URAIAN KOEFISIEN SAT HARGA SATUAN (Rp)


PEKERJAAN PERSIAPAN
Pengukuran Lapangan ls
1 m' Pengukuran dan pemasangan bouwplank
Bahan
Kayu meranti 5/7 0.012 M3 40,000.00 Rp
Paku biasa 2" - 5" 0.020 Kg 16,500.00 Rp
Kayu papan 3/20 ( sengon ) 0.007 M3 1,300,000.00 Rp
JUMLAH Rp
Tenaga
Tukang kayu 0.100 Oh 92,500.00 Rp
Pekerja 0.100 Oh 80,500.00 Rp
Kepala tukang 0.010 Oh 110,000.00 Rp
Mandor 0.005 Oh 130,000.00 Rp
JUMLAH Rp
Rp

PEKERJAAN TANAH
1 m3 Galian tanah biasa sedalam 1 meter
Tenaga
Pekerja 0.750 Oh 80,500.00 Rp
Mandor 0.025 Oh 130,000.00 Rp
JUMLAH Rp
Rp

1 m3 Urugan kembali
Tenaga
Pekerja 0.2500 Oh 80,500.00 Rp
Mandor 0.0083 Oh 130,000.00 Rp
JUMLAH Rp
Rp

PEKERJAAN PONDASI
1 m3 Pasang pondasi batu kosong (aanstamping)
Bahan
Batu belah 15/20 cm 1.200 M3 200,000.00 Rp
Pasir urug 0.432 M3 195,000.00 Rp
JUMLAH Rp
Tenaga
Pekerja 0.780 Oh 80,500.00 Rp
Tukang batu 0.390 Oh 92,500.00 Rp
Kepala tukang 0.039 Oh 110,000.00 Rp
Mandor 0.039 Oh 130,000.00 Rp
JUMLAH Rp
Rp

1 m3 Pasang pondasi batu belah 1 Pc : 5 PP


Bahan
Batu belah 15/20 cm 1.200 M3 200,000.00 Rp
Semen portland 136.000 Kg 1,500.00 Rp
Pasir pasang 0.544 M3 275,000.00 Rp
JUMLAH Rp
Tenaga
Pekerja 1.500 Oh 80,500.00 Rp
Tukang batu 0.750 Oh 92,500.00 Rp
Kepala tukang 0.075 Oh 110,000.00 Rp
Mandor 0.075 Oh 130,000.00 Rp
JUMLAH Rp
Rp

1 m3 Urugan pasir
Bahan
Pasir Urug 1.200 M3 195,000.00 Rp
JUMLAH Rp
Tenaga
Pekerja 0.300 Oh 80,500.00 Rp
Mandor 0.010 Oh 130,000.00 Rp
JUMLAH Rp
Rp

PEKERJAAN BETON
1 m3 Membuat Sloof beton bertulang ( 150 Kg besi + Bekisting )
Bahan
Kayu terentang ( kayu tahun ) 0.270 M3 4,500,000.00 Rp
Paku Biasa 2'' - 5'' 2.000 Kg 16,500.00 Rp
Minyak bekisting 0.600 Lt 15,000.00 Rp
Besi beton polos 157.500 Kg 25,000.00 Rp
Kawat beton 2.250 Kg 20,000.00 Rp
semen Portland 336.000 Kg 1,500.00 Rp
Pasir beton 0.540 M3 285,000.00 Rp
Koral beton 0.810 M3 290,000.00 Rp
Jumlah Rp
Tenaga
Pekerja 5.300 Oh 80,500.00 Rp
Tukang batu 0.275 Oh 95,000.00 Rp
Tukang kayu 1.560 Oh 92,500.00 Rp
Tukang Besi 1.050 Oh 92,500.00 Rp
Kepala tukang 0.262 Oh 110,000.00 Rp
Mandor 0.265 Oh 130,000.00 Rp
Jumlah Rp
Rp

1 m3 Membuat Kolom beton bertulang ( 150 Kg besi + Bekisting )


Bahan
Kayu terentang (tahun) 0.320 M3 4,500,000.00 Rp
Paku Biasa 2'' - 5'' 3.200 Kg 16,500.00 Rp
Minyak bekisting 1.600 Lt 15,000.00 Rp
Besi beton polos 157.500 Kg 25,000.00 Rp
Kawat beton 2.250 Kg 20,000.00 Rp
semen Portland 336.000 Kg 1,500.00 Rp
Pasir beton 0.540 M3 285,000.00 Rp
Koral beton 0.810 M3 250,000.00 Rp
kayu balok (meranti) 0.120 M3 6,600,000.00 Rp
Playwood 9 mm 2.800 Lbr 170,000.00 Rp
Dolken Ø -8 cm/ 4 m 32.000 Btg 37,400.00 Rp
Jumlah Rp
Tenaga
Pekerja 5.300 Oh 80,500.00 Rp
Tukang batu 0.275 Oh 92,500.00 Rp
Tukang kayu 1.300 Oh 92,500.00 Rp
Tukang Besi 1.050 Oh 92,500.00 Rp
Kepala tukang 0.262 Oh 110,000.00 Rp
Mandor 0.265 Oh 130,000.00 Rp
JUMLAH Rp
Rp
1 m' Membuat ring balok beton bertulang ( 10 x 15 ) cm
Bahan
Kayu meranti 0.003 M3 120,000.00 Rp
Paku Biasa 2'' - 5'' 0.020 Kg 20,000.00 Rp
Besi beton polos 3.600 Kg 25,000.00 Rp
Kawat beton 0.050 Kg 20,000.00 Rp
semen Portland 5.500 Kg 1,500.00 Rp
Pasir beton 0.009 M3 285,000.00 Rp
Koral beton 0.015 M3 290,000.00 Rp
Jumlah Rp
Tenaga
Pekerja 0.297 Oh 80,500.00 Rp
Tukang batu 0.033 Oh 92,500.00 Rp
Tukang kayu 0.033 Oh 92,500.00 Rp
Tukang Besi 0.033 Oh 92,500.00 Rp
Kepala tukang 0.010 Oh 110,000.00 Rp
Mandor 0.015 Oh 130,000.00 Rp
JUMLAH Rp
Rp
1 M3 Beton Tumbuk,1 Pc : 3Ps: 5kr
Bahan
semen portland 218.000 Kg 1,500.00 Rp
pasir beton 0.520 M3 285,000.00 Rp
koral beton 0.870 M3 290,000.00 Rp
JUMLAH Rp
Tenaga
pekerja 1.650 Oh 80,500.00 Rp
Tukang batu 0.250 Oh 92,500.00 Rp
Kepala tukang 0.025 Oh 110,000.00 Rp
Mandor 0.080 Oh 130,000.00 Rp
JUMLAH Rp
Rp

1 m3 plat lantai Tb 10 cm beton bertulang (90 kg +bekisting )


Bahan
beton bertulang 1 pc : 2 ps : 3 kr 1.000 M3 455,000.00 Rp
pasang bekisiting untuk lantai 10.000 M2 495,500.00 Rp
besi beton polos 90.000 Kg 25,000.00 Rp
JUMLAH Rp
Tenaga
Pekerja 2.667 Oh 80,500.00 Rp
Tukang besi 0.875 Oh 92,500.00 Rp
Tukang kayu 0.330 Oh 95,000.00 Rp
Kepala tukang 0.068 Oh 110,000.00 Rp
Mandor 0.133 Oh 130,000.00 Rp
JUMLAH Rp
Rp

