REKAPITULASI

RENCANA ANGGARAN BIAYA ( RAB )

KEGIATAN : PENGEMBANGAN DISTRIBUSI AIR MINUM


PEKERJAAN : PEMBANGUNAN INSTALASI PENGOLAHAN AIR BERSIH (IPA) PDAM KP.50
L/Dtk IKK SELAKAU
LOKASI : KEC. SELAKAU, KABUPATEN SAMBAS
TAHUN ANGGARAN : 2019
SUMBER DANA : DAK REGULER 2019

HARGA
NO. URAIAN SATUAN
Rp

I PEKERJAAN PERSIAPAN 87.000.000,00


II PEKERJAAN BANGUNAN AIR BAKU & PERPIPAAN 6.715.817.858,34
III BANGUNAN PELENGKAP UNIT AIR BAKU 261.293.396,59
IV PEKERJAAN BANGUNAN PRODUKSI TERMASUK M & E 8.828.869.861,83
V PEKERJAAN SIPIL UNIT PRODUKSI 3.736.223.011,90
VI PEKERJAAN PELAYANAN/DISTRIBUSI 11.325.747.288,99
VII PEKERJAAN LAIN-LAIN 863.205.000,00

A JUMLAH 31.818.156.417,65
B PPn (A x 10 %) 3.181.815.641,77
C JUMLAH TOTAL (A + B) 34.999.972.059,42
D DIBULATKAN 35.000.000.000,00

Terbilang : ......................Tiga Puluh Lima Milyar Rupiah ............................

Sambas, 2019
Kepala Dinas Perumahan Rakyat
Kawasan Pemukiman dan
Lingkungan Hidup

EKO SUSANTO, SKM.M.Kes.


Nip. 19650312 198603 1 022
RENCANA ANGGARAN BIAYA
ENGINEER ESTIMATE ( EE )

KEGIATAN : PENGEMBANGAN DISTRIBUSI AIR MINUM


PEKERJAAN : PEMBANGUNAN INSTALASI PENGOLAHAN AIR BERSIH (IPA) PDAM KP.50 L/Dtk IKK SELAKAU
LOKASI : KEC. SELAKAU, KABUPATEN SAMBAS
TAHUN ANGGARAN : 2019
SUMBER DANA : DAK REGULER 2019

HARGA SATUAN TOTAL HARGA


NO. NAMA KEGIATAN SATUAN VOLUME
(Rupiah) (Rupiah)
I PEKERJAAN PERSIAPAN
1 Mobilisasi dan Demobilisasi, Dokumentasi, Gambar-gambar Asbuilt Drawing, Pelaporan ls 1,00 45.000.000,00 45.000.000,00
2 Pengukuran Kembali, Pembersihan Lapangan dan Pematokan ls 1,00 12.000.000,00 12.000.000,00
3 Pengadaan Alat Kesehatan dan Keselamatan Kerja ( K3 ) ls 1,00 30.000.000,00 30.000.000,00
Jumlah Pekerjaan Persiapan 87.000.000,00
II PEKERJAAN BANGUNAN AIR BAKU & PERPIPAAN
1 Pembuatan bangunan intake 50 l/dt unit 1,00 735.505.000,00 735.505.000,00
2 Saringan Dari besi beton 3 bh dia. 18 mm ls 1,00 20.000.000,00 20.000.000,00
3 Pembuatan Bangunan Rumah Jaga Intake lantai gantung m2 50,00 5.914.240,74 295.712.037,04
4 Pembuatan Bangunan Rumah Pompa Intake lantai gantung m2 30,00 10.822.156,25 324.664.687,50
5 Pompa air baku (Centrifugal) lengkap dengan Valve, kap 75 l/det, H=60m unit 2,00 161.480.620,00 322.961.240,00
6 Wash Out Pipa Air baku Diameter : 150 mm (Tee dgn 2 valve) unit 1,00 14.016.844,94 14.016.844,94
7 Air Valve Pipa Air Baku Diameter : 200 mm x 75 mm (lengkap dgn hydrant tee) unit 1,00 3.821.000,00 3.821.000,00
8 Jembatan pipa Diameter : 200 mm m 18,00 4.284.722,22 77.125.000,00
9 Panel pompa air baku lengkap dengan MCCB, contactor, thermis unit 1,00 34.955.550,00 34.955.550,00
10 Pengadaan dan Pemasangan Pipa air baku dia. 200 mm HDFE ( air baku ) m 6.000,00 772.507,45 4.635.044.711,63
11 Pengetesan dan Pegurasan Pipa ( pipa terpasang ) m 51.451,00 4.212,44 216.734.037,24
12 Pengangkutan Pipa Air Baku Ls 1,00 12.862.750,00 12.862.750,00
13 Cross Jalan pipa Gip dia. 200 mm m 10,00 2.241.500,00 22.415.000,00
Jumlah Pekerjaan Bangunan Air Baku dan Perpipaan 6.715.817.858,34
III BANGUNAN PELENGKAP UNIT AIR BAKU
1 Jalan inspeksi di intake (sesuai dengan kebutuhan) m2 50,00 210.278,40 10.513.920,11
2 Timbunan Tanah Pilihan m3 190,00 140.909,00 26.772.710,00
3 Jembatan masuk ke Intake unit 1,00 178.000.000,00 178.000.000,00
4 Penimbunan badan jalan dengan batu kong uk: L 4 m m3 1.260,00 9.018,15 11.362.866,48
5 Pagar terbuat dari pondasi batu kali, BRC 1,5m termasuk pintu m' 70,00 387.770,00 27.143.900,00
6 - CFL - 250 watt Untuk penerangan termasuk tiang 6 m dengan unit unit 1,00 7.500.000,00 7.500.000,00
Jumlah Pekerjaan Bangunan Unit Air Baku 261.293.396,59
IV PEKERJAAN BANGUNAN PRODUKSI TERMASUK M & E
1 IPA 50 L/dt beton lengkap dengan accessories unit 1,00 6.174.258.933,33 6.174.258.933,33
2 Pengadaan dan pemasangan Bangunan atap IPA dari galvalum dengan rangka baja ls 1,00 90.000.000,00 90.000.000,00
3 Pompa dosing lengkap dengan accessories unit 6,00 46.392.340,00 278.354.040,00
4 Tangki pembubuh bahan kimia lengkap dengan accessories volume : 1000 liter unit 6,00 5.000.000,00 30.000.000,00
5 Tangki mixer bahan kimia 1000 liter unit 2,00 5.000.000,00 10.000.000,00
6 Tangki mixer bahan kimia 1500 liter unit 1,00 7.500.000,00 7.500.000,00
7 Mixer alum, Soda ash dan Kaporit (900 ~ 1000 rpm) unit 3,00 7.500.000,00 22.500.000,00
8 Pembuatan Bak Reservoir Kapasitas 400 m3 m3 400,00 3.162.603,33 1.265.041.333,33
8 Pekerjaan Batu Pasang m3 94,50 1.087.892,59 102.805.849,57
9 Pompa Blower 11 kw unit 2,00 87.000.000,00 174.000.000,00
10 Water meter Induk air minum Diameter : 200 mm unit 2,00 76.623.000,00 153.246.000,00
11 Pipa PVC lengkap dengan accessories m 60,00 45.124,43 2.707.465,60
12 Flow indicator air baku diameter : 200 mm (Flap type) unit 1,00 19.440.000,00 19.440.000,00
13 Panel pompa back wash lengkap dengan MCCB, contactor, thermis, unit 1,00 34.955.550,00 34.955.550,00
14 Panel pompa kimia dan mixer lengkap dengan MCCB, contactor, 22.513.140,00 22.513.140,00
unit 1,00
15 thermis, push button, lampu control dan lain-lain
Panel MDP dan change over switch unit 1,00 34.955.550,00 34.955.550,00
16 Kabel-kabel untuk kebutuhan kabel power genset, kabel pompa ls 1,00 27.260.000,00 27.260.000,00
17 Lampu penerangan (termasuk saklar dan stopcontac)
- TL 1 x 40 watt (ditiap ruang kantor, operasi dan genset) unit 16,00 105.000,00 1.680.000,00
- CFL - 250 watt Untuk penerangan termasuk tiang 6 m dengan unit photo voltaik unit 4,00 7.500.000,00 30.000.000,00
18 Penangkal Petir Lengkap dgn Kabel B.C standar PLN ls 1,00 2.400.000,00 2.400.000,00
19 Pengadaan Arus Listrik ( PLN ) Kaps. 105 Kva Ls 2,00 172.626.000,00 345.252.000,00
Jumlah Pekerjaan Bangunan Produksi Termasuk M & E 8.828.869.861,83
V PEKERJAAN SIPIL UNIT PRODUKSI
1 Pembuatan pondasi paket IPA unit 1,00 88.408.000,00 88.408.000,00
2 Rumah Dinas di lokasi IPA ( 2 unit ) m2 101,00 3.702.370,37 373.939.407,41
3 Pos Satpam m2 6,00 3.702.370,37 22.214.222,22
4 Rumah operasi terbuat dari pasangan batu bata, lantai keramik, m2 70,00 3.702.370,37 259.165.925,93
5 Bangunan gudang sparepart, terbuat dari pasangan, m2 36,00 10.822.156,25 389.597.625,00
6 Bangunan Kantor dan Bangunan Laboratorium m2 90,00 3.702.370,37 333.213.333,33
7 Rumah pompa air minum (centrifugal) termasuk pondasi pompa untuk 3 unit m2 30,00 10.822.156,25 324.664.687,50
8 Pompa Distribusi ( Centrifugal ) Kapasitas 20 l/dt Head 60 m unit 1,00 66.328.145,00 66.328.145,00
9 Saluran drainase terbuka terbuat dari pasangan batu bata (0.3 x 0.4 m) m 153,00 293.587,50 44.918.887,50
10 Pagar terbuat dari pondasi batu kali, dinding batu bata setinggi 0,50 m dan BRC m 400,00 387.770,00 155.108.000,00
11 Jalan masuk /lingkungan terbuat dari berton bertulang campuran 1:2:3 m2 300,00 210.278,40 63.083.520,68
12 Penimbunan badan jalan dengan batu kong uk: L 6 m m3 1.260,00 264.317,40 333.039.924,00
13 Papan nama IKK (permanen) termasuk penerangannya unit 1,00 15.000.000,00 15.000.000,00
14 Pembuatan reservoir air bersih m3 400,00 3.162.603,33 1.265.041.333,33
15 Perpipaan sampel air baku, perpipaan sampel air minum diameter : 1/2 " ls 1,00 2.500.000,00 2.500.000,00
Jumlah Pekerjaan Sipil Unit Produksi 3.736.223.011,90
HARGA SATUAN TOTAL HARGA
NO. NAMA KEGIATAN SATUAN VOLUME
(Rupiah) (Rupiah)
VI PEKERJAAN PELAYANAN/DISTRIBUSI
1 Penggalian 1 m3 tanah biasa sedalam 1 m m3 14.406,28 82.045,00 1.181.963.242,60
2 Pengurugan kembali 1 m3 galian tanah (1/3 Galian;-Tanah Biasa Sedalam 1 M) m3 4.802,09 29.772,00 142.967.922,72
3 Penggalian 1 m3 Tanah Keras berbatuan sedalam 1 m m3 1.876,00 148.863,00 279.266.988,00
4 Perbaikan Kembali rabat beton m3 402,00 121.539,34 48.858.814,55
5 Jembatan Pipa Dia. 75 mm m 48,00 2.161.500,00 103.752.000,00
6 Jembatan Pipa Dia. 100 mm m 12,00 2.626.222,22 31.514.666,67
7 Jembatan Pipa Dia. 150 mm m 12,00 3.258.500,00 39.102.000,00
5 Beton Pemberat Pipa Transmisi dia. 200 mm m3 11,26 717.255,90 8.076.301,43
6 Pengurugan 1 m3 dengan pasir urug m3 2.058,04 267.362,00 550.241.690,48
7 Pengadaan dan Pemasangan 1 m pipa PE Ø 75 mm m 35.000,00 162.618,76 5.691.656.630,51
8 Pengadaan dan Pemasangan 1 m pipa PE Ø 100 mm m 8.026,00 242.297,21 1.944.677.404,26
9 Pengadaan dan Pemasangan 1 m pipa PE Ø 150 mm m 1.725,00 468.776,65 808.639.719,39
10 Pengadaan dan Pemasangan 1 m pipa PE Ø 200 mm m 700,00 707.185,58 495.029.908,38
Jumlah Pekerjaan Bangunan Unit Air Baku 11.325.747.288,99
VII PEKERJAAN LAIN-LAIN
1 Peralatan laboratorium
a. Jartess 6 Beaker Unit 1,00 30.000.000,00 30.000.000,00
b. Turbidity Meter ( Alat pengetes Ph, Zat Besi dan Kekeruhan ) Unit 1,00 35.000.000,00 35.000.000,00
c. Beaker Glass bh 6,00 350.000,00 2.100.000,00
2 Uji coba (termasuk bahan kimia, bahan bakar dan lain-lain) 120 jam ls 1,00 25.000.000,00 25.000.000,00
3 Pekerjaan akhir/finishing ls 1,00 15.000.000,00 15.000.000,00
4 Bahan Kimia dan Energi :
- Alum sulfat kg 4.000,00 6.363,00 25.452.000,00
- Soda Ash kg 2.000,00 12.727,00 25.454.000,00
- Kaporit kg 500,00 30.000,00 15.000.000,00
- Solar ltr 5.000,00 6.727,00 33.635.000,00
5 Sambungan Rumah ( SR ) unit 400,00 1.641.410,00 656.564.000,00
Jumlah Pekerjaan lain-lain 863.205.000,00
JUMLAH 31.818.156.418
PPn 10 % 3.181.815.642
TOTAL SELURUHNYA 34.999.972.059
DIBULATKAN 35.000.000.000
PROYEK PENYUSUNAN DED SPAM IKK 2019

