REKAPITULASI RENCANA ANGGARAN BIAYA

KEGIATAN : PENGADAAN PRASARANA DAN PENDUKUNG FASILITAS PELAYANAN KESEHATAN


PEKERJAAN : PEMBANGUNAN PRASARANA AIR BERSIH PUSKESMAS
LOKASI : PUSKESMAS LAMBUYA KEC. LAMBUYA KAB. KONAWE
SUMBER DANA : DAK BIDANG KESEHATAN
TAHUN ANGGARAN : 2022

TOTAL HARGA
NO. URAIAN PEKERJAAN (Rp)
I PEKERJAAN PERSIAPAN 4,891,668.00
II PENGADAAN & PEMASANGAN INSTALASI AIR BERSIH #NAME?
III PEKERJAAN BANGUNAN RUMAH ALAT #NAME?
IV PEKERJAAN AKHIR 1,000,000.00
TOTAL #NAME?
PPN 11 % (TOTAL) #NAME?
GRAND TOTAL #NAME?
DIBULATKAN #NAME?

TERBILANG : #NAME?

Unaaha, 2022
MENGETAHUI : DIBUAT :
PEJABAT PELAKSANA TEKNIS KEGIATAN (PPTK) KONSULTAN PERENCANA
BIDANG PELAYANAN KESEHATAN CV. DINDING JELAJAH
DINAS KESEHATAN KABUPATEN KONAWE

ASWAN, SKM.,MKM M. FAHRI USMAN, S. Ars.


Nip. 19880605 201001 1 005 Direktur

MENYETUJUI :
KEPALA DINAS KESEHATAN
KABUPATEN KONAWE

Drg. MAWAR T. M.Kes


Nip. 19660726 200212 1 001
RENCANA ANGGARAN BIAYA
(R. A. B)
KEGIATAN : PENGADAAN PRASARANA DAN PENDUKUNG FASILITAS PELAYANAN KESEHATAN
PEKERJAAN : PEMBANGUNAN PRASARANA AIR BERSIH PUSKESMAS
LOKASI : PUSKESMAS LAMBUYA KEC. LAMBUYA KAB. KONAWE
SUMBER DANA : DAK BIDANG KESEHATAN
TAHUN ANGGARAN : 2022
HARGA JUMLAH
NO. URAIAN PEKERJAAN VOLUME SAT. SATUAN HARGA
(Rp) (Rp)
I PEKERJAAN PERSIAPAN
1 Pembersihan Awal Lokasi 1.00 Ls 750,000.00 750,000.00
2 Pengukuran dan Pasangan Bouwplank 12.00 m' 82,639.00 991,668.00
3 Listrik & Penerangan Kerja 1.00 Ls 600,000.00 600,000.00
4 Pengadaan air kerja dan P3K 1.00 Ls 350,000.00 350,000.00
5 Papan Nama Proyek 1.00 Ls 200,000.00 200,000.00
6 Administrasi (Dokumentasi & Laporan Proyek) 1.00 Ls 2,000,000.00 2,000,000.00
Sub Jumlah I 4,891,668.00
II PENGADAAN & PEMASANGAN INSTALASI AIR BERSIH
1 Pengadaan dan pemasangan Tangki Filter
- Tangki Filter TFR 10x54 + Pasir Silika (Sand Filter) 1.00 Set 2,800,000.00 2,800,000.00
- Tangki Filter TFR 10x54 + Mangan Zeolit (Manganese Greensand Filter 1.00 Set 3,200,000.00 3,200,000.00
- Tangki Filter TFR 10x54 + Karbon Aktif (Activated Carbon Filter) 1.00 Set 3,250,000.00 3,250,000.00
- Tangki Filter TFR 10x54 + Resin Cation 1.00 Set 3,700,000.00 3,700,000.00
2 Pengadaan dan pemasangan Catridge Filter 4.00 Bh 250,000.00 1,000,000.00
3 Pengadaan Water Torn Stainless (Pakai Kaki) TVS 1000 L 3.00 Bh 4,500,000.00 13,500,000.00
2 Pengadaan Water Torn Viber (Tandon Air) Kapasitas 2200 L 1.00 Bh 3,500,000.00 3,500,000.00
4 Pengadaan dan pemasangan Mesin Air Jet Pump, kap.250 watt 1.00 Unit 1,700,000.00 1,700,000.00
5 Pengadaan dan pemasangan Mesin Pompa Stainless, kap.350 watt 2.00 Unit 2,100,000.00 4,200,000.00
6 Pengadaan dan pemasangan Mesin RO 4000 GPD Kapasitas 15.200 L, 1750 Wat 1.00 Set 30,000,000.00 30,000,000.00
7 Pengadaan dan pemasangan Ultra Violet 12gpm 1.00 Bh 2,500,000.00 2,500,000.00
8 Pengadaan dan pemasangan Panel Box + Lengkap Accessories 1.00 Set 1,500,000.00 1,500,000.00
1 Pek. pemasangan Pipa 3/4" + Accessories (instalasi air bersih) 48.00 m' #NAME? #NAME?
9 Pengadaan Rangka Stainless dudukan filter 1.00 Ls 2,500,000.00 2,500,000.00
10 Test & Uji Fungsi Alat 1.00 Ls 1,500,000.00 1,500,000.00
Sub Jumlah II #NAME?
III PEKERJAAN BANGUNAN RUMAH ALAT
A. Pekerjaan Pondasi dan Tanah
1 Pek. Galian Tanah 7.74 m³ 81,362.50 629,745.75
2 Pek. Batu Kosong 2.49 m³ 604,233.00 1,504,540.17
3 Pek. Pasangan batu gunung 1 : 5 5.18 m³ 1,108,724.20 5,743,191.36

B. Pekerjaan Beton
1 Pek. Pas. Sloof 15/20
- Cor Beton 0.42 m³ #NAME? #NAME?
- Besi Beton 73.82 Kg 26,392.50 1,948,294.35
- Bekisting Sloof 5.52 m² 172,186.05 950,467.00
2 Pekerjaan Pas. Kolom Praktis 11/11
- Cor Beton, Besi Beton, Bekisting 13.82 m' 132,687.00 1,833,734.34
3 Pekerjaan Pas. Balok Latey 10/15
- Cor Beton, Besi Beton, Bekisting 7.70 m' 159,109.51 1,225,143.23
4 Pekerjaan Pas. Ringbalk 10/15
- Cor Beton, Besi Beton, Bekisting 14.00 m' 159,109.51 2,227,533.14

C. Pekerjaan Dinding
1 Pekerjaan Pasangan Dinding 1/2 Bata Adukan 1PC : 5PS 38.17 m² 152,126.71 5,806,676.52
2 Pekerjaan Plasteran Dinding Adukan 1PC : 5PS 76.34 m² 75,038.74 5,728,457.41
3 Pekerjaan Plasteran Beton Adukan 1PC : 2PS 5.35 m² #NAME? #NAME?
HARGA JUMLAH
NO. URAIAN PEKERJAAN VOLUME SAT. SATUAN HARGA
(Rp) (Rp)
4 Pekerjaan Plasteran Pondasi Adukan 1PC : 5PS 8.44 m² 75,038.74 633,326.97
5 Pekerjaan Acian Pasta Semen Plesteran Dinding dan Plesteran Beton 90.13 m² 45,307.12 4,083,530.73
HARGA JUMLAH
NO. URAIAN PEKERJAAN VOLUME SAT. SATUAN HARGA
(Rp) (Rp)
D. Pekerjaan Kusen, Pintu, Ventilasi dan Kaca
1 Pek. Kusen Pintu, Jendela dan Ventilasi Kayu Klas II 0.13 m³ #NAME? #NAME?
2 Pas. Daun Pintu Panil Kayu Klas I (pintu 2 daun) 3.36 m² #NAME? #NAME?
3 Pek. Pas. Kaca Bening T. 5 mm 1.30 m² #NAME? #NAME?

E. Pekerjaan Penggantung dan Pengunci


1 Pek. Pas. Kunci Pintu 2x Putar 1.00 Bh #NAME? #NAME?
2 Pek. Pas. Engsel Pintu 6.00 Bh #NAME? #NAME?
3 Pek. Pas. Kunci slot/Grendel Biasa 2.00 Bh #NAME? #NAME?

F. Pekerjaan Lantai
1 Pek. Urugan Tanah Bawah Lantai 4.48 m³ #NAME? #NAME?
2 Pek. Urugan Pasir Bawah Lantai 0.50 m³ 199,525.00 99,762.50
3 Pek. Pas. Rabat Lantai Adukan (Slab Beton K-100) 1.15 m³ #NAME? #NAME?
4 Pek. Pas. Tegel Keramik 60x60 cm, anti sliip 16.64 m² #NAME? #NAME?

G. Pekerjaan Plafond
1 Pek. Pas. Rangka Plafond besi hollow 1x40.40.2mm, modul 60 x 60 cm 24.15 m² #NAME? #NAME?
2 Pek. Pas. Plafond Kalsiboard t=3 mm 24.15 m² #NAME? #NAME?
3 Pek. Pas. List Plafond profil kayu 27.80 m' #NAME? #NAME?

H. Pekerjaan Atap dan Listplank


1 Pek. Pas. Rangka Atap Baja Ringan Main Truss C.75-75 + Reng R.33-0.45 37.48 m² #NAME? #NAME?
2 Pek. Rangka Atap/ Tiang, Besi Hollow
- Rangka Atap Besi Hollow Hitam 40x40x2 24.70 m' #NAME? #NAME?
- Tiang Atap Besi Hollow Hitam 40x60x2 9.80 m' #NAME? #NAME?
- Pengecatan Rangka Atap dan Tiang Besi Hollow 5.18 m² #NAME? #NAME?
3 Pekerjaan Pas. Atap Spandek 0.30 mm 44.98 m² #NAME? #NAME?
4 Pekerjaan Pas. Nok Atap Spandek 0.30 mm 17.00 m' #NAME? #NAME?
5 Pek. Listplank Kalsiplank, Uk. 1 x 20 Cm x 8 mm 22.80 m' #NAME? #NAME?

I. Pekerjaan Pengecatan
1 Pekerjaan Pengecatan Dinding, Kolom, dan Balok 83.39 m² #NAME? #NAME?
2 Pekerjaan Pengecatan Kusen, Pintu dan Ventilasi 12.39 m² #NAME? #NAME?
3 Pekerjaan Pengecatan Plafond 24.15 m² #NAME? #NAME?

J. Pekerjaan Listrik
1 Pekerjaan Pas. Titik Instalasi (Inc. Kabel 1x2.5 + Pipa Instalasi/Acc) 5.00 Titik #NAME? #NAME?
2 Pekerjaan Pas. Lampu Philips LED 19 Watt + Fitting Lampu 2.00 Bh #NAME? #NAME?
3 Pekerjaan Pas. Saklar ganda ex. Philips 1.00 Bh #NAME? #NAME?
4 Pekerjaan Pas. Stop Kontak ex. Philips 4.00 Bh #NAME? #NAME?
5 Biaya Penyambungan Daya 3500 VA + SLO + Stroom Awal + Biaya PPJ 1.00 Titik 4,000,000.00 4,000,000.00
Sub Jumlah III #NAME?
IV PEKERJAAN AKHIR
1 Pek. Pembersihan sisa-sisa pekerjaan 1.00 Ls 1,000,000.00 1,000,000.00

Sub Jumlah IV 1,000,000.00


BACK UP QUANTITY

SATAP 2 KONSEL
Data Opname Dimensi Pondasi
Panjang Pondasi Lebar Bawah = 0.60 m¹
P. Pondasi Pagar Depan Kanan = 20.00 m¹ Lebar Atas = 0.25 m¹
P. Pondasi Pagar Depan Kiri = 64.00 m¹ Tinggi Pondasi = 0.70 m¹
P. Pondasi Pagar Samping Kanan = m¹ Tinggi Galian = 0.55 m¹
P. Pondasi Pagar Samping Kiri = m¹ 84.00 m¹ Tebal Aanstamping = 0.20 m¹

Jumlah Kolom Utama


Kolom Pagar Depan Kanan = 8.00 Titik 60
Kolom Pagar Depan Kiri = 22.00 Titik
Kolom Pagar Samping Kanan = Titik TINGGI PONDASI 70
Kolom Pagar Samping Kiri = Titik

Jumlah Grid
Jumlah Grid Pagar Depan Kanan = 6.00 Unit = 2.80 m¹ Panjang
Jumlah Grid Pagar Depan Kiri = 21.00 Unit = 2.80 m¹ Panjang

Jumlah Grid Pagar Penutup Kanan = 1.00 Unit = 1.60 m¹ Panjang


Jumlah Grid Pagar Penutup Kiri = Unit = - m¹ Panjang

Jumlah Grid Pagar Samping Kanan = Unit = - m¹ Panjang


Jumlah Grid Pagar Samping Kiri = Unit = - m¹ Panjang (199.98)
Tinggi Pagar Samping = 1.25 m¹

No. URAIAN PEKERJAAN & CALCULATION SHEET


I. PEKERJAAN PERSIAPAN
1 Pek. Gudang dan Barak Kerja = 1.00 Ls
2 Pek. Pengukuran dan Pemasangan bouwplank = 1.00 Ls
3 Pek. Air Kerja = 1.00 Ls
4 Pek. Administrasi / Dokumentasi / Laporan = 1.00 Ls
5 Pek. Papan Nama Proyek = 1.00 Ls
6 K3 dan Keselamatan Kerja = 1.00 Ls
7 Pembersihan Sisa Pekerjaan = 1.00 Ls
8 Pek. Pembongkaran Bangunan Lama = Ls

