ANALISA HARGA SATUAN

PROGRAM : -

KEGIATAN : PEMBANGUNAN PASTORI


PEKERJAAN : PEMBANGUNAN PASTORI
LOKASI : ALO KEC. RAINIS
TAHUN ANGGARAN : 2023

A.2.2.1.4. Pengukuran dan Pemasangan 1 m' Bouplank

HARGA SATUAN SUB TOTAL


NO U R A I A N KODE SATUAN KOEF
(Rp) (Rp)
A. TENAGA KERJA
1 Pekerja L.01 OH 0,100 100.000,00 10.000,00
2 Tukang Kayu L.02 OH 0,100 200.000,00 20.000,00
3 Kepala Tukang L.03 OH 0,010 250.000,00 2.500,00
4 Mandor L.04 OH 0,005 - -

32.500,00
B. BAHAN
1 Kayu Balok 5/7 M3 0,012 1.800.000,00 21.600,00
2 Paku 2" - 3 " Kg 0,020 47.446,56 948,93
3 Kayu Papan 3/20 M3 0,007 1.800.000,00 12.600,00

35.148,93
C. PERALATAN

-
D. Jumlah (A+B+C) 67.648,93
E. Overhead & Profit
F. HARGA SATUAN (D + E) 67.648,93

A.2.3.1.1. Penggalian 1 M3 Tanah Biasa Sedalam 1 M

HARGA SATUAN SUB TOTAL


NO U R A I A N KODE SATUAN KOEF
(Rp) (Rp)
A. TENAGA KERJA
1 Pekerja L.01 OH 0,750 100.000,00 75.000,00
2 Mandor L.04 OH 0,025 - -

75.000,00
B. BAHAN

C. PERALATAN

D. Jumlah (A+B+C) 75.000,00


E. Overhead & Profit
F. HARGA SATUAN (D + E) 75.000,00

A.2.3.1.2. Penggalian 1 M3 Tanah Biasa Sedalam 2 M

HARGA SATUAN SUB TOTAL


NO U R A I A N KODE SATUAN KOEF
(Rp) (Rp)
A. TENAGA KERJA
1 Pekerja L.01 OH 0,900 100.000,00 90.000,00
2 Mandor L.04 OH 0,045 - -

90.000,00
B. BAHAN

C. PERALATAN

D. Jumlah (A+B+C) 90.000,00


E. Overhead & Profit
F. HARGA SATUAN (D + E) 90.000,00
A.2.3.1.9. Pengurungan Kembali 1 M3 Galian Tanah

HARGA SATUAN SUB TOTAL


NO U R A I A N KODE SATUAN KOEF
(Rp) (Rp)
A. TENAGA KERJA
1 Pekerja L.01 OH 0,500 100.000,00 50.000,00
2 Mandor L.04 OH 0,050 - -

50.000,00
B. BAHAN

C. PERALATAN

D. Jumlah (A+B+C) 50.000,00


E. Overhead & Profit
F. HARGA SATUAN (D + E) 50.000,00

A.2.3.1.11a. Pengurugan 1 M3 Dengan Tanah Urug

HARGA SATUAN SUB TOTAL


NO U R A I A N KODE SATUAN KOEF
(Rp) (Rp)
A. TENAGA KERJA
1 Pekerja L.01 OH 0,300 100.000,00 30.000,00
2 Mandor L.04 OH 0,010 - -

30.000,00
B. BAHAN
Tanah Urug M3 1,2000 - -

-
C. PERALATAN

D. Jumlah (A+B+C) 30.000,00


E. Overhead & Profit
F. HARGA SATUAN (D + E) 30.000,00

A.2.3.1.11b. Pengurugan 1 M3 Dengan Pasir Urug

HARGA SATUAN SUB TOTAL


NO U R A I A N KODE SATUAN KOEF
(Rp) (Rp)
A. TENAGA KERJA
1 Pekerja L.01 OH 0,300 100.000,00 30.000,00
2 Mandor L.04 OH 0,010 - -

30.000,00
B. BAHAN
Pasir Urug M3 1,2000 200.000,00 240.000,00

240.000,00
C. PERALATAN

D. Jumlah (A+B+C) 270.000,00


E. Overhead & Profit
F. HARGA SATUAN (D + E) 270.000,00
A.3.2.1.2 Pemasangan 1 M3 Pondasi Batu Belah Campuran 1 : 4

HARGA SATUAN SUB TOTAL


NO U R A I A N KODE SATUAN KOEFISIEN
(Rp) (Rp)
A. TENAGA KERJA
1 Pekerja L.01 OH 1,500 150.000,00 225.000,00
2 Tukang Batu L.02 OH 0,750 200.000,00 150.000,00
3 Kepala Tukang L.03 OH 0,075 250.000,00 18.750,00
4 Mandor L.04 OH 0,075 - -

393.750,00
B. BAHAN
1 Batu Belah M3 1,200 541.250,00 649.500,00
2 Semen Portland Kg 163,000 1.800,00 293.400,00
3 Pasir Pasang M3 0,520 200.000,00 104.000,00

1.046.900,00
C. PERALATAN

D. Jumlah (A+B+C) 1.440.650,00


E. Overhead & Profit
F. HARGA SATUAN (D + E) 1.440.650,00

A.3.2.1.9 Pemasangan 1 M3 Batu Kosong (Anstamping)

HARGA SATUAN SUB TOTAL


NO U R A I A N KODE SATUAN KOEFISIEN
(Rp) (Rp)
A. TENAGA KERJA
1 Pekerja L.01 OH 0,780 150.000,00 117.000,00
2 Tukang Batu L.02 OH 0,390 200.000,00 78.000,00
3 Kepala Tukang L.03 OH 0,039 250.000,00 9.750,00
4 Mandor L.04 OH 0,039 - -

204.750,00
B. BAHAN
1 Batu Belah M3 1,200 541.250,00 649.500,00
2 Pasir Urug M3 0,432 200.000,00 86.400,00

735.900,00
C. PERALATAN

D. Jumlah (A+B+C) 940.650,00


E. Overhead & Profit
F. HARGA SATUAN (D + E) 940.650,00

A.4.1.1.17 Membuat 10 Kg Dengan Besi Polos atau Besi Ulir

HARGA SATUAN SUB TOTAL


NO U R A I A N KODE SATUAN KOEFISIEN
(Rp) (Rp)
A. TENAGA KERJA
1 Pekerja L.01 OH 0,070 150.000,00 10.500,00
2 Tukang Besi L.02 OH 0,070 200.000,00 14.000,00
3 Kepala Tukang L.03 OH 0,007 250.000,00 1.750,00
4 Mandor L.04 OH 0,004 - -

26.250,00
B. BAHAN
1 Besi Beton (Polos/Ulir) Kg 10,500 14.571,00 152.995,50
2 Kawat Beton Kg 0,150 28.118,75 4.217,81

157.213,31
C. PERALATAN

D. Jumlah (A+B+C) 183.463,31


E. Overhead & Profit (Contoh 15 %)
F. HARGA SATUAN (D + E) 183.463,31
A.4.1.1.21 (K3) Pemasangan 1 M2 Bekisting Untuk Sloof

HARGA SATUAN SUB TOTAL


NO U R A I A N KODE SATUAN KOEFISIEN
(Rp) (Rp)
A. TENAGA KERJA
1 Pekerja L.01 OH 0,520 150.000,00 78.000,00
2 Tukang Kayu L.02 OH 0,260 200.000,00 52.000,00
3 Kepala Tukang L.03 OH 0,026 250.000,00 6.500,00
4 Mandor L.04 OH 0,026 - -

136.500,00
B. BAHAN
1 Kayu Kelas III M3 0,045 2.000.000,00 90.000,00
2 Paku 5 - 10 cm Kg 0,300 47.446,56 14.233,97
3 Minyak Bekisting Liter 0,100 15.000,00 1.500,00

