JADWAL WAKTU PELAKSANAAN

Instansi : Rumah Sakit Umum Pusat Dr. Sitanala Tangerang


Kegiatan : Pekerjaan Konsultansi Perencanaan Pembangunan Gedung Medical Check Up Rumah Sakit Umum Pusat
: Dr. Sitanala Tangerang
Tahun Anggaran : 2022
Lokasi : Jl. Dr. Sitanala Tangerang
No. Kontrak : KN.01.04/XXXI.6.2/07079/2022
Tanggal : 3 Agustus 2022
No. SPMK : KN.01.03/XXXI.6.2/07080/2022
Tanggal : 3 Agustus 2022
JADWAL WAKTU PELAKSANAAN (130 HARI KALENDER)
BOBOT PRESTASI BULAN AGUSTUS 2022 BULAN SEPTEMBER 2022 BULAN OKTOBER 2022 BULAN NOPEMBER 2022 BLN DES 2022
NO URAIAN PEKERJAAN JUMLAH (RP) (%)
KET
M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12 M13 M14 M15 M16 M17 M18 M19
3-9 10-16 17-23 24-30 31/8-6/9 7-13 14-20 21-27 28/9-4/10 5-11 12-18 19-25 26/10-1/11 2-8 9-15 16-22 23-29 30/11-6/12 7-10
I PEKERJAAN PERSIAPAN
A PEKERJAAN PERSIAPAN Rp 171,899,127.08 0.780 0.041 0.041 0.041 0.041 0.041 0.041 0.041 0.041 0.041 0.041 0.041 0.041 0.041 0.041 0.041 0.041 0.041 0.041 0.041
II PEKERJAAN STRUKTUR
A PEKERJAAN TANAH Rp 113,271,288.63 0.514 0.171 0.171 0.171
B PEKERJAAN STRUKTUR LANTAI 1 Rp 4,407,236,052.96 20.005 1.500 5.001 5.001 5.001 3.501
C PEKERJAAN STRUKTUR LANTAI 2 Rp 3,563,835,736.66 16.177 2.157 5.392 5.392 3.235
D PEKERJAAN STRUKTUR LANTAI 3 Rp 2,457,400,076.45 11.155 1.859 3.718 3.718 1.859
E PEKERJAAN STRUKTUR LANTAI ATAP Rp 1,280,333,803.44 5.812 0.872 2.906 2.034
III PEKERJAAN ARSITEKTUR
A PEKERJAAN ARSITEKTUR LANTAI 1 Rp 1,598,294,918.14 7.255 0.622 1.036 1.036 1.036 1.036 1.036 1.036 0.415
B PEKERJAAN ARSITEKTUR LANTAI 2 Rp 2,035,122,229.20 9.238 0.924 1.540 1.540 1.540 1.540 1.540 0.616
C PEKERJAAN ARSITEKTUR LANTAI 3 Rp 308,182,549.13 1.399 0.350 0.350 0.350 0.350
D PEKERJAAN ARSITEKTUR LANTAI ATAP Rp 185,890,637.93 0.844 0.211 0.211 0.211 0.211
E PEKERJAAN ARSITEKTUR FASADE Rp 2,390,792,579.35 10.852 1.302 1.736 2.170 2.170 2.170 1.302
IV PEKERJAAN ELEKTRIKAL
A PEKERJAAN PERALATAN UTAMA ELEKTRIKAL
1. PEKERJAAN PENGADAAN LISTRIK Rp 152,250,000.00 0.691 0.115 0.115 0.115 0.115 0.115 0.115
2. PEKERJAAN PASANG KABEL TR 400 / 1 KV Rp 337,311,578.18 1.531 0.255 0.255 0.255 0.255 0.255 0.255
B PEKERJAAN PANEL DAYA DAN PENERANGAN
1. PEKERJAAN PANEL DAYA DAN PENERANGAN LANTAI 1 Rp 69,932,500.80 0.317 0.053 0.053 0.053 0.053 0.053 0.053
2. PEKERJAAN PANEL DAYA DAN PENERANGAN LANTAI 2 Rp 17,885,978.80 0.081 0.014 0.014 0.014 0.014 0.014 0.014
3. PEKERJAAN PANEL DAYA DAN PENERANGAN LANTAI ATAP Rp 7,962,394.00 0.036 0.006 0.006 0.006 0.006 0.006 0.006
C PEKERJAAN INSTALASI PENERANGAN DAN STOP KONTAK
1. PEKERJAAN INSTALASI PENERANGAN & STOP KONTAK LT.1 Rp 91,562,135.50 0.416 0.069 0.069 0.069 0.069 0.069 0.069
