Anda di halaman 1dari 8

REKAPITULASI LAPORAN MINGGUAN

PROGRAM : PEMENUHAN UPAYA KESEHATAN PERORANGAN DAN UPAYA KESEHATAN MASYARAKAT

KEGIATAN : PENYEDIAAN FASILITAS PELAYANAN KESEHATAN UKM & UKP KEWENANGAN DAERAH KABUPATEN/KOTA

PEKERJAAN : PEMBANGUNAN PUSKESMAS PEMBANTU (DAK)

LOKASI : DESA MNESATBUBAK DAN DESA SAINONI KEC. POLEN KAB. TTS

TAHUN ANGGARAN : 2023 Minggu Ke : 18 12 November 2023 s/d 18 November 2023

BOBOT (%)
S/D MINGGU LALU MINGGU INI S/D MINGU INI
JUMLAH HARGA
NO URAIAN PEKERJAAN BOBOT BOBOT BOBOT KET.
(RP) JUMLAH HARGA (RP) JUMLAH HARGA (RP) JUMLAH HARGA (RP)
(%) (%) (%)

1 2 3 4 5 6 7 8 9 10 11

I PEMBANGUNAN PUSTU DESA MNESATBUBAK


I PEKERJAAN PERSIAPAN 9,104,085.00 1.66 7,933,032.37 1.45 210,526.32 0.04 8,143,558.68 1.48
II PEKERJAAN TANAH DAN URUGAN 8,503,490.60 1.55 4,576,193.60 0.83 - - 4,576,193.60 0.83
III PEKERJAAN PASANGAN DAN PLESTERAN 83,790,927.56 15.26 83,790,927.56 15.26 - - 83,790,927.56 15.26
IV PEKERJAAN BETON 38,075,051.84 6.94 36,587,393.36 6.66 - - 36,587,393.36 6.66
V PEKERJAAN ATAP DAN PLAFON 44,861,758.92 8.17 44,861,758.92 8.17 - - 44,861,758.92 8.17
VI PEKERJAAN KUSEN+PENGGANTUNG 27,270,324.40 4.97 3,766,730.00 0.69 11,740,042.60 2.14 15,506,772.60 2.82
VII PEKERJAAN KERAMIK LANTAI DAN DINDING 19,245,062.80 3.51 19,245,062.80 3.51 - - 19,245,062.80 3.51
VIII PEKERJAAN INSTALASI LISTTRIK 5,610,964.00 1.02 - - 5,610,964.00 1.02 5,610,964.00 1.02
IX PEKERJAAN SANITASI 23,208,035.00 4.23 10,394,384.00 1.89 6,706,825.50 1.22 17,101,209.50 3.12
X PEKERJAAN FINISHING 14,806,876.46 2.70 9,409,597.43 1.71 4,786,903.99 0.87 14,196,501.42 2.59
TOTAL I 274,476,576.58 50.00 220,565,080.04 40.18 29,055,262.41 5.29 249,620,342.44 45.47
LAPORAN KEMAJUAN PEKERJAAN MINGGUAN

PROGRAM : PEMENUHAN UPAYA KESEHATAN PERORANGAN DAN UPAYA KESEHATAN MASYARAKAT


KEGIATAN : PENYEDIAAN FASILITAS PELAYANAN KESEHATAN UKM & UKP KEWENANGAN DAERAH KABUPATEN/KOTA
PEKERJAAN : PEMBANGUNAN PUSTU DESA MNESATBUBAK
LOKASI : DESA MNESATBUBAK KEC. POLEN KAB. TTS
TAHUN ANGGARAN : 2023 Minggu Ke : 18 12 November 2023 s/d 18 November 2023

