DAFTAR ANALISA

ANALISA URAIAN PEKERJAAN HARGA SATUAN UPAH BAHAN JUMLAH

SNI 01.1.5 1 M2 Pembersihan Lapangan


0.0050 Mandor @ Rp. 87,500.00 Rp. 437.50
0.0500 Kepala tukang @ Rp. 85,000.00 Rp. 4,250.00
0.0500 Tukang kayu @ Rp. 70,000.00 Rp. 3,500.00
0.0500 Pembantu tukang @ Rp. 50,000.00 Rp. 2,500.00
Rp. 10,687.50 Rp. 0.00 Rp. 10,687.50

SNI 01.1.6 1 M' Pengukuran dan pasang bouwplank


0.0050 Mandor @ Rp. 87,500.00 Rp. 437.50
0.0050 Kepala tukang kayu @ Rp. 85,000.00 Rp. 425.00
0.0500 Tukang kayu @ Rp. 70,000.00 Rp. 3,500.00
0.0500 Pembantu tukang kayu @ Rp. 50,000.00 Rp. 2,500.00
0.0040 M3 Kayu klas III @ Rp. 1,000,000.00 4,000.00 Rp. 4,000.00
0.0040 M3 Papan bouwplank @ Rp. 1,250,000.00 Rp. 5,000.00
0.0200 Kg Paku kayu @ Rp. 18,500.00 Rp. 370.00
Rp. 10,862.50 Rp. 9,370.00 Rp. 20,232.50

SNI 01.1.12 1 M2 Pembuatan Jalan Sementara


0.0050 Mandor @ Rp. 87,500.00 Rp. 437.50
1.0000 Pekerja @ Rp. 50,000.00 Rp. 50,000.00
0.0100 M3 Pasir Pasang @ Rp. 125,000.00 Rp. 1,250.00
0.0900 M3 Batu Pecah 5 / 7 @ Rp. 473,437.50 Rp. 42,609.38
0.1500 M3 Batu Belah 15 / 20 @ Rp. 441,875.00 Rp. 66,281.25
Rp. 50,437.50 Rp. 110,140.63 Rp. 160,578.13

SNI 01.2.1 1 M3 Galian tanah biasa sedalam 1 m'


0.0400 Mandor @ Rp. 87,500.00 Rp. 3,500.00
0.4000 Tukang gali tanah @ Rp. 65,000.00 Rp. 26,000.00
Rp. 29,500.00 Rp. Rp. 29,500.00

SNI 01.2.2 1 M3 Galian tanah biasa sedalam 2 m'


0.0520 Mandor @ Rp. 87,500.00 Rp. 4,550.00
0.5260 Tukang gali tanah @ Rp. 65,000.00 Rp. 34,190.00
Rp. 38,740.00 Rp. Rp. 38,740.00

SNI 01.2.9 1 M3 Urugan kembali


0.0190 Mandor @ Rp. 87,500.00 Rp. 1,662.50
0.1920 Tukang gali tanah @ Rp. 65,000.00 Rp. 12,480.00
Rp. 14,142.50 Rp. Rp. 14,142.50

SNI 01.2.15 1 M3 Urugan pasir terhitung penyiraman


0.0250 Mandor @ Rp. 87,500.00 Rp. 2,187.50
0.2500 Pembantu tukang batu @ Rp. 50,000.00 Rp. 12,500.00
1.2000 M3 Pasir urug @ Rp. 57,375.00 Rp. 68,850.00
Rp. 14,687.50 Rp. 68,850.00 Rp. 83,537.50

SNI 01.2.15.a 1 M3 Timbunan tanah urug terhitung pemadatan


0.0250 Mandor @ Rp. 87,500.00 Rp. 2,187.50 Rp.
0.2500 Pembantu tukang batu @ Rp. 50,000.00 Rp. 12,500.00 Rp.
1.2000 M3 Tanah Subur @ Rp. 75,000.00 Rp. Rp. 90,000.00
1.2000 M3 Tanah urug @ Rp. 53,000.00 Rp. Rp. 63,600.00
Rp. 14,687.50 Rp. 63,600.00 Rp. 78,287.50
Tanah Subur Rp. 14,687.50 Rp. 90,000.00 Rp. 104,687.50
SNI 02.1.5 1 M3 Pasang pondasi batu belah adukan 1 Pc : 5 Ps
0.0150 Mandor @ Rp. 87,500.00 Rp. 1,312.50
0.0600 Kepala tukang batu @ Rp. 85,000.00 Rp. 5,100.00
0.6000 Tukang batu @ Rp. 70,000.00 Rp. 42,000.00
1.5000 Pembantu tukang batu @ Rp. 50,000.00 Rp. 75,000.00
1.2000 M3 Batu belah @ Rp. 441,875.00 Rp. 530,250.00
2.7000 Zak Semen PC 40 Kg ( Gresik ) @ Rp. 55,000.00 Rp. 148,500.00
0.4300 M3 Pasir pasang @ Rp. 125,000.00 Rp. 53,750.00
Rp. 123,412.50 Rp. 732,500.00 Rp. 855,912.50

ANALISA URAIAN PEKERJAAN HARGA SATUAN UPAH BAHAN JUMLAH

SNI 02.1.13 1 M3 Pasang pondasi batu kosong tbl. 20 cm ( anstamping )


0.0780 Mandor @ Rp. 87,500.00 Rp. 6,825.00

Hal -1
0.0390 Kepala tukang batu @ Rp. 85,000.00 Rp. 3,315.00
0.3900 Tukang batu @ Rp. 70,000.00 Rp. 27,300.00
0.7810 Pembantu tukang batu @ Rp. 50,000.00 Rp. 39,050.00
1.2000 M3 Batu belah @ Rp. 441,875.00 Rp. 530,250.00
Rp. 76,490.00 Rp. 530,250.00 Rp. 606,740.00

SNI 03.3.2 1 M² Plesteran tbl. 15 mm camp 1 Pc : 2 Ps


0.0040 Mandor @ Rp. 87,500.00 Rp. 350.00
0.0020 Kepala tukang batu @ Rp. 85,000.00 Rp. 170.00
0.0200 Tukang batu @ Rp. 70,000.00 Rp. 1,400.00
0.0400 Pembantu tukang batu @ Rp. 50,000.00 Rp. 2,000.00
0.2130 Zak Semen PC 40 Kg ( Gresik ) @ Rp. 55,000.00 Rp. 11,715.00
0.0170 M3 Pasir pasang @ Rp. 125,000.00 Rp. 2,125.00
Rp. 3,920.00 Rp. 13,840.00 Rp. 17,760.00

SNI 03.3.4 1 M² Plesteran tbl. 15 mm camp 1 Pc : 4 Ps


0.0040 Mandor @ Rp. 87,500.00 Rp. 350.00
0.0020 Kepala tukang batu @ Rp. 85,000.00 Rp. 170.00
0.0200 Tukang batu @ Rp. 70,000.00 Rp. 1,400.00
0.0400 Pembantu tukang batu @ Rp. 50,000.00 Rp. 2,000.00
0.1300 Zak Semen PC 40 Kg ( Gresik ) @ Rp. 55,000.00 Rp. 7,150.00
0.0200 M3 Pasir pasang @ Rp. 125,000.00 Rp. 2,500.00
Rp. 3,920.00 Rp. 9,650.00 Rp. 13,570.00

F.8 10 M2 Pekerjaan bekisting


0.1000 Mandor @ Rp. 87,500.00 Rp. 8,750.00
0.5000 Kepala tukang kayu @ Rp. 85,000.00 Rp. 42,500.00
5.0000 Tukang kayu @ Rp. 70,000.00 Rp. 350,000.00
2.0000 Pembantu tukang kayu @ Rp. 50,000.00 Rp. 100,000.00
0.4000 M3 Papan bekisting @ Rp. 1,650,000.00 Rp. 660,000.00
4.0000 Kg. Paku kayu @ Rp. 18,500.00 Rp. 74,000.00
Rp. 501,250.00 Rp. 734,000.00 Rp. 1,235,250.00

G.41 1 M3 Pekerjaan spesi 1 Pc : 2 Ps : 3 Krl


0.3000 Mandor @ Rp. 87,500.00 Rp. 26,250.00
0.1000 Kepala tukang batu @ Rp. 85,000.00 Rp. 8,500.00
1.0000 Tukang batu @ Rp. 70,000.00 Rp. 70,000.00
6.0000 Pembantu tukang batu @ Rp. 50,000.00 Rp. 300,000.00
0.8200 M3 Kerikil sungai @ Rp. 550,000.00 Rp. 451,000.00
6.8000 Zak Semen PC 40 Kg ( Gresik ) @ Rp. 55,000.00 Rp. 374,000.00
0.5400 M3 Pasir pasang @ Rp. 125,000.00 Rp. 67,500.00
Rp. 404,750.00 Rp. 892,500.00 Rp. 1,297,250.00

G.41.a 1 M3 Pekerjaan spesi 1 Pc : 2 Ps : 3 Krl dengan tulangan tunggal


0.3000 Mandor @ Rp. 87,500.00 Rp. 26,250.00
0.1000 Kepala tukang batu @ Rp. 85,000.00 Rp. 8,500.00
1.0000 Tukang batu @ Rp. 70,000.00 Rp. 70,000.00
6.0000 Pembantu tukang batu @ Rp. 50,000.00 Rp. 300,000.00
0.8200 M3 Kerikil sungai @ Rp. 550,000.00 Rp. 451,000.00
6.8000 Zak Semen PC 40 Kg ( Gresik ) @ Rp. 55,000.00 Rp. 374,000.00
0.5400 M3 Pasir pasang @ Rp. 125,000.00 Rp. 67,500.00
43.0000 Kg. Besi beton @ Rp. 16,750.00 Rp. 720,250.00
0.0460 Kawat Beton @ Rp. 17,500.00 Rp. 805.00
Ls Bekisting @ Rp. 5,500.00 Rp. 5,500.00
Rp. 404,750.00 Rp. 1,619,055.00 Rp. 2,023,805.00

G.67 1 M2 Pekerjaan spesi 1 Pc : 3 Ps : 4 Krl, tebal 5 Cm


0.0600 Mandor @ Rp. 87,500.00 Rp. 5,250.00
0.0020 Kepala tukang batu @ Rp. 85,000.00 Rp. 170.00
0.0200 Tukang batu @ Rp. 70,000.00 Rp. 1,400.00
1.1500 Pembantu tukang batu @ Rp. 50,000.00 Rp. 57,500.00
0.0440 M3 Kerikil sungai @ Rp. 550,000.00 Rp. 24,200.00
0.2100 Zak Semen PC 40 Kg ( Gresik ) @ Rp. 55,000.00 Rp. 11,550.00
0.5400 M3 Pasir pasang @ Rp. 125,000.00 Rp. 67,500.00
Rp. 64,320.00 Rp. 103,250.00 Rp. 167,570.00

ANALISA URAIAN PEKERJAAN HARGA SATUAN UPAH BAHAN JUMLAH

I.2 100 Kg. Pekerjaan besi


2.2500 Kepala tukang besi @ Rp. 85,000.00 Rp. 191,250.00
6.7500 Tukang besi @ Rp. 70,000.00 Rp. 472,500.00
6.7500 Pembantu tukang besi @ Rp. 50,000.00 Rp. 337,500.00
110.0000 Kg. Besi beton @ Rp. 16,750.00 Rp. 1,842,500.00

