Anda di halaman 1dari 10

2023

Minggu Ke 21 ( Dua Puluh Satu )


23-Nov-2023
Periode
29-Nov-2023

·PROGRES FISIK : 48.84 %


PROGRES PEKERJAAN MINGGUAN

PRESENTASE (%)
KONTRAK
SAMPAI DENGAN
MINGGU LALU MINGGU INI
MINGGU INI
No. URAIAN PEKERJAAN

HARGA SATUAN JUMLAH HARGA BOBOT VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT
SAT VOL VOL ADD

( Rp ) ( Rp ) (%) (%) (%) (%)

1 2 3 4 5 6 7 8 10 11 13 14 16 17

A PEKERJAAN BANGUNAN PUSKESMAS

I PEKERJAAN PERSIAPAN

1 Pengukuran dan Pemasangan Bouwplank M1 91.80 91.80 143,165.54 13,142,596.19 0.178 91.80 0.178 - 91.80 0.178 100.0

2 Papan Nama Proyek BH 1.00 1.00 576,372.72 576,372.72 0.008 1.00 0.008 - 1.00 0.008 100.0

3 Pembuatan Direksi Keet Los Kerja dan Gudang M2 30.00 30.00 2,617,215.61 78,516,468.37 1.063 30.00 1.063 - 30.00 1.063 100.0

4 Pembongkaran dan Pengangkuta Hasil Bongkaran 1 Gedung Eksisting Ls 1.00 1.00 7,500,000.00 7,500,000.00 0.102 1.00 0.102 - 1.00 0.102 100.0

5 Pemagaran Daerah Kerja M1 99.80 99.80 106,063.95 10,585,182.37 0.143 99.80 0.143 - 99.80 0.143 100.0

6 Manajemen Mutu / Pengujian Material Ls 1.00 1.00 5,000,000.00 5,000,000.00 0.068 1.00 0.068 - 1.00 0.068 100.0

7 Keselamatan dan Kesehatan Kerja (K3) Ls 1.00 1.00 45,300,000.00 45,300,000.00 0.613 1.00 0.613 - 1.00 0.613 100.0

8 Administrasi ,Dokumentasi & Pelaporan Ls 1.00 1.00 7,500,000.00 7,500,000.00 0.102 0.65 0.066 - 0.65 0.066 65.0

9 Mobilisasi dan Demobilisasi Ls 1.00 1.00 9,250,000.00 9,250,000.00 0.125 0.65 0.081 - 0.65 0.081 65.0

JUMLAH PEKERJAAN PERSIAPAN 177,370,619.65 2.40 2.32 - 2.32


II PEKERJAAN TANAH DAN URUGAN

1 Pek. Galian Perataan Tanah (Stripping) dan Pembersihan Lahan M3 115.20 115.20 82,775.00 9,535,680.00 0.129 115.20 0.129 - 115.20 0.129 100.0

2 Pek. Galian Tanah untuk Pondasi Footplate M3 99.00 108.50 82,775.00 8,981,418.60 0.122 108.50 0.122 - 108.50 0.122 100.0

3 Pek. Galian Tanah untuk Pondasi Menerus dan Selasar M3 209.08 172.00 82,775.00 14,236,968.90 0.193 172.00 0.193 - 172.00 0.193 100.0

4 Pek. Urugan Pasir Dibawah Pondasi Menerus M3 17.88 18.31 1,785,818.40 32,706,767.82 0.443 18.31 0.443 - 18.31 0.443 100.0

5 Pek. Urugan Pasir Dibawah Lantai dan Selasar M3 28.08 28.08 1,785,818.40 50,145,736.05 0.679 28.08 0.679 - 28.08 0.679 100.0

6 Pek. Urugan Sirtu Peninggi Pail Lantai dan Selasar M3 80.59 80.59 1,783,068.40 143,689,012.84 1.946 80.59 1.946 - 80.59 1.946 100.0

