RINCIAN REKAPITULASI TERMIJN I 30%

PAKET 10 REVIEW DESAIN PEMBANGUNAN JEMBATAN S. RANTAU BERANGIN CS

NOMOR KONTRAK : HK.02.01/Bb23-P2JN.R1/10


TANGGAL 15 MARET 2022
PERIODE 01 APRIL 2022 S/D 30 APRIL 2022

NILAI KONTRAK BULAN LALU BULAN INI SAMPAI BULAN INI


No URAIAN SISA
(Rp) (Rp) (Rp) (Rp)

I. BIAYA LANGSUNG PERSONIL 927,558,400


1 Profesional Staff 620,350,000 - 81,430,000 81,430,000 538,920,000
2 Sub Profesional Staff 161,708,400 - 13,475,700 13,475,700 148,232,700
3 Supporting Staff 145,500,000 - 23,500,000 23,500,000 122,000,000

II. BIAYA LANGSUNG NON PERSONIL 233,320,000


1 Mobilisasi/Demobilisasi 22,600,000 - 5,700,000 5,700,000 16,900,000
2 Fasilitas Kegiatan 81,120,000 - 15,820,000 15,820,000 65,300,000
3 Biaya Survei dan Penggunaan Peralatan dan Transportasi 118,100,000 - 9,000,000 9,000,000 109,100,000
6 Biaya Pelaporan 11,500,000 - 625,000 625,000 10,875,000

TOTAL
1,160,878,400 - 149,550,700 149,550,700 1,011,327,700
PPN 10%
116,087,840 - 14,955,070 14,955,070 101,132,770
TAMBAHAN PPN 1%
11,608,784 - 1,495,507 1,495,507 10,113,277
TOTAL BIAYA
1,288,575,024 - 166,001,277 166,001,277 1,122,573,747
PENGAMBILAN / PENGEMBALIAN UANG MUKA
255,393,199 - 33,200,255 33,200,255 222,192,944
INVOICE BULAN INI
- 132,801,022 132,801,022 900,380,803

DIBULATKAN - 132,801,000 132,801,000 900,380,800


Terbilang : Seratus Tiga Puluh Dua Juta Delapan Ratus Satu Ribu Rupiah

Pekanbaru, 30 April 2022


DISETUJUI OLEH : DIBUAT OLEH :
PEJABAT PEMBUAT KOMITMEN PT. ANGELA OERIP MANDIRI (KSO)
(PPK) CV. GITA LESTARI CONSULTAN
PRIMAWATY SILAEN, ST, MT Ir. BUDI SUPRIANTORO
NIP. 197710062002122008 Direktur Utama
RINCIAN REKAPITULASI TERMIJN I 30%

PAKET 10 REVIEW DESAIN PEMBANGUNAN JEMBATAN S. RANTAU BERANGIN CS

NOMOR KONTRAK : HK.02.01/Bb23-P2JN.R1/10


TANGGAL 15 MARET 2022
PERIODE 01 APRIL 2022 S/D 30 APRIL 2022

NILAI KONTRAK JUMLAH BIAYA BULAN LALU BULAN INI SAMPAI BULAN INI
No URAIAN SISA
(Rp) (Rp) (Rp) (Rp) (Rp)

I. BIAYA LANGSUNG PERSONIL 927,558,400


1 Profesional Staff 620,350,000 - 81,430,000 81,430,000 538,920,000
2 Sub Profesional Staff 161,708,400 - 13,475,700 13,475,700 148,232,700
3 Supporting Staff 145,500,000 - 23,500,000 23,500,000 122,000,000

II. BIAYA LANGSUNG NON PERSONIL 233,320,000


1 Mobilisasi/Demobilisasi 22,600,000 - 5,700,000 5,700,000 16,900,000
2 Fasilitas Kegiatan 81,120,000 - 15,820,000 15,820,000 65,300,000
3 Biaya Survei dan Penggunaan Peralatan dan Transportasi 118,100,000 - 9,000,000 9,000,000 109,100,000
6 Biaya Pelaporan 11,500,000 - 625,000 625,000 10,875,000