Hal -2
2.0000 Kg. Kawat beton @ Rp. 17,500.00 Rp. 35,000.00
Rp. 1,001,250.00 Rp. 1,877,500.00 Rp. 2,878,750.00
1 Kg Rp. 10,012.50 Rp. 18,775.00 Rp. 28,787.50
L.1 Pekerjaan menyiram dan membongkar bekisting
4.0000 Pembantu tukang @ Rp. 50,000.00 Rp. 200,000.00
Rp. 200,000.00 Rp. Rp. 200,000.00

F.1a 1 M2 Pekerjaan perancah


0.0250 Mandor @ Rp. 87,500.00 Rp. 2,187.50
0.1500 Kepala tukang kayu @ Rp. 85,000.00 Rp. 12,750.00
1.5000 Tukang kayu @ Rp. 70,000.00 Rp. 105,000.00
0.5000 Pembantu tukang kayu @ Rp. 50,000.00 Rp. 25,000.00
48.0000 M' Kayu bulat @ Rp. 3,125.00 Rp. 150,000.00
0.0100 M3 Papan untuk alas @ Rp. 1,650,000.00 Rp. 16,500.00
0.0060 M3 Kayu 5/7 cm ( Kls. III ) @ Rp. 1,000,000.00 Rp. 6,000.00
1.0000 Kg. Paku kayu @ Rp. 18,500.00 Rp. 18,500.00
Rp. 144,937.50 Rp. 191,000.00 Rp. 335,937.50
2 x sambung Rp. 671,875.00

G.44 1 M3 Beton camp. 1 Pc : 3 Ps : 6 Krl


0.3000 Mandor @ Rp. 87,500.00 Rp. 26,250.00
0.0500 Kepala tukang batu @ Rp. 85,000.00 Rp. 4,250.00
0.5000 Tukang batu @ Rp. 70,000.00 Rp. 35,000.00
6.0000 Pembantu tukang batu @ Rp. 50,000.00 Rp. 300,000.00
1.0160 M3 Kerikil sungai @ Rp. 550,000.00 Rp. 558,800.00
4.2400 Zak Semen PC 40 Kg ( Gresik ) @ Rp. 55,000.00 Rp. 233,200.00
0.5080 M3 Pasir beton @ Rp. 125,000.00 Rp. 63,500.00
Rp. 365,500.00 Rp. 855,500.00 Rp. 1,221,000.00

F.1 1 m3 Mengerjakan rangka bawah ulin


0.2500 Mandor @ Rp. 87,500.00 Rp. 21,875.00
0.7500 Kepala Tukang Kayu @ Rp. 85,000.00 Rp. 63,750.00
7.5000 Tukang Kayu @ Rp. 70,000.00 Rp. 525,000.00
5.0000 Pembantu Tukang Kayu @ Rp. 50,000.00 Rp. 250,000.00
1.1000 m3 balok ulin @ Rp. 4,000,000.00 4,400,000.00 Rp. 4,400,000.00
5.0000 kg paku ulin @ Rp. 22,500.00 Rp. 112,500.00
Rp. 5,260,625.00 Rp. 4,512,500.00 Rp. 9,773,125.00

F.38 1 m2 Mengerjakan lantai ulin 2 cm


0.4000 Pekerja @ Rp. 50,000.00 Rp. 20,000.00
0.0200 Mandor @ Rp. 87,500.00 Rp. 1,750.00
1.2500 Tukang Kayu @ Rp. 70,000.00 Rp. 87,500.00
0.1250 Kepala Tukang @ Rp. 85,000.00 Rp. 10,625.00
0.0200 m3 papan ulin @ Rp. 4,500,000.00 Rp. 90,000.00
0.2000 kg paku ulin @ Rp. 22,500.00 Rp. 4,500.00
Rp. 119,875.00 Rp. 94,500.00 Rp. 214,375.00

F.38a 1 m2 Mengerjakan lantai ulin 3 cm


0.4000 Pekerja @ Rp. 50,000.00 Rp. 20,000.00
0.0200 Mandor @ Rp. 87,500.00 Rp. 1,750.00
1.2500 Tukang Kayu @ Rp. 70,000.00 Rp. 87,500.00
0.1250 Kepala Tukang @ Rp. 85,000.00 Rp. 10,625.00
0.0300 m3 papan ulin @ Rp. 4,500,000.00 Rp. 135,000.00
0.2000 kg paku ulin @ Rp. 22,500.00 Rp. 4,500.00
Rp. 119,875.00 Rp. 139,500.00 Rp. 259,375.00

Hal -3
DAFTAR ANALISA
ANALISA URAIAN PEKERJAAN HARGA SATUAN UPAH BAHAN JUMLAH

SNI 01.1.5 1 M2 Pembersihan Lapangan


0.0050 Mandor @ Rp. 87,500.00 Rp. 437.50
0.0500 Kepala tukang @ Rp. 85,000.00 Rp. 4,250.00
0.0500 Tukang kayu @ Rp. 70,000.00 Rp. 3,500.00
0.0500 Pembantu tukang @ Rp. 50,000.00 Rp. 2,500.00
Rp. 10,687.50 Rp. 0.00 Rp. 10,687.50

SNI 01.1.6 1 M' Pengukuran dan pasang bouwplank


0.0050 Mandor @ Rp. 87,500.00 Rp. 437.50
0.0050 Kepala tukang kayu @ Rp. 85,000.00 Rp. 425.00
0.0500 Tukang kayu @ Rp. 70,000.00 Rp. 3,500.00
0.0500 Pembantu tukang kayu @ Rp. 50,000.00 Rp. 2,500.00
0.0040 M3 Kayu klas III @ Rp. 1,000,000.00 4,000.00 Rp. 4,000.00
0.0040 M3 Papan bouwplank @ Rp. 1,250,000.00 Rp. 5,000.00
0.0200 Kg Paku kayu @ Rp. 18,500.00 Rp. 370.00
Rp. 10,862.50 Rp. 9,370.00 Rp. 20,232.50

SNI 01.1.12 1 M2 Pembuatan Jalan Sementara


0.0050 Mandor @ Rp. 87,500.00 Rp. 437.50
1.0000 Pekerja @ Rp. 50,000.00 Rp. 50,000.00
0.0100 M3 Pasir Pasang @ Rp. 125,000.00 Rp. 1,250.00
0.0900 M3 Batu Pecah 5 / 7 @ Rp. 473,437.50 Rp. 42,609.38
0.1500 M3 Batu Belah 15 / 20 @ Rp. 441,875.00 Rp. 66,281.25
Rp. 50,437.50 Rp. 110,140.63 Rp. 160,578.13

SNI 01.2.1 1 M 3 Galian tanah biasa sedalam 1 m'


0.0400 Mandor @ Rp. 87,500.00 Rp. 3,500.00
0.4000 Tukang gali tanah @ Rp. 65,000.00 Rp. 26,000.00
Rp. 29,500.00 Rp. Rp. 29,500.00

SNI 01.2.2 1 M 3 Galian tanah biasa sedalam 2 m'


0.0520 Mandor @ Rp. 87,500.00 Rp. 4,550.00
0.5260 Tukang gali tanah @ Rp. 65,000.00 Rp. 34,190.00
Rp. 38,740.00 Rp. Rp. 38,740.00

SNI 01.2.9 1 M 3 Urugan kembali


0.0190 Mandor @ Rp. 87,500.00 Rp. 1,662.50
0.1920 Tukang gali tanah @ Rp. 65,000.00 Rp. 12,480.00
Rp. 14,142.50 Rp. Rp. 14,142.50

SNI 01.2.15 1 M 3 Urugan pasir terhitung penyiraman


0.0250 Mandor @ Rp. 87,500.00 Rp. 2,187.50
0.2500 Pembantu tukang batu @ Rp. 50,000.00 Rp. 12,500.00
1.2000 M3 Pasir urug @ Rp. 57,375.00 Rp. 68,850.00
Rp. 14,687.50 Rp. 68,850.00 Rp. 83,537.50

SNI 01.2.15.a 1 M 3 Timbunan tanah urug terhitung pemadatan


0.0250 Mandor @ Rp. 87,500.00 Rp. 2,187.50 Rp.
0.2500 Pembantu tukang batu @ Rp. 50,000.00 Rp. 12,500.00 Rp.
1.2000 M3 Tanah Subur @ Rp. 75,000.00 Rp. Rp. 90,000.00
1.2000 M3 Tanah urug @ Rp. 53,000.00 Rp. Rp. 63,600.00
Rp. 14,687.50 Rp. 63,600.00 Rp. 78,287.50
Tanah Subur Rp. 14,687.50 Rp. 90,000.00 Rp. 104,687.50
SNI 02.1.5 1 M 3 Pasang pondasi batu belah adukan 1 Pc : 5 Ps
0.0150 Mandor @ Rp. 87,500.00 Rp. 1,312.50
0.0600 Kepala tukang batu @ Rp. 85,000.00 Rp. 5,100.00
0.6000 Tukang batu @ Rp. 70,000.00 Rp. 42,000.00
1.5000 Pembantu tukang batu @ Rp. 50,000.00 Rp. 75,000.00
1.2000 M3 Batu belah @ Rp. 441,875.00 Rp. 530,250.00
2.7000 Zak Semen PC 40 Kg ( Gresik ) @ Rp. 55,000.00 Rp. 148,500.00
0.4300 M3 Pasir pasang @ Rp. 125,000.00 Rp. 53,750.00
Rp. 123,412.50 Rp. 732,500.00 Rp. 855,912.50
SNI 02.1.13 1 M 3 Pasang pondasi batu kosong tbl. 20 cm ( anstamping )
0.0780 Mandor @ Rp. 87,500.00 Rp. 6,825.00
0.0390 Kepala tukang batu @ Rp. 85,000.00 Rp. 3,315.00
0.3900 Tukang batu @ Rp. 70,000.00 Rp. 27,300.00
0.7810 Pembantu tukang batu @ Rp. 50,000.00 Rp. 39,050.00
1.2000 M3 Batu belah @ Rp. 441,875.00 Rp. 530,250.00
Rp. 76,490.00 Rp. 530,250.00 Rp. 606,740.00

SNI 03.1.12 1 M 2 Pasangan bata 1/2 bata camp 1 Pc : 2 Ps


0.0480 Mandor @ Rp. 87,500.00 Rp. 4,200.00
0.0160 Kepala tukang batu @ Rp. 85,000.00 Rp. 1,360.00
0.1600 Tukang batu @ Rp. 70,000.00 Rp. 11,200.00
0.4800 Pembantu tukang batu @ Rp. 50,000.00 Rp. 24,000.00
80.0000 Bh Batu bata @ Rp. 437.50 Rp. 35,000.00
0.6500 Zak Semen PC 40 Kg ( Gresik ) @ Rp. 55,000.00 Rp. 35,750.00
0.0420 M3 Pasir pasang @ Rp. 125,000.00 Rp. 5,250.00
Rp. 40,760.00 Rp. 76,000.00 Rp. 116,760.00

SNI 03.1.3 1 M 2 Pasangan bata 1 batu camp 1 Pc : 4 Ps


0.0960 Mandor @ Rp. 87,500.00 Rp. 8,400.00
0.0320 Kepala tukang batu @ Rp. 85,000.00 Rp. 2,720.00
0.3200 Tukang batu @ Rp. 70,000.00 Rp. 22,400.00
0.9600 Pembantu tukang batu @ Rp. 50,000.00 Rp. 48,000.00
160.0000 Bh Batu bata @ Rp. 437.50 Rp. 70,000.00
88.8800 Bh Bata beton @ Rp. 1,562.50 Rp. 138,875.00
1.1000 Zak Semen PC 40 Kg ( Gresik ) @ Rp. 55,000.00 Rp. 60,500.00
0.0960 M3 Pasir pasang @ Rp. 125,000.00 Rp. 12,000.00
Bata Merah Rp. 81,520.00 Rp. 142,500.00 Rp. 224,020.00
Bata beton Rp. 81,520.00 Rp. 211,375.00 Rp. 292,895.00

