REKAPITULASI ANGGARAN BIAYA

Nama Kegiatan : PEMBANGUNAN SARANA DAN PRASARANA KELURAHAN


Nama Pekerjaan : PEMBUATAN JARINGAN AIR BERSIH KELURAHAN TEGALREJO
Lokasi : KELURAHAN TEGALREJO
Tahun : 2023
JUMLAH HARGA TOTAL HARGA
NO JENIS PEKERJAAN
(Rp.) (Rp.)

A PEKERJAAN PERSIAPAN 2,800,000.00 2,800,000.00

B PEMBUATAN INTAKE 9,499,124.34 9,499,124.34

C INSTALASI PERPIPAAN DAN ACCESSORIES 111,716,194.30 111,716,194.30

E PEKERJAAN AKHIR 252,272.73 252,272.73

TOTAL PEKERJAAN Rp 124,267,591.37


PPN 11% Rp 13,669,435.05
JUMLAH TOTAL Rp 137,937,026.42
DIBULATKAN Rp 137,937,000.00

Terbilang : Seratus Tiga Puluh Tujuh Juta Sembilan Ratus Tiga Puluh Tujuh Ribu Rupiah

POSO,………………….. 2023

CV. FATAHILLAH KONSTRUKSI 88

NADIA AMALIA
Direktris
ESTIMATE ENGINEERING (EE)
Nama Kegiatan : PEMBANGUNAN SARANA DAN PRASARANA KELURAHAN

Nama Pekerjaan : PEMBUATAN JARINGAN AIR BERSIH KELURAHAN TEGALREJO

Lokasi : KELURAHAN TEGALREJO

Tahun Anggaran : 2023

HARGA JUMLAH PAJAK JUMLAH


NO. URAIAN PEKERJAAN SAT VOL TOTAL (Rp.)
SATUAN (Rp.) HARGA (Rp.) (%) PAJAK (%)

1 2 3 4 Harga5satuan 6 7 8 9
Jenis barang/jasa Satuan Volume Pajak (%) Pajak (Rp.) Total (Rp.)
(Rp.)
A PEKERJAAN PERSIAPAN 3,108,000.00
1 Pembersihan Lokasi Pekerjaan Ls 1.00 2,500,000.00 2,500,000.00 11.00 275,000.00 2,775,000.00
2 Pemasangan Papan Proyek Ls 1.00 300,000.00 300,000.00 11.00 33,000.00 333,000.00

B PEMBUATAN INTAKE 10,544,028.02

1 Galian Tanah M3 1.80 86,625.00 155,925.00 11.00 17,151.75 173,076.75


2 Pembesian Kg 48.74 21,898.25 1,067,320.71 11.00 117,405.28 1,184,725.98
3 Bekesting M2 5.68 332,207.70 1,886,939.74 11.00 207,563.37 2,094,503.11
4 Beton cor Camp 1 : 2 : 3 M 3
0.65 1,249,772.42 812,352.07 11.00 89,358.73 901,710.80
5 Pasangan Batu Camp 1 : 3 M3 4.10 1,027,482.50 4,212,678.25 11.00 463,394.61 4,676,072.86
6 Plesteran 1 : 3 M2 11.22 76,468.26 858,307.28 11.00 94,413.80 952,721.08
7 Acian M 2
11.22 45,045.00 505,601.30 11.00 55,616.14 561,217.44

C INSTALASI PERPIPAAN DAN ACCESSORIES 124,004,975.68

1 Pipa Gip ø 4" M '


15.00 285,681.24 4,285,218.60 11.00 471,374.05 4,756,592.65
2 Pipa PVC ø 4" M' 84.00 188,344.06 15,820,901.25 11.00 1,740,299.14 17,561,200.39
3 Pipa PVC ø 3" M' 100.00 155,612.19 15,561,218.75 11.00 1,711,734.06 17,272,952.81
4 Pipa PVC ø 2" M' 158.00 131,972.50 20,851,655.00 11.00 2,293,682.05 23,145,337.05
5 Pipa PVC ø 1" M' 643.00 77,806.09 50,029,318.28 11.00 5,503,225.01 55,532,543.29
6. Over Shock ø 4 - 3 " Bh 1.00 65,986.25 65,986.25 11.00 7,258.49 73,244.74
7 Over Shock ø 3 - 2 " Bh 1.00 38,903.05 38,903.05 11.00 4,279.34 43,182.38
8 Over Shock ø 2 - 1 " Bh 1.00 32,993.13 32,993.13 11.00 3,629.24 36,622.37
9 Gate Valve ø 3" Bh 1.00 1,800,000.00 1,800,000.00 11.00 198,000.00 1,998,000.00
10 Gate Valve ø 4" Bh 1.00 2,780,000.00 2,780,000.00 11.00 305,800.00 3,085,800.00
11 Baut Bh 10.00 45,000.00 450,000.00 11.00 49,500.00 499,500.00

E PEKERJAAN AKHIR 2,775,000.00

1 Pembersihan Akhir Ls 1.00 1,000,000.00 1,000,000.00 11.00 110,000.00 1,110,000.00


2 Laporan dan Dokumentasi Ls 1.00 1,500,000.00 1,500,000.00 11.00 165,000.00 1,665,000.00