II. PEK. TANAH, PASIR DAN PASANGAN PONDASI


1 Pek. Galian Tanah
RUMUS = P X L X T
P. Pondasi Depan Kanan = 20.00 X 0.60 X 0.55 = 6.60 m³
P. Pondasi Depan Kiri = 64.00 X 0.60 X 0.55 = 21.12 m³
Pagar Samping Kanan = - X 0.60 X 0.55 = 0.00 m³
Pagar Samping Kiri = - X 0.60 X 0.55 = 0.00 m³
V. Total = 27.72 m³

2 Pek. Urugan Tanah Kembali


RUMUS = V. Galian / 4.00 Galian
P. Pondasi Depan Kanan = 6.60 / 4.00 = 1.65 m³
P. Pondasi Depan Kiri = 21.12 / 4.00 = 5.28 m³
Pagar Samping Kanan = - / 4.00 = 0.00 m³
Pagar Samping Kiri = - / 4.00 = 0.00 m³
V. Total = 6.93 m³

3 Pek. Urugan Pasir bawah Pondasi


RUMUS = P X L X T
P. Pondasi Depan Kanan = 20.00 X 0.60 X 0.05 = 0.60 m³
P. Pondasi Depan Kiri = 64.00 X 0.60 X 0.05 = 1.92 m³
Pagar Samping Kanan = - X 0.60 X 0.05 = - m³
Pagar Samping Kiri = - X 0.60 X 0.05 = - m³
V. Total = 2.52 m³

4 Pek. Pas. Batu Kosong Pondasi


RUMUS = P X L X T
P. Pondasi Depan Kanan = 20.00 X 0.60 X 0.20 = 2.40 m³
P. Pondasi Depan Kiri = 64.00 X 0.60 X 0.20 = 7.68 m³
Pagar Samping Kanan = - X 0.60 X 0.20 = 0.00 m³
Pagar Samping Kiri = - X 0.60 X 0.20 = 0.00 m³
V. Total = 10.08 m³

5 Pek. Pas. Pondasi Batu Gunung 1 : 5 ( Bangunan )


RUMUS = P X Lbr rata2 X T
P. Pondasi Depan Kanan = 20.00 X 0.43 X 0.70 = 5.95 m³
P. Pondasi Depan Kiri = 64.00 X 0.43 X 0.70 = 19.04 m³
Pagar Samping Kanan = - X 0.43 X 0.70 = 0.00 m³
Pagar Samping Kiri = - X 0.43 X 0.70 = 0.00 m³
V. Total = 24.99 m³

III. PEK. PASANGAN BATU BATA DAN PLESTERAN


1 Pek. Dinding Pagar Batu Bata, 1 Pc : 5 Psr
RUMUS = P X T - Opening X Jml. Grid
Pagar Depan Kanan = 2.80 X 0.50 - 0.03 X 6.00 = 8.25 m³
16.8 = 0.76 X 0.60 - - X 6.00 = 2.74 m³
4.56
Pagar Depan Kiri = 2.80 X 0.50 - 0.03 X 21.00 = 28.88 m³
= 0.76 X 0.60 - - X 21.00 = 9.58 m³

Pagar Penutup Kanan = 1.60 X 1.25 1.00 X 1.00 = 2.00 m³


Pagar Penutup Kiri = - X 1.26 1.00 X - = - m³

Pagar Samping Kanan = - X 1.26 1.00 X - = - m³


Pagar Samping Kiri = - X 1.26 1.00 X - = - m³
V. Total = 51.44 m³

2 Pek.Plesteran 1 Pc : 5 Psr
RUMUS = P X T X Jml. Grid
Pagar Depan Kanan = 1.14 X 0.75 X 6.00 = 10.26 m²
= 3.10 X 0.85 X 6.00 = 31.62 m²

Pagar Depan Kiri = 1.14 X 0.75 X 21.00 = 35.91 m²


= 3.10 X 0.85 X 21.00 = 110.67 m²

Pagar Penutup Kanan = 1.80 X 1.60 X 1.00 = 5.76 m²


Pagar Penutup Kiri = - X 1.60 X - = - m²

Pagar Samping Kanan = - X 1.60 X - = - m²


Pagar Samping Kiri = - X 1.60 X - = - m²
V. Total = 194.22 m³

3 Pek. Plesteran Pondasi + Acian Semen,1 Pc : 5 Psr


RUMUS = P X T X Jml. Bidang
P. Pondasi Depan Kanan = 20.00 X 0.25 X 2 = 10 m²
P. Pondasi Depan Kiri = 64.00 X 0.25 X 2 = 32 m²
Pagar Samping Kanan = - X 0.25 X 2 = 0 m²
Pagar Samping Kiri = - X 0.25 X 2 = 0 m²
84.00 V. Total = 42.00 m³

IV. PEK. BETON, TRALIS DAN PINTU PAGAR


1 Pek. Slof Beton Uk. 10/20 Cm
RUMUS = P X L sloof X T Sloof
- Beton = 84.00 X 0.10 X 0.20 = 1.68 m³
V. Total = 1.68 m³

RUMUS = P X 2.T Sloof


Bekisting Sloof = 84.00 X 0.40 = 33.6 m²
- V. Total = 33.60 m²
- Pembesian
RUMUS P X Jml/P. Tul X Bj. Besi
Tulangan Pokok 4 Ø 10 mm = 84.00 X 4.00 X 0.617 = 207.14 Kg
Beugel Ø 6 mm - 15 cm = 560.00 X 0.49 X 0.222 60.65 Kg
V. Total = 267.80 Kg

2 Pek. Kolom Beton Uk. 17/22 Cm


RUMUS = T X P X L X Jml. Kolom
Beton = 1.60 X 0.22 X 0.17 X 30.00 = 1.80 m³
V. Total = 1.80 m³

RUMUS = 2P + 2L X T X Jml. Kolom


Bekisting Kolom = 0.44 + 0.34 X 1.60 X 30.00 = 37.44 m²
V. Total = 37.44 m²
Pembesian
RUMUS = P X Jml/P. Tul
Tulangan Pokok 4 Ø 10 mm = 55.50 X 4.00 X 0.617 = 136.86 Kg
Beugel Ø 6 mm - 15 cm = 370.00 X 0.66 X 0.222 = 54.20 Kg
V. Total = 191.06 Kg

3 Pek. Kolom Beton Uk. 11/11 Cm


RUMUS = T X Titik/Grid X Jml. Grid
Beton Kolom 11/11 = 0.75 X 2.00 X 27.00 = 40.50 m¹
V. Total = 40.50 m¹

4 Pek. Ringbalk Beton Uk 10/15 Cm


RUMUS = P X Jml. Grid
Pagar Depan Kanan = 2.80 X 6.00 Ringbalk Tengah = 16.80 m¹
= 0.76 X 6.00 Ringbalk Atas 2 x = 4.56 m¹
Pagar Depan Kiri = 2.80 X 21.00 Ringbalk Tengah = 58.80 m¹
= 0.76 X 21.00 Ringbalk Atas 2 x = 15.96 m¹
Pagar Penutup Kanan = 1.60 X 1.00 Ringbalk Atas = 1.60 m¹
Pagar Penutup Kiri = - X - Ringbalk Atas = - m¹
Pagar Samping Kanan = 2.80 X - Ringbalk Atas = - m¹
Pagar Samping Kiri = 2.80 X - Ringbalk Atas = - m¹
V. Total = 97.72 m¹

5 Pek. Beton Tanpa Tulang Uk 27/32 Cm ( Topi)


RUMUS = P X L X T X Jml
0.32 X 0.27 X 0.05 X 30.00 = 0.13 m³
V. Total = 0.13 m¹

6 Pas. Tralis Pagar Besi 4/4 T. 1,4mm dan 2/4 t.1,4mm


RUMUS = P X T X JML
1.85 X 0.63 X 27.00 = 31.47 m²
V. Total = 31.47 m²

V. PEKERJAAN PENGECATAN DAN PEMBERSIHAN AKHIR


1 Pek. Cat Anti Lumut ( No Drop atau Sejenis )
RUMUS = Jumlah Luas Plesteran
V = 194.22 m²

2 Pembersihan Sisa Pekerjaan


= 1.00 Ls

1,063.09 863.10706

(199.98)
REKAPITULASI
RINCIAN ANGGARAN BIAYA

Pekerjaan : Pembangunan Pagar SD SMPN Satu Atap 2 Konawe Selatan


Lokasi : SD SMPN Satu Atap 2 Konawe Selatan
Tahun Anggaran : 2022

NO. URAIAN PEKERJAAN TOTAL HARGA

I PEK. PENDAHULUAN / PERSIAPAN Rp 6,899,000.00


II PEK. TANAH, PASIR DAN PASANGAN PONDASI Rp 36,959,911.55
III PEK. PASANGAN BATU BATA DAN PLESTERAN Rp 27,453,491.79
IV PEK. BETON, TRALIS DAN PINTU PAGAR Rp 83,379,735.10
V PEKERJAAN PENGECATAN DAN PEMBERSIHAN AKHIR Rp 7,617,700.76

NILAI PEKERJAAN Rp 162,309,839.19


PPN 11 % Rp 17,854,082.31
NILAI TOTAL Rp 180,163,921.50
DIBULATKAN Rp 180,160,000.00

Terbilang : Seratus Delapan Puluh Juta Seratus Enam Puluh Ribu Rupiah,--

Kendari, 14 Agustus 2023

Dibuat Oleh :
CV. BUMI SULTRA

FAJAR NOVIANTARTO
Direktur
RINCIAN ANGGARAN BIAYA

Pekerjaan : Pembangunan Pagar SD SMPN Satu Atap 2 Konawe Selatan


Lokasi : SD SMPN Satu Atap 2 Konawe Selatan
Tahun Anggaran : 2022

NO. URAIAN PEKERJAAN VOL. SAT. HARGA SATUAN JUMLAH HARGA

I PEK. PENDAHULUAN / PERSIAPAN


1 Pek. Gudang dan Barak Kerja 1.00 Ls 1,250,000.00 Rp 1,250,000.00
2 Pek. Pengukuran dan Pemasangan bouwplank 1.00 Ls 750,000.00 Rp 750,000.00
3 Pek. Air Kerja 1.00 Ls 745,000.00 Rp 745,000.00
4 Pek. Administrasi / Dokumentasi / Laporan 1.00 Ls 2,100,000.00 Rp 2,100,000.00
5 Pek. Papan Nama Proyek 1.00 Ls 154,000.00 Rp 154,000.00
6 K3 dan Keselamatan Kerja 1.00 Ls 1,900,000.00 Rp 1,900,000.00
JUMLAH I
PEK. PENDAHULUAN / PERSIAPAN 6,899,000.00
II PEK. TANAH, PASIR DAN PASANGAN PONDASI
1 Pek. Galian Tanah 27.72 M3 81,362.50 Rp 2,255,368.50
2 Pek. Urugan Tanah Kembali 6.93 M3 58,305.00 Rp 404,053.65
3 Pek. Urugan Pasir bawah Pondasi 2.52 M3 199,525.00 Rp 502,803.00
4 Pek. Pas. Batu Kosong Pondasi 10.08 M3 604,233.00 Rp 6,090,668.64
5 Pek. Pas. Pondasi Batu Gunung 1 : 5 ( Bangunan ) 24.99 M3 1,108,724.20 Rp 27,707,017.76
JUMLAH II PEK. TANAH, PASIR DAN PASANGAN PONDASI 36,959,911.55
III PEK. PASANGAN BATU BATA DAN PLESTERAN
1 Pek. Dinding Pagar Batu Bata, 1 Pc : 5 Psr 51.44 M2 152,126.71 Rp 7,824,941.58
2 Pek.Plesteran 1 Pc : 5 Psr 194.22 M2 75,038.74 Rp 14,574,024.08
3 Pek. Plesteran Pondasi + Acian Semen,1 Pc : 5 Psr 42.00 M2 120,345.86 Rp 5,054,526.12
JUMLAH III PEK. PASANGAN BATU BATA DAN PLESTERAN 27,453,491.79
IV PEK. BETON, TRALIS DAN PINTU PAGAR
1 Pek. Slof Beton Uk. 10/20 Cm
- Beton 1.68 M3 1,555,163.41 Rp 2,612,674.53
- Bekisting Sloof 33.60 M2 172,186.05 Rp 5,785,451.28
- Pembesian 267.80 Kg 26,392.50 Rp 7,067,799.68
2 Pek. Kolom Beton Uk. 17/22 Cm
- Beton 1.80 M3 1,555,163.41 Rp 2,791,829.35
- Bekisting Kolom 2 X Pakai 37.44 M2 235,207.77 Rp 8,806,178.91
- Pembesian 191.06 Kg 26,392.50 Rp 5,042,570.79
3 Pek. Kolom Beton Uk. 11/11 Cm 40.50 M1 132,687.00 Rp 5,373,823.50
4 Pek. Ringbalk Beton Uk 10/15 Cm 97.72 M1 159,109.51 Rp 15,548,181.32
5 Pek. Beton Tanpa Tulang Uk 27/32 Cm ( Topi) 0.13 M3 1,555,163.41 Rp 201,549.18
6 Pas. Tralis Pagar Besi 4/4 T. 1,4mm dan 2/4 t.1,4mm 31.47 M2 958,090.68 Rp 30,149,676.56
JUMLAH IV PEK. BETON, TRALIS DAN PINTU PAGAR 83,379,735.10
V PEKERJAAN PENGECATAN DAN PEMBERSIHAN AKHIR
1 Pek. Cat Anti Lumut ( No Drop atau Sejenis ) 194.22 M2 36,647.62 Rp 7,117,700.76
2 Pembersihan Sisa Pekerjaan 1.00 Ls 500,000.00 Rp 500,000.00
JUMLAH V PEKERJAAN PENGECATAN DAN PEMBERSIHAN AKHIR 7,617,700.76

Kendari, 14 Agustus 2023

Dibuat Oleh :
CV. BUMI SULTRA

FAJAR NOVIANTARTO
Direktur
DAFTAR HARGA SATUAN PEKERJAAN
I A.2.2.1 HARGA SATUAN PEKERJAAN PERSIAPAN
- A. 2.2.1.2. Pembuatan 1 m2 Pagar Sementara dari Seng Gelombang Tinggi 2 meter Rp. 243,340.00
- A. 2.2.1.4. Pengukuran dan pemasangan 1 m’ Bouwplank Rp. 82,639.00

II A.2.3.1.1. HARGA SATUAN PEKERJAAN TANAH


- A.2.3.1.1. Penggalian 1 m³ Tanah Biasa Sedalam 1 m Rp. 81,362.50
- A.2.3.1.9. Pengurugan kembali 1 m3 galian tanah Rp. 58,305.00
- A.2.3.1.11. Pengurugan 1 m³ dengan pasir urug Rp. 199,525.00
- ### #NAME?