KEGIATAN PENGEMBANGAN DISTRIBUSI AIR MINUM


PEKERJAAN PEMBANGUNAN INSTALASI PENGOLAHAN AIR BERSIH (IPA) PDAM KP.50 L/Dtk IKK SELAKAU
LOKASI KEC. SELAKAU, KABUPATEN SAMBAS
TAHUN ANGGARAN 2019
SUMBER DANA DAK REGULER 2019

REKAP ANALISA PEKERJAAN DAN HARGA SATUAN


Kode Harga satuan
No. Uraian Pekerjaan Unit
Analisa (Rp. X 1000)

1 Intake Sumuran Bulat, kapasitas 10 - 20 L/dt Unit parsial 1.a 101.498.000,00


2 Intake Sodetan, kapasitas 10 - 20 L/dt Unit parsial 1.c #REF!
3 Intake Ponton, kapasitas 20 L/dt Unit parsial 1.e 145.388.000,00
4 Intake Ponton, kapasitas 10 L/dt Unit parsial 1.f 112.747.000,00
5 Intake Dermaga, kapasitas 10 - 20 L/dt Unit parsial 1.g 96.305.000,00
6 Bak Prasedimentasi (22x6x2)m M2 parsial 3.a 3.758.259,49
7 Turap Pasangan Batu Kali M3 An.SNBK 6.5 1.087.892,59
8 Pompa Sub.M. Non Clogging 5 l/dt H = 30 m Unit p.l 62.596.800,00
9 Pompa Sub.M. Non Clogging 10 l/dt H = 30 m Unit p.l 72.193.680,00
10 Pompa Sub.M. Non Clogging 20 l/dt H = 30 m Unit p.l 92.124.540,00
11 Pompa Sub.M. Non Clogging 30 l/dt H = 30 m Unit p.l 100.440.000,00
12 Pompa Sub.M. Non Clogging 40 l/dt H = 30 m Unit p.l 140.810.400,00
13 Pompa Sub.M. Non Clogging 50 l/dt H = 30 m Unit p.l 145.800.000,00
14 Pompa Centrifugal 5 l/dt H=60 m Unit p.l 33.222.830,00
15 Pompa Centrifugal 10 l/dt H=60 m Unit p.l 38.534.793,00
16 Pompa Centrifugal 15 l/dt H=60 m Unit p.l 41.843.573,33
17 Pompa Centrifugal 20 l/dt H=60 m Unit p.l 66.328.145,00
18 Pompa Centrifugal 25 l/dt H=60 m Unit p.l 69.578.000,00
19 Pompa Centrifugal 30 l/dt H=60 m Unit p.l 89.450.556,00
20 Pompa Centrifugal 40 l/dt H=60 m Unit p.l 105.184.361,00
21 Pompa Centrifugal 50 l/dt H=60 m Unit p.l 138.004.220,00
22 Pompa Centrifugal 75 l/dt H=60 m Unit p.l 161.480.620,00
23 Genset 10 KVA Unit p.l 139.541.066,67
24 Genset 15 KVA Unit p.l 147.572.493,33
25 Genset 20 KVA Unit p.l 155.048.740,00
26 Genset 25 KVA Unit p.l 174.386.686,67
27 Genset 30 KVA Unit p.l 182.429.006,67
28 Genset 40 KVA Unit p.l 195.507.720,00
29 Genset 45 KVA Unit p.l 214.916.346,67
30 Genset 50 KVA Unit p.l 236.470.200,00
31 Genset 60 KVA Unit p.l 241.232.803,33
32 Genset 75 KVA Unit p.l 245.995.406,67
33 Genset 80 KVA Unit p.l 274.455.000,00
34 Genset 88 KVA Unit p.l 293.512.000,00
35 Genset 100 KVA Unit p.l 325.100.766,67
36 Genset 125 KVA Unit p.l 366.279.118,08
37 Genset 135 KVA Unit p.l 407.457.470,00
38 Genset 150 KVA Unit p.l 439.352.390,00
39 Panel Pompa / Genset / Induk / MDP lengkap Unit p.l 34.955.550,00
40 Panel Pompa Dozing Kimia lengkap Unit p.l 22.513.140,00
41 Pompa Dozing Unit p.l 46.392.340,00
42 Wash Out DN 150 x 75 mm lengkap Box Valve Beton 1:2:3 Unit sub parsial 15 14.016.844,94
43 Air valve DN 200 x 25 mm lengkap Box Pas. Bata 1:2:3 Unit parsial 9 3.821.000,00
44 Jembatan Pipa DN 200 mm Tipe Gantung per M' M' parsial 13.a2 6.928.137,93
45 Jembatan Pipa DN 200 mm dengan Gelagar per M' M' parsial 13.a 4.284.722,22
46 Jembatan Pipa DN 150 mm dengan Gelagar per M' M' parsial 13.b 3.258.500,00
47 Cross Jalan DN 200 mm M' parsial 14.a 2.241.500,00
48 Cross Jalan DN 150 mm M' parsial 14.b 1.642.200,00
49 Penyeberangan Bawah Sungai (SIPHON) Pipa DN 150 MM M' parsial 15 1.918.825,00
50 Pengadaan Pipa GIP DN 200 mm Medium M' p.l 1.044.651,80
51 Pengadaan Pipa GIP DN 150 mm Medium M' p.l 686.603,80
52 Pengadaan Pipa GIP DN 100 mm Medium M' p.l 438.091,10
53 Pengadaan Pipa GIP DN 75 mm Medium M' p.l 305.777,00
54 Pengadaan Pipa GIP DN 50 mm Medium M' p.l 182.514,30
55 Pengadaan Pipa PVC DN 200 mm RRJ, S 12,5 M' p.l 339.205,39
56 Pengadaan Pipa PVC DN 150 mm RRJ, S 12,5 M' p.l 219.842,14
57 Pengadaan Pipa PVC DN 100 mm RRJ, S 12,5 M' p.l 103.047,35
58 Pengadaan Pipa PVC DN 75 mm RRJ, S 12,5 M' p.l 69.717,49
59 Pengadaan Pipa PVC DN 50 mm SCJ S 10 M' p.l 34.164,86
60 Pengadaan Pipa PE DN 200 mm NP 10 M' p.l 597.534,35
61 Pengadaan Pipa PE DN 150 mm NP 10 M' p.l 383.774,35
62 Pengadaan Pipa PE DN 100 mm NP 10 M' p.l 181.944,83
63 Pengadaan Pipa PE DN 75 mm NP 10 M' p.l 103.399,72
64 Pengadaan Pipa PE DN 50 mm NP 10 M' p.l 46.728,27
65 Pemasangan pipa GIP DN 200 Galian Tanah Normal M' Anls. Taksir 29.065,58
66 Pemasangan pipa GIP DN 150 Galian Tanah Normal M' Anls. Taksir 20.965,85
67 Pemasangan pipa GIP DN 100 Galian Tanah Normal M' Anls. Taksir 18.106,02
68 Pemasangan pipa GIP DN 75 Galian Tanah Normal M' Anls. Taksir 16.199,46
69 Pemasangan pipa GIP DN 50 Galian Tanah Normal M' Anls. Taksir 12.866,13
70 Pemasangan pipa PVC DN 200 Galian Tanah Normal M' Anls. Taksir 24.898,92
71 Pemasangan pipa PVC DN 150 Galian Tanah Normal M' Anls. Taksir 22.175,26
72 Pemasangan pipa PVC DN 100 Galian Tanah Normal M' Anls. Taksir 17.272,68
73 Pemasangan pipa PVC DN 75 Galian Tanah Normal M' Anls. Taksir 12.866,13
74 Pemasangan pipa PVC DN 50 Galian Tanah Normal M' Anls. Taksir 45.124,43
75 Pemasangan pipa PE DN 200 Galian Tanah Normal M' Anls. Taksir 109.651,23
76 Pemasangan pipa PE DN 150 Galian Tanah Normal M' Anls. Taksir 85.002,30
77 Pemasangan pipa PE DN 100 Galian Tanah Normal M' Anls. Taksir 60.352,38
78 Pemasangan pipa PE DN 75 Galian Tanah Normal M' Anls. Taksir 59.219,04
79 Pemasangan pipa PE DN 50 Galian Tanah Normal M' Anls. Taksir 59.219,04
80 Pemasangan pipa GIP DN 200 Galian Tanah Cadas Berbatu M' Anls. Taksir 29.065,58
81 Pemasangan pipa GIP DN 150 Galian Tanah Cadas Berbatu M' Anls. Taksir 20.965,85
82 Pemasangan pipa GIP DN 100 Galian Tanah Cadas Berbatu M' Anls. Taksir 18.106,02
83 Pemasangan pipa GIP DN 75 Galian Tanah Cadas Berbatu M' Anls. Taksir 16.199,46
84 Pemasangan pipa GIP DN 50 Galian Tanah Cadas Berbatu M' Anls. Taksir 12.866,13
85 Pemasangan pipa PVC DN 200 Galian Tanah Cadas Berbatu M' Anls. Taksir 24.898,92
86 Pemasangan pipa PVC DN 150 Galian Tanah Cadas Berbatu M' Anls. Taksir 22.175,26
87 Pemasangan pipa PVC DN 100 Galian Tanah Cadas Berbatu M' Anls. Taksir 17.272,68
88 Pemasangan pipa PVC DN 75 Galian Tanah Cadas Berbatu M' Anls. Taksir 12.866,13
89 Pemasangan pipa PVC DN 50 Galian Tanah Cadas Berbatu M' Anls. Taksir 45.124,43
90 Pemasangan pipa PE DN 200 Galian Tanah Cadas Berbatu M' Anls. Taksir 109.651,23
91 Pemasangan pipa PE DN 150 Galian Tanah Cadas Berbatu M' Anls. Taksir 85.002,30
92 Pemasangan pipa PE DN 100 Galian Tanah Cadas Berbatu M' Anls. Taksir 60.352,38
93 Pemasangan pipa PE DN 75 Galian Tanah Cadas Berbatu M' Anls. Taksir 59.219,04
94 Pemasangan pipa PE DN 50 Galian Tanah Cadas Berbatu M' Anls. Taksir 59.219,04
95 Pengetesan dan Pengurasan Pipa DN 200 mm M' Anls. Taksir 5.509,41
96 Pengetesan dan Pengurasan Pipa DN 150 mm M' Anls. Taksir 4.571,96
97 Pengetesan dan Pengurasan Pipa DN 100 mm M' Anls. Taksir 3.736,82
98 Pengetesan dan Pengurasan Pipa DN 75 mm M' Anls. Taksir 3.031,55
99 Harga Rata Biaya Pengurasan pipa 4.212,44
100 Pengetesan dan Pengurasan Pipa DN 50 mm M' Anls. Taksir 2.357,46
101 Meter Induk (sistem 20 L/dt) lengkap Box Beton 1:2:3 Unit parsial 10.a 84.285.000,00
102 Meter Induk (sistem 10 L/dt) lengkap Box Beton 1:2:3 Unit parsial 10.b 41.874.000,00
103 Meter Induk (sistem 6 L/dt) lengkap Box Beton 1:2:3 Unit parsial 10.c 38.310.000,00
104 Flow Meter (Flap) DN 8" Unit p.l 19.440.000,00
105 Flow Meter (Flap) DN 6" Unit p.l 15.714.000,00
106 Paket IPA 10 L/dt Unit p.l 2.110.554.600,00
107 Paket IPA 20 L/dt Unit p.l 3.037.019.333,33
108 Bangunan Atap IPA Unit parsial 6. 34.691.000,00
109 Pondasi IPA Unit parsial 7. 88.408.000,00
110 Reservoir 80 m3 Beton K 225 M3 parsial 2.a 5.619.237,50
111 Reservoir 100 m3 Beton K 225 M3 parsial 2.b 5.352.700,00
113 Reservoir 150 m3 Beton K 225 M3 parsial 2.c 4.784.940,00
112 Reservoir 300 m3 Beton K 225 M3 parsial 2.d 3.162.603,33
113 Reservoir 700 m3 Beton K 225 M3 4.427.644,67
115 Bak Penampung Lumpur (SDB) 100 m3, Pasangan bata 1:2 Unit parsial 4.b 122.044.000,00
116 Tangki lengkap pondasi beton 1:2:3 kap. 5000 L Unit parsial 8.a 33.581.000,00
117 Tangki lengkap pondasi beton 1:2:3 kap. 3000 L Unit parsial 8.b 24.010.000,00
118 Rumah Operasional IPA & Rumah Jaga M2 parsial 5.a 5.914.240,74
119 Rumah Genset & Rumah Pompa (dengan Pondasi) M2 parsial 5.b 10.822.156,25
120 Lansekap per 100 m2 luas lahan IPA 100 M2 parsial 16 24.000.000,00
121 Drainase 30x40x40 dari M' parsial 11.b 293.587,50
122 Jalan Inspeksi dari beton 1:2:3 M3 Supl. SN BT 6.5 210.278,40
123 Pagar BRC (lengkap pintu dan tiang 1.5m) M' parsial 12 387.770,00
124 Lampu CFL - 250 watt termasuk tiang 6 m Unit p.l 7.500.000,00
125 Penangkal Petir Unit p.l 2.400.000,00
126 Pekerjaan dan pemasangan tiang listrik btg - 25.000.000,00
PROYEK PENYUSUNAN DED SPAM IKK 2019