BOBOT (%)
S/D MINGGU LALU MINGGU INI S/D MINGGU INI
HARGA SATUAN
NO URAIAN PEKERJAAN SAT VOL JUMLAH HARA (RP) KET.
(RP) VOL JUMLAH HARGA (RP) BOBOT VOL JUMLAH HARGA (RP) BOBOT VOL JUMLAH HARGA (RP) BOBOT
(%) (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
PEMBANGUNAN PUSTU DESA MNESATBUBAK
I Pekerjaan Persiapan
Pengukuran dan Bouplank Ls 1.00 1,500,000.00 1,500,000.00 0.55 1.00 1,500,000.00 0.55 - - 1.00 1,500,000.00 0.55
Pengadaan Air untuk Kerja Ls 1.00 800,000.00 800,000.00 0.29 1.00 800,000.00 0.29 - - 1.00 800,000.00 0.29
Papan Nama Proyek Ls 1.00 350,000.00 350,000.00 0.13 1.00 350,000.00 0.13 - - 1.00 350,000.00 0.13
Perlengkapan K3 Ls 1.00 2,000,000.00 2,000,000.00 0.73 0.89 1,789,473.68 0.65 0.05 105,263.16 0.04 0.95 1,894,736.84 0.69
Administrasi dan Dokumentasi Ls 1.00 2,000,000.00 2,000,000.00 0.73 0.89 1,789,473.68 0.65 0.05 105,263.16 0.04 0.95 1,894,736.84 0.69
Mobilisasi dan Demobilisasi Ls 1.00 1,500,000.00 1,500,000.00 0.55 0.50 750,000.00 0.27 - - 0.50 750,000.00 0.27
Pek. Pembersihan Lahan M2 91.30 10,450.00 954,085.00 0.35 91.30 954,085.00 0.35 - - 91.30 954,085.00 0.35
9,104,085.00 3.32 7,933,032.37 2.89 210,526.32 0.08 8,143,558.68 2.97
II Pekerjaan Tanah dan Urugan
Pek. Galian Pondasi Menerus M3 25.69 72,875.00 1,872,158.75 0.68 25.69 1,872,158.75 0.68 - - 25.69 1,872,158.75 0.68
Pek. Urugan Tanah Kembali M3 4.80 49,500.00 237,600.00 0.09 4.80 237,600.00 0.09 - - 4.80 237,600.00 0.09
Pek. Urugan Pasir Bawah Pondasi Menerus M3 24.90 187,550.00 4,669,995.00 1.70 3.96 742,698.00 0.27 - - 3.96 742,698.00 0.27
Pek. Urugan Pasir Bawah Lantai t = 5 cm M3 3.20 187,550.00 600,160.00 0.22 3.20 600,160.00 0.22 - - 3.20 600,160.00 0.22
Pek. Urugan Sirtu Peninggian Lantai M3 6.41 175,285.00 1,123,576.85 0.41 6.41 1,123,576.85 0.41 - - 6.41 1,123,576.85 0.41
8,503,490.60 3.10 4,576,193.60 1.67 - - 4,576,193.60 1.67
III Pekerjaan Pasangan dan Plesteran
Pek. Anstamping Batu M3 5.80 335,329.00 1,944,908.20 0.71 5.80 1,944,908.20 0.71 - - 5.80 1,944,908.20 0.71
Pek. Pondasi Batu Karang 1 :4 M3 24.07 713,256.00 17,168,071.92 6.25 24.07 17,168,071.92 6.25 - - 24.07 17,168,071.92 6.25
Pek. Pasangan Tembok 1:4 M2 170.56 185,009.00 31,555,135.04 11.50 170.56 31,555,135.04 11.50 - - 170.56 31,555,135.04 11.50
Pek. Plesteran Tembok + Kolom 1: 4 M2 341.12 59,206.00 20,196,350.72 7.36 341.12 20,196,350.72 7.36 - - 341.12 20,196,350.72 7.36
Pek. Plesteran Pondasi 1: 4 M2 13.80 59,206.00 817,042.80 0.30 13.80 817,042.80 0.30 - - 13.80 817,042.80 0.30
Pek. Acian M2 341.12 35,499.00 12,109,418.88 4.41 341.12 12,109,418.88 4.41 - - 341.12 12,109,418.88 4.41
83,790,927.56 30.53 83,790,927.56 30.53 - - 83,790,927.56 30.53
IV Pekerjaan Beton
Cor Sloof 11X20 cm K - 175 Kg/Cm2
-. Pekerjaan Beton M3 1.80 1,001,828.00 1,803,290.40 0.66 1.80 1,803,290.40 0.66 - - 1.80 1,803,290.40 0.66
-. Pekerjaan Pembesian BJTP 24 Kg 325.07 13,427.00 4,364,714.89 1.59 325.07 4,364,714.89 1.59 - - 325.07 4,364,714.89 1.59
-. Pekerjaan Bekiting 2 x Pakai M2 24.00 201,487.00 4,835,688.00 1.76 24.00 4,835,688.00 1.76 - - 24.00 4,835,688.00 1.76
Cor Kolom Teras 15X30 cm K - 175 Kg\Cm2
-. Pekerjaan Beton M3 0.63 1,001,828.00 631,151.64 0.23 0.63 631,151.64 0.23 - - 0.63 631,151.64 0.23
-. Pekerjaan Pembesian BJTP 24 Kg 109.62 13,427.00 1,471,867.74 0.54 109.62 1,471,867.74 0.54 - - 109.62 1,471,867.74 0.54
-. Pekerjaan Bekiting 2 x Pakai M2 12.60 304,113.00 3,831,823.80 1.40 12.60 3,831,823.80 1.40 - - 12.60 3,831,823.80 1.40
