JUMLAH HARGA
NO. URAIAN
(Rp)
I PEKERJAAN PERSIAPAN 8,128,225.00
II PEKERJAAN TANAH DAN URUGAN 20,516,386.93
III PEK. PASANGAN, PLESTERAN & LANTAI 242,513,772.04
IV PEKERJAAN BETON 276,443,118.05
V PEKERJAAN KUSEN & DAUN PINTU/JENDELA 54,420,830.34
VI PEKERJAAN PENGGANTUNG & PENGUNCI 2,854,580.00
VII PEKERJAAN CAT 52,497,826.42
VIII PEKERJAAN ATAP 239,086,455.60
IX PEKERJAAN INSTALASI LISTRIK 19,643,800.00
X PEKERJAAN PAGAR KELILING 115,836,116.39
XI PEKERJAAN LAIN - LAIN 1,000,000.00
JUMLAH NILAI KONSTRUKSI 1,032,941,110.77
TOTAL 1,032,941,110.77
DIBULATKAN 1,032,900,000.00
Terbilang: Satu Milyar Tiga Puluh Dua Juta Sembilan Ratus Ribu Rupiah 837,900,000
FREDRIKUS BAU, ST
DAFTAR ANALISA HARGA SATUAN
11 1 m2 Lantai keramik 40 x 40 cm
1.0000 m2 Keramik lantai 40 x 40 cm Rp 100,000.00 Rp 100,000.00
0.3780 zak Semen Rp 60,500.00 Rp 22,869.00
0.0230 m3 Pasir pasang Rp 183,300.00 Rp 4,215.90
1.5000 kg Semen warna Rp 7,000.00 Rp 10,500.00
0.3500 OH Tukang Rp 100,000.00 Rp 35,000.00
0.0350 OH Kepala tukang Rp 110,000.00 Rp 3,850.00
0.6200 OH Pekerja Rp 80,000.00 Rp 49,600.00
0.0300 OH Mandor Rp 115,000.00 Rp 3,450.00
Jumlah Rp 229,484.90
a. Begisting Tripleks 9 mm :
0.075 m3 Balok Kayu Klas II Rp 3,250,000.00 Rp 243,750.00
2.770 lbr Tripleks 9 mm Rp 125,000.00 Rp 346,250.00
4.000 kg Paku Rp 20,000.00 Rp 80,000.00
2.000 OH Pekerja Rp 80,000.00 Rp 160,000.00
0.100 OH Mandor Rp 115,000.00 Rp 11,500.00
5.000 OH Tukang Rp 100,000.00 Rp 500,000.00
0.500 OH Kepala Tukang Rp 110,000.00 Rp 55,000.00
sub jumlah a Rp 1,396,500.00
b. Penyokong
0.25 m3 Balok Kayu Klas II Rp 3,250,000.00 Rp 812,500.00
4 OH Tukang Rp 100,000.00 Rp 400,000.00
1.05 OH Kepala tukang Rp 110,000.00 Rp 115,500.00
2 OH Pekerja Rp 80,000.00 Rp 160,000.00
0.175 OH Mandor Rp 115,000.00 Rp 20,125.00
sub jumlah b Rp 1,508,125.00
c. Pembongkaran dan Penyiraman
4 OH Pekerja Rp 80,000.00 Rp 320,000.00
sub jumlah c Rp 320,000.00
14 Cor Beton Sloof, Ring Balk, Kolom Praktis (Pembesian 110 Kg)
Beton Cor Rp 883,824.00
Pembesian 110 Rp 2,535,720.00
a. Begisting Tripleks 9 mm : Rp 1,396,500.00
Pembongkaran dan Penyiraman Rp 320,000.00
Rp 5,136,044.00
15 Cor Beton Tangga, Balok Induk (25/30), Plat Lantai Pembesian 125 Kg
Beton Cor Rp 877,399.00
Pembesian 135 kg Rp 2,897,909.00
Begisting Tripleks Rp 1,367,500.00
Penyokong Rp 1,485,000.00
Pembongkaran dan Penyiraman Rp 312,000.00
Rp 6,939,808.00
34 1 m2 Pekerjaan polytur
0.0170 kg Cheerlack Rp 34,500.00 Rp 586.50
0.3300 ltr Spiritus Rp 14,000.00 Rp 4,620.00
0.1500 lbr Kertas pasir (Amplas) Rp 5,000.00 Rp 750.00
0.2500 OH Tukang Rp 100,000.00 Rp 25,000.00
0.0250 OH Kepala tukang Rp 110,000.00 Rp 2,750.00
0.0680 OH Pekerja Rp 80,000.00 Rp 5,440.00
0.0034 OH Mandor Rp 115,000.00 Rp 391.00
Jumlah Rp 39,537.50
35 1.0000 titik Instalasi Penerangan dg Kabel NYM 3X2.5 mm
1.0000 m1 Kabel NYM 3x2.5 mm2 Rp 11,700.00 Rp 11,700.00
1 ls Material bantu T dos,klem,dll Rp 15,000.00 Rp 15,000.00
0.15 oh Tukang Listrik Rp 100,000.00 Rp 15,000.00
0.15 oh Pekerja Rp 80,000.00 Rp 12,000.00
0.18 oh Mandor Rp 115,000.00 Rp 20,700.00
Rp 74,400.00
36 Membuat Pondasi Foot Plat dan Plat Lantai di bawah tanah Mutu Beton K 275 (Pembesian 150 Kg / M3 Beton)
0.2 M³ Kayu kelas III / pe@Rp. Rp 2,500,000.00 Rp 500,000.00
1.5 Kg Paku 7 s/d 12 cm @Rp. Rp 25,000.00 Rp 37,500.00
0.4 Ltr Minyak begesting@Rp. Rp 43,750.00 Rp 17,500.00
