 4 M' M3 4,000,000.00
- 0,06 / 0,05 x 4 M' M3 4,000,000.00
- 3 x 25 x 3 M' M3 4,000,000.00
- 4 x 25 x 3 M' M3 4,000,000.00

3. Reep/Lat Kayu Klas I (ex. Kayu Besi, Lenggua)


- Kayu Klas I 5/7 cm x 4 M' M3 4,000,000.00
- Kayu Klas I 3/5 cm x 4 M' M3 4,000,000.00
- Kayu Klas I 2/3 cm x 4 M' M3 4,000,000.00

4. Kayu Klas II (ex. Kayu Putih)


- 10 / 10 x 4 M' M3 2,500,000.00
- 5 / 10 x 4 M' M3 2,500,000.00
- 6 / 12 x 4 M' M3 2,500,000.00
- 8 / 12 x 4 M' M3 2,500,000.00
- 4 / 6 x 4 M' M3 2,500,000.00

5. Papan Kayu Klas II (ex. Kayu Putih)


- 3 x 25 x 3 M' M3 2,500,000.00
- 4 x 25 x 3 M' M3 2,500,000.00
- 5 x 25 x 3 M' M3 2,500,000.00

6. Reep/Lat Kayu Klas II (ex. Kayu Putih)


- Kayu Klas II 5/7 cm x 4 M' M3 2,500,000.00
- Kayu Klas II 3/5 cm x 4 M' M3 2,500,000.00
- Kayu Klas II 2/3 cm x 4 M' M3 2,500,000.00
- Kayu Perancah Batang 15,000.00 Satuan Harga Kec. Tansel
- Kayu Bakar M3 500,000.00 Satuan Harga Kec. Tansel
HARGA DASAR
NO URAIAN SATUAN KETERANGAN
(Rp.)
1 2 4 5 8

VII BETON BUIS

- Ukuran t = 10 cm x 50 cm x Ø 100 cm Buah 1,500,000.00 Satuan Harga Kec. Tansel


- Ukuran t = 15 cm x 50 cm x Ø 100 cm Buah 1,650,000.00 Satuan Harga Kec. Tansel
- Ukuran t = 16 cm x 50 cm x Ø 100 cm Buah 1,800,000.00 Satuan Harga Kec. Tansel
- Ukuran t = 20 cm x 50 cm x Ø 100 cm Buah 1,950,000.00 Satuan Harga Kec. Tansel
- Ukuran t = 25 cm x 50 cm x Ø 100 cm Buah 2,150,000.00 Satuan Harga Kec. Tansel
- Ukuran t = 30 cm x 50 cm x Ø 100 cm Buah 2,300,000.00 Satuan Harga Kec. Tansel

VIII KARET

- Karet Elastomerik Jenis 2 Buah 3,000,000.00 Satuan Harga Kec. Tansel

IX BAHAN LANTAI

- Ubin Keramik Warna 20 x 20 cm M2 68,000.00 Satuan Harga Kec. Tansel


- Ubin Keramik Warna 25 x 25 cm M2 71,000.00 Satuan Harga Kec. Tansel
- Ubin Keramik Warna 30 x 30 cm M2 70,000.00 Satuan Harga Kec. Tansel
- Ubin Keramik Warna 40 x 40 cm M2 76,000.00 Satuan Harga Kec. Tansel
- Plint Keramik Warna 15 x 20 cm M2 71,000.00 Satuan Harga Kec. Tansel
- Plint Keramik Warna 40 x 40 cm M2 88,000.00 Satuan Harga Kec. Tansel
- Plint Keramik Warna 50 x 50 cm M2 85,000.00 Satuan Harga Kec. Tansel
- Granit 60 x 60 cm M2 285,000.00 Satuan Harga Kec. Tansel
- Granit 80 x 80 cm M2 295,000.00 Satuan Harga Kec. Tansel
- Wafel Warna 30 x 30 cm M2 375,000.00 Satuan Harga Kec. Tansel
- Wafel Warna 40 x 40 cm M2 375,000.00 Satuan Harga Kec. Tansel
- Paving Block Buah 7,500.00 Satuan Harga Kec. Tansel
- Teraso 30 x 30 cm Buah 7,200.00 Satuan Harga Kec. Tansel
- Ubin Porselin Lokal 11 x 11 cm Buah 2,700.00 Satuan Harga Kec. Tansel
- Ubin Porselin Lokal 15 x 15 cm Buah 3,600.00 Satuan Harga Kec. Tansel
- Ubin Porselin Mosaik Porselin Lokal 15 x 15 cm M2 86,200.00 Satuan Harga Kec. Tansel
- Ubin Porselin Vinil Lapis Asbes M2 81,000.00 Satuan Harga Kec. Tansel
- Ubin Porselin Vinil Lapis Karet M2 72,000.00 Satuan Harga Kec. Tansel
- Ubin Porselin Vinil Roll 2 AN 2 x 1 M' M2 243,000.00 Satuan Harga Kec. Tansel
- Karpet Klas I Meter 85,000.00 Satuan Harga Kec. Tansel

X BAHAN BESI

1. Besi Polos Standard

- Besi Beton dia 4,5 mm Staf 31,000.00 Satuan Harga Kec. Tansel
- Besi Beton dia 6 mm Staf 30,000.00 Satuan Harga Kec. Tansel
- Besi Beton dia 8 mm Staf 62,000.00 Satuan Harga Kec. Tansel
- Besi Beton dia 10 mm Staf 94,000.00 Satuan Harga Kec. Tansel
- Besi Beton dia 12 mm Staf 170,000.00 Satuan Harga Kec. Tansel
- Besi Beton dia 16 mm Staf 275,000.00 Satuan Harga Kec. Tansel
- Besi Beton dia 19 mm Staf 350,000.00 Satuan Harga Kec. Tansel
- Besi Beton dia 22 mm Staf 390,000.00 Satuan Harga Kec. Tansel
- Besi Beton dia 25 mm Staf 601,087.50 Satuan Harga Kec. Tansel
- Besi Beton dia 32 mm Staf 1,150,000.00 Satuan Harga Kec. Tansel
HARGA DASAR
NO URAIAN SATUAN KETERANGAN
(Rp.)
1 2 4 5 8

2. Besi Ulir Standard

- Besi Beton dia 12 mm Staf 160,000.00 Satuan Harga Kec. Tansel


- Besi Beton dia 16 mm Staf 170,000.00 Satuan Harga Kec. Tansel
- Besi Beton dia 19 mm Staf 410,000.00 Satuan Harga Kec. Tansel
- Besi Beton dia 22 mm Staf 540,000.00 Satuan Harga Kec. Tansel
- Besi Beton dia 25 mm Staf 700,000.00 Satuan Harga Kec. Tansel
- Besi Beton dia 32 mm Staf 1,150,000.00 Satuan Harga Kec. Tansel

