Harga Satuan SNI, 1M³ Pekerjaan Galian Tanah Dengan Alat Berat

0.0600 Jam Excavator Rp 655,000 Rp 39,300


0.1271 Jam Dump Truck Rp 555,000 Rp 70,541
0.1050 OH Operator Rp 200,000 Rp 21,000
0.1050 OH Helper Rp 80,000 Rp 8,400
0.1050 OH Sopir Rp 175,000 Rp 18,375
0.1050 OH Pembantu Sopir Rp 80,000 Rp 8,400
0.2100 OH Pekerja Rp 80,000 Rp 16,800
0.0525 OH Mandor Rp 175,000 Rp 9,188
Rp 192,003

1M' Pipa gorong-gorong Beton Bertulang Ø40Cm, type A


2.0000 OH Pekerja Rp 80,000 Rp 160,000
0.6667 OH Tukang Rp 110,000 Rp 73,337
0.3333 OH Mandor Rp 175,000 Rp 58,328
1.0000 M' Gorong² Beton Tulang Ø40cm Rp 301,000 Rp 301,000
0.6650 M³ Beton K-250 Rp 850,000 Rp 565,250
0.0530 M³ Beton K-125 Rp 725,000 Rp 38,425
0.2300 M³ Blinding Stone Rp 470,000 Rp 108,100
0.0000 Kg Penulangan Ulir Rp 18,000 Rp 0
0.7600 M³ Galian Tanah Rp 32,600 Rp 24,776
0.6500 M² Begesting Ringan Rp 65,000 Rp 42,250
0.0349 Jam Stamper Rp 250,000 Rp 8,725
0.3347 Jam Mobile Crane Rp 600,000 Rp 200,820
0.6024 Jam Concrete Vibrator Rp 250,000 Rp 150,600
Rp 1,731,611

1M' Pipa gorong-gorong Beton Bertulang Ø80Cm, type A


2.0000 OH Pekerja Rp 80,000 Rp 160,000
0.6667 OH Tukang Rp 110,000 Rp 73,337
0.3333 OH Mandor Rp 175,000 Rp 58,328
1.0000 M' Gorong² Beton Tulang Ø40cm Rp 301,000 Rp 301,000
1.1260 M³ Beton K-250 Rp 850,000 Rp 957,100
0.0730 M³ Beton K-125 Rp 725,000 Rp 52,925
0.3120 M³ Blinding Stone Rp 470,000 Rp 146,640
0.0000 Kg Penulangan Ulir Rp 18,000 Rp 0
1.6460 M³ Galian Tanah Rp 32,600 Rp 53,660
2.8200 M² Begesting Ringan Rp 65,000 Rp 183,300
0.0448 Jam Stamper Rp 250,000 Rp 11,200
0.3347 Jam Mobile Crane Rp 600,000 Rp 200,820
0.6024 Jam Concrete Vibrator Rp 250,000 Rp 150,600
Rp 2,348,909
1M' Pipa gorong-gorong Beton Bertulang 2 Ø80Cm, type C
3.2941 OH Pekerja Rp 80,000 Rp 263,528
0.8235 OH Tukang Rp 110,000 Rp 90,585
0.4118 OH Mandor Rp 175,000 Rp 72,065
2.0000 M' Gorong² Beton Tulang Ø40cm Rp 301,000 Rp 602,000
2.2380 M³ Beton K-250 Rp 850,000 Rp 1,902,300
0.0760 M³ Beton K-125 Rp 725,000 Rp 55,100
0.3720 M³ Blinding Stone Rp 470,000 Rp 174,840
0.0000 Kg Penulangan Ulir Rp 18,000 Rp 0
1.8880 M³ Galian Tanah Rp 32,600 Rp 61,549
5.6400 M² Begesting Ringan Rp 65,000 Rp 366,600
0.0448 Jam Stamper Rp 250,000 Rp 11,200
0.7530 Jam Mobile Crane Rp 600,000 Rp 451,800
0.6024 Jam Concrete Vibrator Rp 250,000 Rp 150,600
Rp 4,202,167