TOTAL 1,160,878,400 - 149,550,700 149,550,700 1,011,327,700

PPN 11% 116,087,840 - 16,450,577 16,450,577 111,246,047

TOTAL BIAYA 1,276,966,240 - 166,001,277 166,001,277 1,122,573,747


PENGAMBILAN / PENGEMBALIAN UANG MUKA 255,393,200 - 33,200,255 33,200,255 222,192,945

INVOICE BULAN INI - 132,801,022 132,801,022 900,380,802

DIBULATKAN - 132,801,000 132,801,000 900,380,800


Terbilang : Seratus Tiga Puluh Dua Juta Delapan Ratus Satu Ribu Rupiah

Pekanbaru, 30 April 2022


DISETUJUI OLEH : DIBUAT OLEH :
PEJABAT PEMBUAT KOMITMEN PT. ANGELA OERIP MANDIRI (KSO)
(PPK) CV. GITA LESTARI CONSULTAN

PRIMAWATY SILAEN, ST, MT Ir. BUDI SUPRIANTORO


NIP. 197710062002122008 Direktur Utama
RINCIAN REKAPITULASI TERMIJN I 30%
PERIODE 01 APRIL 2022 S/D 30 APRIL 2022

PAKET 10 REVIEW DESAIN PEMBANGUNAN JEMBATAN S. RANTAU BERANGIN CS


NOMOR KONTRAK : HK.02.01/Bb23-P2JN.R1/10
TANGGAL 15 MARET 2022
I BIAYA LANGSUNG PERSONIL

Bulan Lalu Bulan Ini Sampai Bulan Ini Sisa Kontrak


Jumlah Beban Biaya Nilai Kontrak
No. Kualifikasi Tenaga Ahli Jumlah Jumlah Biaya Jumlah Jumlah Biaya Jumlah Jumlah Biaya Jumlah Jumlah Biaya
Orang Satuan Bulan (Rp.) (Rp.) Org/Bln (Rp) Org/Bln (Rp) Org/Bln (Rp) Org/Bln (Rp)

A Profesional Staff
1 Team Leader 1 OB 5 28,130,000.00 140,650,000 - - 1.00 28,130,000 1.00 28,130,000 4.00 112,520,000
2 Ahli Jembatan 1 OB 5 26,650,000.00 133,250,000 - - 1.00 26,650,000 1.00 26,650,000 4.00 106,600,000
3 Ahli Geoteknik 1 OB 3 26,650,000.00 79,950,000 - - - - - - 3.00 79,950,000
4 Ahli Hidrologi 1 OB 3 26,650,000.00 79,950,000 - - - - - - 3.00 79,950,000
5 Ahli K3 Konstruksi 1 OB 3 26,650,000.00 79,950,000 - - 1.00 26,650,000 1.00 26,650,000 2.00 53,300,000
6 Ahli Kuantitas dan Biaya 1 OB 4 26,650,000.00 106,600,000 - - - - - - 4.00 106,600,000

Jumlah Biaya Tenaga Ahli Profesional ( A ) 23 620,350,000 - 81,430,000 81,430,000 538,920,000

B Sub Profesional Staff


1 Asisten Ahli Jembatan 1 OB 5 13,475,700.00 67,378,500 - - 1.00 13,475,700 1.00 13,475,700 4.00 53,902,800
2 Asisten Geoteknik 1 OB 3 13,475,700.00 40,427,100 - - - - - - 3.00 40,427,100
3 Asisten Ahli Kuantitas dan Biaya 1 OB 4 13,475,700.00 53,902,800 - - - - - - 4.00 53,902,800

Jumlah Biaya Tenaga Ahli Profesional ( B ) 12 161,708,400 - 13,475,700 13,475,700 148,232,700


C Supporting Staff
1 Surveyor 1 1 OB 3 6,000,000 18,000,000 - - 1.00 6,000,000 1.00 6,000,000 2.00 12,000,000
2 Surveyor 2 1 OB 3 6,000,000 18,000,000 - - 1.00 6,000,000 1.00 6,000,000 2.00 12,000,000
3 Draftman 1 1 OB 4 6,500,000 26,000,000 - - - - - - 4.00 26,000,000
4 Draftman 2 1 OB 4 6,500,000 26,000,000 - - - - - - 4.00 26,000,000
5 Operator Komputer 1 OB 5 6,500,000 32,500,000 - - 1.00 6,500,000 1.00 6,500,000 4.00 26,000,000
6 Driver 1 OB 5 2,750,000 13,750,000 - - 1.00 2,750,000 1.00 2,750,000 4.00 11,000,000
7 Office Boy 1 OB 5 2,250,000 11,250,000 - - 1.00 2,250,000 1.00 2,250,000 4.00 9,000,000

