PEKERJAAN : PEMBUATAN PAGAR PENGAMAN ASET ( AMP ) NO. KONTRAK ADDENDUM. 01 : HK.02.01/Bb1-PRESV/62.1/APBN/2023
NO. KONTRAK : HK.02.01/Bb1-PRESV/62/APBN/2023 TGL. KONTRAK ADDENDUM. 01 : 15 JUNI 2023
TGL. KONTRAK : 10 APRIL 2023 NILAI KONTRAK ADDENDUM. 01 : Rp. 2.457.520.000,-
NILAI KONTRAK : Rp. 2.318.686.400,-
SUMBER DANA : APBN MURNI
TAHUN ANGGARAN : 2023
LOKASI : KECAMATAN TEUNOM
KAB. / KOTA : ACEH JAYA
PROVINSI : ACEH
KONTRAK AWAL KONTRAK ADDENDUM. 01 JUMLAH SERAPAN DANA PRESTASI KEMAJUAN PEKERJAAN
JUMLAH JUMLAH JUMLAH JUMLAH TOTAL TOTAL TOTAL TOTAL TOTAL TOTAL
NO. URAIAN PEKERJAAN TOTAL TOTAL TOTAL TOTAL SAMPAI BULAN BULAN SAMPAI BULAN SAMPAI BULAN SAMPAI
HARGA BOBOT HARGA BOBOT LALU INI INI BULAN LALU INI BULAN INI
( Rp ) (%) ( Rp ) (%) ( Rp ) ( Rp ) ( Rp ) (%) (%) (%)
1 PEKERJAAN PERSIAPAN 43.517.058,47 2,083 41.917.058,47 1,893 8.338.203,47 3.788.200,00 12.126.403,47 0,399 0,149 0,548
2 PEK. GALIAN TANAH DAN PONDASI BATU GUNUNG 165.486.538,23 7,922 324.006.190,90 14,634 16.550.255,41 150.669.328,83 167.219.584,24 0,792 6,761 7,553
3 PEKERJAAN STRUKTUR 1.118.140.944,58 53,528 1.090.010.783,01 49,233 58.596.465,61 422.720.612,86 481.317.078,47 2,805 18,935 21,740
4 PEKERJAAN PASANGAN DAN PLASTERAN 497.337.370,32 23,809 421.594.238,92 19,042 0,00 42.968.596,13 42.968.596,13 0,000 1,941 1,941
5 PEKERJAAN PENGECATAN 189.219.130,07 9,058 177.978.363,81 8,039 0,00 0,00 0,00 0,000 0,000 0,000
6 PEKERJAAN LAIN - LAIN 75.205.625,00 3,600 71.708.125,00 3,239 0,00 0,00 0,00 0,000 0,000 0,000
7 PEKERJAAN RAMP BETON PINTU MASUK 0,00 0,000 86.775.394,73 3,919 0,00 0,00 0,00 0,000 0,000 0,000
PEKERJAAN : PEMBUATAN PAGAR PENGAMAN ASET ( AMP ) NOMOR KONTRAK ADDENDUM. 01 : HK.02.01/Bb1-PRESV/62.1/APBN/2023
NO. KONTRAK : HK.02.01/Bb1-PRESV/62/APBN/2023 TANGGAL KONTRAK ADDENDUM. 01 : 15 JUNI 2023
TGL. KONTRAK : 10 APRIL 2023 NILAI KONTRAK ADDENDUM. 01 : Rp. 2.457.520.000,-
NILAI KONTRAK : Rp. 2.318.686.400,-
SUMBER DANA : APBN MURNI
TAHUN ANGGARAN : 2023
LOKASI : KECAMATAN TEUNOM
KAB. / KOTA : ACEH JAYA
PROVINSI : ACEH
A. PEKERJAAN PAGAR
KONTRAK AWAL KONTRAK ADDENDUM. 01 PRESTASI KEMAJUAN PEKERJAAN JUMLAH SERAPAN DANA
HARGA JUMLAH JUMLAH HARGA JUMLAH JUMLAH SAMPAI BULAN LALU BULAN INI SAMPAI BULAN INI JUMLAH TOTAL JUMLAH TOTAL JUMLAH TOTAL
NO. URAIAN PEKERJAAN SATUAN TOTAL TOTAL SATUAN TOTAL TOTAL PROG. PROG. PROG. SAMPAI BULAN SAMPAI
VOLUME SAT. VOLUME BOBOT BOBOT BOBOT