1M' Saluran U - Beton Type DS-2


1.4000 Pekerja Rp 80,000 Rp 112,000
0.2800 Tukang Rp 110,000 Rp 30,800
0.1400 Mandor Rp 175,000 Rp 24,500
0.5550 Beton K-250 Rp 850,000 Rp 471,750
0.1150 Beton K-125 Rp 725,000 Rp 83,375
30.5250 Penulangan Ulir Rp 18,000 Rp 549,450
5.5000 Begesting Ringan Rp 130,000 Rp 715,000
0.1458 Excavator Rp 655,000 Rp 95,499
0.1791 Dump Truck Rp 555,000 Rp 99,401
0.2008 Concrete Vibrator Rp 250,000 Rp 50,200
2,231,975

1M' Saluran U - Beton Type DS-2A


1.4000 Pekerja Rp 80,000 Rp 112,000
0.2800 Tukang Rp 110,000 Rp 30,800
0.1400 Mandor Rp 175,000 Rp 24,500
0.7500 Beton K-250 Rp 850,000 Rp 637,500
41.2500 Penulangan Ulir Rp 18,000 Rp 742,500
0.0500 Beton Klas E Rp 710,000 Rp 35,500
4.7000 Begesting Ringan Rp 130,000 Rp 611,000
0.1281 Excavator Rp 655,000 Rp 83,906
0.1574 Dump Truck Rp 555,000 Rp 87,357
0.2008 Concrete Vibrator Rp 250,000 Rp 50,200
2,415,263
1M' Saluran U - Beton Type DS-2B
1.4000 Pekerja Rp 80,000 Rp 112,000
0.2800 Tukang Rp 110,000 Rp 30,800
0.1400 Mandor Rp 175,000 Rp 24,500
0.6500 Beton K-250 Rp 850,000 Rp 552,500
36.3000 Penulangan Ulir Rp 18,000 Rp 653,400
0.0600 Beton Klas E Rp 710,000 Rp 42,600
3.5000 Begesting Ringan Rp 130,000 Rp 455,000
0.1016 Excavator Rp 655,000 Rp 66,548
0.1248 Dump Truck Rp 555,000 Rp 69,264
0.2008 Concrete Vibrator Rp 250,000 Rp 50,200
2,056,812

1M' Saluran U - Beton Type DS-3A


2.3333 Pekerja Rp 80,000 Rp 186,664
0.4667 Tukang Rp 110,000 Rp 51,337
0.2333 Mandor Rp 175,000 Rp 40,828
0.4100 Beton K-250 Rp 850,000 Rp 348,500
22.5500 Penulangan Ulir Rp 18,000 Rp 405,900
0.0400 Beton K - 125 Rp 725,000 Rp 29,000
2.3000 Begesting Ringan Rp 130,000 Rp 299,000
0.0501 Excavator Rp 655,000 Rp 32,816
0.0615 Dump Truck Rp 555,000 Rp 34,133
0.2008 Concrete Vibrator Rp 250,000 Rp 50,200
1,478,377

1M' Saluran U - Beton Type DS-3B


2.3333 Pekerja Rp 80,000 Rp 186,664
0.4667 Tukang Rp 110,000 Rp 51,337
0.2333 Mandor Rp 175,000 Rp 40,828
0.2550 Beton K-250 Rp 850,000 Rp 216,750
14.0250 Penulangan Ulir Rp 18,000 Rp 252,450
0.0750 Beton K - 125 Rp 725,000 Rp 54,375
2.3000 Begesting Ringan Rp 130,000 Rp 299,000
1.0000 Grill Rp 1,100,000 Rp 1,100,000
0.0501 Excavator Rp 655,000 Rp 32,816
0.0615 Dump Truck Rp 555,000 Rp 34,133
0.2008 Concrete Vibrator Rp 250,000 Rp 50,200
2,318,552
PROYEK : PEKERJAAN DRAINASI
LOKASI : REST AREA KM 319-B PEMALANG