Jumlah Biaya Tenaga Penunjang ( C ) 29 145,500,000 - 23,500,000 23,500,000 122,000,000


I. JUMLAH BIAYA LANGSUNG PERSONIL ( A + B + C ) 927,558,400 - 118,405,700 118,405,700 809,152,700

Diketahui Oleh : Konsultan Perencana


PROJECT OFFICER PT. ANGELA OERIP MANDIRI (KSO)
SNVT P2JN PROVINSI RIAU CV. GITA LESTARI CONSULTAN

RAMA DWI ARYANDI, ST, Ir. BUDI SUPRIANTORO


NIP. 199207202018021001 Direktur Utama
RINCIAN REKAPITULASI TERMIJN I 30%
PERIODE 01 APRIL 2022 S/D 30 APRIL 2022

PAKET 10 REVIEW DESAIN PEMBANGUNAN JEMBATAN S. RANTAU BERANGIN CS


NOMOR KONTRAK : HK.02.01/Bb23-P2JN.R1/10
TANGGAL 15 MARET 2022

II. BIAYA LANGSUNG NON PERSONIL


II.1 Mobilisasi/Demobilisasi

Bulan Lalu Bulan Ini Sampai Bulan Ini Sisa Kontrak


Nilai Kontrak
No. Uraian Satuan Volume Beban Biaya (Rp) Jumlah Jumlah Biaya Jumlah Jumlah Biaya Jumlah Jumlah Biaya Jumlah Jumlah Biaya
(Rp) (Rp) (Rp) (Rp) (Rp)

1 Profesional Staff (6) PP 12 1,000,000 12,000,000 - - 3.00 3,000,000 3.00 3,000,000 9.00 9,000,000
2 Sub Profesional Staff (3) PP 6 700,000 4,200,000 - - 1.00 700,000 1.00 700,000 5.00 3,500,000
3 Supporting Staff (8) PP 16 400,000 6,400,000 - - 5.00 2,000,000 5.00 2,000,000 11.00 4,400,000

II.1 Jumlah Biaya Mobilisasi - Demobilisasi 22,600,000 - 5,700,000 5,700,000 16,900,000

II.2 Fasilitas Kegiatan

Volume Bulan Lalu Bulan Ini Sampai Bulan Ini Sisa Kontrak
Nilai Kontrak
No. Uraian Satuan Beban Biaya (Rp.) Jumlah Jumlah Biaya Jumlah Jumlah Biaya Jumlah Jumlah Biaya Jumlah Jumlah Biaya
(Rp.) Org/Bln (Rp) Org/Bln (Rp) Org/Bln (Rp) Org/Bln (Rp)

1 Perjalanan Dinas
Perjalanan Dinas ke Jakarta
-Tiket Pesawat Tim Leader dan Ahli Jembatan (6 kali) PP 12.00 1,000,000 12,000,000 - - - - - - 12.00 12,000,000
- Penginapan (2 malam per perjalanan dinas) OH 24.00 350,000 8,400,000 - - - - - - 24.00 8,400,000
2 Sewa Kendaraan Roda 4 & Biaya Operasional Bln 5.00 4,500,000 22,500,000 - - 1.00 4,500,000 1.00 4,500,000 4.00 18,000,000
3 Sewa Kendaraan Roda 2-1 & Biaya Operasional Bln 3.00 800,000 2,400,000 - - 1.00 800,000 1.00 800,000 2.00 1,600,000
4 Sewa Kendaraan Roda 2-2 & Biaya Operasional Bln 3.00 800,000 2,400,000 - - 1.00 800,000 1.00 800,000 2.00 1,600,000
5 Komunikasi Bln 5.00 800,000 4,000,000 - - 1.00 800,000 1.00 800,000 4.00 3,200,000
6 Komputer - 1 Bln 4.00 800,000 3,200,000 - - 1.00 800,000 1.00 800,000 3.00 2,400,000
7 Komputer - 2 Bln 4.00 800,000 3,200,000 - - 1.00 800,000 1.00 800,000 3.00 2,400,000
8 Sewa Printer A3 Bln 5.00 350,000 1,750,000 - - 1.00 350,000 1.00 350,000 4.00 1,400,000
9 Sewa Printer A4 Bln 5.00 300,000 1,500,000 - - 1.00 300,000 1.00 300,000 4.00 1,200,000
10 Biaya ATK Bln 5.00 1,750,000 8,750,000 - - 1.00 1,750,000 1.00 1,750,000 4.00 7,000,000
11 Sewa Kamera Bln 4.00 300,000 1,200,000 - - 1.00 300,000 1.00 300,000 3.00 900,000
12 Sewa Hand GPS Bln 3.00 600,000 1,800,000 - - 1.00 600,000 1.00 600,000 2.00 1,200,000
13 Sewa Kantor & Mess Bln 5.00 1,000,000 5,000,000 - - 1.00 1,000,000 1.00 1,000,000 4.00 4,000,000
14 Peralatan K3
- Rompi Pengaman Personil Buah 11.00 80,000 880,000 - - 11.00 880,000 11.00 880,000 - -
- Helm Pengaman Buah 11.00 40,000 440,000 - - 11.00 440,000 11.00 440,000 - -
- Sepatu Safety Buah 11.00 120,000 1,320,000 - - 11.00 1,320,000 11.00 1,320,000 - -
- Kaca Mata Safety Buah 11.00 20,000 220,000 - - 11.00 220,000 11.00 220,000 - -
- Alat Ukur (meteran) Buah 2.00 80,000 160,000 - - 2.00 160,000 2.00 160,000 - -