105.733,97
C. PERALATAN

D. Jumlah (A+B+C) 242.233,97


E. Overhead & Profit
F. HARGA SATUAN (D + E) 242.233,97

A.4.1.1.22 (K3) Pemasangan 1 M2 Bekisting Untuk Kolom

HARGA SATUAN SUB TOTAL


NO U R A I A N KODE SATUAN KOEFISIEN
(Rp) (Rp)
A. TENAGA KERJA
1 Pekerja L.01 OH 0,660 150.000,00 99.000,00
2 Tukang Kayu L.02 OH 0,330 200.000,00 66.000,00
3 Kepala Tukang L.03 OH 0,033 250.000,00 8.250,00
4 Mandor L.04 OH 0,033 - -

173.250,00
B. BAHAN
1 Kayu Kelas III M3 0,040 2.000.000,00 80.000,00
2 Paku 5 - 12 cm Kg 0,400 47.446,56 18.978,62
3 Minyak Bekisting Liter 0,200 15.000,00 3.000,00
4 Balok Kayu Kelas III M3 0,015 2.000.000,00 30.000,00
5 Plywood Tebal 9 mm Lbr 0,350 127.301,25 44.555,44
6 Dolken Kayu Ø 8-10cm -panjang 4m Batang 2,000 20.000,00 40.000,00

216.534,06
C. PERALATAN

D. Jumlah (A+B+C) 389.784,06


E. Overhead & Profit
F. HARGA SATUAN (D + E) 389.784,06

A.4.1.1.23 (K3) Pemasangan 1 M2 Bekisting Untuk Balok

HARGA SATUAN SUB TOTAL


NO U R A I A N KODE SATUAN KOEFISIEN
(Rp) (Rp)
A. TENAGA KERJA
1 Pekerja L.01 OH 0,660 150.000,00 99.000,00
2 Tukang Kayu L.02 OH 0,330 200.000,00 66.000,00
3 Kepala Tukang L.03 OH 0,033 250.000,00 8.250,00
4 Mandor L.04 OH 0,033 - -

173.250,00
B. BAHAN
1 Kayu Kelas III M3 0,040 2.000.000,00 80.000,00
2 Paku 5 - 12 cm Kg 0,400 47.446,56 18.978,62
3 Minyak Bekisting Liter 0,200 15.000,00 3.000,00
4 Balok Kayu Kelas III M3 0,018 2.000.000,00 36.000,00
5 Plywood Tebal 9 mm Lbr 0,350 127.301,25 44.555,44
6 Dolken Kayu Ø 8-10cm -panjang 4m Batang 2,000 20.000,00 40.000,00

222.534,06
C. PERALATAN

D. Jumlah (A+B+C) 395.784,06


E. Overhead & Profit
F. HARGA SATUAN (D + E) 395.784,06
A.4.1.1.24 (K3) Pemasangan 1 M2 Bekisting Untuk Lantai

HARGA SATUAN SUB TOTAL


NO U R A I A N KODE SATUAN KOEFISIEN
(Rp) (Rp)
A. TENAGA KERJA
1 Pekerja L.01 OH 0,660 150.000,00 99.000,00
2 Tukang Kayu L.02 OH 0,330 200.000,00 66.000,00
3 Kepala Tukang L.03 OH 0,033 250.000,00 8.250,00
4 Mandor L.04 OH 0,033 - -

173.250,00
B. BAHAN
1 Kayu Kelas III M3 0,040 2.000.000,00 80.000,00
2 Paku 5 - 12 cm Kg 0,400 47.446,56 18.978,62
3 Minyak Bekisting Liter 0,200 15.000,00 3.000,00
4 Balok Kayu Kelas III M3 0,015 2.000.000,00 30.000,00
5 Plywood Tebal 9 mm Lbr 0,350 127.301,25 44.555,44
6 Dolken Kayu Ø 8-10cm -panjang 4m Batang 6,000 20.000,00 120.000,00

296.534,06
C. PERALATAN

D. Jumlah (A+B+C) 469.784,06


E. Overhead & Profit
F. HARGA SATUAN (D + E) 469.784,06

Membuat 1 M3 Beton Tumbuk Camp 1 Sp 3 PP 5 Kr

HARGA SATUAN SUB TOTAL


NO U R A I A N KODE SATUAN KOEFISIEN
(Rp) (Rp)
A. TENAGA KERJA
1 Pekerja L.01 OH 1,650 150.000,00 247.500,00
2 Tukang Batu L.02 OH 0,250 200.000,00 50.000,00
3 Kepala Tukang L.03 OH 0,025 250.000,00 6.250,00
4 Mandor L.04 OH 0,080 - -

303.750,00
B. BAHAN
1 Semen Portland Kg 218,000 1.800,00 392.400,00
2 Pasir Beton M3 0,520 200.000,00 104.000,00
3 Kerikil Beton M3 0,870 650.000,00 565.500,00

1.061.900,00
C. PERALATAN

D. Jumlah (A+B+C) 1.365.650,00


E. Overhead & Profit
F. HARGA SATUAN (D + E) 1.365.650,00

Membuat 1 M3 Beton Camp 1 Sp 2 PP 3 Kr

HARGA SATUAN SUB TOTAL


NO U R A I A N KODE SATUAN KOEFISIEN
(Rp) (Rp)
A. TENAGA KERJA
1 Pekerja L.01 OH 1,650 150.000,00 247.500,00
2 Tukang Batu L.02 OH 0,275 200.000,00 55.000,00
3 Kepala Tukang L.03 OH 0,027 250.000,00 6.750,00
4 Mandor L.04 OH 0,075 - -

309.250,00
B. BAHAN
1 Semen Portland Kg 326,000 1.800,00 586.800,00
2 Pasir Beton M3 0,540 200.000,00 108.000,00
3 Kerikil Beton M3 0,810 650.000,00 526.500,00

1.221.300,00
C. PERALATAN

D. Jumlah (A+B+C) 1.530.550,00


E. Overhead & Profit
F. HARGA SATUAN (D + E) 1.530.550,00
1 M3 Plat Beton Bertulang Camp. 1 : 2 : 3 (112.820 Kg Besi + Bekisting ) Tebal 8 cm

HARGA SATUAN SUB TOTAL


NO U R A I A N KODE SATUAN KOEFISIEN
(Rp) (Rp)
A. TENAGA KERJA

1 Beton Camp. 1 : 2 : 3 M3 1,000 1.530.550,00 1.530.550,00


2 Besi Beton Kg 112,820 18.346,33 2.069.823,92
3 Bekisting M2 6,250 469.784,06 2.936.150,37

6.536.524,29

D. Jumlah (A+B+C) 6.536.524,29


E. Overhead & Profit
F. HARGA SATUAN (D + E) 6.536.524,29

A.4.4.1.8. Pemasangan 1 M2 Dinding Batako Cetak (8x15x25) cm tebal 1/2 batako Campuran 1 SP : 3 PP

HARGA SATUAN SUB TOTAL


NO U R A I A N KODE SATUAN KOEFISIEN
(Rp) (Rp)
A. TENAGA KERJA
1 Pekerja L.01 OH 0,300 150.000,00 45.000,00
2 Tukang Batu L.02 OH 0,100 200.000,00 20.000,00
3 Kepala Tukang L.03 OH 0,010 250.000,00 2.500,00
4 Mandor L.04 OH 0,015 - -

67.500,00

B. BAHAN
1 Batako M3 23,000 3.629,88 83.487,13
2 SemenPortland Kg 14,370 1.800,00 25.866,00
3 Pasir Pasang M3 0,040 200.000,00 8.000,00

117.353,13
C. PERALATAN

D. Jumlah (A+B+C) 184.853,13


E. Overhead & Profit -
F. HARGA SATUAN (D + E) 184.853,13

A.4.4.1.9. Pemasangan 1 M2 Dinding Batako Cetak (11x15x30) cm tebal 1/2 batako Campuran 1 SP : 4 PP

HARGA SATUAN SUB TOTAL


NO U R A I A N KODE SATUAN KOEFISIEN
(Rp) (Rp)
A. TENAGA KERJA
1 Pekerja L.01 OH 0,300 150.000,00 45.000,00
2 Tukang Batu L.02 OH 0,100 200.000,00 20.000,00
3 Kepala Tukang L.03 OH 0,010 250.000,00 2.500,00
4 Mandor L.04 OH 0,015 - -