SNI 03.1.14 1 M 2 Pasangan bata ½ bata camp 1 Pc : 4 Ps


0.0480 Mandor @ Rp. 87,500.00 Rp. 4,200.00
0.0160 Kepala tukang batu @ Rp. 85,000.00 Rp. 1,360.00
0.1600 Tukang batu @ Rp. 70,000.00 Rp. 11,200.00
0.4800 Pembantu tukang batu @ Rp. 50,000.00 Rp. 24,000.00
80.0000 Bh Batu bata @ Rp. 437.50 Rp. 35,000.00
44.4400 Bh Bata beton @ Rp. 1,562.50 Rp. 69,437.50
0.4000 Zak Semen PC 40 Kg ( Gresik ) @ Rp. 55,000.00 Rp. 22,000.00
0.0510 M3 Pasir pasang @ Rp. 125,000.00 Rp. 6,375.00
Bata Merah Rp. 35,200.00 Rp. 63,375.00 Rp. 98,575.00
Bata beton Rp. 35,200.00 Rp. 97,812.50 Rp. 133,012.50
Bata beton 1 = 2 x Rp. 70,400.00 Rp. 183,500.00 Rp. 253,900.00
Bata beton 1,5 = 3 x Rp. 211,200.00 Rp. 502,687.50 Rp. 713,887.50

SNI 03.3.2 1 M² Plesteran tbl. 15 mm camp 1 Pc : 2 Ps


0.0040 Mandor @ Rp. 87,500.00 Rp. 350.00
0.0020 Kepala tukang batu @ Rp. 85,000.00 Rp. 170.00
0.0200 Tukang batu @ Rp. 70,000.00 Rp. 1,400.00
0.0400 Pembantu tukang batu @ Rp. 50,000.00 Rp. 2,000.00
0.2130 Zak Semen PC 40 Kg ( Gresik ) @ Rp. 55,000.00 Rp. 11,715.00
0.0170 M3 Pasir pasang @ Rp. 125,000.00 Rp. 2,125.00
Rp. 3,920.00 Rp. 13,840.00 Rp. 17,760.00

SNI 03.3.4 1 M² Plesteran tbl. 15 mm camp 1 Pc : 4 Ps


0.0040 Mandor @ Rp. 87,500.00 Rp. 350.00
0.0020 Kepala tukang batu @ Rp. 85,000.00 Rp. 170.00
0.0200 Tukang batu @ Rp. 70,000.00 Rp. 1,400.00
0.0400 Pembantu tukang batu @ Rp. 50,000.00 Rp. 2,000.00
0.1300 Zak Semen PC 40 Kg ( Gresik ) @ Rp. 55,000.00 Rp. 7,150.00
0.0200 M3 Pasir pasang @ Rp. 125,000.00 Rp. 2,500.00
Rp. 3,920.00 Rp. 9,650.00 Rp. 13,570.00

SNI 06.1.17 1 M² Pasang Jalusi mati Ky. Lanan


0.0250 Mandor @ Rp. 87,500.00 Rp. 2,187.50
0.2000 Kepala tukang @ Rp. 85,000.00 Rp. 17,000.00
2.0000 Tukang @ Rp. 70,000.00 Rp. 140,000.00
0.5000 Pekerja @ Rp. 50,000.00 Rp. 25,000.00
0.0600 M3 Kayu Kls II ( Papan ) @ Rp. 1,281,250.00 Rp. 76,875.00
0.1500 Kg Paku @ Rp. 18,500.00 Rp. 2,775.00
Rp. 184,187.50 Rp. 79,650.00 Rp. 263,837.50
SNI 11.1.1 1 M 3 Kosen pintu / jendela kayu ulin
0.4600 Mandor @ Rp. 87,500.00 Rp. 40,250.00
3.1000 Kepala tukang kayu @ Rp. 85,000.00 Rp. 263,500.00
31.0000 Tukang kayu @ Rp. 70,000.00 Rp. 2,170,000.00
9.3000 Pembantu tukang kayu @ Rp. 50,000.00 Rp. 465,000.00
1.1000 M3 Kayu ulin @ Rp. 4,000,000.00 Rp. 4,400,000.00
3.0000 Kg. Paku ulin @ Rp. 22,500.00 Rp. 67,500.00
56.0000 Bh Angker @ Rp. 3,437.50 Rp. 192,500.00
Rp. 2,938,750.00 Rp. 4,660,000.00 Rp. 7,598,750.00

SNI 11.1.2a 1 M 3 Kosen partisi kayu lanan


0.3600 Mandor @ Rp. 87,500.00 Rp. 31,500.00
2.4000 Kepala tukang kayu @ Rp. 85,000.00 Rp. 204,000.00
24.0000 Tukang kayu @ Rp. 70,000.00 Rp. 1,680,000.00
7.2000 Pembantu tukang kayu @ Rp. 50,000.00 Rp. 360,000.00
1.2000 M3 Kayu lanan @ Rp. 1,281,250.00 Rp. 1,537,500.00
3.0000 Kg. Paku kayu @ Rp. 18,500.00 Rp. 55,500.00
Rp. 2,275,500.00 Rp. 1,593,000.00 Rp. 3,868,500.00

SNI 11.1.4 1 M 2 Pintu / jendela panil kayu Ulin


0.0170 Mandor @ Rp. 87,500.00 Rp. 1,487.50
0.2700 Kepala tukang kayu @ Rp. 85,000.00 Rp. 22,950.00
2.7000 Tukang kayu @ Rp. 70,000.00 Rp. 189,000.00
1.3500 Pembantu tukang kayu @ Rp. 50,000.00 Rp. 67,500.00
0.0440 M3 Papan Ulin @ Rp. 4,500,000.00 Rp. 198,000.00
0.1000 Kg. Lem kayu @ Rp. 25,000.00 Rp. 2,500.00
Rp. 280,937.50 Rp. 200,500.00 Rp. 481,437.50

SNI 11.1.5 1 M 2 Pintu / jendela panil kayu Lanan


0.0050 Mandor @ Rp. 87,500.00 Rp. 437.50
0.2000 Kepala tukang kayu @ Rp. 85,000.00 Rp. 17,000.00
2.0000 Tukang kayu @ Rp. 70,000.00 Rp. 140,000.00
1.0000 Pembantu tukang kayu @ Rp. 50,000.00 Rp. 50,000.00
0.0440 M3 Papan lanan @ Rp. 1,687,500.00 Rp. 74,250.00
0.1000 Kg. Lem kayu @ Rp. 25,000.00 Rp. 2,500.00
Rp. 207,437.50 Rp. 76,750.00 Rp. 284,187.50

SNI 11.1.7a 1 M 2 Pintu / jendela kaca kayu lanan


0.0400 Mandor @ Rp. 87,500.00 Rp. 3,500.00
0.2000 Kepala tukang kayu @ Rp. 85,000.00 Rp. 17,000.00
2.0000 Tukang kayu @ Rp. 70,000.00 Rp. 140,000.00
0.8000 Pembantu tukang kayu @ Rp. 50,000.00 Rp. 40,000.00
0.0300 M3 Kayu lanan @ Rp. 1,281,250.00 Rp. 38,437.50
0.0500 Kg. Paku kayu @ Rp. 18,500.00 Rp. 925.00
0.5630 M2 Kaca rayband 5 mm @ Rp. 100,000.00 Rp. 56,300.00
Rp. 200,500.00 Rp. 95,662.50 Rp. 296,162.50

SNI 11.1.7b 1 M 2 Pintu / jendela kaca kayu lanan comb. Multiplek


0.0400 Mandor @ Rp. 87,500.00 Rp. 3,500.00
0.2000 Kepala tukang kayu @ Rp. 85,000.00 Rp. 17,000.00
2.0000 Tukang kayu @ Rp. 70,000.00 Rp. 140,000.00
0.8000 Pembantu tukang kayu @ Rp. 50,000.00 Rp. 40,000.00
0.0300 M3 Kayu lanan @ Rp. 1,281,250.00 Rp. 38,437.50
0.0500 Kg. Paku kayu @ Rp. 18,500.00 Rp. 925.00
0.1790 Lbr. Multiplek 9 mm @ Rp. 90,750.00 Rp. 16,244.25
0.4290 M2 Kaca rayband 5 mm @ Rp. 100,000.00 Rp. 42,900.00
7.0000 M' List profil @ Rp. 5,000.00 Rp. 35,000.00
Rp. 200,500.00 Rp. 133,506.75 Rp. 334,006.75

SNI 11.1.7c 1 M 2 Pintu / jendela multiplek rangka kayu lanan


0.0400 Mandor @ Rp. 87,500.00 Rp. 3,500.00
0.2000 Kepala tukang kayu @ Rp. 85,000.00 Rp. 17,000.00
2.0000 Tukang kayu @ Rp. 70,000.00 Rp. 140,000.00
0.8000 Pembantu tukang kayu @ Rp. 50,000.00 Rp. 40,000.00
0.0300 M3 Kayu lanan @ Rp. 1,281,250.00 Rp. 38,437.50
0.0500 Kg. Paku kayu @ Rp. 18,500.00 Rp. 925.00
0.2000 Lbr. Multiplek 9 mm @ Rp. 90,750.00 Rp. 18,150.00
7.0000 M' List profil @ Rp. 5,000.00 Rp. 35,000.00
Rp. 200,500.00 Rp. 92,512.50 Rp. 293,012.50
SNI 11.1.13 1 M 2 Pintu plywood rangkap rangka kayu lanan
0.0240 Mandor @ Rp. 87,500.00 Rp. 2,100.00
0.1600 Kepala tukang kayu @ Rp. 85,000.00 Rp. 13,600.00
1.6000 Tukang kayu @ Rp. 70,000.00 Rp. 112,000.00
0.4800 Pembantu tukang kayu @ Rp. 50,000.00 Rp. 24,000.00
0.0193 M3 Papan kayu lanan @ Rp. 1,687,500.00 Rp. Rp. 32,568.75
0.0300 Kg. Paku plywood @ Rp. 18,750.00 Rp. Rp. 562.50
1.0000 Lbr. Plywood 3 mm @ Rp. 75,000.00 Rp. Rp. 75,000.00
0.1150 Kg. Lem kayu @ Rp. 25,000.00 Rp. Rp. 2,875.00
Rp. 151,700.00 Rp. 111,006.25 Rp. 262,706.25

SNI 11.2.2 1 M 3 Kuda-kuda bentang s/d 6 M' kayu lanan


0.2500 Mandor @ Rp. 87,500.00 Rp. 21,875.00 Rp.
1.5000 Kepala Tukang @ Rp. 85,000.00 Rp. 127,500.00 Rp.
15.0000 Tukang Kayu @ Rp. 70,000.00 Rp. 1,050,000.00 Rp.
5.0000 Pembantu Tukang @ Rp. 50,000.00 Rp. 250,000.00 Rp.
1.1000 M3 Kayu Lanan @ Rp. 1,281,250.00 Rp. Rp. 1,409,375.00
3.0000 Kg. Paku (Kayu) @ Rp. 18,500.00 Rp. Rp. 55,500.00
15.0000 Kg. Besi Strip @ Rp. 11,625.00 Rp. Rp. 174,375.00
Rp. 1,449,375.00 Rp. 1,639,250.00 Rp. 3,088,625.00