III A.3.2.1 HARGA SATUAN PEKERJAAN PONDASI


- A.3.2.1.3. Pemas.1 m³ Pondasi Batu Gunung camp. 1SP : 5PP Rp. 1,108,724.20
- A.3.2.1.9. Pemas.1 m³ Batu kosong (anstamping) Rp. 604,233.00

IV A.4.1.1. HARGA SATUAN PEKERJAAN BETON


- ### #NAME?
- ### #NAME?
- A.4.1.1.7. Membuat 1 m³ beton mutu f'c = 19,3 Mpa (K 225), Rp. 1,555,163.41
- A.4.1.1.17. Pembesian 10 Kg dengan besi polos atau besi ulir Rp. 263,925.00
- Jadi dalam 1 Kg dibutuhkan Rp. 26,392.50
- ### #NAME?
- A.4.1.1.21. (K3) Pemas.1 m² bekisting untuk sloof Rp. 172,186.05
- A.4.1.1.22. (K3) Pemas.1 m² bekisting untuk kolom 2 Kali Pakai Rp. 235,207.77
- ### #NAME?
- A.4.1.1.36. membuat 1 m' ring balok beton bertulang ( 10x15 ) cm Rp. 159,109.51
- A.4.1.1.35 . membuat 1 m' kolom praktis beton bertulang ( 11x11 ) cm Rp. 132,687.00

V A.4.2.1 HARGA SATUAN PEKERJAAN BESI


- ### #NAME?
- Jadi dalam 1 cm dibutuhkan #NAME?
- A.4.2.1.5. Pengerjaan 10 cm pengelasan dengan las listrik (tanpa upah dan Overhead) Rp. 6,072.50
- ### #NAME?
- ### #NAME?
- ### #NAME?
- ### #NAME?
- ### #NAME?
- ### #NAME?
- ### #NAME?

VI A.4.4.1 HARGA SATUAN PEKERJAAN PASANGAN DINDING


- ### #NAME?
- ### #NAME?
- A.4.4.1.10 Pemas.1m² dinding bata merah cm tebal ½ batu camp. 1SP : 5PP Rp. 152,126.71

VI A.4.4.2 HARGA SATUAN PEKERJAAN PLESTERAN


- ### #NAME?
- ### #NAME?
- ### #NAME?
- A.4.4.2.5. Pemas.1m² plesteran 1 SP : 5 PP tebal 15 mm Rp. 75,038.74
- ### #NAME?
- A.4.4.2.27. Pemas.1m² acian Rp. 45,307.12

VII ###
- ### #NAME?
- ### #NAME?
- ### #NAME?
- #NAME? #NAME?
- #NAME? #NAME?

IX ###
- #NAME? #NAME?
- ### #NAME?

X ###
- ### #NAME?
- ### #NAME?
- ### #NAME?
- ### #NAME?

XI ###
- ### #NAME?
- ### #NAME?
- ### #NAME?
- ### #NAME?
- ### #NAME?
- ### #NAME?
- ### #NAME?
- ### #NAME?
- #NAME? #NAME?
XII ###
- ### #NAME?
- ### #NAME?
- ### #NAME?
- ### #NAME?
- ### #NAME?
- ### #NAME?
- ### #NAME?

XIII ###
- #NAME? #NAME?
- #NAME? #NAME?
- #NAME? #NAME?
- ### #NAME?
- A.4.7.1.10. Pengecetan 1 m² tembok baru ( 1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penut Rp. 36,647.62
- ### #NAME?
- ### #NAME?
- ### #NAME?
- ### #NAME?
- ### #NAME?
- ### #NAME?

XV ###
- ### #NAME?
- ### #NAME?
- ### #NAME?
- ### #NAME?
- ### #NAME?

Unaaha, 2022
DIBUAT OLEH
KONSULTAN PERENCANA
CV. DINDING JELAJAH

M. FAHRI USMAN, S. Ars.


19620407 198103 2 002 Direktur
Rincian Daftar Kuantitas & Harga Biaya Penerapan
Sistem Manajemen Keselamatan & Kesehatan Kerja (SMK3)

Harga Satuan Jumlah Harga


No. Uraian Satuan Kuantitas
(Rp) (Rp)
1 Penyiapan RK3K
a. Pembuatan Manual, Prosedur, Instruksi
Set 1.00 300,000.00 300,000.00
Kerja, Ijin Kerja
b. Pembuatan Kartu Identitas Pekerja (KIP) Org - -
Sub Total Penyiapan RK3K 300,000.00
g. Papan Informasi K3 Bh 1.00 100,000.00 100,000.00
Sub Total Sosialisasi, Promosi dan Pelatihan 100,000.00
3 Alat Pelindung Kerja
e. Pembatas Area (Restricted Area) Ls 1.00 200,000.00 200,000.00
Sub Total Alat Pelindung Kerja 200,000.00
4 Alat Pelindung Diri
a. Topi Pelindung (Safety Helmet) Bh 5.00 100,000.00 500,000.00
h. Sepatu Keselamatan (Safety Shoes) Psg 5.00 100,000.00 500,000.00
Sub Total Alat Pelindung Diri 1,000,000.00
5 Asuransi dan Perizinan
a. BPJS Ketenagakerjaan & Kesehatan Ls 1.00 378,000.00 378,000.00
Sub Total Asuransi dan Perizinan 378,000.00
6 Personil K3
b. Petugas K3 OB 1.00 500,000.00 500,000.00
Sub Total Personel K3 500,000.00
7 Fasilitas Sarana Kesehatan
Peralatan P3K (Kotak P3K, Tandu, Tabung
a. Ls 1.00 250,000.00 250,000.00
Oksigen, Obat Luka, Perban dll)
Sub Total Fasilitas Kesehatan 250,000.00
8 Rambu-rambu
a. Rambu Petunjuk Bh 1.00 50,000.00 50,000.00
b. Rambu Larangan Bh 1.00 50,000.00 50,000.00
c. Rambu Peringatan Bh 1.00 50,000.00 50,000.00
d. Rambu Kewajiban Bh 1.00 50,000.00 50,000.00
e. Rambu Informasi Bh 1.00 50,000.00 50,000.00
Sub Total Rambu-rambu 250,000.00
9 Lain Lain Terkait Pengendalian Risiko K3
c. Bendera K3 Bh 1.00 100,000.00 100,000.00
Sub Total Kegiatan dan peralatan terkait dengan pengendalian Risiko Keselamatan Konstruksi 100,000.00
J u m l a h (1+2+3+4+5+6+7+8+9) 3,078,000.00

Kendari, 14 Agustus 2023

Dibuat Oleh :
#NAME?

Rp -
Rp -
RINCIAN HARGA BIAYA PENERAPAN
SISTEM MANAJEMEN KESELAMATAN & KESEHATAN KERJA (SMK3)

Pekerjaan : Pembangunan Pagar SD SMPN Satu Atap 2 Konawe Selatan


Lokasi : SD SMPN Satu Atap 2 Konawe Selatan
Tahun Anggaran : 2022

HARGA SATUAN JUMLAH HARGA


No. URAIAN SATUAN KUANTITAS
(Rp) (Rp)

1 Papan Informasi K3 Bh 1.00 100,000.00 100,000.00


2 Pembatas Area (Restricted Area) Ls 1.00 200,000.00 200,000.00
3 Topi Pelindung (Safety Helmet) Bh 5.00 100,000.00 500,000.00
4 Sepatu Keselamatan (Safety Shoes) Psg 5.00 100,000.00 500,000.00
Peralatan P3K (Kotak P3K, Tandu,
5 Ls 1.00 250,000.00 250,000.00
Tabung Oksigen, Obat Luka, Perban dll)
6 Rambu Petunjuk Bh 1.00 50,000.00 50,000.00
7 Rambu Larangan Bh 1.00 50,000.00 50,000.00
8 Rambu Peringatan Bh 1.00 50,000.00 50,000.00
9 Rambu Kewajiban Bh 1.00 50,000.00 50,000.00
10 Rambu Informasi Bh 1.00 50,000.00 50,000.00
11 Bendera K3 Bh 1.00 100,000.00 100,000.00
1,900,000.00

Kendari, 14 Agustus 2023

Dibuat Oleh :
CV. BUMI SULTRA

FAJAR NOVIANTARTO
Direktur
ANALISIS HARGA SATUAN PEKERJAAN (AHSP) Bid. CIPTA KARYA
Berdasarkan Peraturan Menteri Pekerjaan Umum dan Perumahan Rakyat
Nomor 1 Tahun 2022

A.2.2.1 HARGA SATUAN PEKERJAAN PERSIAPAN


A. 2.2.1.2. Pembuatan 1 m2 Pagar Sementara dari Seng Gelombang Tinggi 2 meter
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.200 100,000.00 20,000.00
Tukang kayu L.02 OH 0.400 120,000.00 48,000.00
Kepala Tukang L.03 OH 0.020 125,000.00 2,500.00
Mandor L.04 OH 0.020 125,000.00 2,500.00
JUMLAH TENAGA KERJA 73,000.00
B BAHAN
Dolken kayu 8-10/400 cm Batang 1.250 12,000.00 15,000.00
Kayu 5/7 m3 0.072 1,300,000.00 93,600.00
Seng Gelombang Lbr 1.200 24,000.00 28,800.00
Paku Campur Kg 0.060 20,000.00 1,200.00
JUMLAH HARGA BAHAN 138,600.00
C PERALATAN

JUMLAH HARGA ALAT

D JUMLAH(A+B+C) 211,600.00
E Overhead dan Profit 15% xD 31,740.00
F Harga Suatu pekerjaan (D+E) 243,340.00

A. 2.2.1.4. Pengukuran dan pemasangan 1 m’ Bouwplank


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.100 90,800.00 9,080.00
Tukang kayu L.02 OH 0.100 120,000.00 12,000.00
Kepala tukang L.03 OH 0.010 130,000.00 1,300.00
Mandor L.04 OH 0.005 106,000.00 530.00
JUMLAH TENAGA KERJA 22,910.00
B BAHAN
Balok Kaso 5/7 Kls II m3 0.012 2,750,000.00 33,000.00
Paku Campur Kg 0.020 27,500.00 550.00
Balok/Papan Kayu Klas III (bekisting) m3 0.007 2,200,000.00 15,400.00
JUMLAH HARGA BAHAN 48,950.00
C PERALATAN

JUMLAH HARGA ALAT

D JUMLAH(A+B+C) 71,860.00
E Overhead dan Profit 15% xD 10,779.00
F Harga Suatu pekerjaan (D+E) 82,639.00
A.2.3.1.1. HARGA SATUAN PEKERJAAN TANAH
A.2.3.1.1. Penggalian 1 m³ Tanah Biasa Sedalam 1 m
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.750 90,800.00 68,100.00
Mandor L.04 OH 0.025 106,000.00 2,650.00
JUMLAH TENAGA KERJA 70,750.00
B BAHAN
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D JUMLAH(A+B+C) 70,750.00
E Overhead dan Profit 15% xD 10,612.50
F Harga Suatu pekerjaan (D+E) 81,362.50

A.2.3.1.9. Pengurugan kembali 1 m3 galian tanah


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.500 90,800.00 45,400.00
Mandor L.04 OH 0.050 106,000.00 5,300.00
JUMLAH TENAGA KERJA 50,700.00
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN

JUMLAH HARGA ALAT

D JUMLAH(A+B+C) 50,700.00
E Overhead dan Profit 15% xD 7,605.00
F Harga Suatu pekerjaan (D+E) 58,305.00

A.2.3.1.11. Pengurugan 1 m³ dengan pasir urug


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.300 90,800.00 27,240.00
Mandor L.04 OH 0.010 106,000.00 1,060.00
JUMLAH TENAGA KERJA 28,300.00
B BAHAN
Pasir urug m3 1.200 121,000.00 145,200.00
JUMLAH HARGA BAHAN 145,200.00
C PERALATAN