XI PLAT

- Besi Plat 2,4 mm' Lbr 800,000.00 Satuan Harga Kec. Tansel
- Besi Plat 1,2 mm' Lbr 880,000.00 Satuan Harga Kec. Tansel
- Besi Siku 50.50.5 Staf 125,000.00 Satuan Harga Kec. Tansel
- Besi Siku 50.50.6 Staf 450,000.00 Satuan Harga Kec. Tansel
- Besi Siku 70.70.7 Staf 450,000.00 Satuan Harga Kec. Tansel
- Besi Siku 70.70.6 Staf 500,000.00 Satuan Harga Kec. Tansel
- Besi Siku 20.20.2 Kg 50,500.00 Satuan Harga Barang Pemprov Jatim
- Besi Siku 40.40.4 Kg 90,000.00
- Besi Siku 60.60.6 Kg 490,700.00 Satuan Harga Barang Pemprov Jatim

1. Plat Strip
- 3/4" X 1/8 X 6 m Staf 30,000.00 Satuan Harga Kec. Tansel
- 3/4" X 3/8 X 6 m Staf 26,000.00 Satuan Harga Kec. Tansel
- 1" X 1/8 X 6 m Staf -
- 1" X 1/8 X 6 m Staf -
- 1" X 3/16 X 6 m Staf -
- 1 1/4" X 3/16 X 6 m Staf -

2. Plat Alumunium
- Ukuran 0,3 mm Lbr 100,000.00 Satuan Harga Kec. Tansel
- Ukuran 0,4 mm Lbr -
- Ukuran 0,5 mm Lbr 127,000.00 Satuan Harga Kec. Tansel
- Ukuran 0,6 mm Lbr -

XII KAWAT

- Kawat Beton / Bendrat Kg 26,000.00 Satuan Harga Kec. Tansel


- Kawat Kasa Plastik Lbr 10,000.00 Satuan Harga Kec. Tansel
- Kawat Kasa Lbr 25,000.00 Satuan Harga Kec. Tansel
- Harmonika Jos M 40,000.00 Satuan Harga Kec. Tansel
- Saringan Pasir ( Ayakan ) M 35,000.00 Satuan Harga Kec. Tansel
- Kawat Duri Rol 110,000.00 Satuan Harga Kec. Tansel
- Kawat Bronjong 4 mm Kg 217,000.00 Satuan Harga Kec. Tansel
- Kawat Bronjong 3 mm Rol 1,500,000.00 Satuan Harga Kec. Tansel
- Kawat Angin M2 17,000.00 Satuan Harga Kec. Tansel
- Akustik 60 x 60 Buah -

XIII BAHAN PLAFON


HARGA DASAR
NO URAIAN SATUAN KETERANGAN
(Rp.)
1 2 4 5 8

- Eternit Klas I 4 mm Lbr 85,000.00 Satuan Harga Kec. Tansel


- Tripleks 1.22 x 2.44 3 mm Lbr 59,000.00 Satuan Harga Kec. Tansel
- Tripleks 1.22 x 2.44 9 mm Lbr 150,000.00 Satuan Harga Kec. Tansel
- Hard Board 4 x 8 x 3 mm Lbr 100,000.00 Satuan Harga Kec. Tansel
- Sost Board 4 x 8 x 3 mm Lbr 46,000.00 Satuan Harga Kec. Tansel
- Play Wood 1.22 x 2.44 x 3 mm Lbr 100,000.00 Satuan Harga Kec. Tansel
- Total Wood 4 x 8 x 3 mm Lbr 85,000.00 Satuan Harga Kec. Tansel
- Teak Wood 4 x 8 x 3 mm Lbr 97,000.00 Satuan Harga Kec. Tansel
- Teak Wood 0.90 x 2.10 Lbr 126,000.00 Satuan Harga Kec. Tansel
- Teak Wood 3 x 7 Lbr 75,000.00 Satuan Harga Kec. Tansel
- Jabar Wood Polos Lbr 171,000.00 Satuan Harga Kec. Tansel
- Jabar Wood Warna Lbr 175,500.00 Satuan Harga Kec. Tansel
- Formika Polos 4 x 8 Lbr 126,000.00 Satuan Harga Kec. Tansel
- Formika Warna 4 x 8 Lbr 90,000.00 Satuan Harga Kec. Tansel
- Formika Polos 3 x 6 Lbr 112,500.00 Satuan Harga Kec. Tansel
- Formika Warna 3 x 6 Lbr 112,500.00 Satuan Harga Kec. Tansel
- Gipsum 9 mm Lbr 95,000.00 Satuan Harga Kec. Tansel
- Less Gipsum M' 50,000.00 Satuan Harga Kec. Tansel
- Less Kayu 3 cm M' 30,000.00 Satuan Harga Kec. Tansel
- Less Kayu 5 cm M' 40,000.00 Satuan Harga Kec. Tansel
- Less Kayu 7 cm M' 50,000.00 Satuan Harga Kec. Tansel

XIV BAHAN PIPA

1. Pipa Gip
- Pipa Gip uk. Md1.8" x 6000 MM Non Ulir Staf / Batang 3,575,000.00 Satuan Harga Kec. Tansel
- Pipa Gip uk. Md1.6" x 6000 MM Non Ulir Staf / Batang 2,600,000.00 Satuan Harga Kec. Tansel
- Pipa Gip uk. Md1.4" x 6000 MM Staf / Batang 1,500,000.00 Satuan Harga Kec. Tansel
- Pipa Gip uk. Md1.3" x 6000 MM Staf / Batang 1,200,000.00 Satuan Harga Kec. Tansel
- Pipa Gip uk. Md1.2 1/2" x 6000 MM Staf / Batang 825,000.00 Satuan Harga Kec. Tansel
- Pipa Gip uk. Md1.2" x 6000 MM Staf / Batang 650,000.00 Satuan Harga Kec. Tansel
- Pipa Gip uk. Md1.1 1/2" x 6000 MM Staf / Batang 450,000.00 Satuan Harga Kec. Tansel
- Pipa Gip uk. Md1.1" x 6000 MM Staf / Batang 275,000.00 Satuan Harga Kec. Tansel
- Pipa Gip uk. Md1.3/4" x 6000 MM Staf / Batang 185,000.00 Satuan Harga Kec. Tansel
- Pipa Gip uk. Md1.1/2" x 6000 MM Staf / Batang 160,000.00 Satuan Harga Kec. Tansel
2. Pipa PVC
- Pipa PVC S.10 RRJ AW dia 8 x 6000 MM Staf / Batang 1,300,000.00 Satuan Harga Kec. Tansel
- Pipa PVC S.10 RRJ AW dia 6 x 6000 MM Staf / Batang 900,000.00 Satuan Harga Kec. Tansel
- Pipa PVC S.10 RRJ AW dia 4 x 6000 MM Staf / Batang 375,000.00 Satuan Harga Kec. Tansel
- Pipa PVC S.10 RRJ AW dia 3" x 6000 MM Staf / Batang 150,000.00 Satuan Harga Kec. Tansel
- Pipa PVC S.10 RRJ AW dia 2 1/2" x 6000 MM Staf / Batang 165,000.00 Satuan Harga Kec. Tansel
- Pipa PVC S.10 RRJ AW dia 2" Staf / Batang 90,000.00 Satuan Harga Kec. Tansel
- Pipa PVC AW dia 1 1/2 X 4000 MM Staf / Batang 88,000.00 Satuan Harga Kec. Tansel
- Pipa PVC AW dia 1 X 4000 MM Staf / Batang 40,000.00 Satuan Harga Kec. Tansel
- Pipa PVC AW dia 3/4 X 4000 MM Staf / Batang 38,000.00 Satuan Harga Kec. Tansel
- Pipa PVC AW dia 1/2 X 4000 MM Staf / Batang 31,000.00 Satuan Harga Kec. Tansel
- Pipa Besi Persegi 20 x 20 mm x 6 m M' 79,200.00 Satuan Harga Kec. Tansel
- Pipa Listrik PVC 5/8" x 4 m M' 10,000.00 Satuan Harga Kec. Tansel
- Pipa Listrik PVC 1/4" x 4 m M' 8,000.00 Satuan Harga Kec. Tansel
- Pipa PVC Triliun SNI S12,5 8" x 6000 mm RRJ Staf / Batang 907,300.00 Satuan Harga Prov. Jatim
- Pipa PVC Triliun SNI S10, 6" x 6000 mm RRJ Staf / Batang 698,800.00 Satuan Harga Prov. Jatim
HARGA DASAR
NO URAIAN SATUAN KETERANGAN
(Rp.)
1 2 4 5 8