PEKERJAAN PASANGAN DAN PLESTERAN


1 m2 Pasangan bata merah tebal 1 bata 1 Pc : 3 PP
Bahan
Bata merah 5 x 11 x 22 cm 140.000 Bh 1,750.00 Rp
Semen portland 32.950 Kg 1,500.00 Rp
Pasir pasang 0.091 M3 275,000.00 Rp
JUMLAH Rp
Tenaga
Pekerja 0.600 Oh 80,500.00 Rp
Tukang batu 0.200 Oh 92,500.00 Rp
Kepala tukang 0.020 Oh 110,000.00 Rp
Mandor 0.030 Oh 130,000.00 Rp
JUMLAH Rp
Rp

1 m2 Plesteran 1 Pc : 5 Ps, tebal : 15 mm


Bahan
semen portland 5.184 Kg 1,500.00 Rp
Pasir pasang 0.026 M3 275,000.00 Rp
JUMLAH Rp
Tenaga
Pekerja 0.300 Oh 80,500.00 Rp
Tukang batu 0.150 Oh 92,500.00 Rp
Kepala tukang 0.015 Oh 110,000.00 Rp
Mandor 0.015 Oh 130,000.00 Rp
JUMLAH Rp
Rp
1 m' Plesteran skoning 1 Pc : 2 Ps, lebar 10 mm
Bahan
semen Portland 0.500 Kg 1,500.00 Rp
Pasir pasang 0.013 M3 275,000.00 Rp
JUMLAH Rp
Tenaga
Pekerja 0.080 Oh 80,500.00 Rp
Tukang batu 0.040 Oh 92,500.00 Rp
Kepala tukang 0.040 Oh 110,000.00 Rp
Mandor 0.004 Oh 130,000.00 Rp
JUMLAH Rp
Rp
1 m2 acian
Bahan
Semen Portland 3.250 Kg 1,500.00 Rp
JUMLAH
Tenaga
Pekerja 0.200 Oh 80,500.00 Rp
Tukang batu 0.100 Oh 92,500.00 Rp
Kepala tukang 0.010 Oh 110,000.00 Rp
Mandor 0.010 Oh 130,000.00 Rp
JUMLAH Rp
Rp
PEKERJAAN PINTU DAN JENDELA
1 m3 Pasang kusen pintu dan jendela kayu kamper
Bahan
Kayu kamper, balok 1.200 M3 3,700,000.00 Rp
Paku 1.250 kg 15,000.00 Rp
Lem kayu 1.000 kg 17,000.00 Rp
JUMLAH Rp
Tenaga
Pekerja 6.000 Oh 80,500.00 Rp
Tukang kayu 18.000 Oh 92,500.00 Rp
Kepala tukang 1.800 Oh 110,000.00 Rp
Mandor 0.300 Oh 130,000.00 Rp
JUMLAH Rp
Rp

1 m2 Pasang pintu dan jendela kaca kayu kamfer


Bahan
Kayu kamfer, papan 0.024 M3 12,990,000.00 Rp
Lem kayu 0.300 kg 17,000.00 Rp
JUMLAH Rp
Tenaga
Pekerja 0.800 Oh 80,500.00 Rp
Tukang kayu 2.400 Oh 92,500.00 Rp
Kepala tukang 0.240 Oh 110,000.00 Rp
Mandor 0.040 Oh 130,000.00 Rp
JUMLAH Rp

1 m2 Pasang pintu dan jendela jalusi kayu kamfer


Bahan
Kayu kamfer, papan 0.064 M3 12,990,000.00 Rp
Lem kayu 0.500 kg 17,000.00 Rp
JUMLAH Rp
Tenaga
Pekerja 1.000 Oh 80,500.00 Rp
Tukang kayu 3.000 Oh 92,500.00 Rp
Kepala tukang 0.300 Oh 110,000.00 Rp
Mandor 0.050 Oh 130,000.00 Rp
JUMLAH Rp
Rp

PEKERJAAN KUNCI DAN KACA


1 buah Pasang Engsel jendela (engsel H kecil)
Bahan :
Engsel jendela 1.000 Bh 10,900.00 Rp
JUMLAH Rp
Tenaga :
Pekerja 0.010 Oh 80,500.00 Rp
Tukang kayu 0.100 Oh 92,500.00 Rp
Kepala Tukang 0.010 Oh 110,000.00 Rp
Mandor 0.001 Oh 130,000.00 Rp
JUMLAH Rp
Rp

1 buah Pasang Engsel pintu (engsel H besar)


Bahan :
Engsel pintu 1.000 Bh 22,200.00 Rp
JUMLAH Rp
Tenaga :
Pekerja 0.015 Oh 80,500.00 Rp
Tukang kayu 0.150 Oh 92,500.00 Rp
Kepala Tukang 0.015 Oh 110,000.00 Rp
Mandor 0.001 Oh 130,000.00 Rp
JUMLAH Rp
Rp

1 buah Pasang Kunci selot


Bahan :
Kunci selot 1.000 Bh 190,000.00 Rp
JUMLAH Rp
Tenaga :
Pekerja 0.020 Oh 80,500.00 Rp
Tukang kayu 0.200 Oh 92,500.00 Rp
Kepala Tukang 0.020 Oh 110,000.00 Rp
Mandor 0.001 Oh 130,000.00 Rp
JUMLAH Rp
Rp

1 buah Pasang grendel


Bahan :
Kait angin 1.000 Bh 13,500.00 Rp
JUMLAH Rp
Tenaga :
Pekerja 0.015 Oh 80,500.00 Rp
Tukang kayu 0.150 Oh 92,500.00 Rp
Kepala Tukang 0.015 Oh 110,000.00 Rp
Mandor 0.00075 Oh 130,000.00 Rp
JUMLAH Rp
Rp

1 buah Pasang Kait Angin


Bahan :
Kait angin 1.000 Bh 13,500.00 Rp
JUMLAH Rp
Tenaga :
Pekerja 0.015 Oh 80,500.00 Rp
Tukang kayu 0.150 Oh 92,500.00 Rp
Kepala Tukang 0.015 Oh 110,000.00 Rp
Mandor 0.00075 Oh 130,000.00 Rp
JUMLAH Rp
Rp

PEKERJAAN ATAP
1 m3 Pasang konstruksi kuda - kuda kayu bangkirai
Bahan
Kayu bangkirai, balok 1.100 M3 13,550,000.00 Rp
Besi strip 15.000 Kg 16,000.00 Rp
Paku biasa 12 cm 5.600 Kg 20,000.00 Rp
JUMLAH Rp
Tenaga
Pekerja 4.000 Oh 80,500.00 Rp
Tukang kayu 12.000 Oh 92,500.00 Rp
Kepala tukang 1.200 Oh 110,000.00 Rp
Mandor 0.200 Oh 130,000.00 Rp
JUMLAH Rp
Rp
1 m' pasang nok stel gelombang 1,08 m
Bahan
Nok stel gelombang 2.050 Lbr 42,000.00 Rp
Paku sekrup 3,5 '' 6.000 Bh 2,000.00 Rp
JUMLAH Rp
Tenaga
Pekerja 0.084 Oh 80,500.00 Rp
Tukang kayu 0.125 Oh 92,500.00 Rp
Kepala tukang 0.013 Oh 110,000.00 Rp
Mandor 0.004 Oh 130,000.00 Rp
JUMLAH Rp
Rp