67.500,00

B. BAHAN
1 Batako Cetak bh 23,000 3.629,88 83.487,13
2 SemenPortland Kg 11,500 1.800,00 20.700,00
3 Pasir Pasang M3 0,043 200.000,00 8.600,00

112.787,13
C. PERALATAN

D. Jumlah (A+B+C) 180.287,13


E. Overhead & Profit
F. HARGA SATUAN (D + E) 180.287,13
A.4.4.2.4 Pemasangan 1 M2 Plesteran 1 SP : 4 PP Tebal 15 mm

HARGA SATUAN SUB TOTAL


NO U R A I A N KODE SATUAN KOEFISIEN
(Rp) (Rp)
A. TENAGA KERJA
1 Pekerja L.01 OH 0,300 150.000,00 45.000,00
2 Tukang Batu L.03 OH 0,100 200.000,00 20.000,00
3 Kepala Tukang L.03 OH 0,015 250.000,00 3.750,00
4 Mandor L.04 OH 0,015 - -

68.750,00

B. BAHAN
1 Semen Portland Kg 6,240 1.800,00 11.232,00
2 Pasir Pasang M3 0,024 200.000,00 4.800,00

16.032,00
C. PERALATAN

D. Jumlah (A+B+C) 84.782,00


E. Overhead & Profit
F. HARGA SATUAN (D + E) 84.782,00

A.4.4.2.14 Pemasangan 1 M2 Plesteran 1 SP : 3 PP Tebal 20 mm

HARGA SATUAN SUB TOTAL


NO U R A I A N KODE SATUAN KOEFISIEN
(Rp) (Rp)
A. TENAGA KERJA
1 Pekerja L.01 OH 0,260 150.000,00 39.000,00
2 Tukang Batu L.03 OH 0,200 200.000,00 40.000,00
3 Kepala Tukang L.03 OH 0,020 250.000,00 5.000,00
4 Mandor L.04 OH 0,013 - -

84.000,00
B. BAHAN
1 Semen Portland Kg 10,368 1.800,00 18.662,40
2 Pasir Pasang M3 0,031 200.000,00 6.200,00

24.862,40
C. PERALATAN

D. Jumlah (A+B+C) 108.862,40


E. Overhead & Profit -
F. HARGA SATUAN (D + E) 108.862,40

A.4.4.2. 27 Pemasangan 1 M2 Acian

HARGA SATUAN SUB TOTAL


NO U R A I A N KODE SATUAN KOEFISIEN
(Rp) (Rp)
A. TENAGA KERJA
1 Pekerja L.01 OH 0,200 150.000,00 30.000,00
2 Tukang Batu L.02 OH 0,100 200.000,00 20.000,00
3 Kepala Tukang L.03 OH 0,010 250.000,00 2.500,00
4 Mandor L.04 OH 0,010 - -

52.500,00

B. BAHAN
1 Semen PC Kg 3,250 1.800,00 5.850,00

5.850,00
C. PERALATAN

D. Jumlah (A+B+C) 58.350,00


E. Overhead & Profit
F. HARGA SATUAN (D + E) 58.350,00
A.4.4.3.34 Pemasangan 1 m2 Lantai Keramik Ukuran 60 cm x 60 cm Interior

HARGA SATUAN SUB TOTAL


NO U R A I A N KODE SATUAN KOEFISIEN
(Rp) (Rp)
A. TENAGA KERJA
1 Pekerja L.01 OH 0,700 150.000,00 105.000,00
2 Tukang Batu L.02 OH 0,350 200.000,00 70.000,00
3 Kepala Tukang L.03 OH 0,035 250.000,00 8.750,00
4 Mandor L.04 OH 0,035 - -

183.750,00

B. BAHAN
1 Keramik 60 X 60 Kualitas I Bh 3,333 48.000,00 160.000,00
2 Semen Portland Kg 8,190 1.800,00 14.742,00
3 Pasir Pasang M3 0,045 200.000,00 9.000,00
4 Semen Warna Kg 1,620 22.000,00 35.640,00

219.382,00
C. PERALATAN

D. Jumlah (A+B+C) 403.132,00


E. Overhead & Profit
F. HARGA SATUAN (D + E) 403.132,00

A.4.4.3.35 B Pemasangan 1 m2 Lantai Keramik Ukuran 40 cm x 40 cm Eksterior

HARGA SATUAN SUB TOTAL


NO U R A I A N KODE SATUAN KOEFISIEN
(Rp) (Rp)
A. TENAGA KERJA
1 Pekerja L.01 OH 0,700 150.000,00 105.000,00
2 Tukang Batu L.02 OH 0,350 200.000,00 70.000,00
3 Kepala Tukang L.03 OH 0,035 250.000,00 8.750,00
4 Mandor L.04 OH 0,035 - -

183.750,00

B. BAHAN
1 Keramik 40 X 40 Kualitas I Bh 7,500 11.333,33 85.000,00
2 Semen Portland Kg 14,150 1.800,00 25.470,00
3 Pasir Pasang M3 0,039 200.000,00 7.800,00
4 Semen Warna Kg 2,000 22.000,00 44.000,00

162.270,00
C. PERALATAN

D. Jumlah (A+B+C) 346.020,00


E. Overhead & Profit -
F. HARGA SATUAN (D + E) 346.020,00

A.4.4.3.36 Pemasangan 1 m2 Lantai Keramik Ukuran 20 cm x 20 cm (Anti Slip)

HARGA SATUAN SUB TOTAL


NO U R A I A N KODE SATUAN KOEFISIEN
(Rp) (Rp)
A. TENAGA KERJA
1 Pekerja L.01 OH 0,700 150.000,00 105.000,00
2 Tukang Batu L.02 OH 0,350 200.000,00 70.000,00
3 Kepala Tukang L.03 OH 0,035 250.000,00 8.750,00
4 Mandor L.04 OH 0,035 - -

183.750,00

B. BAHAN
1 Keramik 20 X 20 Kwalitas I Doos 1,050 101.750,00 106.837,50
2 Semen Portland Kg 10,400 1.800,00 18.720,00
3 Pasir Pasang M3 0,045 200.000,00 9.000,00
4 Semen Warna Kg 0,500 22.000,00 11.000,00

145.557,50
C. PERALATAN

D. Jumlah (A+B+C) 329.307,50


E. Overhead & Profit
F. HARGA SATUAN (D + E) 329.307,50
A.4.4.3.50 Pemasangan 1 M2 Lantai Keramik Dinding Motif Batu Alam Uk. 20 x40 cm

HARGA SATUAN SUB TOTAL


NO U R A I A N KODE SATUAN KOEFISIEN
(Rp) (Rp)
A. TENAGA KERJA
1 Pekerja L.01 OH 0,700 150.000,00 105.000,00
2 Tukang Batu L.02 OH 0,350 200.000,00 70.000,00
3 Kepala Tukang L.03 OH 0,045 250.000,00 11.250,00
4 Mandor L.04 OH 0,045 - -

186.250,00

B. BAHAN
1 Keramik Dinding Motif Batu Alam Uk. 20 x 40 cm m2 0,010 102.000,00 1.020,00
2 Semen Portland Kg 10,000 1.800,00 18.000,00
3 Pasir Pasang M3 0,018 200.000,00 3.600,00
4 Semen Warna Kg 1,940 22.000,00 42.680,00

65.300,00
C. PERALATAN

D. Jumlah (A+B+C) 251.550,00


E. Overhead & Profit (Contoh 15 %)
F. HARGA SATUAN (D + E) 251.550,00

A.4.5.1.5. Pemasangan 1 M2 Langit - Langit Tripleks Ukuran (120 x 240) cm tebal 3 mm , 4 mm & 6 mm

HARGA SATUAN SUB TOTAL


NO U R A I A N KODE SATUAN KOEFISIEN
(Rp) (Rp)
A. TENAGA KERJA
1 Pekerja L.01 OH 0,100 150.000,00 15.000,00
2 Tukang Kayu L.02 OH 0,100 200.000,00 20.000,00
3 Kepala Tukang L.03 OH 0,010 250.000,00 2.500,00
4 Mandor L.04 OH 0,005 - -