- Knie PVC AW di 8" Buah 412,000.00 Satuan Harga Kec. Tansel


- Knie PVC AW dia 6" Buah 300,000.00 Satuan Harga Kec. Tansel
- Knie PVC AW dia 4" Buah 150,000.00 Satuan Harga Kec. Tansel
- Knie PVC AW dia 3" Buah 25,000.00 Satuan Harga Kec. Tansel
- Knie PVC AW dia 2 1/2" Buah 25,000.00 Satuan Harga Kec. Tansel
- Knie PVC AW dia 2" Buah 15,000.00 Satuan Harga Kec. Tansel
- Knie PVC AW dia 1 1/2 " Buah 25,000.00 Satuan Harga Kec. Tansel
- Knie PVC AW dia 1 " Buah 3,000.00 Satuan Harga Kec. Tansel
- Knie PVC AW dia 3/4 " Buah 2,500.00 Satuan Harga Kec. Tansel
- Knie PVC AW dia 1/2" Buah 2,000.00 Satuan Harga Kec. Tansel
- Knie GIP dia 4" Buah 200,000.00 Satuan Harga Kec. Tansel
- Knie GIP dia 3" Buah 125,000.00 Satuan Harga Kec. Tansel
- Knie GIP dia 2 1/2" Buah 60,000.00 Satuan Harga Kec. Tansel
- Knie GIP dia 2" Buah 35,000.00 Satuan Harga Kec. Tansel
- Knie GIP dia 1 1/2" Buah 25,000.00 Satuan Harga Kec. Tansel
- Knie GIP dia 1" Buah 15,000.00 Satuan Harga Kec. Tansel
- Knie GIP dia 3/4" Buah 8,500.00 Satuan Harga Kec. Tansel
- Knie GIP dia 1/2" Buah 6,000.00 Satuan Harga Kec. Tansel

- Over Sock GIP 6" x 4" SGP Las Buah 132,900.00 Satuan Harga Prov. Jatim
- Over Sock GIP 4" x 3" SGP Las Buah 60,100.00 Satuan Harga Prov. Jatim
- Sok GIP dia 6" Buah 125,000.00 Satuan Harga Kec. Tansel
- Sok GIP dia 4" Buah 90,000.00 Satuan Harga Kec. Tansel
- Sok GIP dia 3" Buah 80,000.00 Satuan Harga Kec. Tansel
- Sok GIP dia 2 1/2" Buah 50,000.00 Satuan Harga Kec. Tansel
- Sok GIP dia 2" Buah 30,000.00 Satuan Harga Kec. Tansel
- Sok GIP dia 1 1/2" Buah 25,000.00 Satuan Harga Kec. Tansel
- Sok GIP dia 1" Buah 15,000.00 Satuan Harga Kec. Tansel
- Sok GIP dia 3/4" Buah 8,500.00 Satuan Harga Kec. Tansel
- Sok GIP dia 1/2" Buah 6,500.00 Satuan Harga Kec. Tansel

- Double Nepel GIP dia 6" Buah 300,000.00 Satuan Harga Kec. Tansel
- Double Nepel GIP dia 4" Buah 150,000.00 Satuan Harga Kec. Tansel
- Double Nepel GIP dia 3" Buah 75,000.00 Satuan Harga Kec. Tansel
- Double Nepel GIP dia 2 1/2" Buah 90,000.00 Satuan Harga Kec. Tansel
- Double Nepel GIP dia 2" Buah 30,000.00 Satuan Harga Kec. Tansel
- Double Nepel GIP dia 1 1/2" Buah 25,000.00 Satuan Harga Kec. Tansel
- Double Nepel GIP dia 1" Buah 15,000.00 Satuan Harga Kec. Tansel
- Double Nepel GIP dia 3/4" Buah 9,000.00 Satuan Harga Kec. Tansel
- Double Nepel GIP dia 1/2" Buah 6,500.00 Satuan Harga Kec. Tansel
- Water Moer 6" Buah 155,000.00 Satuan Harga Kec. Tansel
- Water Moer 4" Buah 350,000.00 Satuan Harga Kec. Tansel
- Water Moer 3" Buah 180,000.00 Satuan Harga Kec. Tansel
- Water Moer 2 1/2" Buah 100,000.00 Satuan Harga Kec. Tansel
- Water Moer 2" Buah 70,000.00 Satuan Harga Kec. Tansel
- Water Moer 1" Buah 30,000.00 Satuan Harga Kec. Tansel
- Water Moer 1/2" Buah 20,000.00 Satuan Harga Kec. Tansel
- Meter Air Type LXLC 6" Standart ISO 4064 Buah 2,964,500.00 Satuan Harga Kec. Tansel
- Meter Air Type LXLC 4" Standart ISO 4064 Buah 2,047,100.00 Satuan Harga Kec. Tansel
- Meter Air Type LXLC 3" Standart ISO 4064 Buah 1,821,050.00 Satuan Harga Kec. Tansel
HARGA DASAR
NO URAIAN SATUAN KETERANGAN
(Rp.)
1 2 4 5 8

- Meter Air Type LXLC 2" Standart ISO 4064 Buah 1,541,540.00 Satuan Harga Kec. Tansel
- Meter Air SR - 13 MM Merk Onda dia 1/2" Buah 300,000.00 Satuan Harga Kec. Tansel