ITEM PEKERJAAN :
1 Pipa Gorong - gorong Beton Bertulang Ø 40Cm type A
2 Pipa Gorong - gorong Beton Bertulang Ø 80Cm type A
3 Pipa Gorong - gorong Beton Bertulang 2 Ø 80Cm type A
4 Saluran U Type DS - 2
5 Saluran U Type DS - 2A
6 Saluran U Type DS - 2B
7 Saluran U Type DS - 3A
8 Saluran U Type DS - 3B
9 Inlet Drain, Type DI - 1
10 Inlet Drain, Type DI - 3
11 Outlet Drain, Type D0 - 1
12 Outlet Drain, Type D0 - 3

NO LOKASI DS - 2 (M') DS - 2A (M') DS - 2B (M') DS - 3A (M') DS - 3B (M') RCP 1x40 (M') RCP 1x80 (M') RCP 2x80 (M')

A ON OFF RAMP
1 Off Ramp 0.00 0.00 0.00 189.00 0.00 0.00 0.00 0.00
2 Connector 0.00 0.00 0.00 20.60 63.00 0.00 0.00 0.00
3 On Ramp 0.00 0.00 0.00 203.00 59.00 0.00 0.00 0.00
B JALAN KAWASAN
1 Kawasan 1 319.60 42.00 0.00 1,041.42 97.00 9.68 31.77 12.17
Kawasan 2 0.00 0.00 0.00 78.89 141.15 15.40 0.00 0.00
Kawasan 3 0.00 142.11 106.23 11.00 0.00 18.40 18.10 0.00
Kawasan 4 0.00 155.86 40.78 291.30 369.72 17.80 43.95 0.00
Kawasan 5 0.00 78.20 0.00 205.54 133.69 8.90 0.00 0.00
Kawasan 6 0.00 22.05 0.00 47.85 63.49 8.90 0.00 0.00
Kawasan 7 0.00 0.00 0.00 67.50 113.07 0.00 19.05 0.00
JUMLAH 319.60 440.22 147.01 2,156.10 1,040.12 79.08 112.87 12.17
PROYEK : PEKERJAAN DRAINASI
LOKASI : REST AREA KM 319-B PEMALANG

ESTIMASI / RAB PEKERJAAN DRAINASI

NO PEKERJAAN VOLUME SAT HARGA SATUAN JUMLAH (RP) KETERANGAN


(RP)
1 Pipa Gorong - gorong Beton Bertulang Ø 40Cm type A 82.08 M' 1,731,611.00 142,130,630.88
2 Pipa Gorong - gorong Beton Bertulang Ø 80Cm type A 112.87 M' 2,348,909.00 265,121,358.83
3 Pipa Gorong - gorong Beton Bertulang 2 Ø 80Cm type A 12.17 M' 4,202,167.00 51,140,372.39
4 Saluran U Type DS - 2 319.60 M' 2,231,975.00 713,339,210.00
5 Saluran U Type DS - 2A 440.22 M' 2,415,263.00 1,063,247,077.86
6 Saluran U Type DS - 2B 147.01 M' 2,056,812.00 302,371,932.12
7 Saluran U Type DS - 3A 2,156.10 M' 1,478,377.00 3,187,528,649.70
8 Saluran U Type DS - 3B 1,040.12 M' 2,318,552.00 2,411,572,306.24

JUMLAH 8,136,451,538.02
PPH 10% 813,645,153.80
JUMLAH KESELURUHAN 8,950,096,691.82

Karanganyar, 19 Nopember 2020


Disetujui Oleh, Dibuat Oleh,

Bapak Y. Soeroso Pancoro Adhi Atmaja Agus Joko Laksono


Presiden Direktur Asstman Legal dan Proyek Manager Pembangunan
Bapak Y. Soeroso Pancoro Adhi Atmaja Agus Joko Laksono
Presiden Direktur Asstman Legal dan Proyek Manager Pembangunan