Pek. Urugan Tanah Peninggi Lantai M3 76.19 60,500.00 4,609,628.10 0.062 76.19 0.062 - 76.19 0.062 100.0

JUMLAH PEKERJAAN TANAH DAN URUGAN 263,905,212.31 3.57 3.57 - 3.57

III PEKERJAAN PASANGAN DAN PLESTERAN

1 Pek. Pasangan Aanstamping / Batu Kosong M3 75.83 51.16 2,383,698.56 121,960,270.04 1.651 51.16 1.651 - 51.16 1.651 100.0

2 Pek. Pasangan Batu Pondasi Menerus Mortar Tipe N (5,2 Mpa) M3 223.71 204.36 3,096,872.03 632,875,938.50 8.569 204.36 8.569 - 204.36 8.569 100.0

3 Pek. Pasangan Batu Pondasi Selasar dan Saluran Mortar Tipe N (5,2 Mpa) M3 46.56 46.56 3,096,872.03 144,186,180.93 1.952 - - - - -

4 Pek. Plester Saluran Selasar 1 Pc : 4 PP Tebal 15 Cm M2 136.08 136.08 109,926.54 14,958,803.49 0.203 - - - - -

5 Pek. Acian Saluran Selasar M2 136.08 136.08 47,279.26 6,433,761.15 0.087 - - - - -

6 Pek. Pasangan Tangga Mortar Tipe N (5,2 Mpa) M3 27.65 27.65 3,096,872.03 85,628,511.63 1.159 - - - - -

7 Pek. Pasangan Bata Ringan (10 x 20 x 60 cm) Dinding dengan Mortar Siap Pakai
M2 1,028.83 1,015.63 325,280.13 330,364,581.14 4.473 1,015.63 4.473 - 1,015.63 4.473 100.0

8 Pek. Pemasangan 1 m2 Dinding Terawang dengan Mortar Tipe N,fc’ 5,2 Mpa M2 9.79 9.79 908,592.31 8,896,118.18 0.120 - - - - -

9 Pek. Plester Dinding dengan Semen Instan (MU 301) Tebal 8 mm M2 2,057.66 2,057.66 136,244.88 280,345,642.04 3.796 - 180.75 0.333 180.75 0.333 8.8

10 Pek. Acian Dinding dengan Semen Instan (MU 270) Tebal 2 mm M2 2,057.66 2,057.66 67,601.15 139,100,185.81 1.883 - - - - -

11 Pek. Pasangan Aluminium Composit Panel ( ACP ) Tebal 4 mm Setara M2 238.44 238.44 1,095,994.04 261,328,819.63 3.538 - - - - -

JUMLAH PEKERJAAN PASANGAN DAN PLESTERAN 2,026,078,812.54 27.43 14.69 0.33 15.03
IV PEKERJAAN BETON BERTULANG

1 Pek. Rabat Lantai Beton Mutu f’c = 7,4 Mpa (K100) M3 16.51 16.51 3,127,991.67 51,643,142.43 0.699 2.53 0.107 7.50 0.318 10.03 0.425 60.8

2 Pek. Rabat Beton Lantai Kerja Footplate Beton Mutu f’c = 7,4 Mpa (K100) M3 6.60 6.60 3,127,991.67 20,644,745.01 0.280 6.60 0.280 - 6.60 0.280 100.0

3 Pek. Footplate 100/100 Cm Beton Mutu f’c = 21,7 Mpa (K250) M3 19.80 19.80 8,280,590.43 163,955,690.51 2.220 19.80 2.220 - 19.80 2.220 100.0

4 Pek. Kolom Pedestal 25/25 Cm Beton Mutu f’c = 21,7 Mpa (K250) M3 5.84 5.78 13,570,974.57 78,397,823.72 1.062 5.78 1.062 - 5.78 1.062 100.0

5 Pek. Kolom Struktur 25/25 Cm Beton Mutu f’c = 21,7 Mpa (K250) M3 16.21 16.09 13,570,974.57 218,323,053.40 2.956 16.09 2.956 - 16.09 2.956 100.0