- Tee Sock GIP dia 6" X 6" X 6" Buah 600,000.00 Satuan Harga Kec. Tansel
- Tee Sock GIP dia 4" X 4" X 4" Buah 175,000.00 Satuan Harga Kec. Tansel
- Tee Sock GIP dia 3" X 3" X 3" Buah 150,000.00 Satuan Harga Kec. Tansel
- Tee Sock GIP dia 2 1/2" X 2 1/2" X 2 1/2" Buah 94,000.00 Satuan Harga Kec. Tansel
- Tee Sock GIP dia 2" X 2" X 2" Buah 45,000.00 Satuan Harga Kec. Tansel
- Tee Sock GIP dia 1" X 1" X 1" Buah 20,000.00 Satuan Harga Kec. Tansel
- Tee Sock GIP dia 1/2" X 1/2" X 1/2" Buah 8,000.00 Satuan Harga Kec. Tansel

- Over Sock (Reducing) PVC 8" x 4" Buah 410,000.00 Satuan Harga Kec. Tansel
- Over Sock (Reducing) PVC 6" X 4" Buah 180,000.00 Satuan Harga Kec. Tansel
- Over Sock (Reducing) PVC 4" X 3" Buah 55,000.00 Satuan Harga Kec. Tansel
- Over Sock (Reducing) PVC 3" X 2" Buah 35,000.00 Satuan Harga Kec. Tansel
- Over Sock (Reducing) PVC 2 X 1" Buah 12,500.00 Satuan Harga Kec. Tansel
- Over Sock (Reducing) PVC 1" X 3/4" Buah 5,000.00 Satuan Harga Kec. Tansel
- Over Sock (Reducing) PVC 3/4 X 1/2" Buah 3,000.00 Satuan Harga Kec. Tansel
- Sock Drat Dalam PVC AW dia 4" Buah 50,000.00 Satuan Harga Kec. Tansel
- Sock Drat Dalam PVC AW dia 3" Buah 40,000.00 Satuan Harga Kec. Tansel
- Sock Drat Dalam PVC AW dia 2" Buah 15,000.00 Satuan Harga Kec. Tansel
- Sock Drat Dalam PVC AW dia 1 1/2" Buah 10,000.00 Satuan Harga Kec. Tansel
- Sock Drat Dalam PVC AW dia 1" Buah 6,000.00 Satuan Harga Kec. Tansel
- Sock Drat Dalam PVC AW dia 3/4" Buah 4,000.00 Satuan Harga Kec. Tansel
- Sock Drat Dalam PVC AW dia 1/2" Buah 3,000.00 Satuan Harga Kec. Tansel
- Sock Drat Dalam Kuningan PVC 3/4" Buah 17,500.00 Satuan Harga Kec. Tansel
- Sock Drat Dalam Kuningan PVC 1/2" Buah 12,000.00 Satuan Harga Kec. Tansel

- Gate Valves Flange Cast Iron 10-K 8" Buah 7,688,250.00 Satuan Harga Kec. Tansel
- Gate Valves Flange Cast Iron 10-K 6" Buah 4,538,000.00 Satuan Harga Kec. Tansel
- Gate Valves Flange Cast Iron 10-K 4" Buah 2,206,000.00 Satuan Harga Kec. Tansel
- Gate Valves Flange Cast Iron 10-K 3" Buah 1,500,000.00 Satuan Harga Kec. Tansel
- Gate Valves Flange Cast Iron 10-K 2" Buah 800,000.00 Satuan Harga Kec. Tansel
- Gate Valves (Putar) Kuningan Merk Onda 21/2" Buah 689,250.00 Satuan Harga Kec. Tansel
- Gate Valves (Putar) Kuningan Merk Onda 2" Buah 500,000.00 Satuan Harga Kec. Tansel
- GateValves (Putar) Kuningan Merk Onda 1/2" Buah 60,000.00 Satuan Harga Kec. Tansel
- GateValves (Putar) Kuningan Merk Onda 1" Buah 150,000.00 Satuan Harga Kec. Tansel
- GateValves (Putar) Kuningan Merk Onda 3/4" Buah 90,000.00 Satuan Harga Kec. Tansel
- GateValves (Putar) Kuningan Merk Onda 1/2" Buah 60,000.00 Satuan Harga Kec. Tansel

- Check Valve Flange 6" Cast Iron 10K ASAHI Buah 3,375,200.00 Satuan Harga Prov. Jatim
- Check Valve Flange 4" Cast Iron 10K ASAHI Buah 1,978,500.00 Satuan Harga Prov. Jatim
- Check Valve Flange 2" Cast Iron 10K ASAHI Buah 640,000.00 Satuan Harga Prov. Jatim

- Ball Valves Handle Kuningan Merk Onda 2" Buah 550,000.00 Satuan Harga Kec. Tansel
- Ball Valves Handle Kuningan Merk Onda 1" Buah 200,000.00 Satuan Harga Kec. Tansel
- Ball Valves Handle Kuningan Merk Onda 3/4" Buah 150,000.00 Satuan Harga Kec. Tansel
- Ball Valves Handle Kuningan Merk Onda 1/2" Buah 95,000.00 Satuan Harga Kec. Tansel
- Kran Merk Onda 3/4" Buah 40,000.00 Satuan Harga Kec. Tansel
- Kran Merk Onda 1/2" Buah 25,000.00 Satuan Harga Kec. Tansel
- Plug Kran Merk Onda 3/4" Buah 85,000.00 Satuan Harga Kec. Tansel
HARGA DASAR
NO URAIAN SATUAN KETERANGAN
(Rp.)
1 2 4 5 8

- Plug Kran Merk Onda 1/2" Buah 45,000.00 Satuan Harga Kec. Tansel

- Over Sock GIP 6" X 4" Buah 125,000.00 Satuan Harga Kec. Tansel
- Over Sock GIP 4" X 3" Buah 130,000.00 Satuan Harga Kec. Tansel
- Over Sock GIP 3" X 2" Buah 75,000.00 Satuan Harga Kec. Tansel
- Over Sock GIP 3 X 1/2" Buah 65,000.00 Satuan Harga Kec. Tansel
- Over Sock GIP 2 1/2" X 2" Buah 47,000.00 Satuan Harga Kec. Tansel
- Over Sock GIP 2" X 11/2" Buah 30,000.00 Satuan Harga Kec. Tansel
- Over Sock GIP 2 x 1" Buah 35,000.00 Satuan Harga Kec. Tansel
- Over Sock GIP 11/2 x 1" Buah 20,000.00 Satuan Harga Kec. Tansel
- Over Sock GIP 1 x 3/4" Buah 13,000.00 Satuan Harga Kec. Tansel
- Over Sock GIP 1 x 1/2" Buah 13,000.00 Satuan Harga Kec. Tansel
- Over Sock GIP 3/4 x 1/2" Buah 10,000.00 Satuan Harga Kec. Tansel
- Kunci Pipa 36" Buah 500,000.00 Satuan Harga Kec. Tansel
- Kunci Pipa 18" Buah 175,000.00 Satuan Harga Kec. Tansel
- Kunci Pipa 14" Buah 120,000.00 Satuan Harga Kec. Tansel
- Kunci Pipa 12" Buah 60,000.00 Satuan Harga Kec. Tansel
- Kunci Pipa (Kunci Rantai)" Buah 250,000.00 Satuan Harga Kec. Tansel
- Alat Sney Pipa 2" s/d 4" Buah 1,200,000.00 Satuan Harga Kec. Tansel
- Alat Sney Pipa 1/2" s/d 2" Buah 700,000.00 Satuan Harga Kec. Tansel
- Alat Sney Pipa 1/2" s/d 1 1/4" Buah 500,000.00 Satuan Harga Kec. Tansel
- Band 60° Gip 6 ˮ Buah -
- Band 60° Gip 8 ˮ Buah -
- Band 45° Gip 6 ˮ Buah 129,600.00 Satuan Harga Prov. Jatim
- Band 45° Gip 8 ˮ Buah 272,000.00 Satuan Harga Prov. Jatim
- Band 90° Gip 8 ˮ Buah 473,600.00 Satuan Harga Prov. Jatim
- Band 90° Gip 6 ˮ Buah 211,000.00 Satuan Harga Prov. Jatim

