VOL Harga BIAYA JUMLAH

URAIAN Sat
Koef. Satuan UPAH ALAT BAHAN HARGA
1 m2 Pek. Konstruksi Baja Ringan (Bersertifikat/Bergaransi 10 tahun)

Main truss C-75-75 2.8 m' 15,000 42,000


Roof Bottom/Reng R 33-0.45 5.1 m' 8,627 43,998
Self Drilling Screw dia-6 x 20 mm (Truss Screw) 25 bh 375 9,375
Self Drilling Screw dia-4 x 16 mm (Roof Batten Screw) 35 bh 350 12,250
Dynabol dia-12 x 120 mm 1 bh 1,500 1,500

Tukang Besi Profil 0.176 oh 130,000 22,880


Kepala Tukang Besi Profil 0.117 oh 140,000 16,380

Mobilisasi 1 Ls 3,000 3,000


Alat bantu (Mesin Bor Listrik) / Genset 1 ls 2,500 2,500
Gambar Disain 1 m2 2,000 2,000
39,260 7,500 109,123
Profit 10% 3,926 750 10,912
43,186 8,250 120,035
43,180 8,250 120,030 171,460
REKAPITULASI RENCANA ANGGARAN BIAYA
PEKERJAAN : PEMBANGUNAN ASRAMA BIVAK TIPE 38 POLRES PAYAKUMBUH TAHUN 2017
LOKASI : KOTA PAYAKUMBUH

NO URAIAN

I PEKERJAAN PENDAHULUAN
II PEKERJAAN PONDASI
III PEKERJAAN STRUKTUR
IV PEKERJAAN DINDING
V PEKERJAAN KUZEN
VI PEKERJAAN KUDA-KUDA & ATAP
VII PEKERJAAN PLAFOND
VIII PEKERJAAN LANTAI
IX PEKERJAAN CAT
X PEKERJAAN INSTALASI LISTRIK BARU
XI PEKERJAAN PERLENGKAPAN DALAM
XII PEKERJAAN GERBANG

JUMLAH
PPN 10 %
TOTAL
DIBULATKAN
Terbilang : Satu Miliar Lima Ratus Sebelas juta Enam Ratus Empat Puluh Ribu Rupiah

Payakumbuh, F

Diketahui Oleh:
Pejabat Pelaksana Teknis Kegiatan
PT. AGOESINDO

AIPTU EDISON NRP 73070375


Paur Logistik Polres Payakumbuh

Disetujui Oleh :
KEPALA KEPOLISIAN RESOR PAYAKUMBUH
SELAKU
KUASA PENGGUNA ANGGARAN/
PEJABAT PEMBUAT KOMITMEN
KUSWOTO, SIK
AJUN KOMISARIS BESAR POLISI NRP. 74100559
RENCANA ANGGARAN BIAYA

TOTAL JUMLAH

17,593,430.04
112,470,417.26
99,983,208.59
424,228,997.38
108,046,268.03
152,395,527.10
132,187,948.94
63,575,073.75
86,610,007.22
43,030,000.00
97,251,866.48
36,847,417.97

1,374,220,162.78
137,422,016.28
1,511,642,179.06
1,511,640,000.00
Ratus Sebelas juta Enam Ratus Empat Puluh Ribu Rupiah

Payakumbuh, Februari 2017

Dibuat Oleh :
Konsultan Perencana
PT. AGOESINDO JAYA MAHESA

Ir. JONNI AGOES


Direktur Utama
DAFTAR HARGA SATUAN BAHAN DAN JASA

TENAGA
NO / BAHAN - BAHAN / STN
PEKERJAAN

A UPAH
1 Pekerja Hari
2 Mandor Hari
3 Tukang Kayu Hari
4 Tukang Batu Hari
5 Tukang Cat Hari
6 Tukang Listrik Hari
7 Tukang Pipa Hari
8 Tukang Besi/ Las Hari
9 Kepala Tukang Kayu Hari
10 Kepala Tukang Batu Hari
11 Kepala Tukang Cat Hari
12 Kepala Tukang Besi Hari
13 Kepala Tukang Listrik Hari
14 Kepala tukang Hari
15 Ahli Pemasangan Pipa Hari
16 Operator Alat Berat Hari
17 Pembantu Operator Hari
18 Tukang Aspal Hari
19 Makanik Hari
20 Pembantu Mekanik Hari
21 Sopir Hari
22 Pembantu Sopir Hari
23 Buruh Terlatih Hari
24 Buruh Tidak Terlatih Hari
25 Pekerja Pembersihan Hari
26 Pekerja Menghampar Hari
27 Petugas Keamanan Hari
28 Petugas Caraka Hari
29 Penjaga Malam Hari
30 Petugas Parkir Hari
31 Tukang Kuda-kuda Baja Hari
32 Supervisor Baja Hari
33 Tukang Besi Hari
34 Tukang Besi Konstruksi Hari

B BAHAN
I. Kayu
1 Kayu Banio Kls I / Sederajat M3
2 Kayu Marsawa Kelas II / Sederajat M3
3 Kayu Surian / Sederajat M3
4 Kayu Meranti / Sederajat M3
5 Kayu Lokal (Kayu Kampung) M3
6 Kayu Lis Profil M'
7 Papan Mal / Sederajat M3
8 Pancang kayu (Rp. 800.000,-/M3) M1
9 Pancang Bambu M'
10 Triplek 3 mm Padang/Sekualitas Lbr
11 Triplek 4 mm Padang/Sekualitas Lbr
12 Multiplek tebal 9 mm Lbr
13 Multiplek tebal 12 mm Lbr
14 Plywood Lbr
15 Gypsum Lbr
16 List profil gypsum M'
17 Pasir Pasang M3
18 Pasir Urug M3
19 Sirtu M3
20 Kerikil M3
21 Batu Kali M3
22 Split 0,5 - 1 M3
23 Batu Pecah 1 - 2 M2
24 Batu Pecah 2 - 3 M3
25 Batu Pecah 3 - 4 M3
26 Batu pecah 5/7 M3
27 Tanah Urug M3
28
29 Semen Padang (50 Kg) Zak
30 Semen Padang (50 Kg) Kg
31 Semen Putih Zak
32 Tepung AFA Kg
33
34 Batu Bata Kls I Bh
35 Batu Bata Kls II Bh
36 Batu Bataco Bh
37 Hollow Brick Bh
38 Paving Block Segi Enam Bh
39 Batu Kerawang Bh
40 Seng Bjls 20 setara gajah berlian Lbr
41 Seng Plat Bjls 20 setara gajah berlian Lbr
42 Seng Warna Bjls 20 setara gajah berlian Lbr
43 Seng Plat Warna Bjls 20 setara gajah berlian Lbr
44 Genteng Metal Berpasir Lbr
45 Perabung Genteng Metal Bh
46 Main truss C-75-75 (Konstruksi Baja Ringan) M'
47 Reng/Reng R 33-0.45 M'
48 Baut/Screw dia-6 x 20 mm (Truss Screw) Bh
49 Baut/Screw dia-4 x 16 mm (Roof Batten Screw) Bh
50 Dynabol dia-12 x 120 mm Bh
51 Talang/Vailey Gutter M'
52 L-Plate Bh
53 Dinabolt Bh
54 Kusen Aluminium 4 inch X 1 3/4 inch warna hitam M'
55 Besi Got Btg
56 Besi Beton Jawa o 6 mm (setara KS) SNI Btg
57 Besi Beton Jawa o 7 mm (setara KS) SNI Btg
58 Besi Beton Jawa o 8 mm (setara KS) SNI Btg
59 Besi Beton Jawa o 9 mm (setara KS) SNI Btg
60 Besi Beton Jawa o 10 mm (setara KS) SNI Btg
61 Besi Beton Jawa o 12 mm (setara KS) SNI Btg
62 Besi Beton Jawa o 14 mm (setara KS) SNI Btg
63 Besi Beton Jawa o 16 mm (setara KS) SNI Btg
64 Besi Beton Jawa o 18 mm (setara KS) SNI Btg
65 Besi Beton Jawa o 19 mm (setara KS) SNI Btg
66 Besi Beton Jawa o 22 mm (setara KS) SNI Btg
67 Besi Beton (Tulangan) (setara KS) SNI Kg
68 Besi Beton Jawa o 12 mm (setara KS) SNI Ulir Btg
69 Besi Beton Jawa o 14 mm (setara KS) SNI Ulir Btg
70 Besi Beton Jawa o 16 mm (setara KS) SNI Ulir Btg
71 Besi Beton Jawa o 18 mm (setara KS) SNI Ulir Btg
72 Besi Beton Jawa o 19 mm (setara KS) SNI Ulir Btg
73 Besi Beton Jawa o 22 mm (setara KS) SNI Ulir Btg
74 Besi Beton (Tulangan) (setara KS) SNI Ulir Kg
75 Besi Siku 2,5.2,5.2 Btg
76 Besi Siku 3,3,03 Btg
77 Besi Siku 4.4,04 Btg
78 Besi Strip/Plat gepeng 1/4x3/4x3,5 Btg
79 Besi Strip/Plat gepeng 1/4x1x3,5 Btg
80 Besi Strip/Plat gepeng 1/8x1x6 Btg
81 Besi Begol panjang 6 m Bh
82 Besi Plat Baja Tebal 4mm Lebar 40mm Btg
83 Kawat Beton Kg
84 Kawat Beronjong 4 mm Kg
85 Kawat Beronjong Pabrikan 3 " (terpasang) M3
86 Besi Hollow ( 40 x 40 ) M
87 Paku 2 - 5 Inc Kg
88 Paku Atap Genteng Metal Ktk
89 Paku Atap/Seng Kg
VII. Cat/ Perlengkapan
1 Cat Minyak setara Dulux Kg
2 Cat air Nipon Kg
3 Cat Pilox Kaleng
4 Nipoon paint/Dulux Setara Ltr
5 Dempul Jadi Kg
6 Plamur Wall Puty Kg
7 Menie Kayu Eizer Kg
8 Menie Besi Kg
9 Cat Dasar Kg
10 Plitur Kg
11 Kapur Sirih Kg
12 Sabun Kg
13 A m p l a s Kain Hl
14 Minyak Tanah Liter
15 Bensin Liter
16 Minyak Solar Liter
17 Minyak Solar Untuk Industri (harga dasar+PBBKB) Liter
18 Minyak Pelumas Mesin Liter
19 Minyak Bekisting Liter
20 Olie Bak Mobil Liter
21 Olie Mesin Liter
22 Olie Gardan Liter
23 Residu Liter
24 Aspal (155 Kg) Drum
25 Gomok Kg
26 Aspal (Distributor) Kg
27 Kaca Bening 3 mm Kaki
28 Kaca Bening 5 mm Kaki
29 Kaca Rayband 3 mm Kaki
30 Kaca Rayband 5 mm Kaki
31 Kaca Tebal 12 mm Tempered M2
32 Kaca Buram 5 mm Kaki
33 Kaca Naco 15 x 70 cm + rangka Daun
34 Kaca Naco 15 x 70 cm + rangka Lbg
35 Granit 60 x 60 cm Essenza setara Ktk
36 Keramik 40 x 40 cm setara IKAD Ktk
37 Keramik 20 x 20 cm setara IKAD Ktk
38 Keramik 20 x 20 cm setara IKAD Bh
39 Keramik 20 x 25 cm setara IKAD Ktk
40 Keramik 10 x 20 setara IKAD Ktk
41 Keramik 10 x 20 setara IKAD Ktk
42 Keramik 10 x 20 setara IKAD Ktk
43 Keramik 10 x 20 setara IKAD Ktk
44 Keramik 10 x 20 setara IKAD Ktk
45 Keramik 10 x 20 setara IKAD Ktk
46 Keramik 10 x 20 setara IKAD
47 Keramik 10 x 20 setara IKAD Bh
48 Bon-bon (lis pinggir) M'
49 Plint tegel Bh
50 Ubin PC Kepala Basah 20 x 20 cm Bh
51 Keramik 20 x 25 cm setara IKAD Ktk
52 Ijuk Saringan Kg
53 Kloset duduk Toto type C Auto (setara) Bh
54 Kloset duduk Toto type CE 7 auto (setara) Bh
55 Kloset jongkok KIA Type EX setara Bh
56 Kloset jongkok KIA Type DX setara Bh
57 Kloset jongkok KIA Type Kampion setara Bh
58 Kloset jongkok KIA Type Kiomio setara Bh
59 Wastafel Komplit KIA type Sunsan jongkok setara Bh
60 Wastafel Komplit KIA type Sunsan duduk setara Bh
61 Urinoir Komplit sedang Bh
62 Urinoir Komplit besar Bh
63 Kran Air Biasa 1/2"/ Asahi (setara) Bh
64 Saringan Kamar Mandi (Floor drain) stainless steel Bh
65 Saringan Kamar Mandi (Floor drain) PVC Bh
66 Bak Fiber 60 x 60 x 60 cm Bh
67 Bak Fiber 70 x 70 x 60 cm Bh
68 Bak Reservoir Fiber Glass ( 0.5 M3 ) Bh
69 Bak Reservoir Fiber Glass ( 1 M3 ) Bh
70 Bak Reservoir Fiber Glass ( 2 M3 ) Bh
71 Pintu + Kusen Fiber Kamar Mandi Unit
72 Talang Petak PVC Btg
73 Pekerjaan Sumur Bor Unit
74 Pompa Air Jet Pump Hitachi DT-P 3000 Gp Unit
75 Kunci Tanam SES Set
76 Kunci Tanam Cap Jangkar RRC 97021 (setara) Set
77 Kunci Tanam Cap Jangkar RRC 746 (setara) Set
78 Kunci Tanam cap Union 2 slang (setara) Set
79 Kunci Tanam antik A/C Italy Set
80 Grendel biasa Bh
81 Grendel SES Bh
82 Grendel hunter Bh
83 Tarikan jendela biasa Bh
84 Kait angin biasa Bh
85 Kait angin Asahi Bh
86 Kait angin Handi Bh
87 Lem kayu Ltr
88 Engsel pintu S K K Bh
89 Engsel pintu SES Bh
90 Engsel Pintu 77 Bh
91 Engsel jendela SKK Bh
92 Engsel jendela SES Bh
93 Pagar BRC 90 Cm Panel
94 Pagar BRC 120 Cm Panel
95 Pipa Hitam o 1/2" panjang 6M Btg
96 Pipa Hitam o 3/4" panjang 6 M Btg
97 Pipa Hitam o 1" panjang 6 M Btg
98 Pipa Hitam o 2" panjang 6M Btg
99 Pipa Galvanis 3" panjang 6M Btg
100 Pipa Galvanis 2,5" panjang 6 M Btg
101 Pipa Galvanis 2" panjang 6M Btg
102 Pipa Galvanis 1/2" Panjang 6M Btg
103 Pipa Stainesteel ( untuk Pagar ) Btg
104 Pipa PVC. 8" setara Wavin AW panjang 4 M Btg
105 Pipa PVC. 6" setara Wavin AW panjang 4 M Btg
106 Pipa PVC. 4" setara Wavin AW panjang 4 M Btg
107 Pipa PVC. 3" setara Wavin AW panjang 4 M Btg
108 Pipa PVC. 2" setara Wavin AW panjang 4 M Btg
109 Pipa PVC. 1" setara Wavin AW panjang 4 M Btg
110 Pipa PVC. 3/4" setara Wavin AW panjang 4M Btg
111 Pipa PVC. 1/2" setara Wavin AW panjang 4M Btg

XIV. Buis Beton


1 Buis beton o 100 cm Bh
2 Buis beton o 80 cm Bh
3 Buis beton o 60 cm Bh
4 Buis beton o 40 cm Bh
5 Buis beton o 30 cm Bh
6 Buis beton o 20 cm Bh
7 Buis beton 1/2 o 50 cm Bh
8 Buis beton 1/2 o 40 cm Bh
9 Buis beton 1/2 o 30 cm Bh
10 Buis beton 1/2 o 20 cm Bh
11 Buis beton 1/2 o 15 cm Bh
12
13 Alat bantu Unit
14 Pasangan Titik Lampu Titik
15 Pasangan Stop Kontak Titik
16 Stop Kontak Bh
17 Saklar ganda Bh
18 Saklar Triple Bh
HARGA SATUAN BAHAN DAN JASA

HARGA BARU (Rp)

100,000.00
140,000.00
130,000.00
130,000.00
130,000.00
130,000.00
130,000.00
130,000.00
140,000.00
140,000.00
140,000.00
140,000.00
140,000.00
140,000.00

8,000,000.00
6,000,000.00
4,800,000.00
4,300,000.00
2,000,000.00
18,000.00
2,000,000.00
5,000.00
10,000.00
51,000.00
68,000.00
125,000.00
170,000.00
200,000.00
94,000.00
18,000.00
135,000.00
100,000.00
90,000.00
150,000.00
145,000.00
302,500.00
295,000.00
290,000.00
265,000.00
240,000.00
45,000.00

59,000.00
1,180.00
120,000.00
9,000.00

700.00
700.00
2,200.00
2,200.00
1,800.00
15,000.00
42,500.00
45,000.00
55,000.00
75,000.00
106,000.00
30,000.00
15,000.00
8,627.00
375.00
350.00
1,500.00
9,000.00
5,000.00
1,800.00
95,000.00
13,500.00
28,000.00
37,000.00
45,000.00
52,000.00
70,000.00
100,000.00 7.4
150,000.00
170,000.00
230,000.00
243,000.00
320,000.00
9,500.00
79,000.00 7.4
123,000.00
164,266.67
196,250.00
232,400.00
311,600.00
10,750.00
45,000.00
59,000.00
80,000.00
13,000.00
15,000.00
15,000.00
13,500.00
15,000.00
15,000.00
12,000.00
14,833.33
19,000.00
17,000.00
22,000.00
20,000.00
65,000.00
38,000.00
25,000.00
120,000.00
28,000.00
21,000.00
25,000.00
25,000.00
28,000.00
53,000.00
7,000.00
4,000.00
6,000.00
9,000.00
8,100.00
5,600.00
-
40,000.00
17,000.00
-
-
-
15,000.00
-
-
-
82,000.00
94,000.00
-
-
535,000.00
98,700.00
-
-
404,400.00
68,000.00
44,000.00
-
64,000.00
-
-
-
-
-
-
-
-
7,500.00
8,000.00
-
44,000.00
25,000.00
4,775,000.00
1,250,000.00
275,000.00
275,000.00
245,000.00
240,000.00
650,000.00
650,000.00
950,000.00
900,000.00
18,000.00
40,000.00
15,000.00
285,000.00
220,000.00
320,000.00
400,000.00
1,200,000.00
300,000.00
54,000.00
3,000,000.00
3,700,000.00
355,000.00
-
-
140,000.00
5,000.00
8,500.00
8,500.00
11,000.00
7,000.00
7,000.00
10,500.00
10,000.00
15,000.00
9,000.00
19,833.33
8,500.00
8,500.00
15,000.00
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-

-
-
-
-
-
-
-
-
-
-
-

-
180,000.00
180,000.00
20,000.00
20,000.00
30,000.00
TIME SCHEDULLE
PEKERJAAN : PEMBANGUNAN ASRAMA BIVAK TIPE 38 POLRES PAYAKUMBUH TAHUN 2017
LOKASI : KOTA PAYAKUMBUH

Bulan I Bulan II Bulan III Bulan III


NO URAIAN BOBOT
1 2 3 4 5 6 7 8 9 10 11 12 9 10 11 12 1,374,220,163

I PEKERJAAN PENDAHULUAN 1.28% 1.28% 100 1.28%


II PEKERJAAN PONDASI 8.18% 1.64% 3.27% 3.27% 8.18%
III PEKERJAAN STRUKTUR 7.28% 2.91% 1.46% 1.46% 1.46% 7.28%
IV PEKERJAAN DINDING 30.87% 6.17% 12.35% 6.17% 6.17% 30.87%
V PEKERJAAN KUZEN 7.86% 1.57% 3.14% 1.57% 1.57% 7.86%
VI PEKERJAAN KUDA-KUDA & ATAP 11.09% 2.22% 4.44% 2.22% 2.22% 50 11.09%
VII PEKERJAAN PLAFOND 9.62% 1.92% 3.85% 1.92% 1.92% 9.62%
VIII PEKERJAAN LANTAI 4.63% 0.93% 1.85% 0.93% 0.93% 4.63%
IX PEKERJAAN CAT 6.30% 1.26% 2.52% 1.26% 1.26% 6.30%
X PEKERJAAN INSTALASI LISTRIK BARU 3.13% 0.63% 1.25% 0.63% 0.63% 3.13%
XI PEKERJAAN PERLENGKAPAN DALAM 7.08% 1.42% 2.83% 1.42% 1.42% 7.08%
XII PEKERJAAN GERBANG 2.68% 0.54% 1.07% 0.54% 0.54% 10 2.68%

JUMLAH 100.00%
MINGGUAN 1.28% 1.64% 6.18% 10.90% 15.38% 10.77% 9.96% 7.93% 6.99% 7.25% 6.00% 4.85% 5.25% 3.11% 1.95% 0.54%
RENCANA
KOMULATIF 0.00% 1.28% 2.92% 9.10% 20.00% 35.38% 46.15% 56.12% 64.05% 71.04% 78.29% 84.29% 89.14% 94.40% 97.51% 99.46% 100.00%
MINGGUAN
REALISASI
KOMULATIF
ANGKA
DEVIASI
PENILAIAN

Payakumbuh, Februari 2017

Dibuat Oleh :
Konsultan Perencana
PT. AGOESINDO JAYA MAHESA

Ir. JONNI AGOES


Direktur Utama
DAFTAR ANALISA BIAYA KONSTRUKSI (ABK)
BANGUNAN GEDUNG DAN PERUMAHAN

PEKERJAAN PERSIAPAN ( SNI, 03 - 2835 - 2002)