1 m3 Pasang konstruksi gording kayu bangkirai


Bahan
Kayu bangkirai, balok 1.100 M3 13,550,000.00 Rp
Besi strip 15.000 Kg 16,000.00 Rp
Paku biasa 12 cm 3.000 Kg 20,000.00 Rp
JUMLAH Rp
Tenaga
Pekerja 2.400 Oh 80,500.00 Rp
Tukang kayu 7.200 Oh 92,500.00 Rp
Kepala tukang 0.720 Oh 110,000.00 Rp
Mandor 0.120 Oh 130,000.00 Rp
JUMLAH Rp
Rp
1 m2 Pasangan balok kayu 8/12, tebal 8 cm, JAT 4,0 m'
Bahan
Balok kayu kamper 8/12 0.0116 M' 350,000.00 Rp
Paku 7 cm - 12 cm 0.150 Kg 15,000.00 Rp
Baut ø 12 - 20 cm 8.340 Bh 12,500.00 Rp
JUMLAH Rp
Tenaga
Pekerja 0.042 Oh 80,500.00 Rp
Tukang kayu 0.126 Oh 92,500.00 Rp
Mandor 0.0042 Oh 130,000.00 Rp
JUMLAH Rp
Rp

1 m2 Pasang atap genting Sokka


Bahan
Genteng Sokka besar 25.000 Bh 2,000.00 Rp
JUMLAH Rp
Tenaga
Pekerja 0.150 Oh 80,500.00 Rp
Tukang kayu 0.075 Oh 92,500.00 Rp
Kepala tukang 0.008 Oh 110,000.00 Rp
Mandor 0.008 Oh 130,000.00 Rp
JUMLAH Rp
Rp

1 m1 Pasang genteng bubung Sokka


Bahan
Genteng bubung sokka 4.000 Bh 7,700.00 Rp
Semen Portland 8.000 Kg 1,500.00 Rp
Pasir Pasang 0.032 M3 275,000.00 Rp
JUMLAH Rp
Tenaga
Pekerja 0.400 Oh 80,500.00 Rp
Tukang kayu 0.200 Oh 92,500.00 Rp
Kepala tukang 0.020 Oh 110,000.00 Rp
Mandor 0.002 Oh 130,000.00 Rp
JUMLAH Rp
Rp
1 m' Pasang lisplank ukuran ( 3 x 20 ) cm, kayu kamfer
Bahan
Kayu kamfer, papan 0.0108 M3 12,990,000.00 Rp
Paku biasa 2" - 5" 0.100 Kg 16,500.00 Rp
JUMLAH Rp
Tenaga
Pekerja 0.100 Oh 80,500.00 Rp
Tukang kayu 0.200 Oh 92,500.00 Rp
Kepala tukang 0.020 Oh 110,000.00 Rp
Mandor 0.005 Oh 130,000.00 Rp
JUMLAH Rp
Rp

PEKERJAAN LANGIT LANGIT


1 m2 Pasang rangka atap genteng keramik kayu kamfer
Bahan
Kayu kamfer 0.012 M3 12,990,000.00 Rp
Paku biasa 2" - 5" 0.150 Kg 16,500.00 Rp
JUMLAH Rp
Tenaga
Pekerja 0.100 Oh 80,500.00 Rp
Tukang kayu 0.100 Oh 92,500.00 Rp
Kepala tukang 0.010 Oh 110,000.00 Rp
Mandor 0.005 Oh 130,000.00 Rp
JUMLAH Rp
Rp
1 m2 Pasang Langit-langit calcyboard (120cm x 240cm x 3,5mm)
Bahan :
CalcyBoard 0.364 Lbr 116,000.00 Rp
Paku Sekrup 0.110 Kg 2,000.00 Rp
JUMLAH Rp
Tenaga
Pekerja 0.100 Oh 80,500.00 Rp
Tukang kayu 0.050 Oh 92,500.00 Rp
Kepala Tukang 0.005 Oh 110,000.00 Rp
Mandor 0.005 Oh 130,000.00 Rp
JUMLAH Rp
Rp
1 m1 Pasang list langit-langit kayu profil
Bahan :
List kayu profil 5x5 cm 1.050 m1 5,000.00 Rp
Paku 0.010 Kg 16,000.00 Rp
JUMLAH Rp
Tenaga
Pekerja 0.050 Oh 80,500.00 Rp
Tukang kayu 0.050 Oh 92,500.00 Rp
Kepala Tukang 0.005 Oh 110,000.00 Rp
Mandor 0.003 Oh 130,000.00 Rp
JUMLAH Rp
Rp

PEKERJAAN LANTAI
1 m2 Pasang Lantai ubin warna uk 30 x 30 cm
Bahan :
Ubin warna 30x30 cm 11.870 Bh 68,000.00 Rp
Semen portland 10.000 Kg 1,500.00 Rp
pasir pasang 0.045 M3 275,000.00 Rp
Semen warna 0.300 kg 12,500.00 Rp
JUMLAH Rp
Tenaga :
Pekerja 0.260 Oh 80,500.00 Rp
Tukang batu 0.130 Oh 92,500.00 Rp
Kepala Tukang 0.013 Oh 110,000.00 Rp
Mandor 0.013 Oh 130,000.00 Rp
JUMLAH Rp
Rp

1 m2 Pasang Lantai ubin PC abu-abu uk 20 x 20 cm


Bahan :
Ubin abu-abu 20x20 cm 26.500 Bh 70,000.00 Rp
Semen portland 10.400 Kg 1,500.00 Rp
pasir pasang 0.045 M3 275,000.00 Rp
JUMLAH Rp
Tenaga :
Pekerja 0.270 Oh 80,500.00 Rp
Tukang batu 0.135 Oh 105,000.00 Rp
Kepala Tukang 0.014 Oh 110,000.00 Rp
Mandor 0.014 Oh 130,000.00 Rp
JUMLAH Rp
Rp

PEKERJAAN SANITASI DAN DRAINASE


1 m2 Pemasangan lapisan ijuk tebal 10 cm
Bahan
Ijuk 6.000 kg 9,000.00 Rp
JUMLAH Rp
Tenaga
Pekerja 0.150 Oh 80,500.00 Rp
Mandor 0.015 Oh 130,000.00 Rp
JUMLAH Rp
Rp

Memasang 1 buah kran diameter 3/4" atau 1/2"


Bahan :
Kran air 1.000 Bh 15,000.00 Rp
Seal tape 0.025 M3 4,000.00 Rp
JUMLAH Rp
Tenaga
Pekerja 0.010 Oh 80,500.00 Rp
Tukang batu 0.100 Oh 92,500.00 Rp
Kepala Tukang 0.010 Oh 110,000.00 Rp
Mandor 0.005 Oh 130,000.00 Rp
JUMLAH Rp
Rp

Pemasangan 1 m’ pipa PVC tipe AW diameter ½ ”


Bahan
pipa PVC 1/2” 1.200 M1 20,000.00 Rp
Perlengkapan 35 % 22,000.00 Rp
JUMLAH Rp
Tenaga
Pekerja 0.036 Oh 80,500.00 Rp
tukang batu 0.060 Oh 92,500.00 Rp
kepala tukang 0.006 Oh 110,000.00 Rp
Mandor 0.002 Oh 130,000.00 Rp
JUMLAH Rp
Rp

Pemasangan 1 m’ pipa PVC tipe AW diameter 3”