XV BAHAN KACA

1. Kaca
- Kaca Bening tbl. 3 mm 120 X 150 M2/Lbr 140,000.00 Satuan Harga Kec. Tansel
- Kaca Polos tbl. 5 mm 120 X 150 M2/Lbr 210,000.00 Satuan Harga Kec. Tansel
- Kaca Es / Kembang tbl. 2 mm M2/Lbr -
- Kaca Es / Kembang tbl. 3 mm M2/Lbr 250,000.00 Satuan Harga Kec. Tansel
- Kaca Es / Kembang tbl. 5 mm M2/Lbr 350,000.00 Satuan Harga Kec. Tansel
- Kaca Ray band tbl. 3 mm M2/Lbr 155,000.00 Satuan Harga Kec. Tansel
- Kaca Ray band tbl. 5 mm M2/Lbr 230,000.00 Satuan Harga Kec. Tansel

2. Rangka Nako
- Jendela Nako 4 mata Buah 50,000.00 Satuan Harga Kec. Tansel
- Jendela Nako 5 mata Buah 62,500.00 Satuan Harga Kec. Tansel
- Jendela Nako 6 mata Buah 75,000.00 Satuan Harga Kec. Tansel
- Jendela Nako 8 mata Buah 100,000.00 Satuan Harga Kec. Tansel
- Jendela Nako 12 mata Buah 150,000.00 Satuan Harga Kec. Tansel

XVI BAHAN LISTRIK

- Lampu LED 80 W COB, 4500-5000K Buah 4,125,000.00 Satuan Harga Prov. Jatim
- Poly Cristal Silicon 240 Wp Buah 4,368,000.00 Satuan Harga Prov. Jatim
- Proteksi 24 V 10 A, IP67 Buah 2,137,500.00 Satuan Harga Prov. Jatim
HARGA DASAR
NO URAIAN SATUAN KETERANGAN
(Rp.)
1 2 4 5 8

- Battery (Deep Cyle VRLA 12 V 120 Ah) Buah 7,250,000.00 Satuan Harga Prov. Jatim
Tiang Besi Kelas Q235, 7m (1 Tiang, 2bh Lengan
- Set 5,300,000.00 Satuan Harga Prov. Jatim
Lampu, 1 Struktur Tiang)
- DC, Karet Sikon Kabel Coper Ungu dan Konektor Set 246,000.00 Satuan Harga Prov. Jatim
- Tiang Besi 9 M 100 daN Batang 7,800,000.00 Satuan Harga Kec. Tansel
- Tiang Besi 11 M 200 daN Batang 5,000,000.00 Satuan Harga Kec. Tansel
- Trafes Besi U 10 x 10 x 180 cm Buah 872,800.00 Satuan Harga Kec. Tansel
- Cross arm type A3 Set 1,635,000.00 Satuan Harga Kec. Tansel
- Arm Tie Set 331,000.00 Satuan Harga Kec. Tansel
- Beugle 4" Buah 65,000.00 Satuan Harga Kec. Tansel
- Baut Beugle 4" Buah 99,000.00 Satuan Harga Kec. Tansel
- Isolator Tumpu 20 KV + Pin Isolator Buah 584,000.00 Satuan Harga Kec. Tansel
- Isolator Tarik 20 KV Set 980,000.00 Satuan Harga Kec. Tansel
- Alumunium Binding Wiere M' 26,000.00 Satuan Harga Kec. Tansel
- AAAC 70 mm2 M' 120,000.00 Satuan Harga Kec. Tansel
- Joint Sleeve 70 mm2 Buah 35,000.00 Satuan Harga Kec. Tansel
- Tap Conektor 35-70 mm2 Buah 30,000.00 Satuan Harga Kec. Tansel
- Bolt and Nuts (M16 x 75) Buah 24,000.00 Satuan Harga Kec. Tansel
- Suspension Assembly Buah 113,000.00 Satuan Harga Kec. Tansel
- Fixed and Assembly Buah 119,000.00 Satuan Harga Kec. Tansel
- Bundle and Proteksion Set 119,000.00 Satuan Harga Kec. Tansel
- Stainless Still Strip M' 65,000.00 Satuan Harga Kec. Tansel
- LVTC 3 x 70 + 1 x 50 mm2 M' 132,000.00 Satuan Harga Kec. Tansel
- Compresion Joit With Cover 50 mm2 Buah 30,000.00 Satuan Harga Kec. Tansel
- Compresion Tension Joint With Cover 70 mm2 Buah 35,000.00 Satuan Harga Kec. Tansel
- Taping Clamp 35-70 mm2 Buah 30,000.00 Satuan Harga Kec. Tansel
- Guy Wire Band 2/8" x 1,5 x 3 Buah 95,000.00 Satuan Harga Kec. Tansel
- Trun Bukle 0,5 x 15" Buah 122,500.00 Satuan Harga Kec. Tansel
- Guy Wire Clamp 35 mm2 Buah 12,000.00 Satuan Harga Kec. Tansel
- Isalator TM (Isalator Blimbing) Buah 165,000.00 Satuan Harga Kec. Tansel
- Achor Rod 5/8" Buah 154,000.00 Satuan Harga Kec. Tansel
- Guy Wire Blok Buah 225,000.00 Satuan Harga Kec. Tansel
- Stell Wire 35 mm2 M' 60,000.00 Satuan Harga Kec. Tansel
- Grund ROD 3/4'' x 1,20 cm Buah 190,000.00 Satuan Harga Kec. Tansel
- Grund Rod Clamp Buah 12,000.00 Satuan Harga Kec. Tansel
- Stoping Braket Buah 25,000.00 Satuan Harga Kec. Tansel
- Earthing Bend 1/8" x 1/2" - 4" x 3/4" Buah 95,000.00 Satuan Harga Kec. Tansel
- Earthing Bend 1/8" x 1/2" - 6" x 3/4" Buah 95,000.00 Satuan Harga Kec. Tansel
- Paralel Grove 70 mm2 Buah 30,000.00 Satuan Harga Kec. Tansel
- Paralel Grove 50 mm2 Buah 25,000.00 Satuan Harga Kec. Tansel
- Besi UNP 10x10x20 cm Buah 193,750.00 Satuan Harga Kec. Tansel
- Pipa Penguat Buah 185,600.00 Satuan Harga Kec. Tansel
- Klem Beugle 3"dua mata Buah 72,000.00 Satuan Harga Kec. Tansel
- Klem Beugle 4"dua mata Buah 72,000.00 Satuan Harga Kec. Tansel
- Strut Arm Benb 1/8"x1 1/2''x4'' Buah 98,800.00 Satuan Harga Kec. Tansel
- Kompresion Lug AL/Cu 35-70 mm2 Buah 79,600.00 Satuan Harga Kec. Tansel
- Scun 35 mm2 Buah 52,200.00 Satuan Harga Kec. Tansel
- Scun 50 mm2 Buah 53,400.00 Satuan Harga Kec. Tansel
- Scun 70 mm2 Buah 62,300.00 Satuan Harga Kec. Tansel
- Dudukan Trafo 3 Phasa 50 KVA Buah 1,039,500.00 Satuan Harga Kec. Tansel
- Dudukan Trafo 3 Phasa 100 KVA Buah 3,326,400.00 Satuan Harga Kec. Tansel
HARGA DASAR
NO URAIAN SATUAN KETERANGAN
(Rp.)
1 2 4 5 8