HARGA
NO. URAIAN BAHAN UPAH
SATUAN

1 1 M' Pengukuran dan pemasangan bowplank


0.012 M3 Kayu 5 x 7 cm 2,000,000.00 24,000.00
0.020 Kg Besi paku 17,000.00 340.00
0.007 M3 Kayu papan 2,000,000.00 14,000.00
0.100 Oh Tukang kayu 130,000.00 13,000.00
0.100 Oh Pekerja 100,000.00 10,000.00
0.010 Oh Kepala tukang 140,000.00 1,400.00
0.005 Oh Mandor 140,000.00 700.00
Jumlah
Over Head
Jumlah Total
4 1 M2 Pembuatan kantor sementara dengan lantai plesteran
1.250 Btg Dolken kayu dia 8 s/d 10 pjg 400 cm 5,000.00 6,250.00
0.180 M Kayu
3
2,000,000.00 360,000.00
0.850 Kg Besi paku 17,000.00 14,450.00
1.100 Kg Besi strip 13,000.00 14,300.00
0.500 Zak Semen portland ( 50 Kg) 59,000.00 29,500.00
0.150 M Pasir pasangan
3
135,000.00 20,250.00
0.100 M Pasir beton
3
135,000.00 13,500.00
0.150 M3 Kerikil beton 150,000.00 22,500.00
30.000 Bh Batu bata 700.00 21,000.00
1.500 Hl Seng gelombang 42,500.00 63,750.00
0.080 M Kaca polos
2
94,000.00 7,520.00
0.060 Hl Plywood 4 mm 68,000.00 4,080.00
2.000 Oh Tukang kayu 130,000.00 260,000.00
1.000 Oh Tukang batu 130,000.00 130,000.00
2.000 Oh Pekerja 100,000.00 200,000.00
0.300 Oh Kepala tukang 140,000.00 42,000.00
0.050 Oh Mandor 140,000.00 7,000.00
Jumlah
Over Head
Jumlah Total
5 1 M2 Pembuatan gudang semen dan alat - alat / Penampungan
1.700 Btg Dolken kayu dia 8 s/d 10 pjg 400 cm 5,000.00 8,500.00
0.210 M Kayu
3
2,000,000.00 420,000.00
0.300 Kg Besi paku 17,000.00 5,100.00
0.210 Zak Semen portland ( 50 Kg) 59,000.00 12,390.00
0.030 M Pasir beton
3
135,000.00 4,050.00
0.050 M Kerikil beton
3
150,000.00 7,500.00
1.500 Hl Seng gelombang 42,500.00 63,750.00
2.000 Oh Tukang kayu 130,000.00 260,000.00
1.000 Oh Pekerja 100,000.00 100,000.00
0.200 Oh Kepala tukang 140,000.00 28,000.00
Jumlah
Over Head
Jumlah Total
2 1 M2 Membersihkan lapangan dan perataan
0.100 Oh Pekerja 100,000.00 10,000.00
0.050 Oh Mandor 140,000.00 7,000.00
Jumlah
Over Head
Jumlah Total
7 1 M2 Pembuatan jalan sementara
0.150 M3 Batu Kali 145,000.00 21,750.00
0.090 Kg Batu pecah 5/7 240,000.00 21,600.00
0.010 Hl Pasir pasangan 135,000.00 135,000.00
1.000 Oh Tukang kayu 130,000.00 130,000.00
0.050 Oh Mandor 140,000.00 7,000.00
Jumlah
Over Head
Jumlah Total
8 1 M3 Bongkaran beton bertulang
6.667 Oh Pekerja 100,000.00 666,700.00
0.333 Oh Mandor 140,000.00 46,620.00
Jumlah
Over Head
Jumlah Total
9 1 M3 Bongkaran dinding tembok bata merah
6.667 Oh Pekerja 100,000.00 666,700.00
0.033 Oh Mandor 140,000.00 4,620.00
Jumlah
Over Head
Jumlah Total
IAYA KONSTRUKSI (ABK)
UNG DAN PERUMAHAN

JUMLAH KETERANGAN

69,784.00
Kayu klas III

38,340.00 Kayu klas III

25,100.00
63,440.00
6,344.00
69,784.00
1,337,710.00

Kayu klas III

Bjls 20
Tebal 3 mm
577,100.00

639,000.00
1,216,100.00
121,610.00
1,337,710.00
1,000,219.00

521,290.00 Bjls 20
388,000.00
909,290.00
90,929.00
1,000,219.00
18,700.00

17,000.00
17,000.00
1,700.00
18,700.00
346,885.00

178,350.00

137,000.00
315,350.00
31,535.00
346,885.00
784,652.00

713,320.00
713,320.00
71,332.00
784,652.00
738,452.00

671,320.00
671,320.00
67,132.00
738,452.00
PEKERJAAN TANAH ( SNI 2835-2008 )
HARGA
NO. URAIAN BAHAN UPAH
SATUAN
1. 1 M3 Galian tanah biasa sedalam 1 meter
0.750 Oh Pekerja 100,000.00 75,000.00
0.025 Oh Mandor 140,000.00 3,500.00
Jumlah
Over Head
Jumlah Total
### 1 M3 Galian tanah biasa sedalam 2 meter
0.900 Oh Pekerja 100,000.00 90,000.00
0.045 Oh Mandor 140,000.00 6,300.00
Jumlah
Over Head
Jumlah Total
### 1 M3 Galian tanah biasa sedalam 3 meter
1.050 Oh Pekerja 100,000.00 105,000.00
0.067 Oh Mandor 140,000.00 9,380.00
Jumlah
Over Head
Jumlah Total
### 1 M3 Galian tanah keras sedalam 1 meter
1.000 Oh Pekerja 100,000.00 100,000.00
0.032 Oh Mandor 140,000.00 4,480.00
Jumlah
Over Head
Jumlah Total
### 1 M3 Galian tanah cadas sedalam 1 meter
1.500 Oh Pekerja 100,000.00 150,000.00
0.060 Oh Mandor 140,000.00 8,400.00
Jumlah
Over Head
Jumlah Total
### 1 M3 Galian tanah lumpur sedalam 1 meter
1.200 Oh Pekerja 100,000.00 120,000.00
0.045 Oh Mandor 140,000.00 6,300.00
Jumlah
Over Head
Jumlah Total
### 1 M3 Pembuangan tanah sejauh 30 meter
0.330 Oh Pekerja 100,000.00 33,000.00
0.010 Oh Mandor 140,000.00 1,400.00
Jumlah
Over Head
Jumlah Total
2. 1 M3 Urugan pasir
1.200 M3 Pasir urug 100,000.00 120,000.00
0.300 Oh Pekerja 100,000.00 30,000.00
0.010 Oh Mandor 140,000.00 1,400.00
Jumlah
Over Head
Jumlah Total
3. 1 M3 Urugan Tanah
1.200 M3 Tanah Urug 45,000.00 54,000.00
0.300 Oh Pekerja 100,000.00 30,000.00
0.010 Oh Mandor 140,000.00 1,400.00
Jumlah
Over Head
Jumlah Total
2 1 M3 Urugan kembali
0.250 Oh Pekerja 100,000.00 25,000.00
0.008 Oh Mandor 140,000.00 1,166.67
Jumlah
Over Head
Jumlah Total
JUMLAH KETERANGAN

86,350.00

78,500.00
78,500.00
7,850.00
86,350.00
105,930.00

96,300.00
96,300.00
9,630.00
105,930.00
125,818.00

114,380.00
114,380.00
11,438.00
125,818.00
114,928.00

104,480.00
104,480.00
10,448.00
114,928.00
174,240.00

158,400.00
158,400.00
15,840.00
174,240.00
138,930.00

126,300.00
126,300.00
12,630.00
138,930.00
37,840.00

34,400.00
34,400.00
3,440.00
37,840.00
166,540.00 0.11
120,000.00 0.132

31,400.00
151,400.00
15,140.00
166,540.00
93,940.00
54,000.00

31,400.00
85,400.00
8,540.00
93,940.00
28,783.33

26,166.67
26,166.67
2,616.67
28,783.33
PEKERJAAN PONDASI ( SNI 2836-2008)
HARGA
NO. URAIAN BAHAN UPAH
SATUAN
#REF! 1 M3 Pasang pondasi batu kali 1 Pc : 2 Ps
1.200 M3 Batu kali 145,000.00 174,000.00
267.000 Kg Semen portland ( 50 Kg) 1,180.00 315,060.00
0.427 M3 Pasir pasangan 135,000.00 57,645.00
1.500 Oh Pekerja 100,000.00 150,000.00
0.600 Oh Tukang batu 130,000.00 78,000.00
0.060 Oh Kepala tukang 140,000.00 8,400.00
0.075 Oh Mandor 140,000.00 10,500.00
Jumlah
Over Head
Jumlah Total
#REF! 1 M3 Pasang pondasi batu kali 1 Pc : 3 Ps
1.200 M3 Batu kali 145,000.00 174,000.00
202.000 Kg Semen portland ( 50 Kg) 1,180.00 238,360.00
0.485 M3 Pasir pasangan 135,000.00 65,475.00
1.500 Oh Pekerja 100,000.00 150,000.00
0.600 Oh Tukang batu 130,000.00 78,000.00
0.060 Oh Kepala tukang 140,000.00 8,400.00
0.075 Oh Mandor 140,000.00 10,500.00
Jumlah
Over Head
Jumlah Total
1. 1 M3 Pasang pondasi batu kali 1 Pc : 4 Ps
1.200 M3 Batu kali 145,000.00 174,000.00
163.000 Kg Semen portland ( 50 Kg) 1,180.00 192,340.00
0.520 M3 Pasir pasangan 135,000.00 70,200.00
1.500 Oh Pekerja 100,000.00 150,000.00
0.750 Oh Tukang batu 130,000.00 97,500.00
0.075 Oh Kepala tukang 140,000.00 10,500.00
0.075 Oh Mandor 140,000.00 10,500.00
Jumlah
Over Head
Jumlah Total
2. 1 M3 Pasang pondasi batu kosong
1.200 M3 Batu kali 145,000.00 174,000.00
0.432 M3 Pasir urug 100,000.00 43,200.00
0.780 Oh Pekerja 100,000.00 78,000.00
0.390 Oh Tukang batu 130,000.00 50,700.00
0.039 Oh Kepala tukang 140,000.00 5,460.00
0.039 Oh Mandor 140,000.00 5,460.00
Jumlah
Over Head
Jumlah Total
#REF! 1 M3 Pasang pondasi siklop 40 % batu kali
Kg Besi beton 9,500.00 -
194.000 Kg Semen portland ( 50 Kg) 1,180.00 228,920.00
0.312 M3 Pasir beton 135,000.00 42,120.00
0.468 M3 Kerikil beton 150,000.00 70,200.00
0.480 M3 Batu Kali 145,000.00 69,600.00
3.400 Oh Pekerja 100,000.00 340,000.00
0.850 Oh Tukang batu 130,000.00 110,500.00
0.085 Oh Kepala tukang 140,000.00 11,900.00
0.170 Oh Mandor 140,000.00 23,800.00
Jumlah
Over Head
Jumlah Total
#REF! 1 M3 Pasang pondasi sumuran diameter 100 cm
0.450 M3 Batu kali 145,000.00 65,250.00
194.000 Kg Semen portland ( 50 Kg) 1,180.00 228,920.00
0.312 Kg Pasir beton 135,000.00 42,120.00
0.468 M3 Kerikil beton 150,000.00 70,200.00
2.380 Oh Pekerja 100,000.00 238,000.00
0.300 Oh Tukang batu 130,000.00 39,000.00
0.030 Oh Kepala tukang 140,000.00 4,200.00
0.080 Oh Mandor 140,000.00 11,200.00
Jumlah
Over Head
Jumlah Total
#REF! 1 Bh Menurunkan cincin sumuran 1 M Pertama
0.938 Oh Pekerja 100,000.00 93,750.00
0.031 Oh Mandor 140,000.00 4,375.00
Jumlah
Over Head
Jumlah Total
#REF! 1 Bh Menurunkan cincin sumuran 1 M Kedua
1.125 Oh Pekerja 100,000.00 112,500.00
0.038 Oh Mandor 140,000.00 5,250.00
Jumlah
Over Head
Jumlah Total
#REF! 1 Bh Menurunkan cincin sumuran 1 M Ketiga
1.350 Oh Pekerja 100,000.00 135,000.00
0.045 Oh Mandor 140,000.00 6,300.00
Jumlah
Over Head
Jumlah Total
#REF! 1 Bh Menurunkan cincin sumuran 1 M Keempat
1.620 Oh Pekerja 100,000.00 162,000.00
0.054 Oh Mandor 140,000.00 7,560.00
Jumlah
Over Head
Jumlah Total
#REF! 1 Bh Menurunkan cincin sumuran 1 M Kelima
1.944 Oh Pekerja 100,000.00 194,400.00
0.065 Oh Mandor 140,000.00 9,072.00
Jumlah
Over Head
Jumlah Total
#REF! 1 BH CICIN SUMURAN DIA. 1.00 - 1.2 M
Cincin Sumuran
0.283 M3 Stamp Beton K 225 772,801.07 218,504.36
130.000 Kg Pembesian 11,826.65 1,537,464.51
Cetakan Sumuran Beton
0.990 M2 Cetakan Beton ( 6 x Pakai) 350,174.00 346,532.78
Jumlah
Over Head
Jumlah Total
JUMLAH KETERANGAN