6 Pek. Kolom Praktis 11/15 Cm Beton Mutu f’c = 21,7 Mpa (K250) M3 10.46 10.46 16,053,275.53 167,917,262.03 2.274 9.94 2.161 - 9.94 2.161 95.0

7 Pek. Sloof 25/35 Cm Beton Mutu f’c = 21,7 Mpa (K250) M3 30.65 0.00 8,481,443.50 - -

7.a Pek. Sloof 25/35 Cm Beton Mutu f’c = 21,7 Mpa (K250) M3 29.60 7,603,465.07 225,072,070.35 3.048 29.60 3.048 - 29.60 3.048 100.0

8 Pek. Sloof 15/20 Cm Beton Mutu f’c = 21,7 Mpa (K250) M3 2.45 2.45 10,852,291.57 26,588,114.34 0.360 2.45 0.360 - 2.45 0.360 100.0

9 Pek. Balok 25/35 Cm Beton Mutu f’c = 21,7 Mpa (K250) M3 32.10 32.10 9,851,907.20 316,246,221.01 4.282 10.20 1.361 21.90 2.921 32.10 4.282 100.0

10 Pek. Ring Balk 10/20 Cm Beton Mutu f’c = 21,7 Mpa (K250) M3 3.17 1.95 10,408,696.79 20,328,184.83 0.275 - - - - -

11 Pek. Talang Beton f’c = 21,7 Mpa (K250) M3 19.00 0.00 11,726,386.29 - -

11a Pek. Lantai Talang Beton f’c = 21,7 Mpa (K250) M3 7.97 8,447,683.60 67,351,691.79 0.912 7.97 0.912 - 7.97 0.912 100.0

11b Pek. Lisplang Luar Beton f’c = 21,7 Mpa (K250) M3 8.77 8,161,250.65 71,574,821.11 0.969 8.77 0.969 - 8.77 0.969 100.0

11c Pek. Lisplang Dalam Beton f’c = 21,7 Mpa (K250) M3 5.44 6,927,472.70 37,657,741.58 0.510 1.38 0.129 4.06 0.380 5.44 0.510 100.0

12 Pek. Meja Beton Mutu f’c = 21,7 Mpa (K250) M3 0.70 0.70 11,726,386.29 8,208,470.40 0.111 - - - - -

13 Pek. Beton Penutup Saluran Selasar Tebal 12 Cm f’c = 21,7 Mpa (K250) M3 0.42 0.42 11,726,386.29 4,925,082.24 0.067 - - - - -

Pek. Balok Latai 10/15 cm Beton Mutu f'c = 21,7 Mpa (K250) M3 2.06 10,344,919.30 21,292,947.40 0.288 1.55 0.217 - 1.55 0.217 75.3