- Dudukan Trafo 3 Phasa 160 KVA Buah 3,326,400.00 Satuan Harga Kec. Tansel
- Dudukan Trafo 3 Phasa 200 KVA Buah 3,326,400.00 Satuan Harga Kec. Tansel
- Pole Bend 2/2 x 114 U/Penahan Trafo Set 99,800.00 Satuan Harga Kec. Tansel
- Cross Arm U/cut Out & Arester Set 1,372,200.00 Satuan Harga Kec. Tansel
- Cut Out 20 KV + Fuse Link 2 A Set 3,800,000.00 Satuan Harga Kec. Tansel
- L Arester 24 KV Set 3,500,000.00 Satuan Harga Kec. Tansel
- Pole Bend 1/2x114 U/Penahan LSVB Set 65,000.00 Satuan Harga Kec. Tansel
- Kawat CU 50 mm2 M' 22,600.00 Satuan Harga Kec. Tansel
- UNP 10x10x70 mm2 Buah 485,000.00 Satuan Harga Kec. Tansel
- Beugle 8" Buah 68,000.00 Satuan Harga Kec. Tansel
- Beugle 6" Buah 65,000.00 Satuan Harga Kec. Tansel
- Elbow PVC 5/8" Buah 1,500.00 Satuan Harga Kec. Tansel
- T Dos PVC 5/8" Buah 5,100.00 Satuan Harga Kec. Tansel
- Pipa Arde (GIP 1/2") Buah 35,800.00 Satuan Harga Kec. Tansel
- Klem No 11 Dos 18,000.00 Satuan Harga Kec. Tansel
- Klem 10 Dos 18,000.00 Satuan Harga Kec. Tansel
- Sekrup Kayu Buah 10,000.00 Satuan Harga Kec. Tansel
- Rol Isolator Buah 12,000.00 Satuan Harga Kec. Tansel
- Lampu Sorot Lapangan 400 Watt Buah 7,000,000.00 Satuan Harga Kec. Tansel
- Kabel NYM 2 x 2,5 mm2 M' 12,000.00 Satuan Harga Kec. Tansel
- Kabel NYM 3 x 2,5mm2 M' 14,000.00 Satuan Harga Kec. Tansel
- Kabel NYA 4 mm2 M' 8,000.00 Satuan Harga Kec. Tansel
- Kabel NYA 2,5 mm2 M' 325,000.00 Satuan Harga Kec. Tansel
- Kabel NYM 4X4 mm2 M' 40,000.00 Satuan Harga Kec. Tansel
- Kabel NYM 2 x 2 1/2 mm2 M' 35,000.00 Satuan Harga Kec. Tansel
- Kabel NYM 3 x 2 1/2 mm2 M' 17,000.00 Satuan Harga Kec. Tansel
- Kabel NYM 2X4 mm2 M' 16,000.00 Satuan Harga Kec. Tansel
- Kabel NYM 3X4 mm2 M' 20,000.00 Satuan Harga Kec. Tansel
- Kabel NYM 4X4 mm2 M' 40,000.00 Satuan Harga Kec. Tansel
- Kabel NYA 1,5 mm2 Roll 300,000.00 Satuan Harga Kec. Tansel
- Kabel NYA 2,5 mm2 Roll 325,000.00 Satuan Harga Kec. Tansel
- Kabel NYA 4 mm2 Roll 450,000.00 Satuan Harga Kec. Tansel
- Stop kontak Buah 25,000.00 Satuan Harga Kec. Tansel
- Lampu Neon (komplit) TL 10 W Buah 65,000.00 Satuan Harga Kec. Tansel
- Lampu Neon (komplit) TL 20 W Buah 85,000.00 Satuan Harga Kec. Tansel
- Lampu TL 1 x 40 W Buah 185,000.00 Satuan Harga Kec. Tansel
- Lampu TL 2 x 40 W Buah 20,000.00 Satuan Harga Kec. Tansel
- MCB 2 A Buah 70,000.00 Satuan Harga Kec. Tansel
- MCB 4 A Buah 70,000.00 Satuan Harga Kec. Tansel
- MCB 6 A Buah 69,000.00 Satuan Harga Kec. Tansel
- MCB 10 A Buah 69,000.00 Satuan Harga Kec. Tansel
- MCB 16 A Buah 170,000.00 Satuan Harga Kec. Tansel
- MCB 20 A Buah 65,000.00 Satuan Harga Kec. Tansel
- MCB 25 A Buah 70,000.00 Satuan Harga Kec. Tansel
- MCB 32 A Buah 70,000.00 Satuan Harga Kec. Tansel
- Boks MCB Tempel 1 Grup Buah 5,000.00 Satuan Harga Kec. Tansel
- Boks MCB Tempel 2 Grup Buah 7,000.00 Satuan Harga Kec. Tansel
- Boks MCB Tempel 4 Grup Buah 40,000.00 Satuan Harga Kec. Tansel
- Boks MCB Tanam 4 Grup Buah 75,000.00 Satuan Harga Kec. Tansel
- Boks MCB Tanam 8 Grup Buah 80,000.00 Satuan Harga Kec. Tansel
- Boks MCB Tanam 10 Grup Buah 120,000.00 Satuan Harga Kec. Tansel
HARGA DASAR
NO URAIAN SATUAN KETERANGAN
(Rp.)
1 2 4 5 8