Cor Kolom Praktis 11X11 cm K - 175 Kg/Cm2
-. Pekerjaan Beton M3 0.71 1,001,828.00 711,297.88 0.26 0.71 711,297.88 0.26 - - 0.71 711,297.88 0.26
-. Pekerjaan Pembesian BJTP 24 Kg 281.62 13,427.00 3,781,311.74 1.38 281.62 3,781,311.74 1.38 - - 281.62 3,781,311.74 1.38
-. Pekerjaan Bekiting 2 x Pakai M2 25.92 113,943.00 2,953,402.56 1.08 25.92 2,953,402.56 1.08 - - 25.92 2,953,402.56 1.08
Cor Ringbalk 11X20 cm K - 175 Kg/Cm2,Ev. 3,50 m
-. Pekerjaan Beton M3 1.80 1,001,828.00 1,803,290.40 0.66 1.80 1,803,290.40 0.66 - - 1.80 1,803,290.40 0.66
-. Pekerjaan Pembesian BJTP 24 Kg 330.77 13,427.00 4,441,248.79 1.62 330.77 4,441,248.79 1.62 - - 330.77 4,441,248.79 1.62
-. Pekerjaan Bekiting 2 x Pakai M2 24.00 310,248.50 7,445,964.00 2.71 24.00 7,445,964.00 2.71 - - 24.00 7,445,964.00 2.71
38,075,051.84 13.87 38,075,051.84 13.87 - - 38,075,051.84 13.87
V Pekerjaan Atap dan Plafond
Pek. Kuda - Kuda Kayu Klas II meranti M3 0.85 5,693,600.00 4,839,560.00 1.76 0.85 4,839,560.00 1.76 - - 0.85 4,839,560.00 1.76
Pek. Gording Kayu Klas II meranti M3 1.35 6,790,245.00 9,166,830.75 3.34 1.35 9,166,830.75 3.34 - - 1.35 9,166,830.75 3.34
Pek. Atap Seng Bjls 0.30 mm M2 130.27 67,727.00 8,822,796.29 3.21 130.27 8,822,796.29 3.21 - - 130.27 8,822,796.29 3.21
Pek. Atap Bubungan Galvalum M 57.07 43,686.00 2,493,160.02 0.91 57.07 2,493,160.02 0.91 - - 57.07 2,493,160.02 0.91
Pek. Woodplank 30 cm M 49.10 64,240.00 3,154,184.00 1.15 49.10 3,154,184.00 1.15 - - 49.10 3,154,184.00 1.15
Pek. Rangka Plafond Kayu M2 104.06 90,849.00 9,453,746.94 3.44 104.06 9,453,746.94 3.44 - - 104.06 9,453,746.94 3.44
Pek. Plafond Tripleks 4 mm M2 104.06 44,291.00 4,608,921.46 1.68 104.06 4,608,921.46 1.68 - - 104.06 4,608,921.46 1.68
Pek. List Plafond Kayu Profil M 60.00 24,590.00 1,475,400.00 0.54 60.00 1,475,400.00 0.54 - - 60.00 1,475,400.00 0.54
Pek. Residu Kayu Kuda-Kuda + Gording Ls 1.00 847,159.46 847,159.46 0.31 1.00 847,159.46 0.31 - - 1.00 847,159.46 0.31
44,861,758.92 16.34 44,861,758.92 16.34 - - 44,861,758.92 16.34
VI Pekerjaan Kusen + Penggantung
Pek. Kusen Kayu Klas II meranti M3 0.55 6,848,600.00 3,766,730.00 1.37 0.55 3,766,730.00 1.37 - - 0.55 3,766,730.00 1.37
Pek. Daun Pintu Panil Kayu Kelas II M2 12.52 584,650.00 7,319,818.00 2.67 - - - 6.26 3,659,909.00 1.33 6.26 3,659,909.00 1.33
Pek. Daun Jendela Bingkai K. Mati 5 mm M2 8.82 693,660.00 6,118,081.20 2.23 - - - 4.41 3,059,040.60 1.11 4.41 3,059,040.60 1.11
Pek. Jelusi kusen kayu kelas II M2 4.16 520,520.00 2,165,363.20 0.79 - - - 2.08 1,082,681.60 0.39 2.08 1,082,681.60 0.39
Pas. Kunci Pintu Bh 8.00 259,710.00 2,077,680.00 0.76 - - - 5.60 1,454,376.00 0.53 5.60 1,454,376.00 0.53
Pas. Engsel Pintu Bh 24.00 53,108.00 1,274,592.00 0.46 - - - 16.80 892,214.40 0.33 16.80 892,214.40 0.33
Pas. Engsel Jendela Bh 18.00 39,435.00 709,830.00 0.26 - - - 12.60 496,881.00 0.18 12.60 496,881.00 0.18
Pas. Kait Angin Bh 18.00 40,700.00 732,600.00 0.27 - - - 12.60 512,820.00 0.19 12.60 512,820.00 0.19
Pas. Grendel Jendela Bh 18.00 46,200.00 831,600.00 0.30 - - - 12.60 582,120.00 0.21 12.60 582,120.00 0.21
Pas. Engsel Boven Bh 18.00 39,435.00 709,830.00 0.26 - - - - - - - -
Pas. Kait Angin Boven Bh 18.00 40,700.00 732,600.00 0.27 - - - - - - - -
Pas. Grendel Boven Bh 18.00 46,200.00 831,600.00 0.30 - - - - - - - -
27,270,324.40 9.94 3,766,730.00 1.37 11,740,042.60 4.28 15,506,772.60 5.65
VII Pekerjaan Lantai