Tenaga
Pekerja 0.081 Oh 80,500.00 Rp
tukang batu 0.135 Oh 92,500.00 Rp
kepala tukang 0.014 Oh 110,000.00 Rp
Mandor 0.004 Oh 130,000.00 Rp
JUMLAH Rp
Bahan
Pipa PVC 3” 1.200 M1 309,000.00 Rp
Perlengkapan 35 % 22,000.00 Rp
JUMLAH Rp
Rp
Pemasangan 1 m’ pipa PVC tipe AW diameter 4”
Tenaga
Pekerja 0.081 Oh 80,500.00 Rp
tukang batu 0.135 Oh 92,500.00 Rp
kepala tukang 0.014 Oh 110,000.00 Rp
Mandor 0.004 Oh 130,000.00 Rp
JUMLAH Rp
Bahan
Pipa PVC 4” 1.200 M1 445,000.00 Rp
Perlengkapan 35 % 10,000.00 Rp
JUMLAH Rp
Rp
Pemasangan 1 buah floor drain
Tenaga
pekerja 0.010 Oh 80,500.00 Rp
tukang batu 0.100 Oh 92,500.00 Rp
kepala tukang 0.010 Oh 110,000.00 Rp
mandor 0.005 Oh 130,000.00 Rp
JUMLAH Rp
Bahan
Floor Drain 1.000 unit 38,000.00 Rp
JUMLAH Rp
Rp

Pemasangan 1buah kloset duduk


Bahan:
Kloset duduk 1.00 Unit 1,250,000.00 Rp
Perlengkapan ls 1,253,000.00 Rp
JUMLAH Rp
Tenaga:
Pekerja 3.30 Oh 80,500.00 Rp
Tukang batu 1.10 Oh 92,500.00 Rp
Kepala Tukang 0.01 Oh 110,000.00 Rp
Mandor 0.16 Oh 130,000.00 Rp
JUMLAH Rp
Rp

PEKERJAAN PENGECATAN DAN FINISHING


1 m2 Pengecatan tembok baru ( 1 lapis plamir, 1 lapis cat dasar dan 2 lapis cat penutup )
Bahan :
plamir tembok 0.100 Kg 30,000.00 Rp
Cat dasar 0.100 Kg 41,500.00 Rp
Cat penutup 2 kali 0.260 Kg 330,000.00 Rp
JUMLAH Rp
Tenaga :
Pekerja 0.020 Oh 80,500.00 Rp
Tukang cat 0.063 Oh 92,500.00 Rp
Kepala Tukang 0.006 Oh 110,000.00 Rp
Mandor 0.003 Oh 130,000.00 Rp
JUMLAH Rp
Rp

1 m2 pengecatan bidang kayu baru ( 1 lapis plamir ), 1 lapis cat dasar, 2 lapis cat penutup
Bahan :
Cat meni kayu 0.200 Kg 80,500.00 Rp
Plamir kayu 0.150 Kg 92,500.00 Rp
Cat dasar 0.170 Kg 41,500.00 Rp
cat penutup 2 kali 0.260 Kg 330,000.00 Rp
JUMLAH Rp
Tenaga :
Pekerja 0.070 Oh 80,500.00 Rp
Tukang cat 0.009 Oh 92,500.00 Rp
Kepala Tukang 0.006 Oh 110,000.00 Rp
Mandor 0.003 Oh 130,000.00 Rp
JUMLAH Rp
Rp
PEKERJAAN ELEKTRKAL
Pemasangan 1 buah titik lampu
Bahan
Pipa listrik 5/8" 3.000 btg 10,000.00 Rp
Kabel 24.000 m 5,000.00 Rp
T Dus 3.000 bh 3,000.00 Rp
L Bow 4.000 bh 2,200.00 Rp
Las Dop 3.000 bh 20,000.00 Rp
Klem 24.000 bh 1,200.00 Rp
Mongkok 1.000 bh 3,000.00 Rp
Saklar 1.000 bh 38,000.00 Rp
Fitting 1.000 bh 15,000.00 Rp
JUMLAH Rp
Tenaga
Upah 100 % Rp
Rp
JUMLAH (Rp) JUMLAH HARGA (Rp)

480.00
330.00
9,100.00
9,910.00

9,250.00
8,050.00
1,100.00
650.000
19,050.00
28,960.00

60,375.00
3,250.00
63,625.00
63,625.00

20,125.00
1,083.33
21,208.33
21,208.33

240,000.00
84,240.00
324,240.00
62,790.00
36,075.00
4,290.00
5,070.00
108,225.00
432,465.00

240,000.00
204,000.00
149,600.00
593,600.00

120,750.00
69,375.00
8,250.00
9,750.00
208,125.00
801,725.00

234,000.000
234,000.000

24,150.00
1,300.00
25,450.00
259,450.00

1,215,000
33,000
9,000
3,937,500
45,000
504,000
153,900
234,900
6,132,300
426,650.00
26,125.00
144,300.00
97,125.00
28,820.00
34,450.00
757,470.00
6,889,770.00

1,440,000.00
52,800.00
24,000.00
3,937,500.00
45,000.00
504,000.00
153,900.00
202,500.00
792,000.00
476,000.00
1,196,800.00
8,824,500.00

426,650.00
25,437.50
120,250.00
97,125.00
28,820.00
34,450.00
732,732.50
9,557,232.50

360.00
400.00
90,000.00
1,000.00
8,250.00
2,565.00
4,350.00
106,925.00

23,908.50
3,052.50
3,052.50
3,052.50
1,100.00
1,950.00
36,116.00
143,041.00

327,000.00
148,200.00
252,300.00
727,500.00

132,825.00
23,125.00
2,750.00
10,400.00
169,100.00
896,600.00

455,000.00
4,955,000.00
2,250,000.00
7,660,000.00

214,693.50
80,937.50
31350
7,480.00
17,290.00
351,751.00
8,011,751.00

245,000.00
49,425.00
25,025.00
319,450.00
48,300.00
18,500.00
2,200.00
3,900.00
72,900.00
392,350.00

7,776.00
7,150.00
14,926.00

24,150.00
13,875.00
1,650.00
1,950.00
41,625.00
56,551.00

750.00
3,575.00
4,325.00

6,440.00
3,700.00
4,400.00
520.00
15,060.00
19,385.00

4,875.00
4,875.00

16,100.00
9,250.00
1,100.00
1,300.00
27,750.00
32,625.00
4,440,000.00
18,750.00
17,000.00
4,475,750.00

483,000.00
1,665,000.00
198,000.00
39,000.00
2,385,000.00
6,860,750.00

311,760.00
5,100.00
316,860.00

64,400.00
222,000.00
26,400.00
5,200.00
318,000.00
634,860.00

831,360.00
8,500.00
839,860.00

80,500.00
277,500.00
33,000.00
6,500.00
397,500.00
1,237,360.00

10,900.00
10,900.00
805.00
9,250.00
1,100.00
65.00
11,220.00
22,120.00

22,200.00
22,200.00

1,207.50
13,875.00
1,650.00
97.50
16,830.00
39,030.00

190,000.00
190,000.00

1,610.00
18,500.00
2,200.00
130.00
22,440.00
212,440.00

13,500.00
13,500.00

1,207.50
13,875.00
1,650.00
97.500
16,830.00
30,330.00
13,500.00
13,500.00

1,207.50
13,875.00
1,650.00
97.500
16,830.00
30,330.00

14,905,000.00
240,000.00
112,000.00
15,257,000.00

322,000.00
1,110,000.00
132,000.00
26,000.00
1,590,000.00
16,847,000.00

86,100.00
12,000.00
98,100.00

6,762.00
11,562.50
1,430.00
520.00
20,274.50
118,374.50

14,905,000.00
240,000.0
60,000.00
15,205,000.00
193,200.00
666,000.00
79,200.00
15,600.00
954,000.00
16,159,000.00