- Boks MCB Tanam 12 Grup Buah 120,000.00 Satuan Harga Kec. Tansel
- Dos Inbow PVC 5/8 Buah 3,000.00 Satuan Harga Kec. Tansel
- T Dos PVC 5/8 Buah 3,000.00 Satuan Harga Kec. Tansel
- Isolator Buah 1,500.00 Satuan Harga Kec. Tansel
- Benang kasur Buah 15,000.00 Satuan Harga Kec. Tansel
- Isolator Bliimbing Buah 173,250.00 Satuan Harga Kec. Tansel
- Fitting Duduk (Tempel) Buah 10,000.00 Satuan Harga Kec. Tansel
- Fitting (Gantung) Buah 6,000.00 Satuan Harga Kec. Tansel
- Fitting Dowun Ligth (Kecil) Buah 50,000.00 Satuan Harga Kec. Tansel
- Fitting Dowun Ligth (Sedang) Buah 60,000.00 Satuan Harga Kec. Tansel
- Fitting Dowun Ligth (Besar) Buah 60,000.00 Satuan Harga Kec. Tansel
- TL Bulat 20 W (komplit) Buah 25,000.00 Satuan Harga Kec. Tansel
- TL Bulat 40 W (komplit) Buah 40,000.00 Satuan Harga Kec. Tansel
- Ongkos Pasang Titik Lampu Titik 170,000.00 Satuan Harga Kec. Tansel
- Saklar Tunggal (Tanam) Buah 10,000.00 Satuan Harga Kec. Tansel
- Saklar Tunggal (Tempel) Buah 10,000.00 Satuan Harga Kec. Tansel
- Saklar Ganda (Tanam) Buah 10,000.00 Satuan Harga Kec. Tansel
- Saklar Ganda (Tempel) Buah 25,000.00 Satuan Harga Kec. Tansel
- Lampu SL 18 W Buah 40,000.00 Satuan Harga Kec. Tansel
- Lampu SL 23 W Buah 45,000.00 Satuan Harga Kec. Tansel
- Panel MCB Buah 300,000.00 Satuan Harga Kec. Tansel
- Lampu TL 1X40 W Buah 175,000.00 Satuan Harga Kec. Tansel
- Lampu TL 2X40 W Buah 200,000.00 Satuan Harga Kec. Tansel
- Sekring 1 phase Buah 50,000.00 Satuan Harga Kec. Tansel
- Sekring 2 phase Buah 60,000.00 Satuan Harga Kec. Tansel
- Stop Kontak Buah 35,000.00 Satuan Harga Kec. Tansel
- Stop Kontak Titik 27,000.00 Satuan Harga Kec. Tansel
- Downlight +Lampu SL 23 W Buah 106,000.00 Satuan Harga Kec. Tansel
- Trafo 3 Phasa 50 Kva Unit 112,855,400.00 Satuan Harga Kec. Tansel
- Trafo 3 Phasa 100 Kva Unit 123,679,500.00 Satuan Harga Kec. Tansel
- Trafo 3 Phasa 160 Kva Unit 174,581,400.00 Satuan Harga Kec. Tansel
- Trafo 3 Phasa 200 Kva Unit 207,020,100.00 Satuan Harga Kec. Tansel
- Dudukan LSVB 3 Phasa 2 Jurusan Unit 1,050,000.00 Satuan Harga Kec. Tansel
- Dudukan LSVB 3 Phasa 3 Jurusan Unit 1,575,000.00 Satuan Harga Kec. Tansel
- Dudukan3 LSVB Phasa 4 Jurusan Unit 3,150,000.00 Satuan Harga Kec. Tansel
- LSVB 3 Phasa 2 Jurusan 250 Kva Unit 7,024,500.00 Satuan Harga Kec. Tansel
- LSVB 3 Phasa 3 Jurusan 450 Kva Unit 14,700,000.00 Satuan Harga Kec. Tansel
- LSVB 3 Phasa 4 Jurusan 650 Kva Unit 15,750,000.00 Satuan Harga Kec. Tansel
- NYY 4 X 5 mm² M' 472,500.00 Satuan Harga Kec. Tansel
- Compresion Lung 50 mm² Al/Cu Buah 80,300.00 Satuan Harga Kec. Tansel
- Ground Rod 3/4 x 2,75 m Buah 291,900.00 Satuan Harga Kec. Tansel
- Ground Rod 3/4" x 1,20 cm Buah 199,500.00 Satuan Harga Kec. Tansel
- Timer Unit 600,000.00 Satuan Harga Prov. Jatim
- Konduit 20 mm Buah 12,500.00 Satuan Harga Kec. Tansel
- Kabel NYYHY 2 X 2.5 mm M' 11,000.00 Satuan Harga Kec. Tansel
- Kabel NYYHY 2 X 1.5 mm M' 8,000.00 Satuan Harga Kec. Tansel

XVII ALAT PENGGANTUNG / PENGUNCI

- Kunci Union Elite ( Komplit) Buah 250,000.00 Satuan Harga Kec. Tansel
- Kunci Union Asli Buah 200,000.00 Satuan Harga Kec. Tansel
HARGA DASAR
NO URAIAN SATUAN KETERANGAN
(Rp.)
1 2 4 5 8

- Kunci Yalle Doble Buah 125,000.00 Satuan Harga Kec. Tansel


- Kunci Tezah Buah 150,000.00 Satuan Harga Kec. Tansel
- Kunci Royal Buah 85,000.00 Satuan Harga Kec. Tansel
- Kunci Kuda Terbang Buah 100,000.00 Satuan Harga Kec. Tansel
- Kunci Saise Buah 475,000.00 Satuan Harga Kec. Tansel
- Engsel Jendela Kuningan 3 " Pasang 40,000.00 Satuan Harga Kec. Tansel
- Engsel Pintu Kuningan 4 " Pasang 50,000.00 Satuan Harga Kec. Tansel
- Grendel jendela Pasang 30,000.00 Satuan Harga Kec. Tansel
- Kait Angin segi Pasang 30,000.00 Satuan Harga Kec. Tansel
- Tarikan Jendela Buah 18,000.00 Satuan Harga Kec. Tansel

XVIII BAHAN SANITAIR

- Kloset Putih Buah 150,000.00 Satuan Harga Kec. Tansel


- Kloset Teraso Buah 215,000.00 Satuan Harga Kec. Tansel
- Kloset Porselin Buah 300,000.00 Satuan Harga Kec. Tansel
- Kloset Warna Buah 154,000.00 Satuan Harga Kec. Tansel
- Kloset Keramik Duduk Buah 1,600,000.00 Satuan Harga Kec. Tansel
- Kloset Keramik Duduk Lengkap Buah 6,000,000.00 Satuan Harga Kec. Tansel
- Wastafel Lokal Putih Buah 600,000.00 Satuan Harga Kec. Tansel
- Wastafel Warna / Keramik Lengkap Buah 1,000,000.00 Satuan Harga Kec. Tansel
- Tempat cuci 1 Lobang Buah 350,000.00 Satuan Harga Kec. Tansel
- Tempat cuci 2 Lobang Buah 575,000.00 Satuan Harga Kec. Tansel
- Urinoir Lokal Putih Buah 2,500,000.00 Satuan Harga Kec. Tansel
- Urinoir Lokal Warna Buah 2,500,000.00 Satuan Harga Kec. Tansel
- Bak air Lapis Keramik 60 x 70 x 80 Buah 2,000,000.00 Satuan Harga Kec. Tansel
- Septic Tank 1,5 x 1,5 x 2 Buah 3,000,000.00 Satuan Harga Kec. Tansel
- Floor Drain (Stainles) Buah 25,000.00 Satuan Harga Kec. Tansel