Pek. Rabat Lantai Ram t = 5 cm, K-100 M3 3.20 894,455.00 2,862,256.00 1.04 3.20 2,862,256.00 1.04 - - 3.20 2,862,256.00 1.04
Pek. Lantai Keramik polish 40 x 40 cm M2 64.06 211,680.00 13,560,220.80 4.94 64.06 13,560,220.80 4.94 - - 64.06 13,560,220.80 4.94
Pek. Dinding Keramik unpolish 25 x 25 cm M2 15.60 180,935.00 2,822,586.00 1.03 15.60 2,822,586.00 1.03 - - 15.60 2,822,586.00 1.03
19,245,062.80 7.01 19,245,062.80 7.01 - - 19,245,062.80 7.01
VIII Pekerjaan Instalasi Listrik
Pas. Titik Lampu Titik 6.00 200,729.00 1,204,374.00 0.44 - - - 6.00 1,204,374.00 0.44 6.00 1,204,374.00 0.44
Pas. Panel MCB Bh 1.00 150,000.00 150,000.00 0.05 - - - 1.00 150,000.00 0.05 1.00 150,000.00 0.05
Pas. Meteran Listrik 900 W Bh 1.00 2,000,000.00 2,000,000.00 0.73 - - - 1.00 2,000,000.00 0.73 1.00 2,000,000.00 0.73
Pas. Stop Kontak Bh 5.00 106,590.00 532,950.00 0.19 - - - 5.00 532,950.00 0.19 5.00 532,950.00 0.19
Pas. Saklar Tunggal Bh 6.00 113,410.00 680,460.00 0.25 - - - 6.00 680,460.00 0.25 6.00 680,460.00 0.25
Pas. Saklar Ganda Bh 2.00 106,590.00 213,180.00 0.08 - - - 2.00 213,180.00 0.08 2.00 213,180.00 0.08
Lampu Bohlam LED 6 Watt Bh 2.00 40,000.00 80,000.00 0.03 - - - 2.00 80,000.00 0.03 2.00 80,000.00 0.03
Pas. Lampu LED Bohlam 12 Watt Bh 10.00 75,000.00 750,000.00 0.27 - - - 10.00 750,000.00 0.27 10.00 750,000.00 0.27
5,610,964.00 2.04 - - 5,610,964.00 2.04 5,610,964.00 2.04
IX Pekerjaan Sanitasi
Pek. Septictank dan Peresapan Unit 1.00 7,508,695.00 7,508,695.00 2.74 1.00 7,508,695.00 2.74 - - 1.00 7,508,695.00 2.74
Pek. Closet Jongkok Bh 1.00 571,703.00 571,703.00 0.21 1.00 571,703.00 0.21 - - 1.00 571,703.00 0.21
Pemasangan 1 buah closet duduk\/monoblock Bh 1.00 1,893,595.00 1,893,595.00 0.69 1.00 1,893,595.00 0.69 - - 1.00 1,893,595.00 0.69
Pek. Wastavel Bh 1.00 881,064.00 881,064.00 0.32 - - - 0.50 440,532.00 0.16 0.50 440,532.00 0.16
Pek. Floor Drain Bh 2.00 67,430.00 134,860.00 0.05 2.00 134,860.00 0.05 - - 2.00 134,860.00 0.05
Pek. Kran Air Bh 3.00 95,177.00 285,531.00 0.10 3.00 285,531.00 0.10 - - 3.00 285,531.00 0.10
Pemasangan 1 Unit Tower lengkap dengan Profil tank unit 1.00 10,432,587.00 10,432,587.00 3.80 - - - 0.50 5,216,293.50 1.90 0.50 5,216,293.50 1.90
Pek. Instalasi Air Kotor Ls 1.00 750,000.00 750,000.00 0.27 - - - 0.70 525,000.00 0.19 0.70 525,000.00 0.19
Pek. Instalasi Air Bersih Ls 1.00 750,000.00 750,000.00 0.27 - - - 0.70 525,000.00 0.19 0.70 525,000.00 0.19
23,208,035.00 8.46 10,394,384.00 3.79 6,706,825.50 2.44 17,101,209.50 6.23
X Pekerjaan Finishing
Pek. Cat Woodplank M2 14.73 45,133.00 664,809.09 0.24 14.73 664,809.09 0.24 - - 14.73 664,809.09 0.24
Pek. Cat Plafond M2 104.06 28,259.00 2,940,631.54 1.07 104.06 2,940,631.54 1.07 - - 104.06 2,940,631.54 1.07
Pek. Cat Tembok dan Kolom M2 341.12 17,015.00 5,804,156.80 2.11 341.12 5,804,156.80 2.11 - - 341.12 5,804,156.80 2.11
Pek. Cat Seng M2 130.27 14,157.00 1,844,232.39 0.67 - - - 130.27 1,844,232.39 0.67 130.27 1,844,232.39 0.67
Pek. Cat Kusen Kayu M2 65.20 45,133.00 2,942,671.60 1.07 - - - 65.20 2,942,671.60 1.07 65.20 2,942,671.60 1.07
Pek. Vernis Daun Pintu Panil Papan M2 12.52 48,752.00 610,375.04 0.22 - - - - - - - -
Jumlah X 14,806,876.46 5.39 9,409,597.43 3.43 4,786,903.99 1.74 14,196,501.42 5.17
TOTAL I+II+III+IV+V+VI+VII+VIII+IX+X 274,476,576.58 100.00 222,052,738.52 80.90 29,055,262.41 10.59 251,108,000.92 91.49
BOBOT TERHADAP KONTRAK 50.00 40.45 5.29 45.74
LAPORAN KEMAJUAN PEKERJAAN MINGGUAN