JUMLAH HARGA ALAT

D JUMLAH(A+B+C) 173,500.00
E Overhead dan Profit 15% xD 26,025.00
F Harga Suatu pekerjaan (D+E) 199,525.00
A.3.2.1 HARGA SATUAN PEKERJAAN PONDASI
A.3.2.1.3. Pemas.1 m³ Pondasi Batu Gunung camp. 1SP : 5PP
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.500 90,800.00 136,200.00
Tukang Batu L.02 OH 0.750 128,000.00 96,000.00
Kepala Tukang L.03 OH 0.075 130,000.00 9,750.00
Mandor L.04 OH 0.075 106,000.00 7,950.00
JUMLAH TENAGA KERJA 249,900.00
B BAHAN
Batu Gunung m³ 1.200 286,000.00 343,200.00
Semen Portland Kg 136.000 1,870.00 254,320.00
Pasir Pasang m³ 0.544 214,500.00 116,688.00
JUMLAH HARGA BAHAN 714,208.00
C PERALATAN

JUMLAH HARGA ALAT


D JUMLAH(A+B+C) 964,108.00
E Overhead dan Profit 15% xD 144,616.20
F Harga Suatu pekerjaan (D+E) 1,108,724.20

A.3.2.1.9. Pemas.1 m³ Batu kosong (anstamping)


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.780 90,800.00 70,824.00
Tukang Batu L.02 OH 0.390 128,000.00 49,920.00
Kepala Tukang L.03 OH 0.039 130,000.00 5,070.00
Mandor L.04 OH 0.039 106,000.00 4,134.00
JUMLAH TENAGA KERJA 129,948.00
B BAHAN
Batu Gunung m³ 1.200 286,000.00 343,200.00
Pasir Urug m³ 0.432 121,000.00 52,272.00
JUMLAH HARGA BAHAN 395,472.00
C PERALATAN
JUMLAH HARGA ALAT
D JUMLAH(A+B+C) 525,420.00
E Overhead dan Profit 15% xD 78,813.00
F Harga Suatu pekerjaan (D+E) 604,233.00

A.4.1.1. HARGA SATUAN PEKERJAAN BETON


A.4.1.1.7. Membuat 1 m³ beton mutu f'c = 19,3 Mpa (K 225),
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.650 90,800.00 149,820.00
Tukang Batu L.02 OH 0.275 128,000.00 35,200.00
Kepala Tukang L.03 OH 0.028 130,000.00 3,640.00
Mandor L.04 OH 0.083 106,000.00 8,798.00
JUMLAH TENAGA KERJA 197,458.00
B BAHAN
Semen Portland Kg 371.000 1,870.00 693,770.00
Pasir Beton Kg 698.000 153.21 106,943.57
Kerikil/Suplit Kg 1,047.000 325.93 341,244.44
Air Liter 215.000 60.00 12,900.00
JUMLAH HARGA BAHAN 1,154,858.02
C PERALATAN
JUMLAH HARGA ALAT
D JUMLAH(A+B+C) 1,352,316.02
E Overhead dan Profit 15% xD 202,847.40
F Harga Suatu pekerjaan (D+E) 1,555,163.41
A.4.1.1.17. Pembesian 10 Kg dengan besi polos atau besi ulir
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.070 90,800.00 6,356.00
Tukang Besi L.02 OH 0.070 128,000.00 8,960.00
Kepala Tukang L.03 OH 0.007 130,000.00 910.00
Mandor L.04 OH 0.004 106,000.00 424.00
JUMLAH TENAGA KERJA 16,650.00
B BAHAN
Besi beton ( polos/ulir ) Kg 10.500 19,800.00 207,900.00
Kawat beton Kg 0.150 33,000.00 4,950.00
JUMLAH HARGA BAHAN 212,850.00
C PERALATAN

JUMLAH HARGA ALAT


D JUMLAH(A+B+C) 229,500.00
E Overhead dan Profit 15% xD 34,425.00
F Harga Suatu pekerjaan (D+E) 263,925.00
G Jadi dalam 1 Kg Besi dibutuhkan 26,392.50

A.4.1.1.21. (K3) Pemas.1 m² bekisting untuk sloof


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.520 90,800.00 47,216.00
Tukang kayu L.02 OH 0.260 120,000.00 31,200.00
Kepala Tukang L.03 OH 0.026 130,000.00 3,380.00
Mandor L.04 OH 0.026 106,000.00 2,756.00
JUMLAH TENAGA KERJA 84,552.00
B BAHAN
Balok/Papan Kayu Klas III (bekisting) m³ 0.045 1,265,000.00 56,925.00
Paku Campur Kg 0.300 27,500.00 8,250.00
JUMLAH HARGA BAHAN 65,175.00
C PERALATAN
JUMLAH HARGA ALAT
D JUMLAH(A+B+C) 149,727.00
E Overhead dan Profit 15% xD 22,459.05
F Harga Suatu pekerjaan (D+E) 172,186.05

A.4.1.1.22. (K3) Pemas.1 m² bekisting untuk kolom 2 Kali Pakai


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.660 90,800.00 59,928.00
Tukang Kayu L.02 OH 0.330 120,000.00 39,600.00
Kepala Tukang L.03 OH 0.033 130,000.00 4,290.00
Mandor L.04 OH 0.033 106,000.00 3,498.00
JUMLAH TENAGA KERJA 107,316.00
B BAHAN
Balok Kayu/Papan kelas III m³ 0.020 1,265,000.00 25,300.00
Paku Campur Kg 0.200 27,500.00 5,500.00
Balok Kayu kelas II m³ 0.008 2,750,000.00 20,625.00
Plywood tebal 9 mm Lbr 0.175 148,500.00 25,987.50
Dolken kayu, 8-10 cm- panj 4 m Batang 1.000 19,800.00 19,800.00
JUMLAH HARGA BAHAN 97,212.50
C PERALATAN
JUMLAH HARGA ALAT
D JUMLAH(A+B+C) 204,528.50
E Overhead dan Profit 15% xD 30,679.27
F Harga Suatu pekerjaan (D+E) 235,207.77
A.4.1.1.36. membuat 1 m' ring balok beton bertulang ( 10x15 ) cm
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.297 90,800.00 26,967.60
Tukang batu L.02 OH 0.033 128,000.00 4,224.00
Tukang Kayu L.02 OH 0.033 120,000.00 3,960.00
Tukang besi L.02 OH 0.033 128,000.00 4,224.00
Kepala Tukang L.03 OH 0.010 130,000.00 1,300.00
Mandor L.04 OH 0.015 106,000.00 1,590.00
JUMLAH TENAGA KERJA 42,265.60
B BAHAN
Balok Kayu/Papan kelas III m³ 0.003 1,265,000.00 3,795.00
Paku Campur Kg 0.020 27,500.00 550.00
Besi beton polos Kg 3.600 19,800.00 71,280.00
Kawat beton Kg 0.050 33,000.00 1,650.00
Semen portland Kg 5.500 1,870.00 10,285.00
Pasir beton m³ 0.009 214,500.00 1,930.50
kerikil/Suplit m³ 0.015 440,000.00 6,600.00
JUMLAH HARGA BAHAN 96,090.50
C PERALATAN

JUMLAH HARGA ALAT


D JUMLAH(A+B+C) 138,356.10
E Overhead dan Profit 15% xD 20,753.42
F Harga Suatu pekerjaan (D+E) 159,109.51

A.4.1.1.35 . membuat 1 m' kolom praktis beton bertulang ( 11x11 ) cm


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.180 90,800.00 16,344.00
Tukang Batu L.02 OH 0.020 128,000.00 2,560.00
Tukang Kayu L.02 OH 0.020 120,000.00 2,400.00
Tukang Besi L.02 OH 0.020 128,000.00 2,560.00
Kepala Tukang L.03 OH 0.006 130,000.00 780.00
Mandor L.04 OH 0.009 106,000.00 954.00
JUMLAH TENAGA KERJA 25,598.00
B BAHAN
Balok Kayu/Papan kelas III m³ 0.002 1,265,000.00 2,530.00
Paku Campur Kg 0.010 27,500.00 275.00
Besi beton polos Kg 3.000 19,800.00 59,400.00
Kawat beton Kg 0.450 33,000.00 14,850.00
Semen portland Kg 4.000 1,870.00 7,480.00
Pasir beton m³ 0.006 214,500.00 1,287.00
kerikil/Suplit m³ 0.009 440,000.00 3,960.00
JUMLAH HARGA BAHAN 89,782.00
C PERALATAN

JUMLAH HARGA ALAT


D JUMLAH(A+B+C) 115,380.00
E Overhead dan Profit 15% xD 17,307.00
F Harga Suatu pekerjaan (D+E) 132,687.00

A.4.2.1 HARGA SATUAN PEKERJAAN BESI


A.4.2.1.5. Pengerjaan 10 cm pengelasan dengan las listrik (tanpa upah dan Overhead)
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A BAHAN
Kawat las listrik Kg 0.400 110,000.00 44,000.00
Solar Liter 0.300 6,800.00 2,040.00
Minyak pelumas Liter 0.040 16,500.00 660.00
JUMLAH HARGA BAHAN 46,700.00
B PERALATAN
Sewa Alat Jam 0.170 82,500.00 14,025.00
JUMLAH HARGA ALAT
C JUMLAH(A+B+C) 60,725.00
D Harga Suatu pekerjaan dalam 1 Cm 6,072.50
A.4.2.1.21. Pemas.1 m² tralis besi hollow 4/4 t=1,4 mm dan 2/4 t=1,4 mm
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.350 90,800.00 31,780.00
Tukang Besi L.03 OH 0.350 128,000.00 44,800.00
Kepala Tukang L.03 OH 0.035 130,000.00 4,550.00
Mandor L.04 OH 0.018 106,000.00 1,908.00
JUMLAH TENAGA KERJA 83,038.00
B BAHAN
Besi Holow galvanish 4/4 T. 1,4mm M1 4.9900 45,833.33 228,708.33
Besi Holow galvanish 2/4 T. 1,4mm M1 7.5200 41,800.00 314,336.00
Pengelasan Cm 31.2000 6,072.50 189,462.00
Cat Besi Kg 0.1880 93,500.00 17,578.00
JUMLAH HARGA BAHAN 750,084.33
C PERALATAN

JUMLAH HARGA ALAT


D JUMLAH(A+B+C) 833,122.33
E Overhead dan Profit 15% xD 124,968.35
F Harga Suatu pekerjaan (D+E) 958,090.68

A.4.4.1 HARGA SATUAN PEKERJAAN PASANGAN DINDING


A.4.4.1.10 Pemas.1m² dinding bata merah cm tebal ½ batu camp. 1SP : 5PP
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.300 90,800.00 27,240.00
Tukang Batu L.03 OH 0.100 128,000.00 12,800.00
Kepala Tukang L.03 OH 0.010 130,000.00 1,300.00
mandor L.04 OH 0.015 106,000.00 1,590.00
JUMLAH TENAGA KERJA 42,930.00
B BAHAN
Bata Merah m³ 70.000 880.00 61,600.00
Semen Portland Kg 9.680 1,870.00 18,101.60
Pasir Pasang m³ 0.045 214,500.00 9,652.50
JUMLAH HARGA BAHAN 89,354.10
C PERALATAN

JUMLAH HARGA ALAT


D JUMLAH(A+B+C) 132,284.10
E Overhead dan Profit 15% xD 19,842.62
F Harga Suatu pekerjaan (D+E) 152,126.71

A.4.4.2 HARGA SATUAN PEKERJAAN PLESTERAN


A.4.4.2.5. Pemas.1m² plesteran 1 SP : 5 PP tebal 15 mm
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.300 90,800.00 27,240.00
Tukang Batu L.03 OH 0.150 128,000.00 19,200.00
Kepala Tukang L.03 OH 0.015 130,000.00 1,950.00
mandor L.04 OH 0.015 106,000.00 1,590.00
JUMLAH TENAGA KERJA 49,980.00
B BAHAN
Semen Portland Kg 5.184 1,870.00 9,694.08
Pasir Pasang m³ 0.026 214,500.00 5,577.00
JUMLAH HARGA BAHAN 15,271.08
C PERALATAN
JUMLAH HARGA ALAT
D JUMLAH(A+B+C) 65,251.08
E Overhead dan Profit 15% xD 9,787.66
F Harga Suatu pekerjaan (D+E) 75,038.74
A.4.4.2.27. Pemas.1m² acian
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.200 90,800.00 18,160.00
Tukang Batu L.03 OH 0.100 128,000.00 12,800.00
Kepala Tukang L.03 OH 0.010 130,000.00 1,300.00
mandor L.04 OH 0.010 106,000.00 1,060.00
JUMLAH TENAGA KERJA 33,320.00
B BAHAN
Semen PC Kg 3.250 1,870.00 6,077.50
JUMLAH HARGA BAHAN 6,077.50
C PERALATAN
JUMLAH HARGA ALAT
D JUMLAH(A+B+C) 39,397.50
E Overhead dan Profit 15% xD 5,909.63
F Harga Suatu pekerjaan (D+E) 45,307.12

A.4.7.1.10. Pengecetan 1 m² tembok baru ( 1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup )
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.020 90,800.00 1,816.00
Tukang cat L.02 Oh 0.063 111,500.00 7,024.50
Kepala Tukang L.03 OH 0.006 130,000.00 819.00
mandor L.04 OH 0.003 106,000.00 318.00
JUMLAH TENAGA KERJA 9,977.50
B BAHAN
Plamuur Kg 0.100 20,900.00 2,090.00
Cat dasar Kg 0.100 55,000.00 5,500.00
Cat penutup Kg 0.260 55,000.00 14,300.00
JUMLAH HARGA BAHAN 21,890.00
C PERALATAN
JUMLAH HARGA ALAT
D JUMLAH(A+B+C) 31,867.50
E Overhead dan Profit 15% xD 4,780.13
F Harga Suatu pekerjaan (D+E) 36,647.62