#REF! #REF!
KEGIATAN PENGEMBANGAN DISTRIBUSI AIR MINUM
PEKERJAAN PEMBANGUNAN INSTALASI PENGOLAHAN AIR BERSIH (IPA) PDAM KP.50 L/Dtk IKK SELAKAU
LOKASI KEC. SELAKAU, KABUPATEN SAMBAS
TAHUN ANGGARAN 2019

DAFTAR ANALISA HARGA SATUAN PEKERJAAN (SNI-02)

Pekerjaan GALIAN & TIMBUNAN PIPA


1 An. TSN 6.1 : 1 m³ Galian Tanah :
0,750 OH Pekerja @ Rp. 104.545,00 Rp. 78.408,75
0,025 OH Mandor @ Rp. 145.454,00 Rp. 3.636,35
Jumlah = Rp. 82.045,10

2 An. TSN 6.6 1m³ Galian Tanah Lumpur :


0,823 OH Pekerja @ Rp. 104.545,00 Rp. 86.040,54
0,083 OH Mandor @ Rp. 145.454,00 Rp. 12.072,68
Jumlah = Rp. 98.113,22

3 An. TSN 6.4 1m³ Galian Tanah Keras :


0,625 OH Pekerja @ Rp. 104.545,00 Rp. 65.340,63
0,062 OH Mandor @ Rp. 145.454,00 Rp. 9.018,15
Jumlah = Rp. 74.358,77
4 An. TSN 6.6 1m³ Galian Tanah Cadas berbatu :
1,250 OH Pekerja @ Rp. 104.545,00 Rp. 130.681,25
0,125 OH Mandor @ Rp. 145.454,00 Rp. 18.181,75
Jumlah = Rp. 148.863,00

5 An. TSN 6.8 : 1 m³ Buang Tanah Galian sejauh 150 m :


0,516 OH Pekerja @ Rp. 104.545,00 Rp. 53.945,22
0,050 OH Mandor @ Rp. 145.454,00 Rp. 7.272,70
Jumlah = Rp. 61.217,92

Total Galian tanah dibuang ( TSN 6.1 + TSN 6.8 ) . . . . . . . . . . . Rp. 143.263,02

6 An. TSN 6.15 1 m³ Timbunan Sirtu/Krikil Kotor dipadatkan dgn Gilas


1,200 m³ Sirtu / Kerikil Kotor @ Rp. 195.454,00 Rp. 234.544,80
0,250 OH Pekerja @ Rp. 104.545,00 Rp. 26.136,25
0,025 OH Mandor @ Rp. 145.454,00 Rp. 3.636,35
1/7500 Biaya Gilas @ Rp. 104.195.649,00 Rp. 13.892,75
Jumlah = Rp. 264.317,40

7 An. W4 Biaya Gilas.


25 hr Sewa Mesin Gilas @ Rp. 1.192.727,00 Rp. 29.818.175,00
25 hr Masinis @ Rp. 136.363,00 Rp. 3.409.075,00
30 hr Penjaga Malam @ Rp. 90.909,00 Rp. 2.727.270,00
500 ltr Minyak Solar @ Rp. 6.727,00 Rp. 3.363.500,00
15 ltr Minyak Pelumas @ Rp. 4.247.727,00 Rp. 63.715.905,00
4 ltr Minyak Gardan @ Rp. 39.181,00 Rp. 156.724,00
5 ltr Minyak Gemuk @ Rp. 51.000,00 Rp. 255.000,00
Ls Pemeliharaan @ Rp. 750.000,00 Rp. 750.000,00
Jumlah = Rp. 104.195.649,00
8 An. TSN 6.9 1 m³ Timbunan Tanah :
0,192 OH Pekerja @ Rp. 104.545,00 Rp. 20.072,64
0,019 OH Mandor @ Rp. 145.454,00 Rp. 2.763,63
Jumlah = Rp. 22.836,27

9 An. TSN 6.11 1 m³ Timbunan Pasir Urug dipadatkan :


1,200 m³ Pasir Urug @ Rp. 195.454,00 Rp. 234.544,80
0,300 OH Pekerja @ Rp. 104.545,00 Rp. 31.363,50
0,010 OH Mandor @ Rp. 145.454,00 Rp. 1.454,54
Rp. 267.362,84
Pekerjaan BATU KALI

10 An.SNBK 6.14 1 m³ Pasangan Batu kosong :


1,200 m³ Batu Kali 15/20 cm @ Rp. 316.181,00 Rp. 379.417,20
0,780 OH Pekerja @ Rp. 104.545,00 Rp. 81.545,10
0,078 OH Mandor @ Rp. 145.454,00 Rp. 145.454,00
Rp. 606.416,30
11 An.SNBK 6.5 1m³ Pasangan batu kali camp. 1 : 4
1,100 m³ Batu kali @ Rp. 316.181,00 Rp. 347.799,10
136,000 Kg Semen Portland @ Rp. 1.721,00 Rp. 234.056,00
0,522 m³ Psr pasang @ Rp. 241.454,00 Rp. 126.038,99
1,500 OH Pekerja @ Rp. 104.545,00 Rp. 156.817,50
0,600 OH Tukang batu @ Rp. 113.636,00 Rp. 68.181,60
0,060 OH Kpl. Tukang @ Rp. 159.090,00 Rp. 9.545,40
0,075 OH Mandor @ Rp. 145.454,00 Rp. 145.454,00
Rp. 1.087.892,59
Pekerjaan BETON

12 An. SN BT 6.4 1 m³ Beton Cor ( 1: 3 : 5 ).


218,000 Kg Portland Cement @ Rp. 1.721,00 Rp. 375.178,00
0,520 m³ Pasir Pasang @ Rp. 241.454,00 Rp. 125.556,08
0,870 m³ Koral Beton @ Rp. 500.181,00 Rp. 435.157,47
Bahan = 500.734,08
1,650 OH Pekerja @ Rp. 104.545,00 Rp. 172.499,25
0,250 OH Tukang Batu @ Rp. 113.636,00 Rp. 28.409,00
0,025 OH Kepala Tukang @ Rp. 159.090,00 Rp. 3.977,25
0,080 OH Mandor @ Rp. 145.454,00 Rp. 11.636,32
Upah = 216.521,82
Bahan & Upah = Rp. 717.255,90