SNI 11.2.4 1 M 3 Kuda-kuda bentang 6 - 9 M' kayu lanan


0.3400 Mandor @ Rp. 87,500.00 Rp. 29,750.00 Rp.
2.0000 Kepala Tukang @ Rp. 85,000.00 Rp. 170,000.00 Rp.
20.0000 Tukang Kayu @ Rp. 70,000.00 Rp. 1,400,000.00 Rp.
6.7000 Pembantu Tukang @ Rp. 50,000.00 Rp. 335,000.00 Rp.
1.1000 M3Kayu Lanan @ Rp. 1,281,250.00 Rp. Rp. 1,409,375.00
3.0000 Kg Paku (Kayu) @ Rp. 18,500.00 Rp. Rp. 55,500.00
15.0000 Kg Besi Strip @ Rp. 11,625.00 Rp. Rp. 174,375.00
Rp. 1,934,750.00 Rp. 1,639,250.00 Rp. 3,574,000.00

SNI 11.2.6 1 M 3 Pasang gording bahan kayu Kls. kuat II


0.0970 Mandor @ Rp. 87,500.00 Rp. 8,487.50
0.5800 Kepala tukang kayu @ Rp. 85,000.00 Rp. 49,300.00
5.8000 Tukang kayu @ Rp. 70,000.00 Rp. 406,000.00
1.9400 Pembantu tukang kayu @ Rp. 50,000.00 Rp. 97,000.00
1.1000 M3 Kayu lanan @ Rp. 1,281,250.00 Rp. 1,409,375.00
2.2000 Kg. Paku kayu @ Rp. 18,500.00 Rp. 40,700.00
Rp. 560,787.50 Rp. 1,450,075.00 Rp. 2,010,862.50

SNI 11.2.12 1 M 3 Rangka atap kasau 5/7 dan reng 3/4 cm


bahan kayu lanan
0.0050 Mandor @ Rp. 87,500.00 Rp. 437.50
0.0100 Kepala tukang kayu @ Rp. 85,000.00 Rp. 850.00
0.1000 Tukang kayu @ Rp. 70,000.00 Rp. 7,000.00
0.1000 Pembantu tukang kayu @ Rp. 50,000.00 Rp. 5,000.00
0.0134 M3 Kayu lanan @ Rp. 1,281,250.00 Rp. 17,168.75
0.2500 Kg. Paku kayu @ Rp. 18,500.00 Rp. 4,625.00
Rp. 13,287.50 Rp. 21,793.75 Rp. 35,081.25

SNI 11.3.2 1 M² Rangka plafond plywood 60 x 120 cm


0.0110 Mandor @ Rp. 87,500.00 Rp. 962.50
0.0350 Kepala tukang kayu @ Rp. 85,000.00 Rp. 2,975.00
0.3500 Tukang kayu @ Rp. 70,000.00 Rp. 24,500.00
0.2100 Pembantu tukang kayu @ Rp. 50,000.00 Rp. 10,500.00
0.0170 M3 Kayu Borneo @ Rp. 1,000,000.00 Rp. 17,000.00
0.1150 Kg. Paku kayu @ Rp. 18,500.00 Rp. 2,127.50
Rp. 38,937.50 Rp. 19,127.50 Rp. 58,065.00
Rangka Dinding Plywood Upah 2/3 x SNI.11.32 Rp. 25,958.33 Rp. 19,127.50 Rp. 45,085.83
SNI 11.4.1 1 M' Papan rambu / listplank
0.0050 Mandor @ Rp. 87,500.00 Rp. 437.50
0.0200 Kepala tukang kayu @ Rp. 85,000.00 Rp. 1,700.00
0.2000 Tukang kayu @ Rp. 70,000.00 Rp. 14,000.00
0.1000 Pembantu tukang kayu @ Rp. 50,000.00 Rp. 5,000.00
0.0046 M3 Papan ulin @ Rp. 4,500,000.00 Rp. 20,700.00
0.0500 Kg. Paku ulin @ Rp. 22,500.00 Rp. 1,125.00
0.0500 Kg. Paku kayu @ Rp. 18,500.00 Rp. 925.00
0.0046 M3 Papan lanan @ Rp. 1,687,500.00 Rp. 7,762.50
Untuk Kayu Ulin Rp. 21,137.50 Rp. 21,825.00 Rp. 42,962.50
Untuk Kayu Lanan Rp. 21,137.50 Rp. 8,687.50 Rp. 29,825.00
SNI 11.5.3a 1 M 2 Dinding pemisah plywood 4 mm & Rangka

0.0100 Mandor @ Rp. 87,500.00 Rp. 875.00


0.0600 Kepala tukang kayu @ Rp. 85,000.00 Rp. 5,100.00
0.6000 Tukang kayu @ Rp. 70,000.00 Rp. 42,000.00
0.2000 Pembantu tukang kayu @ Rp. 50,000.00 Rp. 10,000.00
0.0260 M3. Kayu lanan @ Rp. 1,281,250.00 Rp. 33,312.50
0.2000 Kg. Paku kayu @ Rp. 18,500.00 Rp. 3,700.00
0.5000 Lbr. Plywood 4 mm @ Rp. 75,000.00 Rp. 37,500.00
4.0000 M. List Profil Besar @ Rp. 5,000.00 Rp. 20,000.00
Rp. 57,975.00 Rp. 94,512.50 Rp. 152,487.50

SNI 12.1.2 1 M² Plafond plywood 60 x 120 cm


0.0050 Mandor @ Rp. 87,500.00 Rp. 437.50
0.0150 Kepala tukang kayu @ Rp. 85,000.00 Rp. 1,275.00
0.1500 Tukang kayu @ Rp. 70,000.00 Rp. 10,500.00
0.1050 Pembantu tukang kayu @ Rp. 50,000.00 Rp. 5,250.00
0.0300 Kg. Paku plywood @ Rp. 18,750.00 Rp. 562.50
0.3750 Lbr. Plywood 4 mm @ Rp. 75,000.00 Rp. 28,125.00
Rp. 17,462.50 Rp. 28,687.50 Rp. 46,150.00
SNI 12.1.2.a 1 M² Plafond Kalciboard 60 x 120 cm
0.005 Mandor @ Rp. 87,500.00 Rp. 437.50
0.015 Kepala tukang kayu @ Rp. 85,000.00 Rp. 1,275.00
0.15 Tukang kayu @ Rp. 70,000.00 Rp. 10,500.00
0.105 Pembantu tukang kayu @ Rp. 50,000.00 Rp. 5,250.00
0.03 Kg. Paku Asbes @ Rp. 21,250.00 Rp. 637.50
0.375 Lbr. Kalciboard @ Rp. 47,500.00 Rp. 17,812.50
Rp. 17,462.50 Rp. 18,450.00 Rp. 35,912.50

SNI 13.2.16.a 1 M2 Penutup atap Genteng metal 2 x 4 - 0,35 mm


0.0060 Mandor @ Rp. 87,500.00 Rp. 525.00 Rp.
0.0060 Kepala tukang kayu @ Rp. 85,000.00 Rp. 510.00 Rp.
0.0600 Tukang kayu @ Rp. 70,000.00 Rp. 4,200.00 Rp.
0.1200 Pembantu tukang kayu @ Rp. 50,000.00 Rp. 6,000.00 Rp.
1.6200 Lbr/M2. Atap …… @ Rp. 87,500.00 Rp. Rp. 141,750.00
0.0407 Kg. Paku Anti Karat @ Rp. 20,625.00 Rp. Rp. 839.44
Rp. 11,235.00 Rp. 142,589.44 Rp. 153,824.44

SNI 13.2.27a 1 M' Bubungan atap


0.0060 Mandor @ Rp. 87,500.00 Rp. 525.00
0.0250 Kepala tukang kayu @ Rp. 85,000.00 Rp. 2,125.00
0.2500 Tukang kayu @ Rp. 70,000.00 Rp. 17,500.00
0.0840 Pembantu tukang kayu @ Rp. 50,000.00 Rp. 4,200.00
1.0000 Lbr. Bubungan Multi Colour @ Rp. 21,875.00 Rp. 21,875.00
0.0200 Kg. Paku Anti karat @ Rp. 20,625.00 Rp. 412.50
Rp. 24,350.00 Rp. 22,287.50 Rp. 46,637.50

K.07 1 M 2 Pekerjaan mengetir / Residu


0.0120 Tukang cat @ Rp. 70,000.00 Rp. 840.00 Rp. 840.00
0.1200 Pekerja @ Rp. 50,000.00 Rp. 6,000.00 Rp. 6,000.00
0.2500 Ltr Ter / Residu @ Rp. 10,625.00 Rp. 2,656.25
0.1500 Ltr. Minyak tanah @ Rp. 5,000.00 Rp. 750.00
Rp. 840.00 Rp. 9,406.25 Rp. 10,246.25

K.15 1 M 2 Pekerjaan melamine


0.5000 Tukang cat @ Rp. 70,000.00 Rp. 35,000.00
0.3500 Ltr. Melamine @ Rp. 35,500.00 Rp. 12,425.00
1.0000 Lbr. Ampelas @ Rp. 3,125.00 Rp. 3,125.00
0.2000 Ltr. Minyak cat @ Rp. 6,250.00 Rp. 1,250.00
Rp. 35,000.00 Rp. 16,800.00 Rp. 51,800.00

K.17 1 M 2 Pekerjaan cat kilap


0.0050 Mandor @ Rp. 87,500.00 Rp. 437.50
0.0150 Kepala tukang cat @ Rp. 85,000.00 Rp. 1,275.00
0.1500 Tukang cat @ Rp. 70,000.00 Rp. 10,500.00
0.1000 Pembantu tukang cat @ Rp. 50,000.00 Rp. 5,000.00
0.2500 Kg. Cat kilap @ Rp. 37,500.00 Rp. 9,375.00
0.1920 Ltr. Minyak cat @ Rp. 6,250.00 Rp. 1,200.00
Rp. 17,212.50 Rp. 10,575.00 Rp. 27,787.50
Upah 2/3 x K.17 Rp. 11,475.00 Rp. 11,775.00 Rp. 23,250.00
K.18 1 M 2 Mengecat kilap Dasar
0.0025 Mandor @ Rp. 87,500.00 Rp. 218.75
0.0075 Kepala tukang cat @ Rp. 85,000.00 Rp. 637.50
0.0750 Tukang cat @ Rp. 70,000.00 Rp. 5,250.00
0.0500 Pembantu tukang cat @ Rp. 50,000.00 Rp. 2,500.00
0.0840 Kg. Cat dasar @ Rp. 14,375.00 Rp. 1,207.50
0.0220 Ltr. Minyak cat @ Rp. 6,250.00 Rp. 137.50
Rp. 6,106.25 Rp. 3,845.00 Rp. 9,951.25

K.18a 1 M 2 Mengecat tembok / plafond 2 kali lapis


0.0020 Kepala tukang cat @ Rp. 85,000.00 Rp. 170.00
0.0200 Tukang cat @ Rp. 70,000.00 Rp. 1,400.00
0.1200 Pembantu tukang cat @ Rp. 50,000.00 Rp. 6,000.00
0.4000 Kg. Cat tembok Danabrite @ Rp. 15,000.00 Rp. 6,000.00
Rp. 7,570.00 Rp. 6,000.00 Rp. 13,570.00

K.30 1 M2 Menggosok dan Mendempul


0.0040 Kepala tukang cat @ Rp. 85,000.00 Rp. 340.00
0.0400 Tukang cat @ Rp. 70,000.00 Rp. 2,800.00
0.5000 Lbr. Amplas @ Rp. 3,125.00 Rp. 1,562.50
0.0800 Kg. Dempul @ Rp. 27,500.00 Rp. 2,200.00
Rp. 4,702.50 Rp. 2,200.00 Rp. 6,902.50