PEKERJAAN HARGA BOBOT PEKERJAAN HARGA BOBOT VOLUME PER. ITEM VOLUME PER. ITEM VOLUME PER. ITEM BULAN LALU INI BULAN INI
( Rp ) ( Rp ) (%) ( Rp ) ( Rp ) (%) (%) (%) (%) (%) (%) (%) ( Rp ) ( Rp ) ( Rp )
1. PEKERJAAN PERSIAPAN
Persiapan Awal
a. Pengukuran Dan pemasangan Bowplank 1,00 Pkt. 1.500.000,00 1.500.000,00 0,072 1,00 1.500.000,00 1.500.000,00 0,068 1,00 0,072 100,00 - - 0,004 0,00 1,00 0,068 100,00 1.500.000,00 - 1.500.000,00
b. Land clearing Area Jalur Pagar Setebal 20 cm 143,06 M2 13.130,25 1.878.413,57 0,090 143,06 13.130,25 1.878.413,57 0,085 143,06 0,090 100,00 - - 0,005 0,00 143,06 0,085 100,00 1.878.413,57 - 1.878.413,57
Persiapan Pendukung
a. Administrasi dan Documentasi 1,00 Pkt 2.000.000,00 2.000.000,00 0,096 1,00 2.000.000,00 2.000.000,00 0,090 0,25 0,024 25,00 0,17 0,014 16,67 0,42 0,038 41,67 500.000,00 333.333,33 833.333,33
b. Quality Control 1,00 Pkt 1.500.000,00 1.500.000,00 0,072 1,00 1.500.000,00 1.500.000,00 0,068 0,25 0,018 25,00 0,17 0,010 16,67 0,42 0,028 41,67 375.000,00 250.000,00 625.000,00
c. Gudang Semen dan Peralatan 12,00 M2 870.765,00 10.449.180,00 0,500 0,00 0,00 0,000 - 0,000 - - 0,00 0,000 - 0,00 0,00
d. Bedeng Pekerja 15,00 M2 870.765,00 13.061.475,00 0,625 0,00 0,00 0,000 - 0,000 - - 0,00 0,000 - 0,00 0,00
e. Air dan Listrik sementara 1,00 Ls 2.550.000,00 2.550.000,00 0,122 1,00 2.550.000,00 2.550.000,00 0,115 0,25 0,031 25,00 0,17 0,017 16,67 0,42 0,048 41,67 637.500,00 425.000,00 1.062.500,00
f. Papan Nama Proyek, Papan informasi 1,00 Ls 499.989,90 499.989,90 0,024 1,00 499.989,90 499.989,90 0,023 1,00 0,024 100,00 - - 0,001 0,00 1,00 0,023 100,00 499.989,90 - 499.989,90
g. SMKK 1,00 Ls 10.078.000,00 10.078.000,00 0,482 1,00 8.478.000,00 8.478.000,00 0,383 0,29 0,141 29,24 0,38 0,118 38,31 0,68 0,259 67,55 2.947.300,00 2.779.866,67 5.727.166,67
h. Renovasi Bangunan Kantor Existing Ls - 0,000 1,00 23.510.655,00 23.510.655,00 1,062 - 0,000 - - - 0,00 - 0,000 0,00 - 0,00 0,00
Sub. Jumlah 43.517.058,47 2,083 41.917.058,47 1,893 0,399 0,149 0,548 8.338.203,47 3.788.200,00 12.126.403,47
3. PEKERJAAN STRUKTUR
Pondasi Tapak
a. Mutu Beton fc = 21,7 Mpa (K-250) 17,14 M3 1.156.773,67 19.827.100,65 0,949 17,14 1.156.773,67 19.822.473,55 0,895 2,38 0,132 13,87 7,63 0,391 44,54 10,01 0,523 58,40 2.748.494,23 8.828.496,62 11.576.990,86
b. Besi Polos 8.045,80 Kg 17.501,40 140.812.764,12 6,741 2.677,43 17.501,40 46.858.726,91 2,116 918,61 0,770 34,31 1.249,26 0,944 46,66 2.167,87 1,714 80,97 16.076.986,18 21.863.800,75 37.940.786,93