13 An. Supl. SN BT 6.4 1 m³ Lantai Dasar - Beton Cor ( 1: 3 : 5 ).


( An. SN BT 6.4 + An. SN PF 6.33 ) Beton Cor + Bekisting Dinding Beton Rp. 1.844.860,11

14 An. Supl. SN BT 6.4-b1 M³ Beton Cor camp. 1: 3 : 5


( An. SN BT 6.4 + An. SN PF 6.32 ) Beton Cor + Bekisting Atap/Lantai Rp. 1.064.697,81

15 An. PF 6.33 1 m² Bekisting Dinding Beton (Plat Form/ Cetakan ).


0,030 m³ Kayu Terentang @ Rp. 1.466.086,00 Rp. 43.982,58
0,400 kg Paku 2'-5' @ Rp. 19.090,00 Rp. 7.636,00
0,020 m³ Balok Kayu Borneo @ Rp. 1.681.813,00 Rp. 33.636,26
0,020 lbr Papan Kelas II @ Rp. 1.333.445,00 Rp.
0,350 lbr Plywood t= 9 mm @ Rp. 145.000,00 Rp. 50.750,00
3,000 bh Dolken Galam Φ 8-10/4 m @ Rp. 11.659,00 Rp. 34.977,00
0,200 ltr Minyak Bekisting @ Rp. 4.247.727,00 Rp. 849.545,40
4,000 bh Formtie /Spacer @ Rp. 7.500,00 Rp. 30.000,00
Bahan = Rp. 1.050.527,24
0,320 OH Pekerja @ Rp. 104.545,00 Rp. 33.454,40
0,330 OH Tukang kayu @ Rp. 113.636,00 Rp. 37.499,88
0,033 OH Kepala Tukang @ Rp. 159.090,00 Rp. 5.249,97
0,006 OH Mandor @ Rp. 145.454,00 Rp. 872,72
Upah = Rp. 77.076,97
1 m² Kayu Cetakan . . . . Bahan & Upah = Rp. 1.127.604,21

16 An. PF 6.32 1 m² Bekisting Lantai/Atap Beton (Plat Form/ Cetakan ).


0,040 m³ Kayu Terentang @ Rp. 1.466.086,00 Rp. 58.643,44
0,400 kg Paku 2'-5' @ Rp. 19.090,00 Rp. 7.636,00
0,015 m³ Balok Kayu Borneo @ Rp. 1.681.813,00 Rp. 25.227,20
0,350 lbr Plywood t= 9 mm @ Rp. 168.818,00 Rp. 59.086,30
6,000 bh Dolken Galam Φ 8-10/4 m @ Rp. 11.659,00 Rp. 69.954,00
0,200 ltr Minyak Bekisting @ Rp. 24.090,00 Rp. 4.818,00
6,000 bh Formtie /Spacer @ Rp. 7.500,00 Rp. 45.000,00
Bahan = Rp. 270.364,94
0,320 OH Pekerja @ Rp. 104.545,00 Rp. 33.454,40
0,330 OH Tukang kayu @ Rp. 113.636,00 Rp. 37.499,88
0,033 OH Kepala Tukang @ Rp. 159.090,00 Rp. 5.249,97
0,006 OH Mandor @ Rp. 145.454,00 Rp. 872,72
Upah = Rp. 77.076,97
1 m² Kayu Cetakan . . . . . . . . Bahan & Upah = Rp. 347.441,91

17 An.SN BT 6.5 1m³ Beton cor camp. 1 : 2 : 3 .


232,000 Kg Semen Portland @ Rp. 1.721,00 Rp. 399.272,00
0,520 m³ Psr beton @ Rp. 241.454,00 Rp. 125.556,08
0,780 m³ Koral beton @ Rp. 500.181,00 Rp. 390.141,18

1,650 OH Pekerja @ Rp. 104.545,00 Rp. 172.499,25


0,250 OH Tukang batu @ Rp. 113.636,00 Rp. 28.409,00
0,025 OH Kpl. Tukang @ Rp. 159.090,00 Rp. 3.977,25
0,080 OH Mandor @ Rp. 145.454,00 Rp. 11.636,32
Jumlah = Rp. 1.131.491,08

18 Supl.-SN BT 6.5 1 m3 Beton Tulang (1:2:3) : (An. SN BT 6.5 + An. PF 6.32 + An.SN BS 6.43)+ Bekisting ..................
Rp. 5.020.221,50
19 An.SN BS 6.43 100 kg Besi Beton
Bahan:
110,000 Kg Besi Beton @ Rp. 26.500,00 Rp. 2.915.000,00
2,000 Kg Kawat beton @ Rp. 28.750,00 Rp. 57.500,00
Jumlah = Rp. 2.972.500,00
Upah Kerja :
3,630 OH Pekerja @ Rp. 104.545,00 Rp. 379.498,35
1,050 OH Tukang besi @ Rp. 113.636,00 Rp. 119.317,80
0,342 OH Kpl. Tukang @ Rp. 159.090,00 Rp. 54.408,78
0,107 OH Mandor @ Rp. 145.454,00 Rp. 15.563,58
Jumlah = Rp. 568.788,51
Jumlah Upah & bahan = Rp. 3.541.288,51
Harga / Kg Rp. 35.412,89
19b "SNI 2002: 6.23 1 m' Pemasangan Waterstop Lebar 300 mm
Bahan:
1,050 m' Waterstop @ Rp. 30.000,00 Rp. 31.500,00
Jumlah = Rp. 31.500,00
Upah Kerja :
0,550 OH Pekerja @ Rp. 104.545,00 Rp. 57.499,75
0,035 OH Tukang batu @ Rp. 113.636,00 Rp. 3.977,26
0,003 OH Mandor @ Rp. 145.454,00 Rp. 436,36
Jumlah = Rp. 61.913,37
Total UP dan Bahan Rp. 93.413,37

20 Anls. G.41.a : 1 m3 Beton 1Pc : 1,5Ps : 2,5Krl = K 225


Upah Kerja :
1,6500 OH Pekerja @ Rp. 104.545,00 Rp. 172.499,25
0,2500 OH Tukang batu @ Rp. 104.545,00 Rp. 26.136,25
0,0250 OH Kepala tukang batu @ Rp. 159.090,00 Rp. 3.977,25
0,0800 OH Mandor @ Rp. 145.454,00 Rp. 11.636,32
Bahan:
7,4200 Zak Semen /PC @ Rp. 86.090,00 Rp. 638.787,80
1,0470 m³ Kerikil @ Rp. 500.181,00 Rp. 523.689,51
0,6980 m³ Pasir Beton @ Rp. 241.454,00 Rp. 168.534,89
1.545.261,27
21 Anls. SP.I : 1 Kg Pekerjaan Pembesian
Upah Kerja :
0,0700 OH Pekerja @ Rp. 104.545,00 Rp. 7.318,15
0,0700 OH Tukang besi @ Rp. 113.636,00 Rp. 7.954,52
0,0070 OH Kepala tukang besi @ Rp. 159.090,00 Rp. 1.113,63
0,0040 OH Mandor @ Rp. 145.454,00 Rp. 581,82
Bahan:
1,0500 Kg Besi Beton (polos/ulir) @ Rp. 26.500,00 Rp. 27.825,00
0,0150 Kg Kawat Beton @ Rp. 28.750,00 Rp. 431,25
45.224,37

22 Anls. B.1.d : 1 m2 Bikisting untuk Lantai / Atap


Upah Kerja :
0,6600 OH Pekerja @ Rp. 104.545,00 Rp. 68.999,70
0,3300 OH Tukang kayu @ Rp. 113.636,00 Rp. 37.499,88
0,0330 OH Kepala tukang kayu @ Rp. 159.090,00 Rp. 5.249,97
0,0330 OH Mandor @ Rp. 145.454,00 Rp. 4.799,98
Bahan:
0,0400 m3 Kayu papan kls III @ Rp. 1.681.813,00 Rp. 67.272,52
0,4000 Kg Paku @ Rp. 19.090,00 Rp. 7.636,00
0,0150 m3 Balok Kayu kls II @ Rp. 3.054.545,00 Rp. 45.818,18
0,3500 Lbr Plywood tebal 9 mm @ Rp. 168.818,00 Rp. 59.086,30
6,0000 Btg Dolken Kayu galam, @ Rp. 11.659,00 Rp. 69.954,00
366.316,53

23 Anls. B.1.e : 1 m2 Bikisting untuk dinding


Upah Kerja :
0,6600 OH Pekerja @ Rp. 104.545,00 Rp. 68.999,70
0,3300 OH Tukang kayu @ Rp. 113.636,00 Rp. 37.499,88
0,0330 OH Kepala tukang kayu @ Rp. 159.090,00 Rp. 5.249,97
0,0330 OH Mandor @ Rp. 145.454,00 Rp. 4.799,98
Bahan:
0,0300 m3 Kayu papan kls III @ Rp. 1.681.813,00 Rp. 50.454,39
0,4000 Kg Paku @ Rp. 19.090,00 Rp. 7.636,00
0,0200 m3 Balok Kayu kls II @ Rp. 3.054.545,00 Rp. 61.090,90
0,3500 Lbr Plywood tebal 9 mm @ Rp. 168.818,00 Rp. 59.086,30
3,0000 Btg Dolken Kayu galam, @ Rp. 11.659,00 Rp. 34.977,00
4,0000 Bh. Formite/penjaga jarak @ Rp. 12.500,00 Rp. 50.000,00
bekisting/spcer @ Rp. Rp. 0,00
379.794,12
24 An. G.41 (Spl. V) : 1 m3 Pek. Beton plat lantai/atap dg. Besi 110 kg = K-225
Upah Kerja :
6,0000 OH Pekerja @ Rp. 104.545,00 Rp. 627.270,00
1,0000 OH Tukang batu @ Rp. 113.636,00 Rp. 113.636,00
0,1000 OH Kepala tukang batu @ Rp. 159.090,00 Rp. 15.909,00
0,3000 OH Mandor @ Rp. 145.454,00 Rp. 43.636,20

Bahan:
1,0000 m3 Beton K-225 @ Rp. 1.545.261,27 Rp. 1.545.261,27
6,0000 m2 Cetakan beton atap @ Rp. 366.316,53 Rp. 2.197.899,16
110,0000 Kg Besi beton @ Rp. 26.500,00 Rp. 2.915.000,00
1,0000 Ls Siram/buka bekisting @ Rp. 45.000,00 Rp. 45.000,00
7.503.611,63

25 An. G.41 (Spl. V.4) : 1 m3 Pek. Beton Dinding dengan besi 110 kg = K-225
Upah Kerja :
6,0000 OH Pekerja @ Rp. 104.545,00 Rp. 627.270,00
1,0000 OH Tukang batu @ Rp. 113.636,00 Rp. 113.636,00
0,1000 OH Kepala tukang batu @ Rp. 159.090,00 Rp. 15.909,00
0,3000 OH Mandor @ Rp. 145.454,00 Rp. 43.636,20
Bahan:
1,0000 m3 Beton K-225 @ Rp. 1.545.261,27 Rp. 1.545.261,27
7,5000 m2 Cetakan beton Dinding @ Rp. 379.794,12 Rp. 2.848.455,92
110,0000 Kg Besi beton @ Rp. 26.500,00 Rp. 2.915.000,00
1,0000 Ls Siram/buka bekisting @ Rp. 45.000,00 Rp. 45.000,00
8.154.168,38