872,965.50

546,705.00

246,900.00
793,605.00
79,360.50
872,965.50
797,208.50

477,835.00

246,900.00
724,735.00
72,473.50
797,208.50
775,544.00
1.370

436,540.00

268,500.00
705,040.00
70,504.00
775,544.00
392,502.00

217,200.00

139,620.00
356,820.00
35,682.00
392,502.00
986,744.00
410,840.00

486,200.00
897,040.00
89,704.00
986,744.00
768,779.00

406,490.00

292,400.00
698,890.00
69,889.00
768,779.00
107,937.50

98,125.00
98,125.00
9,812.50
107,937.50
129,525.00

117,750.00
117,750.00
11,775.00
129,525.00
155,430.00

141,300.00
141,300.00
14,130.00
155,430.00
186,516.00

169,560.00
169,560.00
16,956.00
186,516.00
223,819.20

203,472.00
203,472.00
20,347.20
223,819.20
2,312,751.81

218,504.36
1,537,464.51

346,532.78
2,102,501.64
210,250.16
2,312,751.81
PEKERJAAN BETON ( SNI 7394-2008 )
HARGA
NO. URAIAN BAHAN UPAH
SATUAN
1. 1 M3 Membuat Lantai Kerja Beton K - 100
230.0 Kg Semen portland ( 50 Kg) 1,180.00 271,400.00
0.638 M3 Pasir beton 135,000.00 86,110.71
0.761 M3 Koral beton 150,000.00 114,111.11
1.200 Oh Pekerja 100,000.00 120,000.00
0.200 Oh Tukang batu 130,000.00 26,000.00
0.020 Oh Kepala tukang 140,000.00 2,800.00
0.060 Oh Mandor 140,000.00 8,400.00
Jumlah
Over Head
Jumlah Total
2. 1 M3 Membuat Beton K - 100
247.0 Kg Semen portland ( 50 Kg) 1,180.00 291,460.00
0.621 M3 Pasir beton 135,000.00 83,796.43
0.740 M3 Koral beton 150,000.00 111,000.00
1.650 Oh Pekerja 100,000.00 165,000.00
0.275 Oh Tukang batu 130,000.00 35,750.00
0.028 Oh Kepala tukang 140,000.00 3,920.00
0.083 Oh Mandor 140,000.00 11,620.00
Jumlah
Over Head
Jumlah Total
### 1 M3 Membuat Beton K - 175
326.0 Kg Semen portland ( 50 Kg) 1,180.00 384,680.00
0.543 M3 Pasir beton 135,000.00 73,285.71
0.762 M3 Koral beton 150,000.00 114,333.33
1.650 Oh Pekerja #REF! #REF!
0.275 Oh Tukang batu #REF! #REF!
0.028 Oh Kepala tukang #REF! #REF!
0.083 Oh Mandor #REF! #REF!
Jumlah
Over Head
Jumlah Total
2 1 M3 Membuat Beton K - 225
371.0 Kg Semen portland ( 50 Kg) 1,180.00 437,780.00
0.499 M3 Pasir beton 135,000.00 67,307.14
0.776 M3 Koral beton 150,000.00 116,333.33
1.650 Oh Pekerja 100,000.00 165,000.00
0.275 Oh Tukang batu 130,000.00 35,750.00
0.028 Oh Kepala tukang 140,000.00 3,920.00
0.083 Oh Mandor 140,000.00 11,620.00
Jumlah
Over Head
Jumlah Total
3 1 Kg Pembesian dengan besi polos atau besi ulir
1.050 Kg Besi beton (polos/ulir) 9,500.00 9,975.00
0.015 Kg Kawat beton 15,000.00 225.00
0.007 Oh Pekerja 100,000.00 700.00
0.007 Oh Tukang besi 130,000.00 910.00
0.0007 Oh Kepala tukang 140,000.00 98.00
0.0004 Oh Mandor 140,000.00 56.00
Jumlah
Over Head
Jumlah Total
4 1 M2 Pasang bekisting untuk pondasi
0.040 M3 Kayu Kelas III 2,000,000.00 80,000.00
0.300 Kg Paku biasa 2" - 5" 17,000.00 5,100.00
0.100 Lt Minyak bekisting 17,000.00 1,700.00
0.520 Oh Pekerja 100,000.00 52,000.00
0.260 Oh Tukang kayu 130,000.00 33,800.00
0.026 Oh Kepala tukang 140,000.00 3,640.00
0.026 Oh Mandor 140,000.00 3,640.00
Jumlah
Over Head
Jumlah Total
5 1 M2 Pasang bekisting untuk sloof
0.045 M3 Kayu Kelas III 2,000,000.00 90,000.00
0.300 Kg Paku biasa 2" - 5" 17,000.00 5,100.00
0.100 Lt Minyak bekisting 17,000.00 1,700.00
0.520 Oh Pekerja 100,000.00 52,000.00
0.260 Oh Tukang kayu 130,000.00 33,800.00
0.026 Oh Kepala tukang 140,000.00 3,640.00
0.026 Oh Mandor 140,000.00 3,640.00
Jumlah
Over Head
Jumlah Total
6 1 M2 Pasang bekisting untuk kolom
0.040 M3 Kayu Kelas III 2,000,000.00 80,000.00
0.400 Kg Paku biasa 2" - 5" 17,000.00 6,800.00
0.200 Lt Minyak bekisting 17,000.00 3,400.00
0.015 M3 Balok kayu Kelas III 2,000,000.00 30,000.00
0.350 Lbr Plywood tebal 9 mm 200,000.00 70,000.00
2.000 Btg Dolken kayu galam dia. 8 - 10/4 m 5,000.00 10,000.00
0.660 Oh Pekerja 100,000.00 66,000.00
0.330 Oh Tukang kayu 130,000.00 42,900.00
0.033 Oh Kepala tukang 140,000.00 4,620.00
0.033 Oh Mandor 140,000.00 4,620.00
Jumlah
Over Head
Jumlah Total
7 1 M2 Pasang bekisting untuk balok
0.040 M3 Kayu Kelas III 2,000,000.00 80,000.00
0.400 Kg Paku biasa 2" - 5" 17,000.00 6,800.00
0.200 Lt Minyak bekisting 17,000.00 3,400.00
0.018 M3 Balok kayu Kelas III 2,000,000.00 36,000.00
0.350 Lbr Plywood tebal 9 mm 200,000.00 70,000.00
2.000 Btg Dolken kayu galam dia. 8 - 10/4 m 5,000.00 10,000.00
0.660 Oh Pekerja 100,000.00 66,000.00
0.330 Oh Tukang kayu 130,000.00 42,900.00
0.033 Oh Kepala tukang 140,000.00 4,620.00
0.033 Oh Mandor 140,000.00 4,620.00
Jumlah
Over Head
Jumlah Total
### 1 M2 Pasang bekisting untuk lantai
0.040 M3 Kayu Kelas III 2,000,000.00 80,000.00
0.400 Kg Paku biasa 2" - 5" 17,000.00 6,800.00
0.200 Lt Minyak bekisting 17,000.00 3,400.00
0.015 M3 Balok kayu Kelas III 2,000,000.00 30,000.00
0.350 Lbr Plywood tebal 9 mm 125,000.00 43,750.00
6.000 Btg Dolken kayu galam dia. 8 - 10/4 m 5,000.00 30,000.00
0.660 Oh Pekerja 100,000.00 66,000.00
0.330 Oh Tukang kayu 130,000.00 42,900.00
0.033 Oh Kepala tukang 140,000.00 4,620.00
0.033 Oh Mandor 140,000.00 4,620.00
Jumlah
Over Head
Jumlah Total
### 1 M2 Pasang bekisting untuk dinding
0.030 M3 Kayu Kelas III 2,000,000.00 60,000.00
0.400 Kg Paku biasa 2" - 5" 17,000.00 6,800.00
0.200 Lt Minyak bekisting 17,000.00 3,400.00
0.020 M3 Balok kayu Kelas III 2,000,000.00 40,000.00
0.350 Lbr Plywood tebal 9 mm 125,000.00 43,750.00
3.000 Btg Dolken kayu galam dia. 8 - 10/4 m 5,000.00 15,000.00
4.000 Bh Formtie/penjaga jarak bekisting /spacer 1,800.00 7,200.00
0.660 Oh Pekerja 100,000.00 66,000.00
0.330 Oh Tukang kayu 130,000.00 42,900.00
0.033 Oh Kepala tukang 140,000.00 4,620.00
0.033 Oh Mandor 140,000.00 4,620.00
Jumlah
Over Head
Jumlah Total
### 1 M2 Pasang bekisting untuk tangga
0.030 M3 Kayu Kelas III 2,000,000.00 60,000.00
0.400 Kg Paku biasa 2" - 5" 17,000.00 6,800.00
0.150 Lt Minyak bekisting 17,000.00 2,550.00
0.015 M3 Balok kayu Kelas III 2,000,000.00 30,000.00
0.350 Lbr Plywood tebal 9 mm 200,000.00 70,000.00
2.000 Btg Dolken kayu galam dia. 8 - 10/4 m 5,000.00 10,000.00
0.660 Oh Pekerja 100,000.00 66,000.00
0.330 Oh Tukang kayu 130,000.00 42,900.00
0.033 Oh Kepala tukang 140,000.00 4,620.00
0.033 Oh Mandor 140,000.00 4,620.00
Jumlah
Over Head
Jumlah Total
### 1 M3 Membuat pondasi beton bertulang (150 Kg besi + bekisting)
0.200 M3 Kayu Kelas III 2,000,000.00 400,000.00
1.500 Kg Paku biasa 2" - 5" 17,000.00 25,500.00
0.400 Lt Minyak bekisting 17,000.00 6,800.00
157.500 Kg Besi beton polos 9,500.00 1,496,250.00
2.250 Kg Kawat beton 15,000.00 33,750.00
336.000 Zak Semen portland ( 50 Kg) 1,180.00 396,480.00
0.540 M3 Pasir beton 135,000.00 72,900.00
0.810 M3 Koral beton 150,000.00 121,500.00
5.300 Oh Pekerja 100,000.00 530,000.00
0.275 Oh Tukang batu 130,000.00 35,750.00
1.300 Oh Tukang kayu 130,000.00 169,000.00
1.050 Oh Tukang besi 130,000.00 136,500.00
0.262 Oh Kepala tukang 140,000.00 36,680.00
0.265 Oh Mandor 140,000.00 37,100.00
Jumlah
Over Head
Jumlah Total
### 1 M3 Membuat sloof beton bertulang (200 Kg besi + bekisting)
0.270 M3 Kayu Kelas III 2,000,000.00 540,000.00
2.000 Kg Paku biasa 2" - 5" 17,000.00 34,000.00
0.600 Lt Minyak bekisting 17,000.00 10,200.00
210.000 KgBesi beton polos 9,500.00 1,995,000.00
3.000 KgKawat beton 15,000.00 45,000.00
336.000 KgSemen portland ( 50 Kg) 1,180.00 396,480.00
0.540 M3Pasir beton 135,000.00 72,900.00
0.810 M3Koral beton 150,000.00 121,500.00
5.650 OhPekerja 100,000.00 565,000.00
0.275 OhTukang batu 130,000.00 35,750.00
1.560 OhTukang kayu 130,000.00 202,800.00
1.400 OhTukang besi 130,000.00 182,000.00
0.323 OhKepala tukang 140,000.00 45,220.00
0.283 OhMandor 140,000.00 39,620.00
Jumlah
Over Head
Jumlah Total
### 1 M3 Membuat kolom beton bertulang (300 Kg besi + bekisting)
0.400 M3 Kayu Kelas III 2,000,000.00 800,000.00
4.000 Kg Paku biasa 2" - 5" 17,000.00 68,000.00
2.000 Lt Minyak bekisting 17,000.00 34,000.00
315.000 Kg Besi beton polos 9,500.00 2,992,500.00
4.500 Kg Kawat beton 15,000.00 67,500.00
336.000 Kg Semen portland ( 50 Kg) 1,180.00 396,480.00
0.540 M3 Pasir beton 135,000.00 72,900.00
0.810 M3 Koral beton 150,000.00 121,500.00
0.150 M3 Kayu balok Kelas III 2,000,000.00 300,000.00
3.500 Lbr Plywood 9 mm 200,000.00 700,000.00
20.000 Btg Dolken dia. 8 cm/4 m 5,000.00 100,000.00
7.050 Oh Pekerja 100,000.00 705,000.00
0.275 Oh Tukang batu 130,000.00 35,750.00
1.650 Oh Tukang kayu 130,000.00 214,500.00
2.100 Oh Tukang besi 130,000.00 273,000.00
0.403 Oh Kepala tukang 140,000.00 56,420.00
0.353 Oh Mandor 140,000.00 49,420.00
Jumlah
Over Head
Jumlah Total
### 1 M3 Membuat balok beton bertulang (200 Kg besi + bekisting)
0.320 M3 Kayu Kelas III 2,000,000.00 640,000.00
3.200 Kg Paku biasa 2" - 5" 17,000.00 54,400.00
1.600 Lt Minyak bekisting 17,000.00 27,200.00
210.000 Kg Besi beton polos 9,500.00 1,995,000.00
3.000 Kg Kawat beton 15,000.00 45,000.00
336.000 Kg Semen portland ( 50 Kg) 1,180.00 396,480.00
0.540 M3 Pasir beton 135,000.00 72,900.00
0.810 M3 Koral beton 150,000.00 121,500.00
0.140 M3 Kayu balok Kelas III 2,000,000.00 280,000.00
2.800 Lbr Plywood 9 mm 200,000.00 560,000.00
16.000 Btg Dolken dia. 8 cm/4 m 5,000.00 80,000.00
6.350 Oh Pekerja #REF! #REF!
0.275 Oh Tukang batu #REF! #REF!
1.650 Oh Tukang kayu #REF! #REF!
1.400 Oh Tukang besi #REF! #REF!
0.333 Oh Kepala tukang #REF! #REF!
0.318 Oh Mandor #REF! #REF!
Jumlah
Over Head
Jumlah Total
### 1 M3 Membuat kolom beton bertulang (150 Kg besi + bekisting)
0.320 M3 Kayu Kelas III 2,000,000.00 640,000.00
3.200 Kg Paku biasa 2" - 5" 17,000.00 54,400.00
1.600 Lt Minyak bekisting 17,000.00 27,200.00
157.500 Kg Besi beton polos 9,500.00 1,496,250.00
2.250 Kg Kawat beton 15,000.00 33,750.00
336.000 Zak Semen portland ( 50 Kg) 1,180.00 396,480.00
0.540 M3 Pasir beton 135,000.00 72,900.00
0.810 M3 Koral beton 150,000.00 121,500.00
0.120 M3 Kayu balok Kelas III 2,000,000.00 240,000.00
2.800 Lbr Plywood 9 mm 200,000.00 560,000.00
32.000 Btg Dolken dia. 8 cm/4 m 5,000.00 160,000.00
5.300 Oh Pekerja #REF! #REF!
0.275 Oh Tukang batu #REF! #REF!
1.300 Oh Tukang kayu #REF! #REF!
1.050 Oh Tukang besi #REF! #REF!
0.265 Oh Kepala tukang #REF! #REF!
0.265 Oh Mandor #REF! #REF!
Jumlah
Over Head
Jumlah Total
### 1 M3 Membuat dinding beton bertulang (150 Kg besi + bekisting)
0.240 M3 Kayu Kelas III 2,000,000.00 480,000.00
3.200 Kg Paku biasa 2" - 5" 17,000.00 54,400.00
1.600 Lt Minyak bekisting 17,000.00 27,200.00
157.500 Kg Besi beton polos 9,500.00 1,496,250.00
2.250 Kg Kawat beton 15,000.00 33,750.00
336.000 Zak Semen portland ( 50 Kg) 1,180.00 396,480.00
0.540 M3 Pasir beton 135,000.00 72,900.00
0.810 M3 Koral beton 150,000.00 121,500.00
0.160 M3 Kayu balok Kelas III 2,000,000.00 320,000.00
2.800 Lbr
Plywood 9 mm 200,000.00 560,000.00
24.000 Btg
Dolken dia. 8 cm/4 m 5,000.00 120,000.00
5.300 OhPekerja #REF! #REF!
0.275 OhTukang batu #REF! #REF!
1.300 OhTukang kayu #REF! #REF!
1.050 OhTukang besi #REF! #REF!
2.620 OhKepala tukang #REF! #REF!
0.265 OhMandor #REF! #REF!
Jumlah
Over Head
Jumlah Total
### 1 M3 Membuat dinding beton bertulang (200 Kg besi + bekisting)
0.250 M3 Kayu Kelas III 2,000,000.00 500,000.00
3.000 Kg Paku biasa 2" - 5" 17,000.00 51,000.00
1.200 Lt Minyak bekisting 17,000.00 20,400.00
210.000 Kg Besi beton polos 9,500.00 1,995,000.00
3.000 Kg Kawat beton 15,000.00 45,000.00
336.000 Zak Semen portland ( 50 Kg) 1,180.00 396,480.00
0.540 M3 Pasir beton 135,000.00 72,900.00
0.810 M3 Koral beton 150,000.00 121,500.00
0.105 M3 Kayu balok Kelas III 2,000,000.00 210,000.00
2.500 Lbr Plywood 9 mm 200,000.00 500,000.00
14.000 Btg Dolken dia. 8 cm/4 m 5,000.00 70,000.00
5.650 Oh Pekerja #REF! #REF!
0.275 Oh Tukang batu #REF! #REF!
1.560 Oh Tukang kayu #REF! #REF!
1.400 Oh Tukang besi #REF! #REF!
0.323 Oh Kepala tukang #REF! #REF!
0.283 Oh Mandor #REF! #REF!
Jumlah
Over Head
Jumlah Total
8 1 M1 Membuat kolom penguat beton bertulang (11 x 11) cm (kolom praktis)
0.002 M3 Kayu Kelas III 2,000,000.00 4,000.00
0.010 Kg Paku biasa 2" - 5" 17,000.00 170.00
3.000 Kg Besi beton polos 9,500.00 28,500.00
0.045 Kg Kawat beton 15,000.00 675.00
4.000 Kg Semen portland ( 50 Kg) 1,180.00 4,720.00
0.006 M3 Pasir beton 135,000.00 810.00
0.009 M3 Koral beton 150,000.00 1,350.00
0.180 Oh Pekerja 100,000.00 18,000.00
0.020 Oh Tukang batu 130,000.00 2,600.00
0.020 Oh Tukang kayu 130,000.00 2,600.00
0.020 Oh Tukang besi 130,000.00 2,600.00
0.006 Oh Kepala tukang 140,000.00 840.00
0.009 Oh Mandor 140,000.00 1,260.00
Jumlah
Over Head
Jumlah Total
10. 1 M1 Membuat ring balok beton bertulang (15 x 20) cm
0.003 M3 Kayu Kelas III 2,000,000.00 6,000.00
0.020 Kg Paku biasa 2" - 5" 17,000.00 340.00
6.300 Kg Besi beton polos 9,500.00 59,850.00
0.050 Kg Kawat beton 15,000.00 750.00
5.500 Kg Semen portland ( 50 Kg) 1,180.00 6,490.00
0.010 M3 Pasir beton 135,000.00 1,350.00
0.025 M3 Koral beton 150,000.00 3,750.00
0.297 Oh Pekerja 100,000.00 29,700.00
0.033 Oh Tukang batu 130,000.00 4,290.00
0.033 Oh Tukang kayu 130,000.00 4,290.00
0.033 Oh Tukang besi 130,000.00 4,290.00
0.010 Oh Kepala tukang 140,000.00 1,400.00
0.015 Oh Mandor 140,000.00 2,100.00
Jumlah
Over Head
Jumlah Total
JUMLAH KETERANGAN

691,704.01

471,621.83

157,200.00
628,821.83
62,882.18
691,704.01
772,801.07

486,256.43

216,290.00
702,546.43
70,254.64
772,801.07
#REF!

572,299.05

#REF!
#REF!
#REF!
#REF!
921,481.52

621,420.48

216,290.00
837,710.48
83,771.05
921,481.52
13,160.40

10,200.00
1,764.00
11,964.00
1,196.40
13,160.40

Kayu klas III

86,800.00

93,080.00
179,880.00
17,988.00
197,868.00
208,868.00
Kayu klas III

96,800.00

93,080.00
189,880.00
18,988.00
208,868.00
350,174.00
Kayu klas III

200,200.00

118,140.00
318,340.00
31,834.00
350,174.00
356,774.00
Kayu klas III

206,200.00

118,140.00
324,340.00
32,434.00
356,774.00
343299
Kayu klas III

193,950.00

118,140.00
312,090.00
31,209.00
343,299.00
323,719.00
Kayu klas III

176,150.00

118,140.00
294,290.00
29,429.00
323,719.00
327,239.00
Kayu klas III

179,350.00

118,140.00
297,490.00
29,749.00
327,239.00
3,848,031.00
Kayu klas III

2,553,180.00

945,030.00
3,498,210.00
349,821.00
3,848,031.00
4714017
Kayu klas III
3,215,080.00

1,070,390.00
4,285,470.00
428,547.00
4,714,017.00
7,685,667.00
Kayu klas III

5,652,880.00

1,334,090.00
6,986,970.00
698,697.00
7,685,667.00
5,514,382.50
Kayu klas III

4,272,480.00

740,595.00
5,013,075.00
501,307.50
5,514,382.50
4848063
Kayu klas III

3,802,480.00

604,850.00
4,407,330.00
440,733.00
4,848,063.00
4,962,160.50
Kayu klas III
3,682,480.00

828,575.00
4,511,055.00
451,105.50
4,962,160.50
5132490
Kayu klas III

3,982,280.00

683,620.00
4,665,900.00
466,590.00
5,132,490.00
74,937.50
Kayu klas III

40,225.00

27,900.00
68,125.00
6,812.50
74,937.50
137,060.00
Kayu klas III

78,530.00

46,070.00
124,600.00
12,460.00
137,060.00
PEKERJAAN DINDING ( SNI 6897-2008)
HARGA
NO. URAIAN BAHAN UPAH
SATUAN
### 1 M2 Pasangan bata merah tebal 1 bata, 1 Pc : 2 Ps
140.00 Bh Bata merah 5 x 11 x 22 cm 700.00 98,000.00
43.500 Kg Semen portland ( 50 Kg) 1,180.00 51,330.00
0.080 M3 Pasir pasangan 135,000.00 10,800.00
0.600 Oh Pekerja 65,000.00 39,000.00
0.200 Oh Tukang batu 80,000.00 16,000.00
0.020 Oh Kepala tukang 95,000.00 1,900.00
0.030 Oh Mandor 95,000.00 2,850.00
Jumlah
Over Head
Jumlah Total
### 1 M2 Pasangan bata merah tebal 1 bata, 1 Pc : 3 Ps
140.00 Bh Bata merah 5 x 11 x 22 cm 700.00 98,000.00
32.950 Kg Semen portland ( 50 Kg) 1,180.00 38,881.00
0.091 M3 Pasir pasangan 135,000.00 12,285.00
0.600 Oh Pekerja 65,000.00 39,000.00
0.200 Oh Tukang batu 80,000.00 16,000.00
0.020 Oh Kepala tukang 95,000.00 1,900.00
0.030 Oh Mandor 95,000.00 2,850.00
Jumlah
Over Head
Jumlah Total
### 1 M2 Pasangan bata merah tebal 1 bata, 1 Pc : 4 Ps
140.00 Bh Bata merah 5 x 11 x 22 cm 700.00 98,000.00
26.550 Kg Semen portland ( 50 Kg) 1,180.00 31,329.00
0.093 M3 Pasir pasangan 135,000.00 12,555.00
0.600 Oh Pekerja 65,000.00 39,000.00
0.200 Oh Tukang batu 80,000.00 16,000.00
0.020 Oh Kepala tukang 95,000.00 1,900.00
0.030 Oh Mandor 95,000.00 2,850.00
Jumlah
Over Head
Jumlah Total
1 1 M2 Pasangan bata merah tebal 1/2 bata, 1 Pc : 2 Ps
70.000 Bh Bata merah 5 x 11 x 22 cm 700.00 49,000.00
18.950 Kg Semen portland ( 50 Kg) 1,180.00 22,361.00
0.038 M3 Pasir pasangan 135,000.00 5,130.00
0.300 Oh Pekerja 100,000.00 30,000.00
0.100 Oh Tukang batu 130,000.00 13,000.00
0.010 Oh Kepala tukang 140,000.00 1,400.00
0.015 Oh Mandor 140,000.00 2,100.00
Jumlah
Over Head
Jumlah Total
2 1 M2 Pasangan bata merah tebal 1/2 bata, 1 Pc : 4 Ps
70.000 Bh Bata merah 5 x 11 x 22 cm 700.00 49,000.00
11.500 Kg Semen portland ( 50 Kg) 1,180.00 13,570.00
0.043 M3 Pasir pasangan 135,000.00 5,805.00
0.300 OhPekerja 100,000.00 30,000.00
0.100 OhTukang batu 130,000.00 13,000.00
0.010 OhKepala tukang 140,000.00 1,400.00
0.015 OhMandor 140,000.00 2,100.00
Jumlah
Over Head
Jumlah Total
### 1 M2 Pasangan bata merah tebal 1/2 bata, 1 Pc : 5 Ps
70.000 Bh Bata merah 5 x 11 x 22 cm 700.00 49,000.00
9.680 Kg Semen portland ( 50 Kg) 1,180.00 11,422.40
0.045 M3 Pasir pasangan 135,000.00 6,075.00
0.300 Oh Pekerja 65,000.00 19,500.00
0.100 Oh Tukang batu 80,000.00 8,000.00
0.010 Oh Kepala tukang 95,000.00 950.00
0.015 Oh Mandor 95,000.00 1,425.00
Jumlah
Over Head
Jumlah Total
### 1 M2 Pasangan Rolag Bata, 1 Pc : 4 Ps
100.00 Bh Bata merah 5 x 11 x 22 cm 700.00 70,000.00
26.550 Kg Semen portland ( 50 Kg) 1,180.00 31,329.00
0.093 M3 Pasir pasangan 135,000.00 12,555.00
0.650 Oh Pekerja 65,000.00 42,250.00
0.200 Oh Tukang batu 80,000.00 16,000.00
0.020 Oh Kepala tukang 95,000.00 1,900.00
0.030 Oh Mandor 95,000.00 2,850.00
Jumlah
Over Head
Jumlah Total
### 1 M2 Pasangan dinding hollowblock (HB. 20)
12.500 Bh Hollow block (HB. 20) 1,600.00 20,000.00
0.270 Zak Semen portland ( 50 Kg) 1,180.00 318.60
0.048 M3 Pasir pasangan 135,000.00 6,480.00
1.950 Kg Besi beton polos 9,000.00 17,550.00
0.350 Oh Pekerja 65,000.00 22,750.00
0.150 Oh Tukang batu 80,000.00 12,000.00
0.015 Oh Kepala tukang 95,000.00 1,425.00
0.017 Oh Mandor 95,000.00 1,615.00
Jumlah
### 1 M2 Pasangan dinding hollowblock (HB. 15)
12.500 Bh Hollow block (HB. 15) 1,600.00 20,000.00
0.209 Zak Semen portland ( 50 Kg) 1,180.00 246.62
0.038 M3 Pasir pasangan 135,000.00 5,130.00
1.950 Kg Besi beton polos 9,000.00 17,550.00
0.320 Oh Pekerja 65,000.00 20,800.00
0.120 Oh Tukang batu 80,000.00 9,600.00
0.012 Oh Kepala tukang 95,000.00 1,140.00
0.015 Oh Mandor 95,000.00 1,425.00
Jumlah
### 1 M2 Pasangan dinding hollowblock (HB. 10)
12.500 Bh Hollow block (HB. 10) 1,600.00 20,000.00
0.150 Zak Semen portland ( 50 Kg) 1,180.00 177.00
0.027 M3 Pasir pasangan 135,000.00 3,645.00
1.950 Kg Besi beton polos 9,000.00 17,550.00
0.320 Oh Pekerja 65,000.00 20,800.00
0.100 Oh Tukang batu 80,000.00 8,000.00
0.010 Oh Kepala tukang 95,000.00 950.00
0.015 Oh Mandor 95,000.00 1,425.00
Jumlah

### 1 M2 Pasangan dinding conblock (CB. 20)


12.500 Bh Concrete block (CB. 20) - -
0.281 Zak Semen portland ( 50 Kg) - -
0.004 M3 Pasir beton - -
0.042 M3 Pasir pasangan - -
3.870 Kg Besi beton polos - -
0.006 Kg Paku biasa 2" - 5" - -
0.001 Kg Kayu terentang - -
0.030 Kg Kawat beton - -
0.005 Kg Kerikil beton - -
0.370 Oh Pekerja 65,000.00 24,050.00
0.157 Oh Tukang batu 80,000.00 12,560.00
0.007 Oh Tukang besi 80,000.00 560.00
0.0164 Oh Kepala tukang 95,000.00 1,558.00
0.0185 Oh Mandor 95,000.00 1,757.50
Jumlah
### 1 M2 Pasangan dinding conblock (CB. 15)
12.500 Bh Concrete block (CB. 15) - -
0.281 Zak Semen portland ( 50 Kg) - -
0.003 M3 Pasir beton - -
0.032 M3 Pasir pasangan - -
0.870 Kg Besi beton polos dia. 8 mm - -
0.004 Kg Paku biasa 2" - 5" - -
0.001 Kg Kayu terentang - -
0.020 Kg Kawat beton - -
0.004 Kg Kerikil beton - -
0.340 Oh Pekerja 65,000.00 22,100.00
0.130 Oh Tukang batu 80,000.00 10,400.00
0.007 Oh Tukang besi 80,000.00 560.00
0.0137 Oh Kepala tukang 95,000.00 1,301.50
0.0170 Oh Mandor 95,000.00 1,615.00
Jumlah
### 1 M2 Pasangan dinding conblock (CB. 10)
12.500 Bh Concrete block (CB. 10) - -
0.144 Zak Semen portland ( 50 Kg) - -
0.002 M3 Pasir beton - -
0.021 M3 Pasir pasangan - -
2.540 Kg Besi beton polos - -
0.003 Kg Paku biasa 2" - 5" - -
0.001 Kg Kayu terentang - -
0.015 Kg Kawat beton - -
0.003 Kg Kerikil beton - -
0.340 Oh Pekerja 65,000.00 22,100.00
0.107 Oh Tukang batu 80,000.00 8,560.00
0.007 Oh Tukang besi 80,000.00 560.00
0.0114 Oh Kepala tukang 95,000.00 1,083.00
0.0170 Oh Mandor 95,000.00 1,615.00
Jumlah