c. Bekisting Tapak 114,24 M2 104.892,38 11.982.904,92 0,574 114,24 104.892,38 11.982.904,92 0,541 15,84 0,080 13,87 50,88 0,237 44,54 66,72 0,316 58,40 1.661.495,22 5.336.924,04 6.998.419,26
3. PEKERJAAN STRUKTUR
Sloof 18 x 25 cm
a. Mutu Beton fc = 21,7 Mpa (K-250) 32,19 M3 1.156.773,67 37.236.544,33 1,783 29,15 1.156.773,67 33.718.506,42 1,523 0,000 - 15,98 0,835 54,81 15,98 0,835 54,81 - 18.479.459,33 18.479.459,33
b. Besi Polos 5.106,59 Kg 17.501,40 89.372.474,23 4,278 5.425,24 17.501,40 94.949.217,25 4,289 0,000 - 2.935,01 2,320 54,10 2.935,01 2,320 54,10 - 51.366.785,34 51.366.785,34
c. Bekisting Sloof 486,40 M2 224.484,75 109.189.382,40 5,227 323,88 224.484,75 72.704.998,41 3,284 0,000 - 177,50 1,800 54,81 177,50 1,800 54,81 - 39.846.043,13 39.846.043,13
Balok Atas 18 x 25 cm
a. Mutu Beton fc = 21,7 Mpa (K-250) M3 - 0,000 29,15 1.156.773,67 33.718.506,42 1,523 0,000 - - - 0,00 0,000 0,00 - 0,00 0,00
b. Besi Polos Kg - 0,000 5.425,24 17.501,40 94.949.217,25 4,289 0,000 - - - 0,00 0,000 0,00 - 0,00 0,00
c. Bekisting Sloof ( Negosiasi ) M2 - 0,000 375,70 193.783,05 72.803.322,97 3,288 0,000 - - - 0,00 0,000 0,00 - 0,00 0,00
Kolom 25 x 25 cm
a. Mutu Beton fc = 21,7 Mpa (K-250) 50,20 M3 1.156.773,67 58.070.038,07 2,780 33,47 1.156.773,67 38.715.768,66 1,749 0,000 - 17,44 0,911 52,10 17,44 0,911 52,10 - 20.171.240,81 20.171.240,81
b. Besi Polos 9.450,18 Kg 17.501,40 165.391.380,25 7,918 4.854,53 17.501,40 84.961.025,05 3,837 0,000 - 2.674,81 2,114 55,10 2.674,81 2,114 55,10 - 46.812.985,85 46.812.985,85
c. Bekisting Kolom 529,86 M2 366.683,63 194.290.985,54 9,301 529,86 366.683,63 194.290.985,54 8,776 0,000 - 279,00 4,621 52,66 279,00 4,621 52,66 - 102.304.731,38 102.304.731,38
d. Bekisting Kolom ( Negosiasi ) M2 - 0,000 5,64 314.546,28 1.774.040,99 0,080 0,000 - - - 0,00 - 0,000 0,00 - 0,00 0,00
5. PEKERJAAN PENGECATAN
a. Pengecatan Dinding 3.719,50 M2 50.307,39 187.118.337,11 8,958 3.507,39 50.307,39 176.447.636,61 7,970 0,000 - - - 0,00 0,000 0,00 - 0,00 0,00
b. Pengecatan Permukaan Baja 76,80 M2 27.354,08 2.100.792,96 0,101 55,96 27.354,08 1.530.727,20 0,069 0,000 - - - 0,00 0,000 0,00 - 0,00 0,00
Sub. Jumlah 189.219.130,07 9,058 177.978.363,81 8,039 0,000 0,000 0,000 0,00 0,00 0,00
Saluran
a. Galian Tanah M3 - 0,000 30,75 75.114,38 2.309.767,03 0,104 - 0,000 - - - 0,00 0,000 0,00 - - 0,00
