Engineer Estimate (EE) Warning Light

Material Upah
No Uraian Pekerjaan Satuan Volume
Harga Satuan Harga Total Total
A. Warning Light ( Tenaga Surya )
a. Pekerjaan Pengadaan
1 Controller Warning Light Modul 1.00 10,000,000.00 10,000,000.00
2 Panel Surya Unit 1.00 5,000,000.00 5,000,000.00
3 Kabel NYY 4x2.5mm m 10.00 30,000.00 300,000.00
4 Lampu Isyarat 3 Aspek 30 cm LED buah 2.00 5,500,000.00 11,000,000.00
5 Battery VRLA 12v 100 A Buah 1.00 2,500,000.00 2,500,000.00
6 Tiang Lengkung Galvanis 4"-3" T 5,5 m buah 1.00 8,000,000.00 8,000,000.00
7 Patok Pengaman buah 4.00 300,000.00 1,200,000.00
8 Angkur 5/8" Panjang 50 cm buah 4.00 100,000.00 400,000.00
9 Mur Baut Angkur buah 4.00 15,000.00 60,000.00

b. Pekerjaan Pemasangan
1 Pekerjaan Cor Tiang Over Head m3 1.28 1,045,300.00 1,337,984.00 718,080.00
2 Pekerjaan Cor Patok Pengaman m3 0.16 1,045,300.00 167,248.00 89,760.00
3 Pekerjaan Galian Tanah Pondasi WL m3 1.62 189,540.00
4 Urugan Tanah Kembali Pondasi m3 0.34 10,880.00
5 Urugan Pasir Dibawah Pondasi m3 0.10 162,500.00 16,869.53 3,322.00
6 Pasang dan Setting Box Lampu buah 2.00 500,000.00
7 Pembuatan Dudukan Controller buah 2.00 100,000.00
8 Pemasangan Controller unit 2.00 100,000.00
9 Pengelasan cm 175.00 270,725.00
10 Pengecatan Patok Pengaman m2 3.20 52,925.00 169,360.00 224,000.00
11 Biaya Programming Controller Ls 2.00 1,000,000.00
12 Mobilisasi Ls 1.00 800,000.00
13 Biaya Pendirian Tiang Unit 2.00 1,000,000.00
Jumlah 40,151,461.53 5,006,307.00
Jumlah (a+b) 45,157,768.53
PPN 10% 4,515,776.85
Harga Total Rp 49,673,545.38