### 1 M2 Pasang dinding latai


2.500 Bh Bondbeam 40 x 20 x 20 cm - -
0.102 Zak Semen portland ( 50 Kg) - -
0.080 M3 Pasir beton - -
1.500 Kg Besi beton polos - -
0.150 M3 Kerikil beton - -
0.100 Oh Pekerja 65,000.00 6,500.00
0.030 Oh Tukang batu 80,000.00 2,400.00
0.030 Oh Tukang besi 80,000.00 2,400.00
0.006 Oh Kepala tukang 95,000.00 570.00
0.005 Oh Mandor 95,000.00 475.00
Jumlah
### 1 M2 Pasang dinding roster/terawang (12 x 11 x 24) cm
36.000 Bh Roster/terawang - -
0.256 Zak Semen portland ( 50 Kg) - -
0.035 M3 Pasir pasangan - -
0.300 Oh Pekerja 65,000.00 19,500.00
0.100 Oh Tukang batu 80,000.00 8,000.00
0.010 Oh Kepala tukang 95,000.00 950.00
0.015 Oh Mandor 95,000.00 1,425.00
Jumlah
### 1 M2 Pasang dinding berongga ukuran (5 x 11 x 24) cm
80.000 Bh Bata berongga - -
0.473 Zak Semen portland ( 50 Kg) - -
0.570 M3 Pasir pasangan - -
0.320 Oh Pekerja 65,000.00 20,800.00
0.150 Oh Tukang batu 80,000.00 12,000.00
0.015 Oh Kepala tukang 95,000.00 1,425.00
0.015 Oh Mandor 95,000.00 1,425.00
Jumlah
### 1 M2 Pasang dinding anyaman bambu, rangka kayu
1.500 M2 Bilik bambu - -
0.014 M3 Kayu 5/7 - -
0.012 Kg Besi paku - -
0.003 M3 List Kayu 2/7 - -
0.100 Oh Pekerja 65,000.00 6,500.00
0.050 Oh Tukang batu 80,000.00 4,000.00
0.005 Oh Kepala tukang 95,000.00 475.00
0.002 Oh Mandor 95,000.00 190.00
Jumlah
### 1 M2 Plesteran waterfroof batacote 3 lapis
0.010 Zak Semen portland ( 50 Kg) - -
2.900 Kg Batacote - -
0.006 M3 Pasir pasangan - -
0.300 Oh Pekerja 65,000.00 19,500.00
0.200 Oh Tukang batu 80,000.00 16,000.00
0.020 Oh Kepala tukang 95,000.00 1,900.00
0.015 Oh Mandor 95,000.00 1,425.00
Jumlah
JUMLAH KETERANGAN

241,868.00

160,130.00

59,750.00
219,880.00
21,988.00
241,868.00
229,807.60

149,166.00

59,750.00
208,916.00
20,891.60
229,807.60
221,797.40

141,884.00

59,750.00
201,634.00
20,163.40
221,797.40
135,290.10 2.16
151.2
40.93 0.82
76,491.00

46,500.00
122,991.00
12,299.10
135,290.10
126,362.50

68,375.00
46,500.00
114,875.00
11,487.50
126,362.50
129,234.90

66,497.40

29,875.00
96,372.40
2,987.50
129,234.90
246,184.00

113,884.00

63,000.00
176,884.00
6,300.00
246,184.00
82,138.60

44,348.60

37,790.00
82,138.60
75,891.62

42,926.62

32,965.00
75,891.62
72,547.00
41,372.00

31,175.00
72,547.00

40,485.50

Kayu klas III

40,485.50
40,485.50
35,976.50

Kayu klas III

35,976.50
35,976.50
33,918.00

Kayu klas III

-
33,918.00
33,918.00

12,345.00

12,345.00
12,345.00
29,875.00

29,875.00
29,875.00
35,650.00

35,650.00
35,650.00
11,165.00

Kayu klas III

- Kayu klas III

11,165.00
11,165.00
38,825.00

-
38,825.00
38,825.00
PEKERJAAN PLESTERAN ( SNI 2837-2008)
HARGA
NO. URAIAN BAHAN UPAH
SATUAN
1 1 M2 Plesteran 1 Pc : 2 Ps, tebal 15 mm
10.224 Kg Semen portland ( 50 Kg) 1,180.00 12,064.32
0.020 M3 Pasir pasangan 135,000.00 2,700.00
0.300 Oh Pekerja #REF! #REF!
0.150 Oh Tukang batu #REF! #REF!
0.015 Oh Kepala tukang #REF! #REF!
0.010 Oh Mandor #REF! #REF!
Jumlah
Over Head
Jumlah Total
2 1 M2 Plesteran 1 Pc : 4 Ps, tebal 15 mm
6.240 Kg Semen portland ( 50 Kg) 1,180.00 7,363.20
0.024 M3 Pasir pasangan 135,000.00 3,240.00
0.300 Oh Pekerja #REF! #REF!
0.150 Oh Tukang batu #REF! #REF!
0.015 Oh Kepala tukang #REF! #REF!
0.010 Oh Mandor #REF! #REF!
Jumlah
Over Head
Jumlah Total
3 1 M' Pasang List Beton
10.224 Kg Semen portland ( 50 Kg) 1,180.00 12,064.32
0.020 M3 Pasir pasangan 135,000.00 2,700.00
0.400 Oh Pekerja #REF! #REF!
0.300 Oh Tukang batu #REF! #REF!
0.030 Oh Kepala tukang #REF! #REF!
0.020 Oh Mandor #REF! #REF!
Jumlah
Over Head
Jumlah Total
4 1 M2 acian
3.250 Kg Semen portland ( 50 Kg) 1,180.00 3,835.00
0.200 Oh Pekerja #REF! #REF!
0.100 Oh Tukang batu #REF! #REF!
0.010 Oh Kepala tukang #REF! #REF!
0.010 Oh Mandor #REF! #REF!
Jumlah
Over Head
Jumlah Total
JUMLAH KETERANGAN

#REF! 34.7
354.7728 7.095456
14,764.32 0.694
Pekerja
Tukang batu
Kepala tukang
#REF! Mandor
#REF!
#REF!
#REF!
#REF! 92.31
0.125 576.0144 11.520288
10,603.20 2.21544

#REF!
#REF!
#REF!
#REF!
#REF!

14,764.32

#REF!
#REF!
#REF!
#REF!
#REF!
3,835.00

#REF!
#REF!
#REF!
#REF!
PEKERJAAN KAYU ( SNI 3434-2008)
HARGA
NO. URAIAN BAHAN UPAH
SATUAN
#REF! 1 M3 Pasang kosen pintu dan jendela kayu borneo (Kelas I)
1.100 M3 Kayu borneo, balok 8,000,000.00 8,800,000.00
1.250 kg Paku 17,000.00 21,250.00
1.000 kg Lem Kayu 15,000.00 15,000.00
6.000 Oh Pekerja 100,000.00 600,000.00
20.000 Oh Tukang kayu 130,000.00 2,600,000.00
2.000 Oh Kepala tukang 140,000.00 280,000.00
0.300 Oh Mandor 140,000.00 42,000.00
Jumlah
Over Head
Jumlah Total
1 1 M3 Pasang kosen pintu dan jendela kayu Kelas II
1.200 M3 Kayu balok 6,000,000.00 7,200,000.00
1.250 kg Paku 17,000.00 21,250.00
1.000 kg Lem Kayu 15,000.00 15,000.00
6.000 Oh Pekerja 100,000.00 600,000.00
18.000 Oh Tukang kayu 130,000.00 2,340,000.00
1.800 Oh Kepala tukang 140,000.00 252,000.00
0.300 Oh Mandor 140,000.00 42,000.00
Jumlah
Over Head
Jumlah Total
#REF! 1 M2 Pasang pintu klamp kayu Marsawa (Kelas II)
0.040 M3 Kayu marsawa papan 6,000,000.00 240,000.00
0.050 Kg Paku biasa 2" - 5" 17,000.00 850.00
0.350 Oh Pekerja 100,000.00 35,000.00
1.050 Oh Tukang kayu 130,000.00 136,500.00
0.105 Oh Kepala tukang 140,000.00 14,700.00
0.018 Oh Mandor 140,000.00 2,520.00
Jumlah
Over Head
Jumlah Total
#REF! 1 M2 Pasang pintu panel kayu Borneo (Kelas I)
0.040 M3 Kayu borneo papan 8,000,000.00 320,000.00
0.500 kg Lem Kayu 15,000.00 7,500.00
1.000 Oh Pekerja 100,000.00 100,000.00
2.500 Oh Tukang kayu 130,000.00 325,000.00
0.250 Oh Kepala tukang 140,000.00 35,000.00
0.050 Oh Mandor 140,000.00 7,000.00
Jumlah
Over Head
Jumlah Total
2 1 M2 Pasang pintu panel kayu Kelas II
0.040 M3 Kayu papan 6,000,000.00 240,000.00
0.500 kg Lem Kayu 15,000.00 7,500.00
1.000 Oh Pekerja 100,000.00 100,000.00
3.000 Oh Tukang kayu 130,000.00 390,000.00
0.300 Oh Kepala tukang 140,000.00 42,000.00
0.030 Oh Mandor 140,000.00 4,200.00
Jumlah
Over Head
Jumlah Total
3 1 M2 Pasang pintu dan jendela kaca kayu Kelas I
1.100 M3 Kayu papan 8,000,000.00 8,800,000.00
0.300 kg Lem Kayu 15,000.00 4,500.00
0.800 Oh Pekerja 100,000.00 80,000.00
2.400 Oh Tukang kayu 130,000.00 312,000.00
0.240 Oh Kepala tukang 140,000.00 33,600.00
0.040 Oh Mandor 140,000.00 5,600.00
Jumlah
Over Head
Jumlah Total
3 1 M2 Pasang Konstruksi kuda-kuda kayu kelas II
1.100 M3 Kayu balok 8,000,000.00 8,800,000.00
15.000 Kg Besi strip 9,500.00 142,500.00
5.600 Kg Paku biasa 2" - 5" 17,000.00 95,200.00
4.000 Oh Pekerja 100,000.00 400,000.00
12.000 Oh Tukang kayu 130,000.00 1,560,000.00
1.200 Oh Kepala tukang 140,000.00 168,000.00
0.200 Oh Mandor 140,000.00 28,000.00
Jumlah
Over Head
Jumlah Total
4 1 M3 Pasang Konstruksi Gordeng kayu kelas II
1.100 M3 Kayu balok 8,000,000.00 8,800,000.00
15.000 Kg Besi strip 9,500.00 142,500.00
3.000 Kg Paku biasa 2" - 5" 17,000.00 51,000.00
2.400 Oh Pekerja 100,000.00 240,000.00
7.200 Oh Tukang kayu 130,000.00 936,000.00
0.720 Oh Kepala tukang 140,000.00 100,800.00
0.120 Oh Mandor 140,000.00 16,800.00
Jumlah
Over Head
Jumlah Total
5 1 M2 Pasang rangka langit-langit (60 x 60) m kayu kelas II
0.0163 M3 Kayu balok 8,000,000.00 130,400.00
0.250 Kg Paku biasa 2" - 5" 17,000.00 4,250.00
0.200 Oh Pekerja 100,000.00 20,000.00
0.300 Oh Tukang kayu 130,000.00 39,000.00
0.030 Oh Kepala tukang 140,000.00 4,200.00
0.010 Oh Mandor 140,000.00 1,400.00
Jumlah
Over Head
Jumlah Total
6 1 M' Pasang lisplang ukuran (3 x 30) cm kayu Marsawa (Kelas II)
0.011 M3 Kayu marsawa papan 8,000,000.00 88,000.00
0.050 Kg Paku biasa 2" - 5" 17,000.00 850.00
0.110 Oh Pekerja 100,000.00 11,000.00
0.200 Oh Tukang kayu 130,000.00 26,000.00
0.020 Oh Kepala tukang 140,000.00 2,800.00
0.005 Oh Mandor 140,000.00 700.00
Jumlah
Over Head
Jumlah Total
7 1 M2 Pas. dinding pemisah plywood rangkap rangka kayu marsawa (Kelas II)
0.028 M3 Kayu marsawa balok 8,000,000.00 224,000.00
0.150 Kg Paku biasa 2" - 5" 17,000.00 2,550.00
0.560 Lt Lem kayu 15,000.00 8,400.00
0.860 Lbr Plywood 4' x 8' x 4 mm 68,000.00 58,480.00
0.200 Oh Pekerja 100,000.00 20,000.00
0.600 Oh Tukang kayu 130,000.00 78,000.00
0.060 Oh Kepala tukang 140,000.00 8,400.00
0.010 Oh Mandor 140,000.00 1,400.00
Jumlah
Over Head
Jumlah Total
JUMLAH KETERANGAN

13,594,075.00

8,836,250.00

3,522,000.00
12,358,250.00
1,235,825.00
13,594,075.00
11,517,275.00

7,236,250.00

3,234,000.00
10,470,250.00
1,047,025.00
11,517,275.00
472,527.00

240,850.00

188,720.00
429,570.00
42,957.00
472,527.00
873,950.00
0.04
327,500.00

467,000.00
794,500.00
79,450.00
873,950.00
862,070.00

247,500.00
536,200.00
783,700.00
78,370.00
862,070.00
10,159,270.00 0.04
0.0056
8,804,500.00

431,200.00
9,235,700.00
923,570.00
10,159,270.00
12,313,070.00

9,037,700.00

2,156,000.00
11,193,700.00
1,119,370.00
12,313,070.00
11,315,810.00

8,993,500.00

1,293,600.00
10,287,100.00
1,028,710.00
11,315,810.00
219,175.00

134,650.00

64,600.00
199,250.00
19,925.00
219,175.00
142,285.00

88,850.00

40,500.00
129,350.00
12,935.00
142,285.00
441,353.00

293,430.00

107,800.00
401,230.00
40,123.00
441,353.00
PEKERJAAN PENUTUP DINDING DAN LANTAI ( SNI 7395-2008 )
HARGA
NO. URAIAN BAHAN UPAH
SATUAN
1 Memasang 1 M2 lantai granit 60 x 60 cm
2.944 Bh granit 60 x 60 cm 134,800.00 396,905.12
0.200 zak Semen portland ( 50 Kg) 1,180.00 236.00
0.045 M3 Pasir pasang 135,000.00 6,075.00
0.190 Kg Semen warna/Tepung afa 9,000.00 1,710.00
0.620 Oh Pekerja 100,000.00 62,000.00
0.350 Oh Tukang batu 130,000.00 45,500.00
0.035 Oh Kepala tukang 140,000.00 4,900.00
0.030 Oh Mandor 140,000.00 4,200.00
Jumlah
Over Head
Jumlah Total
1 1 M2 Pasang lantai keramik 60 x 60 cm Kesat
2.944 Bh granit 60 x 60 cm 148,280.00 436,595.63
0.200 Kg Semen portland ( 50 Kg) 1,180.00 236.00
0.045 M3 Pasir pasang 135,000.00 6,075.00
0.190 Kg Semen warna/Tepung afa 9,000.00 1,710.00
0.620 Oh Pekerja 100,000.00 62,000.00
0.350 Oh Tukang batu 130,000.00 45,500.00
0.035 Oh Kepala tukang 140,000.00 4,900.00
0.030 Oh Mandor 140,000.00 4,200.00
Jumlah
Over Head
Jumlah Total
#REF! 1 M2 Pasang lantai keramik 30 x 30 cm
11.870 Bh Ubin keramik 40 x 40 cm 36,763.64 436,384.36
10.000 Kg Semen portland ( 50 Kg) 1,180.00 11,800.00
0.045 M3 Pasir pasang 135,000.00 6,075.00
1.500 Kg Semen warna/Tepung afa 9,000.00 13,500.00
0.260 Oh Pekerja 100,000.00 26,000.00
0.130 Oh Tukang batu 130,000.00 16,900.00
0.013 Oh Kepala tukang 140,000.00 1,820.00
0.013 Oh Mandor 140,000.00 1,820.00
Jumlah
Over Head
Jumlah Total
1 1 M2 Pasang lantai keramik 20 x 20 cm
26.500 Bh Ubin keramik 20 x 20 cm 1,692.31 44,846.15
10.400 Kg Semen portland ( 50 Kg) 1,180.00 12,272.00
0.045 M3 Pasir pasang 135,000.00 6,075.00
1.620 Kg Semen warna/Tepung afa 9,000.00 14,580.00
0.270 Oh Pekerja 100,000.00 27,000.00
0.135 Oh Tukang batu 130,000.00 17,550.00
0.014 Oh Kepala tukang 140,000.00 1,960.00
0.014 Oh Mandor 140,000.00 1,960.00
Jumlah
Over Head
Jumlah Total
3 1 M2 Pasang dinding Keramik 20 x 25 cm
20.000 Bh Keramik 20 x 25 2,200.00 44,000.00
9.300 Kg Semen portland ( 50 Kg) 1,180.00 10,974.00
0.018 M3 Pasir pasang 135,000.00 2,430.00
2.750 Kg Semen warna/Tepung afa 9,000.00 24,750.00
0.600 Oh Pekerja 100,000.00 60,000.00
0.450 Oh Tukang batu 130,000.00 58,500.00
0.045 Oh Kepala tukang 140,000.00 6,300.00
0.030 Oh Mandor 140,000.00 4,200.00
Jumlah
Over Head
Jumlah Total
3b 1 M2 Pasang dinding Keramik 40x40 cm
6.630 Bh Ubin keramik 40 x 40 cm 11,333.33 75,140.00
9.300 Kg Semen portland ( 50 Kg) 1,180.00 10,974.00
0.018 M3 Pasir pasang 135,000.00 2,430.00
2.750 Kg Semen warna/Tepung afa 9,000.00 24,750.00
0.600 Oh Pekerja 100,000.00 60,000.00
0.450 Oh Tukang batu 130,000.00 58,500.00
0.045 Oh Kepala tukang 140,000.00 6,300.00
0.030 Oh Mandor 140,000.00 4,200.00
Jumlah
Over Head
Jumlah Total
4 1 M2 Pasang dinding batu tempel hitam/Batu Alam
1.100 M2 Batu tempel hitam 120,000.00 132,000.00
11.750 Zak Semen portland ( 50 Kg) 1,180.00 13,865.00
0.035 M3 Pasir pasang 135,000.00 4,725.00
0.700 Oh Pekerja 100,000.00 70,000.00
0.350 Oh Tukang batu 130,000.00 45,500.00
0.035 Oh Kepala tukang 140,000.00 4,900.00
0.030 Oh Mandor 140,000.00 4,200.00
Jumlah
Over Head
Jumlah Total
NI 7395-2008 )
JUMLAH KETERANGAN

573,678.73

404,926.12

116,600.00
521,526.12
52,152.61
573,678.73
617,338.30

444,616.63

116,600.00
561,216.63
56,121.66
617,338.30
565,729.30

467,759.36

46,540.00
514,299.36
51,429.94
565,729.30
138,867.47

77,773.15

48,470.00
126,243.15
12,624.32
138,867.47
232,269.40

82,154.00

129,000.00
211,154.00
21,115.40
232,269.40
266,523.40

113,294.00

129,000.00
242,294.00
24,229.40
266,523.40
302,709.00

150,590.00

124,600
275,190.00
27,519.00
302,709.00
PEKERJAAN BESI ( SNI 7393-2008)
HARGA
NO. URAIAN BAHAN UPAH
SATUAN
1 Memasang 1 Kg Besi Profil ( Rangka Atap )
1.150 Kg Besi profil 9,600.00 11,040.00
0.060 Oh Pekerja 65,000.00 3,900.00
0.060 Oh Tukang besi 80,000.00 4,800.00
0.006 Oh Kepala tukang 95,000.00 570.00
0.003 Oh Mandor 95,000.00 285.00
Jumlah
Over Head
Jumlah Total
2 Memasang 1 Kg rangka atap baja
1.150 Kg Besi Siku 40.40.4 9,600.00 11,040.00
0.060 Oh Pekerja 65,000.00 3,900.00
0.060 Oh Tukang besi 80,000.00 4,800.00
0.006 Oh Kepala tukang 95,000.00 570.00
0.003 Oh Mandor 95,000.00 285.00
Jumlah
Over Head
Jumlah Total
3 Mengerjakan 100 Kg Perakitan
1.000 ltr Solar 6,400.00 6,400.00
0.100 ltr Minyak Pelumas 35,000.00 3,500.00
0.100 Oh Pekerja 65,000.00 6,500.00
0.100 Oh Tukang besi 80,000.00 8,000.00
0.001 Oh Kepala tukang 95,000.00 95.00
0.005 Oh Mandor 95,000.00 475.00
0.008 Jam Sewa Alat 100,000.00 800.00
Jumlah ......@