b. Urug Kembali Bekas Galian Tanah M3 - 0,000 7,69 54.153,75 416.306,95 0,019 - 0,000 - - - 0,00 0,000 0,00 - - 0,00
c. Pasir Alas Dipadatkan M3 - 0,000 1,23 162.345,75 199.685,27 0,009 - 0,000 - - - 0,00 0,000 0,00 - - 0,00
d. Beton Mutu, fc = 21,7 Mpa (K-250) M3 - 0,000 4,92 1.156.773,67 5.691.326,44 0,257 - 0,000 - - - 0,00 0,000 0,00 - - 0,00
e. Pasangan Batu Gunung Dengan Mortar M3 - 0,000 10,15 902.173,13 9.154.801,79 0,413 - 0,000 - - - 0,00 0,000 0,00 - - 0,00
f. Angkur Besi Polos Kg - 0,000 63,38 17.501,40 1.109.217,40 0,050 - 0,000 - - - 0,00 0,000 0,00 - - 0,00
g. Plasteran Pasangan Batu Gunung M2 - 0,000 22,55 79.137,77 1.784.556,60 0,081 - 0,000 - - - 0,00 0,000 0,00 - - 0,00
Sub. Jumlah - 0,000 86.775.394,73 3,919 0,000 0,000 0,000 0,00 0,00 0,00
JUMLAH TOTAL - A 2.088.906.666,67 100,000 2.213.990.154,84 100,000 3,997 27,785 31,781 83.484.924,49 620.146.737,81 703.631.662,29
PEKERJAAN : PEMBUATAN PAGAR PENGAMAN ASET ( AMP ) NOMOR KONTRAK ADDENDUM. 01 : HK.02.01/Bb1-PRESV/62.1/APBN/2023
NO. KONTRAK : HK.02.01/Bb1-PRESV/62/APBN/2023 TANGGAL KONTRAK ADDENDUM. 01 : 15 JUNI 2023
TGL. KONTRAK : 10 APRIL 2023 NILAI KONTRAK ADDENDUM. 01 : Rp. 2.457.520.000,-
NILAI KONTRAK : Rp. 2.318.686.400,-
SUMBER DANA : APBN MURNI
TAHUN ANGGARAN : 2023
LOKASI : KECAMATAN TEUNOM
KAB. / KOTA : ACEH JAYA
PROVINSI : ACEH
B. PEKERJAAN SMK3
KONTRAK AWAL KONTRAK ADDENDUM. 01 PRESTASI KEMAJUAN PEKERJAAN JUMLAH SERAPAN DANA
HARGA JUMLAH JUMLAH HARGA JUMLAH JUMLAH SAMPAI BULAN LALU BULAN INI SAMPAI BULAN INI JUMLAH TOTAL JUMLAH TOTAL JUMLAH TOTAL
NO. URAIAN PEKERJAAN SATUAN TOTAL TOTAL SATUAN TOTAL TOTAL PROG. PROG. PROG. SAMPAI BULAN SAMPAI
VOLUME SAT. VOLUME BOBOT BOBOT BOBOT
PEKERJAAN HARGA BOBOT PEKERJAAN HARGA BOBOT VOLUME PER. ITEM VOLUME PER. ITEM VOLUME PER. ITEM BULAN LALU INI BULAN INI
( Rp ) ( Rp ) (%) ( Rp ) ( Rp ) (%) (%) (%) (%) (%) (%) (%) ( Rp ) ( Rp ) ( Rp )
a. Petugas Keselamatan Konstruksi, Petugas K3Konstruksi 1,00 Org 4.000.000,00 4.000.000,00 0,191 1,000 4.000.000,00 4.000.000,00 0,181 0,25 0,048 25,00 0,17 0,027 16,67 0,42 0,075 41,67 1.000.000,00 666.666,67 1.666.666,67
Sub. Jumlah 4.000.000,00 0,191 4.000.000,00 0,181 0,048 0,027 0,075 1.000.000,000 666.666,667 1.666.666,667
HARGA JUMLAH JUMLAH HARGA JUMLAH JUMLAH SAMPAI BULAN LALU BULAN INI SAMPAI BULAN INI JUMLAH TOTAL JUMLAH TOTAL JUMLAH TOTAL
NO. URAIAN PEKERJAAN SATUAN TOTAL TOTAL SATUAN TOTAL TOTAL PROG. PROG. PROG. SAMPAI BULAN SAMPAI
VOLUME SAT. VOLUME BOBOT BOBOT BOBOT