K.30.a 1 M2 Menggosok dan Memplamir


0.0040 Kepala tukang cat @ Rp. 85,000.00 Rp. 340.00
0.0400 Tukang cat @ Rp. 70,000.00 Rp. 2,800.00
0.5000 Lbr. Amplas @ Rp. 3,125.00 Rp. 1,562.50
0.0800 Kg. Plamur @ Rp. 6,875.00 Rp. 550.00
Rp. 4,702.50 Rp. 550.00 Rp. 5,252.50

SUP. IVa 1 M² Pasangan lantai keramik


0.0250 Mandor @ Rp. 87,500.00 Rp. 2,187.50
0.0250 Kepala tukang batu @ Rp. 85,000.00 Rp. 2,125.00
0.2500 Tukang batu @ Rp. 70,000.00 Rp. 17,500.00
0.5000 Pembantu tukang batu @ Rp. 50,000.00 Rp. 25,000.00
1.0000 Pak Keramik granit 40 x 40/60 cm @ Rp. 265,625.00 Rp. 265,625.00
1.0000 Pak Keramik 30 x 30 cm @ Rp. 59,375.00 Rp. 59,375.00
1.0000 Pak Keramik 20 x 20 cm @ Rp. 59,375.00 Rp. 59,375.00
1.0000 Pak Mozaik 30 X 30 cm @ Rp. 56,250.00 Rp. 56,250.00
0.1080 Zak Semen PC 40 Kg ( Gresik ) @ Rp. 55,000.00 Rp. 5,940.00
0.0170 M3 Pasir pasang @ Rp. 125,000.00 Rp. 2,125.00
2.0000 Kg. Semen putih @ Rp. 2,500.00 Rp. 5,000.00
Keramik 30 x 30 Rp. 46,812.50 Rp. 72,440.00 Rp. 119,252.50
Keramik 20 x 20 Rp. 46,812.50 Rp. 72,440.00 Rp. 119,252.50
Keramik mozaik Rp. 46,812.50 Rp. 69,315.00 Rp. 116,127.50
Keramik Granit sjn 40 x40/60 Rp. 46,812.50 Rp. 278,690.00 Rp. 325,502.50

SUP. IVb 1 M² Pasangan dinding keramik


0.0250 Mandor @ Rp. 87,500.00 Rp. 2,187.50
0.0250 Kepala tukang batu @ Rp. 85,000.00 Rp. 2,125.00
0.2500 Tukang batu @ Rp. 70,000.00 Rp. 17,500.00
0.5000 Pembantu tukang batu @ Rp. 50,000.00 Rp. 25,000.00
1.0000 Pak Keramik 20 x 25 cm @ Rp. 59,375.00 Rp. 59,375.00
0.1080 Zak Semen PC 40 Kg ( Gresik ) @ Rp. 55,000.00 Rp. 5,940.00
0.0170 M3 Pasir pasang @ Rp. 125,000.00 Rp. 2,125.00
2.0000 Kg. Semen putih @ Rp. 2,500.00 Rp. 5,000.00
Rp. 46,812.50 Rp. 72,440.00 Rp. 119,252.50
SUP. IV.c 1 M² Pasangan Glass Block dinding
0.0250 Mandor @ Rp. 87,500.00 Rp. 2,187.50
0.0250 Kepala tukang batu @ Rp. 85,000.00 Rp. 2,125.00
0.2500 Tukang batu @ Rp. 70,000.00 Rp. 17,500.00
0.5000 Pembantu tukang batu @ Rp. 50,000.00 Rp. 25,000.00
25.0000 Bh Glass block 20 x 20 cm @ Rp. 9,375.00 Rp. 234,375.00
10.0000 Kg. Semen putih @ Rp. 2,500.00 Rp. 25,000.00
Rp. 51,125.00 Rp. 259,375.00 Rp. 310,500.00
SUP. IV d 1 M² Pasangan dinding keramik ( List 10/25 )
0.0250 Mandor @ Rp. 87,500.00 Rp. 2,187.50
0.0250 Kepala tukang batu @ Rp. 85,000.00 Rp. 2,125.00
0.2500 Tukang batu @ Rp. 70,000.00 Rp. 17,500.00
0.5000 Pembantu tukang batu @ Rp. 50,000.00 Rp. 25,000.00
40.0000 Bh Keramik 10 x 25 cm @ Rp. 6,500.00 Rp. 260,000.00
0.1080 Zak Semen PC 40 Kg ( Gresik ) @ Rp. 55,000.00 Rp. 5,940.00
0.0100 M3 Pasir pasang @ Rp. 125,000.00 Rp. 1,250.00
2.0000 Kg. Semen putih @ Rp. 2,500.00 Rp. 5,000.00
Rp. 46,812.50 Rp. 272,190.00 Rp. 319,002.50
1 M' List Rp. 31,900.25
F.8 10 M 2 Pekerjaan bekisting
0.1000 Mandor @ Rp. 87,500.00 Rp. 8,750.00
0.5000 Kepala tukang kayu @ Rp. 85,000.00 Rp. 42,500.00
5.0000 Tukang kayu @ Rp. 70,000.00 Rp. 350,000.00
2.0000 Pembantu tukang kayu @ Rp. 50,000.00 Rp. 100,000.00
0.4000 M3 Papan bekisting @ Rp. 1,650,000.00 Rp. 660,000.00
4.0000 Kg. Paku kayu @ Rp. 18,500.00 Rp. 74,000.00
Rp. 501,250.00 Rp. 734,000.00 Rp. 1,235,250.00

G.41 1 M 3 Pekerjaan spesi 1 Pc : 2 Ps : 3 Krl


0.3000 Mandor @ Rp. 87,500.00 Rp. 26,250.00
0.1000 Kepala tukang batu @ Rp. 85,000.00 Rp. 8,500.00
1.0000 Tukang batu @ Rp. 70,000.00 Rp. 70,000.00
6.0000 Pembantu tukang batu @ Rp. 50,000.00 Rp. 300,000.00
0.8200 M3 Kerikil sungai @ Rp. 550,000.00 Rp. 451,000.00
6.8000 Zak Semen PC 40 Kg ( Gresik ) @ Rp. 55,000.00 Rp. 374,000.00
0.5400 M3 Pasir pasang @ Rp. 125,000.00 Rp. 67,500.00
Rp. 404,750.00 Rp. 892,500.00 Rp. 1,297,250.00

G.41.a 1 M 3 Pekerjaan spesi 1 Pc : 2 Ps : 3 Krl dengan tulangan tunggal


0.3000 Mandor @ Rp. 87,500.00 Rp. 26,250.00
0.1000 Kepala tukang batu @ Rp. 85,000.00 Rp. 8,500.00
1.0000 Tukang batu @ Rp. 70,000.00 Rp. 70,000.00
6.0000 Pembantu tukang batu @ Rp. 50,000.00 Rp. 300,000.00
0.8200 M3 Kerikil sungai @ Rp. 550,000.00 Rp. 451,000.00
6.8000 Zak Semen PC 40 Kg ( Gresik ) @ Rp. 55,000.00 Rp. 374,000.00
0.5400 M3 Pasir pasang @ Rp. 125,000.00 Rp. 67,500.00
43.0000 Kg. Besi beton @ Rp. 16,750.00 Rp. 720,250.00
0.0460 Kawat Beton @ Rp. 17,500.00 Rp. 805.00
Ls Bekisting @ Rp. 5,500.00 Rp. 5,500.00
Rp. 404,750.00 Rp. 1,619,055.00 Rp. 2,023,805.00

G.67 1 M2 Pekerjaan spesi 1 Pc : 3 Ps : 4 Krl, tebal 5 Cm


0.0600 Mandor @ Rp. 87,500.00 Rp. 5,250.00
0.0020 Kepala tukang batu @ Rp. 85,000.00 Rp. 170.00
0.0200 Tukang batu @ Rp. 70,000.00 Rp. 1,400.00
1.1500 Pembantu tukang batu @ Rp. 50,000.00 Rp. 57,500.00
0.0440 M3 Kerikil sungai @ Rp. 550,000.00 Rp. 24,200.00
0.2100 Zak Semen PC 40 Kg ( Gresik ) @ Rp. 55,000.00 Rp. 11,550.00
0.5400 M3 Pasir pasang @ Rp. 125,000.00 Rp. 67,500.00
Rp. 64,320.00 Rp. 103,250.00 Rp. 167,570.00

I.2 100 Kg. Pekerjaan besi


2.2500 Kepala tukang besi @ Rp. 85,000.00 Rp. 191,250.00
6.7500 Tukang besi @ Rp. 70,000.00 Rp. 472,500.00
6.7500 Pembantu tukang besi @ Rp. 50,000.00 Rp. 337,500.00
110.0000 Kg. Besi beton @ Rp. 16,750.00 Rp. 1,842,500.00
2.0000 Kg. Kawat beton @ Rp. 17,500.00 Rp. 35,000.00
Rp. 1,001,250.00 Rp. 1,877,500.00 Rp. 2,878,750.00
1 Kg Rp. 10,012.50 Rp. 18,775.00 Rp. 28,787.50
L.1 Pekerjaan menyiram dan membongkar bekisting
4.0000 Pembantu tukang @ Rp. 50,000.00 Rp. 200,000.00
Rp. 200,000.00 Rp. Rp. 200,000.00

F.1a 1 M 2 Pekerjaan perancah


0.0250 Mandor @ Rp. 87,500.00 Rp. 2,187.50
0.1500 Kepala tukang kayu @ Rp. 85,000.00 Rp. 12,750.00
1.5000 Tukang kayu @ Rp. 70,000.00 Rp. 105,000.00
0.5000 Pembantu tukang kayu @ Rp. 50,000.00 Rp. 25,000.00
48.0000 M' Kayu bulat @ Rp. 3,125.00 Rp. 150,000.00
0.0100 M3 Papan untuk alas @ Rp. 1,650,000.00 Rp. 16,500.00
0.0060 M3 Kayu 5/7 cm ( Kls. III ) @ Rp. 1,000,000.00 Rp. 6,000.00
1.0000 Kg. Paku kayu @ Rp. 18,500.00 Rp. 18,500.00
Rp. 144,937.50 Rp. 191,000.00 Rp. 335,937.50
2 x sambung Rp. 671,875.00
SUP. V 1 M 3 Beton bertulang camp. 1 Pc : 2 Ps : 3 Kr ( dengan besi 100 Kg )
Pekerjaan bekesting (F.8) Rp. 501,250.00 Rp. 734,000.00
Pekerjaan Spesi (G.41) Rp. 404,750.00 Rp. 892,500.00
Pekerjaan Besi (I.2) Rp. 1,001,250.00 Rp. 1,877,500.00
Pekerjaan menyiram/bongkaran (L.1) Rp. 200,000.00 Rp. 0.00

Rp. 2,107,250.00 Rp. 3,504,000.00 Rp. 5,611,250.00


SUP. V.a 1 M 3 Beton bertulang camp. 1 Pc : 2 Ps : 3 Kr ( dengan besi 125 Kg )
Pekerjaan bekesting (F.8) Rp. 501,250.00 Rp. 734,000.00
Pekerjaan Spesi (G.41) Rp. 404,750.00 Rp. 892,500.00
Pekerjaan Besi (I.2 x 1,25) Rp. 1,251,562.50 Rp. 2,346,875.00
Pekerjaan menyiram/bongkaran (L.1) Rp. 200,000.00 Rp. 0.00
Rp. 2,357,562.50 Rp. 3,973,375.00 Rp. 6,330,937.50

SUP. V.b 1 M 3 Beton bertulang camp. 1 Pc : 2 Ps : 3 Kr ( dengan besi 135 Kg )


Pekerjaan bekesting (F.8) Rp. 501,250.00 Rp. 734,000.00
Pekerjaan Spesi (G.41) Rp. 404,750.00 Rp. 892,500.00
Pekerjaan Besi (I.2 x 1,35) Rp. 1,351,687.50 Rp. 2,534,625.00
Pekerjaan menyiram/bongkaran (L.1) Rp. 200,000.00 Rp. 0.00

Rp. 2,457,687.50 Rp. 4,161,125.00 Rp. 6,618,812.50

SUP. V.c 1 M 3 Beton bertulang camp. 1 Pc : 2 Ps : 3 Kr ( dengan besi 150 Kg )


Pekerjaan bekesting (F.8) Rp. 501,250.00 Rp. 734,000.00
Pekerjaan Spesi (G.41) Rp. 404,750.00 Rp. 892,500.00
Pekerjaan Besi (I.2 x 1,5) Rp. 1,501,875.00 Rp. 2,816,250.00
Pekerjaan menyiram/bongkaran (L.1) Rp. 200,000.00 Rp.