Jumlah 1 Kg = @ / 100
Over Head
Jumlah Total
4 Memasang 1 M2 Pintu besi Plat Baja t = 2 mm Rangkap, Rangka Baja siku
15.000 Kg Besi siku L 30,30,3 9,600.00
32.000 Kg besi plat baja 9,600.00 307,200.00
0.050 Kg Kawat Las 15,000.00 750.00
1.050 Oh Pekerja 65,000.00 68,250.00
1.050 Oh Tukang besi konstruksi 80,000.00 84,000.00
0.105 Oh Kepala tukang 95,000.00 9,975.00
0.052 Oh Mandor 95,000.00 4,940.00
Jumlah
Over Head
Jumlah Total
5 Memasang 1 M2 Pagar Teralis Teras Depan
2.300 Btg Besi Hollow 40x40x1,2 75,000.00 172,500.00
0.050 Kg Kawat Las 15,000.00 750.00
1.050 Oh Pekerja 65,000.00 68,250.00
1.050 Oh Tukang besi konstruksi 80,000.00 84,000.00
0.105 Oh Kepala tukang 95,000.00 9,975.00
0.052 Oh Mandor 95,000.00 4,940.00
Jumlah
Over Head
Jumlah Total
6 Memasang 1 M2 Pagar Teralis Teras Belakang
2.160 Btg Besi Hollow 40x40x1,2 75,000.00 162,000.00
0.050 Kg Kawat Las 15,000.00 750.00
1.050 Oh Pekerja 65,000.00 68,250.00
1.050 Oh Tukang besi konstruksi 80,000.00 84,000.00
0.105 Oh Kepala tukang 95,000.00 9,975.00
0.052 Oh Mandor 95,000.00 4,940.00
Jumlah
Over Head
Jumlah Total
7 Memasang 1 M2 Pagar BRC
0.347 Pnl Pagar BRC 120 cm 225,000.00 78,075.00
2.600 M Besi Pipa Galvanis 2 " 64,583.33 167,916.67
0.050 Kg Kawat Las 15,000.00 750.00
1.050 Oh Pekerja 65,000.00 68,250.00
1.050 Oh Tukang besi konstruksi 80,000.00 84,000.00
0.105 Oh Kepala tukang 95,000.00 9,975.00
0.052 Oh Mandor 95,000.00 4,940.00
Jumlah
Over Head
Jumlah Total
8 Memasang 1 M2 Pagar Stainless Steel
2.600 M Besi Pipa Stainless Steel 2 " 64,583.33 167,916.67
6.500 M Besi Pipa Stainless Steel 1 " 40,000.00 260,000.00
0.050 Kg Kawat Las 15,000.00 750.00
1.050 Oh Pekerja 65,000.00 68,250.00
1.050 Oh Tukang besi konstruksi 80,000.00 84,000.00
0.105 Oh Kepala tukang 95,000.00 9,975.00
0.052 Oh Mandor 95,000.00 4,940.00
Jumlah
Over Head
Jumlah Total
1 Mengerjakan 1 cm Pengelasan dengan las listrik
0.040 Kg Kawat Las 15,000.00 600.00
0.030 Ltr Solar 6,400.00 192.00
0.040 Ltr Minyak Pelumas 35,000.00 1,400.00
0.017 Jam Sewa Alat 100,000.00 1,700.00
0.040 Oh Pekerja 65,000.00 2,600.00
0.002 Oh Tukang besi konstruksi 80,000.00 160.00
0.0002 Oh Kepala tukang 95,000.00 19.00
0.0002 Oh Mandor 95,000.00 19.00
Jumlah
2 Memasang 1 M Pipa dia 2 1/2 "
1.000 M Pipa Galvanis 64,583.33 64,583.33
5.000 cm Las Listrik 6,690.00 33,450.00
Jumlah
Over Head
Jumlah Total
10 Memasang 1 M2 pintu rooling door besi
1.000 M2 Pintu gulung besi 400,000.00 400,000.00
1.200 Oh Pekerja 65,000.00 78,000.00
1.200 Oh Tukang besi konstruksi 80,000.00 96,000.00
0.120 Oh Kepala tukang 95,000.00 11,400.00
0.006 Oh Mandor 95,000.00 570.00
Jumlah
Over Head
Jumlah Total
11 Memasang 1 M2 pintu lipat (Foolding Door)
1.000 M2 pintu lipat 450,000.00 450,000.00
0.440 Oh Pekerja 65,000.00 28,600.00
0.440 Oh Tukang besi konstruksi 80,000.00 35,200.00
0.044 Oh Kepala tukang 95,000.00 4,180.00
0.022 Oh Mandor 95,000.00 2,090.00
Jumlah
Over Head
Jumlah Total
12 Memasang 1 M2 pintu suncreen aluminium
1.000 M2 Suncreem aluminium 400,000.00 400,000.00
0.080 Oh Pekerja 65,000.00 5,200.00
0.800 Oh Tukang besi konstruksi 80,000.00 64,000.00
0.080 Oh Kepala tukang 95,000.00 7,600.00
0.004 Oh Mandor 95,000.00 380.00
Jumlah
Over Head
Jumlah Total
13 Memasang 1 M2 Rolling door Alumunium
1.000 M2 Roll door 400,000.00 400,000.00
1.000 Oh Pekerja 65,000.00 65,000.00
1.000 Oh Tukang besi konstruksi 80,000.00 80,000.00
0.100 Oh Kepala tukang 95,000.00 9,500.00
0.050 Oh Mandor 95,000.00 4,750.00
Jumlah
Over Head
Jumlah Total
14 Memasang 1 M1 Kusen aluminium
1.000 M Profil aluminium 95,000.00 95,000.00
2.000 bh Skrup fixer 750.00 1,500.00
0.060tube Sealent 25,000.00 1,500.00
0.043Oh Pekerja 65,000.00 2,795.00
0.043Oh Tukang besi konstruksi 80,000.00 3,440.00
0.0043Oh Kepala tukang 95,000.00 408.50
0.0021Oh Mandor 95,000.00 199.50
Jumlah
Over Head
Jumlah Total
15 Memasang 1 M2 pintu aluminium
4.400 M Profil aluminium 95,000.00 418,000.00
14.600 M Aluminium Strip 8,500.00 124,100.00
0.085 Oh Pekerja 65,000.00 5,525.00
0.085 Oh Tukang besi konstruksi 80,000.00 6,800.00
0.0085 Oh Kepala tukang 95,000.00 807.50
0.0042 Oh Mandor 95,000.00 399.00
Jumlah
Over Head
Jumlah Total
16 Memasang 1 M2 Pintu Kaca Rangka aluminium
4.400 M Profil aluminium 95,000.00 418,000.00
1.000 M2 Profil Kaca 83,000.00 83,000.00
0.270 tube Sealent 25,000.00 6,750.00
0.085 Oh Pekerja 65,000.00 5,525.00
0.085 Oh Tukang besi konstruksi 80,000.00 6,800.00
0.008 Oh Kepala tukang 95,000.00 760.00
0.004 Oh Mandor 95,000.00 380.00
Jumlah
Over Head
Jumlah Total
17 Memasang 1 M2 Venetions blinds
1.000 M2 Venetions blinds 50,000.00 50,000.00
0.350 Oh Pekerja 65,000.00 22,750.00
0.350 Oh Tukang kayu 80,000.00 28,000.00
0.035 Oh Kepala tukang 95,000.00 3,325.00
0.018 Oh Mandor 95,000.00 1,710.00
Jumlah
Over Head
Jumlah Total
2 Memasang 1 M2 terali besi
6.177 Kg Besi strip 2 x 3 9,600.00 59,299.20
27.080 cm Pengelasan 6,690.00 181,165.20
1.670 Oh Pekerja 65,000.00 108,550.00
1.670 Oh Tukang Besi 80,000.00 133,600.00
0.012 Oh Kepala tukang 95,000.00 1,140.00
0.083 Oh Mandor 95,000.00 7,885.00
Jumlah
Over Head
Jumlah Total
JUMLAH KETERANGAN

22,654.50
11,040.00

9,555.00
20,595.00
2,059.50
22,654.50
22,654.50
11,040.00

9,555.00
20,595.00
2,059.50
22,654.50
283.47

9,900.00

15,870.00
25,770.00

257.70
25.77
283.47
522,626.50

307,950.00

167,165.00
475,115.00
47,511.50
522,626.50
374,456.50
173,250.00

167,165.00
340,415.00
34,041.50
374,456.50
362,906.50

162,750.00

167,165.00
329,915.00
32,991.50
362,906.50
455,297.33

246,741.67

167,165.00
413,906.67
41,390.67
455,297.33
655,414.83

428,666.67

167,165.00
595,831.67
59,583.17
655,414.83
6,690.00

3,892.00
2,798.00
6,690.00

98,033.33

98,033.33
9,803.33
107,836.67
644,567.00
400,000.00

185,970.00
585,970.00
58,597.00
644,567.00
572,077.00
450,000.00

70,070.00
520,070.00
52,007.00
572,077.00
524,898.00
400,000.00

77,180.00
477,180.00
47,718.00
524,898.00
615,175.00
400,000.00

159,250.00
559,250.00
55,925.00
615,175.00
115,327.30
98,000.00

6,843.00
104,843.00
10,484.30
115,327.30
611,194.65

542,100.00

13,531.50
555,631.50
55,563.15
611,194.65
573,336.50

507,750.00

13,465.00
521,215.00
52,121.50
573,336.50
116,363.50
50,000.00

55,785.00
105,785.00
10,578.50
116,363.50
540,803.34

240,464.40

251,175.00
491,639.40
49,163.94
540,803.34
PEKERJAAN BESI DAN ALUMINIUM ( SNI 7393-2008)
HARGA
NO. URAIAN SATUAN BAHAN
1 1 M1 Pasang Kusen aluminium
1.000 M Profil aluminium 95,000.00 95,000.00
2.000 bh Skrup fixer 750.00 1,500.00
0.060 tube Sealent 30,000.00 1,800.00
0.043 Oh Pekerja 100,000.00
0.043 Oh Tukang besi konstruksi 130,000.00
0.004 Oh Kepala tukang 140,000.00
0.002 Oh Mandor 140,000.00
Jumlah
Over Head
Jumlah Total
2 1 Unit Pasang Pintu dan Jendela Kaca Rangka aluminium
4.900 M Profil aluminium 95,000.00 465,500.00
0.460 M2 Profil Kaca tebal 5 mm 94,000.00 43,240.00
1.000 psg Engsel flooring hinge 6,000,000.00 6,000,000.00
0.270 tube Sealent 30,000.00 8,100.00
1.000 Unit Kunci Tanam 228,910.00 228,910.00
2.000 Unit Hand Vatten 130,000.00 260,000.00
0.085 Oh Pekerja 100,000.00
0.085 Oh Tukang besi konstruksi 130,000.00
0.008 Oh Kepala tukang 140,000.00
0.004 Oh Mandor 140,000.00
Jumlah
Over Head
Jumlah Total
2 1 Unit Pasang Pintu dan Jendela Kaca Rangka aluminium Tipe JG 2
16.500 M Profil aluminium 95,000.00 1,567,500.00
1.876 M2 Profil Kaca tebal 5 mm 94,000.00 176,362.80
psg Engsel flooring hinge -
0.270 tube Sealent 30,000.00 8,100.00
1.000 Unit Kunci Tanam 228,910.00 228,910.00
2.000 Unit Hand Vatten 130,000.00 260,000.00
0.085 Oh Pekerja 100,000.00
0.085 Oh Tukang besi konstruksi 130,000.00
0.008 Oh Kepala tukang 140,000.00
0.004 Oh Mandor 140,000.00
Jumlah
Over Head
Jumlah Total
3 1 Unit Pasang Pintu Kaca Rangka aluminium type 1
1 Unit Pintu Kaca Rangka aluminium 7,729,678.00
6 Bh Engsel Pintu Alluminium 31,251.00
1 Bh Kunci Tanam 191,730.00
2 Bh Hand Vatten 25,751.00
Jumlah
4 1 Unit Pasang Pintu Kaca Rangka aluminium Tipe 2
1.89 M2 Rangka Alluminium 7,729,678.00
3 Bh Engsel Pintu Alluminium 22,940.00
1 Bh Kunci Tanam 173,400.00
1 Bh Hand Vatten 44,700.00
Jumlah
5 1 Unit Pasang Jendela Kaca Rangka aluminium Type 1
8.6 M Profil aluminium 95,000.00 817,000.00
3.6 M2 Profil Kaca tebal 5 mm 94,000.00 338,400.00
0.27 tube Sealent 30,000.00 8,100.00
0.5 Oh Pekerja 100,000.00
0.085 Oh Tukang besi konstruksi 130,000.00
0.008 Oh Kepala tukang 140,000.00
0.004 Oh Mandor 140,000.00
Jumlah
Over Head
Jumlah Total
5 1 Unit Pasang Jendela Kaca Rangka aluminium Type 2
10.200 M Profil aluminium 95,000.00 969,000.00
6.160 M2 Profil Kaca tebal 5 mm 94,000.00 579,040.00
0.270 tube Sealent 30,000.00 8,100.00
0.085 Oh Pekerja 100,000.00
0.085 Oh Tukang besi konstruksi 130,000.00
0.008 Oh Kepala tukang 140,000.00
0.004 Oh Mandor 140,000.00
Jumlah
Over Head
Jumlah Total
5 1 Unit Pasang Jendela Kaca Rangka aluminium Type 3
6.500 M Profil aluminium 95,000.00 617,500.00
2.415 M2 Profil Kaca tebal 5 mm 94,000.00 227,010.00
0.270 tube Sealent 30,000.00 8,100.00
0.085 Oh Pekerja 100,000.00
0.085 Oh Tukang besi konstruksi 130,000.00
0.008 Oh Kepala tukang 140,000.00
0.004 Oh Mandor 140,000.00
Jumlah
Over Head
Jumlah Total
5 1 Unit Pasang Jendela Kaca Rangka aluminium Type 4
4.400 M Profil aluminium 95,000.00 418,000.00
0.850 M2 Profil Kaca tebal 5 mm 94,000.00 79,900.00
0.270 tube Sealent 30,000.00 8,100.00
0.085 Oh Pekerja 100,000.00
0.085 Oh Tukang besi konstruksi 130,000.00
0.008 Oh Kepala tukang 140,000.00
0.004 Oh Mandor 140,000.00
Jumlah
Over Head
Jumlah Total
7 1 Unit Pasang Jendela Kaca Rangka aluminium Tipe J3
0.650 M2 Rangka Alluminium 7,729,678.00
3.000 Bh Engsel Jendela 21,612.25
1.000 Bh Grendel 33,165.00
1.000 Bh Hand Vatten 29,118.38
1.000 Bh Kait Angin 28,018.38
Jumlah
8 1 Unit Pasang Jendela Kaca Rangka aluminium Tipe JK1
1.800 M2 Rangka Alluminium 7,729,678.00
4.000 Bh Engsel Jendela 21,612.25
4.000 Bh Grendel 33,165.00
4.000 Bh Hand Vatten 29,118.38
4.000 Bh Kait Angin 28,018.38
Jumlah
9 1 Unit Pasang Jendela Kaca Rangka aluminium Tipe JK2
3.200 M2 Rangka Alluminium 7,729,678.00
8.000 Bh Engsel Jendela 21,612.25
8.000 Bh Grendel 33,165.00
8.000 Bh Hand Vatten 29,118.38
8.000 Bh Kait Angin 28,018.38
Jumlah
8 1 Unit Pasang Jendela Kaca Rangka aluminium
2.600 M2 Rangka Alluminium 7,729,678.00
6.000 Bh Engsel Jendela 21,612.25
1.000 Bh Grendel 33,165.00
1.000 Bh Hand Vatten 29,118.38
1.000 Bh Kait Angin 28,018.38
Jumlah
5 1 Unit Pasang Jendela Kaca Rangka aluminium Type 1 musholla
4.400 M Profil aluminium 95,000.00 418,000.00
1.040 M2 Profil Kaca tebal 5 mm 94,000.00 97,760.00
0.270 tube Sealent 30,000.00 8,100.00
0.085 Oh Pekerja 100,000.00
0.085 Oh Tukang besi konstruksi 130,000.00
0.008 Oh Kepala tukang 140,000.00
0.004 Oh Mandor 140,000.00
Jumlah
Over Head
Jumlah Total
5 1 Unit Pasang Jendela Kaca Rangka aluminium Type 2
4.800 M Profil aluminium 95,000.00 456,000.00
1.280 M2 Profil Kaca tebal 5 mm 94,000.00 120,320.00
0.270 tube Sealent 30,000.00 8,100.00
0.085 Oh Pekerja 100,000.00
0.085 Oh Tukang besi konstruksi 130,000.00
0.008 Oh Kepala tukang 140,000.00
0.004 Oh Mandor 140,000.00
Jumlah
Over Head
Jumlah Total
5 1 Unit Pasang Jendela Kaca Rangka aluminium Type 2
9.120 M Profil aluminium 95,000.00 866,400.00
2.236 M2 Profil Kaca tebal 5 mm 94,000.00 210,184.00
0.270 tube Sealent 30,000.00 8,100.00
0.085 Oh Pekerja 100,000.00
0.085 Oh Tukang besi konstruksi 130,000.00
0.008 Oh Kepala tukang 140,000.00
0.004 Oh Mandor 140,000.00
Jumlah
Over Head
Jumlah Total

3 1 Unit Jendela Kaca Rangka aluminium


8.400 M Profil aluminium 95,000.00 798,000.00
1.400 M2 Profil Kaca tebal 5 mm 94,000.00 131,600.00
0.270 tube Sealent 30,000.00 8,100.00
6.000 Bh Engsel Jendela 26,367.00 158,202.00
4.000 Bh Grendel 47,520.00 190,080.00
2.000 Bh Tarikan Jendela 33,225.50 66,451.00
2.000 Bh Kait Angin 37,075.50 74,151.00
0.085 Oh Pekerja 100,000.00
0.085 Oh Tukang besi konstruksi 130,000.00
0.008 Oh Kepala tukang 140,000.00
0.004 Oh Mandor 140,000.00
Jumlah
Over Head
Jumlah Total
JUMLAH
UPAH KET

98,300.00
4300
5590
602
294 10,786.00
109,086.00
10,908.60
119,994.60

7,005,750.00
8,500.00
11,050.00
1,120.00
560.00 21,230.00
7,026,980.00
702,698.00
7,729,678.00

2,240,872.80
8,500.00
11,050.00
1,120.00
560.00 21,230.00
2,262,102.80
226,210.28
2,488,313.08

7,729,678.00
187,506.00
191,730.00
51,502.00
8,160,416.00
14,609,091.42
68,820.00
173,400.00
44,700.00
14,896,011.42

1,163,500.00
50,000.00
11,050.00
1,120.00
560.00 62,730.00
1226230
122,623.00
1348853

1,556,140.00
8,500.00
11,050.00
1,120.00
560.00 21,230.00
1,577,370.00
157,737.00
1,735,107.00

852,610.00
8,500.00
11,050.00
1,120.00
560.00 21,230.00
873,840.00
87,384.00
961,224.00

506,000.00
8,500.00
11,050.00
1,120.00
560.00 21,230.00
527,230.00
52,723.00
579,953.00

5,024,290.70
64,836.75
33,165.00
29,118.38
28,018.38
5179429.2

13,913,420.40
86,449.00
132,660.00
116,473.50
112,073.50
14361076.4

24,734,969.60
172,898.00
265,320.00
232,947.00
224,147.00
25630281.6

20,097,162.80
129,673.50
33,165.00
29,118.38
28,018.38
20317138.05

523,860.00
8,500.00
11,050.00
1,120.00
560.00 21,230.00
545,090.00
54,509.00
599599

584,420.00
8,500.00
11,050.00
1,120.00
560.00 21,230.00
605,650.00
60,565.00
666215

1,084,684.00
8,500.00
11,050.00
1,120.00
560.00 21,230.00
1,105,914.00
110,591.40
1,216,505.40

1,426,584.00
8,500.00
11,050.00
1,120.00
560.00 21,230.00
1,447,814.00
144,781.40
1,592,595.40
PEKERJAAN LANGIT-LANGIT ( SNI 2839-2008)
HARGA
NO. URAIAN BAHAN UPAH
SATUAN
#REF! 1 M2 Langit-langit asbes (1,00 x 1,00) m,
1.100 Lbr Pelat asbes tebal 6 mm 34,000.00 37,400.00
0.010 Kg Paku 17,000.00 170.00
0.030 Oh Pekerja #REF! #REF!
0.070 Oh Tukang kayu #REF! #REF!
0.007 Oh Kepala tukang #REF! #REF!
0.002 Oh Mandor #REF! #REF!
Jumlah
Over Head
Jumlah Total
#REF! 1 M2 Langit-langit akustik (30 x 30) cm
12.000 Lbr Akustik ukuran 30 x 30 cm 3,750.00 45,000.00
0.050 Kg Paku 17,000.00 850.00
0.060 Oh Pekerja #REF! #REF!
0.120 Oh Tukang kayu #REF! #REF!
0.012 Oh Kepala tukang #REF! #REF!
0.003 Oh Mandor #REF! #REF!
Jumlah
Over Head
Jumlah Total
#REF! 1 M2 Langit-langit akustik (30 x 60) cm
5.800 Lbr Akustik ukuran 30 x 60 cm 7,758.62 45,000.00
0.050 Kg Paku 17,000.00 850.00
0.060 Oh Pekerja #REF! #REF!
0.100 Oh Tukang kayu #REF! #REF!
0.010 Oh Kepala tukang #REF! #REF!
0.003 Oh Mandor #REF! #REF!
Jumlah
Over Head
Jumlah Total
#REF! 1 M2 Langit-langit akustik (60 x 120) cm
1.500 Lbr Akustik arm strong ukuran 60 x 120 cm 30,000.00 45,000.00
0.050 Kg Paku 17,000.00 850.00
0.060 Oh Pekerja #REF! #REF!
0.100 Oh Tukang kayu #REF! #REF!
0.010 Oh Kepala tukang #REF! #REF!
0.003 Oh Mandor #REF! #REF!
Jumlah
Over Head
Jumlah Total
1 1 M2 Langit-langit triplek (120 x 240) cm, 3 mm , 4 mm dan 6 mm
0.375 Lbr Triplek 4' x 8' x 4 mm 68,000.00 25,500.00
0.030 Kg Paku 17,000.00 510.00
0.100 Oh Pekerja #REF! #REF!
0.100 Oh Tukang kayu #REF! #REF!
0.010 Oh Kepala tukang #REF! #REF!
0.005 Oh Mandor #REF! #REF!
Jumlah
Over Head
Jumlah Total
2 1 M1 List Langit-langit profil gypsum t = 10 cm
1.100 M1 List profil gypsum 18,000.00 19,800.00
0.010 Kg Paku 17,000.00 170.00
0.050 Oh Pekerja 100,000.00 5,000.00
0.050 Oh Tukang kayu 130,000.00 6,500.00
0.005 Oh Kepala tukang 140,000.00 700.00
0.003 Oh Mandor 140,000.00 420.00
Jumlah
Over Head
Jumlah Total
2 1 M2 Langit-langit gypsum board, tebal 9 rpm
0.364 Lbr Gypsum board (120 x 240 x 9) mm 174,000.00 63,336.00
0.110 Kg Paku sekrup 17,000.00 1,870.00
0.100 Oh Pekerja 100,000.00 10,000.00
0.050 Oh Tukang kayu 130,000.00 6,500.00
0.005 Oh Kepala tukang 140,000.00 700.00
0.005 Oh Mandor 140,000.00 700.00
Jumlah
Over Head
Jumlah Total
3 1 M2 Langit-langit Grc semen board, tebal 8 mm + Rangka Besi Hollow
4.200 M1 Besi Hollow ( 40 x 40 ) 21,675.00 91,035.00
0.364 Lbr Semen board (120 x 240 x 9) mm 174,000.00 63,336.00
0.110 Kg Paku sekrup 17,000.00 1,870.00
0.150 Oh Pekerja 100,000.00 15,000.00
0.500 Oh Tukang kayu 130,000.00 65,000.00
0.050 Oh Kepala tukang 140,000.00 7,000.00
0.008 Oh Mandor 140,000.00 1,120.00
Jumlah
Over Head
Jumlah Total
2 1 M' List Langit-langit kayu profil
1.050 M1 List Kayu Profil 18,000.00 18,900.00
0.010 Kg Paku 17,000.00 170.00
0.050 Oh Pekerja #REF! #REF!
0.050 Oh Tukang kayu #REF! #REF!
0.005 Oh Kepala tukang #REF! #REF!
0.003 Oh Mandor #REF! #REF!
Jumlah
Over Head
Jumlah Total
JUMLAH KETERANGAN

#REF!