XIX FLOOR DRAIN

- Ukuran Dia. 0,5 m x 0,55 m Buah 15,000.00 Satuan Harga Kec. Tansel
- Ukuran Dia. 0,7 m x 0,7 m Buah 7,500.00 Satuan Harga Kec. Tansel
- Ukuran Dia. 0,5 m x 0,55 m (Plastik) Buah 5,000.00 Satuan Harga Kec. Tansel
- Ukuran Dia. 0,7 m x 0,7 m (Teraso) Buah 110,000.00 Satuan Harga Kec. Tansel
- Saringan Air (metal) Buah 35,000.00 Satuan Harga Kec. Tansel
- Saringan Air (plastik) Buah 30,000.00 Satuan Harga Kec. Tansel

XX POMPA

- Pompa Air 80 Watt Nasional (Otomatic) Buah 850,000.00 Satuan Harga Kec. Tansel
- Pompa Air 100 Watt Sanyo (Otomatic) Buah 1,550,000.00 Satuan Harga Kec. Tansel
- Pompa Air Dragon Buah 1,600,000.00 Satuan Harga Kec. Tansel
- Pompa Air Tangan Dragon Buah -

XXI BAHAN ASPAL

- Aspal Panas Kg 17,000.00 Satuan Harga Kec. Tansel


- Aspal Dingin Kg 15,000.00 Satuan Harga Kec. Tansel
Aspal Emulsi Kg 15,000.00 Satuan Harga Kec. Tansel
- Aspal Beton Kg 15,000.00 Satuan Harga Kec. Tansel
HARGA DASAR
NO URAIAN SATUAN KETERANGAN
(Rp.)
1 2 4 5 8

- Premium Subsidi Liter 6,600.00 Satuan Harga Kec. Tansel


- Minyak Tanah Subsidi Liter 4,800.00 Satuan Harga Kec. Tansel
- Solar Subsidi Liter 6,400.00 Satuan Harga Kec. Tansel
- Premium Industri * Liter 9,600.70 Satuan Harga Kec. Tansel
- Minyak Tanah Industri * Liter 12,519.05 Satuan Harga Kec. Tansel
- Solar Industri * Liter 12,310.10 Satuan Harga Kec. Tansel
- Minyak Diesel* Liter 11,360.90 Satuan Harga Kec. Tansel
- Minyak Bakar * Liter 8,327.65 Satuan Harga Kec. Tansel

*: Harga per 01 Juni 2017 oleh PT. PERTAMINA (Persero) Kantor Pemasaran Ambon untuk Bidang
Usaha Kontraktor Jalan, Usaha Transportasi (Darat/Laut)

XXII BAHAN PAKU DAN BOUT

1. Paku

- Paku uk. 1-4 cm Kg 20,000.00 Satuan Harga Kec. Tansel


- Paku uk. 5-12 cm Kg 15,000.00 Satuan Harga Kec. Tansel
- Paku Sirap Kg 21,000.00 Satuan Harga Kec. Tansel
- Paku Sekrup/Ulir Kg 35,000.00 Satuan Harga Kec. Tansel
- Paku Senk Kg 26,000.00 Satuan Harga Kec. Tansel
- Paku Firkan Kg 18,000.00 Satuan Harga Kec. Tansel

2. Bout

- Bout 1/2" Buah 2,500.00 Satuan Harga Kec. Tansel


- Bout 10 Buah 3,250.00 Satuan Harga Kec. Tansel
- Bout 30 Buah 8,000.00 Satuan Harga Kec. Tansel

XXIII BAHAN FINISHING

- Amplas Kayu / Besi Lbr 6,000.00 Satuan Harga Kec. Tansel


- Dempul Kayu Kg 60,000.00 Satuan Harga Kec. Tansel
- Spiritus Ltr 20,000.00 Satuan Harga Kec. Tansel
- Minyak Cat Kg 30,000.00 Satuan Harga Kec. Tansel
- Politur Kg 50,000.00 Satuan Harga Kec. Tansel
- Teac Oil / Minyak Bekesting Kg 35,000.00 Satuan Harga Kec. Tansel
- Meni Kayu Kg 25,000.00 Satuan Harga Kec. Tansel
- Meni Besi Kg 29,000.00 Satuan Harga Kec. Tansel
- Cat Besi Kg 56,000.00 Satuan Harga Kec. Tansel
- Cat Dasar / Meni Kg 54,000.00 Satuan Harga Kec. Tansel
- Cat Dinding (ex. Merk Glotex) Kg 55,000.00 Satuan Harga Kec. Tansel
- Cat Dinding (ex. Merk Patua) Kg 65,000.00 Satuan Harga Kec. Tansel
- Cat Dinding (ex. Merk Dana Pain) Kg 125,000.00 Satuan Harga Kec. Tansel
- Cat Dinding (ex. Merk Pinotex) Kg 54,000.00 Satuan Harga Kec. Tansel
- Cat Marka Jalan Kg 60,000.00 Satuan Harga Kec. Tansel
- Cat Dinding (25 Kg) (ex. Metrolite) Kg 520,000.00 Satuan Harga Kec. Tansel
- Cat Dinding (ex. Dulux Interior) Kg 325,000.00 Satuan Harga Kec. Tansel
- Cat Dinding (ex. Dulux Eksterior) Kg 325,000.00 Satuan Harga Kec. Tansel
- Cat Dinding (ex. Aqua Proof) Kg 180,000.00 Satuan Harga Kec. Tansel
- Colkarium Kg -
HARGA DASAR
NO URAIAN SATUAN KETERANGAN
(Rp.)
1 2 4 5 8

- Kapur Api Kg 10,000.00 Satuan Harga Kec. Tansel


- Matex Kg -
- Plamir Tembok 20 Kg Ember 200,000.00 Satuan Harga Kec. Tansel
- Cat Dana Brite Kg 45,000.00 Satuan Harga Kec. Tansel
- Residu Kg 4,500.00 Satuan Harga Kec. Tansel
- Cat ICI Kg 65,000.00 Satuan Harga Kec. Tansel
- Lem Kayu Kg 60,000.00 Satuan Harga Kec. Tansel
- Selang Nipon 1/2" M' 20,000.00 Satuan Harga Kec. Tansel
- Selang Nipon 1/4" M' 15,000.00 Satuan Harga Kec. Tansel
- Selang Biasa 1/2" M' 9,000.00 Satuan Harga Kec. Tansel

Catatan : Harga Dasar tidak termasuk Biaya Transport,Pajak, Keuntungan, dan Lain-lain.

Anda mungkin juga menyukai