Kendari, 14 Agustus 2023

Dibuat Oleh :
CV. BUMI SULTRA

FAJAR NOVIANTARTO
Direktur
Rincian Daftar Kuantitas & Harga Biaya Penerapan
Sistem Manajemen Keselamatan & Kesehatan Kerja (SMK3)

Harga Satuan Jumlah Harga


No. Uraian Satuan Kuantitas
(Rp) (Rp)
1 Penyiapan RK3K
a.Pembuatan Manual, Prosedur, Instruksi Kerja,
Set 1.00 300,000.00 300,000.00
Ijin Kerja
b. Pembuatan Kartu Identitas Pekerja (KIP) Org - -
Sub Total Penyiapan RK3K 300,000.00
2 Sosialisasi dan Promosi K3
a. Induksi K3 (Safety Induction) Org - - -
b. Pengarahan K3 (Safety Briefing) Org - - -
Pertemuan Keselamatan (Safety Talk dan/atau
Tool Box Meeting)
c. Pelatihan K3
a. Bekerja diketinggian Org - -
b. K3 Peralatan Konstruksi & Penggunaan Bahan
- -
Kimia (MSDS) Org
c. Analisis Keselamatan Pekerjaan Org - - -
d. Prilaku Berbasis Keselamatan (Budaya K3) Org - - -
e. P3K Org - - -
d. Simulasi K3 Org - - -
e. Spanduk (Banner) Lbr 1.00 - -
f. Poster Lbr 1.00 - -
g. Papan Informasi K3 Bh 1.00 100,000.00 100,000.00
Sub Total Sosialisasi, Promosi dan Pelatihan 100,000.00
3 Alat Pelindung Kerja
a. Jaring Pengaman (Safety Net) Ls - - -
b. Tali Keselamatan ( Life Line) Ls - 300,000.00 -
c. Penahan Jatuh (Safety Deck) Ls - - -
d. Pagar Pengaman (Guard Railling) Ls - - -
e. Pembatas Area (Restricted Area) Ls 1.00 200,000.00 200,000.00
Sub Total Alat Pelindung Kerja 200,000.00
4 Alat Pelindung Diri
a. Topi Pelindung (Safety Helmet) Bh 5.00 100,000.00 500,000.00
b. Pelindung Mata (Goggles Spectacles) Psg - - -
c. Tameng Muka (Face Shield) Bh - - -
d. Masker Selam (Breathing Apparatus) Bh - - -
e. Pelindung Telinga (Ear Plug, Ear Muff) Psg - - -
f. Pelindung Pernafasan & Mulut (Masker) Bh - 5,000.00 -
g. Sarung Tangan (Safety Gloves) Psg - 20,000.00 -
h. Sepatu Keselamatan (Safety Shoes) Psg 5.00 100,000.00 500,000.00
i. Penunjang Seluruh Tubuh (Full Body Harnes) Psg - - -
j. Jaket Pelampung (Life Vest) Bh - - -
k. Rompi Keselamatan (Safety Vest) Bh - - -
l. Celemek (Apron/Coveralls) Bh - - -
m. Pelindung Jatuh (Fall Arester) Bh - - -
Sub Total Alat Pelindung Diri 1,000,000.00
5 Asuransi dan Perizinan
a. BPJS Ketenagakerjaan & Kesehatan Ls 1.00 378,000.00 378,000.00
b. Surat Ijin Kelaikan Alat Alat/Kend. - - -
c. Surat Ijin Operator Lb/Alat - - -
Surat Ijin Pengesahan Pembina Keselamatan &
-
d. Kesehatan Kerja Ls - -
Sub Total Asuransi dan Perizinan 378,000.00
6 Personil K3
a. Ahli K3 OB - - -
b. Petugas K3 OB 1.00 500,000.00 500,000.00
c. Petugas Tanggap Darurat OB - - -
d. Petugas P3K OB - - -
Asisten Petugas K3/Safety Man/Pengatur Lalu
- - -
e. Lintas (Flag Man) OB
f. Petugas Medis OB - - -
Sub Total Personel K3 500,000.00
7 Fasilitas Sarana Kesehatan
Peralatan P3K (Kotak P3K, Tandu, Tabung
a. Ls 1.00 250,000.00 250,000.00
Oksigen,
Ruang Obat
P3K Luka, Tidur
(Tempat Perban dll) Stetoskop,
Pasien
b. Ls - - -
Timbangan Berat badan Tensi Meter)
c. Peralatan Pengasapan (Fogging) Bh - - -
d. Obat Pengasapan Kali - - -
Sub Total Fasilitas Kesehatan 250,000.00
8 Rambu-rambu
a. Rambu Petunjuk Bh 1.00 50,000.00 50,000.00
b. Rambu Larangan Bh 1.00 50,000.00 50,000.00
c. Rambu Peringatan Bh 1.00 50,000.00 50,000.00
d. Rambu Kewajiban Bh 1.00 50,000.00 50,000.00
e. Rambu Informasi Bh 1.00 50,000.00 50,000.00
f. Rambu Pekerjaan Sementara Bh - - -
g. Tongkat Pengatur Lalu Lintas(Warning Light Stick) Bh - - -
h. Kerucut Lalu Lintas (Traffic Cone) Bh - - -
i. Lampu Putar (Rotary Lamp) Bh - - -
j. Lampu Selang Lalu Lintas Ls - - -
Sub Total Rambu-rambu 250,000.00
9 Lain Lain Terkait Pengendalian Risiko K3
a. Alat Pemadam Api Ringan (APAR) Bh - - -
b. Sirine Bh - - -
c. Bendera K3 Bh 1.00 100,000.00 100,000.00
d. Jalur Evakuasi (Escape Route) Ls - - -
e. Lampu Darurat (Emergency Lamp) Bh - - -
f. Program Inspeksi & Audit Internal Org - - -
g. Pelaporan & Penyelidikan Insiden Ls - - -
Sub Total Kegiatan dan peralatan terkait dengan pengendalian Risiko Keselamatan Konstruksi 100,000.00
J u m l a h (1+2+3+4+5+6+7+8+9) 3,078,000.00
UPAH KERJA DAN HARGA BAHAN

KEGIATAN : PEMBANGUNAN PAGAR SEKOLAH TAHUN ANGGARAN 2022


PEKERJAAN : SD SMPN Satu Atap 2 Konawe Selatan
KAB./KOTA : KONAWE SELATAN
PROVINSI : SULAWESI TENGGARA

MEREK/
NO. N A M A / JENIS BARANG SATUAN HARGA
TYPE

I. HARGA DASAR SATUAN UPAH


1 - Pekerja OH Rp 91,000.00
2 - Tukang Kayu OH Rp 120,000.00
3 - Tukang Batu OH Rp 128,000.00
4 - Tukang Besi OH Rp 128,000.00
5 - Tukang Las OH Rp 128,000.00
6 - Tukang Cat OH Rp 111,500.00
7 - Tukang Listrik OH Rp 111,500.00
8 - Kepala Tukang OH Rp 130,000.00
9 - Mandor OH Rp 106,000.00

II. BAHAN TANAH, PASIR DAN BATU


1 - Pasir Urug M3 Rp 121,000.00
2 - Pasir Pasang M3 Rp 214,500.00
3 - Pasir Beton M3 Rp 214,500.00
4 - Pasir Beton, Kg Rp 153.21
5 - Kerikil Beton M3 Rp 440,000.00
6 - Batu Pecah/Suplit 2/3 M3 Rp 440,000.00
7 - Batu Pecah/Suplit 2/3, Kg Rp 325.93
8 - Batu Gunung M3 Rp 286,000.00
9 - Batu bata Bh Rp 880.00

III. BAHAN SEMEN


1 - Portland Cement Kg Rp 1,870.00
2 - Semen Warna Kg Rp 1,870.00

IV. BAHAN KAYU


1 Balok Kayu Kls II M3 Rp 2,750,000.00
2 - Balok Kayu Kelas III M3 Rp 2,200,000.00
3 - Balok Kayu Bekisting Kelas IV M3 Rp 1,265,000.00
4 - Dolken Ø (8–10) cm, panjang 4 m Btg Rp 19,800.00
5 - Kasau 5/7 kayu kls II M3 Rp 2,750,000.00
6 - Papan Kayu Kls II M3 Rp 2,750,000.00
7 - Papan Kayu Kelas III M3 Rp 2,200,000.00
8 - Papan Bekisting Kelas IV M3 Rp 1,265,000.00
9 - Multipleks 9 mm Lbr Rp 148,500.00
10 - Tripleks 3mm Lbr Rp 82,500.00
MEREK/
NO. N A M A / JENIS BARANG SATUAN HARGA
TYPE

V. - BAHAN BESI DAN ALUMINIUM


1 - Besi Beton Kg Rp 19,800.00
2 - Kawat beton Kg Rp 33,000.00
3 - Kawat las listrik Kg Rp 110,000.00
4 - Paku Biasa 5 - 12 cm Kg Rp 27,500.00
5 - Besi Siku m1 Rp 27,500.00
6 - Besi Hollow Galvanis 40x40 mm Tebal 1,4 mm M1 Rp 40,333.33
7 - Besi Hollow Galvanis 20x40 mm Tebal 1,4 mm M1 Rp 30,250.00

VI. - BAHAN KACA PENGGUNCI/PENGGANTUNG


1 - Gembok Bh Rp 66,000.00
2 - Engsel Bubut Bh Rp 82,500.00

VII. - BAHAN CAT/FINISHING


1 - Cat Tembok Kg Rp 38,500.00
2 - Cat Anti Lumut No Drop Kg Rp 55,000.00
3 - Plamir Tembok Big Lion (5 Kg) Kg Rp 20,900.00
4 - Kuas Bh Rp 33,000.00
5 - Kuas Roll Bh Rp 55,000.00
6 - Cat Besi Kg Rp 93,500.00

VIII. - BAHAN DAN ALAT LAINNYA


1 - Air Ltr Rp 55.00
2 - Solar Liter Rp 6,800.00
3 - Minyak Pelumas Liter Rp 16,500.00
4 - Sewa Mesin las Jam Rp 82,500.00
5 - Topi Pelindung (Safety Helmet) Bh Rp 110,000.00
6 - Sarung Tangan (Safety Gloves) Psg Rp 22,000.00

Kendari, 14 Agustus 2023

Dibuat Oleh :
#NAME?

Rp -
#NAME?
UPAH KERJA DAN HARGA BAHAN

Pekerjaan : Pembangunan Pagar SD SMPN Satu Atap 2 Konawe Selatan


Lokasi : SD SMPN Satu Atap 2 Konawe Selatan
Tahun Anggaran : 2022

NO. N A M A / JENIS BARANG SATUAN HARGA

I. HARGA DASAR SATUAN UPAH


1 - Pekerja OH 90,800.00
2 - Tukang Kayu OH 120,000.00
3 - Tukang Batu OH 128,000.00
4 - Tukang Besi OH 128,000.00
5 - Tukang Cat OH 111,500.00
6 - Kepala Tukang OH 130,000.00
7 - Mandor OH 106,000.00

II. BAHAN TANAH, PASIR DAN BATU


1 - Pasir Urug M3 121,000.00
2 - Pasir Pasang M3 214,500.00
3 - Pasir Beton M3 214,500.00
4 - Pasir Beton, Kg 153.21
5 - Kerikil Beton M3 440,000.00
6 - Batu Pecah/Suplit 2/3 M3 440,000.00
7 - Batu Pecah/Suplit 2/3, Kg 325.93
8 - Batu Gunung M3 286,000.00
9 - Batu bata Bh 880.00

III. BAHAN SEMEN


1 - Portland Cement Kg 1,870.00

IV. BAHAN KAYU


1 Balok Kayu Kls II M3 2,750,000.00
2 - Balok Kayu Kelas III M3 2,200,000.00
3 - Dolken Ø (8–10) cm, panjang 4 m Btg 19,800.00
4 - Papan Bekisting Kelas IV M3 1,265,000.00
5 - Multipleks 9 mm Lbr 148,500.00

V. - BAHAN BESI DAN ALUMINIUM


1 - Besi Beton Kg 19,800.00
2 - Kawat beton Kg 33,000.00
3 - Kawat las listrik Kg 110,000.00
4 - Paku Biasa 5 - 12 cm Kg 27,500.00
5 - Besi Hollow Galvanis 40x40 mm Tebal 1,4 mm M1 45,833.33
6 - Besi Hollow Galvanis 20x40 mm Tebal 1,4 mm M1 41,800.00
NO. N A M A / JENIS BARANG SATUAN HARGA

VI. - BAHAN CAT/FINISHING


1 - Cat Tembok Kg 38,500.00
2 - Cat Anti Lumut No Drop Kg 55,000.00
3 - Plamir Tembok Big Lion (5 Kg) Kg 20,900.00
4 - Cat Besi Kg 93,500.00

VII. - BAHAN DAN ALAT LAINNYA


1 - Air Ltr 60.00
2 - Solar Liter 6,800.00
3 - Minyak Pelumas Liter 16,500.00
4 - Sewa Mesin las Jam 82,500.00