Rp. 2,607,875.00 Rp. 4,442,750.00 Rp. 7,050,625.00

SUP. V.d 1 M 3 Beton bertulang camp. 1 Pc : 2 Ps : 3 Kr ( dengan besi 175 Kg )


Pekerjaan bekesting (F.8) Rp. 501,250.00 Rp. 734,000.00
Pekerjaan Spesi (G.41) Rp. 404,750.00 Rp. 892,500.00
Pekerjaan Besi (I.2 x 1.75) Rp. 1,752,187.50 Rp. 3,285,625.00
Pekerjaan menyiram/bongkaran (L.1) Rp. 200,000.00 Rp. 0.00

Rp. 2,858,187.50 Rp. 4,912,125.00 Rp. 7,770,312.50

SUP. V.e 1 M 3 Beton bertulang camp. 1 Pc : 2 Ps : 3 Kr ( dengan besi 200 Kg )


Pekerjaan bekesting (F.8) Rp. 501,250.00 Rp. 734,000.00
Pekerjaan Spesi (G.41) Rp. 404,750.00 Rp. 892,500.00
Pekerjaan Besi (I.2 x 2.0) Rp. 2,002,500.00 Rp. 3,755,000.00
Pekerjaan menyiram/bongkaran (L.1) Rp. 200,000.00 Rp. 0.00

Rp. 3,108,500.00 Rp. 5,381,500.00 Rp. 8,490,000.00

SUP. V.f 1 M 3 Beton bertulang camp. 1 Pc : 2 Ps : 3 Kr ( dengan besi 225 Kg )


Pekerjaan bekesting (F.8) Rp. 501,250.00 Rp. 734,000.00
Pekerjaan Spesi (G.41) Rp. 404,750.00 Rp. 892,500.00
Pekerjaan Besi (I.2 x 2.25) Rp. 2,252,812.50 Rp. 4,224,375.00
Pekerjaan menyiram/bongkaran (L.1) Rp. 200,000.00 Rp. 0.00
Rp. 3,358,812.50 Rp. 5,850,875.00 Rp. 9,209,687.50

SUP. V.g 1 M 3 Beton bertulang camp. 1 Pc : 2 Ps : 3 Kr ( dengan besi 225 Kg )


Pekerjaan bekesting (F.8) Rp. 501,250.00 Rp. 734,000.00
Pekerjaan Spesi (G.41) Rp. 404,750.00 Rp. 892,500.00
Pekerjaan Besi (I.2 x 2.25) Rp. 2,503,125.00 Rp. 4,693,750.00
Pekerjaan menyiram/bongkaran (L.1) Rp. 200,000.00 Rp. 0.00
Rp. 3,609,125.00 Rp. 6,320,250.00 Rp. 9,929,375.00

G.44 1 M 3 Beton camp. 1 Pc : 3 Ps : 6 Krl


0.3000 Mandor @ Rp. 87,500.00 Rp. 26,250.00
0.0500 Kepala tukang batu @ Rp. 85,000.00 Rp. 4,250.00
0.5000 Tukang batu @ Rp. 70,000.00 Rp. 35,000.00
6.0000 Pembantu tukang batu @ Rp. 50,000.00 Rp. 300,000.00
1.0160 M3 Kerikil sungai @ Rp. 550,000.00 Rp. 558,800.00
4.2400 Zak Semen PC 40 Kg ( Gresik ) @ Rp. 55,000.00 Rp. 233,200.00
0.5080 M3 Pasir beton @ Rp. 125,000.00 Rp. 63,500.00
Rp. 365,500.00 Rp. 855,500.00 Rp. 1,221,000.00
L.4 1 M3 Membongkar dinding Tembok dan membersihkan
0.1000 Tukang batu @ Rp. 70,000.00 Rp. 7,000.00
2.0000 Pekerja @ Rp. 50,000.00 Rp. 100,000.00
Rp. 107,000.00 Rp. Rp. 107,000.00
Rp. 207,000.00 Rp. Rp. 207,000.00

L.7 1 M 2 Menurunkan atap bahan tidak dipakai lagi


0.0200 Mandor @ Rp. 87,500.00 Rp. 1,750.00
0.0100 Kepala tukang kayu @ Rp. 85,000.00 Rp. 850.00
Rp. 2,600.00 Rp. Rp. 2,600.00

L.10 1 M2 Membongkar Rangka Atap ( Kasau Reng )


0.0100 Mandor @ Rp. 87,500.00 Rp. 875.00
0.0060 Kepala tukang kayu @ Rp. 85,000.00 Rp. 510.00
0.0600 Tukang kayu @ Rp. 70,000.00 Rp. 4,200.00
0.0200 Pembantu tukang kayu @ Rp. 50,000.00 Rp. 1,000.00
Rp. 6,585.00 Rp. Rp. 6,585.00
L.11 1 M 2 Membongkar dinding, lantai, plafond kayu
0.0100 Mandor @ Rp. 87,500.00 Rp. 875.00
0.0060 Kepala tukang kayu @ Rp. 85,000.00 Rp. 510.00
0.0600 Tukang kayu @ Rp. 70,000.00 Rp. 4,200.00
0.2000 Pembantu tukang kayu @ Rp. 50,000.00 Rp. 10,000.00
Rp. 15,585.00 Rp. Rp. 15,585.00

L.12 1 M3 Membongkar Kuda-Kuda / Gelagar Jembatan


0.2000 Mandor @ Rp. 87,500.00 Rp. 17,500.00
0.6000 Kepala tukang kayu @ Rp. 85,000.00 Rp. 51,000.00
6.0000 Tukang kayu @ Rp. 70,000.00 Rp. 420,000.00
4.0000 Pembantu tukang kayu @ Rp. 50,000.00 Rp. 200,000.00
Rp. 688,500.00 Rp. Rp. 688,500.00

F.38.b 1 M2 Dinding ( Tawing Layar ) papan Ulin & Lanan diserut rapi tebal 2 cm
1.8000 tukang kayu @ Rp. 70,000.00 @ Rp. 126,000.00 @ Rp.
0.1800 kepala tukang @ Rp. 85,000.00 @ Rp. 15,300.00 @ Rp.
0.6000 pekerja @ Rp. 50,000.00 @ Rp. 30,000.00 @ Rp.
0.0300 mandor @ Rp. 87,500.00 @ Rp. 2,625.00 @ Rp.
0.2000 Kg paku ulin @ Rp. 22,500.00 @ Rp. @ Rp. 4,500.00
0.2000 Kg paku kayu @ Rp. 18,500.00 @ Rp. @ Rp. 3,700.00
0.0290 M3 papan ulin @ Rp. 4,500,000.00 @ Rp. @ Rp. 130,500.00
0.0290 M3 papan lanan @ Rp. 1,687,500.00 @ Rp. @ Rp. 48,937.50
Papan Ulin Rp. 173,925.00 Rp. 135,000.00 Rp. 308,925.00
Papan Lanan upah 1/2 F.38.b Rp. 86,962.50 Rp. 52,637.50 Rp. 139,600.00
Tidak diketam upah 1/3 F.38.b Rp. 57,975.00 Rp. 52,637.50 Rp. 110,612.50

L.8 1 M2 Membongkar Atap Seng


0.0100 Mandor @ Rp. 87,500.00 Rp. 875.00
0.0500 Pembantu tukang kayu @ Rp. 50,000.00 Rp. 2,500.00
Rp. 3,375.00 Rp. Rp. 3,375.00
SNI 12.1.7a 1 M² Penutup langit-langit Papan Moulding 20 cm
0.0120 Mandor @ Rp. 87,500.00 Rp. 1,050.00
0.0670 Kepala tukang kayu @ Rp. 85,000.00 Rp. 5,695.00
0.6700 Tukang kayu @ Rp. 70,000.00 Rp. 46,900.00
0.2300 Pembantu tukang kayu @ Rp. 50,000.00 Rp. 11,500.00
1.5000 Keping Kayu lanan @ Rp. 27,217.74 Rp. 40,826.61
10.0000 Bh. Sekrup @ Rp. 275.00 Rp. 2,750.00
Rp. 65,145.00 Rp. 43,576.61 Rp. 108,721.61
W.01 1 M3 URUGAN PASIR ALAS JALAN
0.1990 Mandor @ Rp. 87,500.00 Rp. Rp. 17,412.50
0.3750 Pekerja @ Rp. 50,000.00 Rp. Rp. 18,750.00
1.2000 M3 Pasir Urug @ Rp. 57,375.00 Rp. 68,850.00
Rp. 68,850.00 Rp. 36,162.50 Rp. 105,012.50

W.04 1 BULAN BIAYA MENGGILAS


1.0000 Mandor @ Rp. 87,500.00 Rp. 87,500.00
150.0000 Pekerja @ Rp. 50,000.00 Rp. 7,500,000.00
1.0000 Oprator @ Rp. 70,000.00 Rp. 70,000.00
1.0000 PembantuOprator @ Rp. 50,000.00 Rp. 50,000.00
30.0000 Penjaga @ Rp. 50,000.00 Rp. 1,500,000.00
1.0000 Pemeliharaan Alat @ Rp. 600,000.00 Rp. 600,000.00
Rp. 9,207,500.00 Rp. 600,000.00 Rp. 9,807,500.00

W.02 1 M2 PASANGAN PERKERASAN TEBAL 15 CM


0.0119 Mandor @ Rp. 87,500.00 Rp. Rp. 1,041.25
0.3750 Pekerja @ Rp. 50,000.00 Rp. Rp. 18,750.00
0.0010 Biaya Gilas @ Rp. 9,807,500.00 Rp. Rp. 9,807.50
0.2000 M3 Batu Pecah 10 - 15 Cm @ Rp. 441,875.00 Rp. 88,375.00
0.0500 M3 Pasir Urug @ Rp. 57,375.00 Rp. 2,868.75
Rp. 91,243.75 Rp. 29,598.75 Rp. 120,842.50

W.03 1 M2 PASANGAN STENSLAG TEBAL 4 CM


0.0038 Mandor @ Rp. 87,500.00 Rp. Rp. 332.50
0.7500 Pekerja @ Rp. 50,000.00 Rp. Rp. 37,500.00
0.0020 Biaya Gilas @ Rp. 9,807,500.00 Rp. Rp. 19,615.00
0.0220 M3 Batu Pecah 2 - 3 Cm @ Rp. 504,000.00 Rp. 11,088.00
0.0200 M3 Pasir Urug @ Rp. 57,375.00 Rp. 1,147.50
Rp. 12,235.50 Rp. 57,447.50 Rp. 69,683.00