26 An.SN BT 6.2 1 m³ beton cor camp. 1 : 3 : 6


197,000 Kg Portland Cement @ Rp. 1.721,00 Rp. 339.037,00
0,470 m³ Psr beton @ Rp. 241.454,00 Rp. 113.483,38
0,940 m³ Kerikil @ Rp. 500.181,00 Rp. 470.170,14
Jumlah = Rp. 922.690,52

1,650 OH Pekerja @ Rp. 104.545,00 Rp. 172.499,25


0,250 OH Tukang batu @ Rp. 113.636,00 Rp. 28.409,00
0,025 OH Kpl. Tukang @ Rp. 159.090,00 Rp. 3.977,25
0,080 OH Mandor @ Rp. 145.454,00 Rp. 11.636,32
Jumlah = Rp. 216.521,82
Jumlah Upah & bahan = Rp. 1.139.212,34

27 Supl An.SN BT 6.2 1m² Lantai Beton camp. 1:3:6 tebal 7 cm ditutup dengan
selapis plesteran tebal 6 mm camp. 1 : 3
20,017 Kg Portland Cement @ Rp. 1.721,00 Rp. 34.448,68
0,048 m³ Psr beton @ Rp. 241.454,00 Rp. 11.630,03
0,078 m³ Kerikil @ Rp. 500.181,00 Rp. 39.180,85

0,222 OH Pekerja @ Rp. 104.545,00 Rp. 23.156,72


0,088 OH Tukang batu @ Rp. 113.636,00 Rp. 9.981,03
0,009 OH Kpl. Tukang @ Rp. 159.090,00 Rp. 1.445,07
0,012 OH Mandor @ Rp. 145.454,00 Rp. 1.696,96
Jumlah Upah & bahan = Rp. 121.539,34

28 An.SN BTM 6.11 1 m2 Pasangan dinding bata tembok 1/2 batu camp. 1 : 4
70,000 bh Batu bata @ Rp. 2.727,00 Rp. 190.890,00
11,500 kg Portland Cement @ Rp. 1.721,00 Rp. 19.791,50
0,043 m³ Pasir Pasang @ Rp. 241.454,00 Rp. 10.382,52

0,320 OH Pekerja @ Rp. 104.545,00 Rp. 33.454,40


0,100 OH Tukang batu @ Rp. 113.636,00 Rp. 11.363,60
0,010 OH Kpl. Tukang @ Rp. 159.090,00 Rp. 1.590,90
0,015 OH Mandor @ Rp. 145.454,00 Rp. 2.181,81
Jumlah Upah & bahan = Rp. 269.654,73

Membuat beton Mutu K. 300/ m3


1,650 OH Pekerja @ Rp. 104.545,00 Rp. 172.499,25
0,275 OH Tukang batu @ Rp. 113.636,00 Rp. 31.249,90
0,028 OH Kpl. Tukang @ Rp. 159.090,00 Rp. 4.454,52
0,083 OH Mandor @ Rp. 145.454,00 Rp. 12.072,68
Jumlah = Rp. 493.703,79

413,000 Kg Portland Cement @ Rp. 1.721,00 Rp. 710.773,00


681,000 m³ Psr beton @ Rp. 241.454,00 Rp. 164.430.174,00
1.021,000 m³ Kerikil 1-2 cm @ Rp. 661.818,00 Rp. 675.716.178,00
Jumlah = Rp. 840.857.125,00
Jumlah Upah & bahan = Rp. 841.350.828,79

29 An.SN PS 6.13 1m² Pelesteran kedap air Camp. 1 : 2 tebal 20 mm


14,280 Kg Portland Cement @ Rp. 1.721,00 Rp. 24.575,88
0,023 m³ Pasir Pasang @ Rp. 241.454,00 Rp. 5.553,44

0,250 OH Pekerja @ Rp. 104.545,00 Rp. 26.136,25


0,200 OH Tukang batu @ Rp. 113.636,00 Rp. 22.727,20
0,020 OH Kepala Tukang @ Rp. 159.090,00 Rp. 3.181,80
0,013 OH Mandor @ Rp. 145.454,00 Rp. 1.818,18
Jumlah Upah & bahan = Rp. 83.992,75
ANALISA TAKSIR PEMASANGAN PIPA PVC

30 An. Taksir 6 m Pemasangan Pipa PVC ø 50 mm :


0,200 OH Pekerja @ Rp. 104.545,00 = Rp. 20.909,00
0,067 OH Mandor @ Rp. 145.454,00 = Rp. 9.696,93
0,133 OH Tukang Pasang Pipa @ Rp. 113.636,00 = Rp. 15.151,47
Ls Peralatan @ Rp. 20.000,00 = Rp. 20.000,00
6,000 btg PVC D. 50 mm @ Rp. 34.164,86 = Rp. 204.989,16
Jumlah = = Rp. 270.746,56
1 m' Pemasangan Pipa PVC ø 50 mm = 1/6 x Rp. 270.746,56 = Rp. 45.124,43

31 An. Taksir 6 m Pemasangan Pipa PVC ø 75 mm :


0,250 OH Pekerja @ Rp. 104.545,00 = Rp. 26.136,25
0,083 OH Mandor @ Rp. 145.454,00 = Rp. 12.121,17
0,167 OH Tukang Pasang Pipa @ Rp. 113.636,00 = Rp. 18.939,33
Ls Peralatan @ Rp. 20.000,00 = Rp. 20.000,00
Jumlah = = Rp. 77.196,75
1 m' Pemasangan Pipa PVC ø 75 mm = 1/6 x Rp. 77.196,75 = Rp. 12.866,13

32 An. Taksir 6 m Pemasangan Pipa PVC ø 100 mm :


0,300 OH Pekerja @ Rp. 104.545,00 = Rp. 31.363,50
0,100 OH Mandor @ Rp. 145.454,00 = Rp. 14.545,40
0,200 OH Tukang Pasang Pipa @ Rp. 113.636,00 = Rp. 22.727,20
Ls Peralatan @ Rp. 35.000,00 = Rp. 35.000,00
Jumlah = = Rp. 103.636,10
1 m' Pemasangan Pipa PVC ø 100 mm = 1/6 x Rp. 103.636,10 = Rp. 17.272,68

33 An. Taksir 6 m Pemasangan Pipa PVC ø 150 mm :


0,429 OH Pekerja @ Rp. 104.545,00 = Rp. 44.805,00
0,143 OH Mandor @ Rp. 145.454,00 = Rp. 20.779,14
0,286 OH Tukang Pasang Pipa @ Rp. 113.636,00 = Rp. 32.467,43
Ls Peralatan @ Rp. 35.000,00 = Rp. 35.000,00
Jumlah = = Rp. 133.051,57
1 m' Pemasangan Pipa PVC ø 150 mm = 1/6 x Rp. 133.051,57 = Rp. 22.175,26

34 An. Taksir 6 m Pemasangan Pipa PVC ø 200 mm :


0,500 OH Pekerja @ Rp. 104.545,00 = Rp. 52.272,50
0,167 OH Mandor @ Rp. 145.454,00 = Rp. 24.242,33
0,333 OH Tukang Pasang Pipa @ Rp. 113.636,00 = Rp. 37.878,67
Ls Peralatan @ Rp. 35.000,00 = Rp. 35.000,00
Jumlah = = Rp. 149.393,50
1 m' Pemasangan Pipa PVC ø 200 mm = 1/6 x Rp. 149.393,50 = Rp. 24.898,92

35 An. Taksir 6 m Pemasangan Pipa PVC ø 250 mm :


0,600 OH Pekerja @ Rp. 104.545,00 = Rp. 62.727,00
0,200 OH Mandor @ Rp. 145.454,00 = Rp. 29.090,80
0,400 OH Tukang Pasang Pipa @ Rp. 113.636,00 = Rp. 45.454,40
Ls Peralatan @ Rp. 50.000,00 = Rp. 50.000,00
Jumlah = = Rp. 187.272,20
1 m' Pemasangan Pipa PVC ø 250 mm = 1/6 x Rp. 187.272,20 = Rp. 31.212,03

36 An. Taksir 6 m Pemasangan Pipa PVC ø 300 mm :


0,750 OH Pekerja @ Rp. 104.545,00 = Rp. 78.408,75
0,250 OH Mandor @ Rp. 145.454,00 = Rp. 36.363,50
0,500 OH Tukang Pasang Pipa @ Rp. 113.636,00 = Rp. 56.818,00
Ls Peralatan @ Rp. 50.000,00 = Rp. 50.000,00
Jumlah = = Rp. 221.590,25
1 m' Pemasangan Pipa PVC ø 300 mm = 1/6 x Rp. 221.590,25 = Rp. 36.931,71

37 An. Taksir 6 m Pemasangan Pipa PVC ø 350 mm :


1,000 OH Pekerja @ Rp. 104.545,00 = Rp. 104.545,00
0,333 OH Mandor @ Rp. 145.454,00 = Rp. 48.484,67
0,667 OH Tukang Pasang Pipa @ Rp. 113.636,00 = Rp. 75.757,33
Ls Peralatan @ Rp. 75.000,00 = Rp. 75.000,00
Jumlah = = Rp. 303.787,00
1 m' Pemasangan Pipa PVC ø 350 mm = 1/6 x Rp. 303.787,00 = Rp. 50.631,17

38 An. Taksir 6 m Pemasangan Pipa PVC ø 400 mm :


1,500 OH Pekerja @ Rp. 104.545,00 = Rp. 156.817,50
0,500 OH Mandor @ Rp. 145.454,00 = Rp. 72.727,00
1,000 OH Tukang Pasang Pipa @ Rp. 113.636,00 = Rp. 113.636,00
Ls Peralatan @ Rp. 75.000,00 = Rp. 75.000,00
Jumlah = = Rp. 418.180,50
1 m' Pemasangan Pipa PVC ø 400 mm = 1/6 x Rp. 418.180,50 = Rp. 69.696,75
ANALISA TAKSIR PEMASANGAN PIPA STEEL/GIP

39 An. Taksir 6 m Pemasangan Pipa Steel/GIP ø 50 mm


0,250 OH Pekerja @ Rp. 104.545,00 = Rp. 26.136,25
0,083 OH Mandor @ Rp. 145.454,00 = Rp. 12.121,17
0,167 OH Tukang Pasang Pipa @ Rp. 113.636,00 = Rp. 18.939,33
0,100 Peralatan (Tracker) @ Rp. 200.000,00 = Rp. 20.000,00
Jumlah = Rp. 77.196,75
1 m' Pemasangan Pipa Steel ø 75 mm = 1/6 x Rp. 77.196,75 = Rp. 12.866,13

40 An. Taksir 6 m Pemasangan Pipa Stee/GIP ø 75 mm


0,250 OH Pekerja @ Rp. 104.545,00 = Rp. 26.136,25
0,083 OH Mandor @ Rp. 145.454,00 = Rp. 12.121,17
0,167 OH Tukang Pasang Pipa @ Rp. 113.636,00 = Rp. 18.939,33
0,200 Peralatan (Tracker) @ Rp. 200.000,00 = Rp. 40.000,00
Jumlah = Rp. 97.196,75
1 m' Pemasangan Pipa Steel ø 75 mm = 1/6 x Rp. 97.196,75 = Rp. 16.199,46