PROGRAM : PEMENUHAN UPAYA KESEHATAN PERORANGAN DAN UPAYA KESEHATAN MASYARAKAT


KEGIATAN : PENYEDIAAN FASILITAS PELAYANAN KESEHATAN UKM & UKP KEWENANGAN DAERAH KABUPATEN/KOTA
PEKERJAAN : PEMBANGUNAN PUSTU DESA SAINONI
LOKASI : DESA SAINONI KEC. POLEN KAB. TTS
TAHUN ANGGARAN : 2023 Minggu Ke : 18 12 November 2023 s/d 18 November 2023

BOBOT (%)
S/D MINGGU LALU MINGGU INI S/D MINGGU INI
HARGA SATUAN
NO URAIAN PEKERJAAN SAT VOL JUMLAH HARA (RP) KET.
(RP) VOL JUMLAH HARGA (RP) BOBOT VOL JUMLAH HARGA (RP) BOBOT VOL JUMLAH HARGA (RP) BOBOT
(%) (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
PEMBANGUNAN PUSTU DESA SAINONI
I Pekerjaan Persiapan
Pengukuran dan Bouplank Ls 1.00 1,500,000.00 1,500,000.00 0.55 1.00 1,500,000.00 0.55 - - 1.00 1,500,000.00 0.55
Pengadaan Air untuk Kerja Ls 1.00 800,000.00 800,000.00 0.29 1.00 800,000.00 0.29 - - 1.00 800,000.00 0.29
Papan Nama Proyek Ls 1.00 350,000.00 350,000.00 0.13 1.00 350,000.00 0.13 - - 1.00 350,000.00 0.13
Perlengkapan K3 Ls 1.00 2,000,000.00 2,000,000.00 0.73 0.89 1,789,473.68 0.65 0.05 105,263.16 0.04 0.95 1,894,736.84 0.69
Administrasi dan Dokumentasi Ls 1.00 2,000,000.00 2,000,000.00 0.73 0.89 1,789,473.68 0.65 0.05 105,263.16 0.04 0.95 1,894,736.84 0.69
Mobilisasi dan Demobilisasi Ls 1.00 1,500,000.00 1,500,000.00 0.55 0.50 750,000.00 0.27 - - 0.50 750,000.00 0.27
Pek. Pembersihan Lahan M2 91.30 10,450.00 954,085.00 0.35 91.30 954,085.00 0.35 - - 91.30 954,085.00 0.35
9,104,085.00 3.32 7,933,032.37 2.89 210,526.32 0.08 8,143,558.68 2.97
II Pekerjaan Tanah dan Urugan
Pek. Galian Pondasi Menerus M3 25.69 72,875.00 1,872,158.75 0.68 25.69 1,872,158.75 0.68 - - 25.69 1,872,158.75 0.68
Pek. Urugan Tanah Kembali M3 4.80 49,500.00 237,600.00 0.09 4.80 237,600.00 0.09 - - 4.80 237,600.00 0.09
Pek. Urugan Pasir Bawah Pondasi Menerus M3 24.90 187,550.00 4,669,995.00 1.70 3.96 742,698.00 0.27 - - 3.96 742,698.00 0.27
Pek. Urugan Pasir Bawah Lantai t = 5 cm M3 3.20 187,550.00 600,160.00 0.22 3.20 600,160.00 0.22 - - 3.20 600,160.00 0.22
Pek. Urugan Sirtu Peninggian Lantai M3 6.41 175,285.00 1,123,576.85 0.41 6.41 1,123,576.85 0.41 - - 6.41 1,123,576.85 0.41
8,503,490.60 3.10 4,576,193.60 1.67 - - 4,576,193.60 1.67
III Pekerjaan Pasangan dan Plesteran
Pek. Anstamping Batu M3 5.80 335,329.00 1,944,908.20 0.71 5.80 1,944,908.20 0.71 - - 5.80 1,944,908.20 0.71
Pek. Pondasi Batu Karang 1 :4 M3 24.07 713,256.00 17,168,071.92 6.25 24.07 17,168,071.92 6.25 - - 24.07 17,168,071.92 6.25
Pek. Pasangan Tembok 1:4 M2 170.56 185,009.00 31,555,135.04 11.50 170.56 31,555,135.04 11.50 - - 170.56 31,555,135.04 11.50