37.500,00

B. BAHAN
1 Tripleks Lbr 0,375 88.000,00 33.000,00
2 Paku Tripleks Kg 0,030 47.450,62 1.423,52

34.423,52
C. PERALATAN

D. Jumlah (A+B+C) 71.923,52


E. Overhead & Profit -
F. HARGA SATUAN (D + E) 71.923,52

A.4.5.1.9. Pemasangan 1 M List Langit - Langit Kayu Profil

HARGA SATUAN SUB TOTAL


NO U R A I A N KODE SATUAN KOEFISIEN
(Rp) (Rp)
A. TENAGA KERJA
1 Pekerja L.01 OH 0,050 150.000,00 7.500,00
2 Tukang Kayu L.02 OH 0,050 200.000,00 10.000,00
3 Kepala Tukang L.03 OH 0,005 250.000,00 1.250,00
4 Mandor L.04 OH 0,003 - -

18.750,00

B. BAHAN
1 List Profil M 1,050 7.000,00 7.350,00
2 Paku Kg 0,010 47.446,56 474,47

7.824,47
C. PERALATAN

D. Jumlah (A+B+C) 26.574,47


E. Overhead & Profit -
F. HARGA SATUAN (D + E) 26.574,47
A.4.5.2.41 Pemasangan 1 m2 Atap Almunium

HARGA SATUAN SUB TOTAL


NO U R A I A N KODE SATUAN KOEFISIEN
(Rp) (Rp)
A. TENAGA KERJA
1 Pekerja L.01 OH 0,150 150.000,00 22.500,00
2 Tukang Kayu L.03 OH 0,750 200.000,00 150.000,00
3 Kepala Tukang L.11 OH 0,080 250.000,00 20.000,00
4 Mandor L.15 OH 0,006 - -

192.500,00

B. BAHAN
1 Seng Almunium m2 0,702 75.000,00 52.631,58
2 Paku Seng Kg 0,040 44.781,67 1.791,27

54.422,85
C. PERALATAN

D. Jumlah (A+B+C) 246.922,85


E. Overhead & Profit
F. HARGA SATUAN (D + E) 246.922,85

A.4.5.2.42 Pemasangan 1 m Nok Almunium

HARGA SATUAN SUB TOTAL


NO U R A I A N KODE SATUAN KOEFISIEN
(Rp) (Rp)
A. TENAGA KERJA
1 Pekerja L.01 OH 0,100 150.000,00 15.000,00
2 Tukang Kayu L.03 OH 1,000 200.000,00 200.000,00
3 Kepala Tukang L.11 OH 0,100 250.000,00 25.000,00
4 Mandor L.15 OH 0,050 - -

240.000,00

B. BAHAN
1 Nok Almunium Bh 0,300 75.480,27 22.644,08
2 Paku Seng Kg 0,040 44.781,67 1.791,27

24.435,35
C. PERALATAN

D. Jumlah (A+B+C) 264.435,35


E. Overhead & Profit
F. HARGA SATUAN (D + E) 264.435,35

A.4.6.1.2 Pembuatan dan pemasangan 1 m3 kusen pintu dan kusen jendela, Kayu Kelas II atau III

HARGA SATUAN SUB TOTAL


NO U R A I A N KODE SATUAN KOEFISIEN
(Rp) (Rp)
A. TENAGA KERJA
1 Pekerja L.01 OH 6,000 150.000,00 900.000,00
2 Tukang Kayu L.03 OH 18,000 200.000,00 3.600.000,00
3 Kepala Tukang L.03 OH 1,800 250.000,00 450.000,00
4 Mandor L.04 OH 0,300 - -

4.950.000,00

B. BAHAN
1 Balok Kayu M3 1,200 2.800.000,00 3.360.000,00
2 Paku 10 Cm Kg 1,250 47.446,56 59.308,19
3 Lem Kayu Kg 1,000 31.697,50 31.697,50

3.451.005,69
C. PERALATAN

D. Jumlah (A+B+C) 8.401.005,69


E. Overhead & Profit
F. HARGA SATUAN (D + E) 8.401.005,69
A.4.6.1.5 Pembuatan dan pemasangan 1 m2 Daun Pintu Panel Kayu Kls I atau Kls II

HARGA SATUAN SUB TOTAL


NO U R A I A N KODE SATUAN KOEFISIEN
(Rp) (Rp)
A. TENAGA KERJA
1 Pekerja L.01 OH 1,000 150.000,00 150.000,00
2 Tukang Kayu L.03 OH 3,000 200.000,00 600.000,00
3 Kepala Tukang L.03 OH 0,300 250.000,00 75.000,00
4 Mandor L.04 OH 0,050 - -

825.000,00

B. BAHAN
1 Papan Kayu M3 0,040 2.800.000,00 112.000,00
2 Lem Kayu Kg 0,500 31.697,50 15.848,75

127.848,75
C. PERALATAN

D. Jumlah (A+B+C) 952.848,75


E. Overhead & Profit (Contoh 15 %)
F. HARGA SATUAN (D + E) 952.848,75

A.4.6.1.6 Pembuatan dan pemasangan 1 m2 Pintu dan Jendela Kaca Kayu Kls I atau Kls II

HARGA SATUAN SUB TOTAL


NO U R A I A N KODE SATUAN KOEFISIEN
(Rp) (Rp)
A. TENAGA KERJA
1 Pekerja L.01 OH 0,800 150.000,00 120.000,00
2 Tukang Kayu L.03 OH 2,400 200.000,00 480.000,00
3 Kepala Tukang L.03 OH 0,240 250.000,00 60.000,00
4 Mandor L.04 OH 0,040 - -

660.000,00

B. BAHAN
1 Papan Kayu M3 0,024 2.800.000,00 67.200,00
2 Lem Kayu Kg 0,300 31.697,50 9.509,25
3 pasangan kaca 5 mm M2 1,000 118.733,05 118.733,05
195.442,30
C. PERALATAN

D. Jumlah (A+B+C) 855.442,30


E. Overhead & Profit
F. HARGA SATUAN (D + E) 855.442,30

A.4.6.1.13 Pemasangan 1M3 Konstruksi Kuda - kuda konvensional, Kayu Kelas II

HARGA SATUAN SUB TOTAL


NO U R A I A N KODE SATUAN KOEFISIEN
(Rp) (Rp)
A. TENAGA KERJA
1 Pekerja L.01 OH 4,000 150.000,00 600.000,00
2 Tukang Kayu L.03 OH 12,000 200.000,00 2.400.000,00
3 Kepala Tukang L.03 OH 1,200 250.000,00 300.000,00
4 Mandor L.04 OH 0,200 - -

3.300.000,00

B. BAHAN
1
Balok Kayu M3 1,100 2.800.000,00 3.080.000,000
2 Besi Strip tebal 5 mm Kg 15,000 48.000,00 720.000,00
3 Paku 12 cm Kg 5,600 47.446,56 265.700,71

4.065.700,71
C. PERALATAN

D. Jumlah (A+B+C) 7.365.700,71


E. Overhead & Profit -
F. HARGA SATUAN (D + E) 7.365.700,71
A.4.6.1.15 Pemasangan 1M3 Konstruksi Gording Kelas II

HARGA SATUAN SUB TOTAL


NO U R A I A N KODE SATUAN KOEFISIEN
(Rp) (Rp)
A. TENAGA KERJA
1 Pekerja L.01 OH 6,700 150.000,00 1.005.000,00
2 Tukang Kayu L.03 OH 20,100 200.000,00 4.020.000,00
3 Kepala Tukang L.03 OH 2,010 250.000,00 502.500,00
4 Mandor L.04 OH 0,335 - -

5.527.500,00

B. BAHAN
1 Balok Kayu M3 1,100 2.800.000,00 3.080.000,00
2 Besi Strip Kg 15,000 48.000,00 720.000,00
3 Paku 12 cm Kg 3,000 47.446,56 142.339,67

