REKAPITULASI
HARGA
NO. URAIAN PEKERJAAN
( Rp )
HARGA JUMLAH
No. URAIAN PEKERJAAN VOLUME SAT
SATUAN (Rp) HARGA (Rp)
1 2 3 4 5 6
A. UPAH
1 Pekerja OH 100.000,00
2 Tukang Kayu OH 152.250,00
3 Tukang Batu OH 152.250,00
4 Tukang Gali OH 152.250,00
5 Tukang Besi / Alluminium OH 152.250,00
6 Tukang Listrik OH 152.250,00
7 Tukang Cat OH 152.250,00
8 Kepala Tukang OH 162.750,00
9 Mandor OH 189.000,00
B. BAHAN PASIR DAN BATU
1 Pasir Pasang M3 220.500,00
2 Pasir beton M3 295.500,00
3 Batu tela @ 10x18x27 Bh 3.900,00
4 Citicon Block @ 60x20x7,5 Bh 19.200,00
5 Tanah Timbunan M3 196.500,00
6 Kerikil 2/3 M3 697.000,00
7 Pasir Urug M3 220.500,00
8 Sirtu M3 277.500,00
9 Batu Kali M3 262.500,00
C. BAHAN KAYU
1 Balok Kayu Besi M3 5.300.000,00
2 Papan Kayu Besi M3 5.300.000,00
3 Balok Kayu Matoa M3 2.600.000,00
4 Papan Kayu Matoa M3 2.600.000,00
5 Balok Kayu Putih M3 2.600.000,00
6 Papan Kayu Putih/ bekesting M3 2.600.000,00
7 Dolken Kayu Diameter 8 - 10/ 400 cm Btg 58.075,00
8 List Dinding Profil Kayu M 58.500,00
D. BAHAN TOKO
1 Wallpaper Motif M2 95.000,00
2 HPL M2 53.000,00
3 Lem Perekat Kg 12.000,00
4 Sekrup Fischer Bh 18.000,00
5 Sealant Tube 25.000,00
6 Kaca Ryben 5 mm M2 453.945,00
7 Sticker Kaca / Sandblast M2 166.666,67
8 Closing Door Set 490.000,00
9 Flooring Door / Engsel tanam Set 350.000,00
10 Engsel Pintu Bh 60.375,00
11 Engsel Jendela Bh 33.690,00
12 Engsel Jendela Aluminium M 84.500,00
13 Kunci Tanam Bh 268.750,00
14 Hak Angin Psg 25.833,00
15 Besi beton Dia. 10mm, ( 11m = 6,787 Kg ) Kg 20.480,00
16 Kawat ikat beton Kg 103.000,00
17 Paku biasa / campuran Kg 21.333,00
18 Sekrup / Paku Gypsum Kg 65.625,00
19 Gypsum (120 x 240) Cm, Tebal 9 mm Lbr 131.250,00
20 Gypsum Board (120 x 240) Cm, Tebal 9 mm Lbr 120.000,00
21 Tepung Gypsum (UB 88) Kg 110.800,00
23 Plywood 9 mm Lbr 177.067,00
24 Lem Kayu Kg 64.000,00
25 Lampu Philips TL 1x18 Watt Bh 91.350,00
26 Lampu Philips TL 1x100 Watt Bh 60.000,00
27 Lampu tanam SL 8 Watt Bh 41.250,00
28 Fitting Hias (Down Light) Bh 60.500,00
29 Stop Kontak 3 Mata Bh 42.419,00
30 Saklar Ganda / Kombinasi Stop Kontak Bh 30.000,00
31 Pipa Listrik 3/8" btg 43.999,98
32 Asesoris Listrik Set 25.000,00
33 Pipa PVC 1/2" Type AW M 5.520,83
34 Pipa PVC 2" Type AW M 19.791,67
35 Pipa PVC 4" Type AW M 64.583,33
36 Kran Air 1/2" + ACC Bh 70.400,00
37 Seal Tape Bh 11.667,00
38 Floor Drain Bh 43.750,00
39 Atap genteng metal lbr 85.750,00
40 Atap Multi roof Lbr 41.000,00
41 Atap Sakura Roof Lbr 41.000,00
42 Atap Spandex Lbr 445.000,00
43 Besi Strip 50.5x0.25 m Bh 10.937,00
44 Besi siku 20.20-3-6m Btg 39.770,00