37,570.00

#REF!
#REF!
#REF!
#REF!
#REF!

45,850.00

#REF!
#REF!
#REF!
#REF!
#REF!

45,850.00

#REF!
#REF!
#REF!
#REF!
#REF!

45,850.00

#REF!
#REF!
#REF!
#REF!
#REF!

26,010.00

#REF!
#REF!
#REF!
#REF!
35,849.00

19,970.00

12,620.00
32,590.00
3,259.00
35,849.00
91,416.60

65,206.00

17,900.00
83,106.00
8,310.60
91,416.60
268,797.10

156,241.00

88,120.00
244,361.00
24,436.10
268,797.10
#REF!

19,070.00

#REF!
#REF!
#REF!
#REF!
PEKERJAAN PENUTUP ATAP ( SNI, 03 - 3436- 2002)
HARGA
NO. URAIAN BAHAN UPAH
SATUAN
### 1 M2 Pasang atap genteng metal
1.320 Lbr Genteng metal ber pasir 106,000.00 139,920.00
0.200 Kg Paku Atap genteng 22,000.00 4,400.00
0.200 Oh Pekerja 100,000.00 20,000.00
0.100 Oh Tukang kayu 130,000.00 13,000.00
0.010 Oh Kepala tukang 140,000.00 1,400.00
0.001 Oh Mandor 140,000.00 140.00
Jumlah
Over Head
Jumlah Total
### 1 M1 Pasang nok genteng metal
1.100 Bh Genteng Metal Berpasir 45,000.00 49,500.00
0.050 Kg Paku Atap genteng 22,000.00 1,100.00
0.250 Oh Pekerja 100,000.00 25,000.00
0.150 Oh Tukang kayu 130,000.00 19,500.00
0.015 Oh Kepala tukang 140,000.00 2,100.00
0.013 Oh Mandor 140,000.00 1,820.00
Jumlah
Over Head
Jumlah Total
1 1 M2 Pasang atap seng gelombang Berwarna
0.700 Lbr Seng Warna Bjls 20 setara gajah berlian 55,000.00 38,500.00
0.020 Kg Paku biasa atap seng 20,000.00 400.00
0.120 Oh Pekerja #REF! #REF!
0.060 Oh Tukang kayu #REF! #REF!
0.006 Oh Kepala tukang #REF! #REF!
0.006 Oh Mandor #REF! #REF!
Jumlah
Over Head
Jumlah Total
2 1 M Pasang atap nok seng (perabung)
0.300 Lbr Seng Plat Warna Bjls 20 setara gajah berlian 75,000.00 22,500.00
0.040 Kg Paku biasa atap seng 20,000.00 800.00
0.150 Oh Pekerja #REF! #REF!
0.070 Oh Tukang kayu #REF! #REF!
0.008 Oh Kepala tukang #REF! #REF!
0.006 Oh Mandor #REF! #REF!
Jumlah
Over Head
Jumlah Total
JUMLAH KETERANGAN

196,746.00
0.32
144,320.00 3.125

34,540.00
178,860.00
17,886.00
196,746.00
108,922.00

50,600.00

48,420.00
99,020.00
9,902.00
108,922.00
#REF!
1.44
38,900.00 0.6944444

#REF!
#REF!
#REF!
#REF!
#REF!

23,300.00

#REF!
#REF!
#REF!
#REF!
PEKERJAAN CAT ( SNI, 03 - 2836 - 2002 )
HARGA
NO. URAIAN BAHAN UPAH
SATUAN
#REF! 1 M2 Pelaburan bidang kayu dengan politur
0.150 Ltr Politur 28,000.00 4,200.00
0.372 Ltr Politur jadi 53,000.00 19,716.00
2.000 Lbr Ampelas 6,000.00 12,000.00
- Oh Pekerja 100,000.00 -
0.060 Oh Tukang cat 130,000.00 7,800.00
0.016 Oh Kepala tukang 140,000.00 2,240.00
0.0025 Oh Mandor 140,000.00 350.00
Jumlah
Over Head
Jumlah Total
#REF! 1 M2 Pelaburan bidang kayu dengan cat residu dan ter
0.350 Ltr Residu atau ter 15,000.00 5,250.00
0.100 Oh Pekerja #REF! #REF!
- Oh Tukang cat #REF! #REF!
- Oh Kepala tukang #REF! #REF!
0.006 Oh Mandor #REF! #REF!
Jumlah
Over Head
Jumlah Total
1 1 M2 Pelaburan bidang kayu dengan cat minyak
0.372 Ltr Cat Minyak 65,000.00 24,180.00
2.000 Lbr Ampelas 6,000.00 12,000.00
- Oh Pekerja 100,000.00 -
0.060 Oh Tukang cat 130,000.00 7,800.00
0.016 Oh Kepala tukang 140,000.00 2,240.00
0.003 Oh Mandor 140,000.00 350.00
Jumlah
Over Head
Jumlah Total
2 1 M2 Pengecatan tembok baru (1 lapis plamir, 1 lapis cat dasar 2 lapis cat penutup
0.100 Kg Plamir 21,000.00 2,100.00
0.100 Kg Cat dasar 28,000.00 2,800.00
0.260 Kg Cat penutup 2 kali 38,000.00 9,880.00
0.020 Oh Pekerja 100,000.00 2,000.00
0.063 Oh Tukang cat 130,000.00 8,190.00
0.0063 Oh Kepala tukang 140,000.00 882.00
0.0025 Oh Mandor 140,000.00 350.00
Jumlah
Over Head
Jumlah Total
JUMLAH KETERANGAN

50,936.60

35,916.00

10,390.00
46,306.00
4,630.60
50,936.60
#REF!
5,250.00

#REF!
#REF!
#REF!
#REF!
51,227.00

36,180.00

10,390.00
46,570.00
4,657.00
51,227.00
28,822.20

14,780.00

11,422.00
26,202.00
2,620.20
28,822.20
PEKERJAAN KUNCI DAN KACA ( SNI, 03 - 2836 - 2002 )
HARGA
NO. URAIAN BAHAN UPAH JUMLAH
SATUAN
### 1 Buah pasang kunci tanam antik
1.000 Bh Kunci tanam antik 5,000.00 5,000.00 5,000.00
0.060 Oh Pekerja 100,000.00 6,000.00
0.600 Oh Tukang kayu 130,000.00 78,000.00
0.060 Oh Kepala tukang 140,000.00 8,400.00
0.003 Oh Mandor 140,000.00 420.00 92,820.00
Jumlah 97,820.00
Over Head 9,782.00
Jumlah Total 107,602.00
1 1 Buah pasang kunci tanam biasa
1.000 Bh Kunci tanam biasa 140,000.00 140,000.00 140,000.00
0.010 Oh Pekerja 100,000.00 1,000.00
0.500 Oh Tukang kayu 130,000.00 65,000.00
0.010 Oh Kepala tukang 140,000.00 1,400.00
0.005 Oh Mandor 140,000.00 700.00 68,100.00
Jumlah 208,100.00
Over Head 20,810.00
Jumlah Total 228,910.00
### 1 Buah pasang kunci tanam kamar mandi
1.000 Bh Kunci tanam kamar mandi 140,000.00 140,000.00 140,000.00
0.005 Oh Pekerja 100,000.00 500.00
0.500 Oh Tukang kayu 130,000.00 65,000.00
0.005 Oh Kepala tukang 140,000.00 700.00
0.0025 Oh Mandor 140,000.00 350.00 66,550.00
Jumlah 206,550.00
Over Head 20,655.00
Jumlah Total 227,205.00
### 1 Buah pasang kunci silinder
1.000 Bh Kunci silinder 355,000.00 355,000.00 355,000.00
0.005 Oh Pekerja 100,000.00 500.00
0.500 Oh Tukang kayu 130,000.00 65,000.00
0.005 Oh Kepala tukang 140,000.00 700.00
0.00025 Oh Mandor 140,000.00 35.00 66,235.00
Jumlah 421,235.00
Over Head 42,123.50
Jumlah Total 463,358.50
2 1 Buah pasang engsel pintu
1.000 Bh Engsel pintu 9,000.00 9,000.00 9,000.00
0.015 Oh Pekerja 100,000.00 1,500.00
0.150 Oh Tukang kayu 130,000.00 19,500.00
0.015 Oh Kepala tukang 140,000.00 2,100.00
0.00075 Oh Mandor 140,000.00 105.00 23,205.00
Jumlah 32,205.00
Over Head 3,220.50
Jumlah Total 35,425.50
3 1 Buah pasang engsel jendela kupu - kupu
1.000 Bh Engsel jendela 8,500.00 8,500.00 8,500.00
0.010 Oh Pekerja 100,000.00 1,000.00
0.100 Oh Tukang kayu 130,000.00 13,000.00
0.010 Oh Kepala tukang 140,000.00 1,400.00
0.0005 Oh Mandor 140,000.00 70.00 15,470.00
Jumlah 23,970.00
Over Head 2,397.00
Jumlah Total 26,367.00
### 1 Buah pasang engsel angin
1.000 Bh Engsel angin - - -
0.020 Oh Pekerja 100,000.00 2,000.00
0.200 Oh Tukang kayu 130,000.00 26,000.00
0.020 Oh Kepala tukang 140,000.00 2,800.00
0.010 Oh Mandor 140,000.00 1,400.00 32,200.00
Jumlah 32,200.00
Over Head 3,220.00
Jumlah Total 35,420.00
4 1 Buah pasang Grendel
1.000 Bh Grendel 11,000.00 11,000.00 11,000.00
0.020 Oh Pekerja 100,000.00 2,000.00
0.200 Oh Tukang kayu 130,000.00 26,000.00
0.020 Oh Kepala tukang 140,000.00 2,800.00
0.010 Oh Mandor 140,000.00 1,400.00 32,200.00
Jumlah 43,200.00
Over Head 4,320.00
Jumlah Total 47,520.00
### 1 Buah pasang spiring knip
1.000 Bh Spiring knip - - -
0.015 Oh Pekerja 100,000.00 1,500.00
0.150 Oh Tukang kayu 130,000.00 19,500.00
0.015 Oh Kepala tukang 140,000.00 2,100.00
0.00075 Oh Mandor 140,000.00 105.00 23,205.00
Jumlah 23,205.00
Over Head 2,320.50
Jumlah Total 25,525.50
5 1 Buah pasang kait angin
1.000 Bh Kait angin 10,500.00 10,500.00 10,500.00
0.015 Oh Pekerja 100,000.00 1,500.00
0.150 Oh Tukang kayu 130,000.00 19,500.00
0.015 Oh Kepala tukang 140,000.00 2,100.00
0.00075 Oh Mandor 140,000.00 105.00 23,205.00
Jumlah 33,705.00
Over Head 3,370.50
Jumlah Total 37,075.50
6 1 Buah pasang tarikan jendela
1.000 Bh Tarikan Jendela 7,000.00 7,000.00 7,000.00
0.015 Oh Pekerja 100,000.00 1,500.00
0.150 Oh Tukang kayu 130,000.00 19,500.00
0.015 Oh Kepala tukang 140,000.00 2,100.00
0.00075 Oh Mandor 140,000.00 105.00 23,205.00
Jumlah 30,205.00
Over Head 3,020.50
Jumlah Total 33,225.50
### 1 Buah pasang door closer
1.000 Bh Door closer - - -
0.050 Oh Pekerja 100,000.00 5,000.00
0.500 Oh Tukang kayu 130,000.00 65,000.00
0.050 Oh Kepala tukang 140,000.00 7,000.00
0.0025 Oh Mandor 140,000.00 350.00 77,350.00
Jumlah 77,350.00
Over Head 7,735.00
Jumlah Total 85,085.00
### 1 Buah pasang kunci selot
1.000 Bh Kunci selot - - -
0.020 Oh Pekerja 65,000.00 1,300.00
0.200 Oh Tukang kayu 80,000.00 16,000.00
0.020 Oh Kepala tukang 95,000.00 1,900.00
0.001 Oh Mandor 95,000.00 95.00 19,295.00
Jumlah 19,295.00
Over Head 1,929.50
Jumlah Total 21,224.50
### 1 Buah pasang pegangan pintu / door holder
1.000 Bh Door holder - - -
0.050 Oh Pekerja 65,000.00 3,250.00
0.500 Oh Tukang kayu 80,000.00 40,000.00
0.050 Oh Kepala tukang 95,000.00 4,750.00
0.0025 Oh Mandor 95,000.00 237.50 48,237.50
Jumlah 48,237.50
Over Head 4,823.75
Jumlah Total 53,061.25
### 1 Buah pasang door stop
1.000 Bh Door stop - - -
0.010 Oh Pekerja 65,000.00 650.00
0.100 Oh Tukang kayu 80,000.00 8,000.00
0.010 Oh Kepala tukang 95,000.00 950.00
0.0005 Oh Mandor 95,000.00 47.50 9,647.50
Jumlah 9,647.50
Over Head 964.75
Jumlah Total 10,612.25
### 1 Buah pasang rel pintu sorong
1.000 Bh Rel pintu sorong - - -
0.060 Oh Pekerja 65,000.00 3,900.00
0.600 Oh Tukang kayu 80,000.00 48,000.00
0.060 Oh Kepala tukang 95,000.00 5,700.00
0.0030 Oh Mandor 95,000.00 285.00 57,885.00
Jumlah 57,885.00
Over Head 5,788.50
Jumlah Total 63,673.50
#N/A
1.000 Bh Kunci lemari - - -
0.025 Oh Pekerja 65,000.00 1,625.00
0.250 Oh Tukang kayu 80,000.00 20,000.00
0.025 Oh Kepala tukang 95,000.00 2,375.00
0.0010 Oh Mandor 95,000.00 95.00 24,095.00
Jumlah 24,095.00
Over Head 2,409.50
Jumlah Total 26,504.50
7 1 M2 Pasang kaca tebal 3 mm
1.000 M2 Kaca 90,000.00 90,000.00 90,000.00
0.015 Oh Pekerja #REF! #REF!
0.150 Oh Tukang kayu #REF! #REF!
0.015 Oh Kepala tukang #REF! #REF!
0.0007 Oh Mandor #REF! #REF! #REF!
Jumlah #REF!
Over Head #REF!
Jumlah Total #REF!
7 1 M2 Pasang kaca tebal 5 mm
1.100 M2 Kaca 117,000.00 128,700.00 128,700.00
0.015 Oh Pekerja 100,000.00 1,500.00
0.150 Oh Tukang kayu 130,000.00 19,500.00
0.015 Oh Kepala tukang 140,000.00 2,100.00
0.0007 Oh Mandor 140,000.00 98.00 23,198.00
Jumlah 151,898.00
Over Head 15,189.80
Jumlah Total 167,087.80
### 1 M2 Pasang kaca tebal 8 mm
1.100 M2 Kaca 140,400.00 154,440.00 154,440.00
0.016 Oh Pekerja 100,000.00 1,600.00
0.160 Oh Tukang kayu 130,000.00 20,800.00
0.016 Oh Kepala tukang 140,000.00 2,240.00
0.0008 Oh Mandor 140,000.00 112.00 24,752.00
Jumlah 179,192.00
Over Head 17,919.20
Jumlah Total 197,111.20
### 1 M2 Pasang kaca buram tebal 12 mm
1.100 M2 Kaca buram - -
0.050 Kg Sealent - - -
0.025 Oh Pekerja 65,000.00 1,625.00
0.250 Oh Tukang kayu 80,000.00 20,000.00
0.025 Oh Kepala tukang 95,000.00 2,375.00
0.0012 Oh Mandor 95,000.00 114.00 24,114.00
Jumlah 24,114.00
Over Head 2,411.40
Jumlah Total 26,525.40
### 1 M2 Pasang kaca cermin tebal 5 mm
1.100 M2 Kaca cermin 117,000.00 128,700.00 128,700.00
0.015 Oh Pekerja 100,000.00 1,500.00
0.150 Oh Tukang kayu 130,000.00 19,500.00
0.015 Oh Kepala tukang 140,000.00 2,100.00
0.0007 Oh Mandor 140,000.00 98.00 23,198.00
Jumlah 151,898.00
Over Head 15,189.80
Jumlah Total 167,087.80
KETERANGAN

107,602.00

228,910.00

227,205.00

463,358.50

35,425.50

26,367.00
35,420.00

47,520.00

25,525.50

37,075.50

33,225.50

85,085.00
21,224.50

53,061.25

10,612.25

63,673.50

26,504.50
#REF!

167,087.80

197,111.20

26,525.40

167,087.80
PEKERJAAN SANITASI ( SNI, 03 - 2836 - 2002 )
HARGA
NO. URAIAN BAHAN UPAH
SATUAN
1 Pemasangan 1 buah kloset Duduk (toto) auto flush
1.000 Bh Kloset Duduk porselen 4,775,000.00 4,775,000.00
0.120 Zak Semen portland ( 50 Kg) 60,000.00 7,200.00
0.010 M3 Pasir pasang 120,000.00 1,200.00
0.100 Oh Pekerja 65,000.00 6,500.00
1.500 Oh Tukang batu 80,000.00 120,000.00
1.500 Oh Kepala tukang 95,000.00 142,500.00
0.160 Oh Mandor 95,000.00 15,200.00
Jumlah
Over Head
Jumlah Total
2 Memasang 1 buah bak mandi fibreglass volume 0,30 m3
1.000 Bh Bak fibreglass 230,000.00 230,000.00
0.018 Pkt Perlengkapan 230,000.00 4,140.00
1.800 Oh Pekerja 65,000.00 117,000.00
2.700 Oh Tukang batu 80,000.00 216,000.00
0.540 Oh Kepala tukang 95,000.00 51,300.00
0.110 Oh Mandor 95,000.00 10,450.00
Jumlah
Over Head
Jumlah Total
3 Memasang 1 M1 pipa PVC tipe AW dia. 1/2"
1.200 M1 Pipa PVC 5,750.00 6,900.00
0.035 Pkt Perlengkapan 19,700.00 689.50
0.036 Oh Pekerja 65,000.00 2,340.00
0.060 Oh Tukang batu 80,000.00 4,800.00
0.006 Oh Kepala tukang 95,000.00 570.00
0.0018 Oh Mandor 95,000.00 171.00
Jumlah
Over Head
Jumlah Total
4 Memasangan 1 M1 pipa PVC tipe AW dia. 3"
1.200 M1 Pipa PVC 49,250.00 59,100.00
0.035 Pkt Perlengkapan 23,500.00 822.50
0.061 Oh Pekerja 65,000.00 3,965.00
0.135 Oh Tukang batu 80,000.00 10,800.00
0.0135 Oh Kepala tukang 95,000.00 1,282.50
0.0041 Oh Mandor 95,000.00 389.50
Jumlah
Over Head
Jumlah Total
5 Pemasangan 1 buah kran dia. 3/4" atau 1/2"
1.000 Bh Kran air 18,000.00 18,000.00
0.025 Bh Seal tape 5,000.00 125.00
0.010 Oh Pekerja 65,000.00 650.00
0.100 Oh Tukang batu 80,000.00 8,000.00
0.010 Oh Kepala tukang 95,000.00 950.00
0.005 Oh Mandor 95,000.00 475.00
Jumlah
Over Head
Jumlah Total
6 Pemasangan 1 buah Floor drain
1.000 Bh Floor drain toto 375,000.00 375,000.00
0.010 Oh Pekerja 65,000.00 650.00
0.100 Oh Tukang batu 80,000.00 8,000.00
0.010 Oh Kepala tukang 95,000.00 950.00
0.005 Oh Mandor 95,000.00 475.00
Jumlah
Over Head
Jumlah Total
7 Septick Tank Kapasitas 50
Bahan + Upah
30 m3 Galian Tanah 56,237.50 1,687,125.00
1 m3 Urugan Kembali 1/4 galian 40,975.00 40,975.00
9.5 m2 Pasangan Bata 1: 2 128,342.50 1,219,253.75
0.7 m3 Beton Tumbuk K 100 612,743.07 428,920.15
19 m2 Plesetran 1 : 2 53,920.68 1,024,492.92
0.408 m3 Plat Penutup Lantai (Plat Dag ) 4,157,561.38 1,697,116.55
1.05 m3 Kerikil Saringan 130,000.00 136,500.00
0.7 m3 Pasir Saringan 120,000.00 84,000.00
2.1 kg Saringan Ijuk 10,000.00 21,000.00
Jumlah
1 Pemasangan 1 buah kloset Duduk (toto) auto flush
1.000 Bh Klosed jongkok porselen 1,750,000.00 1,750,000.00
0.120 Zak Semen portland ( 50 Kg) 60,000.00 7,200.00
0.010 M3 Pasir pasang 120,000.00 1,200.00
0.100 Oh Pekerja 65,000.00 6,500.00
1.500 Oh Tukang batu 80,000.00 120,000.00
1.500 Oh Kepala tukang 95,000.00 142,500.00
0.160 Oh Mandor 95,000.00 15,200.00
Jumlah
Over Head
Jumlah Total

16
0.291
1.75
2.041
0.2041
JUMLAH KETERANGAN

5,574,360.00

4,783,400.00

284,200.00
5,067,600.00
506,760.00
5,574,360.00
691,779.00

234,140.00

394,750
628,890.00
62,889.00
691,779.00
17,017.55

7,589.50

7,881
15,470.50
1,547.05
17,017.55
83,995.45

59,922.50

16,437
76,359.50
7,635.95
83,995.45
31,020.00

18,125.00

10,075
28,200.00
2,820.00
31,020.00
423,582.50
375,000.00

10,075
385,075.00
38,507.50
423,582.50
6,339,383

6,339,383.37
6,339,383.37
2,246,860.00

1,758,400.00

284,200.00
2,042,600.00
204,260.00
2,246,860.00
RENCANA ANGGARAN BIAYA
PEKERJAAN :
LOKASI :