3.942.339,67
C. PERALATAN

D. Jumlah (A+B+C) 9.469.839,67


E. Overhead & Profit -
F. HARGA SATUAN (D + E) 9.469.839,67

A.4.6.1.20 Pemasangan 1M2 Rangka Langit -Langit 60 x 60 cm Kayu Kelas II atau III

HARGA SATUAN SUB TOTAL


NO U R A I A N KODE SATUAN KOEFISIEN
(Rp) (Rp)
A. TENAGA KERJA
1 Pekerja L.01 OH 0,200 150.000,00 30.000,00
2 Tukang Kayu L.03 OH 0,300 200.000,00 60.000,00
3 Kepala Tukang L.03 OH 0,030 250.000,00 7.500,00
4 Mandor L.04 OH 0,010 - -

97.500,00

B. BAHAN
1 Kaso 5/7 M3 0,016 2.800.000,00 45.640,00
2 Paku 7 - 10 Cm Kg 0,250 47.446,56 11.861,64

57.501,64
C. PERALATAN

D. Jumlah (A+B+C) 155.001,64


E. Overhead & Profit -
F. HARGA SATUAN (D + E) 155.001,64

A.4.6.1.21 Pemasangan 1 M Lisplank GRC 0,9 mm X 2440 mm

HARGA SATUAN SUB TOTAL


NO U R A I A N KODE SATUAN KOEFISIEN
(Rp) (Rp)
A. TENAGA KERJA
1 Pekerja L.01 OH 0,100 150.000,00 15.000,00
2 Tukang Kayu L.03 OH 0,200 200.000,00 40.000,00
3 Kepala Tukang L.03 OH 0,020 250.000,00 5.000,00
4 Mandor L.04 OH 0,005 - -

60.000,00

B. BAHAN
1 Grc 0,9 x 20 Cm M 0,491 160.000,00 78.571,43
2 Paku Skrup Kg 0,100 75.000,00 7.500,00

86.071,43
C. PERALATAN

D. Jumlah (A+B+C) 146.071,43


E. Overhead & Profit
F. HARGA SATUAN (D + E) 146.071,43
A.4.6.2.2 Pemasangan 1 buah kunci tanam Biasa

HARGA SATUAN SUB TOTAL


NO U R A I A N KODE SATUAN KOEFISIEN
(Rp) (Rp)
A. TENAGA KERJA
1 Pekerja L.01 OH 0,010 150.000,00 1.500,00
2 Tukang Kayu L.03 OH 0,500 200.000,00 100.000,00
3 Kepala Tukang L.03 OH 0,050 250.000,00 12.500,00
4 Mandor L.04 OH 0,005 - -

114.000,00

B. BAHAN
1 Kunci Tanam 3 Lever Kualitas Terbaik Buah 1,000 205.000,00 205.000,00

205.000,00
C. PERALATAN

D. Jumlah (A+B+C) 319.000,00


E. Overhead & Profit
F. HARGA SATUAN (D + E) 319.000,00

A.4.6.2.3 Pemasangan 1 buah kunci Kamar Mandi

HARGA SATUAN SUB TOTAL


NO U R A I A N KODE SATUAN KOEFISIEN
(Rp) (Rp)
A. TENAGA KERJA
1 Pekerja L.01 OH 0,005 150.000,00 750,00
2 Tukang Kayu L.03 OH 0,500 200.000,00 100.000,00
3 Kepala Tukang L.03 OH 0,050 250.000,00 12.500,00
4 Mandor L.04 OH 0,003 - -

113.250,00

B. BAHAN
1 Kunci Tanam Buah 1,000 128.000,00 128.000,00

128.000,00
C. PERALATAN

D. Jumlah (A+B+C) 241.250,00


E. Overhead & Profit
F. HARGA SATUAN (D + E) 241.250,00

A.4.6.2.5 Pemasangan 1 Pasang Engsel Pintu

HARGA SATUAN SUB TOTAL


NO U R A I A N KODE SATUAN KOEFISIEN
(Rp) (Rp)
A. TENAGA KERJA
1 Pekerja L.01 OH 0,015 150.000,00 2.250,00
2 Tukang Kayu L.03 OH 0,150 200.000,00 30.000,00
3 Kepala Tukang L.03 OH 0,015 250.000,00 3.750,00
4 Mandor L.04 OH 0,001 - -

36.000,00

B. BAHAN
1 Engsel Pintu Alumunium Psng 1,000 63.250,00 63.250,00

63.250,00
C. PERALATAN

D. Jumlah (A+B+C) 99.250,00


E. Overhead & Profit
F. HARGA SATUAN (D + E) 99.250,00
A.4.6.2.5 Pemasangan 1 Pasang Engsel Jendela

HARGA SATUAN SUB TOTAL


NO U R A I A N KODE SATUAN KOEFISIEN
(Rp) (Rp)
A. TENAGA KERJA
1 Pekerja L.01 OH 0,015 150.000,00 2.250,00
2 Tukang Kayu L.03 OH 0,150 200.000,00 30.000,00
3 Kepala Tukang L.03 OH 0,015 250.000,00 3.750,00
4 Mandor L.04 OH 0,001 - -

36.000,00

B. BAHAN
1 Engsel Pintu H 5" Psng 1,000 34.845,00 34.845,00

34.845,00
C. PERALATAN

D. Jumlah (A+B+C) 70.845,00


E. Overhead & Profit
F. HARGA SATUAN (D + E) 70.845,00

A.4.6.2.8.a Pemasangan 1 buah Grendel Pintu

HARGA SATUAN SUB TOTAL


NO U R A I A N KODE SATUAN KOEFISIEN
(Rp) (Rp)
A. TENAGA KERJA
1 Pekerja L.01 OH 0,015 150.000,00 2.250,00
2 Tukang Kayu L.03 OH 0,150 200.000,00 30.000,00
3 Kepala Tukang L.03 OH 0,015 250.000,00 3.750,00
4 Mandor L.04 OH 0,008 - -

36.000,00

B. BAHAN
1 Grendel Pintu (Standard) Buah 1,000 22.500,00 22.500,00

22.500,00
C. PERALATAN

D. Jumlah (A+B+C) 58.500,00


E. Overhead & Profit
F. HARGA SATUAN (D + E) 58.500,00

A.4.6.2.8.b. Pemasangan 1 buah Grendel Jendela

HARGA SATUAN SUB TOTAL


NO U R A I A N KODE SATUAN KOEFISIEN
(Rp) (Rp)
A. TENAGA KERJA
1 Pekerja L.01 OH 0,015 150.000,00 2.250,00
2 Tukang Kayu L.03 OH 0,150 200.000,00 30.000,00
3 Kepala Tukang L.03 OH 0,015 250.000,00 3.750,00
4 Mandor L.04 OH 0,008 - -

36.000,00

B. BAHAN
1 Grendel Jendela (Standard) Buah 1,000 15.000,00 15.000,00

15.000,00
C. PERALATAN

D. Jumlah (A+B+C) 51.000,00


E. Overhead & Profit
F. HARGA SATUAN (D + E) 51.000,00
A.4.6.2.9 Pemasangan 1 buah Kait Angin

HARGA SATUAN SUB TOTAL


NO U R A I A N KODE SATUAN KOEFISIEN
(Rp) (Rp)
A. TENAGA KERJA
1 Pekerja L.01 OH 0,015 150.000,00 2.250,00
2 Tukang Kayu L.03 OH 0,150 200.000,00 30.000,00
3 Kepala Tukang L.03 OH 0,015 250.000,00 3.750,00
4 Mandor L.04 OH 0,008 - -

36.000,00

B. BAHAN
1 Kait Angin (Standard) Buah 1,000 15.000,00 15.000,00

15.000,00
C. PERALATAN

D. Jumlah (A+B+C) 51.000,00


E. Overhead & Profit
F. HARGA SATUAN (D + E) 51.000,00

A.4.6.2.9 Pemasangan 1 buah Tarikan Jendela

HARGA SATUAN SUB TOTAL


NO U R A I A N KODE SATUAN KOEFISIEN
(Rp) (Rp)
A. TENAGA KERJA
1 Pekerja L.01 OH 0,015 150.000,00 2.250,00
2 Tukang Kayu L.03 OH 0,150 200.000,00 30.000,00
3 Kepala Tukang L.03 OH 0,015 250.000,00 3.750,00
4 Mandor L.04 OH 0,008 - -