JUMLAH PEKERJAAN BETON BERTULANG 1,500,127,062.14 20.31 15.78 3.62 19.40


V PEKERJAAN KUSEN, PINTU , JENDELA DAN PENGGANTUNG

1 Pek. Kusen Aluminium M' 973.85 973.85 198,891.00 193,689,997.18 2.623 - - - - -

2 Pek. Daun Bouvenlight Pintu Utama + Kaca 5 mm Panasap M2 0.83 0.83 1,619,167.61 1,343,909.11 0.018 - - - - -

3 Pek. Daun Pintu Aluminium + Kaca 8 mm Panasap M2 81.18 81.18 1,205,262.60 97,843,218.07 1.325 - - - - -

4 Pek. Daun Jendela Aluminium + Kaca 5 mm Panasap M2 64.88 71.45 1,072,715.60 76,647,031.61 1.038 - - - - -

5 Pek. Daun Bouvenlight Aluminium + Kaca 5 mm Panasap M2 14.60 32.09 1,072,715.60 34,428,592.72 0.466 - - - - -

6 Pas. Pintu Aluminium KM/WC Unit 3.00 3.00 1,553,554.58 4,660,663.73 0.063 - - - - -

7 Pas. Pintu Aluminium KM/WC Untuk Difabel Unit 1.00 1.00 1,553,554.58 1,553,554.58 0.021 - - - - -

8 Pek. Kaca Mati Panasap 5 mm M2 108.81 89.92 342,067.61 30,758,103.72 0.416 - - - - -

9 Pas. Kunci Pintu + Jendela + BouvenlightAluminium Bh 168.00 124.00 274,129.52 33,992,061.04 0.460 - - - - -

10 Pas. Pull Handel Pintu PSG 47.00 47.00 250,974.52 11,795,802.65 0.160 - - - - -

11 Pas. Hengsel Jendela + Bouvenlight Bh 194.00 194.00 37,437.02 7,262,782.75 0.098 - - - - -

12 Pas. Engsel Sliding Jendela + Bouvenlight Bh 84.00 54.00 392,927.37 21,218,078.11 0.287 - - - - -

13 Pas. Engsel Pintu Bh 141.00 141.00 58,084.02 8,189,847.45 0.111 - - - - -

14 Pas. Door Closer Bh 47.00 47.00 261,479.52 12,289,537.65 0.166 - - - - -

15 Pas. Hak Angin Pintu + Jendela + Bouvenlight Bh 105.00 0.00 46,072.02 - -

16 Pas. Grendel Pintu + Jendela + Bouvenlight Bh 8.00 115.00 58,364.52 6,711,920.32 0.091 - - - - -

JUMLAH PEKERJAAN KUSEN, PINTU , JENDELA DAN PENGGANTUNG 542,385,100.70 7.34 - - -

VI PEKERJAAN ATAP DAN PLAFOND

1 Pek. Kuda-kuda + Reng Baja Ringan M2 630.92 630.92 446,045.35 281,418,933.54 3.810 - 314.56 1.900 314.56 1.900 49.9

2 Pek. Atap Bitumen gelombang Monolayer 3 mm Onduline M2 630.92 630.92 215,617.76 136,037,555.29 1.842 - - - - -

3 Pek. Bubungan Atap + Jurai Ounduline M 107.36 107.36 375,402.58 40,303,220.56 0.546 - - - - -

4 Pek. Plafond Gypsum Rangka Hollow 40.40 mm Modul 60 x 60 M2 567.41 567.41 771,053.57 437,503,508.14 5.924 - - - - -

JUMLAH PEKERJAAN ATAP DAN PLAFOND 895,263,217.52 12.12 - 1.90 1.90


VII PEKERJAAN LANTAI

1 Pek. Pas. Granit Tile 60 x 60 Anti Slip Teras, Selasar dan Tangga M2 101.65 101.65 373,884.49 38,005,358.03 0.515 - - - - -

2 Pek. Pas. Granit Tile 60 x 60 Polos M2 427.27 426.29 373,884.49 159,381,348.22 2.158 - - - - -

3 Pek. Pas. Keramik 20 x 40 Meja Beton dan Bak M2 11.09 11.09 280,496.11 3,110,701.82 0.042 - - - - -

4 Pek. Pas. Keramik 20 x 40 Dinding M2 74.30 74.30 280,496.11 20,840,860.68 0.282 - - - - -

5 Pek. Pas. Keramik 10 x 60 Plint M2 47.99 47.99 162,172.77 7,782,671.39 0.105 - - - - -

6 Pek. Pas. Keramik 20 x 20 KM/WC M2 65.20 16.91 437,223.63 7,393,451.55 0.100 - - - - -

JUMLAH PEKERJAAN LANTAI 236,514,391.68 3.20 - - -

VIII PEKERJAAN 2 UNIT SEPTICTANK DAN SANITAIR

1 Pek. Galian Tanah Septictank & Bak Kontrol M3 31.5 31.50 82,775.00 2,607,412.50 0.035 - - - - -

2 Pas. Bata Ringan Septictank dan Bak Kontrol dengan Mortar Siap Pakai M2 58.5 58.50 325,280.13 19,028,887.46 0.258 - - - - -