II.2 Jumlah Biaya Kantor (A+B) 81,120,000 - 15,820,000 15,820,000 65,300,000

Diketahui Oleh : Konsultan Perencana


PROJECT OFFICER PT. ANGELA OERIP MANDIRI (KSO)
SNVT P2JN PROVINSI RIAU CV. GITA LESTARI CONSULTAN

RAMA DWI ARYANDI, ST, Ir. BUDI SUPRIANTORO


NIP. 199207202018021001 Direktur Utama
RINCIAN REKAPITULASI TERMIJN I 30%
PERIODE 01 APRIL 2022 S/D 30 APRIL 2022

PAKET 10 REVIEW DESAIN PEMBANGUNAN JEMBATAN S. RANTAU BERANGIN CS


NOMOR KONTRAK : HK.02.01/Bb23-P2JN.R1/10
TANGGAL 15 MARET 2022

II.3 Biaya Survei dan Penggunaan Peralatan dan Transportasi


Bulan Lalu Bulan Ini Sampai Bulan Ini Sisa Kontrak
Nilai Kontrak
No. Uraian Satuan Volume Beban Biaya (Rp) Jumlah Jumlah Biaya Jumlah Jumlah Biaya Jumlah Jumlah Biaya Jumlah Jumlah Biaya
(Rp) (Rp) (Rp) (Rp) (Rp)
A. Penggunaan Peralatan
1 Survey Pendahuluan (12 hari)
- BBM Ls 1.00 500,000 500,000 - - 1.00 500,000 1.00 500,000 - -
- Penginapan (2 kamar) Malam 24.00 350,000 8,400,000 - - 24.00 8,400,000 24.00 8,400,000 - -
2 Survei Topografi (Inc Mob/Demob, Transport, Report) Ha 5.00 2,200,000 11,000,000 - - - - - - 5.00 11,000,000
3 Field Test
- Deep Boring m 180.00 350,000 63,000,000 - - - - - - 180.00 63,000,000
- SPT (every 2,0 M) nos 90.00 150,000 13,500,000 - - - - - - 90.00 13,500,000
- Undisturbed Samples, UDS nos 24.00 100,000 2,400,000 - - - - - - 24.00 2,400,000
4 Laboratory Testing
- Index Properties
Natural Moisture Content nos 24.00 100,000 2,400,000 - - - - - - 24.00 2,400,000
Unit Weight nos 24.00 100,000 2,400,000 - - - - - - 24.00 2,400,000
Specific Gravity, GS nos 24.00 100,000 2,400,000 - - - - - - 24.00 2,400,000
grain Size Analysis nos 24.00 100,000 2,400,000 - - - - - - 24.00 2,400,000
Hidrometer nos 24.00 100,000 2,400,000 - - - - - - 24.00 2,400,000
Atterberg Limit nos 24.00 100,000 2,400,000 - - - - - - 24.00 2,400,000
- Shear Stregth
UU triaxial test nos 24.00 100,000 2,400,000 - - - - - - 24.00 2,400,000
- Compression Parameter
Concolidation nos 24.00 100,000 2,400,000 - - - - - - 24.00 2,400,000
5 Patok BM dan Patok Survey Ls 1.00 100,000 100,000 - - 1.00 100,000 1.00 100,000 - -

