REKAPITULASI ANGGARAN BIAYA

Nama Kegiatan : PEMBANGUNAN SARANA DAN PRASARANA KELURAHAN


Nama Pekerjaan : PEMBUATAN JARINGAN AIR BERSIH KELURAHAN TEGALREJO
Lokasi : KELURAHAN TEGALREJO
Tahun : 2023
JUMLAH HARGA TOTAL HARGA
NO JENIS PEKERJAAN
(Rp.) (Rp.)

A PEKERJAAN PERSIAPAN 2,800,000.00 2,800,000.00

B PEMBUATAN INTAKE 9,499,124.34 9,499,124.34

C INSTALASI PERPIPAAN DAN ACCESSORIES 111,716,194.30 111,716,194.30

E PEKERJAAN AKHIR 252,272.73 252,272.73

TOTAL PEKERJAAN Rp 124,267,591.37


PPN 11% Rp 13,669,435.05
JUMLAH TOTAL Rp 137,937,026.42
DIBULATKAN Rp 137,937,000.00

Terbilang : Seratus Tiga Puluh Tujuh Juta Sembilan Ratus Tiga Puluh Tujuh Ribu Rupiah

POSO,…………………………….. 2023

CV. FATAHILLAH KONSTRUKSI 88

…………………………………………
Direktur
ESTIMATE ENGINEERING (EE)
PEMBUATAN JARINGAN AIR BERSIH KELURAHAN TEGALREJO
TAHUN ANGGARAN 2023

HARGA JUMLAH HARGA PAJAK JUMLAH


NO. URAIAN PEKERJAAN SAT VOL TOTAL (Rp.)
SATUAN (Rp.) (Rp.) (%) PAJAK (%)
1 2 3 4 Harga5satuan 6 7 8 9
Jenis barang/jasa Satuan Volume Pajak (%) Pajak (Rp.) Total (Rp.)
(Rp.)
A PEKERJAAN PERSIAPAN 3,108,000.00
1 Pembersihan Lokasi Pekerjaan Ls 1.00 2,500,000.00 2,500,000.00 11.00 275,000.00 2,775,000.00
2 Pemasangan Papan Proyek Ls 1.00 300,000.00 300,000.00 11.00 33,000.00 333,000.00

B PEMBUATAN INTAKE 10,544,028.02

1 Galian Tanah M3 1.80 86,625.00 155,925.00 11.00 17,151.75 173,076.75


2 Pembesian Kg 48.74 21,898.25 1,067,320.71 11.00 117,405.28 1,184,725.98
3 Bekesting M2 5.68 332,207.70 1,886,939.74 11.00 207,563.37 2,094,503.11
4 Beton cor Camp 1 : 2 : 3 M3 0.65 1,249,772.42 812,352.07 11.00 89,358.73 901,710.80
5 Pasangan Batu Camp 1 : 3 M3 4.10 1,027,482.50 4,212,678.25 11.00 463,394.61 4,676,072.86
6 Plesteran 1 : 3 M2 11.22 76,468.26 858,307.28 11.00 94,413.80 952,721.08
7 Acian M2 11.22 45,045.00 505,601.30 11.00 55,616.14 561,217.44

C INSTALASI PERPIPAAN DAN ACCESSORIES 124,004,975.68

1 Pipa Gip ø 4" M' 15.00 285,681.24 4,285,218.60 11.00 471,374.05 4,756,592.65
2 Pipa PVC ø 4" M' 84.00 188,344.06 15,820,901.25 11.00 1,740,299.14 17,561,200.39
3 Pipa PVC ø 3" M' 100.00 155,612.19 15,561,218.75 11.00 1,711,734.06 17,272,952.81
4 Pipa PVC ø 2" M' 158.00 131,972.50 20,851,655.00 11.00 2,293,682.05 23,145,337.05
5 Pipa PVC ø 1" M' 643.00 77,806.09 50,029,318.28 11.00 5,503,225.01 55,532,543.29
6. Over Shock ø 4 - 3 " Bh 1.00 65,986.25 65,986.25 11.00 7,258.49 73,244.74
7 Over Shock ø 3 - 2 " Bh 1.00 38,903.05 38,903.05 11.00 4,279.34 43,182.38
8 Over Shock ø 2 - 1 " Bh 1.00 32,993.13 32,993.13 11.00 3,629.24 36,622.37
9 Gate Valve ø 3" Bh 1.00 1,800,000.00 1,800,000.00 11.00 198,000.00 1,998,000.00
10 Gate Valve ø 4" Bh 1.00 2,780,000.00 2,780,000.00 11.00 305,800.00 3,085,800.00
11 Baut Bh 10.00 45,000.00 450,000.00 11.00 49,500.00 499,500.00

E PEKERJAAN AKHIR 2,775,000.00

1 Pembersihan Akhir Ls 1.00 1,000,000.00 1,000,000.00 11.00 110,000.00 1,110,000.00


2 Laporan dan Dokumentasi Ls 1.00 1,500,000.00 1,500,000.00 11.00 165,000.00 1,665,000.00