45 Besi siku 30.30 3.6m Btg 107.500,00
46 Besi siku 40.40 4.6m Btg 150.500,00
47 Besi siku 40.40 5.6m Btg 118.258,00
48 Besi siku 50.50 4.6m Btg 215.000,00
49 Besi siku 50.50-5-6m Btg 220.370,00
50 Besi siku 60.60-6.6m Btg 382.700,00
51 Besi siku 100.100-10-6m Btg 1.347.500,00
52 Besi Beton Macam-macam Ukuran Kg 20.480,00
53 Box sekering 2 group + ACC set 78.484,00
54 Box sekering 4 group bh 33.320,00
55 Box sekering 8 group bh 59.120,00
56 Box sekering 1 group bh 78.487,00
57 sekering Khas 1 Group bh 38.700,00
58 sekering Khas 2 Group bh 57.000,00
59 sekering Khas 3 Group bh 79.570,00
60 Cat Dulux Weather Shield kg 65.000,00
61 Cat Tembok Biasa kg 23.125,00
62 Cat Besi kg 81.250,00
63 Cat minyak kayu/ Junior 88 kg 81.250,00
64 Cat plafond kg 29.973,00
65 Cat plamur tembok kg 57.000,00
66 Cat Genteng/ Atap Kg 39.375,00
67 Closet duduk Lux - Ex Toto bh 3.008.000,00
68 Closet jongkok bh 302.083,00
69 Dolken (buah) 4 meter m3 2.500.000,00
70 Dolken (buah) 4 meter btg 58.075,00
71 Door closed bh 125.000,00
72 Door stop bh 50.000,00
73 Daun Pintu Alumunium + Kaca 1cm Set 6.500.000,00
74 Daun Pintu Kaca 5'' set 3.100.000,00
75 Daun Jendela Alumunium + Kaca 3'' set 820.000,00
76 Daun Pintu Kaca 5'' set 3.100.002,00
77 Daun Jalusi Alumunium + Kaca 3'' set 500.000,00
78 Floor drain bh 43.750,00
79 Grendel jendela buka bh 33.690,00
80 Grendel pintu double psg 64.375,00
81 Gypsum board 9 mm lbr 110.080,00
82 Hak angin psg 25.883,00
83 Handle pintu bh 177.417,00
84 Kabel NYM 2 x 2,5 mm m' 14.213,00
85 Kabel NYM 2 x 1,5 mm m' 13.227,00
86 Kabel NYM 3 x 2,5 mm m' 18.693,00
87 Kabel NYM 3 x 1,5 mm m' 14.640,00
88 Kabel NYY 4 x 1,6 mm putih m' 73.000,00
89 Klem Kabel Bngks 17.000,00
90 Kap Lampu/Viting Bh 27.896,00
91 Kaca cermin 5mm m2 113.920,00
92 Kaca Bening 5 mm m2 348.750,00
93 Kaca Riben 5 mm m2 363.750,00
94 Kawat Harmonika m' 75.200,00
95 Kawat nyamuk besi m' 53.646,00
96 Kawat nyamuk plastik m' 37.620,00
97 Kawat beton kg 103.000,00
98 Keramik 20/20 m2 4.125,00
99 Keramik 20/25 m2 8.593,75
100 Keramik 30/30 m2 8.901,55
101 Keramik 40/40 m2 26.562,50
102 Kerikil agregat beton m3 757.000,00
103 Kertas gosok lbr 20.171,00
104 Kran air + ACC bh 59.000,00
105 Kunci cilynder set 140.000,00
106 Kunci Tanam merk Royal 1 x slaag atau setera Bh 150.000,00
107 Kunci tanam 2 slaag ex. Yalee set 383.400,00
108 Kitchen Zink,Royal SB9 1 lubang lengkap Bh 430.000,00
109 Kitchen Zink,Royal SB1, 1 lubang lengkap Bh 344.000,00
110 Kitchen Zink, royal SB2, 2 Lubang Lengkap Bh 913.750,00
111 Kusen Alumunium Silver M1 180.000,00