2. PEKERJAAN INSTALASI PENERANGAN & STOP KONTAK LT.2 Rp 90,291,254.00 0.410 0.068 0.068 0.068 0.068 0.068 0.068
D PEKERJAAN KABEL TRAY ELEKTRIKAL DAN KABEL LADDER
1. PEKERJAAN KABEL TRAY ELEKTRIKAL LANTAI 1 Rp 23,145,070.49 0.105 0.018 0.018 0.018 0.018 0.018 0.018
2. PEKERJAAN KABEL TRAY ELEKTRIKAL LANTAI 2 Rp 24,163,908.14 0.110 0.018 0.018 0.018 0.018 0.018 0.018
E PEKERJAAN PENANGKAL PETIR Rp 72,191,977.70 0.328 0.055 0.055 0.055 0.055 0.055 0.055
V PEKERJAAN ELEKTRONIK
A PEKERJAAN FIRE ALARM
1. PEKERJAAN TERMINAL BOX FIRE ALARM Rp 4,114,385.00 0.019 0.003 0.003 0.003 0.003 0.003 0.003
2. PEKERJAAN INSTALASI PENGKABELAN FIRE ALARM Rp 2,692,126.80 0.012 0.002 0.002 0.002 0.002 0.002 0.002
3. PEKERJAAN INSTALASI FIRE ALARM LANTAI 1 Rp 33,947,655.50 0.154 0.026 0.026 0.026 0.026 0.026 0.026
4. PEKERJAAN INSTALASI FIRE ALARM LANTAI 2 Rp 66,227,166.50 0.301 0.050 0.050 0.050 0.050 0.050 0.050
B PEKERJAAN TATA SUARA
1. PEKERJAAN INSTALASI TATA SUARA LANTAI 1 Rp 14,511,059.42 0.066 0.011 0.011 0.011 0.011 0.011 0.011
2. PEKERJAAN INSTALASI TATA SUARA LANTAI 2 Rp 22,180,280.06 0.101 0.017 0.017 0.017 0.017 0.017 0.017
3. PEKERJAAN INSTALASI PENGKABELAN SISTEM TATA SUARA Rp 10,653,093.00 0.048 0.008 0.008 0.008 0.008 0.008 0.008
C PEKERJAAN IT (INFORMASI DAN TEKNOLOGI) -
1. PEKERJAAN PERALATAN UTAMA PEKERJAAN IT Rp 8,847,795.00 0.040 0.007 0.007 0.007 0.007 0.007 0.007
2. PEKERJAAN INSTALASI SISTEM IT LANTAI 1 Rp 10,985,562.50 0.050 0.008 0.008 0.008 0.008 0.008 0.008
3. PEKERJAAN INSTALASI SISTEM IT LANTAI 2 Rp 11,424,985.00 0.052 0.009 0.009 0.009 0.009 0.009 0.009
D PEKERJAAN MATV
1. PEKERJAAN PERALATAN UTAMA PEKERJAAN MATV Rp 2,250,000.00 0.010 0.002 0.002 0.002 0.002 0.002 0.002
2. PEKERJAAN INSTALASI SISTEM MATV LANTAI 1 Rp 2,195,902.50 0.010 0.002 0.002 0.002 0.002 0.002 0.002
3. PEKERJAAN INSTALASI SISTEM MATV LANTAI 2 Rp 2,195,902.50 0.010 0.002 0.002 0.002 0.002 0.002 0.002
E PEKERJAAN KABEL TRAY ELEKTRONIK DAN KABEL LADDER
1. PEKERJAAN KABEL TRAY ELEKTRONIK LANTAI 1 Rp 19,090,049.42 0.087 0.014 0.014 0.014 0.014 0.014 0.014
2. PEKERJAAN KABEL TRAY ELEKTRONIK LANTAI 2 Rp 19,090,049.42 0.087 0.014 0.014 0.014 0.014 0.014 0.014
VI PEKERJAAN PLUMBING
A PEKERJAAN INSTALASI AIR BERIH
1. PEKERJAAN INSTALASI AIR BERSIH RUANG POMPA Rp 96,725,000.00 0.439 0.073 0.073 0.073 0.073 0.073 0.073
2. PEKERJAAN INSTALASI AIR BERSIH LANTAI 1 Rp 8,305,250.00 0.038 0.006 0.006 0.006 0.006 0.006 0.006
3. PEKERJAAN INSTALASI AIR BERSIH LANTAI 2 Rp 28,439,050.00 0.129 0.022 0.022 0.022 0.022 0.022 0.022
4. PEKERJAAN INSTALASI AIR BERSIH LANTAI ATAP Rp 76,804,000.00 0.349 0.058 0.058 0.058 0.058 0.058 0.058
