Terbilang : Seratus Tiga Puluh Tujuh Juta Sembilan Ratus Tiga Puluh Tujuh Ribu Rupiah
POSO,…………………………….. 2023
…………………………………………
Direktur
ESTIMATE ENGINEERING (EE)
PEMBUATAN JARINGAN AIR BERSIH KELURAHAN TEGALREJO
TAHUN ANGGARAN 2023
1 Pipa Gip ø 4" M' 15.00 285,681.24 4,285,218.60 11.00 471,374.05 4,756,592.65
2 Pipa PVC ø 4" M' 84.00 188,344.06 15,820,901.25 11.00 1,740,299.14 17,561,200.39
3 Pipa PVC ø 3" M' 100.00 155,612.19 15,561,218.75 11.00 1,711,734.06 17,272,952.81
4 Pipa PVC ø 2" M' 158.00 131,972.50 20,851,655.00 11.00 2,293,682.05 23,145,337.05
5 Pipa PVC ø 1" M' 643.00 77,806.09 50,029,318.28 11.00 5,503,225.01 55,532,543.29
6. Over Shock ø 4 - 3 " Bh 1.00 65,986.25 65,986.25 11.00 7,258.49 73,244.74
7 Over Shock ø 3 - 2 " Bh 1.00 38,903.05 38,903.05 11.00 4,279.34 43,182.38
8 Over Shock ø 2 - 1 " Bh 1.00 32,993.13 32,993.13 11.00 3,629.24 36,622.37
9 Gate Valve ø 3" Bh 1.00 1,800,000.00 1,800,000.00 11.00 198,000.00 1,998,000.00
10 Gate Valve ø 4" Bh 1.00 2,780,000.00 2,780,000.00 11.00 305,800.00 3,085,800.00
11 Baut Bh 10.00 45,000.00 450,000.00 11.00 49,500.00 499,500.00