4,060.00
2,250.00
104,250.00
110,560.00

3,381.00
11,655.00
546.00
15,582.00
126,142.00

50,000.00
50,000.00

12,075.00
6,937.50
880.00
1,040.00
20,932.50
70,932.50

30,800.00
12,000.00
8,800.00
51,600.00

32,200.00
18,500.00
2,200.00
260.00
53,160.00
104,760.00
140,292.00
1,650.00
141,942.00

8,050.00
18,500.00
2,200.00
650.00
29,400.00
171,342.00

155,880.00
2,475.00
158,355.00

8,050.00
9,250.00
1,100.00
650.00
19,050.00
177,405.00

42,224.00
220.00
42,444.00

8,050.00
4,625.00
550.00
650.00
13,875.00
56,319.00

5,250.00
160.00
5,410.00
4,025.00
4,625.00
550.00
390.00
9,590.00
15,000.00

807,160.00
15,000.00
12,375.00
3,750.00
838,285.00

20,930.00
12,025.00
1,430.00
1,690.00
36,075.00
874,360.00

1,855,000.00
15,600.00
12,375.00
1,882,975.00

21,735.00
14,175.00
1,540.00
1,820.00
39,270.00
1,922,245.00

54,000.00
54,000.00
12,075.00
1,950.00
14,025.00
68,025.00

15,000.00
100.00
15,100.00

805.00
9,250.00
1,100.00
650.00
11,805.00
26,905.00

24,000.00
770,000.00
794,000.00

2,898.00
5,550.00
660.00
260.00
9,368.00
803,368.00

6,520.50
12,487.50
1,485.00
520.00
21,013.00

370,800.00
770,000.00
382,850.00
403,863.00
6,520.50
12,487.50
1,485.00
520.00
21,013.00

534,000.00
350,000.00
884,000.00
905,013.00

805.00
9,250.00
1,100.00
650.00
11,805.00

38,000.00
38,000.00
49,805.00

1,250,000.00
1,253,000.00
2,503,000.00

265,650.00
101,750.00
1,100.00
20,800.00
389,300.00
2,892,300.00

3,000.00
4,150.00
85,800.00
92,950.00
1,610.00
5,827.50
693.00
325.00
8,455.50
101,405.50

16,100.00
13,875.00
7,055.00
85,800.00
122,830.00

5,635.00
832.50
660.00
325.00
7,452.50
130,282.50

30,000.00
120,000.00
9,000.00
8,800.00
60,000.00
28,800.00
3,000.00
38,000.00
15,000.00
312,600.00

286,300.00
598,900.00

JUMLAH TOTAL HARGA 79,296,705.83


NO NAMA BARANG SATUAN HARGA BARANG
1 Balok kayu kamper 8/12 M' 375,000.00
2 Bata merah 5 x 11 x 22 cm BH 1,750.00
3 Batu belah 15/20 cm M3 200,000.00
4 Baut ø 12 - 20 cm M' 8,000.00
5 Besi beton polos Kg 25,000.00
6 Besi strip Kg 16,000.00
7 beton bertulang 1 pc : 2 ps : 3 kr Kg 455,000.00
8 CalcyBoard Lbr 116,000.00
9 Cat dasar (Propan) Kg 41,500.00
10 Cat meni kayu (Cap Pedang) Kg 38,000.00
11 Cat penutup 2 kali kg 330,000.00
12 Dolken Ø -8 cm/ 4 m Btg 37,400.00
13 Engsel jendela (GRT) Bh 10,900.00
14 Engsel pintu (GRT) Bh 22,200.00
15 Fitting Bh 15,000.00
16 Floor Drain UNIT 38,000.00
17 Genteng bubung sokka UNIT 7,700.00
18 Genteng Sokka besar Bh 2,000.00
19 Ijuk IKAT 9,000.00
20 Kabel M 5,000.00
21 Kait angin M 13,500.00
22 Kawat beton Kg 20,000.00
23 kayu balok (meranti) Kg 6,600,000.00
24 Kayu bangkirai, balok IKAT 13,550,000.00
25 Kayu kamfer, papan Kg 12,990,000.00
26 Kayu kamper, balok Kg 3,700,000.00
27 Kayu meranti Kg 120,000.00
28 Kayu meranti 5/7 M3 40,000.00
29 Kayu papan 3/20 ( sengon ) M3 1,300,000.00
30 Kayu terentang ( kayu tahun ) M3 4,500,000.00
31 Klem M3 1,200.00
32 Kloset duduk UNIT 1,250,000.00
33 Koral beton UNIT 290,000.00
34 Kran air Bh 15,000.00
35 Kunci selot Bh 190,000.00
36 L Bow Bh 2,200.00
37 Las Dop Bh 20,000.00
38 Lem kayu Bh 17,000.00
39 List kayu profil 5x5 cm M1 5,000.00
40 Minyak bekisting Lt 15,000.00
41 Mongkok Lt 3,000.00
42 Nok stel gelombang Lbr 42,000.00
43 Paku M3 15,000.00
44 Paku 7 cm - 12 cm M1 16,000.00
45 Paku biasa 12 cm Kg 20,000.00
46 Paku biasa 2" - 5" Kg 16,500.00
47 Paku sekrup 3,5 '' Bh 2,000.00
48 pasang bekisiting untuk lantai M2 495,500.00
49 Pasir beton Lt 285,000.00
50 Pasir pasang M2 275,000.00
51 Pasir urug M2 195,000.00
52 pipa PVC 1/2” (Rucika) M1 20,000.00
53 Pipa listrik 5/8" (Rucika) Btg 10,000.00
54 Pipa PVC 3” (Rucika) M1 309,000.00
55 Pipa PVC 4” (Rucika) M1 445,000.00
56 Plamir kayu (Propan) Kg 37,000.00
57 plamir tembok Kg 30,000.00
58 Playwood 9 mm lbr 170,000.00
59 Saklar lbr 38,000.00
60 Seal tape M3 5,000.00
61 Semen portland KG 1,500.00
62 Semen warna Kg 12,500.00
63 T Dus Bh 3,000.00
64 Ubin abu-abu 20x20 cm M2 70,000.00
65 Ubin warna 30x30 cm M2 68,000.00

NO TENAGA SATUAN UPAH


1 Kepala tukang OH 110,000.00
2 Kepala tukang batu OH 105,000.00
3 Kepala tukang kayu OH 105,000.00
4 Kepala tukang listrik OH 105,000.00
5 Mandor OH 130,000.00
6 Pekerja OH 80,500.00
7 Pembatu tukang listrik OH 70,000.00
8 Tukang batu OH 92,500.00
9 Tukang Besi OH 92,500.00
10 Tukang cat OH 92,500.00
11 Tukang kayu OH 92,500.00
12 Tukang Listrik OH 92,500.00
NO NAMA PEKERJAAN SATUAN PANJANG LEBAR TINGGI
A Pekerjaan Persiapan
1 Meratakan dan Membersihakn lokasi M2 17 8
2 Membuat kantor sementara / direksi kit M2 6 3
3 Membuat sumur Units
4 Pengukuran dan Pemasangan bowplank M' 17 8

B PEKERJAAN PONDASI
Galian taah pondasi tepi M3 39 0.5 1.1
1
Galian tanah pondasi tengah M3 24 0.8 1.1
Urugan pasir pondasi tepi M3 39 0.5 0.1
2
Urugan pasir pondasi tengah M3 24 0.8 0.1
Pasangan batu kosong pondasi tepi M3 39 0.5 0.2
3
Pasangan batu kosong pondasi tengah M3 24 0.8 0.2
Pasangan batu belah pondasi tepi M3 39 0.65 0.8
4
Pasangan batu belah pondasi tengah M3 24 0.9 0.8
5 Urugan tanah kembali M3 1/4 x galian