Kendari, 14 Agustus 2023

Dibuat Oleh :
CV. BUMI SULTRA

FAJAR NOVIANTARTO
Direktur
Rekapitulasi Monthly Certificate (MC) : 0 (NOL)
Periode Bulan : NOVEMBER 2023
KONTRAKTOR PEMERINTAH KABUPATEN KONAWE SELATAN
NO. KONTRAK : 602/27/SPK/JLN/BM-02/DPUTR/2023
DINAS PEKERJAAN UMUM DAN TATA RUANG
CV. PUTRA PRIMA PERKASA NILAI KONTRAK : Rp. 199.800.000,-
JL. KOMPLEKS PERKANTORAN NO. 1 ANDOLO LOKASI PROYEK : Desa Sindang Kasih Kec. Ranomeeto Barat
KONSULTAN SUPERVISI PERIODE : NOVEMBER 2023
PEKERJAAN : BOBOT S/D BULAN INI : 0.00 %
CV. ALPHA ENGINEERING
Pembangunan Jalan Rabat Beton Dusun IV Desa Sindang Kasih Kec. Ranomeeto
CONSULTANT Barat
TARGET KONTRAK KEMAJUAN PEKERJAAN
MC BULAN LALU BULAN INI SAMPAI BULAN INI
BOBOT PEKERJAAN BOBOT PEKERJAAN BOBOT PEKERJAAN
No URAIAN PEKERJAAN JUMLAH HARGA BOBOT
JUMLAH HARGA JUMLAH HARGA JUMLAH HARGA
YANG YANG YANG
TERTIMBANG TERTIMBANG TERTIMBANG
DICAPAI DICAPAI DICAPAI
Rp. % % % Rp. % % Rp. % % Rp.
1 2 3 4 5 6 7 8 9 10 11 12 13

I DIVISI 1. UMUM Rp 23,510,000.00 13.07 - - - - - - - - -

III DIVISI 3. PEKERJAAN TANAH DAN GEOSINTETIK Rp 3,089,525.60 1.72 - - - - - - - - -

IV DIVISI 7. STRUKTUR Rp 153,313,501.00 85.22 - - - - - - - - -

REAL COST Rp 179,913,026.60 100.00


PPN 11 % Rp 19,790,432.93 - - - - - - - - - -
TOTAL COST Rp 199,703,459.53 - - - - - - - - - -
GRAND TOTAL (DIBULATKAN) Rp 199,700,000.00 -

Andoolo, November 2023


Mengetahui / Menyetujui Pejabat Pelaksana Teknis Kegiatan (PPTK) Konsultan Supervisi Kontrakor Pelaksana ;
Pejabat Pembuat Komitmen (PPK) Dinas Pekerjaan Umum dan Tata Ruang CV. ALPHA ENGINEERING CONSULTANT CV. PUTRA PRIMA PERKASA

AMSARULA,ST.,M.PW
SAPRIADI MUSTAMIR, ST BASUKI RAHMAT, A.Md. EKO SUSILO HARTONO
Nip. 19800308200604 1 010 Nip. 19790407 200604 1 010 Direktur Direktur
LAPORAN PROGRESS PEKERJAAN
Monthly Certificate (MC) : 0 (NOL)
Periode Bulan : NOVEMBER 2023
KONTRAKTOR PEMERINTAH KABUPATEN KONAWE SELATAN
NO. KONTRAK : 602/27/SPK/JLN/BM-02/DPUTR/2023
CV. PUTRA PRIMA PERKASA DINAS PEKERJAAN UMUM DAN TATA RUANG NILAI KONTRAK : Rp. 199.800.000,-
JL. KOMPLEKS PERKANTORAN NO. 1 ANDOLO LOKASI PROYEK : Desa Sindang Kasih Kec. Ranomeeto Barat
KONSULTAN SUPERVISI PERIODE BULAN : NOVEMBER 2023
PEKERJAAN : BOBOT S/D BULAN INI : 0.00 %
CV. ALPHA ENGINEERING
Pembangunan Jalan Rabat Beton Dusun IV Desa Sindang Kasih Kec. Ranomeeto
CONSULTANT
Barat
KEMAJUAN PEKERJAAN
TARGET KONTRAK
BULAN LALU BULAN INI SAMPAI BULAN INI
BOBOT
NO. URAIAN PEKERJAAN SATUAN BOBOT BOBOT BOBOT BOBOT BOBOT BOBOT
HARGA JUMLAH HARGA VOLUME VOLUME VOLUME
VOLUME DICAPAI TERTIMBANG DICAPAI TERTIMBANG DICAPAI TERTIMBANG
DICAPAI DICAPAI DICAPAI
Rp. Rp. % % % % % % %
a b c d e f g h i j k l m n o p
I DIVISI 1. UMUM
1 Mobilisasi LS 1.00 18,160,000.00 Rp 18,160,000.00 10.09 - - - - - - - - -
2 Manajemen dan Keselamatan Lalu Lintas LS 1.00 2,450,000.00 Rp 2,450,000.00 1.36 - - - - - - - - -
3 Keselamatan dan Kesehatan Kerja LS 1.00 2,900,000.00 Rp 2,900,000.00 1.61 - - - - - - - - -
JUMLAH I DIVISI 1. UMUM 23,510,000.00
III DIVISI 3. PEKERJAAN TANAH DAN GEOSINTETIK -
Penyiapan Badan Jalan M2 534.52 5,780.00 Rp 3,089,525.60 1.72 - - - - - - - - -
JUMLAH III DIVISI 3. PEKERJAAN TANAH DAN GEOSINTETIK 3,089,525.60 -
IV DIVISI 7. STRUKTUR - - - - - - - - - -
Beton strukur, fc’20 MPa M3 80.18 1,602,350.00 Rp 128,476,423.00 71.41 - - - - - - - - -
Baja Tulangan Polos-BjTP 280 Kg 1,166.06 21,300.00 Rp 24,837,078.00 13.81 - - - - - - - - -
JUMLAH IV DIVISI 7. STRUKTUR 153,313,501.00 #REF!
SUB-TOTAL 179,913,026.60 100.00

Mengetahui / Menyetujui Andoolo, November 2023


Pejabat Pembuat Komitmen (PPK) Pejabat Pelaksana Teknis Kegiatan (PPTK) Koordinator Koordinator Direksi Konsultan Supervisi Kontrakor Pelaksana ;
Dinas Pekerjaan Umum dan Tata Ruang Dinas Pekerjaan Umum dan Tata Ruang Dinas Pekerjaan Umum dan Tata Ruang CV. ALPHA ENGINEERING CONSULTANT CV. PUTRA PRIMA PERKASA

SAPRIADI MUSTAMIR, ST WAHYUDDIN MUHAMMAD IQBAL, ST. BASUKI RAHMAT, A.Md. EKO SUSILO HARTONO
Nip. 19800308200604 1 010 Nip. 19790407 200604 1 010 Nip. 19760806 201101 1 008 Direktur Direktur
RENCANA PENGGUNAAN UANG MUKA 50%

Pekerjaan : Pembangunan Jalan Rabat Beton Dusun IV Desa Sindang Kasih Kec. Ranomeeto Barat
Lokasi : Lrg Anaway Kel. Ranomeeto Kec. Ranomeeto
Sumber Dana : APBD Kabupaten Konawe Selatan
Tahun Anggaran : 2023

NO. URAIAN PEKERJAAN SAT. VOL. HARGA SATUAN JUMLAH HARGA

I DIVISI 1. UMUM
1 Mobilisasi LS 1.00 9,550,000.00 Rp 9,550,000.00
2 Penyiapan Dokumen Penerapan SMKK LS 1.00
3 Sosilaisasi, Promosi dan Pelatihan LS 1.00 200,000.00 Rp 200,000.00
4 Alat Pelindung Kerja dan Alat Pelindung Diri LS 1.00 1,350,000.00 Rp 1,350,000.00
5 Personel Keselamatan Konstruksi LS 1.00 2,950,000.00 Rp 2,950,000.00
6 Fasilitas sarana, prasarana, dan alat kesehatan LS 1.00 500,000.00 Rp 500,000.00
7 Rambu dan Perlengkapan Lalu Lintas yang diperlukan atau Mana LS 1.00 1,450,000.00 Rp 1,450,000.00
8 Kegiatan dan Peralatan Terkait Pengendalian Resiko Keselamata LS 1.00 200,000.00 Rp 200,000.00
JUMLAH 16,200,000.00
II PENGADAAN MATERIAL LOKAL
1 Pasir M3 40.00 143,000.00 Rp 5,720,000.00
2 Suplit M3 20.00 245,000.00 Rp 4,900,000.00
3 Papan Bekisting M3 6.00 1,500,000.00 Rp 9,000,000.00
4 Dolken BATANG 20.00 19,800.00 Rp 396,000.00
JUMLAH 20,016,000.00
III PENGADAAN MATERIAL TOKO
1 Semen ZAK 185.00 93,400.00 Rp 17,279,000.00
2 Besi 8 BATANG 140.00 95,000.00 Rp 13,300,000.00
3 Kawat Bendrat ROL 6.00 660,000.00 Rp 3,960,000.00
4 Paku Campur KG 22.00 27,500.00 Rp 605,000.00
JUMLAH 35,144,000.00
VI UPAH KERJA
1 Panjar Upah Kerja Borongan 1.00 18,645,000.00 Rp 18,645,000.00
JUMLAH 18,645,000.00
SUB TOTAL 90,005,000.00
PPN 11% 9,900,550.00
GRAND TOTAL 99,905,550.00
DIBULATKAN 99,900,000.00
Andoolo, November 2023
Diperiksa Oleh Dibuat Oleh
Konsultan Supervisi Kontrakor Pelaksana ;
CV. ALPHA ENGINEERING CONSULTANT CV. PUTRA PRIMA PERKASA

BASUKI RAHMAT, A.Md. EKO SUSILO HARTONO


Direktur Direktur

Mengetahui / Menyetujui

Koordinator Direksi Pejabat Pelaksana Teknis Kegiatan (PPTK)


Dinas Pekerjaan Umum dan Tata Ruang Dinas Pekerjaan Umum dan Tata Ruang

WAHYUDDIN MUHAMMAD IQBAL, ST. SAPRIADI MUSTAMIR, ST


Nip. 19760806 201101 1 008 Nip. 19790407 200604 1 010

Pejabat Pembuat Komitmen (PPK)


Dinas Pekerjaan Umum dan Tata Ruang

AMSARULA,ST.,M.PW
Nip. 19800308200604 1 010
0

Nomor : 017/CV.PPP/RPUM/XI/2023
Lampiran : Rincian Penggunaan Uang Muka
Perihal : Permohonan Uang Muka
Kepada Yth.

Pejabat Pembuat Komitmen (PPK)


Dinas Pekerjaan Umum dan Tata Ruang
Di,
Andoolo.

Sehubungan dengan Perjanjian Kontrak Nomor : 602/27/SPK/JLN/BM-02/DPUTR/2023 tanggal 02 november 2023


Perihal Pembangunan Jalan Rabat Beton Dusun IV Desa Sindang Kasih Kec. Ranomeeto Barat pada Kantor
Dinas Pekerjaan Umum dan Tata Ruang Kabupaten Konawe Selatan dengan nilai Kontrak Rp. 199.800.000,-( SERATUS
SEMBILAN PULUH SEMBILAN JUTA DELAPAN RATUS RIBU RUPIAH)

Maka dengan ini kami mengajukan permohonan kiranya perusahaan kami dapat diberikan uang muka sebesar 50% dari
Nilai Kontrak atau dengan perhitungan sebagai berikut :

50% X Rp. 199.800.000,- = Rp. 99.900.000.- dan Dibulatkan = Rp. 99.900.000.-


Terbilang = SERATUS SEMBILAN PULUH SEMBILAN JUTA DELAPAN RATUS RIBU RUPIAH

Bersama dengan ini kami lampirkan :


1. Rincian penggunaan uang muka
2. Foto nol lokasi pekerjaan
3. MC Nol
4. Surat Jaminan Uang Muka

Demikian permohonan ini kami ajukan, atas perkenaanya diucapkan terima kasih.