36.000,00

B. BAHAN
1 Tarikan Jendela (Standard) Buah 1,000 10.000,00 10.000,00

10.000,00
C. PERALATAN

D. Jumlah (A+B+C) 46.000,00


E. Overhead & Profit
F. HARGA SATUAN (D + E) 46.000,00

A.4.7.1.3. 1 M2 Pengecetan Tembok/ Plafond 2x

HARGA SATUAN SUB TOTAL


NO U R A I A N KODE SATUAN KOEFISIEN
(Rp) (Rp)
A. TENAGA KERJA
1 Pekerja L.01 OH 0,1200 150.000,00 18.000,00
2 Tukang Cat L.02 OH 0,0200 200.000,00 4.000,00
3 Kepala Tukang L.03 OH 0,0020 250.000,00 500,00
4 Mandor L.04 OH 0,0015 - -

22.500,00

B. BAHAN
1 Cat Tembok Kg 0,1200 35.000,00 4.200,00

4.200,00
C. PERALATAN

D. Jumlah (A+B+C) 26.700,00


E. Overhead & Profit -
F. HARGA SATUAN (D + E) 26.700,00
A.4.7.1.7. Pelaburan 1m2 bidang kayu dengan politur

HARGA SATUAN SUB TOTAL


NO U R A I A N KODE SATUAN KOEFISIEN
(Rp) (Rp)
A. TENAGA KERJA
1 Pekerja L.01 OH 0,040 150.000,00 6.000,00
2 Tukang Cat L.02 OH 0,060 200.000,00 12.000,00
3 Kepala Tukang L.03 OH 0,016 250.000,00 4.000,00
4 Mandor L.04 OH 0,003 - -

22.000,00

B. BAHAN
1 Politur L 0,150 44.550,00 6.682,50
2 Politur Jadi L 0,372 44.550,00 16.572,60
3 Ampelas Lbr 2,000 3.850,00 7.700,00

30.955,10
C. PERALATAN

D. Jumlah (A+B+C) 52.955,10


E. Overhead & Profit
F. HARGA SATUAN (D + E) 52.955,10

A.5.1.1.2. Pemasangan 1 buah Closet Jongkok Porselen

HARGA SATUAN SUB TOTAL


NO U R A I A N KODE SATUAN KOEFISIEN
(Rp) (Rp)
A. TENAGA KERJA
1 Pekerja L.01 OH 1,000 150.000,00 150.000,00
2 Tukang Batu L.02 OH 1,500 200.000,00 300.000,00
3 Kepala Tukang L.03 OH 0,150 250.000,00 37.500,00
4 Mandor L.04 OH 0,160 - -

487.500,00

B. BAHAN

1 Closet Jongkok Unit 1,000 175.000,00 175.000,00


2 Semen Portland Kg 6,000 1.800,00 10.800,00
3 Pasir Pasang M3 0,010 200.000,00 2.000,00

187.800,00
C. PERALATAN

D. Jumlah (A+B+C) 675.300,00


E. Overhead & Profit -
F. HARGA SATUAN (D + E) 675.300,00

A.5.1.1.7. Pemasangan 1 buah bak Mandi Lapis Keramik Ukuran 40 x 40 x 50

HARGA SATUAN SUB TOTAL


NO U R A I A N KODE SATUAN KOEFISIEN
(Rp) (Rp)
A. TENAGA KERJA

B. BAHAN

1 Pas Batu Batako Sp 1 : 3 M2 0,120 184.853,13 22.182,38


2 Plesteran Sp 1 : 3 M2 1,800 97.346,80 175.224,24
3 Keramik 20 x 20 M2 1,800 386.770,00 696.186,00
5 Pipa Buang Air M1 1,000 11.700,00 11.700,00

905.292,62
C. PERALATAN

D. Jumlah (A+B+C) 905.292,62


E. Overhead & Profit -
F. HARGA SATUAN (D + E) 905.292,62
A.5.1.1.14. Pemasangan 1 buah floor drain Setara Toto

HARGA SATUAN SUB TOTAL


NO U R A I A N KODE SATUAN KOEFISIEN
(Rp) (Rp)
A. TENAGA KERJA
1 Pekerja L.01 OH 0,010 150.000,00 1.500,00
2 Tukang Batu L.02 OH 0,100 200.000,00 20.000,00
3 Kepala Tukang L.03 OH 0,010 250.000,00 2.500,00
4 Mandor L.04 OH 0,005 - -

24.000,00

B. BAHAN

1 floor drain Setara Toto Unit 1,000 86.250,00 86.250,00

86.250,00
C. PERALATAN

D. Jumlah (A+B+C) 110.250,00


E. Overhead & Profit
F. HARGA SATUAN (D + E) 110.250,00

A.5.1.1.19. Pemasangan 1 Buah Kran Air Wastafel Kwalitas Terbaik

HARGA SATUAN SUB TOTAL


NO U R A I A N KODE SATUAN KOEFISIEN
(Rp) (Rp)
A. TENAGA KERJA
1 Pekerja L.01 OH 0,010 150.000,00 1.500,00
2 Tukang Pipa L.02 OH 0,400 200.000,00 80.000,00
3 Kepala Tukang L.03 OH 0,040 250.000,00 10.000,00
4 Mandor L.04 OH 0,005 - -

91.500,00

B. BAHAN
1 Kran Air Wastafel Kwalitas Terbaik Buah 1,000 103.500,00 103.500,00
2 Sealtape Buah 0,025 - -

103.500,00
C. PERALATAN

D. Jumlah (A+B+C) 195.000,00


E. Overhead & Profit (Contoh 15 %)
F. HARGA SATUAN (D + E) 195.000,00

A.5.1.1.25. Pemasangan 1 M Pipa PVC tipe AW diamter 1/2 "

HARGA SATUAN SUB TOTAL


NO U R A I A N KODE SATUAN KOEFISIEN
(Rp) (Rp)
A. TENAGA KERJA
1 Pekerja L.01 OH 0,036 150.000,00 5.400,00
2 Tukang Pipa L.02 OH 0,060 200.000,00 12.000,00
3 Kepala Tukang L.03 OH 0,006 250.000,00 1.500,00
4 Mandor L.04 OH 0,002 - -

18.900,00

B. BAHAN
1 Pipa PVC M 1,200 3.666,67 4.400,00
2 Perlengkapan Ls 0,350 3.666,67 1.283,33

5.683,33
C. PERALATAN

D. Jumlah (A+B+C) 24.583,33


E. Overhead & Profit -
F. HARGA SATUAN (D + E) 24.583,33
A.5.1.1.32. Pemasangan 1 M Pipa PVC tipe AW diamter 3"

HARGA SATUAN SUB TOTAL


NO U R A I A N KODE SATUAN KOEFISIEN
(Rp) (Rp)
A. TENAGA KERJA
1 Pekerja L.01 OH 0,081 150.000,00 12.150,00
2 Tukang Pipa L.02 OH 0,135 200.000,00 27.000,00
3 Kepala Tukang L.03 OH 0,135 250.000,00 33.750,00
4 Mandor L.04 OH 0,004 - -

72.900,00

B. BAHAN
1 Pipa PVC 3" M 1,200 30.000,00 36.000,00
2 Perlengkapan Ls 0,350 30.000,00 10.500,00

46.500,00
C. PERALATAN

D. Jumlah (A+B+C) 119.400,00


E. Overhead & Profit (Contoh 15 %)
F. HARGA SATUAN (D + E) 119.400,00

A.5.1.1.32. Pemasangan 1 M Pipa PVC tipe AW diamter 4"