PEKERJAAN HARGA BOBOT PEKERJAAN HARGA BOBOT VOLUME PER. ITEM VOLUME PER. ITEM VOLUME PER. ITEM BULAN LALU INI BULAN INI
( Rp ) ( Rp ) (%) ( Rp ) ( Rp ) (%) (%) (%) (%) (%) (%) (%) ( Rp ) ( Rp ) ( Rp )
7. Rambu dan Perlengkapan Lalu Lintas yang diperlukan atau Manajemen Lalu Lintas
a. Rambu Petunjuk 2,00 Bh 50.000,00 100.000,00 0,005 2,000 50.000,00 100.000,00 0,005 0,000 - 2,00 0,005 100,00 2,00 0,005 100,00 - 100.000,00 100.000,00
b. Rambu Larangan 2,00 Bh 50.000,00 100.000,00 0,005 2,000 50.000,00 100.000,00 0,005 0,000 - 2,00 0,005 100,00 2,00 0,005 100,00 - 100.000,00 100.000,00
c. Rambu Peringatan 2,00 Bh 50.000,00 100.000,00 0,005 2,000 50.000,00 100.000,00 0,005 0,000 - 2,00 0,005 100,00 2,00 0,005 100,00 - 100.000,00 100.000,00
d. Rambu Kewajiban 2,00 Bh 50.000,00 100.000,00 0,005 2,000 50.000,00 100.000,00 0,005 0,000 - 2,00 0,005 100,00 2,00 0,005 100,00 - 100.000,00 100.000,00
e. Rambu Informasi 2,00 Bh 50.000,00 100.000,00 0,005 2,000 50.000,00 100.000,00 0,005 0,000 - 2,00 0,005 100,00 2,00 0,005 100,00 - 100.000,00 100.000,00
Sub. Jumlah 500.000,00 0,024 500.000,00 0,023 0,000 0,023 0,023 0,000 500.000,000 500.000,000
JUMLAH TOTAL - B 10.078.000,00 0,482 8.478.000,00 0,383 0,141 0,118 0,259 2.947.300,000 2.779.866,667 5.727.166,667
PEKERJAAN : PEMBUATAN PAGAR PENGAMAN ASET ( AMP ) NO. KONTRAK ADDENDUM. 01 : HK.02.01/Bb1-PRESV/62.1/APBN/2023
NO. KONTRAK : HK.02.01/Bb1-PRESV/62/APBN/2023 TGL. KONTRAK ADDENDUM. 01: 15 JUNI 2023
TGL. KONTRAK : 10 APRIL 2023 NILAI KONTRAK ADDENDUM. 01: Rp. 2.457.520.000,-
NILAI KONTRAK : Rp. 2.318.686.400,-
SUMBER DANA : APBN MURNI
TAHUN ANGGARAN : 2023
LOKASI : KECAMATAN TEUNOM
KAB. / KOTA : ACEH JAYA
PROVINSI : ACEH
JUMLAH JUMLAH APRIL 2023 MEI 2023 JUNI 2023 JULI 2023 AGUSTUS 2023 SEPTEMBER 2023 OKTOBER 2023
TOTAL TOTAL M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12 M13 M14 M15 M16 M17 M18 M19 M20 M21 M22 M23 M24
NO. URAIAN PEKERJAAN SKALA / KET.
HARGA BOBOT 18 April 25 April 01 Mei 08 Mei 16 Mei 24 Mei 01 Juni 08 Juni 16 Juni 24 Juni 01 Juli 08 Juli 16 Juli 24 Juli 01 Agst. 08 Agst. 16 Agst. 24 Agst. 01 Sept. 08 Sept. 16 Sept. 24 Sept. 01 Okt. 08 Okt.
KONTRAK KONTRAK s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d
ADDENDUM. 01 ADD. 01 24 April 30 April 07 Mei 15 Mei 23 Mei 31 Mei 07 Juni 15 Juni 23 Juni 30 Juni 07 Juli 15 Juli 23 Juli 31 Juli 07 Agst. 15 Agst. 23 Agst. 31 Agst. 07 Sept. 15 Sept. 23 Sept. 30 Sept. 07 Okt. 14 Okt.