3 Pek. Plester Dinding dengan Semen Instan (MU 301) M2 44.00 44.00 136,244.88 5,994,774.77 0.081 - - - - -

4 Pek. Acian Dinding dengan Semen Instan (MU 270) M2 44.00 44.00 67,601.15 2,974,450.67 0.040 - - - - -

5 Pek. Kolom Praktis 11/15 Beton Mutu f’c = 21,7 Mpa (K250) M3 0.45 0.45 16,053,275.53 7,223,973.99 0.098 - - - - -

6 Pek. Rabat Lantai Beton f’c = 14,5 Mpa (K175) M3 0.8 0.80 3,127,991.67 2,502,393.33 0.034 - - - - -

7 Pek. Sloof 15/20 Beton Mutu f’c = 21,7 Mpa (K250) M3 0.78 0.78 10,852,291.57 8,464,787.42 0.115 - - - - -

8 Pek. Ring Balk 10/20 Beton Mutu f’c = 21,7 Mpa (K250) M3 0.52 0.52 10,408,696.79 5,412,522.33 0.073 - - - - -

9 Pek. Plat Beton f’c = 21,7 Mpa (K250) M3 1.68 1.68 11,726,386.29 19,700,328.96 0.267 - - - - -

10 Pas. Pipa PVC Ø 4" Class AW Setara (Limbah Padat) M1 39.00 39.00 81,316.49 3,171,343.01 0.043 - - - - -

11 Pas. Pipa PVC Ø 3" Class AW Setara (Limbah Talang) M1 146.40 129.00 63,158.24 8,147,412.62 0.110 - - - - -

12 Pas. Pipa PVC Ø 2" Class AW Setara (Limbah Cair) M1 676.94 212.90 40,249.36 8,569,089.25 0.116 - - - - -

13 Pas. Pipa PVC Ø 2" Class AW Setara (Air Bersih) M1 90.32 90.32 40,249.36 3,635,322.41 0.049 - - - - -

14 Pas. Pipa PVC Ø 3/4" Class AW Setara (Air Bersih) M1 69.08 40.00 22,412.82 896,512.87 0.012 - - - - -

15 Pas. Closet Duduk Komplit Tabung Air Standar SNI Bh 4.00 4.00 3,190,179.52 12,760,718.10 0.173 - - - - -
16 Pek. Pasang Kran Air 1/2" Bh 4.00 4.00 162,644.07 650,576.26 0.009 - - - - -