Pek. Plesteran Tembok + Kolom 1: 4 M2 341.12 59,206.00 20,196,350.72 7.36 341.12 20,196,350.72 7.36 - - 341.12 20,196,350.72 7.36
Pek. Plesteran Pondasi 1: 4 M2 13.80 59,206.00 817,042.80 0.30 13.80 817,042.80 0.30 - - 13.80 817,042.80 0.30
Pek. Acian M2 341.12 35,499.00 12,109,418.88 4.41 341.12 12,109,418.88 4.41 - - 341.12 12,109,418.88 4.41
83,790,927.56 30.53 83,790,927.56 30.53 - - 83,790,927.56 30.53
IV Pekerjaan Beton
Cor Sloof 11X20 cm K - 175 Kg/Cm2
-. Pekerjaan Beton M3 1.80 1,001,828.00 1,803,290.40 0.66 1.80 1,803,290.40 0.66 - - 1.80 1,803,290.40 0.66
-. Pekerjaan Pembesian BJTP 24 Kg 325.07 13,427.00 4,364,714.89 1.59 325.07 4,364,714.89 1.59 - - 325.07 4,364,714.89 1.59
-. Pekerjaan Bekiting 2 x Pakai M2 24.00 201,487.00 4,835,688.00 1.76 24.00 4,835,688.00 1.76 - - 24.00 4,835,688.00 1.76
Cor Kolom Teras 15X30 cm K - 175 Kg\Cm2 0.00
-. Pekerjaan Beton M3 0.63 1,001,828.00 631,151.64 0.23 0.63 631,151.64 0.23 - - 0.63 631,151.64 0.23
-. Pekerjaan Pembesian BJTP 24 Kg 109.62 13,427.00 1,471,867.74 0.54 109.62 1,471,867.74 0.54 - - 109.62 1,471,867.74 0.54
-. Pekerjaan Bekiting 2 x Pakai M2 12.60 304,113.00 3,831,823.80 1.40 12.60 3,831,823.80 1.40 - - 12.60 3,831,823.80 1.40
Cor Kolom Praktis 11X11 cm K - 175 Kg/Cm2 0.00
-. Pekerjaan Beton M3 0.71 1,001,828.00 711,297.88 0.26 0.71 711,297.88 0.26 - - 0.71 711,297.88 0.26
-. Pekerjaan Pembesian BJTP 24 Kg 281.62 13,427.00 3,781,311.74 1.38 281.62 3,781,311.74 1.38 - - 281.62 3,781,311.74 1.38
-. Pekerjaan Bekiting 2 x Pakai M2 25.92 113,943.00 2,953,402.56 1.08 25.92 2,953,402.56 1.08 - - 25.92 2,953,402.56 1.08
Cor Ringbalk 11X20 cm K - 175 Kg/Cm2,Ev. 3,50 m 0.00
-. Pekerjaan Beton M3 1.80 1,001,828.00 1,803,290.40 0.66 1.80 1,803,290.40 0.66 - - 1.80 1,803,290.40 0.66
-. Pekerjaan Pembesian BJTP 24 Kg 330.77 13,427.00 4,441,248.79 1.62 330.77 4,441,248.79 1.62 - - 330.77 4,441,248.79 1.62
-. Pekerjaan Bekiting 2 x Pakai M2 24.00 310,248.50 7,445,964.00 2.71 24.00 7,445,964.00 2.71 - - 24.00 7,445,964.00 2.71
38,075,051.84 13.87 38,075,051.84 13.87 - - 38,075,051.84 13.87
V Pekerjaan Atap dan Plafond
Pek. Kuda - Kuda Kayu Klas II meranti M3 0.85 5,693,600.00 4,839,560.00 1.76 0.85 4,839,560.00 1.76 - - 0.85 4,839,560.00 1.76
Pek. Gording Kayu Klas II meranti M3 1.35 6,790,245.00 9,166,830.75 3.34 1.35 9,166,830.75 3.34 - - 1.35 9,166,830.75 3.34
Pek. Atap Seng Bjls 0.30 mm M2 130.27 67,727.00 8,822,796.29 3.21 130.27 8,822,796.29 3.21 - - 130.27 8,822,796.29 3.21
Pek. Atap Bubungan Galvalum M 57.07 43,686.00 2,493,160.02 0.91 57.07 2,493,160.02 0.91 - - 57.07 2,493,160.02 0.91
Pek. Woodplank 30 cm M 49.10 64,240.00 3,154,184.00 1.15 49.10 3,154,184.00 1.15 - - 49.10 3,154,184.00 1.15