W.05 1 00 M2 PENGASPALAN
0.5000 Mandor @ Rp. 87,500.00 Rp. Rp. 43,750.00
10.0000 Pekerja @ Rp. 50,000.00 Rp. Rp. 500,000.00
0.0133 Biaya Gilas @ Rp. 9,807,500.00 Rp. Rp. 130,439.75
250.0000 Kg Aspal @ Rp. 5,250.00 Rp. 1,312,500.00
1.2000 M3 Batu Split @ Rp. 550,000.00 Rp. 660,000.00
1.0000 Alat Bantu @ Rp. 200,000.00 Rp. 200,000.00
0.0200 M3 Pasir Urug @ Rp. 57,375.00 Rp. 1,147.50
Rp. 2,173,647.50 Rp. 674,189.75 Rp. 2,847,837.25
UNTUK 1 M2 = 1/100 Rp. 21,736.48 Rp. 6,741.90 Rp. 28,478.37

W.06 1 M2 PASANGAN PERKERASAN TEBAL 7 CM


0.0119 Mandor @ Rp. 87,500.00 Rp. Rp. 1,041.25
0.2350 Pekerja @ Rp. 50,000.00 Rp. Rp. 11,750.00
0.0010 Biaya Gilas @ Rp. 9,807,500.00 Rp. Rp. 9,807.50
0.0720 M3 Batu Pecah 5/7 Cm @ Rp. 473,437.50 Rp. 34,087.50
0.0500 M3 Pasir Urug @ Rp. 57,375.00 Rp. 2,868.75
Rp. 36,956.25 Rp. 22,598.75 Rp. 59,555.00

SUPL. VI PASANG PAVING BLOK


0.0150 Mandor @ Rp. 87,500.00 Rp. 1,312.50
0.0200 Kepala Tukang @ Rp. 85,000.00 Rp. 1,700.00
0.1500 Tukang @ Rp. 70,000.00 Rp. 10,500.00
0.1500 Pekerja @ Rp. 50,000.00 Rp. 7,500.00
36.0000 Paving Blok @ Rp. 2,125.00 Rp. Rp. 76,500.00
0.0750 M3 Pasir Pasang @ Rp. 125,000.00 Rp. Rp. 9,375.00

Rp. 21,012.50 Rp. 85,875.00 Rp. 106,887.50


SNI 10.1.4 1 Bh Memasang Urinoir
0.1000 Mandor @ Rp. 87,500.00 Rp. 8,750.00
0.1000 Kepala tukang @ Rp. 85,000.00 Rp. 8,500.00
1.0000 Tukang @ Rp. 70,000.00 Rp. 70,000.00
1.0000 Pekerja @ Rp. 50,000.00 Rp. 50,000.00
0.0100 M3 Pasir pasang @ Rp. 125,000.00 Rp. 1,250.00
6.0000 Kg Semen Portland @ Rp. 1,375.00 Rp. 8,250.00
1.0000 Bh Westafel @ Rp. 343,750.00 Rp. 343,750.00
Rp. 137,250.00 Rp. 353,250.00 Rp. 490,500.00

SNI 11.1.7 1 M' Memasang Kusen Aluminium


0.0040 Mandor @ Rp. 87,500.00 350.00
0.0800 Kepala tukang Besi @ Rp. 85,000.00 6,800.00
0.8000 Tukang Besi @ Rp. 70,000.00 56,000.00
0.0800 Pembantu tukang Besi @ Rp. 50,000.00 4,000.00
1.0000 M' Kusen Aluminium @ Rp. 59,375.00 Rp. 59,375.00
Rp. 67,150.00 Rp. 59,375.00 Rp. 126,525.00

SNI 11.1.8 1 M 2 Memasang Rolling Door


0.0052 Mandor @ Rp. 87,500.00 Rp. 455.00
0.1050 Kepala Tukang Besi @ Rp. 85,000.00 Rp. 8,925.00
1.5000 Tukang Besi @ Rp. 70,000.00 Rp. 105,000.00
1.0500 Pembantu tukang Besi @ Rp. 50,000.00 Rp. 52,500.00
1.0000 M2 Rolling Door @ Rp. 625,000.00 Rp. 625,000.00
Rp. 166,880.00 Rp. 625,000.00 Rp. 791,880.00

SNI 11.1.9 1 M 2 Memasang Pintu Aluminium


0.0052 Mandor @ Rp. 87,500.00 Rp. 455.00
0.1050 Kepala Tukang Besi @ Rp. 85,000.00 Rp. 8,925.00
1.0500 Tukang Besi @ Rp. 70,000.00 Rp. 73,500.00
1.0500 Pembantu tukang Besi @ Rp. 50,000.00 Rp. 52,500.00
1.0000 M2 Pintu Aluminium @ Rp. 386,200.00 Rp. 386,200.00
Rp. 135,380.00 Rp. 386,200.00 Rp. 521,580.00

F.1 1 m3 Mengerjakan rangka bawah ulin


0.2500 Mandor @ Rp. 87,500.00 Rp. 21,875.00
0.7500 Kepala Tukang Kayu @ Rp. 85,000.00 Rp. 63,750.00
7.5000 Tukang Kayu @ Rp. 70,000.00 Rp. 525,000.00
5.0000 Pembantu Tukang Kayu @ Rp. 50,000.00 Rp. 250,000.00
1.1000 m3 balok ulin @ Rp. 4,000,000.00 4,400,000.00 Rp. 4,400,000.00
5.0000 kg paku ulin @ Rp. 22,500.00 Rp. 112,500.00
Rp. 5,260,625.00 Rp. 4,512,500.00 Rp. 9,773,125.00

F.38 1 m2 Mengerjakan lantai ulin 2 cm


0.4000 Pekerja @ Rp. 50,000.00 Rp. 20,000.00
0.0200 Mandor @ Rp. 87,500.00 Rp. 1,750.00
1.2500 Tukang Kayu @ Rp. 70,000.00 Rp. 87,500.00
0.1250 Kepala Tukang @ Rp. 85,000.00 Rp. 10,625.00
0.0200 m3 papan ulin @ Rp. 4,500,000.00 Rp. 90,000.00
0.2000 kg paku ulin @ Rp. 22,500.00 Rp. 4,500.00
Rp. 119,875.00 Rp. 94,500.00 Rp. 214,375.00

F.38a 1 m2 Mengerjakan lantai ulin 3 cm


0.4000 Pekerja @ Rp. 50,000.00 Rp. 20,000.00
0.0200 Mandor @ Rp. 87,500.00 Rp. 1,750.00
1.2500 Tukang Kayu @ Rp. 70,000.00 Rp. 87,500.00
0.1250 Kepala Tukang @ Rp. 85,000.00 Rp. 10,625.00
0.0300 m3 papan ulin @ Rp. 4,500,000.00 Rp. 135,000.00
0.2000 kg paku ulin @ Rp. 22,500.00 Rp. 4,500.00
Rp. 119,875.00 Rp. 139,500.00 Rp. 259,375.00
DAFTAR HARGA SATUAN UPAH DAN BAHAN KABUPATEN SERUYAN

HARGA
No. URAIAN SATUAN AKHIR

A. HARGA SATUAN BAHAN


1 Ampelas merk HAMER Lbr Rp. 3,125.00
2 Angker Bh Rp. 3,437.50
3 Atap Genteng Metal Surya Roof 0.35 -2 x 4 M2 Rp. 87,500.00
4 Atap Genteng Metal Surya Roof 0.4 -2 x 4 M2 Rp. 137,500.00
5 Aspal emulsi Kg Rp. 5,250.00
6 Aspal AC Pn 60/70 Kg Rp. 9,125.00
7 Bubungan Genteng Metal M' Rp. 21,875.00
8 Bak Mandi Teraso 70 x 70 - Rp. -
9 Bak Mandi Fibre Glass 50 x 50 Segi Empat Kecil Bh Rp. 225,000.00
10 Bak Mandi Fibre Glass 70 x 70 Sudut Bh Rp. 250,000.00
11 Bak Mandi Fibre Glass 70 x 70 Segi Empat Besar Bh Rp. 187,500.00
12 Balok Kayu Kl. I ( Ulin ) M3 Rp. 4,000,000.00
13 Balok Kayu Kl. II Kamfer Kruing / Lanan M3 Rp. 1,281,250.00
14 Balok Kayu Kl. III Borneo / Dll. M3 Rp. 1,000,000.00
15 Batu Bata Bh Rp. 437.50
16 Batu Bata beton pres Bh Rp. 1,562.50
17 Batu Kali / Batu Belah M3 Rp. 441,875.00
18 Batu Pecah 1-2 cm M3 Rp. 550,000.00
19 Batu Pecah 2-3 cm M 3
Rp. 504,000.00
20 Batu Pecah 3-5 cm M3 Rp. 472,500.00
21 Batu Pecah 5-7 cm M3 Rp. 473,437.50
22 Batu Pecah 10-15 cm M3 Rp. 441,875.00
23 Besi Beton Polos Kg Rp. 16,750.00
24 Besi Baja Siku Kg Rp. 11,625.00
25 Besi Begel/Baut Kuda-kuda Kg Rp. 15,625.00
26 Cat Kayu Dasar Kg Rp. 14,375.00
27 Cat Kayu Mengkilap Kg Rp. 37,500.00
28 Cat Melamine / Teak Oil Ltr Rp. 35,500.00
29 Cat Menie Kg Rp. 14,375.00
30 Cat Tembok ( Vinilex / Setara) Kg Rp. 15,000.00
32 Dempul Kayu merk KEMBANG Kg Rp. 27,500.00
33 Grendel Bh Rp. 9,375.00
34 Floor Drain Bh Rp. 10,625.00
35 Formica Lbr Rp. 56,250.00
36 Gerendel Bh Rp. 9,375.00
37 Hak Angin Besar merk EXEL Bh Rp. 9,375.00
38 Wastafel Berwarna KIA Set Rp. 281,250.00
39 Handle variatif ( kuningan ) Bh Rp. 9,375.00
40 Kaca Bening ukuran 3 mm M2 Rp. 78,750.00
41 Kaca Bening ukuran 5 mm M2 Rp. 93,750.00
42 Kaca Buram ukuran 5 mm M2 Rp. 93,750.00
43 Kaca Ray-band ukuran 5 mm M 2
Rp. 100,000.00
44 Kaca 5 mm Want way M2 Rp. 187,500.00
45 Kawat Beton Kg Rp. 17,500.00
46 Kayu Dolken / Galam Dia. 8 - 10 Cm Pjng 4 M Btg Rp. 12,500.00
47 Keramik 20 X 25 cm Dost Rp. 56,250.00
48 Keramik 20 X 20 cm warna Dost Rp. 56,250.00
49 Keramik 30 X 30 cm Merk Roman sejenis Dost Rp. 59,375.00
HARGA
No. URAIAN SATUAN AKHIR