17 Pek. Socket Kran Air 1/2" Bh 8.00 8.00 85,644.07 685,152.53 0.009 - - - - -

18 Pek. Fausit Shocket Air 1/2" Bh 4.00 4.00 17,837.31 71,349.24 0.001 - - - - -

19 Pas. Floor Drain 2" Aluminium Bh 5.00 5.00 92,441.04 462,205.20 0.006 - - - - -

20 Pas, Roof Drain Ø 3 " besi tuang Bh 24.00 11.00 97,941.04 1,077,351.44 0.015 - - - - -

21 Pas. Washtafel Komplit Kran Standar SNI Bh 5.00 5.00 1,054,667.53 5,273,337.67 0.071 - - - - -

22 Pas. Bak Cuci Aluminium Set Bh 5.00 5.00 621,070.71 3,105,353.57 0.042 - - - - -

23 Pas. Grease Trap Unit 1.00 1.00 502,837.31 502,837.31 0.007 - - - - -

24 Pas. Spoel Hoek Janitor Bh 1.00 1.00 9,032,229.44 9,032,229.44 0.122 - - - - -

25 Pek. Hand Relling Stainles Toilet Pjg 60cm Bh 4.00 4.00 246,386.04 985,544.16 0.013 - - - - -

JUMLAH PEKERJAAN 2 UNIT SEPTICTANK DAN SANITAIR 132,935,866.51 1.80 - - -

IX INSTALASI LISTRIK

1 Pas. Titik Lampu Titik 92.00 92.00 1,095,105.53 100,749,709.17 1.364 - - - - -

2 Pas. MCB Bh 2.00 2.00 926,739.93 1,853,479.86 0.025 - - - - -

3 Pas. Arde Panel Unit 1.00 1.00 378,337.31 378,337.31 0.005 - - - - -

4 Pas. Sakelar Ganda Bh 25.00 25.00 281,792.08 7,044,802.01 0.095 - - - - -

5 Pas. Sakelar Tunggal Bh 19.00 19.00 287,292.08 5,458,549.53 0.074 - - - - -

6 Pas. Stop Kontak Bh 50.00 50.00 281,792.08 14,089,604.02 0.191 - - - - -

7 Pas. Fitting Emergency + NICAD baterai Bh 4.00 4.00 112,837.31 451,349.24 0.006 - - - - -

8 Pas. Fire Extinguisher Powder Kapasitas 3 Kg Bh 1.00 1.00 1,232,229.44 1,232,229.44 0.017 - - - - -

9 Pas. Lampu LED 24 Watt Bh 6.00 6.00 102,837.31 617,023.86 0.008 - - - - -

10 Pas. Lampu LED 14 Watt Bh 70.00 70.00 87,837.31 6,148,611.65 0.083 - - - - -

11 Pas. Lampu LED 10 Watt Bh 23.00 23.00 67,837.31 1,560,258.11 0.021 - - - - -

JUMLAH PEKERJAAN INSTALASI LISTRIK 139,583,954.20 1.89 - - -


X PEKERJAAN PENANGKAL PETIR

1 Pek. Splitter Lighting Protection Unit 2.00 2.00 2,000,000.00 4,000,000.00 0.054 - - - - -

2 Pek. Kabel BC 1 X 50 mm2 M1 52.00 52.00 100,000.00 5,200,000.00 0.070 - - - - -

3 Pek. Instalasi Lengkap dengan Material Bantu Unit 1.00 1.00 3,000,000.00 3,000,000.00 0.041 - - - - -

4 Grounding System + Bak Kontrol Unit 1.00 1.00 4,000,000.00 4,000,000.00 0.054 - - - - -

JUMLAH PEKERJAAN PENANGKAL PETIR 16,200,000.00 0.22 - - -

XI PEKERJAAN JALAN MASUK

1 Pek. Galian Perataan Tanah (Stripping) dan Pembersihan Jalan Masuk M3 112.00 112.00 82,775.00 9,270,800.00 0.126 61.10 0.068 3.24 0.004 64.34 0.072 57.4

2 Pek. Pasangan Batu Kastin Mortar Tipe N (5,2 Mpa) M3 21.60 55.69 3,096,872.03 172,455,088.92 2.335 21.29 0.893 14.08 0.590 35.37 1.483 63.5

3 Pek. Urugan Pasir Dibawah Paving Block M3 19.20 19.20 1,785,818.40 34,287,713.29 0.464 - - - - -

4 Pek. Pasangan Pavingblock Hexagon (Blok Beton) Natural tebal 8cm M2 192.00 225.00 430,547.29 96,873,140.11 1.312 - - - - -

5 Pek. Plester Kastin 1 Pc : 4 PP Tebal 15 Cm M2 124.80 124.80 109,926.54 13,718,832.13 0.186 - - - - -

6 Pek. Acian Kastin M2 124.80 124.80 47,279.26 5,900,451.15 0.080 - - - - -

7 Pek. Beton 25/25 cm Beton Mutu f’c = 21,7 Mpa (K250) ( Umpak ) M3 3.30 3.30 13,570,974.57 44,784,216.08 0.606 - - - - -