200 Kg Besi beton ulir @Rp. Rp 18,828.45 Rp 3,765,690.00
2.25 Kg Kawat ikat beton @Rp. Rp 27,675.00 Rp 62,268.75
400 Kg Semen portland @Rp. Rp 1,250.00 Rp 500,000.00
0.54 M³ Pasir beton @Rp. Rp 331,250.00 Rp 178,875.00
0.81 M³ Batu pecah 2/3 cm@Rp. Rp 468,750.00 Rp 379,687.50
5.3 OH Pekerja @Rp. Rp 78,000.00 Rp 413,400.00
0.28 OH Tukang batu @Rp. Rp 90,000.00 Rp 24,750.00
1.3 OH Tukang kayu @Rp. Rp 90,000.00 Rp 117,000.00
1.05 OH Tukang besi @Rp. Rp 125,000.00 Rp 131,250.00
0.26 OH Kepala tukang @Rp. Rp 115,000.00 Rp 30,130.00
0.27 OH Mandor @Rp. Rp 130,000.00 Rp 34,450.00
Jumlah Rp 6,192,501.25
38 1 m2 pasangan Batako
20 bh Batako Rp 3,500.00 = Rp. Rp 70,000.00
0.05 m3 Pasir Pasang Rp 183,300.00 = Rp. 8248.5
9.68 kg Semen Portland Rp 1,512.50 = Rp. 14641
0.3 OH Pekerja Rp 80,000.00 = Rp. 24000
0.1 OH Tukang Rp 100,000.00 = Rp. 10000
0.01 OH Kepala Tukang Rp 110,000.00 = Rp. 1100
0.02 OH Mandor Rp 115,000.00 = Rp. 1725
129,714.50
RENCANA ANGGARAN BIAYA (RAB)
PEKERJAAN : PEMBANGUNAN KAPELA ST. ISODORUS PANTAE
LOKASI :
PEMILIK :
HARGA
JUMLAH HARGA
NO. URAIAN VOLUME SAT. SATUAN
(Rp)
(Rp)
I PEKERJAAN PERSIAPAN
1 Pengukuran dan Pemasangan Bowplank 57.000 m' 72,425.00 4,128,225.00
2 Pengadaan Air Kerja 1.000 Ls 4,000,000.00 4,000,000.00
JUMLAH I 8,128,225.00
II PEKERJAAN TANAH DAN URUGAN
1 Galian Tanah untuk Pondasi Biasa 101.440 m3 36,600.00 3,712,704.00
2 Urugan Kembali Bekas Galian Pondasi Biasa 33.813 m3 17,545.00 593,254.93
3 Urugan Pasir di bawah Pondasi 4.200 m3 185,110.00 777,462.00
4 Urugan Sirtu di bawah Lantai 94.800 m3 162,795.00 15,432,966.00
JUMLAH II 20,516,386.93
III PEK. PASANGAN, PLESTERAN & LANTAI
1 Aanstamping Pondasi Biasa 10.680 m3 293,920.00 3,139,065.60
2 Pasangan Pondasi Biasa 64.080 m3 683,900.20 43,824,324.82
3 Pasangan Tembok Batu Merah 1pc : 5 psr 447.065 m2 182,214.50 81,461,725.44
4 Plesteran Tembok & Kaki Pondasi 1 pc : 5 psr 523.07 m2 44,366.60 23,206,615.63
5 Acian Plest.Tembok & Kaki Pondasi dengan Saus Semen 523.07 m2 35,110.00 18,364,812.15
6 Pasangan Keramik 40x40 316.00 m2 229,484.90 72,517,228.40
JUMLAH III 242,513,772.04
IV PEKERJAAN BETON
1 Sloof beton bertulang 25/35 7.788 m3 6,939,808.00 54,043,754.80
2 Kolom beton bertulang 30x30 19.530 m3 6,939,808.00 135,534,450.24
3 Balok Beton bertulang 20/30 0.840 m3 6,939,808.00 5,829,438.72
4 Balok Beton bertulang 15/30 3.420 m3 6,939,808.00 23,734,143.36
5 Ring-balk beton bertulang 20/25 114.000 m1 91,679.85 10,451,502.90
6 Cor Foot Plate 3.969 m3 6,939,808.00 27,544,097.95
7 Cor lantai rabat 1pc : 3psr : 5krl, tebal 7 cm 21.840 m3 883,962.00 19,305,730.08
JUMLAH IV 276,443,118.05
V PEKERJAAN KUSEN & DAUN PINTU/JENDELA
1 Pekerjaan Kusen 0.346 m3 6,806,250.00 2,354,962.50
2 Pek. Daun Pintu Panil kayu 34.363 m2 1,214,875.00 41,746,992.60
3 Pek. jendela Panil kaca 10.034 m2 1,028,350.00 10,318,875.24
JUMLAH V 54,420,830.34
VI PEKERJAAN PENGGANTUNG & PENGUNCI
1 Kunci tanam besar 2x putar 4.000 bh 250,475.00 1,001,900.00
2 Engsel nylon besar untuk daun pintu 16.000 bh 41,942.00 671,072.00
3 Engsel nylon sedang untuk daun jendela 12.000 bh 34,942.00 419,304.00
4 Grendel besar untuk daun pintu 16.000 bh 25,000.00 400,000.00
5 Grendel sedang untuk daun jendela 6.000 bh 28,942.00 173,652.00
6 kait angin untuk daun jendela 6.000 bh 31,442.00 188,652.00
JUMLAH VII 2,854,580.00