HARGA SATUAN SUB TOTAL


NO U R A I A N KODE SATUAN KOEFISIEN
(Rp) (Rp)
A. TENAGA KERJA
1 Pekerja L.01 OH 0,081 150.000,00 12.150,00
2 Tukang Pipa L.02 OH 0,135 200.000,00 27.000,00
3 Kepala Tukang L.03 OH 0,135 250.000,00 33.750,00
4 Mandor L.04 OH 0,004 - -

72.900,00

B. BAHAN
1 Pipa PVC 4" M 1,200 41.666,67 50.000,00
2 Perlengkapan Ls 0,350 41.666,67 14.583,33

64.583,33
C. PERALATAN

D. Jumlah (A+B+C) 137.483,33


E. Overhead & Profit (Contoh 15 %)
F. HARGA SATUAN (D + E) 137.483,33

Pembuatan Septictank dan Rembesan dilengkapi Bak Kontrol 1 Unit

HARGA SATUAN SUB TOTAL


NO U R A I A N KODE SATUAN KOEFISIEN
(Rp) (Rp)

1 Pek Galian Tanah M3 12,650 90.000,00 1.138.500,00


2 Pek Urugan Kembali M3 4,217 50.000,00 210.833,33
3 Pek. Cor beton tumbuk 1 : 3 : 5 M3 0,413 1.365.650,00 564.013,45
4 Pek. Urugan Pasir M3 0,479 270.000,00 129.330,00
5 Pas. Batu Bata Sp. 1 : 3 M2 8,502 184.853,13 1.571.621,27
6 Beton Bertulang (Besi 110 Kg) M3 0,477 6.536.524,29 3.117.922,09
7 Plesteran Sp. 1 : 3 M2 23,090 108.862,40 2.513.632,82
8 Pas. Batu Kosong M3 0,764 717.531,00 548.193,68
9 Timbunan Batu Karang M3 0,650 160.000,00 104.000,00
10 Pek. Urugan Kerikil M3 0,325 320.000,00 104.000,00
11 Pipa PVC dia. 4" Ujng 2,000 337.881,50 675.763,00
12 Pipa Hawa dia. 1.5" (GIP) Ujng 0,330 362.687,00 119.686,71
13 Ijuk M3 0,714 134.550,00 96.068,70

D. Jumlah (A+B+C) 10.893.565,05


E. Overhead & Profit
F. HARGA SATUAN (D + E) 10.893.565,05
A.5.2.1.3. Pemasangan Sekring Box 3 Group Titik

HARGA SATUAN SUB TOTAL


NO U R A I A N KODE SATUAN KOEFISIEN
(Rp) (Rp)
A. TENAGA KERJA
1 Tukang Listrik L.02 OH 0,100 1.191.750,00 119.175,00

119.175,00

B. BAHAN
1 Sekring Box NCB 3 Group Unit 1,000 75.000,00 75.000,00
2 Kabel Rafo 3 x 2.5 NYM M' 0,050 10.000,00 500,00
3 Mangkok Bh 1,000 10.000,00 10.000,00
4 Perekat Sp. 1 : 3 M2 0,003 97.346,80 292,04

85.792,04
C. PERALATAN

D. Jumlah (A+B+C) 204.967,04


E. Overhead & Profit
F. HARGA SATUAN (D + E) 204.967,04

A.5.2.1.5. Pemasangan Stop Kontak INBOW Terbaik

HARGA SATUAN SUB TOTAL


NO U R A I A N KODE SATUAN KOEFISIEN
(Rp) (Rp)
A. TENAGA KERJA
1 Tukang Listrik L.01 OH 0,061 1.191.750,00 72.696,75
2 Mandor L.04 OH 0,003 - -

72.696,75

B. BAHAN
1 Stop Kontak Inbow ( Terbaik ) Bh 1,000 45.000,00 45.000,00
2 Kabel 2x2,5mm NYM M' 0,050 7.500,00 375,00
3 Mangkok Bh 1,000 10.000,00 10.000,00
4 Spesi Perekat Sp, 1 : 3 M2 0,003 97.346,80 292,04

55.667,04
C. PERALATAN

D. Jumlah (A+B+C) 128.363,79


E. Overhead & Profit
F. HARGA SATUAN (D + E) 128.363,79

A.5.2.1.6. Pemasangan Saklar Ganda INBOW Terbaik

HARGA SATUAN SUB TOTAL


NO U R A I A N KODE SATUAN KOEFISIEN
(Rp) (Rp)
A. TENAGA KERJA
1 Tukang Listrik L.01 OH 0,061 1.191.750,00 72.696,75
2 Mandor L.04 OH 0,003 - -

72.696,75

B. BAHAN
1 Saklar Ganda Inbow (Terbaik) Bh 1,000 45.000,00 45.000,00
2 Kabel 2x2,5mm NYM M' 0,050 7.500,00 375,00
3 Mangkok Bh 1,000 10.000,00 10.000,00
4 Spesi Perekat Sp, 1 : 3 M2 0,003 97.346,80 292,04
55.667,04
C. PERALATAN

D. Jumlah (A+B+C) 128.363,79


E. Overhead & Profit
F. HARGA SATUAN (D + E) 128.363,79
A.5.2.1.7. Pemasangan Saklar Tunggal INBOW Terbaik

HARGA SATUAN SUB TOTAL


NO U R A I A N KODE SATUAN KOEFISIEN
(Rp) (Rp)
A. TENAGA KERJA
1 Tukang Listrik L.01 OH 0,061 1.191.750,00 72.696,75
2 Mandor L.04 OH 0,003 - -

72.696,75

B. BAHAN
1 Saklar Tunggal Inbow (Terbaik) Bh 1,000 30.000,00 30.000,00
2 Kabel Rafo 3 x 2.5 NYM M' 0,050 10.000,00 500,00
3 Mangkok Bh 1,000 10.000,00 10.000,00
4 Spesi Perekat Sp, 1 : 3 M2 0,003 97.346,80 292,04

40.792,04
C. PERALATAN

D. Jumlah (A+B+C) 113.488,79


E. Overhead & Profit
F. HARGA SATUAN (D + E) 113.488,79

A.5.2.1.7. Pemasangan Lampu CL 8 Watt Feteng Tempel. Titik

HARGA SATUAN SUB TOTAL


NO U R A I A N KODE SATUAN KOEFISIEN
(Rp) (Rp)
A. TENAGA KERJA
1 Tukang Listrik L.01 OH 0,035 1.191.750,00 41.711,25
2 Mandor L.04 OH 0,002 - -

41.711,25

B. BAHAN
1 Lampu CL 8 Watt Bh 1,000 32.000,00 32.000,00
2 Kabel Ravo 3 x 2,5 M' 0,250 10.000,00 2.500,00
3 Isolasi Bh 0,050 25.000,00 1.250,00

35.750,00
C. PERALATAN

D. Jumlah (A+B+C) 77.461,25


E. Overhead & Profit
F. HARGA SATUAN (D + E) 77.461,25

A.5.2.1.7. Pemasangan Lampu CL 11 Watt Feteng Tempel. Titik

HARGA SATUAN SUB TOTAL


NO U R A I A N KODE SATUAN KOEFISIEN
(Rp) (Rp)
A. TENAGA KERJA
1 Tukang Listrik L.01 OH 0,035 1.191.750,00 41.711,25
2 Mandor L.04 OH 0,002 - -

41.711,25

B. BAHAN
1 Lampu CL 11 Watt Bh 1,000 46.000,00 46.000,00
2 Kabel Ravo 3 x 2,5 M' 0,250 10.000,00 2.500,00
3 Isolasi Bh 0,050 25.000,00 1.250,00

49.750,00
C. PERALATAN

D. Jumlah (A+B+C) 91.461,25


E. Overhead & Profit
F. HARGA SATUAN (D + E) 91.461,25
A.5.2.1.8. Pemasangan Lampu CL 18 Watt Feteng Tempel. Titik

HARGA SATUAN SUB TOTAL


NO U R A I A N KODE SATUAN KOEFISIEN
(Rp) (Rp)
A. TENAGA KERJA
1 Tukang Listrik L.01 OH 0,035 1.191.750,00 41.711,25
2 Mandor L.04 OH 0,002 - -