NO URAIAN SAT VOLUME

I PEKERJAAN PENDAHULUAN
Pekerjaan Pembongkaran Ls 1.00

II PEKERJAAN PONDASI
Galian Tanah Pondasi M3 238.15
Urugan Tanah Bekas Galian M3 78.59
Pasangan Aanstampang M3 45.47
Pasangan Batu Kali 1 : 4 M3 95.48
Timbunan Tanah M3 97.72
III PEKERJAAN STRUKTUR
Sloof 15/20
Stamp Beton K225 M3 7.14
Pembesian Kg 1,252.08
Bekisting Sloof M2 31.75
Kolom 20x30 (K1)
Stamp Beton K225 M3 0.86
Pembesian Kg 270.17
Bekisting Sloof M2 14.40
Kolom 25x25 (K2)
Stamp Beton K225 M3 1.35
Pembesian Kg 404.89
Bekisting Sloof M2 21.60
Kolom 15x15 (K3)
Stamp Beton K225 M3 5.51
Pembesian Kg 4,588.17
Bekisting Sloof M2 146.88
Ring Balok
Stamp Beton K225 M3 7.14
Pembesian Kg 1,252.08
Bekisting Balok M2 32.48
Balok Latei
Stamp Beton K225 M3 3.03
Pembesian Kg 581.04
Bekisting Balok M2 27.77
Dag Beton K 225
Stamp Beton K225 M3 7.57
Pembesian Kg 733.76
Bekisting M2 42.45

IV PEKERJAAN DINDING
Pasangan Bata 1/2 Bata 1pc : 2ps M2 142.89
Pasangan Bata 1/2 Bata 1pc : 4ps M2 617.44
Plesteran 1pc : 2ps M2 314.36
Plesteran 1pc : 4ps M2 1,234.89
Acian M2 1,549.25
Pasangan Lobang Angin Batu Bh 105.00

V PEKERJAAN KUZEN
Pasangan Kuzen Pintu dan Jendela Kayu kls I M3 1.15
Pasangan Pintu Panil M2 11.33
Pasangan rangka Jendela Kaca Kayu kls I M3 10.62
Pasangan Kaca Tebal 5 mm M2 17.61
Pasangan Engsel Pintu Bh 42.00
Pasangan Engsel Jendela Bh 26.00
Pasangan Kunci Tanam 2 Slag SES Bh 10.00
Pasangan Grendel Pintu Bh 60.00
Pasangan Grendel Jendela Bh 26.00
Pasangan Kait Angin Bh 50.00
Pasangan Tarikan Jendela Bh 13.00
Pasangan Pintu Aluminium + Rangka+kunci tanam Unit 6.00
Pasangan Pintu Aluminium Geser+rangka+kunci Unit 1.00
Pasangan Dinding Kaca Tebal 12mm M2 12.87
Klem Sudut Dinding Kaca Psg 5.00
VI PEKERJAAN KUDA-KUDA & ATAP
Pasangan Kuda-kuda Baja Ringan M2 750.94
Pasangan Atap Genteng Metal Berpasir M2 750.94
Pasangan Perabung Genteng metal berpasir M' 111.65
Pasangan Lisplank M' 61.00

VII PEKERJAAN PLAFOND


Pasangan Plafond Gypsum tebal 9 mm + Rangka Besi Hollow M2 417.28
Pasangan List Plafond Kayu M' 1,794.30

VIII PEKERJAAN LANTAI


Beton K 100 Lantai M3 22.89
Timbunan Pasir M3 32.71
Pasangan Granite 60 x 60 cm (Polished/Mengkilap) M2 327.05

IX PEKERJAAN CAT
Cat dinding dengan cat Air M2 1,549.25
Cat Plafond dengan cat air M2 417.28
Cat Kuzen, pintu, jendela dengan Cat Minyak M2 131.94

X PEKERJAAN INSTALASI LISTRIK BARU


Pasangan Titik Lampu ttk 58.00
Pasangan Stop kontak ttk 35.00
Stop Kontak Unit 35.00
Saklar tunggal Unit 7.00
Saklar Ganda Unit 19.00
Pasangan lampu Led 8 Watt
Pasangan lampu Led 14 Watt
Pasangan lampu Led 20 Watt Unit 78.00
Distribution Box Bh 1.00
Panel MCB Unit 5.00
XI PEKERJAAN PERLENGKAPAN DALAM
Pasangan Lantai Granite 60 x 60 cm (kesat Esenza Setara) M2 18.72
Pasangan Dinding Granite 60 x 60 cm Kesat (esenza Setara) M2 71.51
Pasangan Kloset Duduk Porselen (toto Setara) Unit 4.00
Pasangan Kloset Jongkok Porselen (toto Setara) Unit 1.00
Pasangan Bak Viber 60 x 60 x 60 cm Unit
Pasang Floor Drain Bh 5.00
Pasang Kran Air Dia 1/2 " Bh 9.00
Instalasi Air Bersih Pipa PVC Tipe AW Dia 3/4" M' 131.10
Instalasi Pembuang Pipa PVC Tipe AW Dia 4" M' 18.50
Instalasi Pembuangan Urine PVC 3 " M' 38.00
Pekerjaan Septiktank Unit 3.00
Tangki Air 2000L stainlessteel Set 1.00

XII PEKERJAAN PAGAR


1. PASANGAN PONDASI
Galian Tanah M3 6.89
Urugan Kembali M3 2.27
Pasangan Batu Kali M3 5.74
Sloof 15/20
Stamp Beton K225 M3 0.69
Pembesian Kg 121.13
Bekisting Sloof M2 3.06
Kolom Pagar K1
Stamp Beton K-225 M3 2.76
Besi Tulangan Kg 219.45
Bekisting M2 14.40
Kolom Pagar K2
Stamp Beton K-225 M3 0.58
Besi Tulangan Kg 44.03
Bekisting M2 11.52
PEKERJAAN DINDING DAN PLESTERAN
Pasangan Batu Bata 1/2 Bata 1pc : 2 ps M2 19.15
Pasangan Dinding Batu Alam M2 9.18
List Profil Beton Pagar M' 36.00
Plesteran M2 38.30
Acian M2 38.30
Cat Tembok M2 38.30
NA ANGGARAN BIAYA

HRG SAT. JUMLAH TOTAL JUMLAH

10,000,000.00
10,000,000.00 10,000,000.00

123,897,467.22
86,350.00 20,564,252.50
28,783.33 2,262,067.78
392,502.00 17,845,103.43
775,544.00 74,046,226.72
93,940.00 9,179,816.80
231,047,632.73

921,481.52 6,583,524.75
13,160.40 16,477,813.06
208,868.00 6,632,255.23

921,481.52 796,160.04
13,160.40 3,555,610.54
208,868.00 3,007,699.20

921,481.52 1,244,000.06
13,160.40 5,328,547.78
208,868.00 4,511,548.80

921,481.52 5,075,520.23
13,160.40 60,382,094.83
208,868.00 30,678,531.84

921,481.52 6,583,524.75
13,160.40 16,477,813.06
356,774.00 11,586,235.65

921,481.52 2,791,536.13
13,160.40 7,646,704.60
356,774.00 9,907,435.59

921,481.52 6,979,301.06
13,160.40 9,656,552.73
356,774.00 15,145,222.79

251,648,491.05
135,290.10 19,331,602.39
126,362.50 78,021,805.36
62,440.75 19,628,749.92
62,440.75 77,107,372.82
35,458.50 54,933,960.57
25,000.00 2,625,000.00

207,604,299.46
13,594,075.00 15,690,961.07
873,950.00 9,897,483.75
10,159,270.00 107,891,447.40
167,087.80 2,942,616.66
35,425.50 1,487,871.00
26,367.00 685,542.00
463,358.50 4,633,585.00
47,520.00 2,851,200.00
47,520.00 1,235,520.00
37,075.50 1,853,775.00
33,225.50 431,931.50
7,729,678.00 46,378,068.00
2,488,313.08 2,488,313.08
535,000.00 6,885,985.00
450,000.00 2,250,000.00
297,341,139.94
171,460.00 128,756,172.40
196,746.00 147,744,441.24
108,922.00 12,161,141.30
142,285.00 8,679,385.00

176,487,657.98
268,797.10 112,163,653.89
35,849.00 64,324,004.10

210,763,019.04
772,801.07 17,692,337.71
166,540.00 5,446,757.32
573,678.73 187,623,924.02

63,438,359.67
28,822.20 44,652,695.35
28,822.20 12,026,927.62
51,227.00 6,758,736.70

28,340,000.00
200,000.00 11,600,000.00
200,000.00 7,000,000.00
55,000.00 1,925,000.00
55,000.00 385,000.00

60,000.00 4,680,000.00
1,000,000.00 1,000,000.00
350,000.00 1,750,000.00
111,877,328.20
617,338.30 11,557,190.22
617,338.30 44,142,774.80
5,574,360.00 22,297,440.00
2,246,860.00 2,246,860.00
691,779.00 -
55,082.50 275,412.50
31,020.00 279,180.00
35,839.10 4,698,506.01
68,350.70 1,264,487.95
68,350.70 2,597,326.60
6,339,383.37 19,018,150.11
3,500,000.00 3,500,000.00

37,682,525.61

69,300.00 477,130.50
23,100.00 52,484.36
656,944.01 3,769,216.25
921,481.52 634,440.03
13,160.40 1,594,066.27
208,868.00 639,136.08

921,481.52 2,546,237.75
13,160.40 2,888,106.00
356,774.00 5,137,545.60

921,481.52 530,773.36
13,160.40 579,490.52
356,774.00 4,110,036.48

135,290.10 2,590,805.42
302,709.00 2,779,625.39
125,000.00 4,500,000.00
62,440.75 2,391,480.80
35,458.50 1,358,060.55
28,822.20 1,103,890.26
ANALISA KUANTITAS
PEKERJAAN : PEMBANGUNAN RUMAH
LOKASI : KABUPAREN LIMA PULUH KOTA

No URAIAN ANALISA

Pembersihan Lapangan
Panjang =
Lebar =

Volume = =

Pasangan Bowplank

Panjang =

Volume = =
Pembersihan Lapangan
Pasangan Bowplank
ANALISA VOLUME

8.00 m
6.00 m

48.00

39.29 m 39.29

39.29
= 48.00
= 39.29
ANALISA KUANTITAS

No URAIAN ANALISA

PANJANG PONDASI (p)


GALIAN
Lebar Atas Galian (L) =
25 Lebar Bawah Galian (L) =
Tinggi Galian (t) =

Volume Galian =
(1.20 + 1.00) x 1 x 216.5 = 238.15 M3
47 2

80 URUGAN BEKAS GALIAN


Volume Galian =
Volume Urugan = 1/3 x Vol Galian
= 0.33 x 238.15
= 78.59 M3
20 ANSTAMPANG
Lebar (L) =
100 Tinggi (t) =

80 Volume Anstampang = 1.00 x 0.20 x 216.5


= 43.30 M3
PONDASI BATU KALI
Lebar Atas Pondasi (L1) =
Lebar Bawah Pondasi (L2) =
Tinggi Pondasi (t) =
Total Panjang (p)

PONDASI1 - Page 134


Volume Pondasi Batu Kali
(0.25 + 0.80) x 0.80 x 216.50 = 90.93 M3
2

PONDASI1 - Page 135


ALISA KUANTITAS

ANALISA VOLUME

216.50
238.15
1.20
1.00
1.00

78.59
238.15

43.30
1.00
0.20

1.00 x 0.20 x 216.5

90.93
0.25
0.80
0.80
216.50

PONDASI1 - Page 136


PONDASI1 - Page 137
ANALISA KUANTITAS

No URAIAN ANALISA

PANJANG PONDASI (p)


GALIAN
List Beton Lebar Atas Galian (L) =
48 Lebar Bawah Galian (L) =
40 List Beton
Tinggi Galian (t) =
20

Jeruji Besi
Volume Galian =
(0.60 + 0.60) x 0.5 x 22.95 = 6.89 M3
Pipa besi Hollow Ø 2"
2
Pagar Teralis Besi

Pipa besi Hollow Ø 2" URUGAN BEKAS GALIAN


100 Volume Galian =
List Beton Volume Urugan = 1/3 x Vol Galian
= 0.33 x 6.89
= 2.27 M3
List Beton

40 Angkur Besi Ø10 Jarak 100 cm

20
Pas. batu kali 1:4
PONDASI BATU KALI
Lebar Atas Pondasi (L1) =
50 Lebar Bawah Pondasi (L2) =
Tinggi Pondasi (t) =
Total Panjang (p)

40
PAGAR - Page 138
50

40
Volume Pondasi Batu Kali
60
(0.4 + 0.60) x 0.50 x 22.95 = 5.74 M3
2

PAGAR - Page 139


ALISA KUANTITAS

ANALISA VOLUME

22.95
6.89
0.60
0.60
0.50

2.27
6.89

5.74
0.40
0.60
0.50
22.95

PAGAR - Page 140


PAGAR - Page 141
ANALISA KUANTITAS

No URAIAN ANALISA
GAMBAR SLOFF
Volume Sloof 15X20 Rumah
Lebar Balok (L) = 0.15
Tinggi Balok (t) = 0.20
Panjang (P) = 216.50
Jumlah (n) = 1.00

Volume = 1 x ( 0.15 x 0.20 x 216.50)

Volume Besi Tulangan

Volume Pemakain Besi (kg)


Jumlah Pjg/ Unit brt besi/m
Besi Dia 12 = 4.00 x 216.62 x 0.888
Begol 8 = 1732.00 x 0.54 x 0.395

Pembesian = 1 x (769.23 + 369.02 )


Volume Bekisting 3 x pakai

Bekisting = 2 x ( 216.50 x 0.20)

Total = (1 x 86.60) / 3
Volume Sloof 15X20 Pagar
Lebar Balok (L) = 0.15
Tinggi Balok (t) = 0.20
Panjang (P) = 22.95
Jumlah (n) = 1.00

Volume = 1 x ( 0.15 x 0.20 x 22.95)

Volume Besi Tulangan

Volume Pemakain Besi (kg)


Jumlah Pjg/ Unit brt besi/m
Besi Dia 12 = 4.00 x 23.07 x 0.888
Begol 8= 184.00 x 0.54 x 0.395

Pembesian = 1 x (81.92 + 39.20 )


Volume Bekisting 3 x pakai

Bekisting = 2 x ( 22.95 x 0.20)

Total = (1 x 9.18) / 3

Stamp beton K225


Tulangan
Bekisting
ANTITAS

VOLUME

M
M
M

6.50

brt besi/m Berat besi


= 769.23
= 369.02

1,138.25

= 86.6

28.87
M
M
M

0.69

brt besi/m Berat besi


= 81.92
= 39.20

121.13

= 9.18

3.06

= 6.50
= 1138.25
= 28.87
ANALISA KUANTITAS

URAIAN ANALISA
Volume Beton K 225 Untuk Kolom 15x15 (K3)
Lebar Kolom (L) = 0.15 M
Panjang Kolom (L) = 0.15 M
Tinggi Balok (t) = 3.60 M

Jumlah (n) = 68.00

Volume = 68 x ( 0.15 x 0.15 x 3.60)


Volume Pemakaian Besi Kolom 15x15
Besi Dia 12 = 4.00 x 1,088.00 x 0.888 =
Begol 10 = 1959.00 x 0.60 x 0.617 =

Volume Bekisting Untuk Kolom 15x15 Untuk 2 x Pakai


Lebar Kolom (L) = 0.60 M
Panjang Kolom (L) = 244.80 M

Volume Bekisting = 2 x ( 244.80 x 0.60)


Volume = 1/2 x ( 293.76)
Stamp beton K225
Pembesian Untuk K3
Bekisting
URAIAN ANALISA
Volume Beton K 225 Untuk Kolom 20x30 (K1)
Lebar Kolom (L) = 0.20 M
Panjang Kolom (L) = 0.30 M
Tinggi Kolom (t) = 3.60 M

Jumlah (n) = 4.00

Volume = 4 x ( 0.20 x 0.30 x 3.60)


Volume Pemakaian Besi Kolom 20x30 (K1)
Besi Dia 12 = 4.00 x 64.00 x 0.888 =
Begol 10 = 116.00 x 0.60 x 0.617 =

Volume Bekisting Untuk Kolom 20x30 Untuk 2 x Pakai


Lebar Kolom (L) = 1.00 M
Panjang Kolom (L) = 14.40 M

Volume Bekisting = 2 x ( 14.40 x 1.00)


Volume = 1/2 x ( 28.80)

Stamp beton K225


Pembesian Untuk K3
Bekisting
URAIAN ANALISA
Volume Beton K 225 Untuk Kolom 25x25 (K2)
Lebar Kolom (L) = 0.25 M
Panjang Kolom (L) = 0.25 M
Tinggi Kolom (t) = 3.60 M

Jumlah (n) = 6.00

Volume = 6 x ( 0.25 x 0.25 x 3.60)


Volume Pemakaian Besi Kolom 25x25 (K2)
Besi Dia 12 = 4.00 x 96.00 x 0.888 =
Begol 10 = 173.00 x 0.60 x 0.617 =

Volume Bekisting Untuk Kolom 25x25 Untuk 2 x Pakai


Lebar Kolom (L) = 1.00 M
Panjang Kolom (L) = 21.60 M

Volume Bekisting = 2 x ( 21.60 x 1.00)


Volume = 1/2 x ( 43.20)

Stamp beton K225


Pembesian Untuk K3
Bekisting
URAIAN ANALISA
Volume Beton K 225 Untuk Kolom 25x25 (K1) PAGAR
Lebar Kolom (L) = 0.50 M
125 Panjang Kolom (L) = 0.40 M
3 Ø 10 Tinggi Kolom (t) = 1.80 M

Jumlah (n) = 8.00


Ø8 - 200

100 3 Ø 10

Volume = 8 x ( 0.50 x 0.40 x 1.80)


Volume Pemakaian Besi Kolom 25x25 (K2)
25
Besi Dia 10 = 1.80 x 144.00 x 0.617 =
4 Ø 10
Begol 8= 9.00 x 16.80 x 0.395 =
37 50 37

Volume Bekisting Untuk Kolom 25x25 Untuk 2 x Pakai


Lebar Kolom (L) = 2.00 M
Panjang Kolom (L) = 1.80 M

Volume Bekisting = 8 x ( 1.80 x 2.00)


Volume = 1/2 x ( 28.80)

Stamp beton K225


Pembesian Untuk K3
Bekisting
URAIAN ANALISA
Volume Beton K 225 Untuk Kolom 25x25 (K2) PAGAR
Lebar Kolom (L) = 0.40 M
Panjang Kolom (L) = 0.40 M
Tinggi Kolom (t) = 1.80 M
40
2 Ø 10 Jumlah (n) = 2.00

Volume = 2 x ( 0.40 x 0.40 x 1.80)


Volume Pemakaian Besi Kolom 25x25 (K2)
Ø8 - 200 Besi Dia 10 = 1.80 x 28.80 x 0.617 =
Begol 8= 9.00 x 3.40 x 0.395 =
40 2 Ø 10

2 Ø 10 Volume Bekisting Untuk Kolom 25x25 Untuk 2 x Pakai


Lebar Kolom (L) = 1.60 M
Panjang Kolom (L) = 1.80 M

Volume Bekisting = 8 x ( 1.80 x 1.60)


Volume = 1/2 x ( 23.04)

Stamp beton K225


Pembesian Untuk K3
Bekisting
ISA KUANTITAS

ANALISA VOLUME

5.51 M3

### 3863.53 Kg
### 724.63 Kg
4588.17 Kg

293.76 M2
146.88 M2
5.51 M3
4588.17 Kg
146.88 M2
ANALISA VOLUME

0.86 M3

### 227.27 Kg
### 42.91 Kg
270.17 Kg

28.8 M2
14.40 M2

0.86 M3
270.17 Kg
14.40 M2
ANALISA VOLUME

1.35 M3

### 340.90 Kg
### 63.99 Kg
404.89 Kg

43.2 M2
21.60 M2

1.35 M3
404.89 Kg
21.60 M2
ANALISA VOLUME

2.76 M3

### 159.80 Kg
### 59.66 Kg
219.45 Kg

28.8 M2
14.40 M2

2.76 M3
219.45 Kg
14.40 M2
ANALISA VOLUME

0.58 M3

### 31.96 Kg
### 12.07 Kg
44.03 Kg

23.04 M2
11.52 M2

0.58 M3
44.03 Kg
11.52 M2
ANALISA KUANTITAS

PEKERJAAN : PEMBANGUNAN RAUNG LAYANAN LANSIA


LOKASI : KEC. RANAH PESISIR

No URAIAN ANALISA

DENAH PASANGAN BATA PASANGAN DINDING BATA


Pasangan Bata 1 : 2
Panjang = 216.50
Tinggi = 0.60
Luas = 129.90

Pasangan Bata 1 : 4
Panjang = 216.50
Tinggi = 3.00
Luas = 561.31

Pengurangan Pasangan Bata 88.19

Panjang = 2.48 m
Lebar = 0.90 m
Jumlah = 8.00 bh
Luas = 17.856 m2

Jendela 2 Jendela 4
Panjang = 1.50 m Panjang = 1.75
Lebar = 1.75 m Lebar = 2.20
Jumlah = 3.00 bh Jumlah = 1.00
Luas = 7.88 m2 Luas = 3.85

Jendela 3 Jendela 1
Panjang = 1.75 m Panjang = 1.75
Lebar = 1.85 m Lebar = 0.80
Jumlah = 1.00 unit Jumlah = 3.00

Total Pasangan Bata 1 : 4


CAT DINDING PENGECATAN PUSTU

Panjang = 2.80 m
Tinggi = 3.80 m
Lebar = 4.50 m
Luas = 442.32 m2

CAT DINDING

REKAPITULASI

Pas. bata 1 : 2
Pas. bata 1 : 4
Plesteran 1 : 2
Plesteran 1 : 4
Acian
Cat Tembok
DENAH PASANGAN BATA PASANGAN DINDING BATA
Pasangan Bata 1 : 4
Panjang = 16.71
Lebar = 0.30
Luas = 5.01

140
Pasangan Bata 1 : 4
Panjang = 9.56
Lebar = 0.30
Jumlah = 3.00
Luas = 8.60

Pasangan Bata 1 : 4
Panjang = 8.06
Lebar = 0.30
Jumlah = 1.00
Luas = 2.42
235

Pasangan Bata 1 : 4
Panjang = 3.23
Lebar = 0.30
Jumlah = 1.00
Luas = 0.97

Total Pasangan Bata 1 : 4

185 100
273 223
Pas. bata 1 : 2
Pas. bata 1 : 4
75 Plesteran 1 : 2
78 Plesteran 1 : 4
Acian
Cat Tembok
VOLUME

m
m
m2
18.95 11.5
0.038 0.043

m
m
m2 Bata Pasir Semen
691.21 48,384.91 4.94 2,461.61
24.14 6,455.10
29.07 8,916.70
178.33 zak