C PEKERJAAN BETON BERTULANG


1 Sloof M3 73 0.15 0.2
Kolom T130 M3 0.15 0.15 1.3
Kolom T 215 M3 0.15 0.15 2.15
2 Kolom T270 M3 0.15 0.15 2.7
Kolom T315 M3 0.15 0.15 3.15
Kolom T360 M3 0.15 0.15 6.3
3 Ring balk M3 6 0.15 0.15
Rabat beton carport M3 5 3 0.05
4 Rabat beton dalam rumah M3 6 6 0.05
Rabat beton teras rumah M3 3 1 0.05
Rabat beton teras belakang M3 6 1 0.05
5 Plat beton P600 M3 6 1.4 0.1
Plat beton P340 M3 3.4 1.4 0.1

D PEKERJAAN PASANGAN DAN PLESTERAN


Pasangan batu bata trasram t30 M2 29.8 0.3
1
Pasangan batu bata trasram t90 M2 5.3 0.9
2 Pasangan batu bata M2 36 3.15
3 Plesteran M2 2 x luas dinding
4 Acian M2 2 x luas dinding
5 Plesteran skoning M2 2 x luas dinding
6 Lantai ubin 30 x30 cm M2 6 1
7 Lantai ubin 20 x 20 cm M2 1.5 1.5

E PEKERJAAN PINTU DAN JENDELA


Kusen pintu
1 Pintu P1 M3 2.06 0.92 0.12
Pintu P2 M3 2.06 0.92 0.12
Kusen jendela
2 Jendela J1 M3 1.48 1.76 0.12
Jendela J2 M3 1.48 1.26 0.12
Panel pintu
3 Pintu P1 M2 2 0.8
Pintu P2 M2 2 0.7
Jendela kaca
4 Jendela J1 M3 0.65 1.64
Jendela J2 M3 0.65 1.14
5 Bovenlight M3 0.72 0.62 0.12
Bovenlight M2 0.6 0.5

F PEKERJAAN KUNCI DAN KACA


1 Engsel pintu BH 3 buah engsel
2 Engsel jendela BH 2 buah engsel
3 Kunci selot BH
4 Grendel BH
5 Kait angin BH
6 Kusen pintu M3 0.12 0.06 4.92
7 Kusen jendela M3 0.12 0.06 7.88

G PEKERJAAN ATAP
1 Kontruksi kuda kuda kayu bangkirai M3 0.08 0.12 15
2 Kontruksi gordng kayu bingkarai M3 6 0.08 0.12
3 Atap nok seng M3 6 0.08 0.12
4 Atap genting soka M3 6 4.5
5 Genteng bubung sokka M3 6
6 Lisplank M3 6

H PEKERJAAN LANGIT LANGIT


1 Langit caclyboard M2 1 1 3.5
2 List langit kayu profil M' 42

I PEKERJAAN ELEKTRIKAL
1 Lampu BH
2 Stop kontak BH
3 Saklar tunggal BH
4 Saklar ganda BH

J PEKERJAAN SANITASI DAN DRAINASE


1 Kran Units
2 Kloset jongkok BH
3 Floordrain BH 1

K PEKERJAAN PENGECATAN
Luas dinding interior M2 48 3.15
Luas dinding eksterior M2 24 3.15
Luas pagar depan M2 20 1.3
Luas pagar belakang M2 28 2.15
QTY JUMLAH JUMLAH TOTAL

136.000
18.000
1.000
2 50.000
205.000

1 21.450
1 21.120 42.570
1 1.950
1 1.920 3.870
1 3.900
1 3.840 7.740
1 10.140
1 8.640 18.780
2.160
72.960

1 2.190
5 0.146
3 0.145
4 0.243
10 0.709
2 0.284 1.527
3 0.405
1 0.750
1 1.800
1 0.150
1 0.300 3.405
1 0.840
1 0.476 1.316
6.248

1 8.940
1 4.770 13.710
113.400
0.567
0.290
3.600
6.000
2.250
139.817

4 0.910
1 0.227 1.137

1 0.313
2 0.448 0.760

4 6.400
1 1.400 7.800

2 2.132
4 2.964 5.096
1 0.054
1 0.300
14.793

5 15.000
3 6.000
6 9.000
6 12.000
3 3.000
4 0.142
1 0.057
45.198

1 0.144
2 0.115
0.058
2 21.000
1 6.000
2 12.000
39.317

45 157.500
1 42.000
199.500
7 7.000
4 4.000
3 3.000
2 2.000
16.000

1 1.000
2 2.000
1.000
4.000

151.200
75.600 226.800
26.000
60.200 86.200

TOTAL 1163.544
RENCANA ANGGARAN BIAYA (RAB)
PEMBANGNAN TEMPAT TINGGAL TYPE 36

VOLUME
NO ITEM PEKERJAAN SAT
(a)
I PEKERJAAN PERSIAPAN
1 Pengukuran dan pemasangan bowplank M' 50.000
2 Direksi kit M2 18.000
3 Meratakan dan membersihkan lokasi M 136.000
4 Membuat sumur Units 1.000

II PEKERJAANN PONDASI
1 Galian tanah M3 42.570
2 Urugan pasir M3 3.870
3 Pasangan batu kosong M3 7.740
4 Pasangan batu belah M3 18.780
5 Urugan tanah kembali M3 2.160

III PEKERJAAN BETON BERTULANG


1 Membuat sloof beton bertulang M3 2.190
2 Membuat kolom beton bertulang M3 1.527
3 Membuat balok beton bertulang M3 3.405
4 Membuat ring balok beton bertulang M3 0.405

IV PEKERJAAN DINDING
1 Pasangan batu bata merah 1/2 bata 1 pc : 3 pp M3 13.710

V PEKERJAAN PLESTERAN
1 Plesteran M2 0.567
2 Acian M2 0.290
3 Plesteran skoning M' 3.600
4 Pasang lantai ubin warna uk 30 x 30 cm M2 6.000

VI PEKERJAAN ATAP
1 Pasang kontruksi kuda kuda kayu bangkirai M3 0.144
2 Pasang kontruksi gording kayu bangkirai M3 0.115
3 Pasang atap nok M' 0.058
4 Pasang atap genting sokka M2 21.000
5 Pasang genteng bubung sokka M1 6.000
6 Pasang lisplank uk (3 x 20) cm, kayu kamper M1 12.000

VII PEKERJAAN PINTU DAN JENDELA


1 Pasang kusen dan jendela kayu kamper M3 1.137
2 Pasang engsel jendela (engsel kuningan kecil) BH 6.000
3 Pasang kunci selot BH 9.000
4 Pasang grendel BH 12.000
5 Pasang kait angin BH 3.000

VIII PEKERJAAN LANGIT LANGIT


1 Pasang langit langit calcyboard M2 157.500
2 Pasang list langit langit kayu profil M' 42.000

IX PEKERJAAN ELEKTRIKAL
1 Pemasangan titik buah lampu BH 7.000
2 Stop kontak BH 4.000
3 Saklar tunggal BH 3.000
4 Saklar ganda BH 2.000

X PEKERJAAN SANITASI DAN DRAINASE


1 Memasang 1 buah kloset duduk porselen BH 2.000
2 Memasang 1 buah kran diameter 3/4" atau 1/2" BH 1.000
3 Pemasangan 1 buah floor drain BH 1.000