112 Kusen Alumunium Coklat M1 200.000,00
113 Kwas Segala Ukuran bh 25.000,00
114 Kwas Roll bh 43.750,00
115 4 klip zet 103.200,00
116 5 klip zet 128.000,00
117 6 klip zet 154.800,00
118 7 klip zet 180.600,00
119 8 klip zet 206.400,00
120 9 klip zet 232.200,00
121 10 klip zet 258.000,00
122 Kaca Lover Bening Lbr 12.900,00
123 Kaca Lover Riben Lbr 16.120,00
124 Lampu TL 20 Watt Bh 91.000,00
125 Lampu TL 40 Watt Bh 60.800,00
126 Lampu SL 25 Watt Bh 67.413,00
127 Lampu SL 40 Watt Bh 67.413,00
128 Lampu Halogen 50 Watt lengkap fitting down light ( terpasang ) Bh 125.000,00
129 Lampu SL 11-14 watt Philips bh 47.000,00
130 Lampu SL 18 watt Philips bh 56.000,00
131 Lampu Pijar 1x60 bh 11.820,00
132 Lampu Pijar 1x100 bh 12.900,00
133 Lampu Baret bh 535.000,00
134 Lem Fox kuning kg 93.013,00
135 List Plafond m' 27.250,00
136 Multipleks 6mm Lbr 130.133,00
137 Multipleks 12mm Lbr 161.250,00
138 Multipleks 15mm Lbr 228.570,00
139 Multipleks 18mm Lbr 280.190,00
140 Minyak bekisting ltr 25.200,00
141 Minyak Cat/ Thinner ltr 54.719,00
142 Meni Kayu Kg 41.667,00
143 Nok atap genteng metal m' 43.947,00
144 Paku aluminium kg 20.000,00
145 Paku campur kg 25.000,00
146 Paku seng kg 58.333,00
147 Paku tripleks kg 36.250,00
148 Paving Blok Segi 6 kg 4.375,00
149 Pipa GIP medium A dia 1/2 m' 26.042,00
150 Pipa GIP medium A dia 3/4 m' 33.333,00
151 Pipa PVC AW Diameter 2" m' 28.645,00
152 Pipa PVC AW Diameter 3" m' 38.541,00
153 Pipa PVC AW Diameter 4" m' 64.583,00
154 Polytur kg 102.083,00
155 Plamir Kayu/Wood filler kg 62.500,00
156 Plywood 9 mm Lbr 177.067,00
157 Plywood 6 mm Lbr 98.000,00
158 Residu/ Teer ltr 10.653,00
159 Saklar ganda set 30.000,00
160 Saklar tunggal set 25.083,00
161 Sekrup Pixer bh 7.500,00
162 Sekrup gypsum kg 65.625,00
163 Semen PC kg 5.625,00
164 Semen PC 50 kg zak 104.188,00
165 Semen warna kg 24.747,00
166 Seng Gelombang BJLS 0.3 lbr 89.279,00
167 Seng plat Bjls 0,30 lbr 77.500,00
168 Seng Aluminium 0.5mm Lbr 129.000,00
169 Seng Aluminium 0.8mm Lbr 195.000,00
170 Seng Galvanis 80x180 cm Lbr 129.000,00
171 Sealant bh 75.000,00
172 Stop kontak bh 40.419,00
173 Teakwood (122 x 244) cm lbr 125.000,00
174 Tripleks 3 mm lbr 74.000,00
175 Tripleks 6 mm lbr 122.600,00
176 Wastafel + ACC bh 718.750,00
177 Kasa Gipsun Roll 10.000,00
178 UB 888 Gypsun Kg 2.458,00
179 Alkasit Kg 12.000,00
180 Paku Gypsun Kg 65.625,00
181 List Profil Gypsun (Lebar 5 cm) M1 62.500,00
182 Engsel Kupu-kupu Nylon (pintu) Bh 61.375,00
183 Engsel Kupu-kupu Nylon (Jendela) Bh 31.690,00
184 Hak angin stell Bh 21.833,00
185 Grendel tanam ( untuk pintu) Bh 91.147,00