8 Pek. Kolom Kayu 8/12 m3 1.69 1.69 10,616,291.21 17,941,532.14 0.243 - - - - -

9 Pek. Rangka Atap Kayu 6/10 m3 2.28 2.28 10,616,291.21 24,205,143.96 0.328 - - - - -

10 Pek. Gording Kayu 6 / 10 m3 4.03 4.03 9,682,309.94 39,019,709.06 0.528 - - - - -

11 Pek. Bubungan Atap Ounduline m1 96.00 96.00 375,402.58 36,038,647.29 0.488 - - - - -

12 Pek. Atap Ounduline m2 345.60 345.60 215,617.76 74,517,496.84 1.009 - - - - -

Pekerjaan Galian Untuk Pas. Batu Kastin m3 30.09 82,775.00 2,490,534.20 0.034 10.11 0.011 10.11 0.011 20.22 0.023 67.2

Pekerjaan Galian Tanah Saluran m3 2.02 82,775.00 167,205.50 0.002 1.50 0.002 0.52 0.001 2.02 0.002 100.0

Pek. Pasangan Batu Saluran Mortar Tipe N (5,2 Mpa) m3 2.72 3,096,872.03 8,414,201.31 0.114 - - - - -

Pek. Plester Saluran 1 Pc : 4 PP Tebal 15 Cm M2 39.13 109,926.54 4,301,425.49 0.058 - - - - -

Pek. Acian Saluran M2 39.13 47,279.26 1,850,037.29 0.025 - - - - -

JUMLAH PEKERJAAN JALAN MASUK 586,236,174.77 7.94 0.97 0.61 1.58


XII PEKERJAAN PAGAR

1 Pek. Pembongkaran Pasangan Batu Pagar Eksisting Semi Mekanis M3 5.74 5.74 40,966.10 235,043.00 0.003 4.62 0.003 - 4.62 0.003 80.5

2 Pek. Pembongkaran Dinding Pagar Eksisting Semi Mekanis M3 6.38 6.38 24,439.78 155,803.57 0.002 6.38 0.002 - 6.38 0.002 100.0

3 Pek. Galian Tanah untuk Pondasi Pagar M3 355.60 179.48 82,775.00 14,856,125.90 0.201 179.48 0.201 - 179.48 0.201 100.0

4 Pek. Urugan Pasir Dibawah Pondasi Pagar M3 89.59 32.00 1,785,818.40 57,142,009.47 0.774 7.87 0.190 0.42 0.010 8.29 0.200 25.9

5 Pek. Pasangan Batu Pondasi Pagar Mortar Tipe N (5,2 Mpa) M3 51.95 57.62 3,096,872.03 178,452,411.86 2.416 42.35 1.776 4.86 0.204 47.21 1.980 81.9

6 Pek. Sloof 10/20 Beton Mutu f’c = 21,7 Mpa (K250) M3 3.16 4.50 10,852,291.57 48,835,312.05 0.661 3.15 0.463 0.79 0.115 3.94 0.578 87.4

7 Pek. Kolom Praktis 20/20 Beton Mutu f’c = 21,7 Mpa (K250) M3 5.38 5.87 11,637,950.48 68,338,045.25 0.925 4.48 0.706 0.30 0.047 4.78 0.753 81.4

8 Pek. Ring Balk 15/20 Beton Mutu f’c = 21,7 Mpa (K250) M3 3.16 7.06 8,459,913.13 59,743,906.49 0.809 4.95 0.567 - 4.95 0.567 70.1

9 Pek. Pasangan Bata Ringan (10 x 20 x 60 cm) Pagar dengan Mortar Siap Pakai M2 16.86 223.30 325,280.13 72,635,052.46 0.984 132.95 0.586 27.72 0.122 160.67 0.708 72.0

10 Pek. Plester Dinding dengan Semen Instan (MU 301) Tebal 8 mm M2 168.64 509.20 136,244.88 69,375,893.45 0.939 - - - - -