II.3 Jumlah Biaya Survei dan Penggunaan Peralatan dan Transportasi 118,100,000 - 9,000,000 9,000,000 109,100,000

II.4 Biaya Pelaporan


Bulan Lalu Bulan Ini Sampai Bulan Ini Sisa Kontrak
Nilai Kontrak
No. Uraian Satuan Volume Beban Biaya (Rp) Jumlah Jumlah Biaya Jumlah Jumlah Biaya Jumlah Jumlah Biaya Jumlah Jumlah Biaya
(Rp) (Rp) (Rp) (Rp) (Rp)
1 Laporan Pendahuluan Buku 5.00 125,000.00 625,000 - - 5.00 625,000 5.00 625,000 - -
2 Laporan Antara Buku 5.00 150,000.00 750,000 - - - - - - - 750,000
3 Draft Laporan Akhir Buku 5.00 150,000.00 750,000 - - - - - - - 750,000
4 Laporan Akhir (Final Report) Buku 5.00 300,000.00 1,500,000 - - - - - - - 1,500,000
5 Eksekutif Summary Buku 5.00 125,000.00 625,000 - - - - - - - 625,000
6 Lapoan Teknis / Khusus Buku 5.00 150,000.00 750,000 - - - - - - - 750,000
7 Dokumen Lelang Buku 5.00 400,000.00 2,000,000 - - - - - - - 2,000,000
8 Presentasi Laporan Kali 5.00 700,000.00 3,500,000 - - - - - - - 3,500,000
9 HD (1 terra) Unit 1.00 1,000,000.00 1,000,000 - - - - - - - 1,000,000

II.4 Jumlah Biaya Pembuatan Laporan 11,500,000 - 625,000 625,000 10,875,000

Diketahui Oleh : Konsultan Perencana


PROJECT OFFICER PT. ANGELA OERIP MANDIRI (KSO)
SNVT P2JN PROVINSI RIAU CV. GITA LESTARI CONSULTAN

RAMA DWI ARYANDI, ST, Ir. BUDI SUPRIANTORO


NIP. 199207202018021001 Direktur Utama
DAFTAR HARGA SATUAN

0
KEGIATAN :
PEKERJAAN : PAKET 10 REVIEW DESAIN PEMBANGUNAN JEMBATAN S. RANTAU BERANGIN CS
NILAI PAGU : Rp -
SUMBER DANA : APBD PROVINSI RIAU
TAHUN ANGGARAN : 2011

DAFTAR HARGA SATUAN UPAH

Harga
No. Uraian Personil / Ahli Satuan Keterangan / Pengalaman
(Rp)

A Tenaga Ahli Profesional


1 Profesional Staff (6) Bulan 9,000,000.00 9 s/d 12 Tahun
2 Sub Profesional Staff (3) Bulan 7,000,000.00 5 s/d 8 Tahun
3 Err:509 Bulan 7,000,000.00 5 s/d 8 Tahun
4 Err:509 Bulan 7,000,000.00 5 s/d 8 Tahun
5 Err:509 Bulan 7,000,000.00 5 s/d 8 Tahun
6 Err:509 Bulan 7,000,000.00 5 s/d 8 Tahun
7 Err:509 Bulan 7,000,000.00 5 s/d 8 Tahun
8 Err:509 Bulan 7,000,000.00 5 s/d 8 Tahun

B Biaya Tenaga Penunjang


1 Ass. Ahli Perencanaan SDA Bulan 2,500,000.00 1 s/d 4 Tahun
2 Surveyor Topografi Bulan 2,500,000.00 1 s/d 4 Tahun
3 Surveyor Mekanika Tanah Bulan 2,500,000.00 1 s/d 4 Tahun
4 Surveyor Hidrologi - Hidrometri Bulan 2,500,000.00 1 s/d 4 Tahun
5 Surveyor Lingkungan, Sosial Ekonomi Bulan 2,500,000.00 1 s/d 4 Tahun
6 Juru Gambar ( Auto CAD) Bulan 2,500,000.00 1 s/d 4 Tahun
7 Operator Komputer Bulan 2,500,000.00 1 s/d 4 Tahun
8 Tenaga Administrasi Bulan 2,500,000.00 1 s/d 4 Tahun
9 Pesuruh Bulan 1,500,000.00 1 s/d 4 Tahun