B PEKERJAAN INSTALASI AIR KOTOR, BEKAS DAN VENT
1. PEKERJAAN PERALATAN UTAMA AIR KOTOR, BEKAS DAN VENT Rp 165,000,000.00 0.749 0.125 0.125 0.125 0.125 0.125 0.125
2. PEKERJAAN INSTALASI AIR KOTOR, BEKAS DAN VENT LANTAI 1 Rp 4,269,050.00 0.019 0.003 0.003 0.003 0.003 0.003 0.003
3. PEKERJAAN INSTALASI AIR KOTOR, BEKAS DAN VENT LANTAI 2 Rp 7,857,200.00 0.036 0.006 0.006 0.006 0.006 0.006 0.006
5. PEKERJAAN INSTALASI AIR KOTOR, BEKAS DAN VENT LANTAI 3 Rp 2,960,050.00 0.013 0.002 0.002 0.002 0.002 0.002 0.002
4. PEKERJAAN INSTALASI AIR KOTOR, BEKAS DAN VENT LANTAI ATAP Rp 35,014,000.00 0.159 0.026 0.026 0.026 0.026 0.026 0.026
VII PEKERJAAN AC DAN VENTILASI
A PEKERJAAN AC LANTAI 1 Rp 82,181,000.00 0.373 0.062 0.062 0.062 0.062 0.062 0.062
B PEKERJAAN EXHAUST LANTAI 1 Rp 7,775,000.00 0.035 0.006 0.006 0.006 0.006 0.006 0.006
C PEKERJAAN AC LANTAI 2 Rp 72,002,000.00 0.327 0.054 0.054 0.054 0.054 0.054 0.054
D PEKERJAAN EXHAUST LANTAI 2 Rp 9,321,000.00 0.042 0.007 0.007 0.007 0.007 0.007 0.007
E PEKERJAAN OUTDOOR UNIT AC LANTAI DAK Rp 247,094,000.00 1.122 0.187 0.187 0.187 0.187 0.187 0.187
F PEKERJAAN AC LANTAI ATAP Rp 1,553,000.00 0.007 0.001 0.001 0.001 0.001 0.001 0.001
VIII PEKERJAAN PEMADAM KEBAKARAN
A PEKERJAAN SISTEM PEMADAM KEBAKARAN LANTAI 1 Rp 8,657,360.00 0.039 0.007 0.007 0.007 0.007 0.007 0.007
B PEKERJAAN SISTEM PEMADAM KEBAKARAN LANTAI 2 Rp 8,657,360.00 0.039 0.007 0.007 0.007 0.007 0.007 0.007
IX PEKERJAAN ELEVATOR DAN ESCALATOR
A PEKERJAAN PEMASANGAN ESCALATOR Rp 1,505,000,000.00 6.831 0.569 1.139 1.139 1.139 1.139 1.139 0.569
X PEKERJAAN LANDSCAPE
A PEKERJAAN TAMAN/LANDSCAPE AREA GEDUNG UTAMA Rp 18,421,273.75 0.084 0.014 0.014 0.014 0.014 0.014 0.014
B PEKERJAAN DRAINASE SITE Rp 15,161,673.60 0.069 0.011 0.011 0.011 0.011 0.011 0.011
JUMLAH PEKERJAAN PEMBANGUNAN RUMAH SAKIT Rp 22,030,559,076.53 100.000
RENCANA BOBOT PRESTASI PERMINGGU (%) 0.041 0.212 0.212 1.713 5.042 5.042 5.042 5.699 5.433 5.433 5.757 7.591 10.733 10.180 10.705 10.044 7.142 3.725 0.252
RENCANA KOMULATIF BOBOT PRESTASI PERMINGGU (%) 0.041 0.254 0.466 2.179 7.221 12.263 17.306 23.005 28.438 33.871 39.629 47.220 57.953 68.133 78.838 88.882 96.023 99.748 100.000
REALISASI BOBOT PRESTASI PERMINGGU (%) 0.219 2.506 0.764 0.535 0.671 5.794
REALISASI KOMULATIF BOBOT PRESTASI PERMINGGU (%) 0.219 2.725 3.489 4.025 4.695 10.489
DEVIASI (%) - 0.178 2.471 3.023 1.846 (2.526) (1.774)

TANGERANG 13 SEPTEMBER 2022

Dibuat oleh :
Diperiksa : Kontraktor Pelaksana
Konsultan Pengawas PT. AREABANGUN PUTRA SEJATI
CV. MAHONI

MOH. IFTAH, ST IR. TASLI, MM


Team Leader Project Manager