41 An. Taksir 6 m Pemasangan Pipa Steel/GIP ø 100 mm


0,300 OH Pekerja @ Rp. 104.545,00 = Rp. 31.363,50
0,100 OH Mandor @ Rp. 145.454,00 = Rp. 14.545,40
0,200 OH Tukang Pasang Pipa @ Rp. 113.636,00 = Rp. 22.727,20
0,200 Peralatan (Tracker) @ Rp. 200.000,00 = Rp. 40.000,00
Jumlah = Rp. 108.636,10
1 m' Pemasangan Pipa Steel ø 100 mm = 1/6 x Rp. 108.636,10 = Rp. 18.106,02

42 An. Taksir 6 m Pemasangan Pipa Steel/GIP ø 150 mm


0,375 OH Pekerja @ Rp. 104.545,00 = Rp. 39.204,38
0,125 OH Mandor @ Rp. 145.454,00 = Rp. 18.181,75
0,250 OH Tukang Pasang Pipa @ Rp. 113.636,00 = Rp. 28.409,00
0,200 Peralatan (Tracker) @ Rp. 200.000,00 = Rp. 40.000,00
Jumlah = Rp. 125.795,13
1 m' Pemasangan Pipa Steel ø 150 mm = 1/6 x Rp. 125.795,13 = Rp. 20.965,85

43 An. Taksir 6 m Pemasangan Pipa Steel/GIP ø 200 mm


0,500 OH Pekerja @ Rp. 104.545,00 = Rp. 52.272,50
0,167 OH Mandor @ Rp. 145.454,00 = Rp. 24.242,33
0,333 OH Tukang Pasang Pipa @ Rp. 113.636,00 = Rp. 37.878,67
0,300 Peralatan (Tracker) @ Rp. 200.000,00 = Rp. 60.000,00
Jumlah = Rp. 174.393,50
1 m' Pemasangan Pipa Steel ø 200 mm = 1/6 x Rp. 174.393,50 = Rp. 29.065,58

44 An. Taksir 6 m Pemasangan Pipa Steel/GIP ø 250 mm


0,600 OH Pekerja @ Rp. 104.545,00 = Rp. 62.727,00
0,200 OH Mandor @ Rp. 145.454,00 = Rp. 29.090,80
0,400 OH Tukang Pasang Pipa @ Rp. 113.636,00 = Rp. 45.454,40
0,300 Peralatan (Tracker) @ Rp. 200.000,00 = Rp. 60.000,00
Jumlah = Rp. 197.272,20
1 m' Pemasangan Pipa Steel ø 250 mm = 1/6 x Rp. 197.272,20 = Rp. 32.878,70

45 An. Taksir 6 m Pemasangan Pipa Steel/GIP ø 300 mm


0,750 OH Pekerja @ Rp. 104.545,00 = Rp. 78.408,75
0,250 OH Mandor @ Rp. 145.454,00 = Rp. 36.363,50
0,500 OH Tukang Pasang Pipa @ Rp. 113.636,00 = Rp. 56.818,00
0,300 Peralatan (Tracker) @ Rp. 200.000,00 = Rp. 60.000,00
Jumlah = Rp. 231.590,25
1 m' Pemasangan Pipa Steel ø 300 mm = 1/6 x Rp. 231.590,25 = Rp. 38.598,38

46 An. Taksir 6 m Pemasangan Pipa Steel/GIP ø 350 mm


1,000 OH Pekerja @ Rp. 104.545,00 = Rp. 104.545,00
0,333 OH Mandor @ Rp. 145.454,00 = Rp. 48.484,67
0,667 OH Tukang Pasang Pipa @ Rp. 113.636,00 = Rp. 75.757,33
0,400 Peralatan (Tracker) @ Rp. 200.000,00 = Rp. 80.000,00
Jumlah = Rp. 308.787,00
1 m' Pemasangan Pipa Steel ø 350 mm = 1/6 x Rp. 308.787,00 = Rp. 51.464,50
47 An. Taksir 6 m Pemasangan Pipa Steel/GIP ø 400 mm
1,500 OH Pekerja @ Rp. 104.545,00 = Rp. 156.817,50
0,500 OH Mandor @ Rp. 145.454,00 = Rp. 72.727,00
1,000 OH Tukang Pasang Pipa @ Rp. 113.636,00 = Rp. 113.636,00
0,400 Peralatan (Tracker) @ Rp. 200.000,00 = Rp. 80.000,00
Jumlah = Rp. 423.180,50
1 m' Pemasangan Pipa Steel ø 400 mm = 1/6 x Rp. 423.180,50 = Rp. 70.530,08

ANALISA TAKSIR PEMASANGAN PIPA HDPE

48 An. 1cm Pengelasan pipa HDPE


0,0250 Lt Solar @ Rp. 6.727,00 = Rp. 168,18
0,0025 Lt Minyak Pelumas @ Rp. 24.090,00 = Rp. 60,23

0,009 OH Pekerja @ Rp. 104.545,00 = Rp. 940,91


0,009 OH Mandor @ Rp. 145.454,00 = Rp. 1.309,09
0,009 OH Tukang Besi @ Rp. 113.636,00 = Rp. 1.022,72
0,004 OH Kep.tukang besi @ Rp. 159.090,00 = Rp. 636,36
0,0045 Hr Sewa mesin las HDPE @ Rp. 727.272,00 = Rp. 3.272,72
Jumlah = Rp. 7.410,20

49 An. Taksir 6 m Pemasangan Pipa HDPE ø 200 mm ( 8 " )


69,0800 Pengelasan @ Rp. 7.410,20 = Rp. 511.896,55

0,3645 OH Pekerja @ Rp. 104.545,00 = Rp. 38.106,65


0,0185 OH Mandor @ Rp. 145.454,00 = Rp. 2.690,90
0,6075 OH Tukang pipa @ Rp. 113.636,00 = Rp. 69.033,87
0,0608 OH Kep.tukang pipa @ Rp. 159.090,00 = Rp. 9.672,67
1,0000 Alat bantu @ Rp. 26.506,76 = Rp. 26.506,76
Jumlah = Rp. 657.907,40
1 m' Pemasangan Pipa HDPE ø 200 mm = 1/6 x Rp. 657.907,40 = Rp. 109.651,23

50 An. Taksir 6 m Pemasangan Pipa HDPE ø 150 mm ( 6 " )


51,8100 Pengelasan @ Rp. 7.410,20 = Rp. 383.922,41

0,3038 OH Pekerja @ Rp. 104.545,00 = Rp. 31.760,77


0,0154 OH Mandor @ Rp. 145.454,00 = Rp. 2.239,99
0,5063 OH Tukang pipa @ Rp. 113.636,00 = Rp. 57.533,91
0,0506 OH Kep.tukang pipa @ Rp. 159.090,00 = Rp. 8.049,95
1,0000 Alat bantu @ Rp. 26.506,76 = Rp. 26.506,76
Jumlah = Rp. 510.013,79
1 m' Pemasangan Pipa HDPE ø 150 mm = 1/6 x Rp. 510.013,79 = Rp. 85.002,30

51 An. Taksir 6 m Pemasangan Pipa HDPE ø 100 mm ( 4 " )


34,5400 Pengelasan @ Rp. 7.410,20 = Rp. 255.948,27

0,2430 OH Pekerja @ Rp. 104.545,00 = Rp. 25.404,44


0,0123 OH Mandor @ Rp. 145.454,00 = Rp. 1.789,08
0,4050 OH Tukang pipa @ Rp. 113.636,00 = Rp. 46.022,58
0,0405 OH Kep.tukang pipa @ Rp. 159.090,00 = Rp. 6.443,15
1,0000 Alat bantu @ Rp. 26.506,76 = Rp. 26.506,76
Jumlah = Rp. 362.114,28
1 m' Pemasangan Pipa HDPE ø 100 mm = 1/6 x Rp. 362.114,28 = Rp. 60.352,38

52 An. Taksir 30 m Pemasangan Pipa HDPE ø 75 mm ( 3 " )


17,2700 Pengelasan @ Rp. 7.410,20 = Rp. 127.974,14

0,0125 OH Pekerja @ Rp. 104.545,00 = Rp. 1.306,81


0,0510 OH Mandor @ Rp. 145.454,00 = Rp. 7.418,15
1,6875 OH Tukang pipa @ Rp. 113.636,00 = Rp. 191.760,75
0,1688 OH Kep.tukang pipa @ Rp. 159.090,00 = Rp. 26.854,39
1,0000 Alat bantu @ Rp. = Rp. 0,00
Jumlah = Rp. 355.314,25
1 m' Pemasangan Pipa HDPE ø 75 mm = 1/30 x Rp. 355.314,25 = Rp. 59.219,04
ANALISA TAKSIR PEKERJAAN PENGETESAN & PENGURASAN PIPA
Pengetesan Pipa
53 Pd1.1 Pengetesan pipa Ø 50 mm
1,099 m3 air bersih @ Rp. 7.272,00 = Rp. 7.991,93
0,050 hk pekerja @ Rp. 104.545,00 = Rp. 5.227,25
0,020 hk tukang @ Rp. 113.636,00 = Rp. 2.272,72
0,010 hk mandor @ Rp. 145.454,00 = Rp. 1.454,54
1,000 hk sewa alat pengetesan pipa @ Rp. 454.545,00 = Rp. 454.545,00
200 m' pengetesan pipa Ø 50 mm Jumlah = Rp. 471.491,44
biaya pengetesan pipa/m Rp. 471.491,44 = Rp. 2.357,46

54 Pd1.2 Pengetesan pipa Ø 75 mm


2,473 m3 air bersih @ Rp. 7.272,00 = Rp. 17.981,84
0,113 hk pekerja @ Rp. 104.545,00 = Rp. 11.761,31
0,045 hk tukang @ Rp. 113.636,00 = Rp. 5.113,62
0,023 hk mandor @ Rp. 145.454,00 = Rp. 3.272,72
1,250 hk sewa alat pengetesan pipa @ Rp. 454.545,00 = Rp. 568.181,25
200 m' pengetesan pipa Ø 75 mm Jumlah = Rp. 606.310,74
biaya pengetesan pipa/m Rp. 606.310,74 = Rp. 3.031,55

55 Pd1.3 Pengetesan pipa Ø 100 mm


4,396 m3 air bersih @ Rp. 7.272,00 = Rp. 31.967,71
0,188 hk pekerja @ Rp. 104.545,00 = Rp. 19.602,19
0,075 hk tukang @ Rp. 113.636,00 = Rp. 8.522,70
0,038 hk mandor @ Rp. 145.454,00 = Rp. 5.454,53
1,500 hk sewa alat pengetesan pipa @ Rp. 454.545,00 = Rp. 681.817,50
200 m' pengetesan pipa Ø 100 mm Jumlah = Rp. 747.364,62
biaya pengetesan pipa/m Rp. 747.364,62 = Rp. 3.736,82