( Rp ) (%) 7 6 7 8 8 8 7 8 8 7 7 8 8 8 7 8 8 8 7 8 8 7 7 7
100,000
1. PEKERJAAN PERSIAPAN
Persiapan Awal
a. Pengukuran Dan pemasangan Bowplank 1.500.000,00 0,068 0,036 0,036 0,000 -0,004
b. Land clearing Area Jalur Pagar Setebal 20 cm 1.878.413,57 0,085 0,030 0,030 0,030 0,000 -0,005
Persiapan Pendukung
a. Administrasi dan Documentasi 2.000.000,00 0,090 0,004 0,004 0,004 0,004 0,004 0,004 0,004 0,004 0,004 0,004 0,004 0,004 0,004 0,004 0,004 0,004 0,004 0,004 0,004 0,004 0,004 0,004 0,004
b. Quality Control 1.500.000,00 0,068 0,012 0,003 0,003 0,003 0,003 0,011 0,011 0,011 0,011
c. Gudang Semen dan Peralatan 0,00 0,000 0,425 0,075 -0,472 -0,028
d. Bedeng Pekerja 0,00 0,000 0,531 0,094 -0,590 -0,035 90,000
e. Air dan Listrik sementara 2.550.000,00 0,115 0,008 0,008 0,008 0,008 0,008 0,074
f. Papan Nama Proyek, Papan informasi 499.989,90 0,023 0,024 -0,001
g. SMKK 8.478.000,00 0,383 0,008 0,061 0,008 0,012 0,021 0,032 0,023 0,022 0,066 0,066 0,066
h. Renovasi Bangunan Kantor Existing 23.510.655,00 1,062 0,354 0,354 0,354
70,000
3. PEKERJAAN STRUKTUR
Pondasi Tapak
a. Mutu Beton fc = 21,7 Mpa (K-250) 19.822.473,55 0,895 0,132 0,112 0,227 0,061 0,061 0,061 0,061 0,061 0,061 0,061
b. Besi Polos 46.858.726,91 2,116 0,295 0,251 0,510 0,151 0,151 0,151 0,151 0,151 0,151 0,151
c. Bekisting Tapak 11.982.904,92 0,541 0,080 0,067 0,137 0,037 0,037 0,037 0,037 0,037 0,037 0,037
Balok Atas 18 x 25 cm
a. Mutu Beton fc = 21,7 Mpa (K-250) 33.718.506,42 1,523 0,381 0,381 0,381 0,381
4,289
50,000
b. Besi Polos 94.949.217,25 1,072 1,072 1,072 1,072
c. Bekisting Sloof ( Negosoasi ) 72.803.322,97 3,288 0,822 0,822 0,822 0,822
Kolom 25 x 25 cm
a. Mutu Beton fc = 21,7 Mpa (K-250) 38.715.768,66 1,749 0,367 0,138 0,138 0,138 0,138 0,138 0,138 0,138 0,138 0,138 0,138
b. Besi Polos 84.961.025,05 3,837 1,030 0,670 0,214 0,214 0,214 0,214 0,214 0,214 0,214 0,214 0,214 0,214
c. Bekisting Kolom 194.290.985,54 8,776 1,861 0,691 0,691 0,691 0,691 0,691 0,691 0,691 0,691 0,691 0,691
d. Bekisting Kolom ( Negosiasi ) 1.774.040,99 0,080 0,040 0,040
5. PEKERJAAN PENGECATAN
a. Pengecatan Dinding 176.447.636,61 7,970 1,328 1,328 1,328 1,328 1,328 1,328
KURVA - S KONTRAK AWAL
b. Pengecatan Permukaan Baja 1.530.727,20 0,069 0,035 0,035
JUMLAH TOTAL / PROGRESS RENCANA MINGGU INI ( % ) 2.213.990.154,84 100,000 0,131 - 0,708 0,918 3,292 3,707 3,822 5,098 4,745 - 4,241 10,176 10,983 9,494 10,060 10,035 7,245 5,785 3,930 1,928 1,928 1,521 0,164 0,089
PROGRESS KUMULATIF RENCANA SAMPAI MINGGU INI ( % ) KONTRAK AWAL 0,000 0,131 0,131 0,840 1,758 5,050 8,757 12,579 17,676 22,421 22,421 26,662 36,838 47,821 57,315 67,375 77,410 84,656 90,441 94,371 96,298 98,226 99,746 99,911 100,000