Hormat kami

CV. PUTRA PRIMA PERKASA

EKO SUSILO HARTONO


Direktur
UPAH KERJA DAN HARGA BAHAN

KEGIATAN : PEMBANGUNAN PAGAR SEKOLAH TAHUN ANGGARAN 2022


PEKERJAAN :
KAB./KOTA : KONAWE SELATAN
PROVINSI : SULAWESI TENGGARA

HARGA HARGA HARGA HARGA HARGA


MEREK/
NO. N A M A / JENIS BARANG SATUAN HARGA LAPANGAN TOKO REMAJA TOKO BANGUN UPGRADE SATUAN
TYPE
KONTRA LAMA ANDUONOHU PERKASA BARUGA 0.1 EE

I. HARGA DASAR SATUAN UPAH


1 - Pekerja OH Rp 91,000.00 91,000.00 91,000.00
2 - Tukang Kayu OH Rp 120,000.00 120,000.00 120,000.00
3 - Tukang Batu OH Rp 128,000.00 128,000.00 128,000.00
4 - Tukang Besi OH Rp 128,000.00 128,000.00 128,000.00
5 - Tukang Las OH Rp 128,000.00 128,000.00 128,000.00
6 - Tukang Cat OH Rp 111,500.00 111,500.00 111,500.00
7 - Tukang Listrik OH Rp 111,500.00 111,500.00 111,500.00
8 - Kepala Tukang OH Rp 130,000.00 130,000.00 130,000.00
9 - Mandor OH Rp 106,000.00 106,000.00 106,000.00

II. BAHAN TANAH, PASIR DAN BATU


1 - Pasir Urug M3 Rp 121,000.00 110,000.00 11000 121,000.00
2 - Pasir Pasang M3 Rp 214,500.00 195,000.00 19500 214,500.00
3 - Pasir Beton M3 Rp 214,500.00 195,000.00 19500 214,500.00
4 - Pasir Beton, Kg Rp 153.21 139.29 13.9285714285714 153.21
5 - Kerikil Beton M3 Rp 440,000.00 400,000.00 40000 440,000.00
6 - Batu Pecah/Suplit 2/3 M3 Rp 440,000.00 400,000.00 40000 440,000.00
7 - Batu Pecah/Suplit 2/3, Kg Rp 325.93 296.30 29.6296296296296 325.93
8 - Batu Gunung M3 Rp 286,000.00 260,000.00 26000 286,000.00
9 - Batu bata Bh Rp 880.00 800.00 80 880.00
HARGA HARGA HARGA HARGA HARGA
MEREK/
NO. N A M A / JENIS BARANG SATUAN HARGA LAPANGAN TOKO REMAJA TOKO BANGUN UPGRADE SATUAN
TYPE
KONTRA LAMA ANDUONOHU PERKASA BARUGA 0.1 EE
III. BAHAN SEMEN
1 - Portland Cement Kg Rp 1,870.00 1,700.00 1740 1680 170 1,870.00
2 - Semen Warna Kg Rp 1,870.00 1,700.00 1740 170 1,870.00

IV. BAHAN KAYU


1 Balok Kayu Kls II M3 Rp 2,750,000.00 2,500,000.00 250000 2,750,000.00
2 - Balok Kayu Kelas III M3 Rp 2,200,000.00 2,000,000.00 200000 2,200,000.00
3 - Balok Kayu Bekisting Kelas IV M3 Rp 1,265,000.00 1,150,000.00 115000 1,265,000.00
4 - Dolken Ø (8–10) cm, panjang 4 m Btg Rp 19,800.00 18,000.00 18,000 1,800 19,800.00
5 - Kasau 5/7 kayu kls II M3 Rp 2,750,000.00 2,500,000.00 250,000 2,750,000.00
6 - Papan Kayu Kls II M3 Rp 2,750,000.00 2,500,000.00 250,000 2,750,000.00
7 - Papan Kayu Kelas III M3 Rp 2,200,000.00 2,000,000.00 200,000 2,200,000.00
8 - Papan Bekisting Kelas IV M3 Rp 1,265,000.00 1,150,000.00 115,000 1,265,000.00
9 - Multipleks 9 mm Lbr Rp 148,500.00 135,000.00 13,500 148,500.00
10 - Tripleks 3mm Lbr Rp 82,500.00 75,000.00 48,000 55,000 7,500 82,500.00

V. - BAHAN BESI DAN ALUMINIUM


1 - Besi Beton Kg Rp 19,800.00 18,000.00 1,800 19,800.00
2 - Kawat beton Kg Rp 33,000.00 30,000.00 30,000 25,000 3,000 33,000.00
3 - Kawat las listrik Kg Rp 110,000.00 100,000.00 100,000 10,000 110,000.00
4 - Paku Biasa 5 - 12 cm Kg Rp 27,500.00 25,000.00 20,000 2,500 27,500.00
5 - Besi Siku m1 Rp 27,500.00 25,000.00 2,500 27,500.00
6 - Besi Hollow 20x40 mm Tebal 1,8 mm M1 Rp 45,833.33 41,666.67 250,000 4,167 45,833.33
7 - Besi Hollow 40x40 mm M1 Rp 41,800.00 38,000.00 3,800 41,800.00

VI. - BAHAN KACA PENGGUNCI/PENGGANTUNG


1 - Gembok Bh Rp 66,000.00 60,000.00 60000 6,000 66,000.00
2 - Engsel Bubut Bh Rp 82,500.00 75,000.00 7,500 82,500.00
HARGA HARGA HARGA HARGA HARGA
MEREK/
NO. N A M A / JENIS BARANG SATUAN HARGA LAPANGAN TOKO REMAJA TOKO BANGUN UPGRADE SATUAN
TYPE
KONTRA LAMA ANDUONOHU PERKASA BARUGA 0.1 EE
VII. - BAHAN CAT/FINISHING
1 - Cat Tembok Kg Rp 38,500.00 35,000.00 3,500 38,500.00
2 - Cat Anti Lumut No Drop Kg Rp 55,000.00 50,000.00 48,000 50,000 5,000 55,000.00
3 - Plamir Tembok Big Lion (5 Kg) Kg Rp 20,900.00 19,000.00 19,000 18,000 1,900 20,900.00
4 - Kuas Bh Rp 33,000.00 30,000.00 30,000 20,000 3,000 33,000.00
5 - Kuas Roll Bh Rp 55,000.00 50,000.00 50,000 40,000 5,000 55,000.00
6 - Cat Besi Kg Rp 93,500.00 85,000.00 85,000 80,000 8,500 93,500.00

VIII. - BAHAN DAN ALAT LAINNYA


1 - Air Ltr Rp 55.00 50.00 5 55.00
2 - Solar Liter Rp 6,800.00 6,800.00 680 7,480.00
3 - Minyak Pelumas Liter Rp 16,500.00 15,000.00 1500 16,500.00
4 - Sewa Mesin las Jam Rp 82,500.00 75,000.00 7500 82,500.00
5 - Topi Pelindung (Safety Helmet) Bh Rp 110,000.00 100,000.00 100000 10000 110,000.00
6 - Sarung Tangan (Safety Gloves) Psg Rp 22,000.00 20,000.00 20000 2000 22,000.00
DAFTAR HARGA SATUAN UPAH KERJA DAN BAHAN
Kegiatan : PENGADAAN PRASARANA DAN PENDUKUNG FASILITAS PELAYANAN KESEHATAN
Pekerjaan : PEMBANGUNAN PRASARANA AIR BERSIH PUSKESMAS
Lokasi : PUSKESMAS LAMBUYA KEC. LAMBUYA KAB. KONAWE
Sumber Dana : DAK BIDANG KESEHATAN
Tahun Anggaran : 2022

UPAH KERJA
NO JENIS JABATAN
HARGA SATUAN HARGA SATUAN
1 Pekerja 100,000 OH 14,286.00 Jam
2 Tukang Kayu 120,000 OH 17,143.00 Jam
3 Tukang Batu 120,000 OH 17,143.00 Jam
4 Tukang Besi 120,000 OH 17,143.00 Jam
5 Tukang Las 120,000 OH 17,143.00 Jam
6 Tukang Cat 120,000 OH 17,143.00 Jam
7 Tukang Pipa 120,000 OH 17,143.00 Jam
8 Kepala Tukang 125,000 OH 17,858.00 Jam
9 Mandor 125,000 OH 17,858.00 Jam

HARGA BAHAN
NO JENIS BAHAN
HARGA SATUAN HARGA SATUAN
A Bahan Pasir, Batu dan Timbunan
1 Timbunan Biasa (didatangkan) 49,000 M3
2 Pasir Urug 90,000 M3
3 Pasir Pasangan 180,000 M3
4 Pasir Beton 180,000 M3
Berat isi Beton = 1400 Kg/M3 128.57 Kg
5 Batu Pecah/Suplit 1/2 270,000 M3
Berat isi Batu Pecah = 1800 Kg/M3 150.00 Kg
6 Batu Gunung 240,000 M3
7 Batu Bata 800 Bh
B Bahan Semen
1 Portland Cemen ( PC ) 1,600 Kg 80,000 Zak
C Bahan Kayu
1 Balok Kayu Kalapi 4,600,000 M3
2 Balok Kaso 5/7 Kls II Isi 1 M3 Balok Kaso 5/7 = 72 Batang 1,400,000 M3 20,000 Btg
3 Papan Kayu Kls I (Jati) 4,600,000 M3
4 Balok/Papan bekisting Kayu Kelas III 1,300,000 M3
5 List Plafond Kayu Profil 4,500 M1 18,000 Btg
6 List Plank Kalsiplank/Woodplank 20 Cm x 8 mm 25,000 M1
7 Kalsiboard 240x120x0,3 cm 75,000 Lbr
D Bahan Keramik
1 Tegel Keramik 60 x 60 Cm Warna, anti sliip 48,500 Bh
E Bahan Penutup Atap
1 Atap Metal Zincalume (Spandek) Tebal = 0,3 mm 52,000 Lembar
2 Nok Bubungan Atap Metal Zincalume (Spandek) lebar 50 cm 22,500 M1
3 Paku Sakura Roof/Spandek 30,000 Kg
F Bahan Besi
1 Besi Beton 18,000 Kg
2 Kawat Bindrat 20,000 Kg
3 Paku Campur 20,000 Kg
4 Paku sekrup/Baut Srew Steel /Perlengkapan Isi dalam 1 Kg = 800 pcs 560,000 Kg 700 Bh
700 bh
5 Besi Hollow Hitam 40x40x2 mm 25,000 M1
6 Besi Hollow Hitam 40x60x2 mm 35,000 M1
7 Besi Hollow Galvalume (Zinc-Aluminium) 40/40/2 9,000 M1 36,000 Batang
8 Main Truss C.75-75 25,000 M1
9 Roof Bottom/Reng R.33 - 0.45 16,000 M1
UPAH KERJA
NO JENIS JABATAN
HARGA SATUAN HARGA SATUAN
10 Self Drilling Screw dia 6 x 20 mm( Truss Screw) 350 Bh
11 Self Drilling Screw dia 4 x 16 mm( Roof Bottom Screw) 250 Bh
12 Dynabolt 2,500 Bh

G Bahan Pengunci/Penggantung dan Kaca


1 Kunci Tanam 2 x putar Biasa 125,000 Bh
2 Engsel Pintu Kayu 21,000 Bh
3 Kunci slot/Grendel 4,000 Bh
4 Kaca Bening 5 mm 102,000 M2

H Bahan Cat/Finishing
1 Cat Meni Besi 28,000 Kg
2 Kuas Rol 30 cm 30,000 Bh
3 Kuas Biasa 6,500 Bh
4 Cat Vernis Kayu 60,000 Ltr
5 Amplas Kayu 3,000 Lbr
6 Dempul Kayu 25,000 Kg
7 Cat Dasar Tembok/Plafond 30,000 Kg
8 Cat Penutup Tembok/Plafond 30,000 Kg
9 Cat Tembok/Water Proof/Anti Bocor/Anti Lumut setara No Drop 91,000 Kg
10 Lem Kayu Merk Fox 30,000 Kg

I Bahan Sanitair dan Plumbing


1 Pipa PVC AW Dia. 3/4", t = 1,2 mm 9,500 M1 38,000 Batang
2 Water Torn Viber (Tandon Air) Kapasitas 2200 L 3,500,000 Bh
3 Tangki Filter TFR 10x54 + Silica 2,800,000 Set
4 Tangki Filter TFR 10x54+ Mangasend 3,200,000 Set
5 Tangki Filter TFR 10x54 + Carbon 3,250,000 Set
6 Tangki Filter TFR 10x54 + Resin Cation 3,700,000 Set
7 Pengadaan dan pemasangan Catridge Filter 0,1 250,000 Bh
8 Water Torn Stainless (Pakai Kaki) kapasitas 1100 L 4,500,000 Bh
9 Mesin Air Jet Pump, kap.250 watt 1,700,000 Unit
10 Mesin Pompa Stainless, kap.350 watt 2,100,000 Unit
11 Mesin RO 4000 GPD Kapasitas 15.200 L, 1750 Watt 30,000,000 Set
12 Panel Box + Lengkap Accessories 1,500,000 Set
13 Ultra Violet 12gpm 2,500,000 Bh
14 Rangka Stainless dudukan filter 2,500,000 Ls
15 Test & Uji Fungsi Alat 1,500,000 Ls

J Bahan Instalasi Listrik


1 Lampu LED 19 Watt Philips 130,000 Bh
2 Pitting Lampu 20,000 Bh
3 Saklar Ganda Ex.Philips 25,000 Bh
4 Stop kontak Ex.Philips 12,000 Bh
5 Kabel NYM 3 x 2,5 mm2 15,000 m1
6 Isolasi Besar 10,000 Bh
7 Klem Kabel No. 18 600 Bh 30,000 Dos
8 Inbow Dos 5,000 Bh
9 Las Dop 3,500 Bh
10 T-Dox Ex. Dexta 5,000 Bh
11 Pipa Listrik PVC 5/8 2,500 M1 10,000 Btg
12 Penyambungan Daya 3500 VA + SLO + Stroom Awal + Biaya PPJ 4,000,000 Ttk

K Bahan Lainnya
1 Air 50 Liter
2 Bahan Bakar Solar (Industri) 10,500 Liter
3 Minyak Pelumas 35,000 Liter
4 Kawat Las 15,000 Kg

Unaaha, 2022
DIBUAT OLEH
KONSULTAN PERENCANA
CV. DINDING JELAJAH
UPAH KERJA
NO JENIS JABATAN
HARGA SATUAN HARGA SATUAN
dr. H. Abd. RAZAK, S.Ked., M.Kes M. FAHRI USMAN, S. Ars.
19620407 198103 2 002 Direktur
Back Up Data
PEKERJAAN : REHABILITASI GEDUNG BENGKEL INSTALASI PSRS
RUMAH SAKIT JIWA
TAHUN ANGGARAN : 2019
LOKASI : KOTA KENDARI PROVINSI SULAWESI TENGGARA