186 Grendel biasa (untuk jendela) Bh 40.771,00
187 Limit Khusus AC Bh 95.147,00
1 1,00 M2 Pembersihan Lokasi
Harga Satuan Jumlah Harga
Kebutuhan Satuan Index
Bahan Upah Bahan Upah
A. BAHAN
-
TOTAL BIAYA BAHAN -
Pekerja OH 0,1000 100.000,00 - 10.000,00
B. TENAGA
Mandor OH 0,03000 189.000,00 - 5.670,00
TOTAL UPAH TENAGA 15.670,00
C. PERALATAN
-
TOTAL BIAYA PERALATAN -
D. Total upah tenaga, biaya material dan peralatan (A+B+C) 15.670,00
E. Overhead + Profit 10 %xD 1.567,00
F. Harga Satuan Pekerjaan (D+E) 17.237,00
C. PERALATAN
-
TOTAL BIAYA PERALATAN -
D. Total upah tenaga, biaya material dan peralatan (A+B+C) 62.649,16
E. Overhead + Profit 10 %xD 6.264,92
F. Harga Satuan Pekerjaan (D+E) 68.914,08
A. BAHAN
-
TOTAL BIAYA BAHAN -
Pekerja o/h 1,0500 100.000,00 105.000,00
B. TENAGA
Mandor o/h 0,0320 189.000,00 6.048,00
TOTAL UPAH TENAGA 111.048,00
C. PERALATAN
-
TOTAL BIAYA PERALATAN -
D. Total upah tenaga, biaya material dan peralatan (A+B+C) 111.048,00
E. Overhead + Profit 10 %xD 11.104,80
F. Harga Satuan Pekerjaan (D+E) 122.152,80
C. PERALATAN
-
TOTAL BIAYA PERALATAN -
D. Total upah tenaga, biaya material dan peralatan (A+B+C) 238.215,00
E. Overhead + Profit 10 %xD 23.821,50
F. Harga Satuan Pekerjaan (D+E) 262.036,50
5 1,00 M3 Pek. Pas. Pondasi Batu Kali 1 : 4
Harga Satuan Jumlah Harga
Kebutuhan Satuan Index
Bahan Upah Bahan Upah
Batu Kali M3 1,050 262.500,00 275.625,00
A. BAHAN Pasir Pasang M3 0,500 220.500,00 110.250,00
Semen PC kg 160,000 5.625,00 900.000,00
TOTAL BIAYA BAHAN 1.285.875,00
Tukang Batu o/h 0,650 152.250,00 98.962,50
Kepala Tukang o/h 0,075 162.750,00 12.206,25
B. TENAGA
Pekerja o/h 1,300 100.000,00 130.000,00
Mandor o/h 0,075 189.000,00 14.175,00
TOTAL UPAH TENAGA 255.343,75
C. PERALATAN
-
TOTAL BIAYA PERALATAN -
D. Total upah tenaga, biaya material dan peralatan (A+B+C) 1.541.218,75
E. Overhead + Profit 10 %xD 154.121,88
F. Harga Satuan Pekerjaan (D+E) 1.695.340,63
C. PERALATAN
-
TOTAL BIAYA PERALATAN -
D. Total upah tenaga, biaya material dan peralatan (A+B+C) 8.210.041,25
E. Overhead + Profit 10 %xD 821.004,13
F. Harga Satuan Pekerjaan (D+E) 9.031.045,38
C. PERALATAN
-
TOTAL BIAYA PERALATAN -
D. Total upah tenaga, biaya material dan peralatan (A+B+C) 8.368.316,25
E. Overhead + Profit 10 % x D 836.831,63
F. Harga Satuan Pekerjaan (D+E) 9.205.147,88
C. PERALATAN
-
TOTAL BIAYA PERALATAN -
D. Total upah tenaga, biaya material dan peralatan (A+B+C) 8.825.066,25
E. Overhead + Profit 10 %xD 882.506,63
F. Harga Satuan Pekerjaan (D+E) 9.707.572,88
9 1,00 M2 Pek. Lantai Papan Kayu Besi di Ketam