56 Pd1.4 Pengetesan pipa Ø 150 mm


9,891 m3 air bersih @ Rp. 7.272,00 = Rp. 71.927,35
0,263 hk pekerja @ Rp. 104.545,00 = Rp. 27.443,06
0,105 hk tukang @ Rp. 113.636,00 = Rp. 11.931,78
0,053 hk mandor @ Rp. 145.454,00 = Rp. 7.636,34
1,750 hk sewa alat pengetesan pipa @ Rp. 454.545,00 = Rp. 795.453,75
200 m' pengetesan pipa Ø 150 mm Jumlah = Rp. 914.392,28
biaya pengetesan pipa/m Rp. 914.392,28 = Rp. 4.571,96

57 Pd1.5 Pengetesan pipa Ø 200 mm


17,584 m3 air bersih @ Rp. 7.272,00 = Rp. 127.870,85
0,363 hk pekerja @ Rp. 104.545,00 = Rp. 37.897,56
0,145 hk tukang @ Rp. 113.636,00 = Rp. 16.477,22
0,073 hk mandor @ Rp. 145.454,00 = Rp. 10.545,42
2,000 hk sewa alat pengetesan pipa @ Rp. 454.545,00 = Rp. 909.090,00
200 m' pengetesan pipa Ø 200 mm Jumlah = Rp. 1.101.881,05
biaya pengetesan pipa/m Rp. 1.101.881,05 = Rp. 5.509,41

Pengurasan & Desinfeksi


58 Pd2.1 Pengurasan dan desinfeksi pipa Ø 50 mm
1,099 m3 air bersih @ Rp. 7.272,00 = Rp. 7.991,93
0,019 kg kaporit 60 % 10 ppm @ Rp. 30.000,00 = Rp. 560,49
0,050 hk pekerja @ Rp. 104.545,00 = Rp. 5.227,25
0,020 hk tukang @ Rp. 113.636,00 = Rp. 2.272,72
0,010 hk mandor @ Rp. 145.454,00 = Rp. 1.454,54
0,500 hk sewa alat pengetesan pipa @ Rp. 454.545,00 = Rp. 227.272,50
200 m' pengurasan dan desinfeksi pipa Ø 50 mm Jumlah = Rp. 244.779,43
biaya pengurasan & desinfeksi pipa/m Rp. 244.779,43 = Rp. 1.223,90

59 Pd2.2 Pengurasan dan desinfeksi pipa Ø 75 mm


2,473 m3 air bersih @ Rp. 7.272,00 = Rp. 17.981,84
0,042 kg kaporit 60 % 10 ppm @ Rp. 30.000,00 = Rp. 1.261,10
0,113 hk pekerja @ Rp. 104.545,00 = Rp. 11.761,31
0,045 hk tukang @ Rp. 113.636,00 = Rp. 5.113,62
0,023 hk mandor @ Rp. 145.454,00 = Rp. 3.272,72
0,625 hk sewa alat pengetesan pipa @ Rp. 454.545,00 = Rp. 284.090,63
200 m' pengurasan dan desinfeksi pipa Ø 75 mm Jumlah = Rp. 323.481,21
biaya pengurasan & desinfeksi pipa/m Rp. 323.481,21 = Rp. 1.617,41
60 Pd2.3 Pengurasan dan desinfeksi pipa Ø 100 mm
4,396 m3 air bersih @ Rp. 7.272,00 = Rp. 31.967,71
0,075 kg kaporit 60 % 10 ppm @ Rp. 30.000,00 = Rp. 2.241,96
0,188 hk pekerja @ Rp. 104.545,00 = Rp. 19.602,19
0,075 hk tukang @ Rp. 113.636,00 = Rp. 8.522,70
0,038 hk mandor @ Rp. 145.454,00 = Rp. 5.454,53
0,750 hk sewa alat pengetesan pipa @ Rp. 454.545,00 = Rp. 340.908,75
200 m' pengurasan dan desinfeksi pipa Ø 100 mm Jumlah = Rp. 408.697,83
biaya pengurasan & desinfeksi pipa/m Rp. 408.697,83 = Rp. 2.043,49

61 Pd2.4 Pengurasan dan desinfeksi pipa Ø 150 mm


9,891 m3 air bersih @ Rp. 7.272,00 = Rp. 71.927,35
0,168 kg kaporit 60 % 10 ppm @ Rp. 30.000,00 = Rp. 5.044,41
0,263 hk pekerja @ Rp. 104.545,00 = Rp. 27.443,06
0,105 hk tukang @ Rp. 113.636,00 = Rp. 11.931,78
0,053 hk mandor @ Rp. 145.454,00 = Rp. 7.636,34
0,875 hk sewa alat pengetesan pipa @ Rp. 454.545,00 = Rp. 397.726,88
200 m' pengurasan dan desinfeksi pipa Ø 150 mm Jumlah = Rp. 521.709,81
biaya pengurasan & desinfeksi pipa/m Rp. 521.709,81 = Rp. 2.608,55

62 Pd2.5 Pengurasan dan desinfeksi pipa Ø 200 mm


17,584 m3 air bersih @ Rp. 7.272,00 = Rp. 127.870,85
0,299 kg kaporit 60 % 10 ppm @ Rp. 30.000,00 = Rp. 8.967,84
0,363 hk pekerja @ Rp. 104.545,00 = Rp. 37.897,56
0,145 hk tukang @ Rp. 113.636,00 = Rp. 16.477,22
0,073 hk mandor @ Rp. 145.454,00 = Rp. 10.545,42
1,000 hk sewa alat pengetesan pipa @ Rp. 454.545,00 = Rp. 454.545,00
200 m' pengurasan dan desinfeksi pipa Ø 200 mm Jumlah = Rp. 656.303,89
biaya pengurasan & desinfeksi pipa/m Rp. 656.303,89 = Rp. 3.281,52

Pekerjaan PELAT & LAS

63 1 m Pengelasan Penuh Tebal = 3 mm


Peralatan :
Ls Sewa Mesin Las @ Rp. 192.384,00 Rp. 1.500.000,00
1.820,000 Ltr Minyak Solar @ Rp. 6.727,00 Rp. 12.243.140,00
10,000 Ltr Oli @ Rp. 35.090,00 Rp. 350.900,00
Ls Biaya Operator @ Rp. 200.000,00 Rp. 200.000,00
Ls Transportasi Peralatan @ Rp. 100.000,00 Rp. 100.000,00
Jumlah = Rp. 14.394.040,00
Upah :
0,580 OH Pekerja @ Rp. 104.545,00 Rp. 60.636,10
0,188 OH Mandor @ Rp. 145.454,00 Rp. 27.345,35
0,290 OH Tukang Las @ Rp. 113.636,00 Rp. 32.954,44
0,203 OH Kotak Kawat Las @ Rp. 200.000,00 Rp. 40.600,00
0,011 OH Peralatan @ Rp. 14.394.040,00 Rp. 158.334,44
Jumlah = Rp. 319.870,33

64 1 m Pemotongan Plat Menggunakan Titik Tek. Tinggi t < 7 mm


0,250 OH Pekerja @ Rp. 104.545,00 Rp. 26.136,25
0,125 OH Mandor @ Rp. 145.454,00 Rp. 18.181,75
0,188 OH Tukang Las @ Rp. 113.636,00 Rp. 21.363,57

0,108 Bh Isi tabung Elpiji @ 50 kg @ Rp. 330.909,00 Rp. 35.738,17


0,063 Bh Isi tabung zat asam @ 75 kg @ Rp. 477.272,00 Rp. 30.068,14
Jumlah = Rp. 131.487,88

65 An. 1cm Pengelasan dengan las listrik


0,040 Kg Kawat Kas @ Rp. 27.272,00 = Rp. 1.090,88
0,030 Lt Solar @ Rp. 6.727,00 = Rp. 201,81
0,004 Lt Minyak Pelumas @ Rp. 4.247.727,00 = Rp. 16.990,91

0,009 OH Pekerja @ Rp. 104.545,00 = Rp. 940,91


0,009 OH Mandor @ Rp. 145.454,00 = Rp. 1.309,09
0,009 OH Tukang Besi @ Rp. 113.636,00 = Rp. 1.022,72
0,004 OH Kep.tukang besi @ Rp. 159.090,00 = Rp. 636,36
0,0028 Hr Sewa mesin las @ Rp. 192.384,00 = Rp. 538,68
Jumlah = Rp. 3.506,85
1 m Pengelasan Penuh = Rp. 350.684,52
Pekerjaan PENGECATAN :
66 An.K.23 100 m² Mengecat :
7,500 OH Tukang @ Rp. 113.636,00 Rp. 852.270,00
0,750 OH Kepala Tukang @ Rp. 159.090,00 Rp. 119.317,50
5,000 OH Pekerja @ Rp. 104.545,00 Rp. 522.725,00
0,250 OH Mandor @ Rp. 145.454,00 Rp. 36.363,50
Jumlah = Rp. 1.530.676,00
1 m² Pengecatan = 1/100 x Rp. 1.530.676,00 Rp. 15.306,76
Supl K.23a Cat Besi / Kilat :
2,000 Upah Mengecat @ Rp. 15.306,76 Rp. 30.613,52
0,283 Kg Cat Kilat @ Rp. 56.818,00 Rp. 16.098,43
Jumlah = Rp. 46.711,95
Supl K.23b Cat Tembok :
2,000 Upah Mengecat @ Rp. 15.306,76 Rp. 30.613,52
0,283 Kg Cat Tembok @ Rp. 42.000,00 Rp. 11.900,00
Jumlah = Rp. 42.513,52

Pekerjaan ATAP & KAYU :

67 Pasang atap seng gelombang


Bahan
0,075 Kg Paku kayu @ Rp. 19.090,00 Rp. 1.431,75
1,100 Lbr Seng gelombang @ Rp. 58.909,00 Rp. 64.799,90

upah
0,100 OH Tukang @ Rp. 113.636,00 Rp. 11.363,60
0,400 OH Kepala Tukang @ Rp. 159.090,00 Rp. 63.636,00
0,150 OH Pekerja @ Rp. 104.545,00 Rp. 15.681,75
0,008 OH Mandor @ Rp. 145.454,00 Rp. 1.163,63

1 m² rangka atap untuk seng gelombang Jumlah = Rp. 158.076,63

68 Pekerjaaan Kusen
Bahan
1,100 m3 Kayu klas II @ Rp. 3.054.545,00 Rp. 3.359.999,50
4,000 Kg Paku kayu @ Rp. 19.090,00 Rp. 76.360,00

upah
0,100 OH Tukang @ Rp. 113.636,00 Rp. 11.363,60
0,400 OH Kepala Tukang @ Rp. 159.090,00 Rp. 63.636,00
0,150 OH Pekerja @ Rp. 104.545,00 Rp. 15.681,75
0,008 OH Mandor @ Rp. 145.454,00 Rp. 1.163,63

1 m3 pekerjaan kusen Jumlah = Rp. 3.528.204,48


A.2.3.1 HARGA SATUAN PEKERJAAN TANAH
A.2.3.1.1. Penggalian 1 m3 tanah biasa sedalam 1 m
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.)
Jumlah Harga (Rp.)
A TENAGA - -
Pekerja L.01.01 OH 0,7500 104.545,00 78.408,75
Mandor L.04.01 OH 0,0250 145.454,00 3.636,35
JUMLAH TENAGA KERJA 82.045,10
B BAHAN - -
JUMLAH HARGA BAHAN -
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 82.045,10
E Overhead & Profit 10% 0% -
F Harga Satuan Pekerjaan (D+E) - 82.045,00

