REKAPITULASI

RENCANA ANGGARAN BIAYA (RAB)

PEKERJAAN : RUKO PASAR TUNGGANG


LOKASI : DESA TUNGGANG
TAHUN ANGGARAN : 2022

SUB JUMLAH JUMLAH


No. URAIAN PEKERJAAN
[Rp] [Rp]
A PEKERJAAN PERSIAPAN 14,170,000.00 14,170,000.00
B SISTEM MANAJEMEN KESELAMATAN DAN KESEHATAN KERJA 16,150,000.00 16,150,000.00
C PEKERJAAN BANGUNAN LANTAI 1 2,371,620,111.56
D PEKERJAAN TANAH DAN PASIR 74,360,991.80
I PEKERJAAN BETON 1,524,373,779.86
III PEKERJAAN PASANGAN 609,710,493.54
IV PEKERJAAN KUSEN PINTU DAN JENDELA 48,121,499.62
V PEKERJAAN INSTALASI LISTRIK 22,390,000.00
VII PEKERJAAN SANITASI 32,960,088.00
VIII PEKERJAAN BESI 7,000,000.00
IX PEKERJAAN PENGECATAN 52,703,258.74
E PEKERJAAN BANGUNAN LANTAI 2 1,236,381,445.25
I PEKERJAAN BETON 479,444,725.82
II PEKERJAAN PASANGAN 561,079,231.26
III PEKERJAAN KUSEN PINTU DAN JENDELA 56,885,998.48
IV PEKERJAAN INSTALASI LISTRIK 29,527,500.00
V PEKERJAAN SANITASI 25,429,918.00
VI PEKERJAAN PENGECATAN 84,014,071.69
F PEKERJAAN BANGUNAN LANTAI 3 557,825,607.43
I PEKERJAAN BETON 367,601,873.57
II PEKERJAAN PASANGAN 71,120,104.31
III PEKERJAAN KUSEN PINTU DAN JENDELA 4,031,374.91
IV PEKERJAAN INSTALASI LISTRIK 4,845,000.00
V PEKERJAAN BESI 7,000,000.00
VI PEKERJAAN PENGECATAN 11,987,954.50
VII PEKERJAAN ATAP 91,239,300.15
SUB JUMLAH FISIK 4,196,147,164.24
DIBULATKAN 4,196,147,000.00
empat milyar seratus sembilan puluh enam juta seratus empat puluh tujuh ribu rupiah

Dibuat oleh,

AHMAD MIRZA DWIANTA

Anda mungkin juga menyukai