PROGRESS RENCANA MINGGU INI ( % ) 0,000 0,012 0,089 0,093 1,045 0,313 2,448 5,549 8,656 1,874 - 5,549 5,538 6,409 6,335 7,127 7,123 5,795 5,861 8,521 7,131 6,053 5,735 1,377 1,366
PROGRESS KUMULATIF RENCANA SAMPAI MINGGU INI ( % ) 0,000 0,012 0,101 0,193 1,239 1,551 4,000 9,549 18,205 20,078 20,078 25,628 31,166 37,575 43,910 51,037 58,159 63,955 69,816 78,337 85,468 91,522 97,257 98,634 100,000
ADDENDUM - 01
PROGRESS RENCANA BULAN INI ( % ) 0,000 0,101 3,899 16,079 23,831 25,907 27,441 2,743
PROGRESS KUMULATIF RENCANA SAMPAI BULAN INI ( % ) 0,000 0,101 4,000 20,078 43,910 69,816 97,257 100,000
PROGRESS REALISASI MINGGU INI ( % ) 0,000 0,012 0,089 0,093 1,045 0,313 2,448 5,549 8,656 6,818 6,758
PROGRESS KUMULATIF REALISASI SAMPAI MINGGU INI ( % ) 0,000 0,012 0,101 0,193 1,239 1,551 4,000 9,549 18,205 25,023 31,781
REALISASI
PROGRESS REALISASI / AKTUAL BULAN INI ( % ) 0,000 0,101 3,899 27,781
PROGRESS KUMULATIF REALISASI / AKTUAL SAMPAI BULAN INI ( % ) 0,000 0,101 4,000 31,781
DEVIASI / SIMPANGAN MINGGUAN ( % ) 0,000 - - 0,000 0,000 0,000 0,000 0,000 0,000 4,944 11,703
DEVIASI
DEVIASI / SIMPANGAN BULANAN ( % ) 0,000 0,00 0,000 11,703
PEKERJAAN : KOLOM DAN PASANGAN BATU 1/2 BATA PEKERJAAN : KOLOM DAN PASANGAN BATU 1/2 BATA
PEKERJAAN : KOLOM DAN PASANGAN BATU 1/2 BATA PEKERJAAN : BALOK SLOOF DAN KOLOM
PEKERJAAN : BALOK SLOOF DAN KOLOM PEKERJAAN : BALOK SLOOF DAN KOLOM
PEKERJAAN : BALOK SLOOF DAN KOLOM PEKERJAAN : BALOK SLOOF DAN KOLOM
PEKERJAAN : BALOK SLOOF DAN KOLOM PEKERJAAN : BALOK SLOOF DAN KOLOM
PEKERJAAN : PONDASI TAPAK DAN PENDESTAL PEKERJAAN : GALIAN PONDASI TAPAK DAN BATU GUNUNG
PEKERJAAN : GALIAN PONDASI TAPAK DAN BATU GUNUNG PEKERJAAN : GALIAN PONDASI TAPAK DAN BATU GUNUNG
PEKERJAAN : GALIAN PONDASI TAPAK DAN BATU GUNUNG PEKERJAAN : GALIAN PONDASI TAPAK DAN BATU GUNUNG
PEKERJAAN : GALIAN PONDASI TAPAK DAN BATU GUNUNG PEKERJAAN : GALIAN PONDASI TAPAK DAN BATU GUNUNG
PEKERJAAN : GALIAN PONDASI TAPAK DAN BATU GUNUNG PEKERJAAN : GALIAN PONDASI TAPAK DAN BATU GUNUNG
PEKERJAAN : GALIAN PONDASI TAPAK DAN BATU GUNUNG PEKERJAAN : GALIAN PONDASI TAPAK DAN BATU GUNUNG
PEKERJAAN : GALIAN PONDASI TAPAK DAN BATU GUNUNG PEKERJAAN : PONDASI BATU GUNUNG, BALOK SLOOF DAN KOLOM
PEKERJAAN : PASANGAN BATU 1/2 BATA PEKERJAAN : PASANGAN BATU 1/2 BATA
PEKERJAAN : PASANGAN BATU 1/2 BATA PEKERJAAN : PASANGAN BATU 1/2 BATA
PEKERJAAN : PASANGAN BATU 1/2 BATA PEKERJAAN : PASANGAN BATU 1/2 BATA
Disetujui Oleh :
BALAI PELAKSANA JALAN NASIONAL ACEH
PROJECT OFFICER PPK PRESERVASI
( Arief Gunawan, ST )
Nip. 19740710 200911 1 001