Harga Satuan Jumlah Harga
Kebutuhan Satuan Index
Bahan Upah Bahan Upah
Ky. Klass I, Papan Kayu Besi 2/20 (diketam) M3 0,0203 5.300.000,00 107.590,00
A. BAHAN
Paku campur Kg 0,2000 21.333,00 4.266,60
TOTAL BIAYA BAHAN 111.856,60
Pekerja o/h 0,6000 100.000,00 60.000,00
Tukang Kayu o/h 1,5000 152.250,00 228.375,00
B. TENAGA
Kepala Tukang o/h 0,3000 162.750,00 48.825,00
Mandor o/h 0,0750 189.000,00 14.175,00
TOTAL UPAH TENAGA 351.375,00
C. PERALATAN
-
TOTAL BIAYA PERALATAN -
D. Total upah tenaga, biaya material dan peralatan (A+B+C) 463.231,60
E. Overhead + Profit 10 % x D 46.323,16
F. Harga Satuan Pekerjaan (D+E) 509.554,76
C. PERALATAN
-
TOTAL BIAYA PERALATAN -
D. Total upah tenaga, biaya material dan peralatan (A+B+C) 119.170,75
E. Overhead + Profit 10 %xD 11.917,08
F. Harga Satuan Pekerjaan (D+E) 131.087,83
C. PERALATAN
-
TOTAL BIAYA PERALATAN -
D. Total upah tenaga, biaya material dan peralatan (A+B+C) 5.756.503,75
E. Overhead + Profit 10 % x D 575.650,38
F. Harga Satuan Pekerjaan (D+E) 6.332.154,13
C. PERALATAN
-
TOTAL BIAYA PERALATAN -
D. Total upah tenaga, biaya material dan peralatan (A+B+C) 859.025,00
E. Overhead + Profit 10 %xD 85.902,50
F. Harga Satuan Pekerjaan (D+E) 944.927,50
13 1,00 Bh Memasang Kunci Tanam 2 Slaag
Harga Satuan Jumlah Harga
Kebutuhan Satuan Index
Bahan Upah Bahan Upah
A. BAHAN Kunci Tanam Union 2 Slaag Bh 1,0000 268.750,00 268.750,00
TOTAL BIAYA BAHAN 268.750,00
Pekerja OH 0,0100 100.000,00 - 1.000,00
Tukang Besi / Alluminium OH 0,5000 152.250,00 - 76.125,00
B. TENAGA
Kepala Tukang OH 0,0100 162.750,00 - 1.627,50
Mandor OH 0,0050 189.000,00 - 945,00
TOTAL UPAH TENAGA 79.697,50
C. PERALATAN
-
TOTAL BIAYA PERALATAN -
D. Total upah tenaga, biaya material dan peralatan (A+B+C) 348.447,50
E. Overhead + Profit 10 %xD 34.844,75
F. Harga Satuan Pekerjaan (D+E) 383.292,25
C. PERALATAN
-
TOTAL BIAYA PERALATAN -
D. Total upah tenaga, biaya material dan peralatan (A+B+C) 87.295,50
E. Overhead + Profit 10 %xD 8.729,55
F. Harga Satuan Pekerjaan (D+E) 96.025,05
C. PERALATAN
-
TOTAL BIAYA PERALATAN -
D. Total upah tenaga, biaya material dan peralatan (A+B+C) 100.269,00
E. Overhead + Profit 10 %xD 10.026,90
F. Harga Satuan Pekerjaan (D+E) 110.295,90
C. PERALATAN
-
TOTAL BIAYA PERALATAN -
D. Total upah tenaga, biaya material dan peralatan (A+B+C) 8.209.786,48
E. Overhead + Profit 10 % x D 820.978,65
F. Harga Satuan Pekerjaan (D+E) 9.030.765,13
17 1,00 M3 Pek.Memasang Gording Ky. Matoa 5/10
Harga Satuan Jumlah Harga
Kebutuhan Satuan Index
Bahan Upah Bahan Upah
Kayu Matoa 5/10 M3 1,0500 2.600.000,00 2.730.000,00