41.711,25

B. BAHAN
1 Lampu CL 18 Watt Bh 1,000 54.800,00 54.800,00
2 Kabel Ravo 3 x 2,5 M' 0,250 10.000,00 2.500,00
3 Isolasi Bh 0,050 25.000,00 1.250,00

58.550,00
C. PERALATAN

D. Jumlah (A+B+C) 100.261,25


E. Overhead & Profit
F. HARGA SATUAN (D + E) 100.261,25

A.5.2.1.9. Pemasangan Lampu Spiral 32 Watt Feteng Tempel. Titik

HARGA SATUAN SUB TOTAL


NO U R A I A N KODE SATUAN KOEFISIEN
(Rp) (Rp)
A. TENAGA KERJA
1 Tukang Listrik L.01 OH 0,035 1.191.750,00 41.711,25
2 Mandor L.04 OH 0,002 - -

41.711,25

B. BAHAN
1 Lampu Spiral 32 Watt Bh 1,000 58.000,00 58.000,00
2 Kabel Ravo 3 x 2,5 M' 0,250 10.000,00 2.500,00
3 Isolasi Bh 0,050 25.000,00 1.250,00

61.750,00
C. PERALATAN

D. Jumlah (A+B+C) 103.461,25


E. Overhead & Profit
F. HARGA SATUAN (D + E) 103.461,25

A.5.2.1.9. Pemasangan Lampu Spiral 42 Watt Feteng Tempel. Titik

HARGA SATUAN SUB TOTAL


NO U R A I A N KODE SATUAN KOEFISIEN
(Rp) (Rp)
A. TENAGA KERJA
1 Tukang Listrik L.01 OH 0,035 1.191.750,00 41.711,25
2 Mandor L.04 OH 0,002 - -

41.711,25

B. BAHAN
1 Lampu Spiral 42 Watt Bh 1,000 70.000,00 70.000,00
2 Kabel Ravo 3 x 2,5 M' 0,250 10.000,00 2.500,00
3 Isolasi Bh 0,050 25.000,00 1.250,00

73.750,00
C. PERALATAN

D. Jumlah (A+B+C) 115.461,25


E. Overhead & Profit
F. HARGA SATUAN (D + E) 115.461,25
Sloof 15x20 (Tulangan utama dia. 12 mm)

HARGA SATUAN SUB TOTAL


NO U R A I A N KODE SATUAN KOEFISIEN
(Rp) (Rp)

1 Beton Camp. 1 : 2 : 3 M3 1,000 1.530.550,00 1.530.550,00


2 Besi Beton Kg 163,816 18.346,33 3.005.416,65
3 Bekisting Untuk Sloof (2x Pakai) M2 2,500 242.233,97 605.584,92

5.141.551,56

D. Jumlah (A+B+C) 5.141.551,56


E. Overhead & Profit
F. HARGA SATUAN (D + E) 5.141.551,56

Sloof 15x25 (Tulangan utama dia. 12 mm)

HARGA SATUAN SUB TOTAL


NO U R A I A N KODE SATUAN KOEFISIEN
(Rp) (Rp)

1 Beton Camp. 1 : 2 : 3 M3 1,000 1.530.550,00 1.530.550,00


2 Besi Beton Kg 226,925 18.346,33 4.163.234,03
3 Bekisting Untuk Sloof (2x Pakai) M2 2,000 242.233,97 484.467,93

6.178.251,96

D. Jumlah (A+B+C) 6.178.251,96


E. Overhead & Profit
F. HARGA SATUAN (D + E) 6.178.251,96

Kolom Praktis 12x12 cm

HARGA SATUAN SUB TOTAL


NO U R A I A N KODE SATUAN KOEFISIEN
(Rp) (Rp)

1 Beton Camp. 1 : 2 : 3 M3 1,000 1.530.550,00 1.530.550,00


2 Besi Beton Kg 243,519 18.346,33 4.467.688,63
3 Bekisting Untuk Kolom (2x Pakai) M2 4,167 389.784,06 1.624.100,25

7.622.338,87

D. Jumlah (A+B+C) 7.622.338,87


E. Overhead & Profit
F. HARGA SATUAN (D + E) 7.622.338,87

Kolom 18x12 cm (Tulangan utama dia. 12 mm)

HARGA SATUAN SUB TOTAL


NO U R A I A N KODE SATUAN KOEFISIEN
(Rp) (Rp)

1 Beton Camp. 1 : 2 : 3 M3 1,000 1.530.550,00 1.530.550,00


2 Besi Beton Kg 299,323 18.346,33 5.491.481,33
3 Bekisting Untuk Kolom (2x Pakai) M2 3,472 389.784,06 1.353.416,87

8.375.448,21

D. Jumlah (A+B+C) 8.375.448,21


E. Overhead & Profit
F. HARGA SATUAN (D + E) 8.375.448,21

Kolom 2 18x12 cm (Tulangan utama dia. 12 mm)

HARGA SATUAN SUB TOTAL


NO U R A I A N KODE SATUAN KOEFISIEN
(Rp) (Rp)

1 Beton Camp. 1 : 2 : 3 M3 1,000 1.530.550,00 1.530.550,00


2 Besi Beton Kg 216,946 18.346,33 3.980.155,48
3 Bekisting Untuk Kolom (2x Pakai) M2 3,472 389.784,06 1.353.416,87

6.864.122,35

D. Jumlah (A+B+C) 6.864.122,35


E. Overhead & Profit
F. HARGA SATUAN (D + E) 6.864.122,35
Balok 12x20 cm

HARGA SATUAN SUB TOTAL


NO U R A I A N KODE SATUAN KOEFISIEN
(Rp) (Rp)

1 Beton Camp. 1 : 2 : 3 M3 1,000 1.530.550,00 1.530.550,00


2 Besi Beton Kg 153,726 18.346,33 2.820.303,40
3 Bekisting Untuk Balok (2x Pakai) M2 2,500 395.784,06 989.460,15

5.340.313,55

D. Jumlah (A+B+C) 5.340.313,55


E. Overhead & Profit
F. HARGA SATUAN (D + E) 5.340.313,55

Balok 15x10 cm

HARGA SATUAN SUB TOTAL


NO U R A I A N KODE SATUAN KOEFISIEN
(Rp) (Rp)

1 Beton Camp. 1 : 2 : 3 M3 1,000 1.530.550,00 1.530.550,00


2 Besi Beton Kg 224,770 18.346,33 4.123.705,40
3 Bekisting Untuk Balok (2x Pakai) M2 3,333 395.784,06 1.319.280,20

6.973.535,60

D. Jumlah (A+B+C) 6.973.535,60


E. Overhead & Profit
F. HARGA SATUAN (D + E) 6.973.535,60

Balok 12x20 cm (Tulangan utama dia. 12 mm, 4 bh)

HARGA SATUAN SUB TOTAL


NO U R A I A N KODE SATUAN KOEFISIEN
(Rp) (Rp)

1 Beton Camp. 1 : 2 : 3 M3 1,000 1.530.550,00 1.530.550,00


2 Besi Beton Kg 236,123 18.346,33 4.331.991,19
3 Bekisting Untuk Balok (2x Pakai) M2 5,417 395.784,06 2.143.830,32

8.006.371,52

D. Jumlah (A+B+C) 8.006.371,52


E. Overhead & Profit
F. HARGA SATUAN (D + E) 8.006.371,52

Plat Beton tebal 12 cm (Pembesian 2 Lapisan) besi 10

HARGA SATUAN SUB TOTAL


NO U R A I A N KODE SATUAN KOEFISIEN
(Rp) (Rp)

1 Beton Camp. 1 : 2 : 3 M3 1,000 1.530.550,00 1.530.550,00


2 Besi Beton Kg 123,300 18.346,33 2.262.102,64
2 Bekisting Untuk Pondasi (2x Pakai) M2 2,083 469.784,06 978.716,79

4.771.369,43

D. Jumlah (A+B+C) 4.771.369,43


E. Overhead & Profit
F. HARGA SATUAN (D + E) 4.771.369,43