Lobang angin 2 4 2 1 1 1
15 J1 j2 jp1 P P1 p2
0.15 1.55 0.6 2.2 2.2 2.2 2.2
0.2 1.6 1.8 0.9 1.3 0.7 0.9
0.45
561.31 1.2
0.45 4.96 4.32 3.96 2.86 1.54 1.98
1.08

Luas Pengurang 21.15


1,382.43

0,60 =Tinggi pasangan bata 1:2


129.90
561.31
129.90
561.31
691.21
1,382.43
m
m
m2

m 80 150 90 80 185 300

m
175 175 175 175
m 263 263

m2

m
m
m
m2

m
m
m
m2

17.00
0.00
17.00

34.01
34.01
80 150 90 80 185 300

175 175 175 175


263 263
ANALISA KUANTITAS

KEGIATAN :
PEKERJAAN :
LOKASI :

No URAIAN ANALISA
GAMBAR KUZEN Type P1
1. Type P.1 ( 1 Unit )
Jumlah
Panjang kozen
Lebar kayu kozen
Tinggi kayu kozen
Lebar daun pintu
Tinggi daun pintu

Kozen = 6.20 x 0.05 x


= 0.05 x 1.00 =

Luas Pintu = 0.65 x 2.30 x

Luas Kaca =
Luas rangka Pi = 0.06 x 6.90 x

Luas Cat Kusen


Pasangan Engsel Pintu
Pasangan Grendel
Luas Kaca
Pasangan Kunci Tanam 2 Slag
Konzen
Luas pintu panel
Cat pintu
No URAIAN ANALISA
No URAIAN ANALISA
GAMBAR KUZEN Type J1 P4
2. Type j1 P4 ( 1 Unit )

Jumlah
105 85 5 70 5 70 5 70 510
Panjang kozen
Lebar kayu kozen
Tinggi kayu kozen
Lebar rangka jendela
5 Panjang rangka jendela
Lebar kaca kiri-kanan
Tinggi kaca kiri-kanan
Lebar kaca tengah
Tinggi kaca tengah
Lebar kaca tengah
Tinggi kaca tengah
Lebar kaca bawah
225235
Tinggi kaca bawah

Kozen = 17.55 x 0.05 x


= 0.13 x 1.00 =

Luas rangka j = 0.06 x 6.75 x

5
Luas Kaca =
Konzen
Pasangan Cat Kusen
Pasangan Engsel Jendela
Pasangan Grendel
Pasangan Tarikan jendela
Pasangan Kait angin
luas Jendela kaca rangka kayu
Luas Cat Rangka Kaca
1. Type P.4 ( 1 Unit )
Jumlah
Panjang kozen
Lebar kayu kozen
No URAIAN ANALISA
Tinggi kayu kozen
Lebar daun pintu
Tinggi daun pintu
Luas Pintu = 0.85 x 2.30 x

Luas pintu panel


Cat pintu panel
Pasangan Kunci Tanam 2 Slag
Pasangan Engsel Pintu
GAMBAR KUZEN Type P2 1. Type P.2 ( 1 Unit )
Jumlah
160 Panjang kozen
Lebar kayu kozen
Tinggi kayu kozen
Lebar daun pintu
Tinggi daun pintu

Kozen = 6.10 x 0.05 x


= 0.05 x 1.00 =

Luas Pintu = 0.65 x 2.20 x

Luas Kaca =
Luas rangka Pi = 0.06 x 6.90 x

Konzen
Luas Cat Kusen
Pasangan Engsel Pintu
Pasangan Grendel
Luas Kaca
Pasangan Kunci Tanam 2 Slag
Konzen
Luas pintu panel
No URAIAN ANALISA
Cat pintu

2. Type j2 ( 3 Unit )
175
105 70 5 70 510 Jumlah
Panjang kozen
Lebar kayu kozen
Tinggi kayu kozen
Lebar rangka jendela
5 Panjang rangka jendela
Lebar kaca kiri-kanan
Tinggi kaca kiri-kanan

215 225

Kozen = 10.25 x 0.05 x


= 0.08 x 3.00 =

Luas rangka j = 0.06 x 9.25 x

Luas Kaca =
5

Pasangan Cat Kusen


Pasangan Engsel Jendela
Pasangan Grendel
Pasangan Tarikan jendela
Pasangan Kait angin
luas Jendela kaca rangka kayu
Luas Cat Rangka Kaca
Konzen
No URAIAN ANALISA
Type P.3 ( 1 Unit )
120
Jumlah
Panjang kozen
Lebar kayu kozen
Tinggi kayu kozen
Lebar daun pintu
Tinggi daun pintu

Kozen = 5.50 x 0.05 x


= 0.04 x 1.00 =

Luas Pintu = 0.90 x 2.10 x

Konzen
Luas Cat Kusen
Pasangan Engsel Pintu
Pasangan Grendel

Pasangan Kunci Tanam 2 Slag


Konzen
Luas pintu panel
Cat pintu

Type P.5 ( 4 Unit )


115 Jumlah
Panjang kozen
105 85 510
Lebar kayu kozen
Tinggi kayu kozen
Lebar daun pintu
15
Tinggi daun pintu
5
No URAIAN 15 ANALISA

Kozen = 5.65 x 0.05 x


= 0.04 x 4.00 =

Luas Pintu = 0.85 x 2.20 x

220 225

Konzen
Luas Cat Kusen
Pasangan Engsel Pintu
Pasangan Grendel

Pasangan Kunci Tanam 2 Slag


Konzen
Luas pintu panel
Cat pintu

2. Type J3 ( 6 Unit )

175
Jumlah
105 70 5 70 510 Panjang kozen
Lebar kayu kozen
Tinggi kayu kozen
Lebar rangka jendela
Panjang rangka jendela
Lebar kaca kiri-kanan
5 Tinggi kaca kiri-kanan
No URAIAN ANALISA

160 170
Kozen = 8.60 x 0.05 x
= 0.06 x 6.00 =

Luas rangka j = 0.06 x 17.20 x

Luas Kaca =

5
Pasangan Cat Kusen
Pasangan Engsel Jendela
Pasangan Grendel
Pasangan Tarikan jendela
Pasangan Kait angin
luas Jendela kaca rangka kayu
Luas Cat Rangka Kaca
Konzen

Type J4 ( 1 Unit )
100
Jumlah
105 70 510 Panjang kozen
Lebar kayu kozen
Tinggi kayu kozen
Lebar rangka jendela
Panjang rangka jendela
Lebar kaca kiri-kanan
5 Tinggi kaca kiri-kanan
No URAIAN ANALISA

Kozen = 5.40 x 0.05 x


160 170
= 0.04 x 1.00 =

Luas rangka j = 0.06 x 8.60 x

Luas Kaca =

Pasangan Cat Kusen


Pasangan Engsel Jendela
5 Pasangan Grendel
Pasangan Tarikan jendela
Pasangan Kait angin
luas Jendela kaca rangka kayu
Luas Cat Rangka Kaca
Konzen

Type J5 ( 2 Unit )
135
Jumlah
105 50 5 50 510
Panjang kozen
Lebar kayu kozen
Tinggi kayu kozen
Lebar rangka jendela
15 Panjang rangka jendela
5 Lebar kaca kiri-kanan
Tinggi kaca kiri-kanan
KACA BLUR KACA BLUR
5 MM 5 MM 6070

5
No URAIAN ANALISA
Kozen = 4.10 x 0.05 x
= 0.03 x 2.00 =

Luas rangka j = 0.06 x 8.60 x

Luas Kaca =

Pasangan Cat Kusen


Pasangan Engsel Jendela
Pasangan Grendel
Pasangan Tarikan jendela
Pasangan Kait angin
luas Jendela kaca rangka kayu
Luas Cat Rangka Kaca
Konzen

Luas Cat Kusen


Pasangan Engsel Pintu
Pasangan Grendel
Pasangan Tarikan jendela
Pasangan Kunci Tanam 2 Slag
Kayu Konzen
Luas pintu panel
Cat Minyak
Pasangan Engsel Jendela
luas Jendela rangka kayu
Luas Kaca tebal 5 mm
Pasangan Kait Angin
No URAIAN ANALISA
KEGIATAN :
PEKERJAAN :
LOKASI :

No URAIAN ANALISA
GAMBAR KUZEN Type P1
1. Type P.1 ( 2 Unit )
Jumlah
Panjang kozen 2,8 + 2,8 + 1,2
5 Lebar kayu kozen
Tinggi kayu kozen
60 Lebar daun pintu
Tinggi daun pintu
5

280 Kozen = 6.80 x 0.05 x


= 0.05 x 2.00 =
210
Luas Pintu = 1.20 x 2.10 x

Papan Papan
Panil Panil

15
Luas Cat Kusen
Pasangan Engsel Pintu
5 5 Pasangan Grendel
120
Pasangan Tarikan jendela
Pasangan Kunci Tanam 2 Slag
Konzen
Luas pintu panel
Cat pintu panel
No URAIAN ANALISA
GAMBAR KUZEN Type Pj1
1. Type P.2 ( 4 Unit )
Jumlah
Panjang kozen 2,8 + 0,9 + 0,65 +1,9 +
Lebar kayu kozen
Tinggi kayu kozen
Lebar daun pintu
Tinggi daun pintu
Lebar rangka jendela
Panjang rangka jendela
Lebar kaca
Tinggi kaca

Kozen = 7.80 x 0.05 x


= 0.06 x 4.00 =

Luas Pintu = 0.80 x 2.10 x

Luas rangka je = 0.06 x 3.26 x

Luas Kaca = 0.48 x 1.03 x

Luas Cat Kusen


Pasangan Engsel Pintu
Pasangan Grendel
Pasangan Engsel jendela
Pasangan Kunci Tanam 2 Slag
Konzen
Luas pintu panel
Cat pintu panel
No URAIAN ANALISA
GAMBAR KUZEN Type J1
2. Type j1 ( 16 Unit )

Jumlah
Panjang kozen = (1,9 X 4)+(0,6 X 6)+(
Lebar kayu kozen
5
Tinggi kayu kozen
60 Lebar rangka jendela
Panjang rangka jendela
5 Lebar kaca kiri-kanan
Tinggi kaca kiri-kanan
190 Lebar kaca tengah
Kaca Kaca Kaca
3 mm
Tinggi kaca tengah
3 mm 5 mm
115

Kozen = 14.20 x 0.05 x


= 0.11 x 16.00 =
5
Luas rangka je = 0.06 x 6.75 x
60
90 Luas Kaca = ( 1,03 x 0,48 x 2 ) + ( 0,6 x 1,15 ) x
15 30
60 100 60
5 5 5 5 Pasangan Cat Kusen
15 Pasangan Engsel Jendela
240
Pasangan Grendel
Pasangan Tarikan jendela
Pasangan Kait angin
luas Jendela kaca rangka kayu

REKAPITULASI

Luas Cat Kusen


Pasangan Engsel Pintu
Pasangan Grendel
Pasangan Tarikan jendela
No URAIAN ANALISA

Pasangan Kunci Tanam 2 Slag


Konzen
Luas pintu panel
Cat pintu panel
Pasangan Engsel Jendela
luas Jendela rangka kayu
Luas Kaca tebal 3 mm
Pasangan Kait Angin
No URAIAN ANALISA

KEGIATAN :
PEKERJAAN :
LOKASI :

No URAIAN ANALISA
GAMBAR KUZEN Type P1
1. Type P.1 ( 1 Unit )
Jumlah
Panjang kozen 2,8 + 2,8 + 1,2
5
Lebar kayu kozen
Tinggi kayu kozen
60
Lebar daun pintu
5 Tinggi daun pintu

280
Kozen = 6.80 x 0.05 x
= 0.05 x 1.00 =
210

Luas Pintu = 1.20 x 2.10 x

Papan Papan
Panil Panil

15
Luas Cat Kusen
Pasangan Engsel Pintu
5 5
120 Pasangan Grendel
Pasangan Tarikan jendela
Pasangan Kunci Tanam 2 Slag
Konzen
Luas pintu panel
Cat pintu panel
No URAIAN ANALISA

GAMBAR KUZEN Type J1


2. Type j1 ( 7 Unit )

Jumlah
Panjang kozen = (1,9 X 4)+(0,6 X 6)+(
Lebar kayu kozen
Tinggi kayu kozen
Lebar rangka jendela
Panjang rangka jendela
Lebar kaca kiri-kanan
Tinggi kaca kiri-kanan
Lebar kaca tengah
Tinggi kaca tengah

Kozen = 14.20 x 0.05 x


= 0.11 x 7.00 =

Luas rangka je = 0.06 x 14.20 x

Luas Kaca = ( 1,03 x 0,48 x 2 ) + ( 0,6 x 1,15 ) x

Pasangan Cat Kusen


Pasangan Engsel Jendela
Pasangan Grendel
Pasangan Tarikan jendela
Pasangan Kait angin
luas Jendela kaca rangka kayu

REKAPITULASI

Luas Cat Kusen


Pasangan Engsel Pintu
Pasangan Grendel
No URAIAN ANALISA

Pasangan Tarikan jendela


Pasangan Kunci Tanam 2 Slag
Konzen
Luas pintu panel
Cat pintu panel
Pasangan Engsel Jendela
luas Jendela rangka kayu
Luas Kaca tebal 3 mm
Pasangan Kait Angin

KEGIATAN :
PEKERJAAN :
LOKASI :

No URAIAN ANALISA
GAMBAR VENTILASI
1. Type V.1 ( 6 Unit )
Jumlah
Panjang kozen (0,7 X 2 )+(0,6 X 2)
Lebar kayu kozen
Tinggi kayu kozen
Lebar ventilasi kaca
Panjang ventilasi kaca
Jumlah kaca untuk 1 ventilasi

Kozen = 2.60 x 0.05 x


= 0.02 x 6.00 =

Luas Kaca = 0.40 x 0.60 x


= 2.88 m2
Luas Cat Kusen
Luas kaca 3 mm
Pasangan Engsel Pintu
Pasangan Grendel
Pasangan Tarikan jendela
No URAIAN ANALISA

Pasangan Kunci Tanam 2 Slag


Konzen
Luas pintu panel
Cat pintu panel
REKAPITULASI

Luas Cat Kusen


Pasangan Engsel Pintu
Pasangan Grendel
Pasangan Tarikan jendela
Pasangan Kunci Tanam 2 Slag
Konzen
Luas pintu panel
Cat pintu panel
Pasangan Engsel Jendela
luas Jendela rangka kayu
Luas Kaca tebal 3 mm
Pasangan Kait Angin
NALISA KUANTITAS

ANALISA VOLUME

= 1.00
= 6.20
= 0.05
= 0.15
= 0.65
= 2.30

0.15 = 0.05
0.05 m3

1.00 = 1.50 M2

= 1.84 m2
2.00 = 0.83 m2

= 0.62 m2
= 8.00 psg
= 4.00 bh
= 1.84 m2
= 1.00 set
= 0.05 m3
= 1.50 m2
= 1.66 m2
ANALISA VOLUME
ANALISA VOLUME

= 3.00
= 17.55
= 0.05
= 0.15
= 0.06
= 6.75
= 0.30
= 0.51
= 0.30
= 0.51
= 0.30
= 0.51
= 0.30
= 0.51

0.15 = 0.13
0.13 m3

3.00 = 1.22 m2

= 3.67 m2
= 0.13 m3
= 1.76 m2
= 6.00 psg
= 12.00 bh
= 3.00 bh
= 12.00 bh
= 1.22 m2
= 16.43 m2

= 3.00
=
= 0.05
ANALISA VOLUME
= 0.15
= 0.85
= 2.30
1.00 = 1.96 M2

= 1.96 m2
= 8.45 m2
= 3.00 set
= 4.00 psg

= 1.00
= 6.10
= 0.05
= 0.15
= 0.65
= 2.20

0.15 = 0.05
0.05 m3

1.00 = 1.43 M2

= 1.84 m2
2.00 = 0.83 m2

= 0.05 m3
= 0.61 m2
= 8.00 psg
= 4.00 bh
= 1.84 m2
= 1.00 set
= 0.05 m3
= 1.43 m2
ANALISA VOLUME
= 1.66 m2

= 3.00
= 10.25
= 0.05
= 0.15
= 0.06
= 9.25
= 0.28
= 0.50

0.15 = 0.08
0.23 m3

3.00 = 1.67 m2

= 2.24 m2

= 3.08 m2
= 6.00 psg
= 12.00 bh
= 3.00 bh
= 12.00 bh
= 1.67 m2
= 17.33 m2
= 0.23 m3
ANALISA VOLUME

= 1.00
= 5.50
= 0.05
= 0.15
= 0.90
= 2.10

0.15 = 0.04
0.04 m3

1.00 = 1.89 M2

= 0.04 m3
= 0.55 m2
= 4.00 psg
= bh

= 1.00 set
= 0.04 m3
= 1.89 m2
= 4.06 m2

= 4.00
= 5.65
= 0.05
= 0.15
= 0.85
= 2.20
ANALISA VOLUME

0.15 = 0.04
0.17 m3

4.00 = 7.48 M2

= 0.17 m3
= 0.57 m2
= 16.00 psg
= bh

= 4.00 set
= 0.17 m3
= 7.48 m2
= 15.24 m2

= 6.00
= 8.60
= 0.05
= 0.15
= 0.06
= 17.20
= 0.28
= 0.36
ANALISA VOLUME

0.15 = 0.06
0.39 m3

6.00 = 6.19 m2

= 1.61 m2

= 0.86 m2
= 12.00 psg
= 24.00 bh
= 6.00 bh
= 24.00 bh
= 6.19 m2
= 26.38 m2
= 0.39 m3

= 1.00
= 5.40
= 0.05
= 0.15
= 0.06
= 8.60
= 0.28
= 0.36
ANALISA VOLUME

0.15 = 0.04
0.04 m3

1.00 = 0.52 m2

= 0.81 m2

= 0.54 m2
= 2.00 psg
= 4.00 bh
= 1.00 bh
= 2.00 bh
= 0.52 m2
= 15.03 m2
= 0.04 m3

= 2.00
= 4.10
= 0.05
= 0.15
= 0.06
= 8.60
= 0.50
= 0.35
ANALISA VOLUME
0.15 = 0.03
0.06 m3

2.00 = 1.03 m2

= 5.60 m2

= 0.41 m2
= psg
= bh
= bh
= bh
= 1.03 m2
= 16.06 m2
= 0.06 m3

= 8.99
= 42.00
= 60.00
= 13.00
= 16.00
= 1.15
= 11.33
= 131.94
= 26.00
= 10.62
= 17.61
= 50.00
ANALISA VOLUME

ANALISA VOLUME

= 2.00
2,8 + 2,8 + 1,2 = 6.80
= 0.05
= 0.15
= 1.20
= 2.10

0.15 = 0.05
0.10 m3

2.00 = 5.04 M2

= 0.68 m2
= 8.00 psg
= 4.00 bh
= -
= 2.00 set
= 0.10 m3
= 5.04 m2
= 10.08 m2
ANALISA VOLUME

= 4.00
2,8 + 0,9 + 0,65 +1,9 +1,55 = 7.80
= 0.05
= 0.15
= 0.80
= 2.10
= 0.06
= 3.26
= 0.48
= 1.03

0.15 = 0.06
0.23 m3

4.00 = 6.72 M2

4.00 = 0.78 m2

4.00 = 1.98 m2

= 0.78 m2
= 8.00 psg
= 8.00 bh
= 8.00
= 4.00 set
= 7.80 m3
= 6.72 m2
= 13.44 m2
ANALISA VOLUME

= 16.00
(1,9 X 4)+(0,6 X 6)+(1 X 3) = 14.20
= 0.05
= 0.15
= 0.06
= 6.75
= 0.48
= 1.03
= 0.60
= 1.15

0.15 = 0.11
1.70 m3

16.00 = 6.48 m2

( 1,03 x 0,48 x 2 ) + ( 0,6 x 1,15 ) x 14 = 26.86 m2

= 1.42 m2
= 32.00 psg
= 64.00 bh
= 32.00 bh
= 64.00 bh
= 6.48 m2

= 2.88
= 16.00
= 76.00
= 32.00
ANALISA VOLUME
= 6.00
= 0.44
= 11.76
= 23.52
= 40.00
= 7.26
= 28.84
= 64.00
ANALISA VOLUME

ANALISA VOLUME

= 1.00
2,8 + 2,8 + 1,2 = 6.80
= 0.05
= 0.15
= 1.20
= 2.10

0.15 = 0.05
0.05 m3

1.00 = 2.52 M2

= 0.68 m2
= 4.00 psg
= 2.00 bh
= -
= 1.00 set
= 0.05 m3
= 2.52 m2
= 5.04 m2
ANALISA VOLUME

= 7.00
(1,9 X 4)+(0,6 X 6)+(1 X 3) = 14.20
= 0.05
= 0.15
= 0.06
= 14.20
= 0.48
= 1.03
= 0.60
= 1.15

0.15 = 0.11
0.75 m3

7.00 = 5.96 m2

( 1,03 x 0,48 x 2 ) + ( 0,6 x 1,15 ) x 7 = 11.75 m2

= 1.42 m2
= 14.00 psg
= 28.00 bh
= 14.00 bh
= 28.00 bh
= 5.96 m2

= 2.10
= 4.00
= 30.00
ANALISA VOLUME
= 14.00
= 1.00
= 0.80
= 2.52
= 5.04
= 14.00
= 5.96
= 11.75
= 28.00

ANALISA VOLUME

= 6.00
(0,7 X 2 )+(0,6 X 2) = 2.60
= 0.05
= 0.15
= 0.40
= 0.60
= 2.00

0.15 = 0.02
0.12 m3

2.00 x 6.00

= 0.26 m2
= 2.88 m2
= - psg
= - bh
= - bh
ANALISA VOLUME
= - set
= - m3
= - m2
= - m2

= 0.26
= -
= -
= -
= -
= 0.12
= -
= -
= -
= -
= 2.88
= -