GAMBAR / SKET PERHITUNGAN

I. PEKERJAAN PERSIAPAN
1. Papan Nama Proyek
Volume = 1.00 Ls

2. Pek. Pembongkaran
Volume = 1.00 Ls

3. Pemasangan Pengukuran dan Bouwplank


Volume = 18.00 M1

4. Pemasangan Pagar Pengaman Sementara


Volume = 82.00 M1

5. Pembuatan Direksi Keet, Gudang/barak Kerja (Sewa)


Volume = 1.00 Ls

6. Listrik & Penerangan Kerja


Volume = 1.00 Ls

7. Air Kerja & Bak Penampung


Volume = 1.00 Ls

8. Administrasi (Dokumentasi, P3K & Laporan Proyek)


Volume = 1.00 Ls

IX. PEKERJAAN BANGUNAN RUMAH ALAT


A. Pekerjaan Pondasi dan Tanah
1. Pek Galian Tanah Pondasi
Volume = P x L x T
Bangunan = 14.00 x 0.65 x 0.60 = 5.46 M3
Teras = 4.50 x 0.30 x 0.20 = 0.27 M3
Rg. Tandon = 6.10 x 0.55 x 0.60 = 2.01 M3
Jumlah = 7.74 M3

2. Pek Pas. Batu Kosong


Volume = P x L x T
Bangunan = 14.00 x 0.65 x 0.20 = 1.82 M3
Rg. Tandon = 6.10 x 0.55 x 0.20 = 0.67 M3
Jumlah = 2.49 M3

3. Pas. Pondasi Batu Gunung 1Pc : 5Psr

Volume = LA + LB x T x P
2
Bangunan = 0.2 + 0.45 x 0.6 x 14.00 = 2.71 M3
2

Bangunan Tandon = 0.25 + 0.45 x 0.8 x 6.10 = 1.70 M3


2

Volume = P x L x T
Teras = 4.50 x 0.20 x 0.60 = 0.54 M3
Tangga = 2.90 x 0.40 x 0.20 = 0.23 M3
Jumlah = 5.18 M3

B. Pekerjaan Beton
1. Pek Sloof 15/20
- Cor Beton
Volume = P x L x T
= 14.00 x 0.15 x 0.20 = 0.42 M3

- Besi Beton
Dik : Panjang Sloof = 14.00 m'
Jumlah Titik Besi (Pot. Sloof) Ø 12 = 4.00 Titik

Panjang Besi yang dibutuhkan Besi Ø 12 + Bengkokan


= 14.00 x 4.00 = 56.00 m'

Jumlah Beugel yang dibutuhkan Besi Ø 8


Back Up Data
PEKERJAAN : REHABILITASI GEDUNG BENGKEL INSTALASI PSRS
RUMAH SAKIT JIWA
TAHUN ANGGARAN : 2019
LOKASI : KOTA KENDARI PROVINSI SULAWESI TENGGARA

GAMBAR / SKET PERHITUNGAN


Beugel Tumpuan
= 14.00 : 0.15 = 93.33 Bh
Pembulatan = 94.00 Bh

Panjang Beugel yang dibutuhkan Besi Ø 8 (hitungan 1 Bh Beugel)


= 0.11 + 0.16 x 2 + 0.11 = 0.65 M1

Panjang Beugel yang dibutuhkan Besi Ø 8


= 94.00 x 0.65 = 61.10 m'

Volume Besi = Kg
Koefisien Besi Ø 12 = 0.006165 x 12 x 12 = 0.88776
= 0.88776 x 56 = 49.71 Kg

Koefisien Besi Ø 8 = 0.006165 x 8 x 8 = 0.39456


= 0.39456 x 61.10 = 24.11 Kg

Total Volume Besi


= 49.71 + 24.11 = 73.82 Kg

- Bekisting Sloef
Volume = P x T x Jml sisi
Sisi Luar = 14.40 x 0.20 x 1.00 = 2.88 M2
Sisi Dalam = 13.20 x 0.20 x 1.00 = 2.64 M2
Jumlah = 5.52 M2

2. Pekerjaan Pas. Kolom Praktis 11/11


Volume = T x Jml
= 3.46 x 4.00 = 13.82 M1

3. Pekerjaan Pas. Balok Latey 10/15


Volume = Pjng Latey
= 7.70 M1

4. Pekerjaan Pas. Ringbalk 10/15


Volume =Pjng Ringbalk
= 14.00 M1

C. Pekerjaan Dinding
1. Pekerjaan Pasangan Dinding 1/2 Bata Adukan 1PC : 5PS
Volume = P x T
= 13.20 x 3.46 = 45.61 M2

Dikurangi Lubang Pintu dan Latey


Volume = P x T x Jml
Pintu = 1.70 x 2.60 x 1.00 = 4.42 M2
Ventilasi = 1.55 x 0.60 x 2.00 = 1.86 M2
Latey = 7.70 x 0.15 = 1.16 M2
Jumlah = 7.44 M2

Luas Pas. Dinding


= 45.61 - 7.44 = 38.17 M2

2. Pekerjaan Plasteran Dinding Adukan 1PC : 5PS


Volume = L. Dinding x 2 sisi
dinding bgn = 38.17 x 2.00 = 76.34 M2

3. Pekerjaan Plasteran Beton Adukan 1PC : 2PS


Volume = L.Balok x T/P x Jml Kolom
Kolom Praktis 11/11 = 0.22 x 3.46 x 4.00 = 3.04 M2
Latey 10/15 = 0.30 x 7.70 x 1.00 = 2.31 M2

Jumlah = 5.35 M2

4. Pekerjaan Plasteran Pondasi Adukan 1PC : 5PS


Volume = P x L
Pondasi Bgn = 8.20 x 0.50 = 4.10 M2
Pondasi Teras = 2.20 x 0.40 = 0.88 M2
0.80 x 0.20 = 0.16 M2
Pondasi Tandon = 6.60 x 0.50 = 3.30 M2
Jumlah = 8.44 M2
Back Up Data
PEKERJAAN : REHABILITASI GEDUNG BENGKEL INSTALASI PSRS
RUMAH SAKIT JIWA
TAHUN ANGGARAN : 2019
LOKASI : KOTA KENDARI PROVINSI SULAWESI TENGGARA

GAMBAR / SKET PERHITUNGAN


4. Pekerjaan Acian Pasta Semen Plesteran Dinding dan Plesteran Beton
Volume = Luas Plesteran
Dinding = 76.34 M2
Beton = 5.35 M2
Pondasi = 8.44 M2
Jumlah = 90.13 M2

D. Pekerjaan Kusen, Pintu, Ventilasi dan Kaca


1. Pek. Kusen Pintu, Jendela dan Ventilasi Kayu Klas II
Volume = L1 x L2 x P
Pintu = 0.05 x 0.13 x 8.60 = 0.06 M3
Ventilasi = 0.05 x 0.13 x 9.20 = 0.06 M3
Jalusi Ventilasi = 0.02 x 0.13 x 5.60 = 0.01 M3
Jumlah = 0.13 M3

2. Pas. Daun Pintu Panil Kayu Klas I


Volume = P x L
Pintu = 1.60 x 2.10 = 3.36 M2

3. Pek. Pas. Kaca T. 5 mm


Volume = P x L x Jml
Pintu = 0.75 x 0.40 x 2.00 = 0.60 M2
Ventilasi = 0.70 x 0.50 x 2.00 = 0.70 M2
Jumlah = 1.30 M2

F. Pekerjaan Lantai
1. Pek. Penimbunan Tanah
Volume = P x L x T
Ruangan = 3.80 x 2.80 x 0.28 = 3.00 M3
Teras = 2.50 x 0.90 x 0.20 = 0.45 M3
Rg. Tandon = 1.90 x 1.90 x 0.28 = 1.02 M3

Jumlah = 4.47 M3

2. Pek. Urugan Pasir Bawah Lantai


Volume = P x L x T
Ruangan = 3.80 x 2.80 x 0.03 = 0.32 M3
Teras = 2.50 x 0.90 x 0.03 = 0.07 M3
Rg. Tandon = 1.90 x 1.90 x 0.03 = 0.11 M3

Jumlah = 0.49 M3

3. Pek. Pas. Rabat Lantai Adukan (Slab Beton K-100)


Volume = P x L x T
Ruangan = 3.80 x 2.80 x 0.05 = 0.53 M3
Teras = 2.50 x 0.95 x 0.05 = 0.12 M3
Rg. Tandon = 2.40 x 2.10 x 0.10 = 0.50 M3

Jumlah = 1.15 M3

4. Pek. Lantai Keramik 60x60 cm


Volume = P x L
Ruangan = 3.80 x 2.80 = 10.64 M2
Teras = 2.00 x 3.00 = 6.00 M2
Jumlah = 16.64 M2

5. Pek. Saluran Air Keliling Bangunan (Cor Beton K.100)


Volume = Pjng Saluran
= 17.70 M1

G. Pekerjaan Plafond
1. Pek. Pas. Rangka Plafond besi hollow 1x40.40.2mm, modul 60 x 60 cm
Volume = P x L
Ruangan = 3.80 x 2.80 = 10.64 M2
Luar = 16.80 x 0.70 = 11.76 M2
3.50 x 0.50 = 1.75 M2
Jumlah = 24.15 M2

3. Pek. Pas. List Plafond profil kayu


Volume = P x Jml
dalam ruangan = 13.40 x 1.00 = 13.40 M1
Luar ruangan = 14.40 x 1.00 = 14.40 M1
Back Up Data
PEKERJAAN : REHABILITASI GEDUNG BENGKEL INSTALASI PSRS
RUMAH SAKIT JIWA
TAHUN ANGGARAN : 2019
LOKASI : KOTA KENDARI PROVINSI SULAWESI TENGGARA

GAMBAR / SKET PERHITUNGAN


Jumlah = 27.80 M1

H. Pekerjaan Atap dan Listplank


1. Pek. Pas. Rangka Atap Baja Ringan Main Truss C.75-75 + Reng R.33-0.45
Volume = LA + LB x T x Jml Sisi
2
Depan blkng = 1.00 + 6.00 x 3.00 x 2.00 = 21.00 M2
2

= 3.70 x 0.40 = 1.48 M2

Samping = 5.00 x 3.00 x 2.00 = 15.00 M2


2
Jumlah = 37.48 M2

2. Pek. Rangka Atap/ Tiang, Besi Hollow Hitam


Rangka Atap Besi Hollow Hitam 40x40x2
Rangka gording = 2.80 x 4.00 = 11.2 M1
Rangka Atap Besi Hollow Hitam 40x40x2 = 4.30 x 1.00 = 4.3 M1 depan
4.60 x 2.00 = 9.2 M1 samping

Jumlah = 24.70 M1

Tiang Atap Besi Hollow Hitam 40x60x2


2.60 x 2.00 = 5.2 M1
2.30 x 2.00 = 4.6 M1
Jumlah = 9.80 M1

Pengecatan Besi Hollow


Rangka gording = 0.16 x 2.80 x 4.00 = 1.792 M2
Rangka Atap Besi Hollow Hitam 40x40x2 = 0.16 x 4.30 x 1.00 = 0.688 M2
0.16 x 4.60 x 1.00 = 0.736 M2

Tiang = 0.20 x 2.60 x 2.00 = 1.04 M2


0.20 x 2.30 x 2.00 = 0.92 M2
Jumlah = 5.18 M2

2. Pekerjaan Pas. Atap Spandek 0.30 mm


Volume = Luas Rangka
Atap Bangunan Utama = = 37.48 M2
Atap Rg Tandon = 2.50 x 3.00 = 7.50 M2
Jumlah = 44.98 M2

3. Pekerjaan Pas. Nok Atap Spandek 0.30 mm


Volume = Pjng Nok
= 17.00 M1

4. Pek. Listplank Kalsiplank, Uk. 1 x 20 Cm x 8 mm


Volume = Pjng Lisplank
Dpn blkng = 12.00
Samping = 10.80
Jumlah = 22.80 M1

F. Pekerjaan Pengecatan
1. Pekerjaan Pengecatan Dinding, Kolom, Balok & Plat Atap
Volume = P x T
Dinding Dalam = 13.20 x 3.30 = 43.56 M2
Dinding Luar = 14.40 x 3.10 = 44.64 M2
Dinding Pondasi = 15.50 x 0.50 = 7.75 M2

Jumlah = 95.95 M2

Dikurangi Lubang Pintu dan Ventilasi


Volume = P x T x Jml
Pintu = 1.70 x 2.60 x 2.00 = 8.84 M2
Ventilasi = 1.55 x 0.60 x 4.00 = 3.72 M2

Jumlah = 12.56 M2

Luas Pengecatan
Back Up Data
PEKERJAAN : REHABILITASI GEDUNG BENGKEL INSTALASI PSRS
RUMAH SAKIT JIWA
TAHUN ANGGARAN : 2019
LOKASI : KOTA KENDARI PROVINSI SULAWESI TENGGARA

GAMBAR / SKET PERHITUNGAN


= 95.95 - 12.56 = 83.39 M2

2. Pekerjaan Pengecatan Kusen, Pintu dan Ventilasi


Volume = P x L x Jml sisi
Kusen Pintu = 8.60 x 0.05 x 2.00 = 0.86 M2 sisi luar
= 10.20 x 0.13 x 1.00 = 1.33 M2 sisi dalam
Kusen Ventilasi = 9.20 x 0.05 x 2.00 = 0.92 M2 sisi luar
= 6.80 x 0.13 x 1.00 = 0.88 M2 sisi dalam
Jalusi Ventilasi = 5.60 x 0.30 x 1.00 = 1.68 M2 sisi luar
Daun Pintu = 1.60 x 2.10 x 2.00 = 6.72 M2

Jumlah = 12.39 M2

Dibuat Oleh :
Konsultan Perencana
CV. FIKRINDO KONSULTAN

…………………….
Staf Teknis

Anda mungkin juga menyukai