XI PEKERJAAN PENGECATAN
1 Pengecatan luas dinding interior dan eksterior M2 226.800
2 Pengecatan pagar belakang dan pagar depan M2 86.200
GGARAN BIAYA (RAB)
MPAT TINGGAL TYPE 36

HARGA SATUAN JUMLAH HARGA TOTAL BIAYA


(b) (Rp) (axb) (Rp) (Rp)

28,960.00 1,448,000.00
1,000.00 18,000.00
1,000.00 136,000.00
1,000.00 1,000.00
1,603,000.00

63,625.00 2,708,516.25
21,208.33 82,076.25 3,351,004.50
432,465.00 3,347,279.10
801,725.00 15,056,395.50 18,403,674.60
259,450.00 560,412.00
21,754,679.10

6,889,770.00 15,088,596.30
9,557,232.50 14,590,310.07
143,041.00 487,054.61
143,041.00 57,931.60
30,223,892.58

392,350.00 5,379,118.50
5,379,118.50

56,551.00 32,064.42
32,625.00 9,461.25
19,385.00 69,786.00
874,360.00 5,246,160.00
5,357,471.67

16,847,000.00 2,425,968.00
16,159,000.00 1,861,516.80
118,374.50 6,818.37
70,932.50 1,489,582.50
104,760.00 628,560.00
171,342.00 2,056,104.00
8,468,549.67

6,860,750.00 7,800,672.75
22,120.00 132,720.00
212,440.00 1,911,960.00
30,330.00 363,960.00
30,330.00 90,990.00
10,300,302.75

56,319.00 8,870,242.50
15,000.00 630,000.00
9,500,242.50

598,900.00 4,192,300.00
38,000.00 152,000.00
38,000.00 114,000.00
38,000.00 76,000.00
4,534,300.00

2,892,300.00 5,784,600.00
26,905.00 26,905.00
49,805.00 49,805.00
5,861,310.00

101,405.50 22,998,767.40
130,282.50 11,230,351.50
34,229,118.90

JUMLAH TOTAL 158,966,664.76


Analisa Biaya Konstruksi (ABK) Bangunan Gedung dan Perumahan
Tahun 2023
Rumah Tinggal sederhana
Kode
No Uraian Pekerjaan
Analisis
1 2 3
A PEKERJAAN PENDAHULUAN
1 Pekerjaan Persiapan
Membersihkan Dan Meratakan Lahan / m2 An 01 SNI
Pekerja
Mandor

2 1 m' Pengukuran dan pemasangan bouwplank 6.4


Bahan
Kayu meranti 5/7
Paku biasa 2" - 5"
Kayu papan 3/20 ( sengon )

Tenaga
Tukang kayu
Pekerja
Kepala tukang
Mandor

B Pekerjaan Tanah
1 1 m3 Galian tanah biasa sedalam 1 meter
Tenaga
Pekerja
Mandor

2 1 m3 Urugan kembali
Tenaga
Pekerja
Mandor

C Pekerjaan Pondasi
1 1 m3 Pasang pondasi batu kosong (aanstamping)
Bahan
Batu belah 15/20 cm
Pasir urug

Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

2 1 m3 Pasang pondasi batu belah 1 Pc : 5 PP


Bahan
Batu belah 15/20 cm
Semen portland
Pasir pasang

Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

3 1 m3 Urugan pasir
Bahan
Pasir Urug

Tenaga
Pekerja
Mandor

D Pekerjaan Beton
1 1 m3 Membuat Sloof beton bertulang ( 150 Kg besi + Bekisting )
Bahan
Kayu terentang ( kayu tahun )
Paku Biasa 2'' - 5''
Minyak bekisting
Besi beton polos
Kawat beton
semen Portland
Pasir beton
Koral beton
Tenaga
Pekerja
Tukang batu
Tukang kayu
Tukang Besi
Kepala tukang
Mandor

2 1 m3 Membuat Kolom beton bertulang ( 150 Kg besi + Bekisting )


Bahan
Kayu terentang (tahun)
Paku Biasa 2'' - 5''
Minyak bekisting
Besi beton polos
Kawat beton
semen Portland
Pasir beton
Koral beton
kayu balok (meranti)
Playwood 9 mm
Dolken Ø -8 cm/ 4 m

Tenaga
Pekerja
Tukang batu
Tukang kayu
Tukang Besi
Kepala tukang
Mandor

3 1 m' Membuat ring balok beton bertulang ( 10 x 15 ) cm


Bahan
Kayu meranti
Paku Biasa 2'' - 5''
Besi beton polos
Kawat beton
semen Portland
Pasir beton
Koral beton

Tenaga
Pekerja
Tukang batu
Tukang kayu
Tukang Besi
Kepala tukang
Mandor

4 1 M3 Beton Tumbuk,1 Pc : 3Ps: 5kr


Bahan
semen portland
pasir beton
koral beton

Tenaga
pekerja
Tukang batu
Kepala tukang
Mandor

5 1 m3 plat lantai Tb 10 cm beton bertulang (90 kg +bekisting )


Bahan
beton bertulang 1 pc : 2 ps : 3 kr
pasang bekisiting untuk lantai
besi beton polos

Tenaga
Pekerja
Tukang besi
Tukang kayu
Kepala tukang
Mandor

E Pekerjaan Pasangan Dan Plesteran


1 1 m2 Pasangan bata merah tebal 1 bata 1 Pc : 3 PP
Bahan
Bata merah 5 x 11 x 22 cm
Semen portland
Pasir pasang

Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor
2 1 m2 Plesteran 1 Pc : 5 Ps, tebal : 15 mm
Bahan
semen portland
Pasir pasang

Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

3 1 m' Plesteran skoning 1 Pc : 2 Ps, lebar 10 mm


Bahan
semen Portland
Pasir pasang

Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

4 1 m2 acian
Bahan
Semen Portland

Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor
Koefisien Satuan Harga Satuan Rp Jumlah Harga Rp Rekapitulasi Rp

4 5 6 7 8

0.1 Oh Rp 80,500.00 Rp 4,000.00


0.05 Oh Rp 130,000.00 Rp 3,000.00
JUMLAH Rp 7,000.00

0.012 M3 Rp 40,000.00 Rp 480.00


0.020 Kg Rp 16,500.00 Rp 330.00
0.007 M3 Rp 1,300,000.00 Rp 9,100.00
JUMLAH Rp 9,910.00

0.100 Oh Rp 92,500.00 Rp 9,250.00


0.100 Oh Rp 80,500.00 Rp 8,050.00
0.010 Oh Rp 110,000.00 Rp 1,100.00
0.005 Oh Rp 130,000.00 Rp 650.00
JUMLAH Rp 19,050.00
Rp 28,960.00

0.750 Oh Rp 80,500.00 Rp 60,375.00


0.025 Oh Rp 130,000.00 Rp 3,250.00
JUMLAH Rp 63,625.00
Rp 63,625.00

0.2500 Oh Rp 80,500.00 Rp 20,125.00


0.0083 Oh Rp 130,000.00 Rp 1,083.33
JUMLAH Rp 21,208.33
Rp 21,208.33
1.200 M3 Rp 200,000.00 Rp 240,000.00
0.432 M3 Rp 195,000.00 Rp 84,240.00
JUMLAH Rp 324,240.00

0.780 Oh Rp 80,500.00 Rp 62,790.00


0.390 Oh Rp 92,500.00 Rp 36,075.00
0.039 Oh Rp 110,000.00 Rp 4,290.00
0.039 Oh Rp 130,000.00 Rp 5,070.00
JUMLAH Rp 108,225.00
Rp 432,465.00