A.2.3.1.9. Pengurugan kembali 1 m3 galian tanah Tanah Biasa Sedalam 1 M


Pengurugan kembali 1 m3 galian dihitung dari 1/3 kali dari koefisien pekerjaan galian
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.)
Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0,2500 104.545,00 26.136,25
Mandor L.04.01 OH 0,0250 145.454,00 3.636,35
JUMLAH TENAGA KERJA 29.772,60
B BAHAN - -
JUMLAH HARGA BAHAN -
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 29.772,60
E Overhead & Profit 10% 0% -
F Harga Satuan Pekerjaan (D+E) - 29.772,00

A.2.3.1.11. Pengurugan 1 m3 dengan pasir urug


No Uraian Kode Satuan Koefisien Harga Satuan (Rp.)
Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0,3000 104.545,00 31.363,50
Mandor L.04.01 OH 0,0100 145.454,00 1.454,54
JUMLAH TENAGA KERJA 32.818,04
B BAHAN
Pasir urug M3 1,2000 195.454,00 234.544,80
JUMLAH HARGA BAHAN 234.544,80
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 267.362,84
E Overhead & Profit 10% 0% -
F Harga Satuan Pekerjaan (D+E) - 267.362,00
A.8.4.1 HARGA SATUAN PEKERJAAN PEMASANGAN PIPA
A.8.4.1.3 (K3) Pemasangan 1 m pipa PVC Ø 110 mm
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.)
Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0,105 104.545,00 10.977,23
Tukang pipa L.02.13 OH 0,053 113.636,00 6.022,71
Mandor L.04.01 OH 0,011 145.454,00 1.599,99
JUMLAH TENAGA KERJA 18.599,93
B BAHAN
Pipa PVC Ø 110 mm m 1,000 103.047,35 103.047,35
JUMLAH HARGA BAHAN 103.047,35
C PERALATAN
Peralatan, Perlengkapan dan Aksesoris % 1,000 1.030,47 1.030,47
JUMLAH HARGA ALAT 1.030,47
D Jumlah (A+B+C) - 122.677,75
E Overhead & Profit 10% 0% -
F Harga Satuan Pekerjaan (D+E) - 122.677,00

A.8.4.1.4 (K3) Pemasangan 1 m pipa PVC Ø 150 mm


No Uraian Kode Satuan Koefisien Harga Satuan (Rp.)
Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0,118 104.545,00 12.336,31
Tukang pipa L.02.13 OH 0,059 113.636,00 6.704,52
Mandor L.04.01 OH 0,012 145.454,00 1.745,45
JUMLAH TENAGA KERJA 20.786,28
B BAHAN
Pipa PVC Ø 150 mm m 1,000 219.842,14 219.842,14
JUMLAH HARGA BAHAN 219.842,14
C PERALATAN
Peralatan, Perlengkapan dan Aksesoris % 1,000 2.198,42 2.198,42
JUMLAH HARGA ALAT 2.198,42
D Jumlah (A+B+C) - 242.826,84
E Overhead & Profit 10% 0% -
F Harga Satuan Pekerjaan (D+E) - 242.826,00

A.8.4.1.5 (K3) Pemasngan 1 m pipa PVC Ø 200 mm


No Uraian Kode Satuan Koefisien Harga Satuan (Rp.)
Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0,189 104.545,00 19.759,01
Tukang pipa L.02.13 OH 0,095 113.636,00 10.795,42
Mandor L.04.01 OH 0,019 145.454,00 2.763,63
JUMLAH TENAGA KERJA 33.318,05
B BAHAN
Pipa PVC Ø 200 mm m 1,000 339.205,39 339.205,39
JUMLAH HARGA BAHAN 339.205,39
C PERALATAN
Peralatan, Perlengkapan dan Aksesoris % 1,000 3.392,05 3.392,05
JUMLAH HARGA ALAT 3.392,05
D Jumlah (A+B+C) - 375.915,49
E Overhead & Profit 10% 0% -
F Harga Satuan Pekerjaan (D+E) - 375.915,00
PROYEK PENYUSUNAN DED SPAM IKK 2019

KEGIATAN PENGEMBANGAN DISTRIBUSI AIR MINUM


PEKERJAAN PEMBANGUNAN INSTALASI PENGOLAHAN AIR BERSIH (IPA) PDAM KP.50 L/Dtk IKK SELAKAU
LOKASI KEC. SELAKAU, KABUPATEN SAMBAS
TAHUN ANGGARAN 2019

DAFTAR HARGA SATUAN BAHAN DAN UPAH

HARGA SATUAN
NO. URAIAN KET.
(Rp)
I. HARGA UPAH :
1 Pekerja 104.545,00 / hari
2 Pekerja terlatih 113.636,00 / hari
3 Mandor 145.454,00 / hari
4 Tukang Batu / Kayu / Cat / Besi 113.636,00 / hari
5 Kepala Tukang 159.090,00 / hari
6 Masinis / Mekanik 136.363,00 / hari
7 Operator pembantu 113.636,00 / hari
8 Operator terlatih 136.363,00 / hari
9 Penjaga Malam 90.909,00 / hari
10 Tukang Pasang Pipa 113.636,00 / hari
11 Sopir pembantu 113.636,00 / hari
12 Sopir 136.363,00 / hari
13 Tukang Las 113.636,00 / hari

II. HARGA BAHAN :


1 Pasir Urug 195.454,00 / m³
2 Pasir Pasang 241.454,00 / m³
3 Pasir Beton 241.454,00 / m³
4 Kerikil Sungai / Kepala Pasir 265.909,00 / m³
5 Pasir Batu /kotor 354.545,00 / m³
6 Batu kali 15/20 316.181,00 / m³
7 Koral Beton / Kerikil Pecah 2/3 500.181,00 / m³
8 Koral Kerikil Pecah 1-2 661.818,00 / m³
9 Batu Pecah 5/7 cm 403.636,00 / m³
10 Batu bata 2.727,00 / bh
11 Portland Cement @ 50 kg 86.090,00 / Zak
12 Portland Cement @ 1 kg 1.721,00 / Kg
13 Besi beton 26.500,00 / kg
14 Kawat beton 28.750,00 / kg
15 Plywood / Multiplex 9 mm 168.818,00 / lembar
16 Kayu Terentang 1.466.086,00 / m³
17 Kayu Dolken / Galam 11.659,00 / bh
18 Kayu Borneo (III) 1.681.813,00 / m³
19 Kayu Kelas II 3.054.545,00 / m³
20 Paku 2' 5' 19.090,00 / kg
21 Cat Tembok 42.000,00 / kg
22 Cat kilat 56.818,00 / kg
23 Kawat Las 27.272,00 / kotak
24 Minyak solar 6.727,00 / ltr
25 Minyak Oli 35.090,00 / ltr
26 Minyak Pelumas 24.090,00 / ltr
27 Pipa Galvanis dia.2" 161.000,00 /btg
28 Pasir Silika 454.545,00 / m³
26 Papan 4.247.727,00 / m³
27 Minyak Gardan 39.181,00 / ltr
28 Minyak Gemuk 51.000,00 / ltr
29 Isi Tabung Elpiji @ 50 kg 330.909,00 / bh
30 Isi Tabung zat asam @ 75 kg 477.272,00 / bh
31 Kawat harmonika 38.627,00 / m2
32 Seng gelombang 58.909,00 / lbr
33 Kaporit 30.000,00 / kg
34 Soda ash 12.727,00 / kg
35 Alum sulfat 6.363,00 / kg
36 Air Bersih untuk Test & Pencucian Pipa 7.272,00 / m³
36 Tanah Pilihan 140.909,00 / m³
III. HARGA dan BIAYA SEWA PERALATAN : -
1 Sewa Mesin Gilas (Walls) 1.192.727,00 /Hari
2 Sewa Mesin Las 192.384,00 /Hari
3 Sewa Mesin Las HDPE 727.272,00 /Hari
4 Sewa Alat Test Tekan Pipa 454.545,00 /Hari
5 Alat Bantu Pancang Cerucuk kayu 681.818,00 /Hari
6 Stamper 42.255,00 /Hari
7 Vibrator 450.940,00 /Hari
8 Pengaduk Beton (Molen) 44.380,00 /Hari
HARGA SATUAN POMPA - IPA
PENGEMBANGAN AIR MINUM
HARGA
No. Jenis Pompa/Panel Akhir

I. POMPA
1 Submersible Sewage Non Clogging
- Q= 5 L/dt ; Head=30 m 62.596.800,00
- Q=10 L/dt ; Head=30 m 72.193.680,00
- Q=20 L/dt ; Head=30 m 92.124.540,00
- Q=30 L/dt ; Head=30 m 100.440.000,00
- Q=40 L/dt ; Head=30 m 140.810.400,00
- Q=50 L/dt ; Head=30 m 145.800.000,00

2 Centrifugal Single Stage End Suction


5 l/det Head 60 m 33.222.830,00
10 l/det 38.534.793,00
15 l/det 41.843.573,33
20 l/det 66.328.145,00
25 l/det 69.578.000,00
30 l/det 89.450.556,00
40 l/det 105.184.361,00
50 l/det 138.004.220,00
75 l/det 161.480.620,00

3 Panel Control
Panel Control - 1,5 kW 22.513.140,00
Panel Control - 2,2 kW 25.842.240,00
Panel Control - 7,5 kW 32.152.950,00
Panel Control - 15 kW 33.802.920,00
Panel Control - 18,0 kW 34.955.550,00

4 Pompa bahan Kimia


- C= 05 L/hr ; P=10 BAR 46.392.340,00
- C= 10 L/hr ; P=10 BAR 46.392.340,00
- C= 20 L/hr ; P=10 BAR 46.392.340,00
- C= 40 L/hr ; P=10 BAR 46.392.340,00
5 Pompa Blower 11 kw 87.000.000,00
HARGA SATUAN GENERATOR SET.
PENGEMBANGAN AIR MINUM
HARGA
No. Jenis Pompa Akhir

II. Generator Set (GENSET)


10 KVA 139.541.066,67
15 KVA 147.572.493,33
20 KVA 155.048.740,00
25 KVA 174.386.686,67
30 KVA 182.429.006,67
40 KVA 195.507.720,00
45 KVA 214.916.346,67
50 KVA 236.470.200,00
60 KVA 241.232.803,33
75 KVA 245.995.406,67
80 KVA 274.455.000,00
88 KVA 293.512.000,00
100 KVA 325.100.766,67
125 KVA 366.279.118,08
135 KVA 407.457.470,00
150 KVA 439.352.390,00

HARGA SATUAN IPA PAKET


PENGEMBANGAN AIR MINUM
HARGA
No. Jenis Pompa Akhir

III. IPA Paket


5 Lpd 1.602.848.683,33
10 Lpd 2.110.554.600,00
20 Lpd 3.037.019.333,33
30 Lpd 4.289.986.836,67
40 Lpd 5.392.486.000,00
50 Lpd 6.174.258.933,33