A. BAHAN
Paku campur Kg 3,0000 21.333,00 63.999,00
TOTAL BIAYA BAHAN 2.793.999,00
Pekerja o/h 2,4000 100.000,00 240.000,00
Tukang Kayu o/h 6,2000 152.250,00 943.950,00
B. TENAGA
Kepala Tukang o/h 0,7200 162.750,00 117.180,00
Mandor o/h 0,1200 189.000,00 22.680,00
TOTAL UPAH TENAGA 1.323.810,00
C. PERALATAN
-
TOTAL BIAYA PERALATAN -
D. Total upah tenaga, biaya material dan peralatan (A+B+C) 4.117.809,00
E. Overhead + Profit 10 % x D 411.780,90
F. Harga Satuan Pekerjaan (D+E) 4.529.589,90
C. PERALATAN
-
TOTAL BIAYA PERALATAN -
D. Total upah tenaga, biaya material dan peralatan (A+B+C) 102.106,15
E. Overhead + Profit 10 %xD 10.210,62
F. Harga Satuan Pekerjaan (D+E) 112.316,77
19 1,00 M' Pek. Atap Gelombang BJLS 30 Total 117.330,15 74.161,90 43.168,25
Harga Satuan Jumlah Harga
Kebutuhan Satuan Index
Bahan Upah Bahan Upah
Atap BJLS 30 M3 0,7000 89.279,00 62.495,30
A. BAHAN
Paku Seng Kg 0,2000 58.333,00 11.666,60
TOTAL BIAYA BAHAN 74.161,90
Pekerja o/h 0,2000 100.000,00 20.000,00
Tukang Kayu o/h 0,1200 152.250,00 18.270,00
B. TENAGA
Kepala Tukang o/h 0,0150 162.750,00 2.441,25
Mandor o/h 0,0130 189.000,00 2.457,00
TOTAL UPAH TENAGA 43.168,25
C. PERALATAN
-
TOTAL BIAYA PERALATAN -
D. Total upah tenaga, biaya material dan peralatan (A+B+C) 117.330,15
E. Overhead + Profit 10 %xD 11.733,02
F. Harga Satuan Pekerjaan (D+E) 129.063,17
C. PERALATAN
-
TOTAL BIAYA PERALATAN -
D. Total upah tenaga, biaya material dan peralatan (A+B+C) 55.338,63
E. Overhead + Profit 10 %xD 5.533,86
F. Harga Satuan Pekerjaan (D+E) 60.872,49
21 1,00 Titik Pasang Intalasi LIstrik & Aksesoris
Harga Satuan Jumlah Harga
Kebutuhan Satuan Index
Bahan Upah Bahan Upah
Pipa Listrik 3/8" Btg 0,5000 43.999,98 21.999,99 -
A. BAHAN Kabel NYM 2 x 2,5 mm M' 10,0000 14.213,00 142.130,00 -
Acsesoris Ls 1,0000 25.000,00 25.000,00 -
TOTAL BIAYA BAHAN 189.129,99
Pekerja OH 0,5000 100.000,00 - 50.000,00
Tukang Listrik OH 0,5000 152.250,00 - 76.125,00
B. TENAGA
Kepala Tukang OH 0,0500 162.750,00 - 8.137,50
Mandor OH 0,02500 189.000,00 - 4.725,00
TOTAL UPAH TENAGA 138.987,50
C. PERALATAN
-
TOTAL BIAYA PERALATAN -
D. Total upah tenaga, biaya material dan peralatan (A+B+C) 328.117,49
E. Overhead + Profit 10 %xD 32.811,75
F. Harga Satuan Pekerjaan (D+E) 360.929,24
C. PERALATAN
-
TOTAL BIAYA PERALATAN -
D. Total upah tenaga, biaya material dan peralatan (A+B+C) 531.900,00
E. Overhead + Profit 10 %xD 53.190,00
F. Harga Satuan Pekerjaan (D+E) 585.090,00
C. PERALATAN
-
TOTAL BIAYA PERALATAN -
D. Total upah tenaga, biaya material dan peralatan (A+B+C) 452.670,48