1.200 M3 Rp 200,000.00 Rp 240,000.00


136.000 Kg Rp 1,500.00 Rp 204,000.00
0.544 M3 Rp 275,000.00 Rp 149,600.00
JUMLAH Rp 593,600.00

1.500 Oh Rp 80,500.00 Rp 120,750.00


0.750 Oh Rp 92,500.00 Rp 69,375.00
0.075 Oh Rp 110,000.00 Rp 8,250.00
0.075 Oh Rp 130,000.00 Rp 9,750.00
JUMLAH Rp 208,125.00
Rp 801,725.00

1.200 M3 Rp 195,000.00 Rp 234,000.00


JUMLAH Rp 234,000.00

0.300 Oh Rp 80,500.00 Rp 24,150.00


0.010 Oh Rp 130,000.00 Rp 1,300.00
JUMLAH Rp 25,450.00
Rp 259,450.00

0.270 M3 Rp 4,500,000.00 Rp 1,215,000.00


2.000 Kg Rp 16,500.00 Rp 33,000.00
0.600 Lt Rp 15,000.00 Rp 9,000.00
157.500 Kg Rp 25,000.00 Rp 3,937,500.00
2.250 Kg Rp 20,000.00 Rp 45,000.00
336.000 Kg Rp 1,500.00 Rp 504,000.00
0.540 M3 Rp 285,000.00 Rp 153,900.00
0.810 M3 Rp 290,000.00 Rp 234,900.00
Jumlah Rp 6,132,300.00
5.300 Oh Rp 80,500.00 Rp 426,650.00
0.275 Oh Rp 95,000.00 Rp 26,125.00
1.560 Oh Rp 92,500.00 Rp 144,300.00
1.050 Oh Rp 92,500.00 Rp 97,125.00
0.262 Oh Rp 110,000.00 Rp 28,820.00
0.265 Oh Rp 130,000.00 Rp 34,450.00
Jumlah Rp 757,470.00
Rp 6,889,770.00

0.320 M3 Rp 4,500,000.00 Rp 1,440,000.00


3.200 Kg Rp 16,500.00 Rp 52,800.00
1.600 Lt Rp 15,000.00 Rp 24,000.00
157.500 Kg Rp 25,000.00 Rp 3,937,500.00
2.250 Kg Rp 20,000.00 Rp 45,000.00
336.000 Kg Rp 1,500.00 Rp 504,000.00
0.540 M3 Rp 285,000.00 Rp 153,900.00
0.810 M3 Rp 250,000.00 Rp 202,500.00
0.120 M3 Rp 6,600,000.00 Rp 792,000.00
2.800 Lbr Rp 170,000.00 Rp 476,000.00
32.000 Btg Rp 37,400.00 Rp 1,196,800.00
Jumlah Rp 8,824,500.00

5.300 Oh Rp 80,500.00 Rp 426,650.00


0.275 Oh Rp 92,500.00 Rp 25,437.50
1.300 Oh Rp 92,500.00 Rp 120,250.00
1.050 Oh Rp 92,500.00 Rp 97,125.00
0.262 Oh Rp 110,000.00 Rp 28,820.00
0.265 Oh Rp 130,000.00 Rp 34,450.00
JUMLAH Rp 732,732.50
Rp 9,557,232.50

0.003 M3 Rp 120,000.00 Rp 360.00


0.020 Kg Rp 20,000.00 Rp 400.00
3.600 Kg Rp 25,000.00 Rp 90,000.00
0.050 Kg Rp 20,000.00 Rp 1,000.00
5.500 Kg Rp 1,500.00 Rp 8,250.00
0.009 M3 Rp 285,000.00 Rp 2,565.00
0.015 M3 Rp 290,000.00 Rp 4,350.00
Jumlah Rp 106,925.00

0.297 Oh Rp 80,500.00 Rp 23,908.50


0.033 Oh Rp 92,500.00 Rp 3,052.50
0.033 Oh Rp 92,500.00 Rp 3,052.50
0.033 Oh Rp 92,500.00 Rp 3,052.50
0.010 Oh Rp 110,000.00 Rp 1,100.00
0.015 Oh Rp 130,000.00 Rp 1,950.00
JUMLAH Rp 36,116.00
Rp 143,041.00

218.000 Kg Rp 1,500.00 Rp 327,000.00


0.520 M3 Rp 285,000.00 Rp 148,200.00
0.870 M3 Rp 290,000.00 Rp 252,300.00
JUMLAH Rp 727,500.00

1.650 Oh Rp 80,500.00 Rp 132,825.00


0.250 Oh Rp 92,500.00 Rp 23,125.00
0.025 Oh Rp 110,000.00 Rp 2,750.00
0.080 Oh Rp 130,000.00 Rp 10,400.00
JUMLAH Rp 169,100.00
Rp 896,600.00

1.000 M3 Rp 455,000.00 Rp 455,000.00


10.000 M2 Rp 495,500.00 Rp 4,955,000.00
90.000 Kg Rp 25,000.00 Rp 2,250,000.00
JUMLAH Rp 7,660,000.00

2.667 Oh Rp 80,500.00 Rp 214,693.50


0.875 Oh Rp 92,500.00 Rp 80,937.50
0.330 Oh Rp 95,000.00 Rp 31,350.00
0.068 Oh Rp 110,000.00 Rp 7,480.00
0.133 Oh Rp 130,000.00 Rp 17,290.00
JUMLAH Rp 351,751.00
Rp 8,011,751.00

140.000 Bh Rp 1,750.00 Rp 245,000.00


32.950 Kg Rp 1,500.00 Rp 49,425.00
0.091 M3 Rp 275,000.00 Rp 25,025.00
JUMLAH Rp 319,450.00

0.600 Oh Rp 80,500.00 Rp 48,300.00


0.200 Oh Rp 92,500.00 Rp 18,500.00
0.020 Oh Rp 110,000.00 Rp 2,200.00
0.030 Oh Rp 130,000.00 Rp 3,900.00
JUMLAH Rp 72,900.00
Rp 392,350.00

5.184 Kg Rp 1,500.00 Rp 7,776.00


0.026 M3 Rp 275,000.00 Rp 7,150.00
JUMLAH Rp 14,926.00

0.300 Oh Rp 80,500.00 Rp 24,150.00


0.150 Oh Rp 92,500.00 Rp 13,875.00
0.015 Oh Rp 110,000.00 Rp 1,650.00
0.015 Oh Rp 130,000.00 Rp 1,950.00
JUMLAH Rp 41,625.00
Rp 56,551.00

0.500 Kg Rp 1,500.00 Rp 750.00


0.013 M3 Rp 275,000.00 Rp 3,575.00
JUMLAH Rp 4,325.00

0.080 Oh Rp 80,500.00 Rp 6,440.00


0.040 Oh Rp 92,500.00 Rp 3,700.00
0.040 Oh Rp 110,000.00 Rp 4,400.00
0.004 Oh Rp 130,000.00 Rp 520.00
JUMLAH Rp 15,060.00
Rp 19,385.00

3.250 Kg Rp 1,500.00 Rp 4,875.00


JUMLAH Rp 4,875.00

0.200 Oh Rp 80,500.00 Rp 16,100.00


0.100 Oh Rp 92,500.00 Rp 9,250.00
0.010 Oh Rp 110,000.00 Rp 1,100.00
0.010 Oh Rp 130,000.00 Rp 1,300.00
JUMLAH Rp 27,750.00
Rp 32,625.00