Pek. Rangka Plafond Kayu M2 104.06 90,849.00 9,453,746.94 3.44 104.06 9,453,746.94 3.44 - - 104.06 9,453,746.94 3.44
Pek. Plafond Tripleks 4 mm M2 104.06 44,291.00 4,608,921.46 1.68 104.06 4,608,921.46 1.68 - - 104.06 4,608,921.46 1.68
Pek. List Plafond Kayu Profil M 60.00 24,590.00 1,475,400.00 0.54 60.00 1,475,400.00 0.54 - - 60.00 1,475,400.00 0.54
Pek. Residu Kayu Kuda-Kuda + Gording Ls 1.00 848,060.36 848,060.36 0.31 1.00 848,060.36 0.31 - - 1.00 848,060.36 0.31
44,862,659.82 16.34 44,862,659.82 16.34 - - 44,862,659.82 16.34
VI Pekerjaan Kusen + Penggantung
Pek. Kusen Kayu Klas II meranti M3 0.55 6,848,600.00 3,766,730.00 1.37 0.55 3,766,730.00 1.37 - - 0.55 3,766,730.00 1.37
Pek. Daun Pintu Panil Kayu Kelas II M2 12.52 584,650.00 7,319,818.00 2.67 - - - 6.26 3,659,909.00 1.33 6.26 3,659,909.00 1.33
Pek. Daun Jendela Bingkai K. Mati 5 mm M2 8.82 693,660.00 6,118,081.20 2.23 - - - 4.41 3,059,040.60 1.11 4.41 3,059,040.60 1.11
Pek. Jelusi kusen kayu kelas II M2 4.16 520,520.00 2,165,363.20 0.79 - - - 2.08 1,082,681.60 0.39 2.08 1,082,681.60 0.39
Pas. Kunci Pintu Bh 8.00 259,710.00 2,077,680.00 0.76 - - - 5.60 1,454,376.00 0.53 5.60 1,454,376.00 0.53
Pas. Engsel Pintu Bh 24.00 53,108.00 1,274,592.00 0.46 - - - 16.80 892,214.40 0.33 16.80 892,214.40 0.33
Pas. Engsel Jendela Bh 18.00 39,435.00 709,830.00 0.26 - - - 12.60 496,881.00 0.18 12.60 496,881.00 0.18
Pas. Kait Angin Bh 18.00 40,700.00 732,600.00 0.27 - - - 12.60 512,820.00 0.19 12.60 512,820.00 0.19
Pas. Grendel Jendela Bh 18.00 46,200.00 831,600.00 0.30 - - - 12.60 582,120.00 0.21 12.60 582,120.00 0.21
Pas. Engsel Boven Bh 18.00 39,435.00 709,830.00 0.26 - - - - - - - -
Pas. Kait Angin Boven Bh 18.00 40,700.00 732,600.00 0.27 - - - - - - - -
Pas. Grendel Boven Bh 18.00 46,200.00 831,600.00 0.30 - - - - - - - -
27,270,324.40 9.94 3,766,730.00 1.37 11,740,042.60 4.28 15,506,772.60 5.65
VII Pekerjaan Lantai
Pek. Rabat Lantai Ram t = 5 cm, K-100 M3 3.20 894,455.00 2,862,256.00 1.04 3.20 2,862,256.00 1.04 - - 3.20 2,862,256.00 1.04
Pek. Lantai Keramik polish 40 x 40 cm M2 64.06 211,680.00 13,560,220.80 4.94 64.06 13,560,220.80 4.94 - - 64.06 13,560,220.80 4.94
Pek. Dinding Keramik unpolish 25 x 25 cm M2 15.60 180,935.00 2,822,586.00 1.03 15.60 2,822,586.00 1.03 - - 15.60 2,822,586.00 1.03
19,245,062.80 7.01 19,245,062.80 7.01 - - 19,245,062.80 7.01
VIII Pekerjaan Instalasi Listrik
Pas. Titik Lampu Titik 6.00 200,729.00 1,204,374.00 0.44 - - - 6.00 1,204,374.00 0.44 6.00 1,204,374.00 0.44
Pas. Panel MCB Bh 1.00 150,000.00 150,000.00 0.05 - - - 1.00 150,000.00 0.05 1.00 150,000.00 0.05
Pas. Meteran Listrik 900 W Bh 1.00 2,000,000.00 2,000,000.00 0.73 - - - 1.00 2,000,000.00 0.73 1.00 2,000,000.00 0.73