DAFTAR HARGA SATUAN BIAYA HARIAN PERSONIL

Jumlah Biaya
No. Uraian Personil / Ahli Keterangan
Orang Trip (Rp)
A Tenaga Ahli Profesional
1 Profesional Staff (6) 1 1 500,000.00
2 Sub Profesional Staff (3) 1 1 350,000.00
3 Err:509 1 1 350,000.00
4 Err:509 1 1 350,000.00
5 Err:509 1 1 350,000.00
6 Err:509 1 1 350,000.00
7 Err:509 1 1 350,000.00
8 Err:509 1 1 350,000.00

B Biaya Tenaga Penunjang


1 Ass. Ahli Perencanaan SDA 1 1 250,000.00
2 Surveyor Topografi 1 1 250,000.00
3 Surveyor Mekanika Tanah 1 1 250,000.00
4 Surveyor Hidrologi - Hidrometri 1 1 250,000.00
5 Surveyor Lingkungan, Sosial Ekonomi 1 1 250,000.00
6 Juru Gambar ( Auto CAD) 1 1 250,000.00
7 Operator Komputer 1 1 250,000.00
8 Tenaga Administrasi 1 1 250,000.00
9 Pesuruh 1 1 250,000.00
DAFTAR HARGA SATUAN BAHAN/SEWA PERALATAN KANTOR/LAPANGAN

Harga Satuan
No. Susunan / Uraian Satuan Keterangan
(Rp)

Alat Kantor & Lain-lain


1 Komputer + Printer Bulan 1,500,000.00
2 Bahan Kantor/ATK Bulan 1,000,000.00
3 Telepon Bulan 250,000.00
4 Faximile Bulan 250,000.00
5 Diskusi/Paparan Laporan Pendahuluan Kali 1,500,000.00
6 Diskusi/Paparan Laporan Antara Kali 1,500,000.00
7 Diskusi/Paparan Laporan Final/Akhir Kali 1,500,000.00

Alat Survey Topographi


8 Sewa Theodolite Harian 2,500,000.00
9 Sewa Water Pass Harian 2,500,000.00
10 Sewa GPS Harian 1,500,000.00
11 Patok Bench Mark (BM) Buah 500,000.00
12 Patok CP Buah 300,000.00
13 Bahan Survey Ls 500,000.00

Alat Survey Hidrologi - Hidrometri


15 Pengumpulan Data / Fotocopy Ls 500,000.00
16 Sewa Current Meter Harian 2,500,000.00
17 Pemasangan Peil Skaal Bh 500,000.00
18 Bahan Survey Ls 500,000.00

Alat Survey Mekanika Tanah


19 Sewa Mobil Bak Harian 350,000.00
20 Sewa Sondir Titik 1,750,000.00
21 Sewa Hand Auger Titik 1,000,000.00
22 Bahan Survey Ls 500,000.00

Alat Survey Sedimentasi


23 Sewa Perahu Harian 350,000.00
24 Botol Sampel Btl 150,000.00
26 Bahan Survey Ls 500,000.00

DAFTAR HARGA SATUAN BAHAN LAPORAN

Harga Satuan
No. Uraian Personil / Ahli Satuan Keterangan
(Rp)

1 Laporan Rencana Mutu Kontrak (RMK) Buku 150,000.00


2 Draft Laporan Pendahuluan Buku 150,000.00
3 Laporan Pendahuluan Buku 150,000.00
4 Laporan Bulanan (3 x 6 bln) Buku 200,000.00
5 Laporan Antara/Sisipan Buku 200,000.00
6 Laporan Penunjang
a. Survey Topographi dan Bathimetri (Nota Perjalanan Pengukuran) Buku 100,000.00
b. Survey Hidro-Oceanografi Buku 100,000.00
c. Survey Mekanika Tanah Buku 100,000.00
d. Nota Desain Buku 500,000.00
e. Rekayasa Ekonomi Teknik Buku 100,000.00
f. Spektek, RAB dan Dokumen Tender Buku 500,000.00
g. Dokumen UKL/UPL Buku 100,000.00
7 Laporan Akhir Sementara Buku 250,000.00
8 Laporan Akhir Ls 300,000.00
9 Laporan Ringkasan Buku 150,000.00
10 Master Copy Laporan & Gambar Desain CD/DVD 20,000.00
11 Foto Dokumentasi Set 100,000.00
12 Master Gambar Peta Ploting Set 750,000.00
13 Blue Print A1 Set 500,000.00
14 Master Gambar Desain Set 750,000.00
16 Blue Print A3 Set 350,000.00