PAKET : ...................
PEKERJAAN : PEMBANGUNAN KANTOR CAMAT LAMURU
LOKASI : LINGKUNGAN LEM'PUE KELURAHAN LALEBATA
KECAMATAN : LAMURU
NAMA PERUSAHAAN : CV. AMMAR UTAMA
V PEKERJAAN STRUKTUR
Pekerjaan Poer Plat,Sloef & Kolom Beton 151,454,753.30
1 Pek.Lantai kerja ad. 1 : 3 : 5 Pondasi Poer K 100 M3 0.77 1,060,058.29 0.075 0.77 100.00 0.075 816,244.89
2 Pondasi Poer
- Bekisting M2 11.67 115,672.15 0.125 11.67 100.00 0.125 1,349,893.99
- Pembesian Kg 90.00 20,167.00 0.167 90.00 100.00 0.167 1,815,030.00
- Beton Struktur K.175 M3 1.20 1,164,438.78 0.129 1.20 100.00 0.129 1,397,326.53
3 Steak Kolom 30 /30
- Bekisting M2 7.50 115,672.15 0.080 7.50 100.00 0.080 867,541.13
- Pembesian Kg 128.00 20,167.00 0.238 128.00 100.00 0.238 2,581,376.00
- Beton Struktur K.225 M3 1.35 1,164,438.78 0.145 1.35 100.00 0.145 1,571,992.35
4 Sloof Beton S1 - 20/25
- Bekisting M2 40.15 115,672.15 0.428 40.15 100.00 0.428 4,644,236.82
- Pembesian Kg 1,456.50 20,167.00 2.709 1,456.50 100.00 2.709 29,373,235.50
- Beton Struktur K.175 M3 9.65 1,164,438.78 1.036 9.65 100.00 1.036 11,236,834.20
5 Sloof Beton S2- 15/20
- Bekisting M2 2.24 115,672.15 0.024 2.24 100.00 0.024 259,105.62
- Pembesian Kg 67.47 20,167.00 0.125 67.47 100.00 0.125 1,360,667.49
- Beton Struktur K.175 M3 0.51 1,164,438.78 0.055 0.51 100.00 0.055 593,863.78
6 Kolom beton K - 30/30
- Bekisting M2 21.00 115,672.15 0.224 21.00 100.00 0.224 2,429,115.15
- Pembesian Kg 330.40 20,167.00 0.615 330.40 100.00 0.615 6,663,176.80
- Beton Struktur K.175 M3 2.75 1,164,438.78 0.295 2.75 100.00 0.295 3,202,206.64
7 Balok Latai 10/15
- Bekisting M2 4.15 115,672.15 0.044 4.15 100.00 0.044 480,039.42
- Pembesian Kg 335.70 20,167.00 0.624 335.70 100.00 0.624 6,770,061.90
- Beton Struktur K.175 M3 1.10 1,164,438.78 0.118 1.10 100.00 0.118 1,280,882.65
8 Ringbalk beton 15/20
- Bekisting M2 15.26 115,672.15 0.163 15.26 100.00 0.163 1,765,157.01
- Pembesian Kg 730.51 20,167.00 1.359 730.51 100.00 1.359 14,732,195.17
- Beton Struktur K.175 M3 6.05 1,164,438.78 0.650 6.05 100.00 0.650 7,044,854.60
9 Kolom Praktis (KP) 11/11 M' 196.50 250,482.01 4.540 196.50 100.00 4.540 49,219,715.67