11 Pek. Acian Dinding dengan Semen Instan (MU 270) Tebal 2 mm M2 168.64 509.20 67,601.15 34,422,506.45 0.466 - - - - -

JUMLAH PEKERJAAN PAGAR 604,192,109.96 8.18 4.49 0.50 4.99

XIII PEKERJAAN PELATARAN

1 Pek. Galian Perataan Tanah (Stripping) dan Pembersihan Pelataran M3 10.00 10.00 82,775.00 827,750.00 0.011 10.00 0.011 - 10.00 0.011 100.0

2 Pek. Pasangan Batu Kastin PelataranMortar Tipe N (5,2 Mpa) M3 3.38 3.38 3,096,872.03 10,451,943.10 0.142 - - - - -

3 Pek. Urugan Pasir Dibawah Paving Block Pelataran M3 5.00 5.00 1,785,818.40 8,929,092.00 0.121 - - - - -

4 Pek. Pasangan Pavingblock Hexagon (Blok Beton) Natural tebal 8cm Pelataran M2 50.00 50.00 430,547.29 21,527,364.47 0.291 - - - - -

5 Pek. Plester Kastin 1 Pc : 4 PP Tebal 15 Cm Pelataran M2 19.50 19.50 109,926.54 2,143,567.52 0.029 - - - - -

6 Pek. Acian Kastin Pelatarn M2 19.50 19.50 47,279.26 921,945.49 0.012 - - - - -

7 PeK. Tiang Bendera + Aksesoris Ls 1.00 1.00 500,000.00 500,000.00 0.007 - - - - -

JUMLAH PEKERJAAN PELATARAN 45,301,662.59 0.61 0.01 - 0.01


XIV PEKERJAAN FINISHING

1 Pek. Cat Tembok Premium (Interior Spotless ) M2 1,667.51 1,667.51 38,514.63 64,223,529.97 0.870 - - - - -

2 Pek. Cat Tembok Premium ( Eksterior Weather Shield) M2 216.64 216.64 38,514.63 8,343,809.35 0.113 - - - - -

3 Pek. Cat Plafond Kualitas Baik M2 567.41 567.41 57,730.64 32,756,940.87 0.444 - - - - -

4 Pek. Waterproofing Talang Beton (Aqua Proof) M2 174.56 174.56 17,805.48 3,108,125.41 0.042 - - - - -

5 Pek. Cat Tembok Pagar Kualitas Baik m2 802.11 802.11 38,514.63 30,892,969.53 0.418 - - - - -

JUMLAH PEKERJAAN FINISHING 139,325,375.13 1.89 - - -

XV PEKERJAAN LAIN-LAIN

1 Pas. Papan Nama Acrylic Unit 30.00 30.00 981,718.17 29,451,545.24 0.399 - - - - -

2 Pembuatan Lambang Puskesmas bahan Acrylic Ls 2.00 2.00 5,000,000.00 10,000,000.00 0.135 - - - - -

3 Pek. Pasangan ACP Tebal 4 mm Setara Untuk Motif Songke Manual M2 4.70 17.64 1,095,994.04 19,333,334.92 0.262 - - - - -

4 Pek. Motif Songke Manual (Cat Dinding Depan) Ls 1.00 1.00 3,500,000.00 3,500,000.00 0.047 - - - - -

5 Pas. Pintu Pagar Dorong Unit 1.00 1.00 10,000,000.00 10,000,000.00 0.135 - - - - -

Pengadaan Air Bersih Ls 1.00 1.00 5,000,000.00 5,000,000.00 0.068 0.50 0.034 - 0.50 0.034 50.0

6 Pembersihan Akhir Ls 1.00 1.00 2,655,500.00 2,655,500.00 0.036 - - - - -

JUMLAH PEKERJAAN LAIN-LAIN 79,940,380.16 1.08 0.03 - 0.03

JUMLAH 7,385,359,939.88 100.00 41.88 6.96 48.84

a REALISASI SAMPAI DENGAN MINGGU LALU 41.88

b REALISASI MINGGU INI 6.96

c REALISASI SAMPAI DENGAN MINGGU INI 48.84