Pas. Stop Kontak Bh 5.00 106,590.00 532,950.00 0.19 - - - 5.00 532,950.00 0.19 5.00 532,950.00 0.19
Pas. Saklar Tunggal Bh 6.00 113,410.00 680,460.00 0.25 - - - 6.00 680,460.00 0.25 6.00 680,460.00 0.25
Pas. Saklar Ganda Bh 2.00 106,590.00 213,180.00 0.08 - - - 2.00 213,180.00 0.08 2.00 213,180.00 0.08
Lampu Bohlam LED 6 Watt Bh 2.00 40,000.00 80,000.00 0.03 - - - 2.00 80,000.00 0.03 2.00 80,000.00 0.03
Pas. Lampu LED Bohlam 12 Watt Bh 10.00 75,000.00 750,000.00 0.27 - - - 10.00 750,000.00 0.27 10.00 750,000.00 0.27
5,610,964.00 2.04 - - 5,610,964.00 2.04 5,610,964.00 2.04
IX Pekerjaan Sanitasi
Pek. Septictank dan Peresapan Unit 1.00 7,508,695.00 7,508,695.00 2.74 1.00 7,508,695.00 2.74 - - 1.00 7,508,695.00 2.74
Pek. Closet Jongkok Bh 1.00 571,703.00 571,703.00 0.21 1.00 571,703.00 0.21 - - 1.00 571,703.00 0.21
Pemasangan 1 buah closet duduk\/monoblock Bh 1.00 1,893,595.00 1,893,595.00 0.69 1.00 1,893,595.00 0.69 - - 1.00 1,893,595.00 0.69
Pek. Wastavel Bh 1.00 881,064.00 881,064.00 0.32 - - - 0.50 440,532.00 0.16 0.50 440,532.00 0.16
Pek. Floor Drain Bh 2.00 67,430.00 134,860.00 0.05 2.00 134,860.00 0.05 - - 2.00 134,860.00 0.05
Pek. Kran Air Bh 3.00 95,177.00 285,531.00 0.10 3.00 285,531.00 0.10 - - 3.00 285,531.00 0.10
Pemasangan 1 Unit Tower lengkap dengan Profil tank unit 1.00 10,432,587.00 10,432,587.00 3.80 - - - 0.50 5,216,293.50 1.90 0.50 5,216,293.50 1.90
Pek. Instalasi Air Kotor Ls 1.00 750,000.00 750,000.00 0.27 - - - 0.70 525,000.00 0.19 0.70 525,000.00 0.19
Pek. Instalasi Air Bersih Ls 1.00 750,000.00 750,000.00 0.27 - - - 0.70 525,000.00 0.19 0.70 525,000.00 0.19
23,208,035.00 8.46 10,394,384.00 3.79 6,706,825.50 2.44 17,101,209.50 6.23
X Pekerjaan Finishing
Pek. Cat Woodplank M2 14.73 45,133.00 664,809.09 0.24 14.73 664,809.09 0.24 - - 14.73 664,809.09 0.24
Pek. Cat Plafond M2 104.06 28,259.00 2,940,631.54 1.07 104.06 2,940,631.54 1.07 - - 104.06 2,940,631.54 1.07
Pek. Cat Tembok dan Kolom M2 341.12 17,015.00 5,804,156.80 2.11 341.12 5,804,156.80 2.11 - - 341.12 5,804,156.80 2.11
Pek. Cat Seng M2 130.27 14,157.00 1,844,232.39 0.67 - - - 130.27 1,844,232.39 0.67 130.27 1,844,232.39 0.67
Pek. Cat Kusen Kayu M2 65.20 45,133.00 2,942,671.60 1.07 - - - 65.20 2,942,671.60 1.07 65.20 2,942,671.60 1.07
Pek. Vernis Daun Pintu Panil Papan M2 12.52 48,752.00 610,375.04 0.22 - - - - - - - -
Jumlah X 14,806,876.46 5.39 9,409,597.43 3.43 4,786,903.99 1.74 14,196,501.42 5.17
TOTAL I+II+III+IV+V+VI+VII+VIII+IX+X 274,477,477.48 100.00 222,053,639.42 80.90 29,055,262.41 10.59 251,108,901.82 91.49
BOBOT TERHADAP KONTRAK 50.00 40.45 5.29 45.74

Anda mungkin juga menyukai