50 Keramik 40 X 40 cm Dost Rp. 59,375.00


51 Keramik Granit sejenis 40 X 40/ 60 cm Dost Rp. 265,625.00
52 Urinoir Warna Putih KIA Set Rp. 375,000.00
53 Urinoir Keramik Standart KIA Bh Rp. 343,750.00
54 Kloset Duduk Keramik Set Rp. 500,000.00
55 Kloset Jongkok Keramik Bh Rp. 115,625.00
56 Closet Duduk Warna Putih Merk INA Set Rp. 593,750.00
57 Closet Jongkok Warna Putih Merk INA Bh Rp. 93,750.00
58 Closet Jongkok Berwarna Merk INA - Rp. -
59 Koral Beton Split M3 Rp. 550,000.00
60 Koral / Kerikil Sungai M3 Rp. 215,475.00
61 Kran Leideng Bh Rp. 18,750.00
62 Kunci Tanam SES Bh Rp. 237,500.00
63 Lampu Pijar Bh Rp. 6,250.00
64 Lampu TL 20 Watt Bh Rp. 46,250.00
65 Lampu TL 40 Watt (bambu) Bh Rp. 93,750.00
66 Lampu Mercuri Bh Rp. 250,000.00
67 Lem Kayu Kg Rp. 25,000.00
68 List Profil tebal 5 cm M' Rp. 5,000.00
69 Minyak Cat merk UNIVERSAL Ltr Rp. 6,250.00
70 Multiplek 6 mm Lbr Rp. 52,500.00
71 Multiplek 9 mm Lbr Rp. 90,750.00
72 Mur Baut Bh Rp. 3,437.50
73 Mur Angkur baja dia 22 - 60 Cm Bh Rp. 3,437.50
74 Mur Angkur baja dia 16 - 60 Cm Bh Rp. 3,437.50
75 Paku Anti Karat (untuk Atap Multi color) Kg Rp. 20,625.00
76 Paku Asbes Kalciboard Kg Rp. 21,250.00
77 Paku Kait / Sumbat Kg Rp. 25,000.00
78 Paku Kayu Kg Rp. 18,500.00
79 Paku Plywood / Teakwood Kg Rp. 18,750.00
80 Paku Reng Kg Rp. 11,875.00
81 Paku Seng Kg Rp. 18,750.00
82 Paku Sirap Kg Rp. 12,500.00
83 Paku Ulin RRT Kg Rp. 22,500.00
84 Papan Bekesting M 3
Rp. 1,650,000.00
85 Papan Kayu (Bouwplank) M3 Rp. 1,250,000.00
86 Papan kayu ulin Kls I ( Ulin ) M3 Rp. 4,500,000.00
87 Papan Kayu Kl. II Kamfer Kruing / Lanan M3 Rp. 1,687,500.00
88 Papan Kayu Kl. III Borneo / Dll. M3 Rp. 1,250,000.00
89 Pasir Beton M3 Rp. 82,550.00
90 Pasir Pasang M3 Rp. 125,000.00
91 Pasir Urug M3 Rp. 57,375.00
92 Pipa PVC Pj 4m 1/2" AW Btg Rp. 15,000.00
93 Pipa PVC Pj 4m 3/4" AW Btg Rp. 21,250.00
94 Pipa PVC Pj 4m 1" AW Btg Rp. 27,500.00
95 Pipa PVC Pj 4m 2" D Btg Rp. 37,500.00
96 Pipa PVC Pj 4m 4" D Btg Rp. 102,500.00
97 Kran Leding Standart Bh Rp. 18,750.00
98 Stop Kran Leding Bh Rp. 20,000.00
99 Plamur Tembok merk WIBER ( 5 Kg ) Kaleng Rp. 34,375.00
100 Plywood 3 mm 122 x 124 Lbr Rp. 62,500.00
101 Plywood 4 mm 122 x 124 Lbr Rp. 75,000.00
102 Pompa Listrik kapasitas 0,5 Ltr / detik Set Rp. 687,500.00
103 Pompa Air Tangan Merk Dragon Set Rp. 343,750.00
104 Pompa Air Tangan Merk Tasako Set Rp. 281,250.00
105 Reng kayu lanan M3 Rp. 750,000.00
106 Residu / teer Ltr Rp. 10,625.00
107 Sekrup Bh Rp. 275.00
HARGA
No. URAIAN SATUAN AKHIR

108 Semen PC ( 40 Kg. / Zak) merk GRESIK Zak Rp. 55,000.00


109 Semen PC ( 50 Kg. / Zak) merk GRESIK Zak Rp. 67,187.50
110 Semen Putih kg Rp. 2,500.00
111 Seng Gelombang BJLS 20 M2 Rp. 47,500.00
112 Seng Gelombang BJLS 18 M2 Rp. 37,500.00
113 Stop Kontak + Instalasi (untuk Beton) Bh Rp. 175,000.00
114 Schakalar ( Standar ) Bh Rp. 12,500.00
115 Tanah Urug Biasa M3 Rp. 53,000.00
116 Tanah Urug Pilihan M3 Rp. 57,850.00
117 Tanah Subur M 3
Rp. 75,000.00
118 Teakwood 4 mm Lbr Rp. 112,500.00
119 Titik Lampu + Instalasi Bh Rp. 175,000.00
120 Urinoir Keramik merk KIA (setara) Bh Rp. 343,750.00
121 Paving Stone Bh Rp. 2,125.00
122 Baja Siku Kg Rp. 11,625.00
123 Baja IWF Kg Rp. 9,500.00
124 Baja plat Strip Bj Rp. 12,000.00
125 List Keramik Dinding 10 x 25 Bh Rp. 6,500.00
126 Engsel Pintu /Jendela setara SES Bh Rp. 12,500.00
127 Engsel Ex. RRC Ukuran 80 x 50 Stel Rp. 10,000.00
128 Engsel Ex RRC Ukuran 140 x 60 Stel Rp. 18,750.00
129 Engsel Lokal "4" ( Pintu ) Bh Rp. 21,875.00
130 Engsel Lokal "5" ( Pintu ) Bh Rp. 31,250.00
131 Engsel Lokal "3" ( Jendela ) Bh Rp. 15,625.00
132 Kalciboard Lbr Rp. 47,500.00
133 Papan Moulding Bengkirai Lbr Rp. 12,500.00
134 Papan Moulding Ramin lbr Rp. 22,500.00
135 Kalciboard/eternit m2 Rp. 53,750.00
136 Glass Block 20 x 20 cm Bh Rp. 9,375.00
137 Baja plat Kg Rp. 12,500.00
138 Pintu Aluminium Engsel Swing M2 Rp. 386,200.00
139 Kosen Aluminium 3" Putih m' Rp. 59,375.00
140 Rolling Door Aluminium m2 Rp. 625,000.00
141 Septictank dan Rembesan Kapasitas 1 M3 Bh Rp. 625,000.00
142 Septictank dan Rembesan Kapasitas 6 M3 Bh Rp. 3,750,000.00
143 Septictank dan Rembesan Kapasitas 4 M3 Bh Rp. 2,712,500.00
144 Septictank dan Rembesan Kapasitas 2 M3 Bh Rp. 2,250,000.00
145 Minyak Tanah Ltr Rp. 5,000.00

B. HARGA SATUAN UPAH


1 Kepala Tukang Batu /besi Org / Hari Rp. 85,000.00
2 Kepala Tukang Cat Org / Hari Rp. 85,000.00
3 Kepala Tukang Kayu Org / Hari Rp. 85,000.00
4 Kepala Tukang Besi Org / Hari Rp. 85,000.00
5 Laden Tukang Batu Org / Hari Rp. 50,000.00
6 Laden Tukang Kayu Org / Hari Rp. 50,000.00
7 Laden Tukang Besi Org / Hari Rp. 50,000.00
8 Laden Tukang Cat Org / Hari Rp. 50,000.00
9 Mandor Org / Hari Rp. 87,500.00
10 Penjaga Malam Org / Hari Rp. 50,000.00
11 Tukang Batu / Besi Org / Hari Rp. 70,000.00
12 Tukang Kayu Org / Hari Rp. 70,000.00
13 Tukang Cat Org / Hari Rp. 70,000.00
14 Tukang Listrik Org / Hari Rp. 65,000.00
15 Tukang Pancang Org / Hari Rp. 65,000.00
16 Tukang Gali Tanah Org / Hari Rp. 65,000.00
RENCANA ANGGARAN BIAYA
PROGRAM : PENGEMBANGAN BUDIDAYA PERIKANAN KABUPATEN SERUYAN TAHUN ANGGARAN 2009
KEGIATAN : PEMBINAAN DAN PENGEMBANGAN PERIKANAN
PEKERJAAN : BELANJA JASA PERENCANAAN LANJUTAN PENGERASAN BETON JALAN PRODUKSI TAMBAK RAKYAT
LOKASI : KECAMATAN SERUYAN HILIR - KABUPATEN SERUYAN

Harga Satuan Jumlah


No. Uraian Pekerjaan Analisa Volume Upah & Bahan Harga Total
(Rp) (Rp). (Rp).

I PEKERJAAN PENDAHULUAN
1 Pengukuran, Pasang Patok dan Bowplank SNI 01.1.6 2,280.00 M2 20,232.50 46,130,100.00
2 Papan Nama Proyek Ls 1.00 Bh 523,000.00 523,000.00
3 Pembuatan Bangsal Kerja Ls 12.00 M2 365,000.00 4,380,000.00
4 Perataan Badan Jalan Ls 1,510.00 M2 22,500.00 33,975,000.00
JUMLAH 85,008,100.00

II PEKERJAAN GORONG - GORONG


1 Galian Tanah Gorong - Gorong SNI 01.2.1 7.50 M3 29,500.00 221,250.00
2 Urugan Tanah Kembali SNI 01.2.9 3.75 M3 14,142.50 53,034.00
3 Pasang Cerucuk Galam Ls 22.00 Btg 18,900.00 415,800.00
4 Pas. Gorong - Gorong diameter 1 m panjang 50 cm Ls 10.00 Bh 465,000.00 4,650,000.00
5 Pembendungan sementara Pasangan Gorong - Gorong Ls 1.00 Ttk 750,400.00 750,400.00
JUMLAH 6,090,484.00

III PEKERJAAN BETON BADAN JALAN


1 Cor badan Jalan Tulangan Tunggal Tbl 10 Cm Pjg 755 M G.41.a 151.00 M3 2,023,805.00 305,594,555.00
2 Lapisan Plastik Pengecoran Badan Jalan Ls 1,510.00 M2 12,750.00 19,252,611.00
JUMLAH 324,847,166.00

IV PEKERJAAN SIRING PENAHAN TANAH


1 Pasangan Tongkat Ulin 10/10 Panjang 4 M F.1 0.28 M3 9,773,125.00 2,736,475.00
2 Pasangan Balok Palang Ulin 5/10 F.1 0.12 M3 9,773,125.00 1,172,775.00
3 Pesangan Papan Ulin 2/20 F.38 24.00 M2 214,375.00 5,145,000.00
JUMLAH 9,054,250.00

REKAPITULASI RENCANA ANGGARAN BIAYA

I PEKERJAAN PENDAHULUAN ………………………………………………………………………………….Rp. 85,008,100.00


II PEKERJAAN GORONG - GORONG ………………………………………………………………………………….Rp. 6,090,484.00
III PEKERJAAN BETON BADAN JALAN ………………………………………………………………………………….Rp. 324,847,166.00
IV PEKERJAAN SIRING PENAHAN TANAH ………………………………………………………………………………….Rp. 9,054,250.00

TOTAL BIAYA FISIK Rp. 425,000,000.00

TERBILANG //// EMPAT RATUS DUA PULUH LIMA JUTA RUPIAH ////

Kuala Pembuang,………..Nopember 2008

Mengetahui : Di Buat Oleh :


Pejabat Pelaksana Teknis Kegiatan Panitia Pengadaan Barang dan Jasa
Pembinaan dan Pengembangan Perikanan Di Lingkungan Dinas Kelautan dan Perikanan
Ketua,

…………………………… ……………………………
NIP………………………. NIP……………………….

Menyetujui :
Kepala Dinas Kelautan dan Perikanan
Kabupaten Seruyan

Ir. RIDUAN SYAHRANI


NIP. 080 096 731

Hal - 18