E. Overhead + Profit 10 % x D 45.267,05
F. Harga Satuan Pekerjaan (D+E) 497.937,53
C. PERALATAN
-
TOTAL BIAYA PERALATAN -
D. Total upah tenaga, biaya material dan peralatan (A+B+C) 457.587,48
E. Overhead + Profit 10 % x D 45.758,75
F. Harga Satuan Pekerjaan (D+E) 503.346,23
25 1,00 Bh Pasang Stop Kontak
Harga Satuan Jumlah Harga
Kebutuhan Satuan Index
Bahan Upah Bahan Upah
Stop Kontak Bh 1,0000 40.419,00 40.419,00 -
Kbl NYM 3x2.5 mm Btg 1,0000 18.693,00 18.693,00 -
A. BAHAN
Pipa Listrik 3/8" M' 4,0000 43.999,98 175.999,92
Acsesoris Ls 1,0000 25.000,00 25.000,00 -
TOTAL BIAYA BAHAN 260.111,92
Pekerja OH 0,5000 100.000,00 - 50.000,00
Tukang Listrik OH 0,5000 152.250,00 - 76.125,00
B. TENAGA
Kepala Tukang OH 0,0500 162.750,00 - 8.137,50
Mandor OH 0,02500 189.000,00 - 4.725,00
TOTAL UPAH TENAGA 138.987,50
C. PERALATAN
-
TOTAL BIAYA PERALATAN -
D. Total upah tenaga, biaya material dan peralatan (A+B+C) 399.099,42
E. Overhead + Profit 10 %xD 39.909,94
F. Harga Satuan Pekerjaan (D+E) 439.009,36
C. PERALATAN
-
TOTAL BIAYA PERALATAN -
D. Total upah tenaga, biaya material dan peralatan (A+B+C) 127.505,83
E. Overhead + Profit 10 %xD 12.750,58
F. Harga Satuan Pekerjaan (D+E) 140.256,41
C. PERALATAN
-
TOTAL BIAYA PERALATAN -
D. Total upah tenaga, biaya material dan peralatan (A+B+C) 49.171,87
E. Overhead + Profit 10 %xD 4.917,19
F. Harga Satuan Pekerjaan (D+E) 54.089,06
C. PERALATAN
-
TOTAL BIAYA PERALATAN -
D. Total upah tenaga, biaya material dan peralatan (A+B+C) 84.162,18
E. Overhead + Profit 10 % x D 8.416,22
F. Harga Satuan Pekerjaan (D+E) 92.578,40
29 1,00 M2 PENGECATAN KAYU (3x) BERIKUT MENI
Harga Satuan Jumlah Harga
Kebutuhan Satuan Index
Bahan Upah Bahan Upah
Meni kayu kg 0,1670 41.667,00 6.958,39
Plamir kayu kg 0,8300 62.500,00 51.875,00
Cat kayu merek Junior 88 Kg 0,2400 81.250,00 19.500,00 -
A. BAHAN
amplas kayu Lbr 0,4000 20.171,00 8.068,40
Minyak cat terpentin Ltr 0,1500 54.719,00 8.207,85 -
Kwas 3'' Bh 0,0500 25.000,00 1.250,00
TOTAL BIAYA BAHAN 95.859,64
Pekerja OH 0,0200 100.000,00 - 2.000,00
Tukang Cat OH 0,0630 152.250,00 - 9.591,75
B. TENAGA
Kepala Tukang OH 0,0063 162.750,00 - 1.025,33
Mandor OH 0,0025 189.000,00 - 472,50
TOTAL UPAH TENAGA 13.089,58
C. PERALATAN
-
TOTAL BIAYA PERALATAN -
D. Total upah tenaga, biaya material dan peralatan (A+B+C) 108.949,21
E. Overhead + Profit 10 %xD 10.894,92
F. Harga Satuan Pekerjaan (D+E) 119.844,14
C. PERALATAN
-
TOTAL BIAYA PERALATAN -
D. Total upah tenaga, biaya material dan peralatan (A+B+C) 14.862,55
E. Overhead + Profit 10 %xD 1.486,26
F. Harga Satuan Pekerjaan (D+E) 16.348,81